ENGINEERING AND PUBLIC WORKS. Transportation Improvements: Santa s Village Road (MR15) Public Meeting

Size: px
Start display at page:

Download "ENGINEERING AND PUBLIC WORKS. Transportation Improvements: Santa s Village Road (MR15) Public Meeting"

Transcription

1 ENGINEERING AND PUBLIC WORKS Transportation Improvements: Santa s Village Road (MR15) Public Meeting March 22, 2018

2 Agenda Welcome and Introductions Fred Jahn: Commissioner of Engineering and Public Works Michelle Hendry: Director, Transportation, Engineering, Solid Waste Elvis Jose: Manager, Engineering Services Paul Hausler: Consultant, RJ Burnside Kevin Butt: Arborist, RJ Burnside Where are we now? Design of Santa s Village Road / Overview of Design Safe Roads Campaign Anticipated Construction Schedule Next Steps Individual Consultations Final Completion of Engineering

3

4

5

6 Santa s Village Road Design 6B Improvement of road surface, road base, subgrade performance issues. Improve user safety deficiencies, drainage, erosion problems, active transportation concerns. Private water and sewer infrastructure upgrades for Santa s Village; Overview of Design Considerations:

7 1. Roadside Safety Existing 3 cable Guide Rail does not provide adequate protection or meet required standards; An additional 820m of steel beam Guide Rail will be installed with proper end treatment where possible; Guide Rail is required to ensure motorist safety and protect structures along the river.

8 2. User Safety and Active Transportation Safety and speed a concern Narrow lanes encourage slower traffic speeds Painted line to delineate traffic lane from shoulder Partnership with OPP Safe Roads Campaign Rumble strips excluded from design Signage has been reviewed in accordance with Provincial and District guidelines

9 3. Access to the Muskoka River Gaps in guide rail will be provided for existing walkways, docks, boathouses/cottages ( m); Guide rail improvements will limit access (in some areas); Additional gaps in the Guide Rail will be considered if requested; (individual property owner consultations)

10 4. Trees and Property Landscape Saving trees is recognized as a priority. The addition of paved road shoulders results in a wider road platform; Removal of trees required, (mature, small caliper trees and brush); District will replant trees where possible on the road allowance or private property, if no impacts to road and overhead clearance; Tree removals and maintenance to be carried out after Thanksgiving 2018.

11 5. Private Services and Parking Private services within the public road allowance require a License of Occupation (LOC); Residents advised by letter dated February 6, to apply for an LOC (if they do not currently have one); LOC issues are unique to each property and individual services can be discussed during one-on-one property owner consultations; Private Services within the travelled portion of the road will be reviewed on a case by case basis; Parking on the side of the road will not be permitted to accommodate unrestricted access to the paved shoulders

12 6. Inconsistent ROW (Right-of-Way) Width Some properties will restrict construction of the proposed road cross-section; Curb and gutter will be used to eliminate ditching and culverts (to minimize impacts to properties and trees) in some areas. Some river access features and structures and other landscape features within the ROW may interfere with road construction (ex. stairs, gardens, fences); these customized issues will be managed with each property owner; Permission to Enter Agreements will be required for grading onto some properties;

13 7. Drainage Drainage will be improved along Santa s Village Road by: Installation of consistent ditching, driveway culverts, additional outlets to the river, ditch cleaning and crowning of the road; Driveway culverts will be replaced with 14 inch diameter culverts and road crossing culverts will be replaced (as required) with a minimum 24 inch diameter culverts; Erosion will be mitigated with the installation of slope reinforcement techniques, rip rap, cut off walls and headwalls at all outlets.

14 8. Driveway Grades Existing driveway grades will be maintained or improved where possible; Additional grading and other work on the affected property may be required and will require signed Permission to Enter agreements with each property owner; Driveway culverts will be replaced/relocated (as required) to provide improved drainage; Existing driveway finishes (asphalt, gravel, concrete, etc.) will be replaced where impacted by construction activities.

15 Anticipated Construction Schedule

16 Santa s Village Road Construction Schedule Tree Management Trimming, Brushing, Removals: Anticipated late October- December 2018 Road Improvement Construction: Anticipated Start: May, 2019 Anticipated Completion: November, 2019 Final Lift of Asphalt: June, 2020

17 How Will I Be Affected During Construction? Access to all properties will be maintained; entry may be restricted temporarily; (owners will be given at least 48 hours notice of access restrictions) No full road closure; Access for emergency vehicles will be maintained at all times; Interruption to residential services such as telephone, hydro, gas, etc. are not anticipated; Waste Management collection will not be affected; Normal working hours are expected to be between 7:00 am and 6:00 pm Monday through Friday; Residents located within construction limits will be notified prior to the start of construction and will be kept informed.

