1 VT15 / Allen Martin Drive Intersection Scoping Study ALTERNATIVES PRESENTATION MEETING DECEMBER 19, 2016
2 Agenda Study Area Project Background Existing Conditions Identified Issues Proposed Alternatives Feedback and Discussion Next Steps The Town would like to be prepared with an approved improvement plan to hold continued developments accountable for impacts 2
3 Project Background The Town of Essex, with assistance from the CCRPC, is conducting this scoping study to evaluate existing conditions at the intersection of Allen Martin Drive and VT315 (Jericho Road). Outcomes for this study: Assessment of existing traffic and safety conditions Consideration of public input over the course of the study Development and evaluation of build alternatives: short, medium and long term Preliminary cost estimates for future engineering, admin, and construction Preferred alternatives for implementation, if warranted A clear and concise report that documents this process 3
4 Project Schedule We are here Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Project Kickoff Ex. Conditions Analysis Local Concerns Meeting Traffic Modeling M Alternatives Analysis VTrans Tech. Meeting Alternatives Presentation Final Report M M 4
5 Study Area Primary Study Area: 250$feet from VT$15 and Allen Martin Drive intersection Secondary Study Area in Purple (Saxon Hill Industrial Park) Future Thompson Drive Extension 5
6 SHIP BuildOut Potential Developable Land Lot C: 37 acres remaining PERMITTED 30 & 42 Allen Martin Drive: 180,000 SF building and 60,000 SF building 3 PERMITTED Allen Brook Development: 116 acres + 28 acres sand extraction NOT PERMITTED 6
7 Crash Review 8 Crash History in SHIP 1 May 2011 May
8 Crash Review Crash History at Study Intersection May 2011May 2016 Date Damage / Injury Road Surface Condition 01/29/16 Property Damage Only Wet Type of Collision Angle Broadside; NB3L and EB3T 09/22/15 Property Damage Only Dry Rear End; NB 06/24/15 Injury Dry Broadside; NB3L, EB3T, and WB3T 02/17/15 Property Damage Only Ice Rear End; EB 11/11/14 Property Damage Only Dry Rear End; NB 02/06/14 Property Damage Only Snow Rear End; WB; 4 cars 06/11/13 Property Damage Only Wet Rear End; WB 09/23/11 Injury Dry Rear End; WB 8
9 Local Concerns Meeting June 8, 2016 IDENTIFIED ISSUES: Rear End Crashes on VT315 Congestion on Allen Martin Drive Congestion on VT315 Speeding vehicles along VT315 Engine braking noise Uncomfortable environment for pedestrians 9
10 Alternatives
11 Alternatives to Address Identified Issues Rear-end crashes on VT-15 Congestion on Allen Martin Drive Congestion on VT Route 15 Speeding vehicles along VT-15 Engine braking noise from vehicles entering speed zone Short Term S1 Restrict Engine Braking X X S2 Extend 35 mph speed zone X X S3 Striped shoulder on VT-15 adjacent to turn lane island S4 Intersection warning sign on approach to Allen Martin Drive on VT-15 Identified Issues ("X" indicates the proposed alternative may partially address the issue) Medium Term M1 Extend green space into VT-15 near turn lane island (permanent S3) X M2 Add a WB left turn lane X X M3 Extend sidewalk along VT-15 from Sandhill Rd X X M4 Add / extend separate NB right- and left-turn lanes X M5 Widen eastbound right turn curve radius X M6 Flashing intersection beacon X X X Uncomfortable environment for pedestrians Long Term L1 Construct Allen Martin Parkway exit from VT-289 X L2 Construct Thompson Drive extension to VT-117 X L3 Intersection Control Modification: Signal X X L4 Intersection Control Modification: Roundabout X X X X L5 Construct connection to Saxon Hill Road X 11
12 Alternatives to Address Identified Issues Rear-end crashes on VT-15 Congestion on Allen Martin Drive Congestion on VT Route 15 Speeding vehicles along VT-15 Engine braking noise from vehicles entering speed zone Short Term S1 Restrict Engine Braking X X S2 Extend 35 mph speed zone X X S3 Striped shoulder on VT-15 adjacent to turn lane island S4 Intersection warning sign on approach to Allen Martin Drive on VT-15 Identified Issues ("X" indicates the proposed alternative may partially address the issue) Medium Term M1 Extend green space into VT-15 near turn lane island (permanent S3) X M2 Add a WB left turn lane X X M3 Extend sidewalk along VT-15 from Sandhill Rd X X M4 Add / extend separate NB right- and left-turn lanes X M5 Widen eastbound right turn curve radius X M6 Flashing intersection beacon X X X Uncomfortable environment for pedestrians Long Term L1 Construct Allen Martin Parkway exit from VT-289 X L2 Construct Thompson Drive extension to VT-117 X L3 Intersection Control Modification: Signal X X L4 Intersection Control Modification: Roundabout X X X X L5 Construct connection to Saxon Hill Road X 12
