Turnpike Projects in Palm Beach County. Palm Beach TPA Update September 20, 2018
|
|
- Reginald Gilbert
- 5 years ago
- Views:
Transcription
1 Turnpike Projects in Palm Beach County Palm Beach TPA Update September 20, 2018
2 Agenda Background Funded Projects Future Project Status Widenings Interchanges Express Lanes Phasing 2
3 Background 45 Miles of the Turnpike Mainline Southern Coin Ticket System 10 Interchanges Glades Road (Boca Raton) Atlantic Avenue (Delray Beach) Boynton Beach Boulevard (Boynton Beach) Lake Worth Road (Lake Worth) Southern Boulevard/SR 80 (West Palm Beach) Jog Road (Partial to and from the south) Okeechobee Boulevard (West Palm Beach) Beeline Highway/SR 710 PGA Boulevard (Palm Beach Gardens) Indiantown Road (Jupiter) 3
4 Funded Construction Projects FY 2018 to 2023 Description # Lanes Widen between MP 86 - Boynton Bch Blvd and MP 93 - Lake Worth Rd* [FPN: ] All-Electronic Tolling Conversion Phase 8 [FPN: ] 8 N/A Phase FY Funds ($M) PE CST PE CST * project will only construct 6 lanes, but will accommodate 8 lanes $2 $188 $10 $107 ($4.5 in PBC) 4
5 Future Project Status 5
6 Congestion Scan March
7 Crashes ( ) South Palm Beach North Palm Beach 7
8 Widening Needs Ultimate Build Out 8
9 10-Year Finance Plan Projects Total $1,775M Description # Lanes Phase FY Funds ($M) Widen between MP SR 710 and MP Indiantown Rd [FPN: ] 8 PE CST $22 $350 Widen between MP 93 - Lake Worth Rd and MP SR 710 [FPN: ] 8 PE CST $10 $459 Widen between MP 86 - Boynton Bch Blvd and MP 93 - Lake Worth Rd [FPN: ] 8 PE CST $1 $185 New Hypoluxo Road Interchange [FPN: ] N/A PE 2020 $1 Widen between MP 81 - Atlantic Ave and MP 86 - Boynton Bch Blvd [FPN: ] 10 PE CST $6 $223 Widen between MP 75 - Glades Rd and MP 81 - Atlantic Ave [FPN: ] 10 PE CST $6 $262 Widen between MP 73 - Broward / Palm Beach CL and MP 75 - Glades Rd [FPN: ] 10 PE CST $3 $248 9
10 Palm Beach County Interchange Modifications Interchanges Alternatives under consideration Ramp Modifications Intersection Treatments Glades Road X X Atlantic Avenue Boynton Beach Boulevard X X Lake Worth Road Southern Boulevard Jog Road X X Okeechobee Boulevard X X Beeline Highway X X PGA Boulevard X X Indiantown Road X X X
11 Express Lanes in Florida In Operation 55 miles Under Construction 84 miles Southeast Florida In Planning/Design 326 miles Jacksonville Orlando Tampa 11
12 Express Lanes in Florida Strategy Long Term Congestion Management Thru Dynamic Tolling Efficient Use of Remaining New Capacity Provide Drivers with Travel Choices Offer a More Predictable Travel Time Deliver a Long-Term Solution to Manage Congestion Reduce Fuel Consumption Decrease Air Pollution Provide Transit Options
13 Palm Beach County Survey Results Having Express Lanes is good for managing congestion on Turnpike Facilities. Having Express Lanes on the Turnpike alongside the regular lanes provides me with a travel choice Agree Neutral Disagree Agree Neutral Disagree Will pay an additional toll if it assures me my travel won t be slowed by traffic conditions. Willing to pay an extra toll if it guarantees a travel time for my trip that is reliable Agree Neutral Disagree 0 Agree Neutral Disagree
14 Bus Exemptions Transit buses School buses Over-the-road buses Equal access for over-the-road buses. An over-the-road bus that serves the public shall be provided access to a toll facility under the same rates, terms and conditions as public transportation buses. Source: Office of the Law Revision Counsel 23 USC 129: Toll roads, bridges, tunnels, and ferries Registered buses are exempt from tolls on interstates. ( ) System. ( ) 14
15 Pricing Considerations Dynamic rates will be displayed on the signs If average express lanes speed falls below 40 mph, then minimum toll will be charged Post-trip toll adjustment to lower toll amount 15
16 Pricing Considerations Level of Service Based Pricing Dynamic pricing expected to occur only during peak periods 16
17 Volume (vph) Veterans Express Lanes Segment 1 (SR 60 to Gunn Hwy) Opened on 12/09/2017 Segment 2 (Gunn to Dale Mabry Hwy) Opened on 5/23/2018 No Dynamic component yet Veterans Expressway widening provided significant improvement to peak period average travel speeds Open to Traffic 2,000 1,800 1,600 1,400 1,200 1, Veterans Express Lanes Southbound Traffic LOS D LOS C LOS B LOS A Hour Ending
