Hope Mills Lake Recreational Improvement Plan. Lake Advisory Committee
|
|
- Osborne Thomas
- 6 years ago
- Views:
Transcription
1 Hope Mills Lake Recreational Improvement Plan
2
3 Phase I Phase II Phase III This Phase is the time period prior to impoundment of the Lake. These items must be accomplished prior to the Lake level rising to the point of interfering with the project This Phase is the time period between impoundment of the Lake and the first anniversary of the completed impoundment. Projects in this Phase need to be completed to improve the standard of living for all citizens This Phase includes all work not completed in the above Phases, and those projects that require further planning, budgeting and implementation. It is recommended that the Commissioners determine a reasonable Lake timeframe Advisory Committee to complete the remaining projects.
4 Figure 1 Figure 2 Showing the damage to the sidewalk completely undermined following Hurricane Mathew Deterioration of the bulkhead wall. This is continuing to happen.
5 Taken from the Lake side, this shows the damage to the sidewalk caused by the undermining of the concrete Figure 3
6 The end of the boat ramp. Showing the drop off towards the creek. Placement of a curb block at the end and placement of signs will provide safety and notify drivers the trailer is about to go beyond the ramp. Figure 4
7 Fishing Pier Initial inspection has indicated that the framework of the current Public Pier is in good condition. Parts of the decking and facia boards should be replaced. In order to improve the use of the Pier it is planned to extend the first part of the pier towards the creek. Currently the ability to fish from the pier is limited, due to the surrounding water level of the pier. Extension towards the creek will improve the fishing experience.
8 Figure 5 Showing the extension to the fishing pier (Blue) and also the location of the Kayak launch (Green) Figure 6 The approximate location of the kayak launch, to the right of the boat ramp.
9 Figure 7 Figure 8 Swimming area as depicted following impoundment after the new dam. Evidence of erosion can be seen on the shoreline. Depth of the water can also be seen to be too low close to the buoys.
10 Figure 9 Although this photo is looking away from the dam, the original bulkhead installed in the swimming area of the original lake (prior to the dam failure) is clearly seen to provide protection from erosion.
11 This photo (from October 2008) shows the slope of the ground from the park area to the waterline. During operations to return the Park to its original state ASI/Schnabel should be requested to try to even out this slope.
12 Figure 10 Figure 11 The floating docks are in need of refurbishment and also need to be adjusted for the water level of 104 MSL. Initial visual check seems to indicate they could be repairable. However, as seen in Figure 11, the docks were installed for a level of 106 MSL, the marking for 105 MSL is considerably lower and the current plan to impound to 104 MSL will require the docks be lowered. As can also be seen the ground at this level should be excavated to allow boats to dock without grounding out. The yellow line in figure 10 indicates the possible level.
13 Figure 12 An example from NC Wildlife for the sign they produced for Lake Raleigh.
14 Irrigation System Irrigation for the park area will provide a means of ensuring survival of the sod/seed that will be installed by ASI/Schnabel in the hottest time of year. It will also greatly improve the capability of maintaining the grass in a high traffic area. By maintaining healthy grass the erosion will be slowed
15 Phase II Providing adequate litter containers in the park area. Lighting for the fishing pier Lighting within the park
16 Parking Marked Crossing for Pedestrians Benches on the fishing pier Benches in the Park area
17 Phase III Improvements to fishing access by adding a new pier closer to the dam. Improvements to the kayak launch area Public access to the ell ladder Complete Museum and Heritage Park Projects
18 Installed floating fishing pier at Lake Rim. A T shaped pier, fully ADA accessable, and with railings on all parts of approach and pier. Due to its modular construction it has the ability to conform to the transition from shore to water, and will adjust to changing levels. Figure 13 Figure 14
19 Figure 16 Figure 15 Photos from the internet (FWMdocks.com and SeeThroughCanoe.com) that show possible improved kayak launches available on the market. Neither of these are recommended, but are shown to indicate various different types of launches. NC Wildlife is willing to assist in the design and possible installation ( dependant upon agreements not yet made).
