Glebe Parking Garage 170 Second Avenue, Ottawa, Ontario Transportation Impact Study

Size: px
Start display at page:

Download "Glebe Parking Garage 170 Second Avenue, Ottawa, Ontario Transportation Impact Study"

Transcription

1 Glebe Parking Garage 17 Second Avenue, Ottawa, Ontario Transportation Impact Study C i t y o f O t t a w a S e p t e m b e r GENIVAR 2611 Queensview Drive, Suite 3 Ottawa, Ontario K2B 8K2 Telephone: Fax:

2

3 Glebe Parking Garage Transportation Impact Study September 213 Table of Contents 1. INTRODUCTION Project Site Site Plan Scope Methodology of the Traffic Analysis EXISTING TRAFFIC CONDITIONS Roadways Traffic Volumes Active Transportation Traffic Analysis of Existing Conditions FUTURE BACKGROUND TRAFFIC CONDITIONS Background Growth Traffic Analysis of Background Conditions FUTURE PROJECTED TRAFFIC CONDITIONS Traffic Generation Traffic Assignment Traffic Analysis of the Projected Conditions Mitigation Measures SITE DESIGN CONCLUSION ACKNOWLEDGEMENTS APPENDIX A PARKING STUDY (EXCERPTS) APPENDIX B SITE PLAN APPENDIX C TRAFFIC COUNT REPORTS APPENDIX D SYNCHRO REPORTS i

4 Glebe Parking Garage Transportation Impact Study September 213 List of Figures Figure 1-1 Project Site and Intersections under Study... 2 Figure 2-1 Existing 213 Traffic Volumes, Afternoon (Saturday) Peak Hour... 6 Figure 2-2 Existing 213 Pedestrian and Bicycle Volumes, Afternoon (Saturday) Peak Hour7 Figure 3-1 Background 218 Traffic Afternoon (Saturday) Peak Hour Figure 4-1 Generated Trips, Afternoon (Saturday) Peak Hour Figure 4-2 Projected 218 Traffic, Afternoon (Saturday) Peak Hour List of Tables Table 2-1 Turning Movement Count Reports... 5 Table 2-2 Intersection Performance, Existing 213 Traffic... 8 Table 3-1 Intersection Performance, Background 218 Traffic Table 4-1 Current Occupancy at 17 Second Avenue Table 4-2 Calculation of Generated Trips Table 4-3 Intersection Performance, Projected 218 Traffic ii

5 Glebe Parking Garage Transportation Impact Study September Introduction GENIVAR has been retained by the City of Ottawa to complete a Transportation Impact Study for the proposed construction of a multi-level parking garage on 17 Second Avenue in the Glebe Area in Ottawa. 1.1 Project Site Data about parking demand in the Glebe Area is taken from the Glebe Local Area Parking Study (referred in this document as the parking study ) produced by Morrison Hershfield in February 213. Figure 1-1 presents the Study Area of that parking study but also highlights the location of the project site and the key intersections under the present study. Appendix A contains excerpts from Morrison Hershfield s parking study. As shown, the project site is located very close to Bank Street between Second Avenue and Third Avenue. A 49-space municipal parking lot currently exists at this location. The proposed parking garage will include approximately 15 spaces, effectively tripling the capacity of the existing parking lot. It will also maintain the accesses on both Second Avenue and Third Avenue. 1.2 Site Plan The site plan including the proposed parking layout on each floor is available in Appendix B. 1.3 Scope The report includes the following: A review of the background traffic operations at key intersections; An assessment of the traffic generated by the proposed development and a review of the projected traffic operations at key intersections; A review of the proposed site design. The key intersections retained for this study are: Bank Street / Second Avenue (two-way stop-controlled); Bank Street / Third Avenue (signalized); Lyon Street / Second Avenue (all-way stop-controlled); Lyon Street / Third Avenue (all-way stop-controlled). The key intersections include the closest intersections from the project site (corners of the rectangle formed by Bank Street, Second Avenue, Lyon Street and Third Avenue). 1

6 Glebe Parking Garage Transportation Impact Study September 213 Figure 1-1 Project Site and Intersections under Study 1 Project Site Intersection under Study 1 Edited from the Glebe Local Area Parking Study produced by Morrison Hershfield in February 213. Study Area refers to the area delimited by Morrison Hershfield for their parking study. 2

7 Glebe Parking Garage Transportation Impact Study September Methodology of the Traffic Analysis The analysis of traffic operations was performed using the software tool Synchro 8 implementing the Highway Capacity Manual (HCM) 2 calculation methodology. The following key parameters are used in Synchro and are consistent with Ottawa s Transportation Impact Assessment Guidelines (26): Ideal Saturation Flow: 1,8 pcu/h; Percentage of Truck Volumes: as per the traffic count reports (minimum 2%); Conflicting Pedestrians and Bicycles: as per the traffic count reports; Passenger Car Equivalent for Heavy Vehicle: 1.7; Stored Passenger Car Length: 7 m; Stored Heavy Vehicle Length: 12 m; Peak Hour Factor:.92; Area Type: Central Business District (CBD). The ideal saturation flow is the assumed maximum number of passenger car units (pcu) per hour that can travel on a single lane under free flow conditions. In the context of a Synchro analysis, any truck is assumed to be equivalent to 1.7 passenger cars. The stored vehicle lengths are used for the calculation of queue lengths. A Peak Hour Factor (PHF) is applied to the traffic volumes in Synchro to account for variations within the peak hour interval; it represents the hourly traffic flow rate divided by the highest 15-min traffic flow rate. The traffic signal operations correspond to the current operations as observed, except for the signal timings which have been optimized for the existing, background and projected traffic conditions. The intersection performance results presented in this document should be interpreted as follow: Volume-to-Capacity (V/C) Ratio: represents the level of utilization of a turning movement. Typically, a V/C value below.85 indicates efficient operations whereas a value above 1 indicates congestion problems. Occasional congestion may occur when this value is between.85 and 1.; Average Delay per Vehicle and Level of Service (LOS): represents the drivers level of satisfaction. The LOS is directly based on the average delay: a delay lower or equal to 1 seconds equals a level of service A while a delay higher than 55 seconds (for an unsignalized intersection) equals a level of service F. Typically, a LOS D is deemed satisfactory. A level of service E or F may require corrective measures depending on the context; 95 th Percentile Queue Length: represents the 95 th longest queue of the peak hour, as estimated by Synchro. The 95 th percentile queue is typically used to determine storage requirements. 3

8 Glebe Parking Garage Transportation Impact Study September 213 4

9 Glebe Parking Garage Transportation Impact Study September Existing Traffic Conditions 2.1 Roadways The main roadways in the vicinity of the project site are Bank Street, Lyon Street, Second Avenue and Third Avenue. The speed limit is 5 km/h on Bank Street and 4 km/h on all other roadways. According to the parking study: The Glebe is primarily a residential neighbourhood, but also features a prominent and flourishing commercial area [i.e. Bank Street], several recreational parks and a major sports/event venue at Lansdowne Park. Institutions include several churches, schools, a fire station and a community centre. Bank Street is a 4-lane undivided arterial located in a densely commercial area. Parking is allowed (and heavily used) on each side of the road except from 7 to 9 a.m. in the northbound direction and from 3:3 to 5:3 p.m. in the southbound direction during weekdays to ensure the availability of 2 lanes in the peak direction during weekday peak hours. Parking duration is limited to 2 hours maximum between 8: a.m. and 5:3 p.m. every day and a fee is required during that time. No storage lanes are provided at the intersections of Bank Street / Second Avenue and Bank Street / Third Avenue; turning movements are performed from shared lanes. Outside the weekday peak periods, Bank Street generally operates as a 2-lane roadway because of the heavy use of the curb lanes for parking. Second Avenue, Third Avenue and Lyon Street are 2-lane undivided local streets located in a residential area. 2.2 Traffic Volumes Turning movement counts have been provided by the City for the intersection at Bank Street / Third Avenue for weekday peak hours in 21 and 212. GENIVAR performed weekday counts for the remaining intersections and Saturday counts for the intersections on Bank Street. Since traffic is found to be very low at the two intersections on Lyon Street, no count or analysis were done at these locations for the Saturday peak hour. The count reports are available in Appendix C. Table 2-1 presents the counts available for the present study. Table 2-1 Turning Movement Count Reports Location Weekday Counts Saturday Counts Bank Street / Second Avenue GENIVAR, 1 September 213 GENIVAR, 14 September 213 Bank Street / Third Avenue City of Ottawa, 7 Aug. 212 (rejected) City of Ottawa, 7 May 21 (adjusted) Lyon Street / Second Avenue GENIVAR, 22 August 213 n/a Lyon Street / Third Avenue GENIVAR, 22 August 213 n/a GENIVAR, 14 September 213 5

10 (31) (513) (22) (34) (488) (14) (32) (59) (12) (42) (518) (16) Glebe Parking Garage Transportation Impact Study September 213 It has been found that the 212 counts provided by the City are suspiciously low when compared to the 21 counts or GENIVAR s count at Bank Street / Second Avenue. For that reason, it has been decided to use the latter as a reference and to adjust the City s 21 counts from the City so that traffic is balanced on Bank Street. The adjusted 213 volumes are presented in Figure 2-1. Figure 2-1 Existing 213 Traffic Volumes, Afternoon (Saturday) Peak Hour Lyon Street Bank Street Second Avenue 8 $ 9 < 17 8 $ 9 < 27 (18)! 43! 4 (2) Second Second 1 = > 14 (16) 7 = > 8 (7) Avenue Avenue 28 " (7) 5 " 3? : # ; (26) 22? : # ; Second Avenue Third Avenue 8 $ 9 < 11 8 $ 9 < 14 (16)! 38! 28 (25) Third Third 6 = > 9 (33) 24 = > 19 (9) Avenue Avenue 38 " (29) 36 " 4? : # ; (53) 67? : # ; Third Avenue Lyon Street Bank Street 2.3 Active Transportation All turning movement counts performed or used for this analysis include pedestrian and bicycle volumes. They are presented in Figure 2-2 for the vehicular weekday afternoon and Saturday peak hours. 6

