VT15 / Allen Martin Drive Intersection Scoping Study

Size: px
Start display at page:

Download "VT15 / Allen Martin Drive Intersection Scoping Study"

Transcription

1 VT15 / Allen Martin Drive Intersection Scoping Study ALTERNATIVES PRESENTATION MEETING DECEMBER 19, 2016

2 Agenda Study Area Project Background Existing Conditions Identified Issues Proposed Alternatives Feedback and Discussion Next Steps The Town would like to be prepared with an approved improvement plan to hold continued developments accountable for impacts 2

3 Project Background The Town of Essex, with assistance from the CCRPC, is conducting this scoping study to evaluate existing conditions at the intersection of Allen Martin Drive and VT315 (Jericho Road). Outcomes for this study: Assessment of existing traffic and safety conditions Consideration of public input over the course of the study Development and evaluation of build alternatives: short, medium and long term Preliminary cost estimates for future engineering, admin, and construction Preferred alternatives for implementation, if warranted A clear and concise report that documents this process 3

4 Project Schedule We are here Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Project Kickoff Ex. Conditions Analysis Local Concerns Meeting Traffic Modeling M Alternatives Analysis VTrans Tech. Meeting Alternatives Presentation Final Report M M 4

5 Study Area Primary Study Area: 250$feet from VT$15 and Allen Martin Drive intersection Secondary Study Area in Purple (Saxon Hill Industrial Park) Future Thompson Drive Extension 5

6 SHIP BuildOut Potential Developable Land Lot C: 37 acres remaining PERMITTED 30 & 42 Allen Martin Drive: 180,000 SF building and 60,000 SF building 3 PERMITTED Allen Brook Development: 116 acres + 28 acres sand extraction NOT PERMITTED 6

7 Crash Review 8 Crash History in SHIP 1 May 2011 May

8 Crash Review Crash History at Study Intersection May 2011May 2016 Date Damage / Injury Road Surface Condition 01/29/16 Property Damage Only Wet Type of Collision Angle Broadside; NB3L and EB3T 09/22/15 Property Damage Only Dry Rear End; NB 06/24/15 Injury Dry Broadside; NB3L, EB3T, and WB3T 02/17/15 Property Damage Only Ice Rear End; EB 11/11/14 Property Damage Only Dry Rear End; NB 02/06/14 Property Damage Only Snow Rear End; WB; 4 cars 06/11/13 Property Damage Only Wet Rear End; WB 09/23/11 Injury Dry Rear End; WB 8

9 Local Concerns Meeting June 8, 2016 IDENTIFIED ISSUES: Rear End Crashes on VT315 Congestion on Allen Martin Drive Congestion on VT315 Speeding vehicles along VT315 Engine braking noise Uncomfortable environment for pedestrians 9

10 Alternatives

11 Alternatives to Address Identified Issues Rear-end crashes on VT-15 Congestion on Allen Martin Drive Congestion on VT Route 15 Speeding vehicles along VT-15 Engine braking noise from vehicles entering speed zone Short Term S1 Restrict Engine Braking X X S2 Extend 35 mph speed zone X X S3 Striped shoulder on VT-15 adjacent to turn lane island S4 Intersection warning sign on approach to Allen Martin Drive on VT-15 Identified Issues ("X" indicates the proposed alternative may partially address the issue) Medium Term M1 Extend green space into VT-15 near turn lane island (permanent S3) X M2 Add a WB left turn lane X X M3 Extend sidewalk along VT-15 from Sandhill Rd X X M4 Add / extend separate NB right- and left-turn lanes X M5 Widen eastbound right turn curve radius X M6 Flashing intersection beacon X X X Uncomfortable environment for pedestrians Long Term L1 Construct Allen Martin Parkway exit from VT-289 X L2 Construct Thompson Drive extension to VT-117 X L3 Intersection Control Modification: Signal X X L4 Intersection Control Modification: Roundabout X X X X L5 Construct connection to Saxon Hill Road X 11

12 Alternatives to Address Identified Issues Rear-end crashes on VT-15 Congestion on Allen Martin Drive Congestion on VT Route 15 Speeding vehicles along VT-15 Engine braking noise from vehicles entering speed zone Short Term S1 Restrict Engine Braking X X S2 Extend 35 mph speed zone X X S3 Striped shoulder on VT-15 adjacent to turn lane island S4 Intersection warning sign on approach to Allen Martin Drive on VT-15 Identified Issues ("X" indicates the proposed alternative may partially address the issue) Medium Term M1 Extend green space into VT-15 near turn lane island (permanent S3) X M2 Add a WB left turn lane X X M3 Extend sidewalk along VT-15 from Sandhill Rd X X M4 Add / extend separate NB right- and left-turn lanes X M5 Widen eastbound right turn curve radius X M6 Flashing intersection beacon X X X Uncomfortable environment for pedestrians Long Term L1 Construct Allen Martin Parkway exit from VT-289 X L2 Construct Thompson Drive extension to VT-117 X L3 Intersection Control Modification: Signal X X L4 Intersection Control Modification: Roundabout X X X X L5 Construct connection to Saxon Hill Road X 12

13 Do Nothing Alternative ISSUES ADDRESSED: None DISCUSSION: Least expensive Least impactful Does not address congestions, safety, or other identified issues RECOMMENDATION: Must be considered Estimated Cost: $0 13

14 S2: Extend Speed Zone ISSUES ADDRESSED: Engine brake noise Speeding through project area Uncomfortable pedestrian environment DISCUSSION: May address the issues, reduce severity of crashes Speed zones should be set by engineering study of the corridor RECOMMENDATION: Recommend speed study Estimated Cost: $2,000 14

15 S3: Striped Shoulder on VT15 at Island ISSUES ADDRESSED: Congestion at Allen Martin Drive Striping in 2011 (Google Streetview) DISCUSSION: Previously there; why removed? Provide improved sight distance, increased left turn storage RECOMMENDATION: Recommend to replace striping Striping in 2016 Estimated Cost: $1,500 15