18 Express Lanes Phasing Turnpike Considerations North Corridor Number of segments and project length Express Lane to Express Lane Connections General toll lane corridor reaches Level of Service D South Corridor
19 Express Lanes Project Phasing Corridor # Widening Projects Length (mi) Includes EL-EL Direct Connect Year at LOS D with GTL Widening EL Implementation Timeframe Southern Corridor S. of Coconut Creek Pkwy to N. of Boynton Beach Blvd Yes (Sawgrass Expwy /Turnpike Mainline Interchange) Upon Completion of Widening Projects Northern Corridor N. of Lake Worth Rd. to N. of Indiantown Road 2 22 No Upon reaching LOS D Express Lanes will only be implemented where and when needed 19
20 Express Lanes Phasing Southern Express Lane Corridor Provides connectivity to Sawgrass Expressway and SW 10 th Street Preserves long term mobility in highest demand area Preliminary ingress/egress points Boynton Beach Blvd Atlantic Ave Glades Rd
21 Questions 21
Gandy Connector: Travel Demand. Policy Committee August 2013
Gandy Connector: Travel Demand Policy Committee August 2013 What options to the Gandy Elevated Lanes exist? What are the current conditions? Who s using Gandy Blvd? What s currently planned? What s been
More information2018 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW BOCA RATON RESORT AND CLUB August 2-5, 2018
Florida Department of TRANSPORTATION 2018 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW BOCA RATON RESORT AND CLUB August 2-5, 2018 Mike Dew, Secretary FLORIDA S CONTINUED GROWTH Florida has currently
More informationA Federal Perspective on Congestion Pricing. Wayne Berman Federal Highway Administration July 8, 2010
A Federal Perspective on Congestion Pricing Wayne Berman Federal Highway Administration July 8, 2010 Overview Background on Congestion Pricing Benefits and Experiences of Pricing Case Study Miami I-95
More informationCITY OF DELRAY BEACH. Overview Map. Commuter Mode of Choice QUICK FACTS. 47 Median Age. 65,804 Residents. 29.1% Traditionally Underserved
CITY OF $51,829 Median Income 291% Traditionally Underserved 438% Growth from 2010 859% HS/GED 345% Bachelors 27,041 Households 620% Labor Force Lake Okeechobee Delray Beach Palm Beach County Commuter
More informationPRESENTATION OUTLINE
November 8, 2017 PRESENTATION OUTLINE Regional Express Lanes Network Purpose/Benefits of Express Lanes 95 Express Phase 3C Project Video and Overview 95 Express Phase 3C Schedule 2 SOUTH FLORIDA REGIONAL
More informationAPPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD
APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD INTERSECTION NEEDS AT SR 7 and OKEECHOBEE BOULEVARD SR 7 Extension Project Development and Environment (PD&E) Study From Okeechobee Boulevard (SR
More informationFlorida Department of Transportation District Six Project FM # Public Information Meeting Tuesday, July 24, 2018
Florida Department of Transportation District Six Project FM #432687-1-52-01 Public Information Meeting Tuesday, July 24, 2018 South Florida Express Lanes Network The I-75/SR 826 Palmetto Express Lanes
More informationCongress Avenue. Palm Beach MPO Subcommittee Meetings December 2017
1 Congress Avenue Palm Beach MPO Subcommittee Meetings December 2017 2 Agenda Study Purpose Study Process Multimodal Alternatives Development Next Steps *ACTION ITEM: CONFIRM ALTERNATIVES TO MOVE INTO
More informationFI N A N C I A L RESOURCER S REVIEW AND UPDATE M I A M I-DADE LO N G R A N G E TRANSPORT T ATION PLAN UPDATE TO THE YE
Appendix B: Miami-Dade LRTP Cost Feasible Projects (Fully Funded and Partially Funded Projects) Fully Funded Projects Existing County roads O&M $317.9 $316.7 $811.5 Non Motorized set aside $27.9 $24.7
More informationMay 10, 2013 Meredith Cruz, (561) Palm Beach County Traffic Report May 10 through May 17, 2013
May 10, 2013 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 10 through May 17, 2013 Palm Beach County Palm Beach County traffic will be affected this week by ongoing
More informationI-264 CORRIDOR EVALUATION STUDY. September 7, 2016 Eric Stringfield VDOT Planning Director Chris Lawrence AECOM Senior Transportation Engineer