11 (28) (394) (42) (21) (21) (285) (428) (3) Glebe Parking Garage Transportation Impact Study September 213 Figure 2-2 Existing 213 Pedestrian and Bicycle Volumes, Afternoon (Saturday) Peak Hour Lyon Street Bank Street Second Avenue (28) Pedestrians 2 $ 2 $!! 1 (1) Bicycle Second Second Avenue Avenue " (3) 2 " # 2 # (55) 27 1 Third Avenue $ 2 $ (29)! 7! 6 (2) Third Third Avenue Avenue 4 " (1) 12 " 3 1 # 2 # 2 (53) 18 1 Third Avenue Lyon Street Bank Street As shown, pedestrian and bicycle traffic is particularly high on Bank Street: there can be as many as 984 pedestrians and 87 bicycles during a single peak hour. This has an important consequence on the traffic capacity of Bank Street / Second Avenue and Bank Street / Third Avenue. It also underlines the dynamic character of Bank Street as a commercial area and the importance of considering the impact on active transportation of any road improvement. 2.4 Traffic Analysis of Existing Conditions The capacity of the intersections under study was evaluated using the software tool Synchro 8, based on the HCM 2 methodology. The results of the analysis for the existing 213 traffic are presented in Table 2-2. Detailed Synchro reports are available in Appendix D. 7

12 Glebe Parking Garage Transportation Impact Study September 213 Table 2-2 Intersection Performance, Existing 213 Traffic Intersection Movement Afternoon Peak Hour Saturday Peak Hour V/C Ratio Avg. Delay (s) Level of Service 95 th Queue Length (m) V/C Ratio Avg. Delay (s) Level of Service 95 th Queue Length (m) Eastbound All.52 1 F F 28 Bank Street / Second Avenue TWSC Westbound All.3 42 E F 9 Northbound All.9 3 A A 2 Southbound All.27 A A 1 Eastbound All D C 28 Westbound All C C 14 Bank Street / Third Avenue Northbound All.57 9 A A 85 Southbound All.4 4 A A 33 Average Delay / Level of Service 1 A 11 B Lyon Street / Second Avenue AWSC Eastbound All.5 8 A n/a Westbound All.9 8 A n/a Northbound All.5 8 A n/a Southbound All.13 8 A n/a n/a Lyon Street / Third Avenue AWSC Eastbound All.6 8 A n/a Westbound All.7 8 A n/a Northbound All.5 7 A n/a Southbound All.11 8 A n/a n/a 8

13 Glebe Parking Garage Transportation Impact Study September 213 The table above indicates that there are currently no capacity issues at any of the intersections under study, all approaches operating below capacity during both weekday afternoon (v/c.66) and Saturday (v/c.88) peak hours. The intersection at Bank Street / Second Avenue does experience very long delays on the side street approaches, which are stopcontrolled. It is noted that this is consistent with what has been observed during the count: drivers waiting for a long time before being able to go straight or perform a left turn. The high volume of pedestrians results in fewer turning opportunities for these drivers and increases the average delay (both in Synchro and in reality). On the other hand, gaps are occasionally made available when signals located at First Avenue and Third Avenue turn red and hold the northbound and southbound traffic. Consistent with what has been observed during the counts, the 95 th percentile queue length on Second Avenue rarely exceeded 4 vehicles. Interestingly, at Bank Street / Second Avenue, during the counts, some drivers have been observed to slowly creep and/or force their way into Bank Street, violating the priority rules. Inversely, some drivers travelling on Bank Street have been observed to courteously stop and let a driver on Second Avenue proceed on Bank Street (notably when traffic is slow and/or the downstream traffic signal is red). It is noted that, at Bank Street / Third Avenue, the 95 th queue length reaches 85 m (according to Synchro) in the northbound direction. This is 25 m more than the distance between Third Avenue and Fourth Avenue. 9

14 Glebe Parking Garage Transportation Impact Study September 213 1

15 Glebe Parking Garage Transportation Impact Study September Future Background Traffic Conditions This section presents the projected intersection performance for the 5-year horizon (218) without the proposed development. 3.1 Background Growth According to the parking study, TRANS 2 forecasts a decrease of traffic on Bank Street during the morning peak hour of the magnitude of 7% to 8% from 25 to 231, partially attributed to an increase in the proportion of trips made by transit, which is expected to increase from roughly 25% in 25 to 32% in 231. However, shopping and recreation trips, which may follow a different trend than commuting trips, are typically lower during the morning peak period and higher during the afternoon and Saturday peak periods. Furthermore, densification and development projects such as the Lansdowne Park redevelopment may somewhat compensate for the downward trend in traffic 3. Therefore, as a conservative measure, a growth rate of 1% per year is applied on all traffic volumes. Figure 3-1 presents the future background 218 traffic. 2 The TRANS Joint Transportation Planning Committee manages transportation studies and collects data for transportation planning at the National Capital Region s level. 3 However, these projects may have been already included in the TRANS projection model; in that case, the forecasted decrease of traffic already takes these into consideration. 11

16 (33) (545) (23) (36) (518) (15) (34) (54) (13) (45) (55) (17) Glebe Parking Garage Transportation Impact Study September 213 Figure 3-1 Background 218 Traffic Afternoon (Saturday) Peak Hour Lyon Street Bank Street Second Avenue 8 $ 9 < 18 8 $ 9 < 29 (19)! 46! 4 (2) Second Second 11 = > 15 (17) 7 = > 8 (7) Avenue Avenue 3 " (7) 5 " 3? : # ; (28) 23? : # ; Second Avenue Third Avenue 8 $ 9 < 12 8 $ 9 < 15 (17)! 4! 3 (27) Third Third 6 = > 1 (35) 26 = > 2 (1) Avenue Avenue 4 " (31) 38 " 4? : # ; (56) 71? : # ; Third Avenue Lyon Street Bank Street 3.2 Traffic Analysis of Background Conditions The results of the analysis for the background 218 traffic are presented in Table 3-1. Detailed Synchro reports are available in Appendix D. 12

17 Glebe Parking Garage Transportation Impact Study September 213 Table 3-1 Intersection Performance, Background 218 Traffic Intersection Movement Afternoon Peak Hour Saturday Peak Hour V/C Ratio Avg. Delay (s) Level of Service 95 th Queue Length (m) V/C Ratio Avg. Delay (s) Level of Service 95 th Queue Length (m) Eastbound All F F 32 Bank Street / Second Avenue TWSC Westbound All E F 1 Northbound All.1 3 A A 2 Southbound All.28 1 A A 1 Eastbound All.7 39 D D 27 Westbound All C C 14 Bank Street / Third Avenue Northbound All.61 1 A A 9 Southbound All.43 3 A A 43 Average Delay / Level of Service 1 A 12 B Lyon Street / Second Avenue AWSC Eastbound All.6 8 A n/a Westbound All.1 8 A n/a Northbound All.5 8 A n/a Southbound All.14 8 A n/a n/a Lyon Street / Third Avenue AWSC Eastbound All.7 8 A n/a Westbound All.8 8 A n/a Northbound All.5 7 A n/a Southbound All.12 8 A n/a n/a According to the results presented above, traffic operations are not expected to change significantly from 213 to 218, except for the eastbound approach at Bank Street / Second Avenue. All approaches would operate below capacity (volume-to-capacity ratio.99). However, the Bank Street / Second Avenue would experience significantly longer delays on the eastbound approach during the Saturday peak hour. 13

18 Glebe Parking Garage Transportation Impact Study September

19 Glebe Parking Garage Transportation Impact Study September Future Projected Traffic Conditions This section presents the projected intersection performance for the 5-year horizon (i.e. 218) with the proposed development. It is assumed that the proposed parking garage will contain exactly 15 spaces. The actual capacity may be slightly more or less. 4.1 Traffic Generation Traffic generation by the proposed development is mainly based on the information presented in the parking study made by Morrison Hershfield. As a conservative measure, it is assumed that the parking lot will be occupied to its practical capacity, i.e. 85% of its full capacity. This is consistent with the forecasted occupancy rate for on-street parking (76% to 86%) presented in Table 18 of the parking study. It is noted that the forecasted occupancy rate for off-street parking is noticeably lower (58% to 61%). This emphasizes the fact that the 85% assumption is conservative. As part of the traffic counts performed on September 1 and September , a count of the number of vehicles parked in the parking lot at 17 Second Avenue was performed before and after each counting period. Table 4-1 presents the number of parked vehicles at these times. Table 4-1 Current Occupancy at 17 Second Avenue Date Time Number of parked vehicles 1 September 213 4:37 p.m. 24 cars, 1 truck (delivery) 6:18 p.m. 17 cars 14 September 213 1:57 a.m. 26 cars 3:8 p.m. 3 cars Based on the information presented in Figure 19 of the parking study, the average parking duration at the existing parking lot at 17 Second Avenue is 43 minutes on a weekday afternoon and 45 minutes on Saturday. These durations are consistent with the average durations on Bank Street south of Glebe Avenue as reported in Table 6 of the parking study (46 min on Thursday, 49 minutes on Saturday). They are used to determine the trip generation rates of the proposed parking garage. Table 4-2 presents the number of generated trips and the underlying assumptions. Table 4-2 Calculation of Generated Trips Weekday Afternoon Saturday Full Parking Capacity Projected Occupancy (85% of Capacity) Current Occupancy 2 28 Projected Occupancy Increase 18 1 Average Parking Duration 43 min 45 min Trip Generation Rate (In and Out) Number of Generated Trips (In / Out) 15 / /

20 Glebe Parking Garage Transportation Impact Study September 213 The projected occupancy is NOT an accurate prediction of how much the future parking garage will be used. It is merely a worst-case scenario for the purpose of the traffic analysis. The trip generation presented above is deemed conservative because it assumes that the peak hour of the parking garage matches the peak hour of Bank Street, which is unlikely, at least on weekday afternoons. According to the parking study, the weekday peak hours of the parking operations are 1 p.m. and 7 p.m., with the latter being more critical. At these times, it is expected that the street traffic will be lower. Also, again for conservative purpose, it is assumed there will be no pass-by trips. In reality, a certain number of trips will be performed by drivers who are already parking somewhere else and would find the future parking garage more convenient. 4.2 Traffic Assignment The site-generated trips are assigned to the road network based on the current traffic distribution. Because the eastbound and westbound approaches of the Bank Street / Second Street intersection already experience long delays, generated trips are expected to avoid them. Figure 4-1 shows the assignment of the site-generated traffic. Figure 4-2 shows the total projected traffic volumes for the 218 horizon. 16

21 (6) 56 (59) (2) (61) Glebe Parking Garage Transportation Impact Study September 213 Figure 4-1 Generated Trips, Afternoon (Saturday) Peak Hour Lyon Street Bank Street 8 Second Avenue (4) 4 "! 5 (5) Second Avenue Second Avenue # ; Second Avenue Third Avenue! 5 (5)! 5 (4) Third Third (61) 56 = Avenue Avenue (4) 4 " (4) 4 " (6) 8? : Third Avenue Lyon Street Bank Street 17