16 S4: Enhanced Intersection Warning Sign ISSUES ADDRESSED: WB rear end crashes DISCUSSION: With queue detector and solar power, alert motorists to stopped traffic in roadway Not necessary if mid3 to long3 term solutions are pursued RECOMMENDATION: Recommended only if no mid to longterm solution is acceptable Estimated Cost: $15,000 16

17 M1: Extend Island into Roadway ISSUES ADDRESSED: Congestion at Allen Martin Drive DISCUSSION: Long term application of S3 Provide improved sight distance, increased left turn storage RECOMMENDATION: Initially recommended in conjunction with other mid term solutions Estimated Cost: $17,500 17

18 M2: Construct WB Left Turn Lane ISSUES ADDRESSED: WB rear end crashes Congestion on VT315 DISCUSSION: Long term application of S3 Provide improved sight distance, increased left turn storage RECOMMENDATION: Initially recommended in conjunction with other midterm solutions Estimated Cost: $390,000 18

19 M4: Extend NB Left & Right Turn Lanes ISSUES ADDRESSED: Congestion and queuing on Allen Martin Drive DISCUSSION: Allows right turning vehicles to bypass queued left turns May not be needed if long3 term alternatives are pursued RECOMMENDATION: Queueing not currently an issue; pursue if long term solutions are not developed Estimated Cost: $165,000 19

20 M5: Widen EBRight Turn Radius ISSUES ADDRESSED: Congestion on VT315 DISCUSSION: Turning trucks track into VT3 15 through OR Allen Martin Drive Will increase pavement width; may increase speed RECOMMENDATION: Redesign / improvements at intersection must account for design vehicle movements Estimated Cost: $17,350 20

21 M6: Flashing Intersection Beacon ISSUES ADDRESSED: Rear End Crashes on VT315 DISCUSSION: Could be placed on span wire with poles designed for ultimate signal (if preferred) RECOMMENDATION: Initially recommended in conjunction with other midterm solutions Estimated Cost: $50,000 21

22 L3: Intersection Control: Signal ISSUES ADDRESSED: Congestion on Allen Martin Drive DISCUSSION: Intersection control warranted with 80 acres additional development Could be phased with mid3 term improvements Acceptable operations Light / noise into neighbors RECOMMENDATION: Viable intersection control Estimated Cost: $1.5 million 22

23 L4: Intersection Control: Roundabout ISSUES ADDRESSED: Congestion on Allen Martin Drive DISCUSSION: Intersection control warranted with 80 acres additional development Turn lane widening unnecessary Generally considered safer Large impacts to fewer properties RECOMMENDATION: Viable intersection control Estimated Cost: $2.0 million 23

24 Intersection Operational Analysis

25 Operational Analysis: 2016 Scenario Volumes 25

26 Operational Analysis: 2036 Scenario Volumes 26

27 Operational Analysis: Existing Geometry DO NOTHING ALTERNATIVE 27

28 Operational Analysis: Intersection Control AM Peak Hour PM Peak Hour Movement Permitted (No Build) Projected (Build) Permitted (No Build) Projected (Build) LOS Delay LOS Delay LOS Delay LOS Delay NB Left A 9.5 B 10.9 A 9.4 A 8.9 NB Right B 10.8 B 12.7 B 12.8 C 24.5 WB Left A 5.9 B 18.0 B 12.0 C 21.3 WB Thru A 4.2 A 4.1 A 5.6 A 8.3 EB Thru A 3.3 A 3.3 A 9.1 B 16.5 EB Right A 3.2 A 3.5 A 4.8 A 7.3 Overall A 5.1 B 10.0 A 9.3 B 16.6 AM Peak Hour PM Peak Hour Movement Permitted (No Build) Projected (Build) Permitted (No Build) Projected (Build) LOS Delay LOS Delay LOS Delay LOS Delay EB A 8 B 15 A 9 B 11 WB B 11 D 26 A 6 A 8 NB A 4 A 4 A 9 C 16 Overall A 9 C 21 A 9 B 12 Traffic is highly directional 28

29 Two Alternative Paths Do Nothing is always an option Can pursue all medium term options and decide signal control mechanism at a later date Medium term options are in direction of signal Fewer medium term alternatives would be used in roundabout 29

30 Contacts COREY MACK, PE PROJECT ENGINEER SAI SAREPALLI, PE CCRPC TRANSPORTATION PLANNING ENGINEER x16 VISIT: projects/scoping/allen3martin3drive3vt153intersection3scoping3study

31 2016 Traffic Conditions: Hourly Traffic Volume VT315 / Allen Martin Drive Adjusted Hourly Traffic Volumes by Direction EB WB NB :00 AM 6:30 AM 7:00 AM 7:30 AM 8:00 AM 8:30 AM 9:00 AM 9:30 AM 10:00 AM 10:30 AM 11:00 AM 11:30 AM 12:00 PM 12:30 PM 1:00 PM 1:30 PM 2:00 PM 2:30 PM 3:00 PM 3:30 PM 4:00 PM 4:30 PM 5:00 PM Vehicles / Hour (Adjusted) Starting Time 31

32 S1: Restrict Engine Braking ISSUES ADDRESSED: Engine brake noise DISCUSSION: Legality, enforceability, and effectiveness questionable Potentially unsafe RECOMMENDATION: Not Recommended 32

33 M3: Extend Sidewalk Along VT15 ISSUES ADDRESSED: Excessive Speed Pedestrian Environment DISCUSSION: Streetscape enhancement may impact perception of road High3priority segment RECOMMENDATION: Conduct scoping study for sidewalk and gateway treatment Existing Sidewalk Proposed Sidewalk 33

34 L1: Allen Martin Parkway / VT289 Intersection ISSUES ADDRESSED: Congestion on Allen Martin Drive DISCUSSION: Most SHIP traffic would use this intersection Increase WB left turns from VT315 Not regionally feasible RECOMMENDATION: Not recommended 34

35 L2: Thompson Drive Extension to VT 117 ISSUES ADDRESSED: Congestion on Allen Martin Drive DISCUSSION: Would not remove traffic from study intersection Not economically feasible for developer RECOMMENDATION: Not recommended Town may wish to retain ROW for future road development 35

