1 Town of Ashland Downtown Planning Initiative 2 nd Community Workshop Presented by: March 29, 2018
2 Agenda Tonight Review project & goals Recap 1st workshop (September 18, 2017) Present design alternatives with discussion Next steps
3 Project Boundaries Phase 1 Pleasant St Corner Spot Town Hall Library LEGEND Roadway Residential Retail Commercial Restaurant Public Building Police & Fire Post Office
4 Project Goals Make downtown an attractive and welcoming place for residents and visitors Make downtown more inviting for business development Make downtown safe and accessible to all users (complete streets) Improve traffic flow Enhance historic character of corridor Explore relocating existing overhead utilities underground Identify and secure construction funding
5 What we learned from the 1 st workshop Attraction to downtown Corner Spot Farmers Market Shops/Restaurants Small Town Feel Greatest challenge with project Traffic RR Crossing Parking Lighting Pedestrian Accommodation Undergrounding Would like to see utilities buried Traffic There is a congestion problem along Main Street during rush hour Parking Perception there is not enough parking downtown What would you like to see happen downtown More Businesses (destination and commercial) Better Parking Management Safer and More Attractive Pedestrian Improvements Better Lighting Wider Sidewalks Bicycle Accommodation
6 Workshop Poll Results Sidewalk Character
7 Workshop Poll Results Crosswalk Treatments
8 Workshop Poll Results Outdoor Seating
9 Workshop Poll Results Wayfinding
10 Workshop Poll Results Street Plantings and Trees
11 Workshop Poll Results Public Art
12 Workshop Poll Results Site Furnishings
13 Workshop Poll Results Lighting
14 Alternative Development Developed two options Bike Lane & No Bike Lane Considerations Pedestrian Safety Level of Service (i.e. Traffic Flow) On-Street Parking Bike Lane Pedestrian/ADA Compliance Streetscape Cost
15 Main Street Alternative A (Water Street to Pleasant Street) 10.5 Sidewalk Main New Traffic Signals 21 Main 10.5 Sidewalk 37 Main The Corner Spot 4 8
16 Main Street Alternative A (Pleasant Street to Front Street) Main 98 Main Federated Church 8 Sidewalk 128 Main Santander Bank New Traffic Signals Glam Salon Nick s Pizza New Curb Extension 9 Sidewalk Ashland House Police Department Town Hall Cumulative Cumulative
17 Main Street Alternative A (Front Street to Homer Avenue) Santander Bank Town Land Municipal Lot 8-10 Sidewalk Pizza Mine New Traffic Signals New Traffic Signals 7-11 Sidewalk Stones Public House Main St. Wine & Spirits U.S. Post Office Cumulative Cumulative
18 Main Street Alternative A (View Toward Water Street)
19 Main Street Alternative B (Water Street to Pleasant Street) No Change in Sidewalk Main New Traffic Signals 21 Main 37 Main No Change in Sidewalk The Corner Spot 4 7
20 Main Street Alternative B (Pleasant Street to Front Street) Main 98 Main 8.5 Sidewalk (+2 ) Federated Church 128 Main Santander Bank New Traffic Signals Glam Salon Nick s Pizza Town Hall Ashland House Police Department Cumulative Cumulative
21 Main Street Alternative B (Front Street to Homer Avenue) Santander Bank Municipal Lot Town Land No Change in Sidewalk Pizza Mine New Traffic Signals New Traffic Signals Stones Public House No Change in Sidewalk Main St. Wine & Spirits U.S. Post Office Cumulative Cumulative
22 Main Street Alternative B (View Toward Water Street)
23 Main Street Alternative C (Pleasant Street to Front Street) Main 98 Main No Change in Sidewalk Federated Church 128 Main Santander Bank New Traffic Signals Glam Salon Nick s Pizza Town Hall Ashland House New Curb Extension Police Department 14 20
24 Main Street Alternative C (View Toward Water Street)
25 Front Street Alternative A (Main Street to the Erica s Ristorante) Sunnyside Cafe Santander Bank 14.5 Sidewalk Agostinelli & Teller Insurance Anthony s Barber Stylist Ashland Public Library Erica s Ristorante New Traffic Signals Town Land Needham Bank 8 Sidewalk Municipal Lot 6 6
26 Front Street Alternative A (Erica s Ristorante to Project Limit) 8 Sidewalk Ashland Lumber Municipal Lot New Connection to Municipal Lot Farmers Market Cumulative Cumulative
27 Front Street Alternative A (View From Main Street)
28 Front Street Alternative B (Main Street to the Erica s Ristorante) Sunnyside Cafe Santander Bank 9 Sidewalk Agostinelli & Teller Insurance Anthony s Barber Stylist Ashland Public Library Erica s Ristorante New Traffic Signals Town Land Needham Bank 8.5 Sidewalk No Change in Sidewalk Municipal Lot 6 7
29 Front Street Alternative B (Erica s Ristorante to Project Limit) No Change in Sidewalk Ashland Lumber Municipal Lot New Connection to Municipal Lot Farmers Market Cumulative Cumulative
30 Front Street Alternative B (View from Main Street)
31 Next Steps Review comments/suggestions from workshop Complete traffic and parking analysis Provide recommendations related to undergrounding Develop preliminary design Present design to community Complete preliminary design