20 Figure 17 The proposed conceptual plan drawn for Heritage Park. Note the date of January 2003.
Lewis River Hydroelectric Projects Settlement Agreement Lewis River Recreation Coordination Committee (LRC) Meeting Agenda
Lewis River Hydroelectric Projects Settlement Agreement Lewis River Recreation Coordination Committee (LRC) Meeting Agenda Date & Time: Wednesday, February 24, 2016 9:30 AM 11:30 AM Place: Merwin Hydro
More informationIssues facing this region include the status of the Sluice Creek tide gates, various tidal wetlands, and locations of public access:
5.6 Guilford Point to Madison Town Line Existing Resources This region extends from Guilford Point to the Madison town line. Named places include Grass Island and the East River. Residential, commercial,
More informationCity of Pittsfield HARBORMASTER RULES AND REGULATIONS on docks
City of Pittsfield HARBORMASTER RULES AND REGULATIONS on docks Definitions Dock: Any permanently fixed or floating structure extending from the upland into the water, capable of use for vessel mooring
More informationWater Resources Report RKLD Annual Meeting July 30, 2016
Water Resources Report RKLD Annual Meeting 2016 July 30, 2016 Topics Hydrology Report Indianford Dam trash rack cleanout performance Experimental Project update Review of PAS project Twin floods- 1 to
More informationCHAPTER 6 10/29/2018 Clean Version REGULATING PIERS, WHARVES, MOORING BUOYS, SWIMMING RAFTS AND INFLATABLES ON ROCK LAKE
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 CHAPTER 6 10/29/2018 Clean Version REGULATING PIERS, WHARVES, MOORING BUOYS,
More informationCity of Pittsfield Harbormaster APPLICATION FOR AN INDIVIDUAL MOORING PERMIT
City of Pittsfield Harbormaster APPLICATION FOR AN INDIVIDUAL MOORING PERMIT INSTRUCTIONS: This application may only be used for requests to place lake moorings. This application must be completed in its
More informationScenarios. The following slides will show existing pictures that deny access, followed by a retrofitted picture that provides access.
Scenarios. The following slides will show existing pictures that deny access, followed by a retrofitted picture that provides access. For the following slides assume an overlay project and provide pedestrian
More informationPortage Bay Park Design Commission Review 4: 90% Design Development January 5, 2017
to be updated to reflect base bid condition Portage Bay Park Design Commission Review 4: 90% Design Development January 5, 2017 Previous Site Plan POTENTIAL PARK CONNECTION & MID-BLOCK CROSSING BOAT STREET
More informationKerr Lake Vegetation Survey. October November Report submitted by NC State University. Background
Kerr Lake Vegetation Survey October November 2012 Report submitted by NC State University Background Hydrilla (Hydrilla verticillata) is a non-native invasive submersed aquatic plant. This plant was first
More informationCity of Roseville Section 13 Design Standards. _Bikeways January 2016 SECTION 13 BIKEWAYS
SECTION 13 BIKEWAYS 13-1 GENERAL The City of Roseville bikeway standards are designed to insure that transportation and recreational bikeways are constructed in a manner that would provide a safe and comfortable
More informationCOMPLETE STREETS DURING CONSTRUCTION
COMPLETE STREETS DURING CONSTRUCTION MAINTAINING ACCESSIBILITY FOR ALL Presented by Robbie Burgess, P.E., PTOE Associate Principal Construction Services Manager Howard Stein Hudson rburgess@hshassoc.com
More informationFINAL Caples Lake Fisheries Management Plan. Version 4.0
FINAL Caples Lake Fisheries Management Plan Version 4.0 August 15, 2008 Purpose The Caples Lake Fisheries Management Plan (Plan) outlines the stocking plan to reestablish a sport fishery in Caples Lake
More informationCanoe/Kayak Launch Sites and Accessibility