36 L5: Saxon Hill Road Connection ISSUES ADDRESSED: Congestion on Allen Martin Drive DISCUSSION: Unlikely to remove traffic from study intersection Require significant investment Create potential traffic impacts through bike network RECOMMENDATION: Not recommended 36

TECHNICAL MEMO #1 EXISTING CONDITIONS

TECHNICAL MEMO #1 EXISTING CONDITIONS TECHNICAL MEMO #1 EXISTING CONDITIONS TO: FROM: Sai Sarepalli, PE (CCRPC) Corey Mack, PE Roxanne Meuse, EIT CC: DATE: December 15, 2016 SUBJECT: Allen Martin Drive and VT(15 Intersection Scoping Study

More information

Albany Shaker Road Corridor Study Public Meeting # 2

Albany Shaker Road Corridor Study Public Meeting # 2 Albany Shaker Road Corridor Study Public Meeting # 2 Scope / Meeting Purpose This project is a CDTC Linkage Study. The Linkage Program is designed to implement the adopted planning and investment principles

More information

TRANSPORTATION FACILITY PLANNING Waugh Chapel Road Maytime Drive to New Market Lane

TRANSPORTATION FACILITY PLANNING Waugh Chapel Road Maytime Drive to New Market Lane July 24, 2018 TRANSPORTATION FACILITY PLANNING Waugh Chapel Road Maytime Drive to New Market Lane DPWandYOU.com Making a difference, together Meeting Agenda Purpose of the project Overview of work conducted

More information

Transportation Planning Division

Transportation Planning Division Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meetings Data Collected Focus Areas within Study Limits Design Principles Tool Box Recommended Concepts Schedule Moving

More information

Truck Climbing Lane Traffic Justification Report

Truck Climbing Lane Traffic Justification Report ROUTE 7 (HARRY BYRD HIGHWAY) WESTBOUND FROM WEST MARKET STREET TO ROUTE 9 (CHARLES TOWN PIKE) Truck Climbing Lane Traffic Justification Report Project No. 6007-053-133, P 101 Ι UPC No. 58599 Prepared by:

More information

Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns

Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns Revised: May 10, 2016 The California Department of Transportation (Caltrans) is planning various

More information

Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC

Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC 1. TABLE OF CONTENTS INTRODUCTION...1 1.1. Site Location and Study Area...1 1.2. Proposed Land Use and Site Access...2 1.3.

More information

Traffic Impact Study WestBranch Residential Development Davidson, NC March 2016

Traffic Impact Study WestBranch Residential Development Davidson, NC March 2016 Traffic Impact Study WestBranch Residential Development Davidson, NC March 216 TRAFFIC IMPACT STUDY FOR THE WestBranch Residential Development LOCATED IN DAVIDSON, NC Prepared For: Lennar Carolinas, LLC

More information

DEPARTMENT OF ENVIRONMENTAL SERVICES. North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis. Prepared for:

DEPARTMENT OF ENVIRONMENTAL SERVICES. North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis. Prepared for: DEPARTMENT OF ENVIRONMENTAL SERVICES North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis Prepared for: Arlington County Department of Environmental Services 2100 Clarendon Boulevard,

More information

Financial Project ID No(s).: and ETDM No(s).: and 14181

Financial Project ID No(s).: and ETDM No(s).: and 14181 Palm Beach Metropolitan Planning Organization (MPO) Presentation I-95 at Boynton Beach Boulevard Interchange and I-95 at Gateway Boulevard Interchange Project Development and Environment Study Palm Beach

More information

ORANGE COUNTY PUBLIC WORKS TRAFFIC INVESTIGATIONS

ORANGE COUNTY PUBLIC WORKS TRAFFIC INVESTIGATIONS ORANGE COUNTY PUBLIC WORKS TRAFFIC INVESTIGATIONS STAFF REPORT OF: January 6, 2019 SUPERVISORIAL DISTRICT: 5 SUBJECT: LOCATION: INVESTIGATOR: O Neill Drive at Roanoke Drive; Ladera Ranch; TB 922-E6 Clever

More information

SR 693 (Pasadena Avenue) Corridor Study from Shore Drive South to 66 th Street

SR 693 (Pasadena Avenue) Corridor Study from Shore Drive South to 66 th Street Welcome and Introduction Sign-in and comment sheets Restrooms and exits Meeting agenda and timeline Meeting goals / expectations Provide input to guide study recommendations Actively participate throughout

More information

Richmond-Adelaide Cycle Tracks

Richmond-Adelaide Cycle Tracks Public Drop-In Event Richmond-Adelaide Cycle Tracks June 25, 2018 12:00 p.m. 3:00 p.m. 4:30 p.m. 7:30 p.m. Metro Hall, Rotunda 55 John Street 1 Purpose of Event In Scope Communicate an update about the

More information

HSM PREDICTIVE METHODS IN PRELIMINARY ENGINEERING

HSM PREDICTIVE METHODS IN PRELIMINARY ENGINEERING HSM PREDICTIVE METHODS IN PRELIMINARY ENGINEERING 2017 ILLINOIS THE CONFERENCE Filiberto Sotelo & Steven Schilke, P.E. OUTLINE Safety & Transportation Management Process What is HSM? Illinois HSM Predictive

More information

MEMORANDUM. DATE March 1, 2012 TO Town of Milton Mark Abbott, Seth Asante, and Efi Pagitsas Boston Region MPO Staff

MEMORANDUM. DATE March 1, 2012 TO Town of Milton Mark Abbott, Seth Asante, and Efi Pagitsas Boston Region MPO Staff MEMORANDUM DATE March 1, 212 TO Town of Milton FROM RE Mark Abbott, Seth Asante, and Efi Pagitsas Boston Region MPO Staff FFY 211 Safety and Operations Analyses at Selected Boston Region MPO Intersections:

More information

Colchester/Riverside/Barrett/ Mill Intersection Study. PAC Meeting #3 September 22, 2016