I-264 CORRIDOR EVALUATION STUDY September 7, 2016 Eric Stringfield VDOT Planning Director Chris Lawrence AECOM Senior Transportation Engineer Study Overview Interchange Locations Study Context Follow-up
More information2017 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW THE RITZ CARLTON, AMELIA ISLAND August 10-13, 2017
Florida Department of TRANSPORTATION 2017 FTBA ANNUAL CONFERENCE FDOT WORK PROGRAM OVERVIEW THE RITZ CARLTON, AMELIA ISLAND August 10-13, 2017 Mike Dew, Secretary FLORIDA S CONTINUED GROWTH Florida has
More informationICPP Phase II Report
Executive Summary... 5 1. Introduction... 11 2. Selection of Express Lane Projects... 13 2.1 Veterans Expressway/SR 589... 13 2.2 Turnpike/SR 821... 15 3. Pricing Policy for Express Lanes... 19 4. Conceptual
More informationI 595 Express Corridor Improvements Project. February 2014 Update
I 595 Express Corridor Improvements Project February 2014 Update PROJECT COMPONENTS Reversible Express Lanes Direct Connect to Florida s Turnpike Open Road Tolling SR 84 Continuous Connection Florida s
More informationHIA Working Group Meeting #4 September 27, 2017
HIA Working Group Meeting #4 September 27, 2017 Icebreaker Agenda US-1 Corridor Study Update Health Indicator Assessment Station Demonstration Area Assessment Preliminary Recommendations Discussion Next
More informationTPA Committee Meetings May 2018
TPA Committee Meetings May 2018 Purpose Develop a comprehensive plan to identify multimodal improvements for all users of the roadway and evaluate the potential for a premium express bus service Overview
More informationManaged Lanes. Steve Schilke, P.E. Major Projects Unit Head District 1. Illinois Traffic Engineering and Safety Conference October 2016
Managed Lanes Steve Schilke, P.E. Major Projects Unit Head District 1 Illinois Traffic Engineering and Safety Conference October 2016 Agenda Managed Lanes Projects I-55 (Stevenson Expressway) Express Toll
More informationLIST OF PRIORITY PROJECTS FY TPA Committee Meetings & Board Review September 2018
LIST OF PRIORITY PROJECTS FY 2020-2024 TPA Committee Meetings & Board Review September 2018 MISSION To collaboratively plan, prioritize, and fund the transportation system. El Rio Trail Boca Raton, May
More informationAlternatives Public Workshop
US 1 Express Lanes Project Development & Environment (PD&E) Study Alternatives Public Workshop August 2013 1 Today s Agenda Project Background and Overview Tier 1 Alternatives Development Tier 2 Decision-Making
More informationToday s Agenda. Welcome & Introductions. I-526 Lowcountry Corridor Update. Table Discussions. Next Steps / Conclusion
SCDOT Turns 100! SCDOT Turns 100! Today s Agenda Welcome & Introductions I-526 Lowcountry Corridor Update Table Discussions Next Steps / Conclusion Project Limits I-526 Lowcountry Corridor Project Description
More informationTransit Operations in the I-95 Express Lanes
Transit Operations in the I-95 Express Lanes TRB 15 th International Conference on Managed Lanes Miami, Florida Presented by Diane Quigley FDOT Transit Planning Administrator May 5, 2016 FDOT Governance
More informationSR 826/PALMETTO EXPRESSWAY EXPRESS LANES PD&E STUDY From US 1/SR 5/Dixie Highway to SR 836/Dolphin Expressway FPID No.: ETDM No.
SR 826/PALMETTO EXPRESSWAY EXPRESS LANES PD&E STUDY From US 1/SR 5/Dixie Highway to SR 836/Dolphin Expressway FPID No.: 432639-1-22-02 ETDM No.: 14308 Newsletter 3 - March 2019 Incluye versión en español
More informationEXISTING PRIORITIES FUNDED FOR CONSTRUCTION LRTP
EXISTING PRIORITIES FUNDED FOR CONSTRUCTION Limits Description Status 1 415489 3 H1865 US HWY 301 FROM SR 674 TO BALM RD Widen 2 lanes to 6 lanes divided County / Construction Programmed 2016 2 405492
More informationAgenda. US-1 Corridor Study and HIA Update. Pathway Diagram / Primary Indicators. Research Questions. Linking Multimodal Improvements to Indicators
Icebreaker Agenda US-1 Corridor Study and HIA Update Pathway Diagram / Primary Indicators Research Questions Linking Multimodal Improvements to Indicators Vulnerable Populations US-1 Corridor Study Vision
More informationTransit Initiatives 1
Transit Initiatives 1 TPA Transit Overview Capital Projects Transit Planning Initiatives Challenges Tri-Rail Layover Facility, New Boca Station Northern Layover Facility $28.7 M; Completion in 2023 Boca
More informationWhat are Managed Lanes?