18 ENGINEERING AND PUBLIC WORKS Muskoka Safe Roads Campaign Highlights from Bracebridge Forum

19 What Brought Us Together?... A Muskoka-Wide Discussion OPP has several priorities related to safer roads Council / EPW has seen a consistent increase in requests from communities Several Community groups are engaged in local safe road initiatives Private sector is investing in marketing Drive Safe initiatives and there are partnership opportunities

20 Community Campaigns in Muskoka Local Road Safety Initiatives

21 Opportunity! Aligning all of these priorities and initiatives into a Muskoka-wide community partnership Engage multiple stakeholder groups in a multifaceted Muskoka Safe Roads Campaign Learn from successes in other communities to motivate behaviour change in drivers using the road networks across Muskoka.

22 Main Campaign Goals To Slow Down Reduce speeding / aggressive driving To Be Safe: Reduce distracted / impaired driving Promote seatbelts To Share The Road Cyclist and pedestrians ORV / ATV / MC Move Over for emergency vehicles Promote AT + construction safety + animal crossings

23 Speed Reduction Your choice of speed can affect others as well as yourself (children, animals, cyclists + other drivers) Take the Pledge! Make Muskoka Roads the Safest! Reduce your speed, stay focused and share the road.

24 Share the Road When everyone drives with care and courtesy, it is easy to share the road Be Safe Be Seen! Take the Pledge! Make Muskoka Roads the Safest! Reduce your speed, stay focused and share the road.

25 Distracted Driving Distracted Driving affects others as well as yourself (children, animals, cyclists + other drivers) and sets examples for future drivers Take the Pledge! Make Muskoka Roads the Safest! Reduce your speed, stay focused and share the road.

26 Other Ideas? WHOA! Only Santa Needs to go that fast!

27 Next Steps? Start of an ongoing dialogue with partners and the community Gravenhurst Forum- - April 11 Huntsville Forum - - April 19 West Muskoka Forum (Mactier) April 25 Working Group forming Call for volunteers at Bracebridge Forum Will look at the input from the forums and other community feedback and then to finalize a campaign strategy and implementation plan for 2018

28 Your Feedback is Important! Santa s Village Road Property Owners: Request for Meeting forms are located on the table at the back of the room; Comment sheets can be completed to communicate your thoughts on this evening s Public Meeting; Individual (one-on-one) meetings can be scheduled via the Request for Meeting Form ; meetings held at the District office regarding specific property impacts and concerns; Staff will also be here after the meeting to address individual concerns following this presentation.

29 Questions and Answers

The District Municipality of Muskoka 70 Pine Street Bracebridge ON P1L 1N3

The District Municipality of Muskoka 70 Pine Street Bracebridge ON P1L 1N3 Public Information Centre Summary Report Muskoka Road 15 (Santa s Village Road) Transportation Improvements from the Beaver Creek Bridge to the Entrance of Santa s Village The District Municipality of

More information

Hospital Link Project Project Update November 2017

Hospital Link Project Project Update November 2017 Hospital Link Project Project Update November 2017 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction is well underway. Read on for important

More information

Hospital Link Project Project Update September 2017

Hospital Link Project Project Update September 2017 Hospital Link Project Project Update September 2017 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction is well underway. Read on for important

More information

Readington Road (C.R. 637) Construction

Readington Road (C.R. 637) Construction Public Information Meeting Thursday, August 2, 2012 Readington Road (C.R. 637) Construction from Dreahook Road to Harlan School Road Branchburg Township, Somerset County Readington Township, Hunterdon

More information

Engineering Your Community Safe

Engineering Your Community Safe Engineering Your Community Safe Andi Bill Transportation Information Center thanks its partners for their support and assistance National Traffic Safety Goal Reasonable goal? Who s Involved? What can you

More information

Complete Streets. Designing Streets for Everyone. Sarnia

Complete Streets. Designing Streets for Everyone. Sarnia Complete Streets Designing Streets for Everyone Sarnia Complete Streets ~ Sarnia ~ 2018 Introduction Our City is made up of a network of streets that we use to go for a walk, cycle to work, drive to the

More information

Tonight is for you. Learn everything you can. Share all your ideas.

Tonight is for you. Learn everything you can. Share all your ideas. Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.

More information

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

City of Margate, Florida. Neighborhood Traffic Management Manual

City of Margate, Florida. Neighborhood Traffic Management Manual City of Margate, Florida Neighborhood Traffic Management Manual Table of Contents Page No. I. INTRODUCTION... 1 II. TRAFFIC CALMING REQUEST AND PROCESSING PROCEDURES... 2 1. COMPLETE AND SUBMIT PROJECT

More information

Public Information Centre

Public Information Centre WELCOME Public Information Centre Father Tobin Road Lougheed Middle School - Library Wednesday November 7, 2012 7:00 p.m.to 9:00 p.m. Please sign in Neighbourhood Traffic Calming Guide Background The City

More information

TRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION

TRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION TRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION CITY OF TORONTO TRANSPORTATION SERVICES DIVISION 2016 TRAFFIC CALMING GUIDE FOR TORONTO TABLE OF CONTENTS Introduction