Colchester/Riverside/Barrett/ Mill Intersection Study. PAC Meeting #3 September 22, 2016 Colchester/Riverside/Barrett/ Mill Intersection Study PAC Meeting #3 September 22, 2016 Tonight s Agenda Review Project Purpose and Need Describe short term and long improvements and changes since public

More information

Washington St. Corridor Study

Washington St. Corridor Study FIGURE 7.17 Bridge Alternatives - Cross Sections 86 Discarded Alternative: Short-Term Bridge Repair Short-term repairs and west bridge span replacement were considered during analysis. Short-term repairs

More information

Freeway ramp intersection study

Freeway ramp intersection study Freeway ramp intersection study Supporting Vision Zero: Zero traffic deaths in San Francisco by 2024 Study Goals: Primary Improve Safety Improve Accessibility Secondary Provide Efficient Circulation Accommodate

More information

Welcome! San Jose Avenue Open House August 25, 2015

Welcome! San Jose Avenue Open House August 25, 2015 Welcome! San Jose Avenue Open House August 25, 2015 Vision Zero The City and County of San Francisco adopted Vision Zero San Francisco Vision Zero High Injury Network as a policy in 2014, committing an

More information

Hard Shoulder Running is a valuable tool July 14, Dean H. Gustafson, PE, PTOE State Operations Engineer VDOT Operations Division

Hard Shoulder Running is a valuable tool July 14, Dean H. Gustafson, PE, PTOE State Operations Engineer VDOT Operations Division Hard Shoulder Running is a valuable tool July 14, 2016 Dean H. Gustafson, PE, PTOE State Operations Engineer VDOT Operations Division Virginia 2 VDOT s Statewide Operations Program Operations Statistics

More information

Shockoe Bottom Preliminary Traffic and Parking Analysis

Shockoe Bottom Preliminary Traffic and Parking Analysis Shockoe Bottom Preliminary Traffic and Parking Analysis Richmond, Virginia August 14, 2013 Prepared For City of Richmond Department of Public Works Prepared By 1001 Boulders Pkwy Suite 300, Richmond, VA

More information

Glenn Avenue Corridor Traffic Operational Evaluation

Glenn Avenue Corridor Traffic Operational Evaluation Glenn Avenue Corridor Traffic Operational Evaluation PREPARED FOR: THE CITY OF AUBURN PREPARED BY: DECEMBER 2007 Glenn Avenue Corridor Study--Auburn, Alabama TABLE OF CONTENTS Introduction... 1 Background

More information

Town of Bethlehem. Planning Assessment. Bethlehem Town Board

Town of Bethlehem. Planning Assessment. Bethlehem Town Board Town of Bethlehem US 9W Corridor Transportation Planning Assessment Presented e to: Bethlehem Town Board June 2009 Overview Study Background Route 9W Corridor Conditions and Improvements Selkirk Bypass

More information

Balancing Operation & Safety for Motorized and Non-Motorized Traffic

Balancing Operation & Safety for Motorized and Non-Motorized Traffic Balancing Operation & Safety for Motorized and Non-Motorized Traffic Brian Willham, PE, PTOE Iowa Director - MOVITE June 30, 2014 Learning Objectives: When & Why should we measure the performance of complete

More information

WELCOME. City of Eden Prairie West 70 th Street

WELCOME. City of Eden Prairie West 70 th Street WELCOME City of Eden Prairie West 70 th Street Project Schedule Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug >>> May WEST SEGMENT Concept Plan Fall 2014 Plan Development Winter 2014 Summer 2015 Construction

More information

Route 29 Solutions Projects

Route 29 Solutions Projects Route 29 Solutions Route 29 Solutions Projects www.route29solutions.org October 10, 2014 Route 29 Widening to Six Lanes Albemarle County This project will widen a 1.8-mile segment of Route 29 from four

More information

Route 28 (South Orleans Road)/Route 39 (Harwich Road)/Quanset Road Intersection

Route 28 (South Orleans Road)/Route 39 (Harwich Road)/Quanset Road Intersection TRAFFIC FEASIBILITY STUDY Route 28 (South Orleans Road)/Route 39 (Harwich Road)/Quanset Road Intersection Orleans, Massachusetts Prepared for: Town of Orleans Prepared by: Fay, Spofford & Thorndike, LLC

More information

Org Chart. Steering. Committee. Project Advisory. Committee. Nicole Losch, PTP Senior Transportation. Bryan Davis, AICP Senior Transportation

Org Chart. Steering. Committee. Project Advisory. Committee. Nicole Losch, PTP Senior Transportation. Bryan Davis, AICP Senior Transportation 1 Org Chart Project Advisory Committee Steering Committee Nicole Losch, PTP Senior Transportation Planner Bryan Davis, AICP Senior Transportation Planner Jonathan Slason, PE Project Manager Diane Meyerhoff

More information

Public Information Meeting. Orange Camp Road. Dr. Martin Luther King Jr. Beltway to I-4. Presented by: Volusia County August 2, 2018

Public Information Meeting. Orange Camp Road. Dr. Martin Luther King Jr. Beltway to I-4. Presented by: Volusia County August 2, 2018 Public Information Meeting Orange Camp Road Dr. Martin Luther King Jr. Beltway to I-4 Presented by: Volusia County August 2, 2018 1 Project Goals To improve the operations and safety for Orange Camp Road

More information

League City Parkway at Brittany Lakes/Fennigan Intersection Evaluation/ Traffic Study. Second Public Meeting February 6, 2018

League City Parkway at Brittany Lakes/Fennigan Intersection Evaluation/ Traffic Study. Second Public Meeting February 6, 2018 League City Parkway at Brittany Lakes/Fennigan Intersection Evaluation/ Traffic Study Second Public Meeting February 6, 2018 City Project Information League City Parkway and Brittany Lakes Dr./ Fennigan

More information

City of Moorhead Committee of the Whole Meeting

City of Moorhead Committee of the Whole Meeting City of Moorhead Committee of the Whole Meeting Corridor Study Limits Center Avenue (Red River to 8th Street) TH 10 (Red River to TH 336) TH 75 (20th Ave S to Main Avenue) 2 Study Need: Project Overview