32 QUESTIONS?
A CHANGING CITY. of Edmonton, it is essential that it reflects the long-term vision of the City.
A CHANGING CITY By the year 2040, Edmonton will be home to more than 1 million people. To accommodate growth and support a healthy and compact city, we need a new approach to development/redevelopment
More informationTraffic Improvements for the Transit Oriented Development District (TODD) Meriden Public Library March 11, 2014
Traffic Improvements for the Transit Oriented Development District (TODD) Meriden Public Library March 11, 2014 Project Overview Coordinate roadway improvements with other major projects HUB Flood Control
More information2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE
About the Project 2014/2015 BIKE ROUTE PLAN The City of Edmonton is planning a major bike route on the south side of Edmonton. This bike route is one part of a plan to provide citizens with transportation
More informationTHE ALAMEDA CONCEPT DESIGN COMMUNITY MEETING 3. A Plan for The Beautiful Way JANUARY 28, 2010
CONCEPT DESIGN COMMUNITY MEETING 3 JANUARY 28, 2010 AGENDA INTRODUCTION COMMUNITY INPUT ROADWAY STUDIES STREETSCAPE DESIGN STATIONS DISCUSSION SUMMARY AND DISCUSSION NEXT STEPS CLOSE INTRODUCTION SCHEDULE
More informationS T A T I O N A R E A P L A N
The Circulation and Access Plan describes vehicle, pedestrian, and transit improvements recommended within the Concept Plan. In order to create and sustain a vibrant business district that provides pedestrian-friendly
More informationPublic Workshop #2. September 14, 2016
Public Workshop #2 September 14, 2016 Agenda Welcome Project Overview Where We Have Been Alternatives for State Street Land Use Street Design Next Steps 2 Project Overview Create a Vibrant State Street
More informationDOWNTOWN TENINO. Goal: Get more People in Downtown. A Pamphlet of Concepts for
A Pamphlet of Concepts for DOWNTOWN TENINO The Tenino Planning Commission believes that the highest potential for economic development and business development in the City of Tenino (in the short-term)
More informationCOWETA HIGH SCHOOL AND EAST HIGHWAY 51
COWETA HIGH SCHOOL AND EAST HIGHWAY 51 Lack of sidewalks along Ben Lumpkin Rd. Lack of crosswalks and ramps at intersection. Hwy 51 is wide to cross as a pedestrian. No ADA compliance or connection to
More informationEl Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018
El Camino Real Specific Plan TAC/CAC Meeting #2 Aug 1, 2018 Land Use Alternatives Goals and Tradeoffs Parks & open space Housing Retail & services Civic spaces Parking Community gathering spaces 3 Alternatives
More informationCommunity Meeting February 27, 2007 Dorchester Avenue Transportation & Streetscape Improvements Action Plan February 27, 2007
Community Meeting Tonight s Agenda 6:00 Introductions South Boston/Dot Ave Improvement Study Background 6:15 Consultant Introductions Review of Scope and Schedule Review of Proposed Corridor Wide Guidelines
More informationNEWMARKET UPHAM S CORNER
SOUTH STATION Planning Initiative NEWMARKET UPHAM S CORNER COLUMBIA ROAD (P) FOUR CORNERS/GENEVA Working Advisory Group (WAG) Meeting #5 TALBOT AVENUE MORTON STREET BLUE HILL AVE/CUMMINS HWY (P) RIVER
More informationFOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St)
FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St) New benches Plant evergreen trees Widen existing sidewalk from 1.5m to 1.8m Marked crosswalk 1.8m wide sidewalk Add pedestrian oriented lights
More informationSTEERING COMMITTEE MEETING June 17, Streetscape Overview Burlington Comprehensive Master Plan
STEERING COMMITTEE MEETING June 17, 2015 Streetscape Overview Burlington Comprehensive Master Plan 1 Introduction Slide This slide show was presented to the Burlington Steering Committee on June 17, 2015
More information2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE
About the Project The City of Edmonton is planning a major bike route on the southside of Edmonton. The Strathcona Bike Route will connect the communities of Strathcona, Garneau and the University area,
More informationAbout the study. North Milwaukee Ave. Key goals of this study are to: Achieve Vision Zero* by. Harmonize the space and improve walkability
About the study Key goals of this study are to: North Milwaukee Avenue is a local and regional street for multiple modes of transportation. It is officially zoned and functions as a pedestrian street southeast
More informationReconnecting Communities ACTION PLAN FOR LOGAN CIRCLE
Reconnecting Communities ACTION PLAN FOR LOGAN CIRCLE Project for Public Spaces, Inc. May 2003 Reconnecting Communities ACTION PLAN FOR LOGAN CIRCLE VINE STREET EXPRESSWAY, PHILADELPHIA, PA Prepared by:
More informationMainstreet Master Plan Land Use
Mainstreet Master Plan 04 Land Use Top Recommendations Active Uses: Promote active ground-floor uses such as retail, restaurants, galleries and personal services with interactive storefronts for Mainstreet
More informationTonight is for you. Learn everything you can. Share all your ideas.
Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.
More informationColchester/Riverside/Barrett/ Mill Intersection Study. PAC Meeting #3 September 22, 2016
Colchester/Riverside/Barrett/ Mill Intersection Study PAC Meeting #3 September 22, 2016 Tonight s Agenda Review Project Purpose and Need Describe short term and long improvements and changes since public
More informationDerby Street. Project Updates. Salem, Massachusetts
Derby Street Project Updates Salem, Massachusetts September 13, 2017 Project Limits Derby Street Project Objectives 1. Improve complete streets elements on Derby Street 2. Improve sidewalks on finger streets
More informationSTONY PLAIN ROAD STREETSCAPE
Jasper Place Revitalization Strategy: Vision The people involved in the Jasper Place Revitalization Strategy envision: Goal 1: Feeling safe in our community Create a community where feeling safe is common--where
More informationcomplete streets design and construction standards public primer City of Edmonton
complete streets design and construction standards public primer City of Edmonton introduction Complete Streets are streets for everyone: people who walk, wheel, bike, take transit, or drive. They are
More information6.4 RECOMMENDED IMPROVEMENTS
6.4 RECOMMENDED IMPROVEMENTS 6.4.1 Williston Road Recommendations While all alternatives would be an improvement over existing conditions, Alternative 3B is recommended over the others because it provides
More information122 Avenue: 107 Street to Fort Road
: 107 Street to Fort Road November 24, 2015 4:30 8:00 p.m. Meeting Purpose Summarize project work completed to date Share results of public input from Phase 1 Share the draft concept plan and proposed
More informationVision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods
N D. Focus Area II Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods Transit Road Focus Area II is located in the Hamlet
More informationThe Wiggle Route in Context
The Wiggle Route in Context In a city of hills, the Wiggle is an important route because it winds its way along the flattest streets from Market to the Panhandle, bringing residents to local parks and
More informationPerryville Transit Oriented Development & Greenway Plan
A Partnership of the Town of Perryville and WILMAPCO Perryville Transit Oriented Development & Greenway Plan Why plan for TOD and Greenways? Identify strategies to enhance community character in Perryville
More information5 CIRCULATION AND STREET DESIGN
5 CIRCULATION AND STREET DESIGN This chapter describes circulation and streetscape improvements proposed for the Northwest Chico Specific Plan Area. It includes detailed design specifications for existing
More informationDowntown Davidson Pedestrian and Bicycle Safety Plan