22 (93) (545) (23) (36) (518) (15) (34) (599) (15) (15) (55) (17) Glebe Parking Garage Transportation Impact Study September 213 Figure 4-2 Projected 218 Traffic, Afternoon (Saturday) Peak Hour Lyon Street Bank Street Second Avenue 8 $ 9 < 18 8 $ 9 < 29 (19)! 51! 4 (2) Second Second 11 = > 15 (17) 7 = > 8 (7) Avenue Avenue 34 " (7) 5 " 3? : # ; (28) 23? : # ; Second Avenue Third Avenue 8 $ 9 < 12 8 $ 9 < 15 (17)! 45! 35 (31) Third Third 6 = > 1 (96) 82 = > 2 (1) Avenue Avenue 45 " (34) 43 " 4? : # ; (116) 151? : # ; Third Avenue Lyon Street Bank Street 18

23 Glebe Parking Garage Transportation Impact Study September Traffic Analysis of the Projected Conditions The results of the analysis for the 218 traffic projection are presented in Table 4-3. Detailed Synchro reports are available in Appendix D. Table 4-3 Intersection Performance, Projected 218 Traffic Intersection Movement Afternoon Peak Hour Saturday Peak Hour V/C Ratio Avg. Delay (s) Level of Service 95 th Queue Length (m) V/C Ratio Avg. Delay (s) Level of Service 95 th Queue Length (m) Eastbound All F F 33 Bank Street / Second Avenue TWSC Westbound All.4 57 F F 11 Northbound All.1 3 A A 3 Southbound All.33 1 A A 1 Eastbound All E D 66 Westbound All B B 14 Bank Street / Third Avenue Northbound All D C 177 Southbound All.53 9 A B 48 Average Delay / Level of Service 37 D 27 C Lyon Street / Second Avenue AWSC Eastbound All.6 8 A n/a Westbound All.11 8 A n/a Northbound All.6 8 A n/a Southbound All.14 8 A n/a n/a Lyon Street / Third Avenue AWSC Eastbound All.7 8 A n/a Westbound All.9 8 A n/a Northbound All.5 7 A n/a Southbound All.12 8 A n/a n/a 19

24 Glebe Parking Garage Transportation Impact Study September 213 According to the results presented in the table above, the all-way stop-controlled intersections at Lyon Street / Second Avenue and Lyon Street / Third Avenue will be practically unaffected by the traffic generated by the proposed parking garage. However, the two-way stop-controlled intersection at Bank Street / Second Avenue is expected to operate with a degraded volume-to-capacity ratio of.77 and 1.4 (from.58 and.99) and an average delay of 194 and 256 seconds (from 118 and 234) on the eastbound approach during the weekday afternoon and Saturday peak hours respectively. The northbound and southbound approaches are unaffected. As for the signalized intersection at Bank Street / Third Avenue, the operations are degraded as the volume-to-capacity ratio of the eastbound approach reaches.98 and.86 (from.7 and.62), its average delay, 77 and 53 seconds (from 39 and 36) and its 95 th queue length, 9 and 66 m (from 31 and 27) during the weekday afternoon and Saturday peak hours respectively. But the most important change is on the northbound approach, with a volume-to-capacity ratio of 1. and.9 (from.61 and.62), an average delay of 54 and 32 seconds (from 1 and 1) and a 95 th queue length of 177 and 177 m (from 84 and 9). Clearly, the increase of the eastbound and northbound left-turn traffic has a considerable impact on the performance of this intersection. It is noted again that, as conservative measures, the present analysis assumes that the peak hour of the parking garage will match that of Bank Street, that no pass-by trips will be included in the generated trips and that the background traffic will grow at 1% per year (instead of decreasing). Therefore, it is concluded that the worst-case scenario will be the intersection at Bank Street / Third Avenue reaching capacity (but not exceeding it) while still operating at a satisfactory level of service (overall LOS D) although with a northbound queue length that will reach 177 m (about 1 m upstream of Fifth Avenue) 5% of the time. 4.4 Mitigation Measures A certain number of small changes can be done to improve the traffic flow at the intersections of Bank Street / Second Avenue and Bank Street / Third Avenue. Since left-turning drivers waiting for a gap are blocking the lane for through and right-turn movements therefore severely reducing the intersection capacity, the level of service could be improved by either prohibiting the left turn movements during peak hours where long delays are an issue (but that would limit the accessibility to the parking garage and the neighbourhood and/or force drivers to use other roads), or prohibiting parking on Bank Street in both direction (instead of the peak direction) near Third Avenue. However, the following must be considered: According to the Transportation Impact Assessment Guidelines (26), a volume-tocapacity ratio of 1. is considered acceptable in the City s urban core. This is consistent with the high volume of pedestrians and bicycles typically encountered in such setting and with the accepted premise that any increase of traffic capacity could be detrimental to them. Therefore, the performance of the Bank Street / Third Avenue intersection is deemed satisfactory. Moreover, increasing traffic capacity would go against the City s Transportation Demand Management policy which aims to limit car traffic and encourage other modes of transportation. The eastbound approach of the Bank Street / Second Avenue intersection performs poorly, but the traffic volume is extremely low and other alternatives are available, such as travelling via Third Avenue. Therefore, no changes are recommended at this location. 2

25 Glebe Parking Garage Transportation Impact Study September 213 Considering the above, and the conservative nature of the present traffic analysis, no changes are recommended at this point at any of the intersections under study. 21

26 Glebe Parking Garage Transportation Impact Study September

27 Glebe Parking Garage Transportation Impact Study September Site Design The latest site plan, which has been submitted on September 13, 213, has been reviewed for conformance with the City of Ottawa Private Approach Bylaw. The proposed development of a four-level, 158-space (subject to change) parking structure having right-of-way frontage on both Second Avenue and Third Avenue conforms to all clauses of the private approach bylaw except for clause 25(l)(i) which states that the minimum separation between a private approach and any other private approach shall be no less than 45 metres. Due to the nature of the site location, this clause is not feasible and as such an exemption will be required. The second aspect of clause 25(l)i) states that the nearest edge of a private access can be no less than 45 metres from the nearest street line (Bank Street right-of-way) which is met on the Second Avenue approach but is not met on the Third Avenue approach. An exemption would also be required for this access. 23

28 Glebe Parking Garage Transportation Impact Study September

29 Glebe Parking Garage Transportation Impact Study September Conclusion The City of Ottawa is proposing the construction of a 15-space parking garage that will replace the existing 49-space parking lot. The purpose of this study is to determine the impact such development will have on the nearby intersections. The Glebe Local Area Parking Study produced by Morrison Hershfield in February 213 is used as a reference to determine the parking occupancy. The traffic operation analysis reveals that all the intersections under study are operating satisfactorily, except for the Bank Street / Second Avenue which experiences long delays at its eastbound and westbound approaches. Without the proposed development, the intersections will all operate in a similar way in 218 (except for the longer delay at the eastbound approach of the Bank Street / Second Avenue intersection). Using conservative assumptions, the analysis reveals that, once the parking garage is built, the intersection at Bank Street / Second Avenue will experience even longer delays at its eastbound approach and the intersection at Bank Street / Third Avenue will reach (but not exceed) capacity. It is concluded that no changes are recommended at Bank Street / Second Avenue since the side street traffic is found to be very low and that drivers on Second Avenue can avoid the intersection at Bank Street by travelling on another street, such as Third Avenue. Also, no changes are recommended at Bank Street / Third Avenue since the intersection s performance, although at capacity, is deemed satisfactory. Moreover, increasing traffic capacity would go against the City s Transportation Demand Management policy which aims to limit car traffic and encourage other modes of transportation. The currently proposed site design is compliant with the City of Ottawa Private Approach Bylaw except for clause 25(l)i) which states that the minimum separation between a private approach and the nearest street line or any other private approach shall be no less than 45 metres. Due to the nature of the site location, this clause is not feasible and as such an exemption will be required. 25

30 Glebe Parking Garage Transportation Impact Study September

31 Glebe Parking Garage Transportation Impact Study September Acknowledgements This report has been completed by Daniel Riendeau, Transportation Engineer, and Angelo Renon, Director, Transportation, GENIVAR. 27

32

33 Glebe Parking Garage Transportation Impact Study Appendix A Parking Study (Excerpts)

34

35 FINAL REPORT Glebe Local Area Parking Study Ottawa, ON Presented to: Mary Gracie, MCIP, RPP Program Manager, Parking Studies City of Ottawa Parking Operations, Maintenance and Development 185 Slidell Street Ottawa, Ontario K1Y 3B5 Project No February 21, 213 Morrison Hershfield 244 Don Reid Drive, Ottawa, ON K1H 1E1, Canada Tel Fax morrisonhershfield.com

36

37 Figure 4 Glebe Land Use Zoning

38 Parking Duration The availability of parking in a given area depends in part on the average parking duration; the shorter the parking duration, the greater the turnover of spaces. Parking duration across the Glebe was analyzed for both Bank Street and side street locations (refer to Table 6 and Figure 16). In general, a significant number of cars are parking for periods of a half hour or less, with most parking for less than an hour. This is particularly true for the paid spaces along Bank Street. Along the side streets, as may be expected, the parking duration tends to be longer due to the less restrictive time limits in certain areas. The side street results are also impacted by residential permit holders who may park on-street for extended periods. It is interesting to note that although the average parking duration on Bank Street increases on Sunday (when parking is free), people still tend to park for less time than the surrounding side streets. While parking fees do impact the parking duration on Bank Street, in absolute terms, the impact is small, with the average parking duration on Sunday only 1 minutes longer than on Thursday and Saturday. However, this small difference has a noticeable impact on occupancy levels, with less parking available on Sunday than on Saturday, even though both days represent weekend conditions. Additional graphs illustrating the parking duration can be found in Appendix G. Bank Street Side Streets Table 6 Average Parking Duration in the Glebe Average Parking Duration (minutes) Location Saturday Sunday Thursday North of Glebe Ave South of Glebe Ave Bank Street - Overall North of Glebe Ave South of Glebe Ave Side Streets - Overall Note: The parking duration results may be affected by the length of the survey period. In particular, since the Sunday survey was only 4 hours long, the actual parking duration may be longer than captured in the data.