13 Do Nothing Alternative ISSUES ADDRESSED: None DISCUSSION: Least expensive Least impactful Does not address congestions, safety, or other identified issues RECOMMENDATION: Must be considered Estimated Cost: $0 13
14 S2: Extend Speed Zone ISSUES ADDRESSED: Engine brake noise Speeding through project area Uncomfortable pedestrian environment DISCUSSION: May address the issues, reduce severity of crashes Speed zones should be set by engineering study of the corridor RECOMMENDATION: Recommend speed study Estimated Cost: $2,000 14
15 S3: Striped Shoulder on VT15 at Island ISSUES ADDRESSED: Congestion at Allen Martin Drive Striping in 2011 (Google Streetview) DISCUSSION: Previously there; why removed? Provide improved sight distance, increased left turn storage RECOMMENDATION: Recommend to replace striping Striping in 2016 Estimated Cost: $1,500 15
16 S4: Enhanced Intersection Warning Sign ISSUES ADDRESSED: WB rear end crashes DISCUSSION: With queue detector and solar power, alert motorists to stopped traffic in roadway Not necessary if mid3 to long3 term solutions are pursued RECOMMENDATION: Recommended only if no mid to longterm solution is acceptable Estimated Cost: $15,000 16
17 M1: Extend Island into Roadway ISSUES ADDRESSED: Congestion at Allen Martin Drive DISCUSSION: Long term application of S3 Provide improved sight distance, increased left turn storage RECOMMENDATION: Initially recommended in conjunction with other mid term solutions Estimated Cost: $17,500 17
18 M2: Construct WB Left Turn Lane ISSUES ADDRESSED: WB rear end crashes Congestion on VT315 DISCUSSION: Long term application of S3 Provide improved sight distance, increased left turn storage RECOMMENDATION: Initially recommended in conjunction with other midterm solutions Estimated Cost: $390,000 18
19 M4: Extend NB Left & Right Turn Lanes ISSUES ADDRESSED: Congestion and queuing on Allen Martin Drive DISCUSSION: Allows right turning vehicles to bypass queued left turns May not be needed if long3 term alternatives are pursued RECOMMENDATION: Queueing not currently an issue; pursue if long term solutions are not developed Estimated Cost: $165,000 19
20 M5: Widen EBRight Turn Radius ISSUES ADDRESSED: Congestion on VT315 DISCUSSION: Turning trucks track into VT3 15 through OR Allen Martin Drive Will increase pavement width; may increase speed RECOMMENDATION: Redesign / improvements at intersection must account for design vehicle movements Estimated Cost: $17,350 20
21 M6: Flashing Intersection Beacon ISSUES ADDRESSED: Rear End Crashes on VT315 DISCUSSION: Could be placed on span wire with poles designed for ultimate signal (if preferred) RECOMMENDATION: Initially recommended in conjunction with other midterm solutions Estimated Cost: $50,000 21
22 L3: Intersection Control: Signal ISSUES ADDRESSED: Congestion on Allen Martin Drive DISCUSSION: Intersection control warranted with 80 acres additional development Could be phased with mid3 term improvements Acceptable operations Light / noise into neighbors RECOMMENDATION: Viable intersection control Estimated Cost: $1.5 million 22
23 L4: Intersection Control: Roundabout ISSUES ADDRESSED: Congestion on Allen Martin Drive DISCUSSION: Intersection control warranted with 80 acres additional development Turn lane widening unnecessary Generally considered safer Large impacts to fewer properties RECOMMENDATION: Viable intersection control Estimated Cost: $2.0 million 23
24 Intersection Operational Analysis
25 Operational Analysis: 2016 Scenario Volumes 25
26 Operational Analysis: 2036 Scenario Volumes 26
27 Operational Analysis: Existing Geometry DO NOTHING ALTERNATIVE 27