Downtown Davidson Pedestrian and Bicycle Safety Plan Enhancement Funds Application Submitted by the Town of Davidson June 2002 Downtown Davidson Pedestrian and Bicycle Safety Plan Project Description At
More informationA Plan for The Beautiful Way NOVEMBER 16, 2009
COMMUNITY VISION WORKSHOP NOVEMBER 16, 2009 AGENDA INTRODUCTION COMMUNITY INPUT REVIEW AND SURVEY RESULTS VISIONING IMAGERY SMALL GROUP VISIONING SESSION NEXT STEPS CLOSE SCHEDULE COMMUNITY SURVEY 198
More informationPlant City Walk-Bike Plan
Plant City Walk-Bike Plan Plant City Commute Mode Share 2.2% 1.4% 2.9% Drove alone 10.2% Carpooled Public transportation (0.1%) Walked Used a Bike (0.4%) 82.9% Taxicab, motorcycle, or other means Worked
More informationFONTAINE AVENUE STUDY Final Report
FONTAINE AVENUE STUDY Final Report March 28, 2005 FONTAINE AVENUE STUDY City of Charlottesville March 28, 2005 Renaissance Planning Group Kenneth Schwartz, FAIA, AICP Director of Design Leigh Wilkerson,
More informationChapter 5 Future Transportation
Chapter 5 Future Transportation The Future Land Use Plan identifies the desired land use designations. The land uses desired for Crozet depend, in large part, on the success of the transportation system,
More informationUDC Street Cross Sections
UDC Street Cross Sections Local Street - Downtown Local Street Mountable Curb Local Street Vertical Curb Alley Major Arterial Minor Arterial Residential Lane Residential Collector Residential Collector
More informationFunctional, Preliminary Design and Detailed Design
Functional, Preliminary Design and Detailed Design Main Street (Echo Drive to the Rideau River), Lees Avenue (Main Street to Chestnut Street), and Rideau River Drive (Main Street to 130m south of Main
More informationPEDESTRIAN CIRCULATION & STREETSCAPE DESIGN
CHAPTER 4 Chapter 4 Pedestrian Circulation & Trails PEDESTRIAN CIRCULATION & STREETSCAPE DESIGN In recent years, the City has constructed new sidewalks and enhanced existing ones in the downtown with brick
More informationObey Creek PEDESTRIAN CIRCULATION EAST WEST PARTNERS PEDESTRIAN CIRCULATION CREEK SIDE LANE SLIP STREET SCOTT MURRAY MAIN STREETS EAST/WEST
THE VILLAGE AT PEDESTRIAN CIRCULATION MAIN STREETS NORTH/SOUTH MAIN STREETS EAST/WEST SLIP STREET CREEK SIDE LANE PEDESTRIAN CIRCULATION DESCRIPTION: Circulation through the downtown of is organized by
More informationPROJECT OBJECTIVES. Improve vehicle capacity for the intersection. Improve pedestrian and bicycle access
COMMUNITY MEETING Project Update March 15, 2010 Purcellville, Virginia OVERVIEW Project need / objectives Project recap Design elements Proposed improvements Summary of project benefits / next steps PROJECT
More informationWhy invest in the 1 Street S.W. Corridor?
Why invest in the 1 Street S.W. Corridor? This project is an investment in the Beltline Community and Calgary s economy. It is anticipated that The City s investment along this corridor will help with
More informationCONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach
CONNECTIVITY PLAN Adopted December 5, 2017 City of Virginia Beach CONTENTS 1.0 Background & Purpose... 2 2.0 Existing Inventory & Analysis... 3 ViBe District Existing Walking Conditions... 4 3.0 ViBe District
More informationMemo. Ocean Avenue Corridor Design Project Public Workshop #2 Summary
Ocean Avenue Corridor Design Project Public Workshop #2 Summary The second public workshop for the Ocean Avenue Corridor Design Project was held on Wednesday, May 14, 2014 from, 6 to 8 pm at Lick Wilmerding
More informationEnhancing Downtown
Enhancing Downtown 2014-2015 Process Masterplan reviewed TIF scope, fund availability, and timing Conceptual cost estimate stage things may change with full engineering Sequencing Coordination with businesses
More informationSTREETSCAPE CONCEPT PLAN
03 STREETSCAPE CONCEPT PLAN Zone 1 This zone includes the gateway into both the downtown and the Village at Harlem. The gateway features are shown closer to the Harlem intersection to make them more prominent.