Canoe/Kayak Launch Sites and Accessibility Doug Alderson, Paddling Trails Coordinator Division of Recreation and Parks Office of Greenways and Trails Each potential access site on a river, lake or ocean
More informationCATAWBA YACHT CLUB RULES Approved 10/6/09
CATAWBA YACHT CLUB RULES Approved 10/6/09 The Board of Governors has established the following rules, and the membership is hereby notified that they are in effect. For the purposes of these rules, the
More informationLaunch Site Accessibility Evaluation & Design Recommendations
Access Recreation Group, LLC Cindy Burkhour, MA, CTRS, CPRP 2454 Lamplighter Drive, Jenison, MI 49428-9127 Phone (616)669-9109 Mobile (616)560-2378 AccessRecreationGroup@juno.com Location: New Buffalo
More informationADA Training Accessible Pedestrian Signal (APS) 2018 MnDOT
ADA Training Accessible Pedestrian Signal (APS) 2018 MnDOT APS and ADA APS is not currently an ADA Standard and is provided at the discretion of the Title II entity APS is recognized in the MnMUTCD, but
More informationCITY OF NEWPORT BEACH HARBOR COMMISSION STAFF REPORT
CITY OF NEWPORT BEACH HARBOR COMMISSION STAFF REPORT Agenda Item No. 2 TO: FROM: SUBJECT: HARBOR COMMISSION Harbor Resources Division (City Manager's Office) Chris Miller, Harbor Resources Supervisor,
More informationWhite Mountain Lakes County Recreation Improvement District Community Town Hall April 27, 2017 WELCOME
White Mountain Lakes County Recreation Improvement District Community Town Hall April 27, 2017 WELCOME INTRODUCTIONS: Jason Whiting, Board of Directors Brandt Clark, Deputy County Attorney Melissa Buckley,
More informationBorough of Danville, PA Traffic Calming Program Guidelines
Borough of Danville, PA Traffic Calming Program Guidelines Adopted by Borough Council on 1 INTRODUCTION Speeding Traffic is a major concern in the Borough of Danville because of its detrimental impacts
More information4/20/17. #32 - Coastal Erosion Case Histories - Lake Michigan
Writing Assignment Due Monday by 11:59 pm #32 - Coastal Erosion Case Histories - Lake Michigan See main class web pages for detailed instructions Submit papers Illinois Compass No copying: Compass will
More informationLake, Boat and Lakeside Greenbelt Regulations. Landings Community Association for Warren Lake
Lake, Boat and Lakeside Greenbelt Regulations Landings Community Association for Warren Lake Version 12.3 Final Approved by the Landings board March 1, 2016 Introduction With the increased population pressure
More informationAPPENDIX B1. CROSS-REFERENCE GUIDE TO THE OHIO REVISED CODE
Appendix B1. Cross-Reference Guide to the Ohio Revised Code Page B1-1 APPENDIX B1. CROSS-REFERENCE GUIDE TO THE OHIO REVISED CODE The Ohio Revised Code (O.R.C.) contains many laws which apply to the control
More informationRLRC COMMUNITIES EAST GRAND FORKS AREA CHARACTER THE RED LAKE RIVER & THE RED RIVER OF THE NORTH CONFLUENCE EAGLE POINT BOAT LAUNCH DESIGN
AREA CHARACTER THE RED LAKE RIVER & THE RED RIVER OF THE NORTH CONFLUENCE EAGLE POINT BOAT LAUNCH DESIGN DESIGN DETAILS 135 AREA CHARACTER East Grand Forks a city of 7,501 people is located across the
More information: AUTHORITY: This ordinance is adopted under the authority granted by Section 30.13(2) and 30.13(3) of the Wisconsin Statutes.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 CHAPTER 6 REGULATING PIERS, WHARVES, MOORING BUOYS, RAFTS, AND INFLATABLES
More informationAmericans with Disabilities Act Transition Plan for Public Right-of-Way Improvements
Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements Prepared by: Public Works Department Engineering Division October 2015 Table of Contents Section I Introduction.. 3
More informationInlet Dredging budget also slashes federal