28 Operational Analysis: Intersection Control AM Peak Hour PM Peak Hour Movement Permitted (No Build) Projected (Build) Permitted (No Build) Projected (Build) LOS Delay LOS Delay LOS Delay LOS Delay NB Left A 9.5 B 10.9 A 9.4 A 8.9 NB Right B 10.8 B 12.7 B 12.8 C 24.5 WB Left A 5.9 B 18.0 B 12.0 C 21.3 WB Thru A 4.2 A 4.1 A 5.6 A 8.3 EB Thru A 3.3 A 3.3 A 9.1 B 16.5 EB Right A 3.2 A 3.5 A 4.8 A 7.3 Overall A 5.1 B 10.0 A 9.3 B 16.6 AM Peak Hour PM Peak Hour Movement Permitted (No Build) Projected (Build) Permitted (No Build) Projected (Build) LOS Delay LOS Delay LOS Delay LOS Delay EB A 8 B 15 A 9 B 11 WB B 11 D 26 A 6 A 8 NB A 4 A 4 A 9 C 16 Overall A 9 C 21 A 9 B 12 Traffic is highly directional 28
29 Two Alternative Paths Do Nothing is always an option Can pursue all medium term options and decide signal control mechanism at a later date Medium term options are in direction of signal Fewer medium term alternatives would be used in roundabout 29
30 Contacts COREY MACK, PE PROJECT ENGINEER SAI SAREPALLI, PE CCRPC TRANSPORTATION PLANNING ENGINEER x16 VISIT: projects/scoping/allen3martin3drive3vt153intersection3scoping3study
31 2016 Traffic Conditions: Hourly Traffic Volume VT315 / Allen Martin Drive Adjusted Hourly Traffic Volumes by Direction EB WB NB :00 AM 6:30 AM 7:00 AM 7:30 AM 8:00 AM 8:30 AM 9:00 AM 9:30 AM 10:00 AM 10:30 AM 11:00 AM 11:30 AM 12:00 PM 12:30 PM 1:00 PM 1:30 PM 2:00 PM 2:30 PM 3:00 PM 3:30 PM 4:00 PM 4:30 PM 5:00 PM Vehicles / Hour (Adjusted) Starting Time 31
32 S1: Restrict Engine Braking ISSUES ADDRESSED: Engine brake noise DISCUSSION: Legality, enforceability, and effectiveness questionable Potentially unsafe RECOMMENDATION: Not Recommended 32
33 M3: Extend Sidewalk Along VT15 ISSUES ADDRESSED: Excessive Speed Pedestrian Environment DISCUSSION: Streetscape enhancement may impact perception of road High3priority segment RECOMMENDATION: Conduct scoping study for sidewalk and gateway treatment Existing Sidewalk Proposed Sidewalk 33
34 L1: Allen Martin Parkway / VT289 Intersection ISSUES ADDRESSED: Congestion on Allen Martin Drive DISCUSSION: Most SHIP traffic would use this intersection Increase WB left turns from VT315 Not regionally feasible RECOMMENDATION: Not recommended 34
35 L2: Thompson Drive Extension to VT 117 ISSUES ADDRESSED: Congestion on Allen Martin Drive DISCUSSION: Would not remove traffic from study intersection Not economically feasible for developer RECOMMENDATION: Not recommended Town may wish to retain ROW for future road development 35
36 L5: Saxon Hill Road Connection ISSUES ADDRESSED: Congestion on Allen Martin Drive DISCUSSION: Unlikely to remove traffic from study intersection Require significant investment Create potential traffic impacts through bike network RECOMMENDATION: Not recommended 36
TECHNICAL MEMO #1 EXISTING CONDITIONS
TECHNICAL MEMO #1 EXISTING CONDITIONS TO: FROM: Sai Sarepalli, PE (CCRPC) Corey Mack, PE Roxanne Meuse, EIT CC: DATE: December 15, 2016 SUBJECT: Allen Martin Drive and VT(15 Intersection Scoping Study
More informationAlbany Shaker Road Corridor Study Public Meeting # 2
Albany Shaker Road Corridor Study Public Meeting # 2 Scope / Meeting Purpose This project is a CDTC Linkage Study. The Linkage Program is designed to implement the adopted planning and investment principles
More informationTRANSPORTATION FACILITY PLANNING Waugh Chapel Road Maytime Drive to New Market Lane
July 24, 2018 TRANSPORTATION FACILITY PLANNING Waugh Chapel Road Maytime Drive to New Market Lane DPWandYOU.com Making a difference, together Meeting Agenda Purpose of the project Overview of work conducted
More informationTransportation Planning Division
Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meetings Data Collected Focus Areas within Study Limits Design Principles Tool Box Recommended Concepts Schedule Moving
More informationTruck Climbing Lane Traffic Justification Report
ROUTE 7 (HARRY BYRD HIGHWAY) WESTBOUND FROM WEST MARKET STREET TO ROUTE 9 (CHARLES TOWN PIKE) Truck Climbing Lane Traffic Justification Report Project No. 6007-053-133, P 101 Ι UPC No. 58599 Prepared by:
More informationCaltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns
Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns Revised: May 10, 2016 The California Department of Transportation (Caltrans) is planning various
More informationTraffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC
Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC 1. TABLE OF CONTENTS INTRODUCTION...1 1.1. Site Location and Study Area...1 1.2. Proposed Land Use and Site Access...2 1.3.