39 Duration data for both parking lots is shown in Figure 19. At 17 Second Avenue, roughly 75% of people park for one hour or less, with some variation between days. 7 Interestingly, with free parking on Sunday, there are a number of people who park for longer than 2 hours (1%), but there are also many more people parking for shorter intervals. At 574 Bank Street, the impact of free Sunday parking is much more significant, with 38% of people parking for 4 hours or more. Monday - Thursday Parking Duration 9% 16% 28% 47% -3 min 31-6 min 61-9 min min >12 min Data Source: Pay & Display Data, April 211 Saturday Parking Duration 1% 16% 31% 43% -3 min 31-6 min 61-9 min min >12 min Monday - Thursday Parking Duration 4% 14% 19% 1% 1% 26% 36% -3 min 31-6 min 61-9 min min 2-3 hrs 3-4 hrs 4+ hours Data Source: Pay & Display Data, April 211 Saturday Parking Duration 1% 1% 21% 6% 27% 21% 23% -3 min 31-6 min 61-9 min min 2-3 hrs 3-4 hrs 4+ hours Data Source: Pay & Display Data, April 211 Sunday Parking Duration 8% 1% 13% 1% 59% -3 min 31-6 min 61-9 min min >12 min Data Source: License Plate Survey, April 212 (1 AM - 4 PM) Data Source: Pay & Display Data, April 211 Sunday Parking Duration 15% -3 min 31-6 min 38% 12% 61-9 min min 2-3 hrs 3-4 hrs 35% 4+ hours Data Source: License Plate Survey, June 212 (1 AM-4 PM) Figure 19 Duration Data for Municipal Lots in the Glebe 7 Duration data based on Pay & Display data is an estimate only, since people may purchase more time than they actually use, or conversely, they may park for longer than the ticket allows.

40 Existing Anticipated Change Future (net impact) Table 17 Projected Impacts of Future Parking Changes (Full Study Area) On-Street Off-Street Demand Supply Occupancy Rate 62% 37% Low High Low High Demand Supply Low High Low High Demand Supply Occupancy Rate 68% 77% 38% 4% Since current occupancy levels are highest in the area south of Glebe Avenue, a similar analysis was carried out focusing on the southern section of the study area, with the results shown below in Table 18. Table 18 Projected Impacts of Future Parking Changes (South of Glebe Avenue) Existing Anticipated Change Future (net impact) On-Street Off-Street Demand Supply Occupancy Rate 73% 57% Low High Low High Demand Supply Low High Low High Demand Supply Occupancy Rate 76% 86% 58% 61% If the maximum growth is achieved, the overall on-street occupancy rate for the area south of Glebe Avenue will exceed the 85% utilization threshold (i.e. the practical capacity), prompting the need for action Although off-street occupancy levels remain relatively low under both intensification scenarios, it is important to note that only some of the off-street supply is available for general public use.

41 Glebe Parking Garage Transportation Impact Study Appendix B Site Plan

42

43 m 2m 4m 6m 8m 1m m 2m 4m 6m 8m 1m Architect of Record / Architecte Responsable: KEYPLAN / PLAN-CLÉ GLEBE PARKING STRUCTURE 17 SECOND AVE., OTTAWA, ONTARIO 1 LEVEL 1 A1 1 : 1 2 LEVEL 2 A1 1 : 1 Date No. Description Project Number / Numéro de Projet Drawn By / Dessinée Par: Checked By / Vérifiée Par: FIRST & SECOND FLOOR PLAN Scale / Échelle A1 1 : 1 16/9/213 2:58:31 PM

44 m 2m 4m 6m 8m 1m m 2m 4m 6m 8m 1m Architect of Record / Architecte Responsable: KEYPLAN / PLAN-CLÉ GLEBE PARKING STRUCTURE 17 SECOND AVE., OTTAWA, ONTARIO 1 LEVEL 3 A2 1 : 1 2 LEVEL 4 A2 1 : 1 Date No. Description Project Number / Numéro de Projet Drawn By / Dessinée Par: Checked By / Vérifiée Par: THIRD & FOURTH FLOOR Scale / Échelle A2 1 : 1 16/9/213 3::14 PM

45 Glebe Parking Garage Transportation Impact Study Appendix C Traffic Count Reports

46

47 Vehicular Turning Movements (15 Min. Volumes) All Vehicles BANK STREET and in Ottawa, ON Survey Date: Tuesday, 1 September 213 Performed By: GENIVAR Grey = Peak Hour BANK STREET BANK STREET Northbound Southbound Eastbound Westbound Time Period LT T RT SUB TOT LT T RT SUB TOT STR TOT LT T RT SUB TOT LT T RT SUB TOT STR TOT GRAND TOTAL 7:15 7: :3 7: :45 8: : 8: :15 8: :3 8: :45 9: : 9: :15 9: : 16: :15 16: :3 16: :45 17: : 17: :15 17: :3 17: :45 18: : 18: TOTAL Note: Volumes above include cars and heavy vehicles. They do not include bicycles. Cars include motorcycles, passenger cars, pick-up trucks (including "heavy-duty"), full-size vans (e.g. Econoline), and any of these with a trailer TM Count - Bank_Second Tue.xlsx Created 16/9/213 1/7

48 Vehicular Turning Movements (15 Min. Volumes) Heavy Vehicles BANK STREET and in Ottawa, ON Survey Date: Tuesday, 1 September 213 Performed By: GENIVAR BANK STREET BANK STREET Northbound Southbound Eastbound Westbound Time Period LT T RT SUB TOT LT T RT SUB TOT STR TOT LT T RT SUB TOT LT T RT SUB TOT STR TOT GRAND TOTAL 7:15 7: :3 7: :45 8: : 8: :15 8: :3 8: :45 9: : 9: :15 9: : 16: :15 16: :3 16: :45 17: : 17: :15 17: :3 17: :45 18: : 18: TOTAL Note: Heavy vehicles include buses and vehicles with more than 2 axles, with the exception of cars with trailers TM Count - Bank_Second Tue.xlsx Created 16/9/213 2/7

49 Vehicular Turning Movements (15 Min. Volumes) Bicycles BANK STREET and in Ottawa, ON Survey Date: Tuesday, 1 September 213 Performed By: GENIVAR BANK STREET BANK STREET Northbound Southbound Eastbound Westbound Time Period LT T RT SUB TOT LT T RT SUB TOT STR TOT LT T RT SUB TOT LT T RT SUB TOT STR TOT GRAND TOTAL 7:15 7: :3 7: :45 8: : 8: :15 8: :3 8: :45 9: : 9: :15 9: : 16: :15 16: :3 16: :45 17: : 17: :15 17: :3 17: :45 18: : 18: TOTAL TM Count - Bank_Second Tue.xlsx Created 16/9/213 3/7

50 Vehicular Turning Movements (15 Min. Volumes) Pedestrians BANK STREET and in Ottawa, ON Survey Date: Tuesday, 1 September 213 Performed By: GENIVAR BANK STREET BANK STREET Parallel Crossing Parallel Crossing Parallel Crossing Parallel Crossing Time Period East West STREET TOTAL South North STREET TOTAL GRAND TOTAL 7:15 7: :3 7: :45 8: : 8: :15 8: :3 8: :45 9: : 9: :15 9: : 16: :15 16: :3 16: :45 17: : 17: :15 17: :3 17: :45 18: : 18: TOTAL TM Count - Bank_Second Tue.xlsx Created 16/9/213 4/7

51 Vehicular Turning Movements All Vehicles and Pedestrians BANK STREET and in Ottawa, ON Survey Date: Tuesday, 1 September 213 Performed By: GENIVAR N Full Period (4.5 hours) BANK STREET BANK STREET BANK STREET BANK STREET Morning Peak (8:15 9:15) Afternoon Peak (16:45 17:45) BANK STREET BANK STREET BANK STREET BANK STREET Note: Volumes above include cars and heavy vehicles. They do not include bicycles. Cars include motorcycles, passenger cars, pick-up trucks (including "heavy-duty"), full-size vans (i.e. Econoline), and any of these with a trailer TM Count - Bank_Second Tue.xlsx 5/7

52 Vehicular Turning Movements Heavy Vehicles BANK STREET and in Ottawa, ON Survey Date: Tuesday, 1 September 213 Performed By: GENIVAR N Full Period (4.5 hours) BANK STREET BANK STREET BANK STREET BANK STREET Morning Peak (8:15 9:15) Afternoon Peak (16:45 17:45) BANK STREET BANK STREET BANK STREET BANK STREET Note: Heavy vehicles include buses and vehicles with more than 2 axles, with the exception of cars with trailers TM Count - Bank_Second Tue.xlsx 6/7

53 Vehicular Turning Movements Bicycles BANK STREET and in Ottawa, ON Survey Date: Tuesday, 1 September 213 Performed By: GENIVAR N Full Period (4.5 hours) BANK STREET BANK STREET BANK STREET BANK STREET Morning Peak (8:15 9:15) Afternoon Peak (16:45 17:45) BANK STREET BANK STREET BANK STREET BANK STREET TM Count - Bank_Second Tue.xlsx 7/7

54

55 Vehicular Turning Movements (15 Min. Volumes) All Vehicles BANK STREET and in Ottawa, ON Survey Date: Saturday, 14 September 213 Performed By: GENIVAR Grey = Peak Hour BANK STREET BANK STREET Northbound Southbound Eastbound Westbound Time Period LT T RT SUB TOT LT T RT SUB TOT STR TOT LT T RT SUB TOT LT T RT SUB TOT STR TOT GRAND TOTAL 11: 11: :15 11: :3 11: :45 12: : 12: :15 12: :3 12: :45 13: : 13: :15 13: :3 13: :45 14: : 14: :15 14: :3 14: :45 15: TOTAL Note: Volumes above include cars and heavy vehicles. They do not include bicycles. Cars include motorcycles, passenger cars, pick-up trucks (including "heavy-duty"), full-size vans (e.g. Econoline), and any of these with a trailer TM Count - Bank_Second Sat.xlsx Created 16/9/213 1/7

56 Vehicular Turning Movements (15 Min. Volumes) Heavy Vehicles BANK STREET and in Ottawa, ON Survey Date: Saturday, 14 September 213 Performed By: GENIVAR BANK STREET BANK STREET Northbound Southbound Eastbound Westbound Time Period LT T RT SUB TOT LT T RT SUB TOT STR TOT LT T RT SUB TOT LT T RT SUB TOT STR TOT GRAND TOTAL 11: 11: :15 11: :3 11: :45 12: : 12: :15 12: :3 12: :45 13: : 13: :15 13: :3 13: :45 14: : 14: :15 14: :3 14: :45 15: TOTAL Note: Heavy vehicles include buses and vehicles with more than 2 axles, with the exception of cars with trailers TM Count - Bank_Second Sat.xlsx Created 16/9/213 2/7