More information

122 Avenue: 107 Street to Fort Road

122 Avenue: 107 Street to Fort Road : 107 Street to Fort Road November 24, 2015 4:30 8:00 p.m. Meeting Purpose Summarize project work completed to date Share results of public input from Phase 1 Share the draft concept plan and proposed

More information

Toward Zero Deaths. Regional SHSP Road Show Meeting. Virginia Strategic Highway Safety Plan. presented by

Toward Zero Deaths. Regional SHSP Road Show Meeting. Virginia Strategic Highway Safety Plan. presented by Toward Zero Deaths Regional SHSP Road Show Meeting presented by Virginia Strategic Highway Safety Plan December 1, 2016 1 Welcome & Introductions Purpose of the Meeting Objectives & Key Outcomes Agenda»

More information

Off-road Trails. Guidance

Off-road Trails. Guidance Off-road Trails Off-road trails are shared use paths located on an independent alignment that provide two-way travel for people walking, bicycling, and other non-motorized users. Trails specifically along

More information

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach CONNECTIVITY PLAN Adopted December 5, 2017 City of Virginia Beach CONTENTS 1.0 Background & Purpose... 2 2.0 Existing Inventory & Analysis... 3 ViBe District Existing Walking Conditions... 4 3.0 ViBe District

More information

Kalamazoo County Weekly Project Updates from the Cities of Portage, Kalamazoo and the Kalamazoo County Road Commission

Kalamazoo County Weekly Project Updates from the Cities of Portage, Kalamazoo and the Kalamazoo County Road Commission FOR IMMEDIATE RELEASE Date: October 31, 2014 Kalamazoo County Weekly Project Updates from the Cities of Portage, Kalamazoo and the Kalamazoo County Road Commission Kalamazoo, MI- In a collaborative effort

More information

Access Management Standards

Access Management Standards Access Management Standards Section 1: Application of Access Standards This chapter describes the Department's access management standards for access connections on the county roadway system. The standards

More information

Chapter 3 DESIGN SPECIFICATIONS

Chapter 3 DESIGN SPECIFICATIONS Brampton PathWays Planning and Design Guidelines 27 Chapter 3 DESIGN SPECIFICATIONS 3.1 CLASS 1 MULTI-USE PATH Off-road multi-use trails are the backbone of the Brampton PathWays Network. They are typically

More information

River Road - Proposed Road Safety Enhancement Measures

River Road - Proposed Road Safety Enhancement Measures City of Richmond Report to Committee To: From: Re: Public Works and Transportation Committee Victor Wei, P. Eng. Director, Transportation Date: June 6, 2017 River Road - Proposed Road Safety Enhancement

More information

Minimum Standards for Driveway Construction Village of Bear Creek

Minimum Standards for Driveway Construction Village of Bear Creek Minimum Standards for Driveway Construction Village of Bear Creek An exception to the following requirements may only be granted by city council. The needs of each drainage system are considered independently,

More information

Access requests to County streets and roadways are processed through one of the following methods:

Access requests to County streets and roadways are processed through one of the following methods: 13.1 GENERAL APPLICATION PROCESS Access requests to County streets and roadways are processed through one of the following methods: A. Planned Developments may set general locations for access points.

More information

Shoulders. Chapter 4: chapter contents

Shoulders. Chapter 4: chapter contents Chapter 4: Shoulders chapter contents Characteristics of Well-Maintained Shoulders 73 Optimal Timing/Conditions for Maintenance 73 Shoulder Maintenance Issues 74 Shoulder Maintenance Activities 75 Repairing

More information

Governance and Priorities Committee Report For the July 2, 2015 Meeting

Governance and Priorities Committee Report For the July 2, 2015 Meeting CITY OF VICTORIA For the July 2, 2015 Meeting To: Governance and Priorities Committee Date: From: Subject: Brad Dellebuur, A/Assistant Director, Transportation and Parking Services Executive Summary The

More information

City of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE

City of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE Welcome Welcome to the third community meeting for the Issaquah-Fall City Road Improvements Project. AGENDA 6:00 p.m. Welcome and sign-in 6:10 p.m. Presentation 6:50 p.m. Open house Learn about the roadway

More information

WELCOME Public Information Centre

WELCOME Public Information Centre WELCOME Public Information Centre Fernforest Drive Brampton Soccer Centre Community Room #2 Tuesday January 19, 2016 6:30 p.m.to 9:00 p.m. Please sign in Neighbourhood Traffic Calming Guide Background

More information

Road Safety Audit training course. Motorways - safety issues of the motorway design

Road Safety Audit training course. Motorways - safety issues of the motorway design Road Safety Audit training course Motorways - safety issues of the motorway design Jesper Mertner, Road safety auditor, COWI A/S 1 ROAD SAFETY AUDITING COURSE Content 1. Safety 2. Cross sections 3. Horizontal