More informationTraffic Impact Study WestBranch Residential Development Davidson, NC March 2016
Traffic Impact Study WestBranch Residential Development Davidson, NC March 216 TRAFFIC IMPACT STUDY FOR THE WestBranch Residential Development LOCATED IN DAVIDSON, NC Prepared For: Lennar Carolinas, LLC
More informationDEPARTMENT OF ENVIRONMENTAL SERVICES. North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis. Prepared for:
DEPARTMENT OF ENVIRONMENTAL SERVICES North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis Prepared for: Arlington County Department of Environmental Services 2100 Clarendon Boulevard,
More informationFinancial Project ID No(s).: and ETDM No(s).: and 14181
Palm Beach Metropolitan Planning Organization (MPO) Presentation I-95 at Boynton Beach Boulevard Interchange and I-95 at Gateway Boulevard Interchange Project Development and Environment Study Palm Beach
More informationORANGE COUNTY PUBLIC WORKS TRAFFIC INVESTIGATIONS
ORANGE COUNTY PUBLIC WORKS TRAFFIC INVESTIGATIONS STAFF REPORT OF: January 6, 2019 SUPERVISORIAL DISTRICT: 5 SUBJECT: LOCATION: INVESTIGATOR: O Neill Drive at Roanoke Drive; Ladera Ranch; TB 922-E6 Clever
More informationSR 693 (Pasadena Avenue) Corridor Study from Shore Drive South to 66 th Street
Welcome and Introduction Sign-in and comment sheets Restrooms and exits Meeting agenda and timeline Meeting goals / expectations Provide input to guide study recommendations Actively participate throughout
More informationRichmond-Adelaide Cycle Tracks
Public Drop-In Event Richmond-Adelaide Cycle Tracks June 25, 2018 12:00 p.m. 3:00 p.m. 4:30 p.m. 7:30 p.m. Metro Hall, Rotunda 55 John Street 1 Purpose of Event In Scope Communicate an update about the
More informationHSM PREDICTIVE METHODS IN PRELIMINARY ENGINEERING
HSM PREDICTIVE METHODS IN PRELIMINARY ENGINEERING 2017 ILLINOIS THE CONFERENCE Filiberto Sotelo & Steven Schilke, P.E. OUTLINE Safety & Transportation Management Process What is HSM? Illinois HSM Predictive
More informationMEMORANDUM. DATE March 1, 2012 TO Town of Milton Mark Abbott, Seth Asante, and Efi Pagitsas Boston Region MPO Staff
MEMORANDUM DATE March 1, 212 TO Town of Milton FROM RE Mark Abbott, Seth Asante, and Efi Pagitsas Boston Region MPO Staff FFY 211 Safety and Operations Analyses at Selected Boston Region MPO Intersections:
More informationColchester/Riverside/Barrett/ Mill Intersection Study. PAC Meeting #3 September 22, 2016
Colchester/Riverside/Barrett/ Mill Intersection Study PAC Meeting #3 September 22, 2016 Tonight s Agenda Review Project Purpose and Need Describe short term and long improvements and changes since public
More informationWashington St. Corridor Study
FIGURE 7.17 Bridge Alternatives - Cross Sections 86 Discarded Alternative: Short-Term Bridge Repair Short-term repairs and west bridge span replacement were considered during analysis. Short-term repairs
More informationFreeway ramp intersection study
Freeway ramp intersection study Supporting Vision Zero: Zero traffic deaths in San Francisco by 2024 Study Goals: Primary Improve Safety Improve Accessibility Secondary Provide Efficient Circulation Accommodate
More informationWelcome! San Jose Avenue Open House August 25, 2015
Welcome! San Jose Avenue Open House August 25, 2015 Vision Zero The City and County of San Francisco adopted Vision Zero San Francisco Vision Zero High Injury Network as a policy in 2014, committing an
More informationHard Shoulder Running is a valuable tool July 14, Dean H. Gustafson, PE, PTOE State Operations Engineer VDOT Operations Division
Hard Shoulder Running is a valuable tool July 14, 2016 Dean H. Gustafson, PE, PTOE State Operations Engineer VDOT Operations Division Virginia 2 VDOT s Statewide Operations Program Operations Statistics
More informationShockoe Bottom Preliminary Traffic and Parking Analysis
Shockoe Bottom Preliminary Traffic and Parking Analysis Richmond, Virginia August 14, 2013 Prepared For City of Richmond Department of Public Works Prepared By 1001 Boulders Pkwy Suite 300, Richmond, VA
More informationGlenn Avenue Corridor Traffic Operational Evaluation
Glenn Avenue Corridor Traffic Operational Evaluation PREPARED FOR: THE CITY OF AUBURN PREPARED BY: DECEMBER 2007 Glenn Avenue Corridor Study--Auburn, Alabama TABLE OF CONTENTS Introduction... 1 Background
More informationTown of Bethlehem. Planning Assessment. Bethlehem Town Board
Town of Bethlehem US 9W Corridor Transportation Planning Assessment Presented e to: Bethlehem Town Board June 2009 Overview Study Background Route 9W Corridor Conditions and Improvements Selkirk Bypass
More informationBalancing Operation & Safety for Motorized and Non-Motorized Traffic
Balancing Operation & Safety for Motorized and Non-Motorized Traffic Brian Willham, PE, PTOE Iowa Director - MOVITE June 30, 2014 Learning Objectives: When & Why should we measure the performance of complete
More informationWELCOME. City of Eden Prairie West 70 th Street
WELCOME City of Eden Prairie West 70 th Street Project Schedule Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug >>> May WEST SEGMENT Concept Plan Fall 2014 Plan Development Winter 2014 Summer 2015 Construction
More informationRoute 29 Solutions Projects
Route 29 Solutions Route 29 Solutions Projects www.route29solutions.org October 10, 2014 Route 29 Widening to Six Lanes Albemarle County This project will widen a 1.8-mile segment of Route 29 from four
More informationRoute 28 (South Orleans Road)/Route 39 (Harwich Road)/Quanset Road Intersection
TRAFFIC FEASIBILITY STUDY Route 28 (South Orleans Road)/Route 39 (Harwich Road)/Quanset Road Intersection Orleans, Massachusetts Prepared for: Town of Orleans Prepared by: Fay, Spofford & Thorndike, LLC