57 Vehicular Turning Movements (15 Min. Volumes) Bicycles BANK STREET and in Ottawa, ON Survey Date: Saturday, 14 September 213 Performed By: GENIVAR BANK STREET BANK STREET Northbound Southbound Eastbound Westbound Time Period LT T RT SUB TOT LT T RT SUB TOT STR TOT LT T RT SUB TOT LT T RT SUB TOT STR TOT GRAND TOTAL 11: 11: :15 11: :3 11: :45 12: : 12: :15 12: :3 12: :45 13: : 13: :15 13: :3 13: :45 14: : 14: :15 14: :3 14: :45 15: TOTAL TM Count - Bank_Second Sat.xlsx Created 16/9/213 3/7

58 Vehicular Turning Movements (15 Min. Volumes) Pedestrians BANK STREET and in Ottawa, ON Survey Date: Saturday, 14 September 213 Performed By: GENIVAR BANK STREET BANK STREET Parallel Crossing Parallel Crossing Parallel Crossing Parallel Crossing Time Period East West STREET TOTAL South North STREET TOTAL GRAND TOTAL 11: 11: :15 11: :3 11: :45 12: : 12: :15 12: :3 12: :45 13: : 13: :15 13: :3 13: :45 14: : 14: :15 14: :3 14: :45 15: TOTAL TM Count - Bank_Second Sat.xlsx Created 16/9/213 4/7

59 Vehicular Turning Movements All Vehicles and Pedestrians BANK STREET and in Ottawa, ON Survey Date: Saturday, 14 September 213 Performed By: GENIVAR N Full Period (4 hours) Saturday Peak (12:15 13:15) BANK STREET BANK STREET BANK STREET BANK STREET Note: Volumes above include cars and heavy vehicles. They do not include bicycles. Cars include motorcycles, passenger cars, pick-up trucks (including "heavy-duty"), full-size vans (i.e. Econoline), and any of these with a trailer TM Count - Bank_Second Sat.xlsx 5/7

60 Vehicular Turning Movements Heavy Vehicles BANK STREET and in Ottawa, ON Survey Date: Saturday, 14 September 213 Performed By: GENIVAR N Full Period (4 hours) Saturday Peak (12:15 13:15) BANK STREET BANK STREET BANK STREET BANK STREET Note: Heavy vehicles include buses and vehicles with more than 2 axles, with the exception of cars with trailers TM Count - Bank_Second Sat.xlsx 6/7

MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. Prepared for:

MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. Prepared for: MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW Prepared for: 2434984 Ontario Inc. 13-5510 Canotek Road Ottawa, Ontario K1J 9J5 June 4, 2015 115-613 Report_2.doc D. J.

More information

Place Vanier 250 Montreal Road Transportation Impact Study Addendum. Prepared for Broccolini Construction September 20 th, 2012

Place Vanier 250 Montreal Road Transportation Impact Study Addendum. Prepared for Broccolini Construction September 20 th, 2012 Update for the May 31 st, 2012 Traffic Impact Study Prepared for Broccolini Construction 111-23596-00 September 20 th, 2012 2611 Queensview Drive, Suite 300, Ottawa, Ontario CANADA K2B 8K2 Telephone: 613-829-2800

More information

TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio

TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio December 12, 2012 Prepared for: The City of Huron 417 Main Huron, OH 44839 Providing Practical Experience Technical Excellence and Client

More information

INDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for:

INDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: INDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW Prepared for: Simluc Contractors Limited 2550 Blackwell Street, Ottawa K1B 5R1 October 18, 2013 113-584 Overview_1.doc D. J.

More information

HENDERSON DEVELOPMENT 213, 217, 221, 221 ½, 223 HENDERSON AVENUE and 65 TEMPLETON STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW.

HENDERSON DEVELOPMENT 213, 217, 221, 221 ½, 223 HENDERSON AVENUE and 65 TEMPLETON STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. HENDERSON DEVELOPMENT 213, 217, 221, 221 ½, 223 HENDERSON AVENUE and 65 TEMPLETON STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW Prepared for: 2294170 Ontario Inc. February 2, 2017 117-652 Report_1.doc

More information

TRAFFIC ASSESSMENT River Edge Colorado

TRAFFIC ASSESSMENT River Edge Colorado TRAFFIC ASSESSMENT River Edge Colorado Submitted by: Fehr & Peers 621 17th Street, Ste. 231 Denver, CO 8293 (33) 296-43 December, 21 App. M-2 Traffic Assessment River Edge Colorado December 21 TABLE OF

More information

QUICKIE C STORE AND GAS BAR 1780 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:

QUICKIE C STORE AND GAS BAR 1780 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: QUICKIE C STORE AND GAS BAR 1780 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: Quickie Convenience Stores Larny Holdings Ltd. c/o PBC Group April 15, 2015 115-615 Report_1.doc D. J. Halpenny

More information

Traffic Impact Study. Westlake Elementary School Westlake, Ohio. TMS Engineers, Inc. June 5, 2017

Traffic Impact Study. Westlake Elementary School Westlake, Ohio. TMS Engineers, Inc. June 5, 2017 TMS Engineers, Inc. Traffic Impact Study Westlake Elementary School Westlake, Ohio June 5, 2017 Prepared for: Westlake City Schools - Board of Education 27200 Hilliard Boulevard Westlake, OH 44145 TRAFFIC

More information

OFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Canada Inc.

OFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Canada Inc. OFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: 9402209 Canada Inc. December 15, 2015 115-625 Report_2.doc D. J. Halpenny & Associates Ltd. Consulting Transportation

More information

INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED. Prepared for: Canada Inc.

INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED. Prepared for: Canada Inc. INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED Prepared for: 7849648 Canada Inc. Octiober 1, 2015 114-598 Overview_2.doc D. J. Halpenny & Associates Ltd. Consulting

More information

OTTAWA TRAIN YARDS PHASE 3 DEVELOPMENT CITY OF OTTAWA TRANSPORTATION IMPACT STUDY. Prepared for:

OTTAWA TRAIN YARDS PHASE 3 DEVELOPMENT CITY OF OTTAWA TRANSPORTATION IMPACT STUDY. Prepared for: OTTAWA TRAIN YARDS PHASE 3 DEVELOPMENT CITY OF OTTAWA TRANSPORTATION IMPACT STUDY Prepared for: The Ottawa Train Yards Inc. 223 Colonnade Road South, Suite 212 Nepean, Ontario K2E 7K3 January 17, 2012

More information

MEETING FACILITY 2901 GIBFORD DRIVE CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: Holiday Inn Express 2881 Gibford Drive Ottawa, ON K1V 2L9

MEETING FACILITY 2901 GIBFORD DRIVE CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: Holiday Inn Express 2881 Gibford Drive Ottawa, ON K1V 2L9 MEETING FACILITY 2901 GIBFORD DRIVE CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: Holiday Inn Express 2881 Gibford Drive Ottawa, ON K1V 2L9 December 18, 2012 112-566 Brief_1.doc D. J. Halpenny & Associates

More information

Walmart (Store # ) 60 th Street North and Marion Road Sioux Falls, South Dakota

Walmart (Store # ) 60 th Street North and Marion Road Sioux Falls, South Dakota Walmart (Store #4865-00) 60 th Street North and Marion Road Sioux Falls, South Dakota Prepared for: Wal-Mart Stores, Inc. Bentonville, Arkansas Prepared by: Kimley-Horn and Associates, Inc. ã2013 Kimley-Horn

More information

URBAN QUARRY HEADQUARTERS 2717 STEVENAGE DRIVE CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Urban Quarry 4123 Belgreen Drive, Ottawa K1G 3N2

URBAN QUARRY HEADQUARTERS 2717 STEVENAGE DRIVE CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: Urban Quarry 4123 Belgreen Drive, Ottawa K1G 3N2 URBAN QUARRY HEADQUARTERS 2717 STEVENAGE DRIVE CITY OF OTTAWA TRANSPORTATION OVERVIEW Prepared for: Urban Quarry 4123 Belgreen Drive, Ottawa K1G 3N2 February 27, 2014 113-584 Overview_1.doc D. J. Halpenny

More information

TRAFFIC IMPACT ANALYSIS

TRAFFIC IMPACT ANALYSIS TRAFFIC IMPACT ANALYSIS FOR THE CHAMPAIGN UNIT#4 SCHOOL DISTRICT PROPOSED HIGH SCHOOL (SPALDING PARK SITE) IN THE CITY OF CHAMPAIGN Final Report Champaign Urbana Urbanized Area Transportation Study 6/24/2014

More information

VIVA RETIREMENT COMMUNITIES OAKVILLE TRAFFIC IMPACT STUDY

VIVA RETIREMENT COMMUNITIES OAKVILLE TRAFFIC IMPACT STUDY VIVA RETIREMENT COMMUNITIES OAKVILLE TRAFFIC IMPACT STUDY VIVA RETIREMENT COMMUNITIES OAKVILLE TRAFFIC IMPACT STUDY DECEMBER 2012 READ, VOORHEES & ASSOCIATES TORONTO, ONTARIO Read, Voorhees & Associates

More information

The proposed development is located within 800m of an existing Transit Station where infill developments and intensification are encouraged.