More information

Frequently Asked Questions (FAQ)

Frequently Asked Questions (FAQ) Frequently Asked s (FAQ) Study Process... 2 Rapid Transit Service and Operations... 5 Public Consultation... 8 Business Impacts... 8 Design and Property Impacts... 9 Construction Impacts...12 Traffic,

More information

Building sidewalks on local streets to reduce accessibility barriers

Building sidewalks on local streets to reduce accessibility barriers Building sidewalks on local streets to reduce accessibility barriers Disability, Access, Inclusion and Advisory Committee 16 February 2016 Fiona Chapman, Manager, Pedestrian Projects Presentation overview

More information

American Railway Engineering and Maintenance of Way Association Letter Ballot. Draft

American Railway Engineering and Maintenance of Way Association Letter Ballot. Draft American Railway Engineering and Maintenance of Way Association Letter Ballot 1. Committee and Subcommittee: Committee 5 Track Subcommittee 9 Road Crossings 2. Letter Ballot Number: 05-17-16 3. Assignment:

More information

Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999

Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999 Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999,1'(; A ACCELERATION Data on acceleration from stop D-29 Effects of grade D-35 Intersections D-97, D-99 Lanes D-97, F-5, F-7, F-15, F-21,

More information

Cyclists and Bikeways: What s your match? A guide to bikeway options for a variety of cyclists

Cyclists and Bikeways: What s your match? A guide to bikeway options for a variety of cyclists Cyclists and Bikeways: What s your match? guide to bikeway options for a variety of cyclists The workshop and this resource were made possible by funding from the Province of Ontario via the Ministry of

More information

Broad Street Bicycle Boulevard Design Guidelines

Broad Street Bicycle Boulevard Design Guidelines Broad Street Bicycle Boulevard Design Guidelines Building from the strategies introduced in the 2013 Bicycle Transportation Plan and community input received thus far, City Transportation Staff have identified

More information

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

Frome Street Bicycle Route

Frome Street Bicycle Route The Adelaide City Council invites engagement from the community about Frome Street Bicycle Route Project Summary Adelaide City Council is seeking feedback on design options to construct bicycle facilities

More information

Highway 1 Kamloops to Alberta Four-Laning Program

Highway 1 Kamloops to Alberta Four-Laning Program Highway 1 Kamloops to Alberta Four-Laning Program COMMUNITY ENGAGEMENT DISCUSSION GUIDE AND FEEDBACK FORM February 7 March 1, 2013 www.bchwy1.ca 1 FEEDBACK FORM INSIDE HOW INPUT WILL BE CONSIDERED FAST

More information

Active Transportation Facility Glossary

Active Transportation Facility Glossary Active Transportation Facility Glossary This document defines different active transportation facilities and suggests appropriate corridor types. Click on a facility type to jump to its definition. Bike

More information

PEDESTRIAN ACTION PLAN

PEDESTRIAN ACTION PLAN ATTACHMENT 2 CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN This page intentionally left blank EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY Setting the Stage

More information

Access Management Guidelines February 2013 THE CITY OF

Access Management Guidelines February 2013 THE CITY OF Access Management Guidelines February 2013 THE CITY OF Table of Contents Introduction 2 Review and Approval Process 5 Technical Guidelines 9... 10... 12 3. Separation Distance: Non-Signalized All-Turns

More information

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Background Agenda Traffic Study Update Class EA Alternatives Bridge

More information

Traffic Control Inspection Checklist Segment:

Traffic Control Inspection Checklist Segment: Traffic Control Inspection Checklist Segment: Simon Contractors Simon Contractors Originator: Description Reviewed by: Initials Date Distribution: Traffic Quality Manager, Site Assistant Traffic Manager

More information

Review of Guidelines for Cycleway Safety Fencing

Review of Guidelines for Cycleway Safety Fencing Review of Guidelines for Cycleway 1.0 PURPOSE 1.1 This document is meant to provide a review of available reference documents for determining appropriate fencing requirements for cycleway paths and shared

More information

CITY OF VISTA TRAFFIC CALMING PROGRAM

CITY OF VISTA TRAFFIC CALMING PROGRAM CITY OF VISTA TRAFFIC CALMING PROGRAM The purpose of the Vista Traffic Calming Program is to reduce speeds of motorists driving through residential neighborhoods. The program does not apply to nonresidential

More information

Strategy for Walking & Cycling Action Plan

Strategy for Walking & Cycling Action Plan Strategy for Walking & Cycling Action Plan To achieve higher levels of walking and cycling activity, the destinations which people access have to be available within suitable distances and designed to

More information

Proposed Bridge Street East Bicycle Lanes Public Open House Thursday, April 27, 2017

Proposed Bridge Street East Bicycle Lanes Public Open House Thursday, April 27, 2017 WELCOME Proposed Bridge Street East Bicycle Lanes Public Open House Thursday, April 27, 2017 Purpose of the Open House The purpose of this Open House is to gain public input on the bicycle lanes proposed