Family Park Broadway Street Park President Slashes Vital Coastal Funding Need Your Support and Help Soundside Park New Playgrounds Complete Beach Nourishment Shoreline Protection President Bush s proposed
More information2010 Kemp Lake Angling and Lake Infrastructure Improvement Proposal
2010 Kemp Lake Angling and Lake Infrastructure Improvement Proposal Prepared for: Capital Regional District Juan de Fuca Electoral Area Community Parks and Recreation #2-6868 West Coast Road P.O. Box 283,
More informationMogollon Rim and White Mountains Angler Report
Mogollon Rim and White Mountains Angler Report Becker Lake, Monday, Nov. 6 Blain O.: Becker Lake fished well last week though the water was cold (50- degrees F at the surface). Fish were scattered everywhere
More informationEarthen Embankments. turning into larger, more costly repairs. The following. The State Dam Safety Program has inspection
TOPIC: COMMON PROBLEMS FOR SMALL DAMS WITH CONCRETE CHANNEL SPILLWAYS The State Dam Safety Program has inspection requirements for state regulated dams. A dam, like any man-made structure, will change
More informationHARBOR INFRASTRUCTURE INVENTORIES Marquette Harbor, Michigan
HARBOR INFRASTRUCTURE INVENTORIES Marquette Harbor, Michigan Harbor Location: Marquette Harbor is located in Marquette Bay on the south shore of Lake Superior, 160 miles west of Sault Ste. Marie, MI and
More informationCity of Los Angeles Department of Building & Safety Disabled Access Section Supplemental Plan Review Checklist No. 8 RECREATION FACILITIES
AMUSEMENT RIDES, BOAT SLIPS, BOWLING LANES, COURT SPORTS, FISHING PIERS Plan Check No. 1. Amusement rides required to comply with 11B-234, Amusement Rides shall provide accessible routes in accordance
More informationPortland Peninsula Sidewalk and Ramp Inventory
Portland Peninsula Sidewalk and Ramp Inventory Conducted June and July of 2008 By Anne Krikorian and Ryan Carmichael Performed under the authority of: Greater Portland Council of Governments And with the
More informationExcavations and Trenches
Purpose Excavation and trenching are among the most hazardous work activities undertaken by the TNRD. This document outlines general requirements and specific safe work procedures to ensure the health
More informationMILEGROUND - AIRPORT ROAD. Fall 2018/ Spring Fall 2020 TBD. US 119 Monongalia County HOW WILL TRAFFIC CONTROL BE HANDLED: KNOW BEFORE YOU GO
MILEGROUD - AIRPORT ROAD US 119 Monongalia County The Mileground - Airport Road project on US 119 involves upgrading the three-lane facility to a five-lane facility to help eliminate congestion and improve
More informationSUMMARY COSTS: (Please attach a detailed budget including all sources of recipient funding)
VIRGINIA SALTWATER RECREATIONAL FISHING DEVELOPMENT FUND SUMMARY PROJECT APPLICATION Please complete all fields. This page should be used as a coversheet for a detailed application. NAME AND ADDRESS OF
More informationMAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report
Page 1 MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report August 1, 2012 MAG Project #481 Page 2 Task 6 Executive Summary and Regional Significance Report Introduction
More informationSidewalk Accessibility Checklist
Starting Address: Ending Address: Date: Sidewalk Accessibility Checklist Please indicate your experience with any barriers you encountered when using the sidewalks in your neighborhood. 1. Did you have
More informationPart 9 Specific Land Uses - Foreshore & Waterway Development
7 FORESHORE AND WATERWAY DEVELOPMENT This section applies to the following development uses proposed within the foreshore area (defined by LM LEP 2014), and contains Council s specific requirements for
More informationTraffic Control Inspection Checklist Segment:
Traffic Control Inspection Checklist Segment: Simon Contractors Simon Contractors Originator: Description Reviewed by: Initials Date Distribution: Traffic Quality Manager, Site Assistant Traffic Manager
More informationImproving intersections for people that walk in Minneapolis
Matthew Dyrdahl, AICP, LCI Bicycle and Pedestrian Coordinator Minneapolis Public Works CITY OF MINNEAPOLIS Improving intersections for people that walk in Minneapolis Transportation Bonanza February 8,
More informationPublic Notice U.S. Army Corps In Reply to Application Number CENAB-OP-RMS (NATIONAL HARBOR (FORMERLY PORT Baltimore District AMERICA])
Public Notice U.S. Army Corps In Reply to Application Number of Engineers CENAB-OP-RMS (NATIONAL HARBOR (FORMERLY PORT Baltimore District AMERICA]) 88-01361 PN 14-05 Comment Period: January 16, 2014 to
More informationC Line Rapid Bus Preliminary Station Design
C Line Rapid Bus Preliminary Station Design C Terrence Anderson, Community Outreach Coordinator Shawn Walding, Senior Engineer Metro Transit TAAC February 1, 2016 1 C Line project overview Substantially
More informationNiantic Center Elementary School
Niantic Elementary School is located in the Northwest corner of the intersection of West Main Street and East Pattagansett Road, as so noted on the Facility Location Map. location Overview: The site is
More informationNORMAL MEAN WATER LEVEL
D. Piers, Moorings and Swimming Rafts on Crystal Lake. I. Purpose- The purpose of this section is to establish standards for piers, mooring and swimming rafts and to regulate their placement upon Crystal
More informationNeighborhood Pedestrian Safety and Traffic Calming Study
Neighborhood Pedestrian Safety and Traffic Calming Study for the area bounded by Foster Avenue, Bedford Avenue, Farragut Road and Ocean Avenue Flatbush, Brooklyn, New York prepared by Michael King, miking@trafficcalmer.com
More informationWALKABILITY CHECKLIST How walkable is your community?
WALKABILITY CHECKLIST How walkable is your community? Everyone benefits from walking and other forms of active transportation. These benefits include: improved fitness, cleaner air, reduced risks of certain
More information2018 ROAD MAINTENANCE PROGRAM
2018 ROAD MAINTENANCE PROGRAM John Tiger Anastasi Town of Bethlehem Superintendent of Highways June 27, 2018 AGENDA Why do we maintain our roads? How is the Road Maintenance Plan developed? The process
More informationNew Orleans Municipal Yacht Harbor
New Orleans Municipal Yacht Harbor Marina Schematic Design Update 601 Poydras St., Suite 1860 New Orleans, LA, 70130 504-648-3560 Post-Katrina Municipal Yacht Harbor: Introduction The MYH was an approximate
More informationThe 2009 Manual on Uniform Traffic Control Devices (MUTCD) (Brief) Highlights for Arizona Practitioners. Arizona Department of Transportation
The 2009 Manual on Uniform Traffic Control Devices (MUTCD) (Brief) Highlights for Arizona Practitioners Arizona Department of Transportation New 2009 MUTCD 9 Parts (down from 10 in 2003) 816 pages (up
More informationWATER SURFACE USE ORDINANCE STATE OF MINNESOTA COUNTY OF CROW WING ORDINANCE NO. 83
WATER SURFACE USE ORDINANCE STATE OF MINNESOTA COUNTY OF CROW WING ORDINANCE NO. 83 AN ORDINANCE REGULATING THE SURFACE USE OF ALL WATERS OF CROW WING COUNTY Be it ordained and enacted by the Crow Wing
More informationTulsa Triathlon. Olympic Distance Course 2017
Race Location Birch Lake in Barnsdall, OK, Twin Coves Area - Google Map Location Driving Directions from Tulsa: Take HWY 75N to OK-20 Collinsville/Skiatook exit Turn left onto OK-20 W/ E 146th St N (signs
More informationADA Technical Frequently Asked Questions
ADA Technical Frequently Asked Questions 1. What is the correct way to select and label curb ramp types using the Standard Construction Details?... 2 2. When do you label a curb ramp as modified (e.g.