The proposed development is located within 800m of an existing Transit Station where infill developments and intensification are encouraged. Stantec Consulting Ltd. 1331 Clyde Avenue, Suite 4 Ottawa ON K2C 3G4 Tel: (613) 722-442 Fax: (613) 722-2799 May 14, 213 File: 1638823 Robinson Park Development Corp. 5699 Power Road Ottawa, ON, K1G 3N4

More information

HOLIDAY INN HOTEL 235 KING EDWARD AVENUE CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for:

HOLIDAY INN HOTEL 235 KING EDWARD AVENUE CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: HOLIDAY INN HOTEL 235 KING EDWARD AVENUE CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: Momentum Planning & Communications 1165 Greenlawn Crescent Ottawa, ON K1L 6C2 June 29, 2015 115-618 Brief_1.doc

More information

Traffic Impact Study WestBranch Residential Development Davidson, NC March 2016

Traffic Impact Study WestBranch Residential Development Davidson, NC March 2016 Traffic Impact Study WestBranch Residential Development Davidson, NC March 216 TRAFFIC IMPACT STUDY FOR THE WestBranch Residential Development LOCATED IN DAVIDSON, NC Prepared For: Lennar Carolinas, LLC

More information

Transportation Impact Study for Abington Terrace

Transportation Impact Study for Abington Terrace Transportation Impact Study for Abington Terrace Abington Township, Montgomery County, PA Sandy A. Koza, P.E., PTOE PA PE License Number PE059911 Prepared by McMahon Associates, Inc. 425 Commerce Drive,

More information

Henderson Avenue Mixed-Use Development

Henderson Avenue Mixed-Use Development Zoning Case: Z145-3 Traffic Impact Analysis Henderson Avenue Mixed-Use Development Dallas, TX October 26 th, 216 Kimley-Horn and Associates, Inc. Dallas, Texas Project #644827 Registered Firm F-928 Traffic

More information

COMMERCIAL DEVELOPMENT 2015 ROBERTSON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:

COMMERCIAL DEVELOPMENT 2015 ROBERTSON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: COMMERCIAL DEVELOPMENT 2015 ROBERTSON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: First Bay Properties Inc. 311 Richmond Road, Suite 203 Ottawa, ON K1Z 6X3 August 8, 2017 117-663 Brief_1.doc

More information

Magnolia Place. Traffic Impact Analysis. Prepared for: City of San Mateo. Prepared by: Hexagon Transportation Consultants, Inc.

Magnolia Place. Traffic Impact Analysis. Prepared for: City of San Mateo. Prepared by: Hexagon Transportation Consultants, Inc. Magnolia Place Traffic Impact Analysis Prepared for: City of San Mateo Prepared by: Hexagon Transportation Consultants, Inc. Updated January 4, 2010 Table of Contents 1. Introduction...1 2. Existing Conditions...6

More information

9 Leeming Drive Redevelopment Ottawa, ON Transportation Brief. Prepared By: Stantec Consulting Ltd.

9 Leeming Drive Redevelopment Ottawa, ON Transportation Brief. Prepared By: Stantec Consulting Ltd. 9 Leeming Drive Redevelopment Ottawa, ON Transportation Brief Prepared By: Stantec Consulting Ltd. TIA GUIDELINES CHECKLIST Report Context Municipal Address Comment: Section 1.1 Location relative to major

More information

Evaluation and Changes to Pedestrian Priority Phase Signal (Scramble Crossing) at Bay Street and Bloor Street

Evaluation and Changes to Pedestrian Priority Phase Signal (Scramble Crossing) at Bay Street and Bloor Street PW2.2 STAFF REPORT ACTION REQUIRED Evaluation and Changes to Pedestrian Priority Phase Signal (Scramble Crossing) at Bay Street and Bloor Street Date: February 12, 2015 To: From: Public Works and Infrastructure

More information

EXECUTIVE SUMMARY. Page 1 of 6

EXECUTIVE SUMMARY. Page 1 of 6 EXECUTIVE SUMMARY The purpose of this report is to identify conformance with the original traffic impact study for the proposed retail development on Lot 5 of Riverdale Retail Filing No. 1 located on the

More information

Project Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015

Project Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015 Meadows Place, TX October 9, 2015 Contents 1 Introduction... 1 2 Data Collection... 1 3 Existing Roadway Network... 2 4 Traffic Volume Development... 2 5 Warrant Analysis... 3 6 Traffic Control Alternative

More information

Road Conversion Study Plumas Street

Road Conversion Study Plumas Street Plumas Street Phase I Submitted to The Regional Transportation Commission of Washoe County Submitted by Zong Tian, Ph.D., P.E. Saeedeh Farivar Haiyuan Li, Ph.D. Center for Advanced Transportation Education

More information

3.9 - Transportation and Traffic

3.9 - Transportation and Traffic Transportation and Traffic 3.9 - Transportation and Traffic This section describes the potential transportation and traffic effects of project implementation on the project site and its surrounding area.

More information

TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT

TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT DEERFIELD TOWNSHIP, WARREN COUNTY, OHIO Nantucket Circle and Montgomery Road () Prepared for: ODLE

More information

Traffic Circulation Study for Neighborhood Southwest of Mockingbird Lane and Airline Road, Highland Park, Texas

Traffic Circulation Study for Neighborhood Southwest of Mockingbird Lane and Airline Road, Highland Park, Texas ARIZONA TEXAS NEW MEXICO OKLAHOMA February 13, 2015 Mr. Meran Dadgostar P.E., R.S. Town of Highland Park 4700 Drexel Dr. Highland Park, Texas 75205 Re: Traffic Circulation Study for Neighborhood Southwest

More information

DUNBOW ROAD FUNCTIONAL PLANNING

DUNBOW ROAD FUNCTIONAL PLANNING DUNBOW ROAD FUNCTIONAL PLANNING Final Report August 3, 216 #31, 316 5th Avenue NE Calgary, AB T2A 6K4 Phone: 43.273.91 Fax: 43.273.344 wattconsultinggroup.com Dunbow Road Functional Planning Final Report

More information

Harrah s Station Square Casino

Harrah s Station Square Casino Transportation Analysis Harrah s Station Square Casino Pittsburgh, Pennsylvania Submitted To: City of Pittsburgh and Pennsylvania Gaming Control Board Prepared By: DKS Associates GAI Consultants December

More information

APARTMENT BUILDING DEVELOPMENT 1161 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION IMPACT STUDY. Prepared for:

APARTMENT BUILDING DEVELOPMENT 1161 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION IMPACT STUDY. Prepared for: APARTMENT BUILDING DEVELOPMENT 1161 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION IMPACT STUDY Prepared for: 1649362 Ontario Inc. c/o Manor Park Management 231 Brittany Drive, Suite D Ottawa ON K1K 0R8 July

More information

HILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF. Prepared for:

HILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF. Prepared for: HILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF Prepared for: Bona Building & Management Co. Ltd. Place Vanier, 333 North River Road Vanier, Ontario K1L 8B9 October

More information

EAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA

EAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA T R A F F I C I M P A C T A N A LY S I S EAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA April 217 T R A F F I C I M P A C T A N A LY S I S EAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA Submitted

More information

NEW YORK CENTRAL PARK SUBDIVISION BLAIS STREET/ST-PIERRE STREET EMBRUN, ONTARIO TRAFFIC IMPACT STUDY. Prepared for:

NEW YORK CENTRAL PARK SUBDIVISION BLAIS STREET/ST-PIERRE STREET EMBRUN, ONTARIO TRAFFIC IMPACT STUDY. Prepared for: NEW YORK CENTRAL PARK SUBDIVISION BLAIS STREET/ST-PIERRE STREET EMBRUN, ONTARIO TRAFFIC IMPACT STUDY Prepared for: Solidex Holdings Limited & Investissement Maurice Lemieux Investments Attn: Mr. Anthony

More information

TRAFFIC IMPACT STUDY. Creekside Thornton, Colorado. For. August 2015 November 2015 Revised: August Prepared for:

TRAFFIC IMPACT STUDY. Creekside Thornton, Colorado. For. August 2015 November 2015 Revised: August Prepared for: TRAFFIC IMPACT STUDY For Creekside Thornton, Colorado August 215 November 215 Revised: August 216 Prepared for: Jansen Strawn Consulting Engineers 45 West 2 nd Avenue Denver, Colorado 8223 Prepared by:

More information

Parking Lot P6C Transportation Impact Assessment

Parking Lot P6C Transportation Impact Assessment Transportation Carleton University Parking Lot P6C Transportation Impact Assessment Prepared by: AECOM 302 1150 Morrison Drive 613 820 8282 tel Ottawa, ON, Canada K2H 8S9 613 820 8338 fax www.aecom.com

More information

Traffic Impact Analysis Chatham County Grocery Chatham County, NC

Traffic Impact Analysis Chatham County Grocery Chatham County, NC Chatham County Grocery Chatham County, NC TABLE OF CONTENTS 1. INTRODUCTION... 1 1.1. Location and Study Area... 1 1.2. Proposed Land Use and Access... 2 1.3. Adjacent Land Uses... 2 1.4. Existing ways...

More information

South Albion-Bolton Community Plan North Hill Supermarket Transportation Study Part B: Evaluation of Alternatives

South Albion-Bolton Community Plan North Hill Supermarket Transportation Study Part B: Evaluation of Alternatives Community Plan North Hill Supermarket Transportation Study Part B: Evaluation of Alternatives Prepared for: The Town of Caledon August 9 Transportation Solutions Ltd. 43 Forest Road Cambridge, ON N1S 3B4

More information

MoPac South: Impact on Cesar Chavez Street and the Downtown Network

MoPac South: Impact on Cesar Chavez Street and the Downtown Network MoPac South: Impact on Cesar Chavez Street and the Downtown Network Prepared by: The University of Texas at Austin Center for Transportation Research Prepared for: Central Texas Regional Mobility Authority

More information

APPENDIX H EXISTING TRAFFIC CONDITIONS ANALYSIS

APPENDIX H EXISTING TRAFFIC CONDITIONS ANALYSIS APPENDIX H EXISTING TRAFFIC CONDITIONS ANALYSIS MEMO : Peter Steacy, P.Eng. Date: December 3, 2014 : Ian Borsuk, P.Eng. Job No.: 3414015-000 Subject: City of Ottawa O-Train Extension Planning & EA Study

More information

FAIRFIELD INN & SUITES HOTEL 135 THAD JOHNSON PRIVATE OTTAWA TRANSPORTATION BRIEF. Prepared for:

FAIRFIELD INN & SUITES HOTEL 135 THAD JOHNSON PRIVATE OTTAWA TRANSPORTATION BRIEF. Prepared for: FAIRFIELD INN & SUITES HOTEL 135 THAD JOHNSON PRIVATE OTTAWA TRANSPORTATION BRIEF Prepared for: Bona Building & Management Co. Ltd. Place Vanier, 333 North River Road Vanier, Ontario K1L 8B9 August 12,

More information

2. Existing Conditions

2. Existing Conditions 2. Existing Conditions The existing traffic and parking conditions on the site and the surrounding area were reviewed based on the study methodology in Section 1.2. 2.1 Existing Land Use The portion of

More information

Mr. Randy Kowalchuk, President

Mr. Randy Kowalchuk, President October 20, 2017 #201, 8506-200th Street, Langley, BC V2Y 0M1 T: 604.371.0091 F: 604.371.0098 Our Reference: 31931 Naramata Benchland Properties 176 Fraser Court, Penticton, BC V2A 8B4 Attention: Mr. Randy

More information

Draft Report. Traffic Impact Study. Superstore, Wal-Mart, and Kent Development. Yarmouth, Nova Scotia. Prepared for

Draft Report. Traffic Impact Study. Superstore, Wal-Mart, and Kent Development. Yarmouth, Nova Scotia. Prepared for oad & Traffic Management Road & Traffic Management R Atlantic Traffic Engineering Specialists Draft Report Traffic Impact Study Superstore, Wal-Mart, and Kent Development Yarmouth, Nova Scotia Prepared

More information

TRAFFIC STUDY GUIDELINES Clarksville Street Department

TRAFFIC STUDY GUIDELINES Clarksville Street Department TRAFFIC STUDY GUIDELINES Clarksville Street Department 9/1/2009 Introduction Traffic studies are used to help the city determine potential impacts to the operation of the surrounding roadway network. Two

More information

Low Level Road Improvements Traffic Analysis. Report

Low Level Road Improvements Traffic Analysis. Report Low Level Road Improvements Traffic Analysis Report June, 22 Table of Contents. INTRODUCTION.... LOW LEVEL ROAD PROJECT....2 STUDY AREA....2. West-End Corridor Improvements... 2.2.2 East-End Corridor Improvements...

