1 DIANE WIATR Active Transportation Coordinator/Senior Planner City of Tacoma APRIL 1, 2015 APWA CONFERENCE TIM HANSEN, PE Chief Operating Officer AHBL, Inc. Project Designer MATT PAVOLKA Project Manager Tucci and Sons, Inc. General Contractor BACKGROUND Tacoma s Mobility Master Plan (MoMaP) First adopted by Council in June 2010 Includes Pedestrian & Bicycle Design Guidelines Amended in 2012 Comprised of about 150 segments/projects Bike Boulevards Bike Lanes Sharrows Cycle Tracks Shared Use Paths Sidewalks Intersection Improvements 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 2
2 BACKGROUND Prioritization of Bike/Pedestrian Projects Connectivity / Gaps Supports inter-modal use Cost effective Destinations served Improves safety readily Motorized trip reduction 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 3 TOP 4 BIKEWAYS Representing about 10% of the build-out of the Mobility Master Plan for bicycle facilities.
3 PRIORITY 1 SEGMENT 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 5 BIKE BOULEVARDS (*) video courtesy of streetfilms.org 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 6
4 PRIORITY 2 & 4 SEGMENTS 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 7 PRIORITY 3 SEGMENT 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 8
5 WRIGHT PARK 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 9 WRIGHT PARK 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 10
6 FUNDING Planned Initial Effort: $1.05 M $500K from LTGO Bonds $200K from REET $350K from Energy Efficiency & Conservation Block Grant Effort consisted of: Sharrows, bike boulevards, bike lanes, and signing Completed in 2012 along Park Avenue 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 11 FUNDING (CONT D) Phase 2 was to consist of bike lanes & curb ramps, and was ready to advertise when Federal Discretionary Grant - $1M Pierce County Regional Council - $500K (CMAQ) Phase 2 grew to include: ~ Ten blocks of roadway upgrades Grind & overlay Complete reconstruction (3 blocks - N 24 th Street) Intersection improvements at 12 locations 40+ additional curb ramp improvements (58 total) In-roadway bike counters 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 12
7 FIRSTS FOR TACOMA 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 13 FIRSTS FOR TACOMA Bike push buttons Cross-bike 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 14
8 FIRSTS FOR TACOMA 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 15 FIRSTS FOR TACOMA Bike Counters (*) image courtesy of Eco Counter website 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 16
9 BIKE COUNTER DATA 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 17 SCOPE ELEMENTS Verify Existing Conditions Base map, field verifications, survey Ride the route!! Determine minimum improvements Safety Stakeholder interests Develop initial design, envision more If unlimited budget, what would be done? Created an a la carte menu from wish list improvements Iterated until fit the budget 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 18
10 ROUTE RECON 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 19 AFTER (1 OF 3) 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 20
11 AFTER (2 OF 3) 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 21 AFTER (3 OF 3) 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 22
12 ROUTE ASSESMENT MAP THE ROUTE USING GIS IDENTIFY BIKE BLVD vs BIKE LANE AREAS / TRAFFIC CALMING WAY FINDING SIGNAGE KEY DESTINATIONS 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 23 SHARROW VS BIKE LANE
13 SHARROW VS BIKE LANE INTERSECTIONS RIDE THE ROUTE IDENTIFY PROBLEM AREAS DEVELOP IMPROVEMENT OPTIONS AT EACH INTERSECTION COST THE OPTIONS 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 26
14 A LA CARTE PROJECT COST 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 27 DESIGN STANDARDS & REFERENCES 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 28
15 INTERSECTION TREATMENTS 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 29 PEDESTRIAN IMPROVEMENTS 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 30
16 SIGNALS AND BIKE DETECTION A project objective was improving intersections with detection or in need of detection. Types of detection: Loop tuned for bikes Video Detection Radar Pucks 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 31 SENSYS MICRORADAR (*) image courtesy of Sensys website 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 32
17 SENSYS PUCK INSTALLATION 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 33 ROAD REPAIR 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 34