More informationCorpus Christi Metropolitan Transportation Plan Fiscal Year Introduction:
Introduction: The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) has continued the efforts started through the Intermodal Surface Transportation Efficiency
More informationADA TRANSITION PLAN 2013
ADA TRANSITION PLAN 2013 TABLE OF CONTENTS Contents Introduction 1 Purpose 2 Identified Obstacles to the Public Right of Way 3 Criteria for Determining Impediments at Village Facilities 4 Removing Barriers
More informationBicycle and Pedestrian Plans and Improvements
Bicycle and Pedestrian Plans and Improvements Presented to the City Council By Randle Harwood, Planning and Development, and Richard Zavala, Parks and Community Services September 24, 2013 Purpose Review
More informationCONDITION ASSESSMENT REPORT
CONDITION ASSESSMENT REPORT ALAMEDA ISLES PROPERTY ASSOCIATION - SMALL CRAFT HARBOR PREPARED BY: 564 AVALON PARK BLVD. E., SUITE 1 # 111 ORLANDO, FLORIDA 88 C.O.A. # 876 SCES Job No.: 106.05-15 MAY 015
More informationADA on Construction. Guidance for Section C Plan Preparers
ADA on Construction Guidance for Section C Plan Preparers Some impacts cannot be avoided and those impacts apply to residents, businesses, motorists, and pedestrians alike. However, good planning can minimize
More informationADA PRESENTATION (CURB RAMPS)
ADA PRESENTATION (CURB RAMPS) ACECNJ/NJDOT/FHWA DESIGN SUMMIT Warren Howard New Jersey Department of Transportation May 21, 2013 ADA Curb Ramps NJDOT wants curb ramps to be designed & constructed properly
More informationTulsa Triathlon Half Distance Course
Race Location Birch Lake in Barnsdall, OK, Twin Coves Area - Google Map Location Driving Directions from Tulsa: Take HWY 75N to OK-20 Collinsville/Skiatook exit Turn left onto OK-20 W/ E 146th St N (signs
More informationAccommodating Pedestrians in the Work Zone
Accommodating Pedestrians in the Work Zone Guidance for Section C Plan Preparers Some impacts cannot be avoided and those impacts apply to residents, businesses, motorists, and pedestrians alike. However,
More information***This summary does not include shad and herring net requirements.***
South Carolina Department of Natural Resources Marine Resources Division Summary of Seine and Gill Net Laws (Saltwater) 2013-2014 This document should be kept on board all vessels using seines or gill
More informationDraft. Lecompton. Table of Contents. Background
Lecompton Table of Contents Existing Infrastructure 80 Funding 82 Policy and Program Recommendations 83 Infrastructure Implementation Scenarios 84 Conclusion 85 Douglas County Lecompton Background Located
More informationVision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods
N D. Focus Area II Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods Transit Road Focus Area II is located in the Hamlet
More informationSmoothing Out the Bumpy Road Ahead
Julie Hannah, P.E. Technical Services and Asset Management May 11, 2017 Smoothing Out the Bumpy Road Ahead Nationwide D = Poor, At Risk Conditions & Capacity Pavement Condition & Congestion Nationwide
More informationComments The Plan for Port Whitby
Comments The Plan for Port Whitby April 24th, 2013 Community Meeting #2 Summary Report Prepared by GLPi April 29th, 2013 1 Introduction The purpose of the Port Whitby Secondary Plan Update, Community Improvement
More informationAN EARTHWORK HILL, RINGED WITH SEATING AND SHAPED TO SLOPE DOWN TO THE RIVER, FORMS THE CENTERPIECE TO A NEW SOCIAL PIER. A WOOD SEATING TERRACE
AN EARTHWORK HILL, RINGED WITH SEATING AND SHAPED TO SLOPE DOWN TO THE RIVER, FORMS THE CENTERPIECE TO A NEW SOCIAL PIER. A WOOD SEATING TERRACE FACES SOUTH. A DRAMATIC RAMP RISES ALONG THE NORTH FACE
More informationFill in the rating for each section. Total up the ratings to see how your neighbourhood scores overall for walkability.