More informationPEDESTRIAN ACTION PLAN
ATTACHMENT 2 CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN This page intentionally left blank EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY Setting the Stage
More informationALBERTA AVENUE WHAT WE HEARD REPORT BUILDING GREAT NEIGHBOURHOODS
ALBERTA AVENUE WHAT WE HEARD REPORT BUILDING GREAT NEIGHBOURHOODS FEBRUARY 2019 EXECUTIVE SUMMARY Starting in 2019, Alberta Avenue will see the replacement and enhancement of its aging collector and local
More informationComments The Plan for Port Whitby
Comments The Plan for Port Whitby April 24th, 2013 Community Meeting #2 Summary Report Prepared by GLPi April 29th, 2013 1 Introduction The purpose of the Port Whitby Secondary Plan Update, Community Improvement
More informationSouthview Blvd & 3 rd Avenue Improvement Project. Public Open House December 4, to 7pm
Southview Blvd & 3 rd Avenue Improvement Project Public Open House December 4, 2014 5 to 7pm Southview Blvd & 3 rd Avenue Public Information Meeting Agenda Presentation 5:30 to 6:15 pm Purpose of Project
More informationElm Street Business District: Streetscape and Signage Plan
Winnetka Preliminary Streetscape & Signage Village Council Presentation 1 Elm Street Business District: Streetscape and Signage Plan VILLAGE OF WINNETKA DOWNTOWN MASTER PLAN VILLAGE COUNCIL PRESENTATION
More informationTRANSPORTATION & MOBILITY
TRANSPORTATION & MOBILITY ROADWAY SYSTEM There are approximately 40 miles of roadways in Manitou Springs. For planning purposes, roadways are typically assigned a functional classification which defines
More informationFulton Market Streetscape
Fulton Market Streetscape Ogden Avenue to Halsted Street Public Meeting Recommended Improvements December 10th, 2014 Meeting Purpose and Goals Present Existing Conditions Community Input and Charrette
More informationCOMPLETE STREETS PLANNER S PORTFOLIO
COMPLETE STREETS PLANNER S PORTFOLIO ISSUE 3 APRIL 2016 PLANNER S PORTFOLIO COMPLETE STREETS 1 2 6 10 14 OVERVIEW MATURE NEIGHBORHOODS GROWING SUBURBS CENTRAL PLACES ACTIVITY CORRIDORS Planner s Portfolio
More informationCity of Birmingham Draft Multi-modal Transportation Plan
City of Birmingham Draft Multi-modal Transportation Plan City Commission Public Hearing Monday, November 25, 2013 7:30 pm Norman Cox, PLA, ASLA The Greenway Collaborative, Inc. Ann Arbor, Michigan The
More informationMAKE YOUR PLACE IN CHANNELSIDE
MAKE YOUR PLACE IN CHANNELSIDE INTRODUCTION PROJECT LIMITS Channelside Drive from Cumberland Ave to Kennedy Boulevard EXISTING CONDITIONS EXISTING CONDITIONS CHANNELSIDE DRIVE FROM E. CUMBERLAND AVENUE
More informationFigure 4-10: Pedestrian Improvements Types of Potential Station Area Improvements - Place-Making Improvements
INCORPORATE FEATURE PAVIN IN CROSSWALK AND INTERSECTION FIELDS Identifies high-priority pedestrian areas and create a station identity through colorful and interesting patterns ADD CURB EXTENSIONS Extending
More informationMiami Health District
Miami Health District Streetscapes, Gateways, and Signage Basis of Design Report Study Miami Partnership Meeting July 21, 2008 Gannett Fleming EDAW The Corradino Group Sponsored by the Miami Partnership:
More informationsummary of issues and opportunities
1 summary of issues and opportunities EXECUTIVE SUMMARY CHAPTER 2: HISTORY - 3: LAND USE This first chapter is an overview of lessons learned from analysis of the existing conditions on El Camino as well
More informationMake Lincoln Highway an economically vibrant corridor that is safe, efficient, and beautiful for local residents and visitors.