Express Lanes What are Managed Lanes? Highway facilities or a set of lanes where operational strategies are proactively implemented and managed in response to changing conditions. http://ops.fhwa.dot.gov/freewaymgmt/managedlanesvideo/index.htm
More informationPublic Hearing October 21, 2014 University of North Florida Adam W. Herbert University Center Alumni Drive Jacksonville, FL 32224
- Project Development & Environment Study from SR 9B to SR 202 (JTB Blvd.) Duval County, Florida Financial Project ID: 209301-3-22-01 Public Hearing October 21, 2014 University of North Florida Adam W.
More informationSanta Clara I-280 CORRIDOR STUDY
Santa Clara I-280 CORRIDOR STUDY OCTOBER 2017 PREPARED BY: 1.1 Background The I-280 Corridor Study within Santa Clara County is a high-level highway planning study led by the Santa Clara VTA, in partnership
More informationFlorida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Five
DISTRICT FIVE PROJECT OVERVIEW Florida s Turnpike Enterprise continues to make significant project investments in District Five. In fiscal years 2014 and 2015, current Turnpike projects total over $330
More informationPlanning Study SR 976. Project Advisory Team Meeting May 24, 2017
` SR 976 BIRD ROAD/SW 40TH STREET FROM SR 821/HEFT TO SR 5/US-1 Miami-Dade County, Florida FPID No.: 434845-4-22-01 Planning Study Project Advisory Team Meeting May 24, 2017 1 Agenda Introductions Project
More informationPublic Hearing Tarrant County. October 11 th, 2012
Public Hearing Tarrant County October 11 th, 2012 Public Hearing Agenda Welcome and Project Overview Ms. Maribel P. Chavez, P.E. District Engineer Texas Department of Transportation Fort Worth District
More informationOperational Comparison of Transit Signal Priority Strategies
Operational Comparison of Transit Signal Priority Strategies Revision Submitted on: November, 0 Author: Adriana Rodriguez, E.I Assistant Engineer Parsons Brinckerhoff 0 South Orange Avenue, Suite 00 Orlando,
More informationI-66 Corridor Improvements Route 15 to I-495. November 2014
I-66 Corridor Improvements Route 15 to I-495 November 2014 I-66 Corridor: Haymarket to the Beltway = Park and Ride Lots 2 Purpose and Need Improve multimodal mobility along the I-66 corridor by providing
More informationHighway 217 Corridor Study. Phase I Overview Report
Highway 217 Corridor Study Phase I Overview Report November 3, 24 BACKGROUND AND OVERVIEW Study purpose The Highway 217 Corridor Study is developing multi-modal transportation solutions for traffic problems
More information!!!!!!!!!!!!!!!!!! Metro!Denver!MTD!Governance!Committee! October!23,!2013!!9:00!AM!to!10:00!AM! Denver!Regional!Council!of!Governments!
MetroDenverMTDGovernanceCommittee October23,2013 9:00AMto10:00AM DenverRegionalCouncilofGovernments MeetingRecord MetroDenverMTDGovernanceCommittee October23,2013 9:00AM Agenda: 9:00AM Welcome&Introductions
More information95 Express Annual Operations Report: Fiscal Year
95 Express Annual Operations Report: Fiscal Year 2014-2015 General The 95 Express Program completed its sixth full Fiscal Year of operations in June 2015. For the FDOT, its Fiscal Year (FY) is from July
More informationTRB Managed Lanes Conference May 22 24, 2012, Oakland, CA
HOT LLanes and d TTransit i P f Performance TRB Managed Lanes Conference May 22 24, 2012, Oakland, CA Miami UPA Transit Results (2008 2010 Data) Miami UPA Transit Improvements 2 new routes Dade-Broward
More informationBay to Bay Boulevard Complete Streets Project
Bay to Bay Boulevard Complete Streets Project Dale Mabry Highway to Bayshore Boulevard February 08, 2018 Photo Source: Tampa Bay Times Alessandra Da Pra Meeting Format Introduction Resurfacing Information
More informationDesign Traffic Technical Memorandum
State Road 7 Extension PD&E Study Design Traffic Technical Memorandum Palm Beach County, FL October 2010 State Road 7 Extension PD&E Study Design Traffic Technical Memorandum Palm Beach County, FL Prepared
More information395 Express Lanes Extension
395 Express Lanes Extension January 2016 Building a network of Express Lanes Project overview Add capacity on I-395 with addition of a third HOV lane and active traffic management Generate guaranteed transit
More informationFINAL DESIGN TRAFFIC TECHNICAL MEMORANDUM
FINAL DESIGN TRAFFIC TECHNICAL MEMORANDUM July 2014 FINAL (SR 43) Project Development and Environment Study From State Road 60 (Adamo Drive) to I-4 (SR 400) Hillsborough County, Florida Work Program Item