More information

City of Wilsonville 5 th Street to Kinsman Road Extension Project

City of Wilsonville 5 th Street to Kinsman Road Extension Project City of Wilsonville 5 th Street to Kinsman Road Walking Tour & Neighborhood Workshop Summary Report Public Outreach Overview On July 18 th, 2017, the City of Wilsonville hosted a neighborhood walking tour

More information

Boston Post Road Design Feasibility Study

Boston Post Road Design Feasibility Study Boston Post Road Design Feasibility Study Prepared for the City of Rye Final Report July 18, 2007 Prepared by: Buckhurst Fish & Jacquemart (BFJ) 115 Fifth Avenue New York, NY 10003 www.bfjplanning.com

More information

Southside Road. Prepared for: City of St. John s Police & Traffic Committee. Prepared by: City of St. John s Traffic Division

Southside Road. Prepared for: City of St. John s Police & Traffic Committee. Prepared by: City of St. John s Traffic Division Southside Road Prepared for: City of St. John s Police & Traffic Committee Prepared by: City of St. John s Traffic Division January 2007 Southside Road - Traffic Report Page 1 of 9 BACKGROUND: th At the

More information

Southview Blvd & 3 rd Avenue Improvement Project. Public Open House December 4, to 7pm

Southview Blvd & 3 rd Avenue Improvement Project. Public Open House December 4, to 7pm Southview Blvd & 3 rd Avenue Improvement Project Public Open House December 4, 2014 5 to 7pm Southview Blvd & 3 rd Avenue Public Information Meeting Agenda Presentation 5:30 to 6:15 pm Purpose of Project

More information

AGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive

AGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive AGENDA REPORT To: From: By: Honorable Mayor and City Council Members Warren Hutmacher, City Manager Tom Black, Public Works Director Date: March 23, 2016 Agenda: March 28, 2016 WORK SESSION AGENDA: Barnwell

More information

Pearl Street / Prospect Street / Colchester Avenue Intersection Scoping Study. April 11, 2013 Steering Committee Meeting #3

Pearl Street / Prospect Street / Colchester Avenue Intersection Scoping Study. April 11, 2013 Steering Committee Meeting #3 Pearl Street / Prospect Street / Colchester Avenue Intersection Scoping Study April 11, 2013 Steering Committee Meeting #3 Meeting Agenda Welcome & Introductions Review Project Purpose & Needs Results

More information

March 11, Lynnfield Board of Selectmen Town of Lynnfield 55 Summer Street Lynnfield, MA Walnut Street Traffic Assessment

March 11, Lynnfield Board of Selectmen Town of Lynnfield 55 Summer Street Lynnfield, MA Walnut Street Traffic Assessment March 11, 2015 Lynnfield Board of Selectmen Town of Lynnfield 55 Summer Street Lynnfield, MA 01940 Re: Walnut Street Traffic Assessment Dear Board of Selectmen Members: As requested, BETA Group, Inc. (BETA)

More information

Arterial Management Plan for US Route 250 and State Route 623

Arterial Management Plan for US Route 250 and State Route 623 Arterial Management Plan for US Route 250 and State Route 623 June 25, 2014 Brad Shelton, AICP Access Management and Traffic Impact Analysis Programs Manager Transportation and Mobility Planning Division

More information

Progress Report on the Design and Planning of an Infrastructure Improvement Project for the Sunnyside TIF District (Phase II)

Progress Report on the Design and Planning of an Infrastructure Improvement Project for the Sunnyside TIF District (Phase II) Presentation to the CNRC Board of Directors Regular Meeting March 11, 2015 1 Agenda Preferred Alternate Refinement for University Avenue, 3rd Street, and Beverly Avenue Intersection Improvements validate

More information

Transportation Planning Division

Transportation Planning Division Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meeting Stakeholder Interviews Data Collection Design Principles Tool Box Recommendations Schedule Moving Forward North

More information

Traffic Impact Analysis Chatham County Grocery Chatham County, NC

Traffic Impact Analysis Chatham County Grocery Chatham County, NC Chatham County Grocery Chatham County, NC TABLE OF CONTENTS 1. INTRODUCTION... 1 1.1. Location and Study Area... 1 1.2. Proposed Land Use and Access... 2 1.3. Adjacent Land Uses... 2 1.4. Existing ways...

More information

Mineral Avenue Corridor Assessment. ITE 2017 Western District Annual Meeting San Diego, CA June 21 st

Mineral Avenue Corridor Assessment. ITE 2017 Western District Annual Meeting San Diego, CA June 21 st Mineral Avenue Corridor Assessment ITE 2017 Western District Annual Meeting San Diego, CA June 21 st Biography - Aaron Heumann, PE, PTOE Currently City of Littleton Transportation Engineering Manager 24

More information

NORTH WILLISTON ROAD SCOPING STUDY

NORTH WILLISTON ROAD SCOPING STUDY DRAFT REPORT NORTH WILLISTON ROAD SCOPING STUDY 2.9.2018 180 Battery Street, Suite 350 Burlington, VT 05401 802.383.0118 www.rsginc.com PREPARED FOR: TOWN OF WILLISTON CHITTENDEN COUNTY PLANNING COMMISSION

More information

91 Express Lanes Model Update 2006 State Route 91 Implementation Plan. Gerald V. Nielsten May 18, 2007

91 Express Lanes Model Update 2006 State Route 91 Implementation Plan. Gerald V. Nielsten May 18, 2007 91 Express Lanes Model Update 2006 State Route 91 Implementation Plan Gerald V. Nielsten May 18, 2007 1 Vollmer Associates LLP is now Stantec Inc. Stantec Inc. completed the acquisition of Vollmer Associates

More information

Bicycle Crashes. Number of Bike Crashes. Total Bike Crashes. are down 21% and severe bike crashes down 8% since 2013 (5 years).

Bicycle Crashes. Number of Bike Crashes. Total Bike Crashes. are down 21% and severe bike crashes down 8% since 2013 (5 years). Bicycle Crashes The City of Fort Collins is well known for its bike culture, and there is a strong focus on encouraging increased riding. Bike safety is an important component of supporting these efforts.