More information

84-88 Columbia Street West Waterloo, Ontario Transportation Impact Study. Paradigm Transportation Solutions Limited

84-88 Columbia Street West Waterloo, Ontario Transportation Impact Study. Paradigm Transportation Solutions Limited 84-88 Columbia Street West Waterloo, Ontario Transportation Impact Study Paradigm Transportation Solutions Limited June 217 Project Summary Project Number 15255 June 217 Client Masri O Inc. Architects

More information

3 ROADWAYS 3.1 CMS ROADWAY NETWORK 3.2 TRAVEL-TIME-BASED PERFORMANCE MEASURES Roadway Travel Time Measures

3 ROADWAYS 3.1 CMS ROADWAY NETWORK 3.2 TRAVEL-TIME-BASED PERFORMANCE MEASURES Roadway Travel Time Measures ROADWAYS Approximately 6 million trips are made in the Boston metropolitan region every day. The vast majority of these trips (80 to percent, depending on trip type) involve the use of the roadway network

More information

D.13 Transportation and Traffic

D.13 Transportation and Traffic This section addresses transportation and traffic issues and impacts related to the Proposed Project. Section D.13.1 provides a description of the affected environment for the Proposed Project. Applicable

More information

CITY OF OAKLAND. 27th Street Bikeway Feasibility and Design. Final Report (v3) March 23, Kimley-Horn and Associates, Inc.

CITY OF OAKLAND. 27th Street Bikeway Feasibility and Design. Final Report (v3) March 23, Kimley-Horn and Associates, Inc. CITY OF OAKLAND 27th Street Bikeway Feasibility and Design Final Report (v3) March 23, 2007 PREPARED BY: Kimley-Horn and Associates, Inc. Table of Contents 1. Introduction 3 2. 27 th Street/Bay Place Corridor

More information

Figure 1: East West Connector Alignment Alternatives Concept Drawing

Figure 1: East West Connector Alignment Alternatives Concept Drawing Page 2 of 9 Figure 1: East West Connector Alignment Alternatives Concept Drawing The Montebello Drive extension will run north south and connect Wilsonville Road to the Boones Ferry Road to Brown Road

More information

Traffic Signal Redesign 50% Design Report

Traffic Signal Redesign 50% Design Report Traffic Signal Redesign 50% Design Report Joseph Davis, Jace Elkins, Jordan Weyrauch and Zach Crimmins CENE 486 Capstone J3Z Engineering March 10 th, 2016 Table of Contents 1.0 Project Description...1

More information

Traffic Impact Study. Roderick Place Columbia Pike Thompson s Station, TN. Transportation Group, LLC Traffic Engineering and Planning

Traffic Impact Study. Roderick Place Columbia Pike Thompson s Station, TN. Transportation Group, LLC Traffic Engineering and Planning F i s c h b a c h Transportation Group, LLC Traffic Engineering and Planning Traffic Impact Study Roderick Place Columbia Pike Thompson s Station, TN Prepared March 2016 Ms. Gillian L. Fischbach, P.E.,

More information

5.3 TRAFFIC, CIRCULATION AND PARKING

5.3 TRAFFIC, CIRCULATION AND PARKING 5.3 TRAFFIC, CIRCULATION AND PARKING This section is based upon the Downtown Lancaster Specific Plan Traffic Impact Analysis (April 2, 2008) and the Downtown Lancaster Specific Plan Parking Analysis (May

More information

List of Attachments. Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections...

List of Attachments. Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections... List of Attachments Exhibits Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections... Existing Lane Geometry and Traffic Controls... Existing

More information

Traffic Impact Analysis

Traffic Impact Analysis Traffic Impact Analysis TRAFFIC IMPACT ANALYSIS FOR A PROPOSED NEIGHBORHOOD SHOPPING CENTER Civic Center Way and Cross Creek Road City of Malibu Prepared for: Goldman Firth Rossi Architects Prepared by:

More information

5858 N COLLEGE, LLC N College Avenue Traffic Impact Study

5858 N COLLEGE, LLC N College Avenue Traffic Impact Study 5858 N COLLEGE, LLC nue Traffic Impact Study August 22, 2016 Contents Traffic Impact Study Page Preparer Qualifications... 1 Introduction... 2 Existing Roadway Conditions... 5 Existing Traffic Conditions...

More information

Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC

Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC 1. TABLE OF CONTENTS INTRODUCTION...1 1.1. Site Location and Study Area...1 1.2. Proposed Land Use and Site Access...2 1.3.

More information

BLOSSOM AT PICKENS SIGNALIZED INTERSECTION IMPROVEMENT STUDY

BLOSSOM AT PICKENS SIGNALIZED INTERSECTION IMPROVEMENT STUDY BLOSSOM AT PICKENS SIGNALIZED INTERSECTION IMPROVEMENT STUDY Class Project Report for ECIV 542 Traffic Engineering Submitted by Omor Sharif Muchun Song Narges Kaveshgar Quyen Pham Chih-Yao Lin Submission

More information

BLUE SEA VILLAGE MER BLEUE 2159 MER BLEUE ROAD OTTAWA, ONTARIO TRANSPORTATION IMPACT ASSESSMENT. Prepared for: Ontario Limited.

BLUE SEA VILLAGE MER BLEUE 2159 MER BLEUE ROAD OTTAWA, ONTARIO TRANSPORTATION IMPACT ASSESSMENT. Prepared for: Ontario Limited. BLUE SEA VILLAGE MER BLEUE 2159 MER BLEUE ROAD OTTAWA, ONTARIO TRANSPORTATION IMPACT ASSESSMENT Prepared for: 2534189 Ontario Limited April 6, 2018 117-668 TIA Report_2.doc D. J. Halpenny & Associates

More information

6060 North Central Expressway Mixed-Use Site Dallas, Texas

6060 North Central Expressway Mixed-Use Site Dallas, Texas Volume 1 Traffic Impact Analysis 6060 North Central Expressway Mixed-Use Site Dallas, Texas April 30, 2018 Kimley-Horn and Associates, Inc. Dallas, Texas Project #063238300 Registered Firm F-928 Traffic

More information

3.2.2 Proposed Road Network within Phase 1B Lands

3.2.2 Proposed Road Network within Phase 1B Lands 3.2.2 Proposed Road Network within Phase 1B Lands Figure 3.1 also shows the proposed road network within the Premier Gateway Phase 1B Employment Area lands, which features two collector roads providing

More information

Troutbeck Farm Development

Troutbeck Farm Development Troutbeck Farm Development Willistown Township, Chester County PA For Submission To: Willistown Township Last Revised: October, 4 TPD# INLM.A. 5 E. High Street Suite 65 Pottstown, PA 9464 6.36.3 TPD@TrafficPD.com

More information

May 5, 2009 File:

May 5, 2009 File: MMM Group Limited Suite 600 1455 West Georgia Street Vancouver, BC V6G 2T3 t: 604-685-9381 f: 604-683-8655 www.mmm.ca May 5, 2009 File: 50-09001-007 1420 1055 West Hastings Street Vancouver, BC V6E 2E9

More information

Grant Avenue Streetscape

Grant Avenue Streetscape REPORT TYPE GOES HERE Grant Avenue Streetscape PREPARED FOR City of Manassas 9027 Center Street Manassas, VA 20110 PREPARED BY 8300 Boone Boulevard Suite 700 Vienna, Virginia 22182 571.389.8121 July 31,

More information

SELECTED ROADWAY CAPACITY ANALYSIS

SELECTED ROADWAY CAPACITY ANALYSIS CHAPTERFOUR SELECTED ROADWAY CAPACITY ANALYSIS 4.1 SELECTED ROADWAY CAPACITY ANALYSIS Introduction Capacity analysis was performed on six selected roadways within the Dearborn County study area using the

More information

J Street and Folsom Boulevard Lane Conversion Project (T ) Before and After Traffic Evaluation

J Street and Folsom Boulevard Lane Conversion Project (T ) Before and After Traffic Evaluation J Street and Folsom Boulevard Lane Conversion Project (T15125400) Before and After Traffic Evaluation Prepared by Transportation Division June 2014 Executive Summary On February 12, 2013, the City of Sacramento

More information

Traffic Impact Study Little Egypt Road Development Denver, North Carolina June 2017

Traffic Impact Study Little Egypt Road Development Denver, North Carolina June 2017 Traffic Impact Study Little Egypt Road Development Denver, North arolina June 2017 N. Little Egypt Road DQ\ QDQFLQJ VDOHV RU RWKHU SHUIRUPDQFH EDVHG FULWHULD Proposed Site Driveways Site Driveway 1 TRAFFI

More information

1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY

1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY 1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY Prepared for: The Town of Chapel Hill Public Works Department Traffic Engineering Division Prepared by: HNTB North Carolina, PC 343

More information

350 SPARKS STREET, OTTAWA HOTEL AND RESIDENTIAL DEVELOPMENT. Transportation Study. Prepared For: Morguard Real Estate Investment Trust.