More informationProject Description Form 8EE
Project Description Form 8EE Basic Project Information Submitting Jurisdiction/Agency: Town of Dumfries Project Title: Route 1 (Fraley Blvd) Widening: Brady's Hill Road to Dumfries Road Project Location:
More informationFDOT Treasure Coast Traffic Report
July 6, 2018 Barbara Kelleher, 954 777 4090 Barbara.Kelleher@dot.state.fl.us FDOT Treasure Coast Traffic Report July 6 through July 13, 2018 TREASURE COAST Construction and maintenance related lane closures
More informationMnPASS System Today and the Future
MnPASS System Today and the Future April 2010 By Nick Thompson Minnesota Department of Transportation Topics Minnesota s Current and Future MnPASS High Occupancy Toll Systems Overview of the MnPASS System
More information2012 PRIORITY TRANSPORTATION PROJECTS
0 PRIORITY TRANSPORTATION PROJECTS The 0 Priority Transportation Projects include candidate road, congestion management, multi-use trail, transit, transportation regional incentive program (TRIP), county
More informationEffects of Traffic Signal Retiming on Safety. Peter J. Yauch, P.E., PTOE Program Manager, TSM&O Albeck Gerken, Inc.
Effects of Traffic Signal Retiming on Safety Peter J. Yauch, P.E., PTOE Program Manager, TSM&O Albeck Gerken, Inc. Introduction It has long been recognized that traffic signal timing can have an impact
More informationPalm Beach County Traffic Report November 16 through November 23, 2018
November 16, 2018 Barbara Kelleher, (954) 777 4090 Barbara.Kelleher@dot.state.fl.us Palm Beach County Traffic Report November 16 through November 23, 2018 Palm Beach County Palm Beach County traffic will
More informationTraffic Safety Study Report City Wide Intersection Study City of Coconut Creek Broward County, Florida
EXHIBIT "A" Traffic Safety Study Report City Wide Intersection Study City of Coconut Creek Broward County, Florida Prepared by: June 8, 2017 Revised January 18, 2018 TABLE OF CONTENTS 1. Introduction...
More informationFinancial Project ID No(s).: and ETDM No(s).: and 14181
Palm Beach Metropolitan Planning Organization (MPO) Presentation I-95 at Boynton Beach Boulevard Interchange and I-95 at Gateway Boulevard Interchange Project Development and Environment Study Palm Beach
More informationState Road 54/56 Tampa Bay s Northern Loop. The Managed Lane Solution Linking I-75 to the Suncoast Parkway
State Road 54/56 Tampa Bay s Northern Loop The Managed Lane Solution Linking I-75 to the Suncoast Parkway SUNCOAST PARKWAY Both I 75 and the Suncoast Parkway are planning, or in the process of constructing,
More informationPreliminary Review of the T-REX Southeast Corridor Highway and Light Rail Transit Project
Preliminary Review of the T-REX Southeast Corridor Highway and Light Rail Transit Project DRCOG Congestion Mitigation Program White Paper 07-1 (February 16, 2007) On time and under budget! Festivities
More informationAppendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station
Appendix C NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station Prepared for: Regional Transportation Department and URS Corporation as part of the North Metro EIS David Evans and Associates,
More information2018 Transportation Alternatives Program (TAP) Application Presentation to Palm Beach TPA BRANT BRIDGE CONNECTION LOOP EXTENSION ON CARL BOLTER DR
2018 Transportation Alternatives Program (TAP) Application Presentation to Palm Beach TPA BRANT BRIDGE CONNECTION LOOP EXTENSION ON CARL BOLTER DR Project Location N N Connecting South Delray Beach Existing
More informationNorthwest Corridor Project Interchange Modification, Interchange Justification and System Analysis Report Reassessment (Phase I)
Northwest Corridor Project Interchange Modification, Interchange Justification and System Analysis Report Reassessment (Phase I) Introduction The Georgia Department of Transportation (GDOT) prepared a
More informationManaged Lanes 2017: What They Are and How They Work. Robert W. Poole, Jr. Director of Transportation Policy Reason Foundation
Managed Lanes 2017: What They Are and How They Work Robert W. Poole, Jr. Director of Transportation Policy Reason Foundation http://reason.org What are Managed Lanes? Lanes restricted by price or vehicle
More information3.0 PROJECT DESCRIPTION
The following section of the Draft EIR contains a description of the proposed Elk Grove Boulevard/SR 99 Interchange Modification project, consistent with the requirements of CEQA Guidelines Section 15124.