More information

Safe Routes to School Action Plan Aberdeen, Idaho

Safe Routes to School Action Plan Aberdeen, Idaho Background Aberdeen, Idaho is a largely agricultural community of nearly 2,000 people and is located in the southeast portion of the state on the western edge of American Falls Reservoir. The community

More information

Montgomery County Life Sciences Center Loop Trail

Montgomery County Life Sciences Center Loop Trail Montgomery County Life Sciences Center Loop Trail Advisory Committee Meeting #1 February 10, 2015 Agenda 1. Project Background 2. Existing Conditions Analysis 3. Examples from Elsewhere 4. Discussion Project

More information

Walking Along the Road. Module 2

Walking Along the Road. Module 2 Walking Along the Road Module 2 Learning Outcomes: 2-2 At the end of this module, you will be able to: Describe the operational and safety benefits of shoulders and sidewalks Select the appropriate design

More information

ROAD OCCUPANCY PERMIT APPLICATION # Damascus Township, 60 Conklin Hill Road, Damascus, PA Tel Fax

ROAD OCCUPANCY PERMIT APPLICATION # Damascus Township, 60 Conklin Hill Road, Damascus, PA Tel Fax Instructions: For a driveway access permit, fill in sections 1, 2, 3 and 4, and the appropriate drawings and sign. For a Utility access, fill in sections 1, 2, 3 and 5, and figures 1 and 3. Prepare a detailed

More information

Closing Plenary Session

Closing Plenary Session TRAFFIC SAFETY CONFERENCE Closing Plenary Session June 9, 2017 Las Colinas, TX Order of Report Out June 9, 2017 Las Colinas, TX Distracted Driving Prioritized Countermeasures Countermeasure 4a Systemically

More information

CASTLE CREEK CORRIDOR PLANNING PUBLIC OPEN HOUSE

CASTLE CREEK CORRIDOR PLANNING PUBLIC OPEN HOUSE CASTLE CREEK CORRIDOR PLANNING PUBLIC OPEN HOUSE Wednesday, November 15, 2017 AGENDA Project Background and Today s Goals Corridor Constraints and Conflicts Usage Information Public Process Schedule Review

More information

SECTION 14: LANDSCAPING AND BEAUTIFICATION

SECTION 14: LANDSCAPING AND BEAUTIFICATION SECTION 14: LANDSCAPING AND BEAUTIFICATION RULE 14.1 GENERAL PROVISIONS 14.1.1 The rules and guidelines contained in this section have been established to provide proper guidelines for the beautification

More information

Welcome to the Open House

Welcome to the Open House Leslie Street Between 19 th Avenue and Stouffville Road Addendum to Class Environmental Assessment Study Welcome to the Open House Please sign in at the front desk. March 28, 2017 Richmond Green Sports

More information

UPTOWN REGIONAL BIKE CORRIDORS PROJECT SAN DIEGO ASSOCIATION OF GOVERNMENTS

UPTOWN REGIONAL BIKE CORRIDORS PROJECT SAN DIEGO ASSOCIATION OF GOVERNMENTS UPTOWN REGIONAL BIKE CORRIDORS PROJECT SAN DIEGO ASSOCIATION OF GOVERNMENTS SUMMARY REPORT: COMMUNITY UPDATE MEETING February 6, 2014 6 8:30 p.m. Roosevelt Middle School Library 3366 Park Blvd, San Diego

More information

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report Page 1 MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report August 1, 2012 MAG Project #481 Page 2 Task 6 Executive Summary and Regional Significance Report Introduction

More information

EMPHASIS AREA 1: PEDESTRIANS

EMPHASIS AREA 1: PEDESTRIANS EMPHASIS AREA 1: PEDESTRIANS A pedestrian is seriously injured or killed every 3 days on Toronto s roads. Pedestrian collisions involve any person that is not riding in a vehicle or on a bicycle. 26% OF

More information

Developing a Safer Cycling Strategy for the ACT ACRS Conference August 2012

Developing a Safer Cycling Strategy for the ACT ACRS Conference August 2012 Developing a Safer Cycling Strategy for the ACT ACRS Conference 2012 Peter Strang Canberra Manager Sarah Court Transport Consultant 10 August 2012 Presentation Outline Background Data Analysis (Stage 1)

More information

Montclair s Complete Streets Experience

Montclair s Complete Streets Experience Presented by: Hon. Jerry Fried, Mayor Montclair Township About Montclair Six square miles Six commuter rail stations Four local bus routes (NJ Transit) Two private commuter bus routes Five business districts

More information

URBANA TRAFFIC COMMISSION Tuesday, November 12, 2013

URBANA TRAFFIC COMMISSION Tuesday, November 12, 2013 URBANA TRAFFIC COMMISSION Tuesday, November 12, 2013 MEMBERS PRESENT: Michael Madigan, City Council Member, Ward 6, Chair Joe Smith, Senior Civil Engineer Pat Connolly, Police Chief MEMBERS ABSENT: None