Lincoln Highway Streetscape Plan Stakeholder Workshop #2 Handout Contents Introduction and Project Vision Planning Principles Specific Recommendations including a Proposed Typical Roadway Section Renderings
More informationNJDOT Complete Streets Checklist
Background The New Jersey Department of Transportation s Complete Streets Policy promotes a comprehensive, integrated, connected multi-modal network by providing connections to bicycling and walking trip
More informationOmaha s Complete Streets Policy
Omaha s Complete Streets Policy (Adopted August 2015) VISION To create great places and enhance our quality of life, the City of Omaha will provide safe, accessible streets for all users. Complete Streets
More informationChapter 4: Funding and Implementation
Chapter 4: Funding and Implementation 83 84 Cost Estimating Cost estimating is an iterative process. When a project is in the conceptual stage, preliminary cost estimates are also provided conceptually,
More informationUNIVERSITY AVENUE CORRIDOR REDESIGN. January 8, 2017 PUBLIC OPEN HOUSE
January 8, 2017 PUBLIC OPEN HOUSE COLLABORATIVE COMMUNITY-BASED DESIGN IS THE FOUNDATION TO A SUCCESSFUL PROJECT AGENDA FOR TONIGHT 1 INTRODUCTIONS 2 WHY ARE WE HERE PROJECT NEED 3 SCHEDULE & GOALS 4 OPEN
More information14 TH STREET TRANSPORTATION & STREETSCAPE DESIGN STUDY PLAN B PLAN B TRANSPORTATION & STREETSCAPE RECOMMENDATIONS
14 TH STREET TRANSPORTATION & STREETSCAPE DESIGN STUDY PLAN B PLAN B TRANSPORTATION & STREETSCAPE RECOMMENDATIONS 141 Symbols Recommendations - Southern End of 14th Street Study Area Streetscape Each icon
More informationCRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN
CRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN Preferred Plan Community Presentation September 27, 2017 City of El Paso de Robles in partnership with: Local Government Commission, W-Trans,
More informationWELCOME. to the meeting for the. Westside Avenue Action Plan Gateway to Revitalization
WELCOME to the meeting for the Columbia Road - Before and After Ridge Road - Before and After Before and After WAAP Bridge Sections Fountain Creek Before Retaining Wall for Roadway 30' Existing Fountain
More informationWELCOME. Purpose of the Open House. Update you on the project. Present a draft recommended plan. Receive your input
WELCOME Purpose of the Open House The Town of Smiths Falls has initiated the Beckwith Street Redevelopment Plan that includes the preparation of a streetscape functional design for the renewal of Beckwith
More informationExecutive Summary Route 30 Corridor Master Plan
Route Corridor Master Plan Project Overview The Route Corridor Master Plan is a coordinated multimodal transportation and land use plan for the entire stretch of Route through East Whiteland Township,
More informationDOWNTOWN MIAMI PEDESTRIAN PRIORITY ZONE
DOWNTOWN MIAMI PEDESTRIAN PRIORITY ZONE AUGUST 6, 2013 DOWNTOWN MIAMI BY THE NUMBERS more than 200,000 people live, work, and play here every day is home to more than 1,000 events each year hosts more
More informationCity of Wilsonville 5 th Street to Kinsman Road Extension Project
City of Wilsonville 5 th Street to Kinsman Road Walking Tour & Neighborhood Workshop Summary Report Public Outreach Overview On July 18 th, 2017, the City of Wilsonville hosted a neighborhood walking tour
More informationMASONIC AVENUE STREET DESIGN STUDY Community Workshop 2. Masonic Ave Street Design Study Community Workshop 2 August 10, 2010
Masonic Ave Street Design Study Community Workshop 2 August 10, 2010 Introduction MASONIC AVENUE STREET DESIGN STUDY Community Workshop 2 SF Municipal Transportation Agency Javad Mirabdal, Project Manager
More informationCity of Davis East Covell Corridor Plan
Community Open House #2 January 22, 2014 6:00 8:00 p.m. Veterans Memorial Center, Club Room City of Davis Introduction The (ECCP) is a taking a comprehensive look at the existing transportation systems
More informationSaskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening
Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening We are here today to present the draft plan for the Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening project