More informationCity of Gainesville Transportation/Roadway Needs PROJECT SUMMARY
A1 Roadway Resurfacing $23,846,000 TYPE: Preservation of existing system Roadway resurfacing A2 Signal Replacement $6,000,000 TYPE: Preservation of existing system Replace traffic signals. B1 W 6th St
More informationFDOT Treasure Coast Traffic Report
July 13, 2018 Barbara Kelleher, 954 777 4090 Barbara.Kelleher@dot.state.fl.us FDOT Treasure Coast Traffic Report July 13 through July 20, 2018 TREASURE COAST Construction and maintenance related lane closures
More informationSR 9/I-95 Interchange at 45 th Street PD&E Study Palm Beach County, Florida FPID No.: FAP No.: ETDM No.
SR 9/I-95 Interchange at PD&E Study Palm Beach County, Florida FPID No.: 436519-1-22-01 FAP No.: 0951-682-1 ETDM No.: 14225 Palm Beach County MPO October 19, 2017 SR 9/I-95 Interchange at PD&E Study Presentation
More informationDonahue Drive Corridor Traffic Operational Evaluation
Donahue Drive Corridor Traffic Operational Evaluation PREPARED FOR: THE CITY OF AUBURN PREPARED BY: JANUARY 2007 Donahue Drive Corridor Study--Auburn, Alabama TABLE OF CONTENTS Introduction... 1 Background
More informationBroward Complete Streets Advisory Committee (CSAC) Meeting. Monday, September 24, 2018
Broward Complete Streets Advisory Committee (CSAC) Meeting Monday, September 24, 2018 HOUSEKEEPING Please make sure you have signed in and have an agenda. This meeting is being recorded. Please introduce
More informationCongestion Management Report
Congestion Management Report F.E. EVERETT TURNPIKE (NORTH), MERRIMACK Segment Length: 7.0 miles Daily Traffic Volumes: 60,000-69,000 Analysis Period: May 2015 Number of Traffic Signals: 0 Number of travel
More informationToll Express Lanes for the Research Triangle region Including discussion of possible applications on I-40
Toll Express Lanes for the Research Triangle region Including discussion of possible applications on I-40 Presentation for discussion at Durham-Chapel Hill-Carrboro MPO TAC meeting Wednesday, December
More informationFlorida Redevelopment Association 2015 Annual Conference
Florida Redevelopment Association 2015 Annual Conference Reimagining State Arterials Jeff Costello, Delray Beach CRA Executive Director I-95 Fed. Hwy Pairs Two blocks west of Intracoastal Waterway One-way
More informationModel Applications for Oakland Park Boulevard Transit Corridor Study
Model Applications for Oakland Park Boulevard Transit Corridor Study Southeast Florida FSUTMS Users Group June 13, 2014 Vikas Jain, AICP, GISP FDOT District Four Auditorium 3400 West Commercial Boulevard,
More informationDescription: Widen I-64 to 6 lanes from I-265 to the KY 53 interchange in Shelby County.
I-64 KIPDA ID # 350 Project Type: ROADWAY CAPACITY Description: Widen I-64 to 6 lanes from I-265 to the KY 53 interchange in Shelby County. Purpose: Project will improve capacity and address safety concerns.