More information

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK This is Meeting 2 Unfortunately, some residents in Bellevue and Virginia Park received the wrong information for this public open house (Meeting

More information

TOWN OF PAYSON TRAFFIC CALMING MANUAL

TOWN OF PAYSON TRAFFIC CALMING MANUAL TOWN OF PAYSON TRAFFIC CALMING MANUAL APPROVED BY THE PAYSON TOWN COUNCIL SEPTEMBER 6, 2007 TOWN OF PAYSON TRAFFIC CALMING POLICY 1.0 Introduction Traffic Calming involves retrofitting physical devices

More information

FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St)

FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St) FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St) New benches Plant evergreen trees Widen existing sidewalk from 1.5m to 1.8m Marked crosswalk 1.8m wide sidewalk Add pedestrian oriented lights

More information

Paoli Road Improvement Feasibility Study

Paoli Road Improvement Feasibility Study Paoli Road Improvement Feasibility Study & Public Participation Project March 24, 2015 Prepared for: Tredyffrin Township Prepared by: McMahon Associates, Inc. with Town Planning Partnership, LLC Glackin

More information

NORTH TURNAROUND. Recommended Design: Expand the existing transit terminal

NORTH TURNAROUND. Recommended Design: Expand the existing transit terminal NORTH TURNAROUND Recommended Design: Expand the existing transit terminal Feedback from stakeholders and the public: Make it easy to transfer between local and Rapid Transit service Why is this design

More information

Purple Line Extension Community Meeting

Purple Line Extension Community Meeting Purple Line Extension Community Meeting August 22, 2016 Agenda Introductions Meeting Goals Project Overview and Schedules Proposed Memorandum of Agreement Overview Stay in Touch! Q & A Meeting Goals Provide

More information

City of Wayzata Comprehensive Plan 2030 Transportation Chapter: Appendix A

City of Wayzata Comprehensive Plan 2030 Transportation Chapter: Appendix A A1. Functional Classification Table A-1 illustrates the Metropolitan Council s detailed criteria established for the functional classification of roadways within the Twin Cities Metropolitan Area. Table

More information

Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening

Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening We are here today to present the draft plan for the Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening project

More information

City of Vallejo Traffic Calming Toolbox

City of Vallejo Traffic Calming Toolbox City of Vallejo Traffic Calming Toolbox June 1, 2013 Final Table of Contents Introduction... 1 Non-Physical Devices... 3 High-Visibility Crosswalk... 3 In Pavement Lighted Crosswalk... 4 Rapid Flashing

More information

CITY OF ANN ARBOR TRAFFIC CALMING PROGRAM PROCESS OVERVIEW. Petitioner defines the project area limits and gathers petition signatures.

CITY OF ANN ARBOR TRAFFIC CALMING PROGRAM PROCESS OVERVIEW. Petitioner defines the project area limits and gathers petition signatures. CITY OF ANN ARBOR TRAFFIC CALMING PROGRAM PROCESS OVERVIEW Step 1: Petition Petitioner defines the project area limits and gathers petition signatures. 50% of addresses within the project area must sign

More information

St. Francis Drive through the City of Santa Fe Corridor Study

St. Francis Drive through the City of Santa Fe Corridor Study VII. ENGINEERING AND ENVIRONMENTAL EVALUATION TRAIL CONNECTIVITY In the southern portion of the Corridor there is a lack of a sidewalk, trail or bicycle facility within the right-ofway. However, the City

More information

10.0 CURB EXTENSIONS GUIDELINE

10.0 CURB EXTENSIONS GUIDELINE 10.0 CURB EXTENSIONS GUIDELINE Road Engineering Design Guidelines Version 1.0 March 2017 City of Toronto, Transportation Services City of Toronto Page 0 Background In early 2014, Transportation Services

More information

2017 Temporary traffic control guidelines for pedestrians. v.2

2017 Temporary traffic control guidelines for pedestrians. v.2 2017 Temporary traffic control guidelines for pedestrians v.2 Temporary Traffic Control Guidelines for Pedestrians (2017) The safety and mobility of pedestrians, cyclists and motorists must be considered

More information

Star Ratings for the Strategic Road Network. Richard Leonard - Highways England

Star Ratings for the Strategic Road Network. Richard Leonard - Highways England Star Ratings for the Strategic Road Network Richard Leonard - Highways England Strategic Direction for Road User Safety 2 Delivery Plan Star Rating - Commitments We will ensure that by the end of 2020

More information

PROJECT FACT SHEET May 25, 2018

PROJECT FACT SHEET May 25, 2018 SITE CHALLENGES & PROJECT BACKGROUND In 2014, the City of Aspen identified the Castle Creek Bridge and Hallam Street corridor as a deficient link in Aspen s bicycle and pedestrian network. Safe and efficient