More information

2015 Data review. Capturing Ready Lane NEXUS vehicles

2015 Data review. Capturing Ready Lane NEXUS vehicles 2015 Data review Capturing Ready Lane NEXUS vehicles Problem: NEXUS users make up the majority of traffic using the Ready Lane, but they are currently considered either standard traffic or Ready Lane traffic.

More information

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Mercer County Planning Division AECOM Transportation (formerly DMJM Harris) January 29, 2009 Agenda Project Status

More information

WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING. March 28, 2017

WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING. March 28, 2017 WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING March 28, 2017 STUDY AREA N MEETING AGENDA Introductions Study Background Alternatives Studied Recommended Alternative Discussion STUDY BACKGROUND

More information

City of Albert Lea Policy and Procedure Manual 4.10 ALBERT LEA CROSSWALK POLICY

City of Albert Lea Policy and Procedure Manual 4.10 ALBERT LEA CROSSWALK POLICY 4.10 ALBERT LEA CROSSWALK POLICY PURPOSE: Pedestrian crosswalks are an integral part of our transportation infrastructure. To be effective and promote safety, marked crosswalks must be installed after

More information

Complete Streets Chicago: Data Driven Design. Luann Hamilton Deputy Commissioner

Complete Streets Chicago: Data Driven Design. Luann Hamilton Deputy Commissioner Complete Streets Chicago: Data Driven Design Luann Hamilton Deputy Commissioner AGENDA Chicago s goals Complete Streets & Sustainable Infrastructure Guides Data-Driven Planning Setting goals Scoping/research

More information

Orange County Rail-Highway Grade Crossing Safety Enhancement Program. City of San Juan Capistrano April 17, 2012

Orange County Rail-Highway Grade Crossing Safety Enhancement Program. City of San Juan Capistrano April 17, 2012 Orange County Rail-Highway Grade Crossing Safety Enhancement Program City of San Juan Capistrano April 17, 2012 Orange County Rail-Highway Grade Crossing Safety Enhancement Program (OCX) 52 crossings 8

More information

North Avenue Corridor Study

North Avenue Corridor Study North Avenue Corridor Study City Council October 6, 2014 Presentation Outline Project Initiation & Process Corridor Conditions & Issues Vision & Goals Concept Development - Development/Evaluation Implementation

More information

CITY OF FRANKLIN, TENNESSEE. Columbia Avenue. Widening & Improvements Project. Public Meeting May 16, 2017

CITY OF FRANKLIN, TENNESSEE. Columbia Avenue. Widening & Improvements Project. Public Meeting May 16, 2017 CITY OF FRANKLIN, TENNESSEE Columbia Avenue Widening & Improvements Project Public Meeting May 16, 2017 Agenda 6:00 6:30 Formal Presentation 6:30 8:00 Town Hall Forum City of Franklin Columbia Avenue Alternatives

More information

Route 29 Corridor Assessment Update. Development of Possible Solutions

Route 29 Corridor Assessment Update. Development of Possible Solutions Route 29 Corridor Assessment Update Development of Possible Solutions Public Workshop #3 October 27, 2016 Purpose of Developing Possible Solutions Recap of where we ve been and timeline for moving forward

More information

Project Advisory Group (PAG) Meeting #2 January 31, SR 693 (Pasadena Avenue) Corridor Study from Shore Drive South to 66 th Street

Project Advisory Group (PAG) Meeting #2 January 31, SR 693 (Pasadena Avenue) Corridor Study from Shore Drive South to 66 th Street Project Advisory Group (PAG) Meeting #2 January 31, 2018 Welcome & Introductions AGENDA 1. Where are we at? 2. Project Survey / Virtual Comment Tool / PAG Meeting #1 / Visioning Workshop Corridor Map Exercise

More information

ROAD SAFETY AUDIT. Granite Avenue at Interstate 93 Ramps. Town of Milton. May 22, Prepared for: MassDOT

ROAD SAFETY AUDIT. Granite Avenue at Interstate 93 Ramps. Town of Milton. May 22, Prepared for: MassDOT ROAD SAFETY AUDIT Granite Avenue at Interstate 93 Ramps Town of Milton May 22, 2017 Prepared for: MassDOT Prepared by: Toole Design Group 2 Oliver Street, Suite 305 Boston, MA 02109 Table of Contents Background...

More information

Roundabout Evaluations in Virginia: US 15/US 50 Gilberts Corner, VA SR 106/SR 634 Prince George County, VA

Roundabout Evaluations in Virginia: US 15/US 50 Gilberts Corner, VA SR 106/SR 634 Prince George County, VA Roundabout Evaluations in Virginia: US 15/US 50 Gilberts Corner, VA SR 106/SR 634 Prince George County, VA VDOT & FHWA Roundabout Workshop September 17, 2013 Chris Tiesler, PE Presentation Outline US 15/US

More information

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto

More information

Trial Restriping Project. October 21, 2010

Trial Restriping Project. October 21, 2010 Arastradero Road Trial Restriping Project P t C t ti C it O t hm ti N 1 Post Construction Community Outreach Meeting No. 1 October 21, 2010 Agenda Staff Introductions Project Background Project Status

More information

Bistro 6. City of Barrie. Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report. Project Number: JDE 1748

Bistro 6. City of Barrie. Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report. Project Number: JDE 1748 City of Barrie Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report Project Number: JDE 1748 Date Submitted: June 12 th, 2017 06/12/17 John Northcote, P.Eng. Professional License

More information

Community Advisory Committee

Community Advisory Committee Community Advisory Committee Meeting #1 November 19, 2014 Presentation Team Matt Fulda, Greater Bridgeport Regional Council Chris Granatini, P.E., Tighe & Bond Craig Yannes, P.E., PE PTOE, Tighe & Bond

More information

Intersection Improvement: Sturgeon Road, Silver Avenue and Murray Park Road Roundabout. Welcome. Public Information Session