More informationOrg Chart. Steering. Committee. Project Advisory. Committee. Nicole Losch, PTP Senior Transportation. Bryan Davis, AICP Senior Transportation
1 Org Chart Project Advisory Committee Steering Committee Nicole Losch, PTP Senior Transportation Planner Bryan Davis, AICP Senior Transportation Planner Jonathan Slason, PE Project Manager Diane Meyerhoff
More informationPublic Information Meeting. Orange Camp Road. Dr. Martin Luther King Jr. Beltway to I-4. Presented by: Volusia County August 2, 2018
Public Information Meeting Orange Camp Road Dr. Martin Luther King Jr. Beltway to I-4 Presented by: Volusia County August 2, 2018 1 Project Goals To improve the operations and safety for Orange Camp Road
More informationLeague City Parkway at Brittany Lakes/Fennigan Intersection Evaluation/ Traffic Study. Second Public Meeting February 6, 2018
League City Parkway at Brittany Lakes/Fennigan Intersection Evaluation/ Traffic Study Second Public Meeting February 6, 2018 City Project Information League City Parkway and Brittany Lakes Dr./ Fennigan
More informationCity of Moorhead Committee of the Whole Meeting
City of Moorhead Committee of the Whole Meeting Corridor Study Limits Center Avenue (Red River to 8th Street) TH 10 (Red River to TH 336) TH 75 (20th Ave S to Main Avenue) 2 Study Need: Project Overview
More informationCity of Wilsonville 5 th Street to Kinsman Road Extension Project
City of Wilsonville 5 th Street to Kinsman Road Walking Tour & Neighborhood Workshop Summary Report Public Outreach Overview On July 18 th, 2017, the City of Wilsonville hosted a neighborhood walking tour
More informationBoston Post Road Design Feasibility Study
Boston Post Road Design Feasibility Study Prepared for the City of Rye Final Report July 18, 2007 Prepared by: Buckhurst Fish & Jacquemart (BFJ) 115 Fifth Avenue New York, NY 10003 www.bfjplanning.com
More informationSouthside Road. Prepared for: City of St. John s Police & Traffic Committee. Prepared by: City of St. John s Traffic Division
Southside Road Prepared for: City of St. John s Police & Traffic Committee Prepared by: City of St. John s Traffic Division January 2007 Southside Road - Traffic Report Page 1 of 9 BACKGROUND: th At the
More informationSouthview Blvd & 3 rd Avenue Improvement Project. Public Open House December 4, to 7pm
Southview Blvd & 3 rd Avenue Improvement Project Public Open House December 4, 2014 5 to 7pm Southview Blvd & 3 rd Avenue Public Information Meeting Agenda Presentation 5:30 to 6:15 pm Purpose of Project
More informationAGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive
AGENDA REPORT To: From: By: Honorable Mayor and City Council Members Warren Hutmacher, City Manager Tom Black, Public Works Director Date: March 23, 2016 Agenda: March 28, 2016 WORK SESSION AGENDA: Barnwell
More informationPearl Street / Prospect Street / Colchester Avenue Intersection Scoping Study. April 11, 2013 Steering Committee Meeting #3
Pearl Street / Prospect Street / Colchester Avenue Intersection Scoping Study April 11, 2013 Steering Committee Meeting #3 Meeting Agenda Welcome & Introductions Review Project Purpose & Needs Results
More informationMarch 11, Lynnfield Board of Selectmen Town of Lynnfield 55 Summer Street Lynnfield, MA Walnut Street Traffic Assessment
March 11, 2015 Lynnfield Board of Selectmen Town of Lynnfield 55 Summer Street Lynnfield, MA 01940 Re: Walnut Street Traffic Assessment Dear Board of Selectmen Members: As requested, BETA Group, Inc. (BETA)
More informationArterial Management Plan for US Route 250 and State Route 623
Arterial Management Plan for US Route 250 and State Route 623 June 25, 2014 Brad Shelton, AICP Access Management and Traffic Impact Analysis Programs Manager Transportation and Mobility Planning Division
More informationProgress Report on the Design and Planning of an Infrastructure Improvement Project for the Sunnyside TIF District (Phase II)
Presentation to the CNRC Board of Directors Regular Meeting March 11, 2015 1 Agenda Preferred Alternate Refinement for University Avenue, 3rd Street, and Beverly Avenue Intersection Improvements validate
More informationTransportation Planning Division
Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meeting Stakeholder Interviews Data Collection Design Principles Tool Box Recommendations Schedule Moving Forward North
More informationTraffic Impact Analysis Chatham County Grocery Chatham County, NC
Chatham County Grocery Chatham County, NC TABLE OF CONTENTS 1. INTRODUCTION... 1 1.1. Location and Study Area... 1 1.2. Proposed Land Use and Access... 2 1.3. Adjacent Land Uses... 2 1.4. Existing ways...
More informationMineral Avenue Corridor Assessment. ITE 2017 Western District Annual Meeting San Diego, CA June 21 st
Mineral Avenue Corridor Assessment ITE 2017 Western District Annual Meeting San Diego, CA June 21 st Biography - Aaron Heumann, PE, PTOE Currently City of Littleton Transportation Engineering Manager 24
More informationNORTH WILLISTON ROAD SCOPING STUDY
DRAFT REPORT NORTH WILLISTON ROAD SCOPING STUDY 2.9.2018 180 Battery Street, Suite 350 Burlington, VT 05401 802.383.0118 www.rsginc.com PREPARED FOR: TOWN OF WILLISTON CHITTENDEN COUNTY PLANNING COMMISSION
More information91 Express Lanes Model Update 2006 State Route 91 Implementation Plan. Gerald V. Nielsten May 18, 2007
91 Express Lanes Model Update 2006 State Route 91 Implementation Plan Gerald V. Nielsten May 18, 2007 1 Vollmer Associates LLP is now Stantec Inc. Stantec Inc. completed the acquisition of Vollmer Associates
More informationBicycle Crashes. Number of Bike Crashes. Total Bike Crashes. are down 21% and severe bike crashes down 8% since 2013 (5 years).