350 SPARKS STREET, OTTAWA HOTEL AND RESIDENTIAL DEVELOPMENT. Transportation Study. Prepared For: Morguard Real Estate Investment Trust. SPARKS STREET, OTTAWA HOTEL AND RESIDENTIAL DEVELOPMENT Transportation Study Prepared For: Morguard Real Estate Investment Trust June, BA Consulting Group Ltd. St. Clair Avenue West, Suite Toronto, ON

More information

FINAL REPORT Traffic Analysis Report Port Coquitlam Recreation Complex Port Coquitlam, BC

FINAL REPORT Traffic Analysis Report Port Coquitlam Recreation Complex Port Coquitlam, BC FINAL REPORT Traffic Analysis Report Port Coquitlam Recreation Complex Port Coquitlam, BC Howes Technical Advantage Ltd. This report was prepared by Howes Technical Advantage Ltd. for the City of Port

More information

Proposed Addition to Pickering Islamic Centre

Proposed Addition to Pickering Islamic Centre TRAFFIC IMPACT STUDY, PARKING STUDY, SITE CIRCULATION REVIEW & TDM PLAN Proposed Addition to Pickering Islamic Centre 265 Brock Road City of Pickering, Ontario Prepared for: Pickering Islamic Centre Masjid

More information

Corporation of the Town of Oakville. December 16, 2013

Corporation of the Town of Oakville. December 16, 2013 Corporation of the Town of Oakville Transportation Impact Analysis and Parking Study for Proposed Secondary School, Oakville Draft Final Report Submitted by: HDR Corporation 100 York Boulevard, Suite 300

More information

ALLEY 24 TRAFFIC STUDY

ALLEY 24 TRAFFIC STUDY ALLEY 24 TRAFFIC STUDY in City of Frostburg, Maryland January 2013 3566 Teays Valley Road Hurricane, WV Office: (304) 397-5508 www.denniscorporation.com Alley 24 Traffic Study January 2013 Frostburg, Maryland

More information

Bistro 6. City of Barrie. Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report. Project Number: JDE 1748

Bistro 6. City of Barrie. Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report. Project Number: JDE 1748 City of Barrie Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report Project Number: JDE 1748 Date Submitted: June 12 th, 2017 06/12/17 John Northcote, P.Eng. Professional License

More information

Existing Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer

Existing Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Date: April 16 th, 2015 To: From: Re: Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Darian Nagle-Gamm, Traffic Engineering Planner Highway 6 (2 nd Street) /

More information

Traffic Study North Shore School District 112

Traffic Study North Shore School District 112 Traffic Study North Shore School District 112 Proposed Expansion of Northwood Junior High School Prepared By: May 1, 2015 1. Introduction Kenig, Lindgren, O Hara, Aboona, Inc. (KLOA, Inc.) has been retained

More information

NO BUILD TRAFFIC OPERATIONS

NO BUILD TRAFFIC OPERATIONS 3. 23 NO BUILD TRAFFIC OPERATIONS This section addresses the operations of the transportation system and details how it would be expected to function under year 23 No Build conditions with the projected

More information

TRAFFIC IMPACT ANALYSIS OF PROPOSED CHESTNUT HILL COLLEGE MASTER PLAN DEVELOPMENT

TRAFFIC IMPACT ANALYSIS OF PROPOSED CHESTNUT HILL COLLEGE MASTER PLAN DEVELOPMENT TRAFFIC IMPACT ANALYSIS OF PROPOSED CHESTNUT HILL COLLEGE MASTER PLAN DEVELOPMENT Prepared by Orth-Rodgers & Associates, Inc. December 14, 2009 Updated November 9, 2010 230 South Broad Street Philadelphia

More information

TAKOMA METRO STATION

TAKOMA METRO STATION TKOM METRO STTION Traffic nalysis Technical Memorandum Station Planning in Support of Joint evelopment Job No. 13-FQ165-LN-2 November 213 WSHINGTON METROPOLITN RE TRNSIT UTHORITY (WMT) Takoma Metro Station

More information

2136 And 2148 Trafalgar Road Townhouse Development Traffic Brief. Paradigm Transportation Solutions Limited

2136 And 2148 Trafalgar Road Townhouse Development Traffic Brief. Paradigm Transportation Solutions Limited 2136 And 2148 Trafalgar Road Townhouse Development Traffic Brief Paradigm Transportation Solutions Limited March 217 March 217 Project: 1627 Diana Vlasic, M.C.I.P., R.P.P Metropolitan Consulting 445 Paletta

More information

Traffic Impact Analysis

Traffic Impact Analysis Traffic Impact Analysis Isle of Capri Casinos, Inc. Waterloo, Iowa SEH No. A-CLAAS0501.00 November 16, 2004 Table of Contents (Continued) Table of Contents Certification Page Table of Contents Page 1.0

More information

Appendix B: Forecasting and Traffic Operations Analysis Framework Document

Appendix B: Forecasting and Traffic Operations Analysis Framework Document Existing Conditions Report - Appendix Appendix B: Forecasting and Traffic Operations Analysis Framework Document This document defines the methodology and assumptions that will be used in the traffic forecasting

More information

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Aaron Elias, Bill Cisco Abstract As part of evaluating the feasibility of a road diet on Orange Grove Boulevard in Pasadena,

More information

Technical Memorandum TRAFFIC IMPACT STUDY. RIDLEY ROAD CONVENIENCE STORE Southampton County, VA. Prepared for: Mr. David Williams.

Technical Memorandum TRAFFIC IMPACT STUDY. RIDLEY ROAD CONVENIENCE STORE Southampton County, VA. Prepared for: Mr. David Williams. Technical Memorandum TRFFIC IMPCT STUDY RIDLEY ROD CONVENIENCE STORE Southampton County, V Prepared for: Mr. David Williams By: Charles Smith, P.E., PTOE EPR Charlottesville, V July 2014 1 TBLE OF CONTENTS

More information

AMEC Earth and Environmental. Bovaird Drive Environmental Assessment. Traffic Study Final Report. August Excellence in Transportation Planning

AMEC Earth and Environmental. Bovaird Drive Environmental Assessment. Traffic Study Final Report. August Excellence in Transportation Planning AMEC Earth and Environmental Bovaird Drive Environmental Assessment Traffic Study Final Report August Excellence in Transportation Planning AMEC Earth and Environmental Bovaird Drive Class EA Traffic

More information

TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS...

TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS... TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS... IX 1 INTRODUCTION... 1 1.1 Project Overview... 1 1.2 Analysis Scenarios...

More information

Traffic Impact Study for Rolling Ridge Redevelopment

Traffic Impact Study for Rolling Ridge Redevelopment Traffic Impact Study for Rolling Ridge Redevelopment Webster Groves, Missouri October 19, 2018 Prepared For: Gershman Commercial Real Estate 150 North Meramec Avenue Suite 500 St. Louis, Missouri 63105

More information

Subject: Solberg Avenue / I-229 Grade Separation: Traffic Analysis

Subject: Solberg Avenue / I-229 Grade Separation: Traffic Analysis MEMORANDUM Transportation Bill Troe, AICP Jason Carbee, AICP 12120 Shamrock Plaza Suite 300 Omaha, NE 68154 (402) 334-8181 (402) 334-1984 (Fax) To: Project File Date: Subject: Solberg Avenue / I-229 Grade

More information

List of Exhibits...ii

List of Exhibits...ii One Brickell Traffic Study TABLE OF CONTENTS List of Exhibits...ii EXECUTIVE SUMMARY...1 1. INTRODUCTION...2 1.1 Study Area...2 1.2 Study Objective...5 2. EXISTING TRAFFIC CONDITIONS...6 2.1 Data Collection...6

More information

Project Niagara. within the Town of Niagara-on-the-Lake

Project Niagara. within the Town of Niagara-on-the-Lake Traffic Traffic Impact Impact Study Study Project Niagara within the Town of Niagara-on-the-Lake Prepared for: Project Niagara July 2009 Traffic Impact Study PROJECT NIAGARA Niagara-On-The-Lake, Ontario

More information

THE LANDMARK AT TALBOT PARK

THE LANDMARK AT TALBOT PARK TRAFFIC IMPACT STUDY FOR THE LANDMARK AT TALBOT PARK IN NORFOLK, VA INTERMODAL ENGINEERING, P.C. OCTOBER, 200 The Landmark at Talbot Park is a proposed redevelopment of the existing apartments along the

More information

TRAFFIC IMPACT STUDY

TRAFFIC IMPACT STUDY TRAFFIC IMPACT STUDY for the GLEN ELLEN COUNTRY CLUB SENIOR RESIDENTIAL REDEVELOPMENT 84 Millis, Massachusetts Prepared by: McMahon Associates, Inc. Prepared for: Toll Brothers, Inc. August 216 DRAFT

More information

CarMax Auto Superstore/ Reconditioning Center #6002 Murrieta, California

CarMax Auto Superstore/ Reconditioning Center #6002 Murrieta, California CarMax Auto Superstore/ Reconditioning Center #6002 Murrieta, California TUSTIN 17782 17th Street Suite 200 Tustin, CA 92780-1947 714.665.4500 Fax: 714.665.4501 LOS ANGELES 145 S. Spring Street Suite 120

More information

Corporate. Report COUNCIL DATE: May 25, 1998 NO: R1500 REGULAR COUNCIL. TO: Mayor & Council DATE: April 27, 1998

Corporate. Report COUNCIL DATE: May 25, 1998 NO: R1500 REGULAR COUNCIL. TO: Mayor & Council DATE: April 27, 1998 R1500 : Traffic Safety at 25 Avenue and 128 Street Intersection Corporate NO: R1500 Report COUNCIL DATE: May 25, 1998 REGULAR COUNCIL TO: Mayor & Council DATE: April 27, 1998 FROM: General Manager, Engineering

More information

Arlington Public Schools Thomas Jefferson Site Evaluation Transportation Networks. Thomas Jefferson Working Group Meeting #6 November 10, 2014

Arlington Public Schools Thomas Jefferson Site Evaluation Transportation Networks. Thomas Jefferson Working Group Meeting #6 November 10, 2014 Arlington Public Schools Thomas Jefferson Site Evaluation Transportation Networks Thomas Jefferson Working Group Meeting #6 November 10, 2014 2 3 INTRODUCTION 4 Goal of our work: Identify and assess multi-modal

More information

Intersection of Massachusetts Avenue and Maple Street in Lexington Signalized Intersection and Roundabout Comparison

Intersection of Massachusetts Avenue and Maple Street in Lexington Signalized Intersection and Roundabout Comparison Intersection of Massachusetts Avenue and Maple Street in Lexington Signalized Intersection and Roundabout Comparison Michael Wallwork, Roundabout Expert, Orange Park, Florida Tom Bertulis (MS, PE, PTOE),

More information