Intersection Improvement: Sturgeon Road, Silver Avenue and Murray Park Road Roundabout. Welcome. Public Information Session Intersection Improvement: 1 Welcome WHY IS AN INTERSECTION IMPROVEMENT NEEDED? 2 Traffic volumes for Sturgeon Road, Silver Avenue and Murray Park Road exceed the capacity of the existing 4-way stop controlled

More information

54 th Avenue North Complete Streets Concept Plan

54 th Avenue North Complete Streets Concept Plan 54 th Avenue North Complete Streets Concept Plan June 2018 TABLE OF CONTENTS Introduction and Purpose...1 Existing Conditions...5 Stakeholder and Public Outreach...15 Preferred Options West Segment...19

More information

Blair Park Traffic Calming Study

Blair Park Traffic Calming Study Blair Park Traffic Calming Study Williston, Vermont Prepared for: Chittenden County Regional Planning Commission Town of Williston, Vermont Prepared by: Stantec Consulting Services Inc. 55 Green Mountain

More information

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009 Summary: Several recent studies have assessed potential development and redevelopment opportunities in the Mercer Crossing area of Trenton, Ewing, and Lawrence. This Princeton Avenue and Spruce Street

More information

STANLEY STREET December 19, 2017

STANLEY STREET December 19, 2017 STANLEY STREET December 19, 2017 Welcome Mike Wiza, Mayor Scott Beduhn, Director of Public Works Agenda 1. Introduction 2. Existing Roadway Conditions 3. Current Alternative Improvements 4. Summary of

More information

180 Grand Avenue, Suite x117 Dowling Associates, Inc.

180 Grand Avenue, Suite x117 Dowling Associates, Inc. 180 Grand Avenue, Suite 250 510.839.1742 x117 Oakland, CA 94612 510.839.0871 fax www.dowlinginc.com mbowman@dowlinginc.com Dowling Associates, Inc. Date: Memorandum To: CC: From: Ms. Leah Greenblat City

More information

Existing Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer

Existing Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Date: April 16 th, 2015 To: From: Re: Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Darian Nagle-Gamm, Traffic Engineering Planner Highway 6 (2 nd Street) /

More information

Newport City Thoroughfare Plan

Newport City Thoroughfare Plan Newport City Thoroughfare Plan Summary This plan is intended to review and make recommendations for Newport City s thoroughfare network, in consideration of the full range of uses of the city s streets.

More information

Road Diets. Presented by: Cristine Gowland, P.E. LADOTD District 62 March 2, 2016

Road Diets. Presented by: Cristine Gowland, P.E. LADOTD District 62 March 2, 2016 Road Diets Presented by: Cristine Gowland, P.E. LADOTD District 62 March 2, 2016 FHWA s 9 Proven Safety Countermeasures 1. Safety Edge 2. Roundabouts 3. Corridor Access Management 4. Backplates with Retroreflective

More information

AGENDA ITEM 6 D THOMASVILLE ROAD (HERMITAGE BOULEVARD TO LIVE OAK PLANTATION ROAD) ROADWAY SAFETY AUDIT

AGENDA ITEM 6 D THOMASVILLE ROAD (HERMITAGE BOULEVARD TO LIVE OAK PLANTATION ROAD) ROADWAY SAFETY AUDIT May 15, 2018 AGENDA ITEM 6 D THOMASVILLE ROAD (HERMITAGE BOULEVARD TO LIVE OAK PLANTATION ROAD) ROADWAY SAFETY AUDIT TYPE OF ITEM: Discussion STATEMENT OF ISSUE The Florida Department of Transportation

More information

Giles Run Connector Road

Giles Run Connector Road Giles Run Connector Road Laurel Hill Adaptive Reuse Area to Laurel Crest Drive South County Federation Meeting June 14, 2016 History Connector road included in the Laurel Hill Comprehensive Plan amendment

More information

DOT Policy and Procedure Integrity Excellence Respect

DOT Policy and Procedure Integrity Excellence Respect DOT Policy and Procedure 05.05.020 Integrity Excellence Respect Alaska s Speed Limit Policy Contained in DOT Policy and Procedure (P&P) 05.05.020, Establishment of Speed Limits and Zones Incorporates pertinent

More information

Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation

Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation City of Hillsdale, Hillsdale County, Michigan June 16, 2016 Final Report Prepared for City of Hillsdale 97 North Broad

More information

Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation

Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation APRIL 2016 A collaborative study between: For Additional Information or to Comment If you would like additional

More information

5. RUNNINGWAY GUIDELINES

5. RUNNINGWAY GUIDELINES 5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved

More information

DUNBOW ROAD FUNCTIONAL PLANNING

DUNBOW ROAD FUNCTIONAL PLANNING DUNBOW ROAD FUNCTIONAL PLANNING Final Report August 3, 216 #31, 316 5th Avenue NE Calgary, AB T2A 6K4 Phone: 43.273.91 Fax: 43.273.344 wattconsultinggroup.com Dunbow Road Functional Planning Final Report

More information

TRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION

TRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION TRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION Transportation Consultants, LLC 1101 17 TH AVENUE SOUTH NASHVILLE, TN 37212

More information

Developing Bikeways in South Denver

Developing Bikeways in South Denver Developing Bikeways in South Denver Southeast Denver, Council District 4 October 24, 2018 1 Denver Moves: Bicycles Citywide Bikeway Master Plan: 2011 2015 State of the practice Enhanced Bikeways (2015)

More information

Walton Acres at Riverwood Athletic Club Clayton, North Carolina

Walton Acres at Riverwood Athletic Club Clayton, North Carolina 9. CONCLUSIONS This Traffic Impact Analysis Update was conducted to determine the potential traffic impacts of the proposed Walton Acres at Riverwood Athletic Club residential development, located east

More information

PROJECT OBJECTIVES. Improve vehicle capacity for the intersection. Improve pedestrian and bicycle access

PROJECT OBJECTIVES. Improve vehicle capacity for the intersection. Improve pedestrian and bicycle access COMMUNITY MEETING Project Update March 15, 2010 Purcellville, Virginia OVERVIEW Project need / objectives Project recap Design elements Proposed improvements Summary of project benefits / next steps PROJECT