18 INTERLAYER REINFORCING (*) image courtesy of Tensar Corp website 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 35 ROAD DESIGN 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 36
19 UNREINFORCED (*) image courtesy of Tensar Corp website 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 37 CONVENTIONAL GRID WITH TACK COAT 3.3 Fatigue Life Ratio (*) image courtesy of Tensar Corp website 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 38
20 GRID WITH INTEGRATED TACK COAT FILM 5.1 Fatigue Life Ratio (*) image courtesy of Tensar Corp website 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 39 CONVENTIONAL GRID WITH TACK COAT 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 40
21 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 41 VIDEO OF GLASSGRID GOING IN 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 42
22 BEFORE FINAL LIFT 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 43 COMPLETED 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 44
23 BEFORE AND AFTER 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 45 BEFORE AND AFTER 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 46
24 BEFORE AND AFTER 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 47 BEFORE AND AFTER 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 48
25 BEFORE AND AFTER 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 49 GREEN CONFLICT ZONES 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 50
26 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 52
27 BIKE COUNTER BIKE LANE 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 53 BIKE COUNTER- BIKE BLVD 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 54
28 CHALLENGES/LESSONS LEARNED? Would have been better to break the project up into smaller projects Coordinating design guidance from multiple sources Google street view saves a ton of time With so many things that can be improved, where do you stop? Historic Trees Rectangular Rapid Flash Beacons (RRFB) 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS MILES OF BIKEWAYS AND PEDESTRIAN IMPROVEMENTS 4 ped/bike-activated beacons 58 ADA curb ramps Traffic calming on Park Avenue In-street bike counters Wayfinding signage Pavement upgrades for 10 blocks 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 56
29 EDUCATION CAMPAIGN 13 MILES OF BIKEWAYS & PEDESTRIAN IMPROVEMENTS 57 ANY QUESTIONS?
Bicycle Facilities Planning
Bicycle Facilities Planning Overview Types of Cyclists Purpose for Riding Types of Facilities Bike Lanes Bicycle Boulevards Cycle Tracks Intersections Signals Signing and Marking Discussion Types of Bicyclists
More informationWatertown Complete Streets Prioritization Plan. Public Meeting #1 December 14, 2017
Watertown Complete Streets Prioritization Plan Public Meeting #1 December 14, 2017 Goals for Public Meeting Overview of MassDOT Complete Streets Funding Program Educate the community on Complete Streets
More informationACTION TRANSMITTAL No
Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: August 25, 2016 TO: FROM: ACTION TRANSMITTAL No. 2016-47 Technical Advisory Committee TAC Funding and Programming Committee
More informationBroad Street Bicycle Boulevard Design Guidelines
Broad Street Bicycle Boulevard Design Guidelines Building from the strategies introduced in the 2013 Bicycle Transportation Plan and community input received thus far, City Transportation Staff have identified
More informationCommerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue
Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue T A N Y A B R O O K S A S S I S T A N T D I R E C T O R M O B I L I T Y P L A N N I N G M O B I L I T Y A N D S
More informationAPPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016
APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of
More informationEngineering - Bicycle and Pedestrian
Capital Improvement Plan Project Summary # Bikeways Program 781,000 860,000 900,000 933,000 933,000 933,000 # Cannonball Path 1,200,000-780,000 - - - # Capital City Trail - 70,000 - - 910,000 - # Goodman
More informationBicycle + Pedestrian Connectivity Gap Analysis
Accelerated Bridge Program Bicycle + Pedestrian Connectivity Gap Analysis Tuesday, October 11 Shriners Hospital, Boston 6:30-8:00 PM Thursday, October 13 Community Rowing, Brighton 6:30-8:00 PM Tuesday,
More informationPEDESTRIAN CROSSING TREATMENTS
PEDESTRIAN CROSSING TREATMENTS BEST PRACTICES Presented by: Doug Enderson, P.E., PTOE Cody Salo, P.E. 1 PRESENTER INTRODUCTIONS Doug Enderson, P.E., PTOE Ped Crossing Experience: ADA Design-Build ADA Inventory