More informationPedestrian and Bicycle Safety Study
Palm Beach MPO Pedestrian and Bicycle Safety Study 44164.16 Palm Beach Metropolitan Planning Organization presents Pedestrian and Bicycle Safety Study Prepared by: Kimley-Horn and Associates, Inc. The
More information7.0 FREEWAYS CONGESTION HOT SPOT PROBLEM & IMPROVEMENT PROJECT ANALYSIS & DEFINITION
7.0 FREEWAYS CONGESTION HOT SPOT PROBLEM & IMPROVEMENT PROJECT ANALYSIS & DEFINITION 7.1 INTRODUCTION & METHODOLOGY FEASIBILITY REPORT Congestion hot spot problem locations have been assessed using the
More informationTransportation Investment Act Gwinnett County. Charlotte J. Nash, Chairman Gwinnett County Board of Commissioners
Transportation Investment Act Gwinnett County Charlotte J. Nash, Chairman Gwinnett County Board of Commissioners April 25, 2012 Transportation Investment Act Gwinnett County Gwinnett County Transportation
More informationWashington DC Section of ITE Project Briefing
Washington DC Section of ITE Project Briefing November 5, 2015 Renée Hamilton, VDOT, Deputy District Administrator I-66 Outside the Beltway Improvement Area Project Location Virginia 2 Purpose and Need
More informationCOMMUNITY WORKSHOP (CW) 3 February 21, 2015
QEW Improvements QEW Improvements COMMUNITY WORKSHOP (CW) 3 February 21, 2015 1 WORKSHOP PURPOSE MOVING FORWARD Review of Technically Preferred alternative Seeking feed back for progressing to next design
More informationQueensboro Bridge Bus Priority Study: Summary of Recommendations. Presentation to Manhattan Community Board 8 May 4, 2011
: Summary of Recommendations Presentation to Manhattan Community Board 8 May 4, 2011 1 Overview Study Goal: Identify cost-effective ways to improve bus speed and reliability for local and express buses
More informationTAMPA BAY EXPRESS (TBX)
TAMPA BAY EXPRESS (TBX) Hank Schneider, P.E. FDOT- District 7 Consultant Project Manager Florida Department of TRANSPORTATION TAMPA BAY EXPRESS AGENDA What is TBX? What does TBX do? Why is TBX Important?
More informationUS 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue
41 US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue EXECUTIVE SUMMARY DRAFT FEBRUARY 2019 Project Overview The US 41 Complete Streets Corridor Planning Study,
More informationFM #: ETDM #: 11241
SR 826/Palmetto Expressway PD&E Study From SR 93/I 75 to the Golden Glades Interchange FM #: 418423 1 22 01 ETDM #: 11241 Agency/ Kick Off Meeting October 27, 2011 2 Location Map From SR 93/I 75 to Golden
More informationAPPENDIX D. May 22, 2002 Open House Summary and Materials
APPENDIX D May 22, 2002 Open House Summary and Materials TH 36 Partnership Study Open House May 22, 2002 Summary of Survey Responses 1. If no new crossing of the St. Croix River is built (e.g. the existing
More informationDULLES AREA TRANSPORTATION ASSOCIATION (DATA) February 18, Susan Shaw, P.E., VDOT, Megaprojects Director
DULLES AREA TRANSPORTATION ASSOCIATION (DATA) February 18, 2015 Susan Shaw, P.E., VDOT, Megaprojects Director I-66 Corridor Conditions Steady population growth Employment growth in activity centers Congestion
More informationMoPac South: Impact on Cesar Chavez Street and the Downtown Network
MoPac South: Impact on Cesar Chavez Street and the Downtown Network Prepared by: The University of Texas at Austin Center for Transportation Research Prepared for: Central Texas Regional Mobility Authority
More informationCongestion Reducing Activities. Toby Carr GDOT Director of Planning April 10, 2014
Congestion Reducing Activities Toby Carr GDOT Director of Planning April 10, 2014 GDOT Performance Dashboard Congestion Congestion Relief Strategies 511 HEROS RTOP Highway Emergency Response Operators
More informationFigure 1: East West Connector Alignment Alternatives Concept Drawing
Page 2 of 9 Figure 1: East West Connector Alignment Alternatives Concept Drawing The Montebello Drive extension will run north south and connect Wilsonville Road to the Boones Ferry Road to Brown Road
More informationCapital Beltway HOT Lanes - Frequently Asked Questions
Capital Beltway HOT Lanes - Frequently Asked Questions December 20, 2007 1. What is the cost of the project? The fixed-price design-build cost is approximately $1.4 billion. 2. Why have the project costs
More informationI-20 ODESSA-MIDLAND CORRIDOR STUDY. Public Meeting for Schematic Design
I-20 ODESSA-MIDLAND CORRIDOR STUDY Public Meeting for Schematic Design The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being,
More informationTolling Study. July 23, 2009
Eastside Corridor Tolling Study Interagency Working Group July 23, 2009 1 Welcome Craig Stone Director of WSDOT Toll Division 2 Agenda Introductions/Roles & Responsibilities Meeting Goals Express Toll
More information::~-~ w ANNUAL LIST OF PALM BEACH MPO PRIORITY PROJECTS FY Adopted July 20, '"',, - ==~"'c;;f'";~":?:'!""
PALM BEACH MPO w ANNUAL LIST OF PRIORITY PROJECTS FY 2019-2023 Adopted July 20, 2017 ::~-~ '"',, - ==~"'c;;f'";~":?:'!"" ~~ Ch a r www. Pa Im M PO.org/p ri oriti es 2300 North Jog Road. 4th Floor.. FL.