More information

Traffic Impact Study Little Egypt Road Development Denver, North Carolina June 2017

Traffic Impact Study Little Egypt Road Development Denver, North Carolina June 2017 Traffic Impact Study Little Egypt Road Development Denver, North arolina June 2017 N. Little Egypt Road DQ\ QDQFLQJ VDOHV RU RWKHU SHUIRUPDQFH EDVHG FULWHULD Proposed Site Driveways Site Driveway 1 TRAFFI

More information

Project Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015

Project Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015 Meadows Place, TX October 9, 2015 Contents 1 Introduction... 1 2 Data Collection... 1 3 Existing Roadway Network... 2 4 Traffic Volume Development... 2 5 Warrant Analysis... 3 6 Traffic Control Alternative

More information

Retrofitting Urban Arterials into Complete Streets

Retrofitting Urban Arterials into Complete Streets Retrofitting Urban Arterials into Complete Streets John N. LaPlante, P.E., P.T.O.E., T.Y. Lin International Prepared for: Illinois Traffic Engineering & Safety Conference Urbana, Illinois October 18, 2007

More information

STILLWATER AVENUE CORRIDOR STUDY Old Town, Maine

STILLWATER AVENUE CORRIDOR STUDY Old Town, Maine Draft Study STILLWATER AVENUE CORRIDOR STUDY Old Town, Maine SUBMITTED TO: BANGOR AREA COMPREHENSIVE TRANSPORTATION SYSTEM SUBMITTED BY: I MAY 23, 2017 DRAFT STILLWATER AVENUE STUDY FINAL REPORT Table

More information

CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM

CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM Date: April 1, 219 To: Honorable City Council c/o City Clerk, Room 395, City Hall Attention: Honorable Mike Bonin, Chair, Transportation Committee From:

More information

Reference number /VP. Lafayette Downtown Congestion Study - Additional Traffic Analysis

Reference number /VP. Lafayette Downtown Congestion Study - Additional Traffic Analysis To James Hinkamp and Tony Coe, City of Lafayette Date January 19, 2017 Copies Reference number 243381/VP From Michael Iswalt and Vanessa Peers File reference 4-05 Subject Lafayette Downtown Congestion

More information

Traffic Study of Fuller Street, Cady Street, West Street and West Avenue. Final Report

Traffic Study of Fuller Street, Cady Street, West Street and West Avenue. Final Report Traffic Study of Fuller Street, Cady Street, West Street and West Avenue Final Report July 2005 Prepared for: Town of Ludlow Prepared by: Pioneer Valley Planning Commission 26 Central Street West Springfield,

More information

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 What s Happening The City plans to mill and resurface Dr. M.L.

More information

Date: September 7, Project #: Re: Spaulding Youth Center Northfield, NH Property. Traffic Impact Study

Date: September 7, Project #: Re: Spaulding Youth Center Northfield, NH Property. Traffic Impact Study To: Ms. Susan C. Ryan Spaulding Youth Center 72 Spaulding Road Northfield, NH 03276 Date: September 7, 2017 Project #: 52455.00 From: Robin Bousa Director of Transportation Systems Re: Spaulding Youth

More information

Data Analysis February to March Identified safety needs from reported collisions and existing travel patterns.

Data Analysis February to March Identified safety needs from reported collisions and existing travel patterns. Welcome! Thank you for participating in today s Valencia Bikeway Improvements workshop. Data Analysis February to March Identified safety needs from reported collisions and existing travel patterns. Initial

More information

Donahue Drive Corridor Traffic Operational Evaluation

Donahue Drive Corridor Traffic Operational Evaluation Donahue Drive Corridor Traffic Operational Evaluation PREPARED FOR: THE CITY OF AUBURN PREPARED BY: JANUARY 2007 Donahue Drive Corridor Study--Auburn, Alabama TABLE OF CONTENTS Introduction... 1 Background

More information

M-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016

M-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016 M-58 HIGHWAY ACCESS MANAGEMENT STUDY Prepared for CITY OF BELTON By May 2016 Introduction Missouri State Highway 58 (M-58 Highway) is a major commercial corridor in the City of Belton. As development has

More information

Las Tunas Downtown Revitalization City Council Study Session. December 1, :00 p.m. Live Oak Park Community Center

Las Tunas Downtown Revitalization City Council Study Session. December 1, :00 p.m. Live Oak Park Community Center Las Tunas Downtown Revitalization City Council Study Session December 1, 2015 7:00 p.m. Live Oak Park Community Center AGENDA 2 Provide downtown context. Confirm project goals. Analyze three design concepts.

More information

Ottawa Beach Road Study

Ottawa Beach Road Study Ottawa Beach Road Study Prepared For: Park Township September 30, 2014 Project No. G140303 OTTAWA BEACH ROAD STUDY PREPARED FOR: PARK TOWNSHIP SEPTEMBER 30, 2014 PROJECT NO. G140303 TABLE OF CONTENTS 1.0

More information

Terwillegar Drive Expressway Draft Concept Plan

Terwillegar Drive Expressway Draft Concept Plan Terwillegar Drive Expressway Draft Concept Plan Anthony Henday Drive to Whitemud Drive November 28 5:00-8:00 p.m. December 1 10:00 a.m. - 3:00 p.m. Let s Talk Today you can: Learn about the new direction

More information

INTERSECTION SAFETY STUDY State Route 57 / Seville Road

INTERSECTION SAFETY STUDY State Route 57 / Seville Road INTERSECTION SAFETY STUDY State Route 57 / Seville Road City of Wadsworth, Medina County, Ohio Prepared For: City of Wadsworth Engineering Department 120 Maple Street Wadsworth, OH 44281 Prepared By: GPD

More information

Interstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project. Prepared September 6, 2017

Interstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project. Prepared September 6, 2017 EODOT Project: ODOT Project: STA-IR 77-.50; PID 00290 Interstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project Summary of Public Comments Received and Responses

More information

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Background Agenda Traffic Study Update Class EA Alternatives Bridge

More information