More informationCity of Madison: 2017 Capital Budget Capital Improvement Plan
Capital Improvement Plan Project Summary Bikeways Program 779,000 751,000 630,000 670,000 703,000 703,000 Cannonball Path 210,000 - - 730,000 - - Cap City Trail 1,140,000-360,000 - - 910,000 Ice Age Junction
More informationMEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year AGENCY CONTACT INFORMATION
MEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year 2016-2017 AGENCY CONTACT INFORMATION Agency Name: City of Livermore Date: 12/4/2017 Primary Point of Contact Name: Debbie
More informationActive Transportation Facility Glossary
Active Transportation Facility Glossary This document defines different active transportation facilities and suggests appropriate corridor types. Click on a facility type to jump to its definition. Bike
More informationCycle Track Design Best Practices Cycle Track Sections
Design Best Practices Sections It is along street segments where the separation and protection methods of cycle tracks offer more comfort than conventional bicycle lanes, and are more attractive to a wide
More informationNJDOT Complete Streets Checklist
Background The New Jersey Department of Transportation s Complete Streets Policy promotes a comprehensive, integrated, connected multi-modal network by providing connections to bicycling and walking trip
More informationCitywide Sidewalk and Crosswalk Programs
Citywide Sidewalk and Crosswalk Programs Council Meeting October 20, 2015 Presented by Rita Hu and Jamal Mahmoud Program Goals Implement the City s comprehensive plan. Provide pedestrian with safe walking
More informationEnvironment and Public Works Committee Presentation
Mixed Use Centers Complete Streets Guidelines Project Environment and Public Works Committee Presentation December 10, 2008 Project Objectives: Conduct an inter-departmental and agency process to study
More informationPublic Works and Infrastructure Committee. General Manager, Transportation Services
STAFF REPORT ACTION REQUIRED Extending the Bay Street Bicycle Lanes Date: May 16, 2013 To: From: Public Works and Infrastructure Committee General Manager, Transportation Services Wards: Toronto Centre
More informationCity of Albert Lea Policy and Procedure Manual 4.10 ALBERT LEA CROSSWALK POLICY
4.10 ALBERT LEA CROSSWALK POLICY PURPOSE: Pedestrian crosswalks are an integral part of our transportation infrastructure. To be effective and promote safety, marked crosswalks must be installed after
More informationThis page intentionally left blank.
This page intentionally left blank. COMMUNITY Coweta Community Overview Coweta Coweta, a residential community located in Wagoner County, is a suburb of Tulsa situated southeast of the metropolitan area
More informationBicycle Boulevards and Neighborhood Greenways
Bicycle Boulevards and Neighborhood Greenways Traffic Safety is Improving for Everyone 90 80 70 60 50 40 30 20 10 0 PORTLAND: TOTAL TRAFFIC FATALITIES 1986-2008 1986 1987 1988 1989 1990 1991 1992 1993
More informationCITY OF CASSELBERRY WINTER PARK DRIVE IMPROVEMENT STUDY
CITY OF CASSELBERRY WINTER PARK DRIVE IMPROVEMENT STUDY Preliminary Recommendations October 2018 2014 HDR, Inc., all rights reserved. PROJECT BACKGROUND WALKING AUDIT FINDINGS PROPOSED IMPROVEMENT CONCEPTS
More informationMPO Staff Report Technical Advisory Committee: May 10, 2017 MPO Executive Board: May 17, 2017
MPO Staff Report Technical Advisory Committee: May 10, 2017 MPO Executive Board: May 17, 2017 RECOMMENDED ACTION: Update on the NDDOT US Business 2 Project Programmed for 2019 Matter of the NDDOT US Business
More informationBicycle and Pedestrian Chapter TPP Update Overview. TAB September 20, 2017
Bicycle and Pedestrian Chapter TPP Update Overview TAB September 20, 2017 Bicycling & Walking in the Twin Cities Where are we now? The Bike-Pedestrian system Current trends New developments Where are we
More informationAppendix D: Planning Level Cost Calculator
Appendix D: Planning Level Cost Calculator Network Costs by Facility Type Facility Type Total Miles of Facility Total Number of Intersections Cost per feature or per mile Total Cost Bicycle Boulevard 52.14
More informationEMPHASIS AREA 1: PEDESTRIANS
EMPHASIS AREA 1: PEDESTRIANS A pedestrian is seriously injured or killed every 3 days on Toronto s roads. Pedestrian collisions involve any person that is not riding in a vehicle or on a bicycle. 26% OF
More informationSRTS IMPLEMENTATION COSTS
SRTS IMPLEMENTATION COSTS What Is a Estimate? A cost estimate establishes the anticipated budget required to implement the actions (the improvement projects and programs) identified in your School Travel