More informationChapter 4 Traffic Analysis
Chapter 4 Traffic Analysis PURPOSE The traffic analysis component of the K-68 Corridor Management Plan incorporates information on the existing transportation network, such as traffic volumes and intersection
More informationBETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY
DRAFT PLAN City Council Meeting August 14, 2017 STUDY AREA Sedgwick Corridor State Route 160, principal arterial with Class 3 access management designation, commuter and freight route, connection to SR
More informationWaterford Lakes Small Area Study
Waterford Lakes Small Area Study Existing Traffic Conditions PREPARED FOR: ORANGE COUNTY PUBLIC WORKS DEPARTMENT TRAFFIC ENGINEERING DIVISION ORLANDO, FLORIDA PREPARED WITH: INWOOD CONSULTING ENGINEERS
More informationSH-6 Corridor Improvement Study Policy Committee Progress Report M O N D AY, J U N E 1 0, B R A Z O S C E N T E R
SH-6 Corridor Improvement Study Policy Committee Progress Report M O N D AY, J U N E 1 0, 2 0 1 3 B R A Z O S C E N T E R Project Overview Study Goals and Objectives» Improve traffic flow» Reduce delay»
More informationSTAKEHOLDER MEETING STANFORD RANCH ROAD/GALLERIA BOULEVARD/SR 65 NORTHBOUND RAMPS PROJECT APPROVAL & ENVIRONMENTAL DOCUMENT (PA&ED) PHASE
STAKEHOLDER MEETING STANFORD RANCH ROAD/GALLERIA BOULEVARD/ SR 65 NORTHBOUND RAMPS PROJECT APPROVAL & ENVIRONMENTAL DOCUMENT (PA&ED) PHASE January 12, 2016 Welcome and Introductions Meeting Goals I 80/SR
More information7.0 Preferred Alternative with Service Road Concept
.0 Preferred Alternative with Service Road Concept This section evaluates the traffic operations for all of the study years for the Build conditions as related to the Preferred Alternative with Service
More informationRoad Diets FDOT Process
Florida Department of TRANSPORTATION Road Diets FDOT Process Humberto Castillero, PE, PTOE Roadway Design Office Purpose of Guide Develop a statewide lane elimination review process Balance state & local
More information4.1 Evaluation Criteria
Section 3 of the I-280 Corridor Study report discussed potential improvements for the I-280 corridor improve mobility for all modes of transportation. This section evaluates those potential improvements
More informationBOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY
7B BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY PLACEMENT: REQUESTS AND PRESENTATIONS PRESET: TITLE: FLORIDA DEPARTMENT OF TRANSPORTATION (FDOT) PRESENTATION RECONSTRUCTION OF SR-76 (SW KANNER HIGHWAY)
More informationI-95/Temple Avenue Improvements Project Colonial Heights, VA
I-95/Temple Avenue Improvements Project Colonial Heights, VA Pardon Our Dust Informational Meeting February 3, 2016 Harold Dyson, P.E. Construction Manager, Richmond District Tom Heil, P.E. Allan Myers
More informationVISION ZERO ACTION PLAN
PALM BEACH Transportation Planning Agency VISION ZERO ACTION PLAN TPA Advisory Committee Meetings March 2019 PURPOSE Present the Data Analysis Key Findings and the Action Items from the Draft Action Plan
More informationI-395 Express Lanes Northern Extension Project Crystal City Civic Association September 21, 2016
I-395 Express Lanes Northern Extension Project Crystal City Civic Association September 21, 2016 Mike Snare, PE, Project Manager Virginia Department of Transportation GEC Michelle Holland, Megaprojects
More informationExecutive Summary June 2015
Executive Summary June 2015 Highway 112 Corridor Study Benton and Washington Counties Executive Summary June 2015 Prepared by Transportation Planning and Policy Division Arkansas State Highway and Transportation
More informationREGIONAL PRIORITIES Presentation to the Tampa Bay Regional Collaboration Committee September 10, 2012
WEST CENTRAL FLORIDA MPO CHAIRS COORDINATING COMMITTEE REGIONAL PRIORITIES Presentation to the Tampa Bay Regional Collaboration Committee September 10, 2012 TRANSPORTATION REGIONAL INCENTIVE PROGRAM (TRIP)
More informationLos Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation
Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto
More informationPalm Beach County Traffic Report January 11 through January 18, 2019
January 11, 2019 Barbara Kelleher, (954) 777 4090 Barbara.Kelleher@dot.state.fl.us Palm Beach County Traffic Report January 11 through January 18, 2019 Palm Beach County Palm Beach County traffic will
More information