Bicycle Crashes The City of Fort Collins is well known for its bike culture, and there is a strong focus on encouraging increased riding. Bike safety is an important component of supporting these efforts.
More information2015 Data review. Capturing Ready Lane NEXUS vehicles
2015 Data review Capturing Ready Lane NEXUS vehicles Problem: NEXUS users make up the majority of traffic using the Ready Lane, but they are currently considered either standard traffic or Ready Lane traffic.
More informationPrinceton Avenue and Spruce Street Transportation and Site Access Enhancements Project
Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Mercer County Planning Division AECOM Transportation (formerly DMJM Harris) January 29, 2009 Agenda Project Status
More informationWISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING. March 28, 2017
WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING March 28, 2017 STUDY AREA N MEETING AGENDA Introductions Study Background Alternatives Studied Recommended Alternative Discussion STUDY BACKGROUND
More informationCity of Albert Lea Policy and Procedure Manual 4.10 ALBERT LEA CROSSWALK POLICY
4.10 ALBERT LEA CROSSWALK POLICY PURPOSE: Pedestrian crosswalks are an integral part of our transportation infrastructure. To be effective and promote safety, marked crosswalks must be installed after
More informationComplete Streets Chicago: Data Driven Design. Luann Hamilton Deputy Commissioner
Complete Streets Chicago: Data Driven Design Luann Hamilton Deputy Commissioner AGENDA Chicago s goals Complete Streets & Sustainable Infrastructure Guides Data-Driven Planning Setting goals Scoping/research
More informationOrange County Rail-Highway Grade Crossing Safety Enhancement Program. City of San Juan Capistrano April 17, 2012
Orange County Rail-Highway Grade Crossing Safety Enhancement Program City of San Juan Capistrano April 17, 2012 Orange County Rail-Highway Grade Crossing Safety Enhancement Program (OCX) 52 crossings 8
More informationNorth Avenue Corridor Study
North Avenue Corridor Study City Council October 6, 2014 Presentation Outline Project Initiation & Process Corridor Conditions & Issues Vision & Goals Concept Development - Development/Evaluation Implementation
More informationCITY OF FRANKLIN, TENNESSEE. Columbia Avenue. Widening & Improvements Project. Public Meeting May 16, 2017
CITY OF FRANKLIN, TENNESSEE Columbia Avenue Widening & Improvements Project Public Meeting May 16, 2017 Agenda 6:00 6:30 Formal Presentation 6:30 8:00 Town Hall Forum City of Franklin Columbia Avenue Alternatives
More informationRoute 29 Corridor Assessment Update. Development of Possible Solutions
Route 29 Corridor Assessment Update Development of Possible Solutions Public Workshop #3 October 27, 2016 Purpose of Developing Possible Solutions Recap of where we ve been and timeline for moving forward
More informationProject Advisory Group (PAG) Meeting #2 January 31, SR 693 (Pasadena Avenue) Corridor Study from Shore Drive South to 66 th Street
Project Advisory Group (PAG) Meeting #2 January 31, 2018 Welcome & Introductions AGENDA 1. Where are we at? 2. Project Survey / Virtual Comment Tool / PAG Meeting #1 / Visioning Workshop Corridor Map Exercise
More informationROAD SAFETY AUDIT. Granite Avenue at Interstate 93 Ramps. Town of Milton. May 22, Prepared for: MassDOT
ROAD SAFETY AUDIT Granite Avenue at Interstate 93 Ramps Town of Milton May 22, 2017 Prepared for: MassDOT Prepared by: Toole Design Group 2 Oliver Street, Suite 305 Boston, MA 02109 Table of Contents Background...