More informationDerby Street. Project Updates. Salem, Massachusetts
Derby Street Project Updates Salem, Massachusetts September 13, 2017 Project Limits Derby Street Project Objectives 1. Improve complete streets elements on Derby Street 2. Improve sidewalks on finger streets
More informationPRESS RELEASE San Joaquin Council of Governments
PRESS RELEASE San Joaquin Council of Governments For Immediate Release February 23, 2018 Contact: Nicole Gorham, 235-0582 gorham@sjcog.org SJCOG Board Awards $19.63 Million in Measure K Bicycle, Pedestrian,
More informationBicycle Transportation Budget Plan: Lawrence, KS
Bicycle Transportation Budget Plan: Lawrence, KS Bicycle Objectives Lawrence Planning Documents Establish a dedicated funding plan to complete the implementation of a bikeway system plan, and for maintenance
More informationProposed Bridge Street East Bicycle Lanes Public Open House Thursday, April 27, 2017
WELCOME Proposed Bridge Street East Bicycle Lanes Public Open House Thursday, April 27, 2017 Purpose of the Open House The purpose of this Open House is to gain public input on the bicycle lanes proposed
More informationPedestrian Crossing Guidelines 2016
Pedestrian Crossing Guidelines 2016 Engineering Services 1.0 Introduction and Background The City of Kingston s first Pedestrian Crossing Guidelines were approved by Council in 2008 in order to provide
More informationCity of Charlottesville Bicycle and Pedestrian Master Plan Update
City of Charlottesville Bicycle and Pedestrian Master Plan Update September 17, 2014 I. Welcome and meeting overview II. Project status update III. Network overview IV. Break-out groups Pedestrian Network
More informationGlebe Neighbourhood Cycling Plan
Glebe Neighbourhood Cycling Plan Summary of Public Comments received after June 5 th Public Information Session Comment STUDY NETWORK CS9, CS8, E, E0 CS4, E CS4 CS8 E Suggestions for alternate cycling
More informationMONTCLAIR SAFE COMPLETE STREETS IMPLEMENTATION PLAN. Monday November 13, 2017 Michael Dannemiller, Principal Engineer NV5, Inc.
MONTCLAIR SAFE COMPLETE STREETS IMPLEMENTATION PLAN Monday November 13, 2017 Michael Dannemiller, Principal Engineer NV5, Inc. PROJECT TEAM THE OFFICE OF BICYCLE AND PEDESTRIAN PROGRAMS, NEW JERSEY DEPARTMENT
More informationGuidance. ATTACHMENT F: Draft Additional Pages for Bicycle Facility Design Toolkit Separated Bike Lanes: Two-Way to One-Way Transitions
ATTACHMENT F: Draft Additional Pages for Bicycle Facility Design Toolkit Separated Bike Lanes: Two-Way to One-Way Transitions This treatment provides a transition from two-way separated bike lanes to one-way
More informationThe DC Pedestrian Master Plan
The DC Pedestrian Master Plan September 28, 2010 George Branyan Pedestrian Program Coordinator District Department of Transportation Presentation Agenda Scope of the Plan Methodology Recommendations Implementation
More informationSTATUS OF 2009 PEDESTRIAN MASTER PLAN (AS OF DECEMBER 2013)
Appendix P.1 STATUS OF 2009 PEDESTRIAN MASTER PLAN (AS OF DECEMBER 2013) The 2009 Pedestrian Master Plan establishes 21 core recommendations in three goal areas to improve pedestrian transportation in
More informationF L E T C H E R A V E N U E
Jan. 29, 2014 Introduction F L E T C H E R A V E N U E FDOT Local Agency Program (LAP) Project FPN: 428214-1-58-01 CIP 63090 Hillsborough County, Traffic Engineering, PWD Stake holders and partners are
More informationBicycle-Pedestrian Master Plan: Chapters 3 and 4 Distribution
Bicycle-Pedestrian Master Plan: Chapters 3 and 4 Distribution Finksburg Planning and Citizens Council March 22, 2018 Overview Progress Citizen Outreach Vision Chapter 3 - Existing Conditions Chapter 4
More informationClick to edit Master title style
Click to edit Master title style Public Information Meeting August 2, 2018 Town of Rotterdam Transportation Alternatives Program Main St (NYS 5S) Pedestrian/Bicycle Access Improvement Project Agenda TAP
More information@ FRIENDLY ACRES COMMUNITY MEETING
@ FRIENDLY ACRES COMMUNITY MEETING April 18, 2017 INTRODUCTIONS City of Redwood City TJKM, GATES + Associates Interns Translators AGENDA Presentation Livable Neighborhood Streets Project Background Highlight
More informationDuwamish Way-finding and CTR Report
V. North Tukwila When the North Tukwila Manufacturing and Industrial Center was designated in 1992 as part of the region s land use and transportation plan, the plan called for the area to set a light-rail
More informationSR-203 Sidewalks and Town-Wide Mobility Improvements. Town Council Presentation September 7, 2016