More information

complete streets design and construction standards public primer City of Edmonton

complete streets design and construction standards public primer City of Edmonton complete streets design and construction standards public primer City of Edmonton introduction Complete Streets are streets for everyone: people who walk, wheel, bike, take transit, or drive. They are

More information

RiNo Railroad Crossing Connectivity Analysis. Stakeholder Workshop June 29, 2017

RiNo Railroad Crossing Connectivity Analysis. Stakeholder Workshop June 29, 2017 RiNo Railroad Crossing Connectivity Analysis Stakeholder Workshop June 29, 2017 Ideas and Considerations Presented at Stakeholder Workshop Primary Focus: 38 th Street (between Walnut & Wynkoop) 1 Basic

More information

CONTENTS EXECUTIVE SUMMARY 1

CONTENTS EXECUTIVE SUMMARY 1 CONTENTS CHAPTER PAGE EXECUTIVE SUMMARY 1 1 ISSUES AND PURPOSE OF THE ANALYSIS 2 1.1 Background 2 1.2 Analysis Area 2 1.3 Issues and Observations 3 1.4 Project and Public Meetings 3 2 LIST OF PREFERRED

More information

6.4 RECOMMENDED IMPROVEMENTS

6.4 RECOMMENDED IMPROVEMENTS 6.4 RECOMMENDED IMPROVEMENTS 6.4.1 Williston Road Recommendations While all alternatives would be an improvement over existing conditions, Alternative 3B is recommended over the others because it provides

More information

Warsaw, Missouri Van Buren Street Preliminary Engineering Report

Warsaw, Missouri Van Buren Street Preliminary Engineering Report Warsaw, Missouri Van Buren Street Preliminary Engineering Report Prepared for: The City of Warsaw 181 Harrison Street Warsaw, MO 65355 (660) 438-5522 Prepared by Charles LePage, P.E. CFS Engineers 119

More information

INTER- AND INTRA-CONNECTIVITY INTERPRETIVE GUIDELINES

INTER- AND INTRA-CONNECTIVITY INTERPRETIVE GUIDELINES INTER- AND INTRA-CONNECTIVITY INTERPRETIVE GUIDELINES Prepared by: The City of Sanibel Planning Department March 6, 2014 Introduction One of the City Councils goals adopted for the fiscal year of 2013-2014

More information

Steps to Conducting a Complete Streets Assessment

Steps to Conducting a Complete Streets Assessment Steps to Conducting a Complete Streets Assessment Familiarize yourself with Complete Streets Read through the Complete Streets Assessment Guidelines. This will give you an idea of what Complete Streets

More information

Welcome to the Public Meeting. Red Hill Business Park South Transportation Master Plan Addendum. December 4, :00 p.m. to 8:00 p.m.

Welcome to the Public Meeting. Red Hill Business Park South Transportation Master Plan Addendum. December 4, :00 p.m. to 8:00 p.m. Welcome Welcome to the Transportation Master Plan Addendum December 4, 2012 6:00 p.m. to 8:00 p.m. Please sign-in Background PIC#1 Public Information Centre #1 (PIC#1) was held on June 25, 2012. Feedback

More information

83 AVENUE PRE-CONSTRUCTION MEETING

83 AVENUE PRE-CONSTRUCTION MEETING 83 AVENUE PRE-CONSTRUCTION MEETING April 6, 2017 5-8PM Please visit displays for project information Talk to staff, ask questions, visit website at: www.edmonton.ca/bike83avenue Pre-Construction Meeting

More information

Shared Use Path Design

Shared Use Path Design 12B-2 Design Manual Chapter 12 - Sidewalks and Bicycle Facilities 12B - Bicycle Facilities Shared Use Path Design A. Accessible Shared Use Path Design 1. General: Applicable portions from the following

More information

Fifth & Kirkham Traffic-Calming Project. 5 th Avenue and Kirkham Street Presented at the UCSF Quarterly Parnassus Community Meeting May 3, 2018

Fifth & Kirkham Traffic-Calming Project. 5 th Avenue and Kirkham Street Presented at the UCSF Quarterly Parnassus Community Meeting May 3, 2018 Fifth & Kirkham Traffic-Calming Project 5 th Avenue and Kirkham Street Presented at the UCSF Quarterly Parnassus Community Meeting May 3, 2018 1 Agenda Welcome and introductions Project history, goals,

More information

CLOSED. The draft concept design has been broken down into 5 categories for the purpose of this survey:

CLOSED. The draft concept design has been broken down into 5 categories for the purpose of this survey: Old Strathcona s neighbourhood renewal process is now at the draft concept design phase. Over the last several months, the city has been gathering local knowledge and resident input that has been used

More information

STEERING COMMITTEE MEETING June 17, Streetscape Overview Burlington Comprehensive Master Plan

STEERING COMMITTEE MEETING June 17, Streetscape Overview Burlington Comprehensive Master Plan STEERING COMMITTEE MEETING June 17, 2015 Streetscape Overview Burlington Comprehensive Master Plan 1 Introduction Slide This slide show was presented to the Burlington Steering Committee on June 17, 2015

More information

This Chapter sets forth the minimum design, technical criteria and specifications to be used in the preparation of all roadway plans.