More informationS.R. 3009, Section A20 South Park & Logan Road Intersection Improvement Project
Open House Public Meeting S.R. 3009, Section A20 South Park & Logan Road Intersection Improvement Project Municipality of Bethel Park, Allegheny County Bethel Park Municipal Building 5001 West Library
More informationTable #6 VISION CHARACTERISTICS
Table #6 VISION White Flint is a place to live, work, play, shop, and walk with sufficient density to encourage quality redevelopment. Vibrant streets and consistent streetscapes are important. CHARACTERISTICS
More informationComplete Streets Successes, Opportunities, and Challenges
Complete Streets Successes, Opportunities, and Challenges Juliet Walker, Transportation Planner, City of Portsmouth Rob Houseman, Director of Planning and Development, Town of Wolfeboro Chris Parker, Director
More informationComplete Streets for Niagara A working method to visualize the creation of a complete street June 20th, 2013
Complete Streets for Niagara A working method to visualize the creation of a complete street June 20th, 2013 C O N T E N T S Introduction and background of the report What is a complete street? What can
More informationLawrence Avenue Streetscape Concepts August 30, 2011
Lawrence Avenue Streetscape Concepts August 30, 2011 Neighborhood Context Phase II: River to Western Ave. Phase I: Western Ave. to Clark St. Key Map Lawrence Ave. Existing Streetscape Conditions East of
More information6.0 PEDESTRIAN AND BICYCLE FACILITIES 6.1 INTRODUCTION 6.2 BICYCLE DEMAND AND SUITABILITY Bicycle Demand
6.0 PEDESTRIAN AND BICYCLE FACILITIES 6.1 INTRODUCTION Bicycle and pedestrian travel along and in the vicinity of the corridor is part of the vision of Somerset and Hunterdon counties and the integrated
More informationCLOSED. Highlights of the Final Concept Design:
The final Concept Design is the result of many months of listening, learning, creating, balancing, and understanding different needs and viewpoints, as well as incorporating technical requirements and
More information7/23/2017 VIA . Michael Hanebutt City of Sacramento Community Development Department 300 Richards Boulevard, 3 rd Floor Sacramento, CA 95811
7/23/2017 VIA EMAIL Michael Hanebutt City of Sacramento Community Development Department 300 Richards Boulevard, 3 rd Floor Sacramento, CA 95811 RE: 65 th Street Apartments (DR17-220) Dear Mr. Hanebutt:
More informationPhasing and Cost Estimate of Downtown Oxford Master Plan Prepared By: Phasing and Cost Estimate of Downtown Oxford Master Plan Purpose of the Study The primary objective of this study is to identify priority
More informationSouthbend to Prima Vista. October 30, Floresta Corridor Master Plan
Application of a Complete Street initiative and how it might function operationally 8 8 Southbend to Prima Vista October 30, 2017 Presentation Agenda 2 Perspective and History Traffic projections, Levels
More informationCity of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE
Welcome Welcome to the third community meeting for the Issaquah-Fall City Road Improvements Project. AGENDA 6:00 p.m. Welcome and sign-in 6:10 p.m. Presentation 6:50 p.m. Open house Learn about the roadway
More informationCommerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue
Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue T A N Y A B R O O K S A S S I S T A N T D I R E C T O R M O B I L I T Y P L A N N I N G M O B I L I T Y A N D S
More informationYork Boulevard Streetscape Master Plan
York Boulevard Streetscape Master Plan October 24 th, 2008 The Story of York Boulevard Streetscape Master Plan Design. Chapter 126 Dealing with Engineers. 2 1 Today s Presentation Topics: 1. Show the streetscape
More informationMARTIN LUTHER KING JR. WAY
OCTOBER 2011 40 Vision and Goals The Martin Luther King, Jr. Way Illustrative Master Plan that follows has been developed through a process of community involvement. It expresses a long term vision for
More informationCommunity Workshop #1 Summary October 2017