SR-203 Sidewalks and Town-Wide Mobility Improvements Town Council Presentation September 7, 2016 SR-203 Sidewalks and Town- Wide Mobility Improvements SR-203 Sidewalks and Appurtenances Town-Wide Mobility
More informationChapter 4: Funding and Implementation
Chapter 4: Funding and Implementation 83 84 Cost Estimating Cost estimating is an iterative process. When a project is in the conceptual stage, preliminary cost estimates are also provided conceptually,
More informationPedestrian Project List and Prioritization
To: Kyle Wagenschutz, City of Memphis CC: From: Anne Conlon and John Cock, Alta Planning + Design Date: December, 2014 Re: Project List Development (Task 3.1-3.2) and Project List Prioritization (Task
More informationHarbord Street and Hoskin Avenue Bicycle Lane Upgrades
STAFF REPORT ACTION REQUIRED and Bicycle Lane Upgrades Date: April 22, 2014 To: From: Wards: Reference Number: Public Works and Infrastructure Committee General Manager, Transportation Services 19 and
More informationArlington s Master Transportation Plan
Arlington s Master Transportation Plan The Master Transportation Plan (MTP) Adopted in eight parts Goals & Policies element and MTP Map adopted in 2007 Bicycle, Pedestrian and Demand and Systems Management
More information2018 AASHTO BIKE GUIDE
2018 AASHTO BIKE GUIDE Your presenters Jessica Fields, PE Denver Office Director Sagar Onta, PE, PTOE Denver Engineering Director 35 years of combined experience street design, transportation planning,
More informationCity of Scotts Valley CITY COUNCIL STAFF REPORT
DATE: April 19, 2017 City of Scotts Valley CITY COUNCIL STAFF REPORT AGENDA ITEM 2 DATE: 4-19-2017 TO: FROM: APPROVED: SUBJECT: Honorable Mayor and City Council Scott Hamby, Public Works Director Jenny
More information» Draft Recommendations» Discussion» Next Steps. Plan for Walking and Biking
SAC Meeting Plan #3 for September Walking and 12, Biking 2018 » Draft Recommendations» Discussion» Next Steps Plan for Walking and Biking » Stakeholder and Public Outreach» Background data collection and
More informationOmaha s Complete Streets Policy
Omaha s Complete Streets Policy (Adopted August 2015) VISION To create great places and enhance our quality of life, the City of Omaha will provide safe, accessible streets for all users. Complete Streets
More informationMajor Bike Routes 102 Avenue Workshop April 21, 2015
Major Bike Routes 102 Avenue Workshop April 21, 2015 Our Purpose Today Provide context on how Major Bike Routes fit into Edmonton s future Share information on what we heard in our last phase, and how
More informationLaurier Segregated Bike Lane Pilot Project July 2013 update
Laurier Segregated Bike Lane Pilot Project July 2013 update Presentation Overview Background Pilot Monitoring Results Mitigation Recommendations Next Steps Laurier 2 Background Laurier Avenue Segregated
More informationHennepin County Pedestrian Plan Public Comment Report
Hennepin County Pedestrian Plan Public Comment Report On May 31, 2013, the draft Hennepin County Pedestrian Plan was released for a 45-day public comment period ending July 15, 2013. The county received
More informationSafe Routes to School Action Plan Aberdeen, Idaho
Background Aberdeen, Idaho is a largely agricultural community of nearly 2,000 people and is located in the southeast portion of the state on the western edge of American Falls Reservoir. The community
More informationRolling Out New Bike Facilities Within the North Bethesda & White Flint Area
Rolling Out New Bike Facilities Within the North Bethesda & White Flint Area Rolling Out New Bike Facilities Within the North Bethesda & White Flint Area Agenda Designing for all Cyclists Background on
More informationFUNDING SOURCES CHAPTER 6
CHAPTER 6 6.1 BICYCLE 6.1.1 Local 6.1.2 Regional 6.1.3 State 6.1.4 Federal 6.1.5 Public Facilities 6.1.6 Bicycle Registration and Licensing Fees 6.1.7 Summary Table 6.1 of Bicycle Funding Sources 6 2 6.2
More informationComplete Streets Funding Program Project Prioritization Plan
Funding Program Project Prioritization Plan Location and Type Needs South Street Crosswalk Installation Stripe a new formalized crosswalk across South Street at the Anne T. Dunphy School pedestrian path
More informationBicycle and Pedestrian Advisory Committee (BPAC) November 21, 2013
Bicycle and Pedestrian Advisory Committee (BPAC) November 21, 2013 OVERALL LAND USE CONCEPT Overall Broadway Valdez District: 95.5 acres (35.1 acres right-of ways + 60.4 acres developable land) Plan Subareas:
More informationNM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County.