This Chapter sets forth the minimum design, technical criteria and specifications to be used in the preparation of all roadway plans. 4.1 GENERAL This Chapter sets forth the minimum design, technical criteria and specifications to be used in the preparation of all roadway plans. These Roadway Standards are for new construction and modification

More information

City of Ann Arbor Pedestrian Safety & Access Task Force

City of Ann Arbor Pedestrian Safety & Access Task Force City of Ann Arbor Pedestrian Safety & Access Task Force (PSATF) Community Wide Meeting Wednesday, July 8th 6:30 to 8:30 PM Multi purpose Room, Downtown Library www.a2gov.org/pedsafety The Greenway Collaborative,

More information

September 20, 2016 L Taraval Rapid Project SFMTA Board of Directors Meeting

September 20, 2016 L Taraval Rapid Project SFMTA Board of Directors Meeting September 20, 2016 L Taraval Rapid Project SFMTA Board of Directors Meeting WHY TARAVAL STREET L TARAVAL PROJECT GOALS 1. Improve state of good repair of our transit system Track and overhead replacement

More information

Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER

Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets City Commission adopted a Complete Streets policy in 2012 Complete Streets are road networks that are designed for all users:

More information

Climate Change Action Plan: Transportation Sector Discussion Paper: Cycling

Climate Change Action Plan: Transportation Sector Discussion Paper: Cycling Climate Change Action Plan: Transportation Sector Discussion Paper: Cycling ontario.ca/climatechange Contents 1. Minister of Transportation s message... 3 2. Introduction... 5 3. Sector Overview and Support

More information

Pre-Construction Meeting

Pre-Construction Meeting Pre-Construction Meeting Wednesday, March 21 Drop-in from 5 9pm Please visit displays for project information, talk to staff, and ask questions! Edmonton.ca/SouthsideBikeRoutes Objectives & Project Scope

More information

The Safe System Approach

The Safe System Approach There are very few areas of public discussion and sentiment which generate as much consensus as road safety. Everyone wants safer roads for all users, and road safety is a key priority for governments,

More information

Accommodating Pedestrians in the Work Zone

Accommodating Pedestrians in the Work Zone Accommodating Pedestrians in the Work Zone Guidance for Section C Plan Preparers Some impacts cannot be avoided and those impacts apply to residents, businesses, motorists, and pedestrians alike. However,

More information

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns Public Informational Meeting University Avenue (Allen Boulevard Segoe Road) March 23, 2011 City of Madison City of Middleton Village of Shorewood Hills Dane County Existing Roadway Conditions Poor pavement

More information

City of Elizabeth City Neighborhood Traffic Calming Policy and Guidelines

City of Elizabeth City Neighborhood Traffic Calming Policy and Guidelines City of Elizabeth City Neighborhood Traffic Calming Policy and Guidelines I. Purpose: The City of Elizabeth City is committed to ensure the overall safety and livability of residential neighborhoods. One

More information

Town of Mooresville, North Carolina Neighborhood Traffic Calming and Control Device Policy

Town of Mooresville, North Carolina Neighborhood Traffic Calming and Control Device Policy Town of Mooresville, North Carolina Neighborhood Traffic Calming and Control Device Policy Adopted January 6, 2014 Town of Mooresville Development Services Department TOWN OF MOORESVILLE NEIGHBORHOOD TRAFFIC

More information

Edenbrook Hill Drive Traffic Calming Study

Edenbrook Hill Drive Traffic Calming Study WELCOME Public Information Centre Edenbrook Hill Drive Traffic Calming Study Fletchers Meadow Secondary School Wednesday January 20, 2016 6:30 p.m.to 9:00 p.m. Please sign in Neighbourhood Traffic Calming

More information

Scarlett Road Bridge & Road Improvements Lambton Park Community School - Gymnasium Tuesday November 28 th, 2017

Scarlett Road Bridge & Road Improvements Lambton Park Community School - Gymnasium Tuesday November 28 th, 2017 Scarlett Road Bridge & Road Improvements Lambton Park Community School - Gymnasium Tuesday November 28 th, 2017 PROJECT LOCATION 2 SCARLETT ROAD BRIDGE Constructed in 1912, the bridge carries 4 active

More information

Austroads National Risk Assessment Model (ANRAM) Chris Jurewicz, ARRB

Austroads National Risk Assessment Model (ANRAM) Chris Jurewicz, ARRB Austroads National Risk Assessment Model (ANRAM) Chris Jurewicz, ARRB Overview Context What is ANRAM? How it is used? Severe crash risk estimation ANRAM Toolkit Next steps 2 Context Diminishing blackspots

More information