Community Workshop #1 Summary October 2017 1 Background Pleasure Point has a unique character and strong community identity. In 2008, the community and the County developed the Pleasure Point Community
More informationIllustrated Principles of Good Planning
Illustrated Principles of Good Planning The Miami 21 Zoning Code incorporates time-tested planning principles into the zoning regulations of our City. These are principles that make for better neighborhoods,
More informationEast Burke Transportation, Safety and Capacity Improvements
East Burke Transportation, Safety and Capacity Improvements The purpose of this project is to increase mobility and improve safety for pedestrians, cyclists, and motor vehicles along VT Route 114 in the
More informationSpeed Limits Study and Proposal. Public Input Session: 8/14/13
Speed Limits Study and Proposal Public Input Session: 8/14/13 Why is Decatur a unique place for this project? First Community Transportation Plan in the nation with a Health Impact Assessment. Strong sense
More informationGRTC Bus Rapid Transit: Semi-Final Design Phase Public Meetings: October 26 & 27, 2015
GRTC Bus Rapid Transit: Semi-Final Design Phase Public Meetings: October 26 & 27, 2015 Welcome! Meeting Agenda Project update presentation Up to 15 minutes for Pulse Q&A about project design. (Please reserve
More informationTypical Cross Section: DOWNTOWN (Observer Highway - 8th Street)
Typical Cross Section: DOWNTOWN (Observer Highway - 8th Street) DRAFT SEPTEMBER 23, 14 1 Washington Street Typical Block Downtown Typical Block: DOWNTOWN (Observer Highway - 8th Street) New crosswalks
More informationMeade Street Bridge Design Alternative Study
Meade Street Bridge Design Alternative Study Preferred Alternative Presentation Stakeholder Meeting #3 June 23, 2011 Presented by: Dan Biggs, RLA Meeting Agenda Purpose: 1. Review Meeting #2 Feedback 2.
More informationBonners Ferry US 95 South Hill Report
Bonners Ferry US 95 South Hill Report December 2014 About New Mobility West Project Partners Sonoran Institute LOR Foundation Boundary Economic Development Council (BEDC) Project for Public Spaces Charlier
More informationLincoln Neighborhood Corridor Plan The LiNC
CITY OF SANTA MONICA Lincoln Neighborhood Corridor Plan The LiNC PLANNING COMMISSION September 2, 2015 COMMUNITY DESIGN + ARCHITECTURE TEAM: Community Design + Architecture Iteris Studio 111 Urban Place
More informationDRAFT. System Components. Greenway Trails. Introduction. Trail Types. Zebulon Greenway Master Plan
5 System Components Wakefield Street Photo Simulation showing Sharrows Introduction The Master Plan identifies various system components that, together, create a comprehensive greenway system. These components
More informationWater Street Promenade. Engineering and Design Services. Public Information Meeting No. 2. Education / Infrastructure / Innovation. Maplewood Avenue &
Public Information Meeting No. 2 Water Street Promenade Maplewood Avenue & Engineering and Design Services Adjacent Areas July 16,2014Portsmouth, NH May 10, 2016 Education / Infrastructure / Innovation
More informationSan Jose Transportation Policy
San Jose Transportation Policy Protected Intersections in LOS Policies to Support Smart Growth Presented by: Manuel Pineda City of San Jose Department of Transportation Bay Area Map San Francisco Oakland
More informationCross Street Corridor Non-Motorized Enhancement Project Project Description
Cross Street Corridor Non-Motorized Enhancement Project Project Description A cooperative study of the Cross Street neighborhood was completed in May 2002 by the City of Ypsilanti, the Depot Town Downtown
More informationPlant City Bicycle and Pedestrian Master Plan. Project Update March 2, 2017
Plant City Bicycle and Pedestrian Master Plan Project Update March 2, 2017 NOV Project Kickoff DEC/ JAN FEB/ MAR Plan Review/Field Work Public Meeting/Coordination Meetings Develop Draft Plan APR/ MAY
More informationItem to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines
Passaic County Complete Streets Checklist - Concept Development Project Name Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines Existing Plans Have
More information