Transportation PRINCE WILLIAM COUNTY 2008 COMPREHENSIVE PLAN NON-MOTORIZED PLAN CONTENTS Goals, Policies, and Action Strategies Table 4 (Bike Facility Classifications and Descriptions) Table 5 (Bike Facility
More informationMeasure A Pedestrian & Bicycle Program Update. April 4, 2019 Board of Directors Agenda Item #10 (b)
Measure A Pedestrian & Bicycle Program Update April 4, 2019 Board of Directors Agenda Item #10 (b) Overview Program background Program allocations & delivery status Feature Project: California Drive Roundabout
More informationDraft North Industrial Area-Wide Traffic Plan
Summary of North Industrial and Hudson Bay Industrial Recommended Improvements Table 1. Summary of s Item Location 1 2 3 4 5 6 7 8 9 10 11 12 Millar Ave north of 51st St Super 8 Motel back lane 400 Block
More informationBuilding Great Neighbourhoods BELLEVUE AND VIRGINIA PARK
Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK This is Meeting 2 Unfortunately, some residents in Bellevue and Virginia Park received the wrong information for this public open house (Meeting
More informationWALKNBIKE DRAFT PLAN NASHVILLE, TENNESSEE EXECUTIVE SUMMARY NASHVILLE, TENNESSEE
NASHVILLE, TENNESSEE EXECUTIVE SUMMARY Executive Summary A world-class multi-modal transportation system is essential to a vibrant city and better quality of life. -Mayor Barry The WalknBike plan aims
More informationThis page intentionally left blank.
This page intentionally left blank. Community Plan Skiatook Community Overview Skiatook Skiatook is a growing city located approximately 14 miles north of downtown Tulsa with its main street, W.C. Rogers
More informationPEDESTRIAN SAFETY ASSESSMENT SR 934/NORMANDY DRIVE AND 71 Street
PEDESTRIAN SAFETY ASSESSMENT SR 934/NORMANDY DRIVE AND 71 Street PRESENTED BY MISLEIDYS LEON TRAFFIC SAFETY PROGRAM ENGINEER FLORIDA DEPARTMENT OF TRANSPORTATION (FDOT) BACKGROUND In response to citizen
More information2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE
About the Project The City of Edmonton is planning a major bike route on the southside of Edmonton. The Strathcona Bike Route will connect the communities of Strathcona, Garneau and the University area,
More informationShifting Gears for a Healthier City
Shifting Gears for a Healthier City Mississauga s Cycling Master Plan is an ambitious strategy that sets out to transform Mississauga into a city that is conducive to cycling for daily transportation needs.
More informationMAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report
Page 1 MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report August 1, 2012 MAG Project #481 Page 2 Task 6 Executive Summary and Regional Significance Report Introduction
More informationProvincetown Parking and Circulation Study
Provincetown Parking and Circulation Study March 15 th, 2016 Spring Provincetown Traffic Hearing Image courtesy of: http://i.imgur.com/rfvfkmt.jpg Presentation Outline + List of considerations + Dismissed
More informationC/CAG. Sunnybrae Elementary School Walking and Bicycling Audit. San Mateo-Foster City School District JUNE 2013
Sunnybrae Elementary School Walking and Bicycling Audit JUNE 2013 San Mateo-Foster City School District C/CAG City/County Association of Governments of San Mateo County SUNNYBRAE ELEMENTARY SCHOOL WALKING
More informationBridgewater Complete Streets Prioritization Plan and Pedestrian Safety Assessment
Bridgewater Complete Streets Prioritization Plan and Pedestrian Safety Assessment Presented by Luciano Rabito Manager of Complete Streets Presented to Bridgewater, MA Wednesday, April 26, 2017 6:30 P.M.