More informationRoundabout Evaluations in Virginia: US 15/US 50 Gilberts Corner, VA SR 106/SR 634 Prince George County, VA
Roundabout Evaluations in Virginia: US 15/US 50 Gilberts Corner, VA SR 106/SR 634 Prince George County, VA VDOT & FHWA Roundabout Workshop September 17, 2013 Chris Tiesler, PE Presentation Outline US 15/US
More informationLos Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation
Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto
More informationTrial Restriping Project. October 21, 2010
Arastradero Road Trial Restriping Project P t C t ti C it O t hm ti N 1 Post Construction Community Outreach Meeting No. 1 October 21, 2010 Agenda Staff Introductions Project Background Project Status
More informationBistro 6. City of Barrie. Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report. Project Number: JDE 1748
City of Barrie Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report Project Number: JDE 1748 Date Submitted: June 12 th, 2017 06/12/17 John Northcote, P.Eng. Professional License
More informationCommunity Advisory Committee
Community Advisory Committee Meeting #1 November 19, 2014 Presentation Team Matt Fulda, Greater Bridgeport Regional Council Chris Granatini, P.E., Tighe & Bond Craig Yannes, P.E., PE PTOE, Tighe & Bond
More informationIntersection Improvement: Sturgeon Road, Silver Avenue and Murray Park Road Roundabout. Welcome. Public Information Session
Intersection Improvement: 1 Welcome WHY IS AN INTERSECTION IMPROVEMENT NEEDED? 2 Traffic volumes for Sturgeon Road, Silver Avenue and Murray Park Road exceed the capacity of the existing 4-way stop controlled
More information54 th Avenue North Complete Streets Concept Plan
54 th Avenue North Complete Streets Concept Plan June 2018 TABLE OF CONTENTS Introduction and Purpose...1 Existing Conditions...5 Stakeholder and Public Outreach...15 Preferred Options West Segment...19
More informationBlair Park Traffic Calming Study
Blair Park Traffic Calming Study Williston, Vermont Prepared for: Chittenden County Regional Planning Commission Town of Williston, Vermont Prepared by: Stantec Consulting Services Inc. 55 Green Mountain
More informationSummary: Mercer County Princeton Avenue & Spruce Street Study January 2009
Summary: Several recent studies have assessed potential development and redevelopment opportunities in the Mercer Crossing area of Trenton, Ewing, and Lawrence. This Princeton Avenue and Spruce Street
More informationSTANLEY STREET December 19, 2017
STANLEY STREET December 19, 2017 Welcome Mike Wiza, Mayor Scott Beduhn, Director of Public Works Agenda 1. Introduction 2. Existing Roadway Conditions 3. Current Alternative Improvements 4. Summary of
More information180 Grand Avenue, Suite x117 Dowling Associates, Inc.
180 Grand Avenue, Suite 250 510.839.1742 x117 Oakland, CA 94612 510.839.0871 fax www.dowlinginc.com mbowman@dowlinginc.com Dowling Associates, Inc. Date: Memorandum To: CC: From: Ms. Leah Greenblat City
More informationExisting Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer
Date: April 16 th, 2015 To: From: Re: Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Darian Nagle-Gamm, Traffic Engineering Planner Highway 6 (2 nd Street) /
More informationNewport City Thoroughfare Plan
Newport City Thoroughfare Plan Summary This plan is intended to review and make recommendations for Newport City s thoroughfare network, in consideration of the full range of uses of the city s streets.
More informationRoad Diets. Presented by: Cristine Gowland, P.E. LADOTD District 62 March 2, 2016
Road Diets Presented by: Cristine Gowland, P.E. LADOTD District 62 March 2, 2016 FHWA s 9 Proven Safety Countermeasures 1. Safety Edge 2. Roundabouts 3. Corridor Access Management 4. Backplates with Retroreflective
More informationAGENDA ITEM 6 D THOMASVILLE ROAD (HERMITAGE BOULEVARD TO LIVE OAK PLANTATION ROAD) ROADWAY SAFETY AUDIT
May 15, 2018 AGENDA ITEM 6 D THOMASVILLE ROAD (HERMITAGE BOULEVARD TO LIVE OAK PLANTATION ROAD) ROADWAY SAFETY AUDIT TYPE OF ITEM: Discussion STATEMENT OF ISSUE The Florida Department of Transportation
More informationGiles Run Connector Road
Giles Run Connector Road Laurel Hill Adaptive Reuse Area to Laurel Crest Drive South County Federation Meeting June 14, 2016 History Connector road included in the Laurel Hill Comprehensive Plan amendment
More informationDOT Policy and Procedure Integrity Excellence Respect
DOT Policy and Procedure 05.05.020 Integrity Excellence Respect Alaska s Speed Limit Policy Contained in DOT Policy and Procedure (P&P) 05.05.020, Establishment of Speed Limits and Zones Incorporates pertinent
More informationEvaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation
Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation City of Hillsdale, Hillsdale County, Michigan June 16, 2016 Final Report Prepared for City of Hillsdale 97 North Broad
More informationMain-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation
Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation APRIL 2016 A collaborative study between: For Additional Information or to Comment If you would like additional
More information5. RUNNINGWAY GUIDELINES
5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved
More informationDUNBOW ROAD FUNCTIONAL PLANNING
DUNBOW ROAD FUNCTIONAL PLANNING Final Report August 3, 216 #31, 316 5th Avenue NE Calgary, AB T2A 6K4 Phone: 43.273.91 Fax: 43.273.344 wattconsultinggroup.com Dunbow Road Functional Planning Final Report
More informationTRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION
TRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION Transportation Consultants, LLC 1101 17 TH AVENUE SOUTH NASHVILLE, TN 37212
More informationDeveloping Bikeways in South Denver