More informationHennepin County Bicycle and Pedestrian Planning
Hennepin County Bicycle and Pedestrian Planning 1 Value of bicycle and sidewalk systems Safety Livability Mobility Health Personal Finances Economic Sustainability Clean Air Recreation Parking and congestion
More informationIBI Group November 5, 2012
IBI Group Agenda Session 1 3:00 PM Welcome / Sign in 3:10 PM Presentation 3:30 PM Questions? 3:35 PM World Café Discussion 4:45 PM Report on top 3 ideas 4:50 PM Next Steps 5:00 PM Adjourn 2 Agenda Session
More informationProposed. City of Grand Junction Complete Streets Policy. Exhibit 10
Proposed City of Grand Junction Complete Streets Policy Exhibit 10 1 City of Grand Junction Complete Streets Policy Vision: The Complete Streets Vision is to develop a safe, efficient, and reliable travel
More informationBicycle Master Plan Goals, Strategies, and Policies
Bicycle Master Plan Goals, Strategies, and Policies Mobilizing 5 This chapter outlines the overarching goals, action statements, and action items Long Beach will take in order to achieve its vision of
More informationCoquitlam Cross-town Bike Route Improving Bicycle Facilities in a Mature Suburban Environment
Coquitlam Cross-town Bike Route Improving Bicycle Facilities in a Mature Suburban Environment Sarah Rocchi, Vice-President, Projects, Opus International Consultants (Main Presenter) Catherine Mohoruk,
More informationBasalt Creek Transportation Refinement Plan Recommendations
Basalt Creek Transportation Refinement Plan Recommendations Introduction The Basalt Creek transportation planning effort analyzed future transportation conditions and evaluated alternative strategies for
More informationComplete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER
Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets City Commission adopted a Complete Streets policy in 2012 Complete Streets are road networks that are designed for all users:
More informationOperations -- Transit From: N/A To: N/A. Improvement Type: Regionally Significant: No
Central Puget Sound Regional 2017-2020 Transportation Improvement Program Amendments and Corrections to be included in the 2017-20 STIP PSRC's Amendment 2017-08 County: King List of 17-08 Amendment Projects:
More informationCity of Novi Non-Motorized Master Plan 2011 Executive Summary
City of Novi Non-Motorized Master Plan 2011 Executive Summary Prepared by: February 28, 2011 Why Plan? Encouraging healthy, active lifestyles through pathway and sidewalk connectivity has been a focus
More informationCOMPLETE STREETS FUNDING PROGRAM
COMPLETE STREETS FUNDING PROGRAM Prepared by: MassDOT Highway Division & Office of Transportation Planning Leading the Na 1 Complete Streets Funding Program 1. Background Complete Streets Defined Complete
More informationProject Status Update
Project Status Update : Novato Boulevard, 4th & 3rd Streets, Sir Francis Drake Boulevard (3), and Miller Avenue Major roads projects target the most heavily traveled roads in Marin County for repairs,
More informationCITY OF TACOMA BICYCLE AND PEDESTRIAN TECHNICAL ADVISORY GROUP MEETING MINUTES
CITY OF TACOMA BICYCLE AND PEDESTRIAN TECHNICAL ADVISORY GROUP MEETING MINUTES DATE: February 9, 2015 GROUP MEMBERS PRESENT: OTHERS PRESENT: Aaron Knight, Dave Cook, Jennifer Halverson Kuehn, Janet Higbee,
More informationCity of Birmingham Draft Multi-modal Transportation Plan
City of Birmingham Draft Multi-modal Transportation Plan City Commission Public Hearing Monday, November 25, 2013 7:30 pm Norman Cox, PLA, ASLA The Greenway Collaborative, Inc. Ann Arbor, Michigan The
More informationREGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES
REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES November 16, 2011 Deb Humphreys North Central Texas Council of Governments Bicycle and Pedestrian Advisory Committee Snapshot of the Guide 1. Introduction
More informationLANCASTER CITY BICYCLE NETWORK