Developing Bikeways in South Denver Southeast Denver, Council District 4 October 24, 2018 1 Denver Moves: Bicycles Citywide Bikeway Master Plan: 2011 2015 State of the practice Enhanced Bikeways (2015)
More informationWalton Acres at Riverwood Athletic Club Clayton, North Carolina
9. CONCLUSIONS This Traffic Impact Analysis Update was conducted to determine the potential traffic impacts of the proposed Walton Acres at Riverwood Athletic Club residential development, located east
More informationPROJECT OBJECTIVES. Improve vehicle capacity for the intersection. Improve pedestrian and bicycle access
COMMUNITY MEETING Project Update March 15, 2010 Purcellville, Virginia OVERVIEW Project need / objectives Project recap Design elements Proposed improvements Summary of project benefits / next steps PROJECT
More informationTraffic Impact Study Little Egypt Road Development Denver, North Carolina June 2017
Traffic Impact Study Little Egypt Road Development Denver, North arolina June 2017 N. Little Egypt Road DQ\ QDQFLQJ VDOHV RU RWKHU SHUIRUPDQFH EDVHG FULWHULD Proposed Site Driveways Site Driveway 1 TRAFFI
More informationProject Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015
Meadows Place, TX October 9, 2015 Contents 1 Introduction... 1 2 Data Collection... 1 3 Existing Roadway Network... 2 4 Traffic Volume Development... 2 5 Warrant Analysis... 3 6 Traffic Control Alternative
More informationRetrofitting Urban Arterials into Complete Streets
Retrofitting Urban Arterials into Complete Streets John N. LaPlante, P.E., P.T.O.E., T.Y. Lin International Prepared for: Illinois Traffic Engineering & Safety Conference Urbana, Illinois October 18, 2007
More informationSTILLWATER AVENUE CORRIDOR STUDY Old Town, Maine
Draft Study STILLWATER AVENUE CORRIDOR STUDY Old Town, Maine SUBMITTED TO: BANGOR AREA COMPREHENSIVE TRANSPORTATION SYSTEM SUBMITTED BY: I MAY 23, 2017 DRAFT STILLWATER AVENUE STUDY FINAL REPORT Table
More informationCITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM
CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM Date: April 1, 219 To: Honorable City Council c/o City Clerk, Room 395, City Hall Attention: Honorable Mike Bonin, Chair, Transportation Committee From:
More informationReference number /VP. Lafayette Downtown Congestion Study - Additional Traffic Analysis
To James Hinkamp and Tony Coe, City of Lafayette Date January 19, 2017 Copies Reference number 243381/VP From Michael Iswalt and Vanessa Peers File reference 4-05 Subject Lafayette Downtown Congestion
More informationTraffic Study of Fuller Street, Cady Street, West Street and West Avenue. Final Report
Traffic Study of Fuller Street, Cady Street, West Street and West Avenue Final Report July 2005 Prepared for: Town of Ludlow Prepared by: Pioneer Valley Planning Commission 26 Central Street West Springfield,
More informationDr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018
Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 What s Happening The City plans to mill and resurface Dr. M.L.
More informationDate: September 7, Project #: Re: Spaulding Youth Center Northfield, NH Property. Traffic Impact Study
To: Ms. Susan C. Ryan Spaulding Youth Center 72 Spaulding Road Northfield, NH 03276 Date: September 7, 2017 Project #: 52455.00 From: Robin Bousa Director of Transportation Systems Re: Spaulding Youth
More informationData Analysis February to March Identified safety needs from reported collisions and existing travel patterns.
Welcome! Thank you for participating in today s Valencia Bikeway Improvements workshop. Data Analysis February to March Identified safety needs from reported collisions and existing travel patterns. Initial
More informationDonahue Drive Corridor Traffic Operational Evaluation
Donahue Drive Corridor Traffic Operational Evaluation PREPARED FOR: THE CITY OF AUBURN PREPARED BY: JANUARY 2007 Donahue Drive Corridor Study--Auburn, Alabama TABLE OF CONTENTS Introduction... 1 Background
More informationM-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016
M-58 HIGHWAY ACCESS MANAGEMENT STUDY Prepared for CITY OF BELTON By May 2016 Introduction Missouri State Highway 58 (M-58 Highway) is a major commercial corridor in the City of Belton. As development has
More informationLas Tunas Downtown Revitalization City Council Study Session. December 1, :00 p.m. Live Oak Park Community Center
Las Tunas Downtown Revitalization City Council Study Session December 1, 2015 7:00 p.m. Live Oak Park Community Center AGENDA 2 Provide downtown context. Confirm project goals. Analyze three design concepts.
More informationOttawa Beach Road Study
Ottawa Beach Road Study Prepared For: Park Township September 30, 2014 Project No. G140303 OTTAWA BEACH ROAD STUDY PREPARED FOR: PARK TOWNSHIP SEPTEMBER 30, 2014 PROJECT NO. G140303 TABLE OF CONTENTS 1.0
More informationTerwillegar Drive Expressway Draft Concept Plan
Terwillegar Drive Expressway Draft Concept Plan Anthony Henday Drive to Whitemud Drive November 28 5:00-8:00 p.m. December 1 10:00 a.m. - 3:00 p.m. Let s Talk Today you can: Learn about the new direction
More informationINTERSECTION SAFETY STUDY State Route 57 / Seville Road
INTERSECTION SAFETY STUDY State Route 57 / Seville Road City of Wadsworth, Medina County, Ohio Prepared For: City of Wadsworth Engineering Department 120 Maple Street Wadsworth, OH 44281 Prepared By: GPD
More informationInterstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project. Prepared September 6, 2017
EODOT Project: ODOT Project: STA-IR 77-.50; PID 00290 Interstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project Summary of Public Comments Received and Responses
More informationMunicipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018
Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Background Agenda Traffic Study Update Class EA Alternatives Bridge