LANCASTER CITY BICYCLE NETWORK Downtown Merchants Meeting Wednesday, July 19, 2017 http://www.lancasteratp. DOWNTOWN WALKABILITY ANALYSIS What changes can be made, in the least amount of time, and for
More informationItem No. 14 Town of Atherton
Item No. 14 Town of Atherton CITY COUNCIL STAFF REPORT CONSENT AGENDA TO: THROUGH: FROM: HONORABLE MAYOR AND CITY COUNCIL GEORGE RODERICKS, CITY MANAGER MICHAEL KASHIWAGI, COMMUNITY SERVICES DIRECTOR MARTY
More informationAGENDA ITEM G-2 Public Works
AGENDA ITEM G-2 Public Works STAFF REPORT City Council Meeting Date: 12/6/2016 Staff Report Number: 16-214-CC Regular Business: Approve the Oak Grove University Crane Bike Improvement Concept Plan, authorize
More informationBike Planning: A New Day
Bike Planning: A New Day Josh Sikich, AICP, LEED AP Chicago Office Director Alta Planning + Design 312-265-0628 joshuasikich@altaplanning.com cities of all sizes are changing Illinois Bike Summit October
More informationDesigning Pedestrian Facilities for Accessibility. Module 8 Maintenance of Pedestrian Facilities and Alternate Pedestrian Access Routes in Work Zones
Designing Pedestrian Facilities for Accessibility Module 8 Maintenance of Pedestrian Facilities and Alternate Pedestrian Access Routes in s Maintenance of Accessible Features Title II (28 CFR 35.133(a))
More informationSafe Streets. City of Lake Forest Park. March 21, 2017
Safe Streets City of Lake Forest Park March 21, 2017 1 01 WELCOME 2 Agenda WELCOME WHAT IS THIS PROJECT? CONTEXT DRAFT CITYWIDE PROJECTS EXERCISE INTRODUCTION 3 02 WHAT IS THIS PROJECT? 4 WHAT IS THIS
More informationTOWN OF PARADISE VALLEY
TOWN OF PARADISE VALLEY The Paradise Valley Bicycle & Pedestrian Master Plan Planning Commission January 16, 2018 Purpose of Today s Meeting Review January 2018 draft plan Input on compliance to SOD Review
More informationBicycle and Pedestrian Planning in a Historically Car-Centric Culture: A Focus on Connectivity, Safety, & Accessibility
Bicycle and Pedestrian Planning in a Historically Car-Centric Culture: A Focus on Connectivity, Safety, & Accessibility Kate Horton and Zylavian Watley Transportation Planners Memphis MPO Date: October
More informationBicycle and Pedestrian Advisory Council May 15, 2015
Bicycle and Pedestrian Advisory Council May 15, 2015 Updates Spring Bike/Ped counts took place Tuesday May 12 Thursday, May 14 40 volunteers and locations counted across the region More than double the
More informationTRAFFIC ACTION PLAN. Laurie Meadows Neighborhood CITY OF SAN MATEO
TRAFFIC ACTION PLAN Laurie Meadows Neighborhood CITY OF SAN MATEO Draft January 2017 Table of Contents Introduction... 2 The Traffic Forum Process... 5 Neighborhood Traffic Issues... 7 Neighborhood Recommendations
More informationLynchburg District Update
Lynchburg District Update Virginia Statewide Bicycle and Pedestrian Advisory Committee Spring Meeting May 16 th, 2017 David Cook Transportation Planner, VDOT Lynchburg District Table of Contents Active
More informationTRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION
TRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION CITY OF TORONTO TRANSPORTATION SERVICES DIVISION 2016 TRAFFIC CALMING GUIDE FOR TORONTO TABLE OF CONTENTS Introduction
More informationGeneral Plan Circulation Element Update Scoping Meeting April 16, 2014 Santa Ana Senior Center, 424 W. 3rd Street, Santa Ana, CA 92701
General Plan Circulation Element Update Scoping Meeting April 16, 2014 Santa Ana Senior Center, 424 W. 3rd Street, Santa Ana, CA 92701 Meeting Agenda 1. Purpose of Scoping Meeting 2. Project Overview 3.
More informationWest Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road
West Dimond Blvd Jodhpur St to Sand Lake CSS Transportation Project Summary Municipality of Anchorage Project # 05 005 Project Manager: John Smith, P.E. (MOA PM&E) Project Administrator: Julie Makela,
More information