WALKABILITY CHECKLIST How walkable is your community? Everyone benefits from walking and other forms of active transportation. These benefits include: improved fitness, cleaner air, reduced risks of certain
More informationImprove the livability of our streets by
Pedestrian and Traffic Calming Policy March 2018 2 of 6 Neighborhood Traffic Calming Policy The City of Aspen continually strives to protect multimodal function while maintaining a high standard of safety.
More informationPine Point Study Committee. Report and Recommendations to Scarborough Town Council. December 10, 2009
The Delphi Group, Inc Results through Alignment: Linking Direction, Capability & Commitment Pine Point Study Committee Report and Recommendations to Scarborough Town Council December 10, 2009 Committee
More informationCommittee Input No. 35-NFPA [ Chapter 1 ] Submitter Information Verification. Committee Statement
Committee Input No. 35-NFPA 1670-2015 [ Chapter 1 ] Chapter 1 Administration 1.1 Scope. 1.1.1* This standard shall identify and establish levels of functional capability for conducting operations at technical
More informationSD Highway 50 in Yankton (4 TH Street) Reconstruction Project NH 0050(99)381 PCN By Josh Larson McLaury Engineering Inc.
SD Highway 50 in Yankton (4 TH Street) Reconstruction Project NH 0050(99)381 PCN 6926 By Josh Larson McLaury Engineering Inc. Project Limits SD 50 from Broadway to Burleigh and from Marne Creek to Archery
More informationMid Rivers Mall Drive Multi-Use Path (Rte. N to MO 364)
Mid Rivers Mall Drive Multi-Use Path (Rte. N to MO 364) Sponsor St Peters Project No. RB19-000022 Project Type Other TOTAL FUNDING Total County Sponsor Federal $1,177,251.00 $238,179.00 $59,546.00 $879,526.00
More informationProject Fact Sheet July, 2018
BELLEVUE AND SYRINGA BIKE SKILLS PARKS Project Fact Sheet July, 2018 Bike parks construction expected to start in August, 2018 After completing a competitive bid process, the City has accepted a bid from
More informationCONNECTICUT RIVER WATERSHED COUNCIL The River Connects Us
CONNECTICUT RIVER WATERSHED COUNCIL The River Connects Us Upper Valley: P.O. Box 206, Saxtons River, VT 05154 Electronic Filing UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Grafton Hydro,
More informationChapter 4: Funding and Implementation
Chapter 4: Funding and Implementation 83 84 Cost Estimating Cost estimating is an iterative process. When a project is in the conceptual stage, preliminary cost estimates are also provided conceptually,
More informationADA Design Overview. Section 2. ADA Design Overview. Pedestrian Access Routes. Pedestrian Access Routes. Overview
ADA Design Overview Section 2 ADA Design Overview Overview Accessible Pedestrian Signals Alternate Fall, 2017 Ann Johnson, PE Services Brady Rutman, SRF Consulting Group 2 Pedestrian Access Route (PAR)
More informationECONOMY PEOPLE ENVIRONMENT
Report Back on Local Transit Improvements May 29, 2013 ECONOMY PEOPLE ENVIRONMENT Intro Council Requested Report Back Topics Progress on Planning for Broadway Subway False Creek Bridges Local Transit Improvements
More informationFulton Market Streetscape
Fulton Market Streetscape Ogden Avenue to Halsted Street Public Meeting Recommended Improvements December 10th, 2014 Meeting Purpose and Goals Present Existing Conditions Community Input and Charrette
More informationAMERICANS WITH DISABILITIES ACT TRANSITION PLAN LEON COUNTY FOR CURB RAMPS AND SIDEWALKS DEPARTMENT OF PUBLIC WORKS. 1 P age
AMERICANS WITH DISABILITIES ACT TRANSITION PLAN FOR CURB RAMPS AND SIDEWALKS 2015 LEON COUNTY DEPARTMENT OF PUBLIC WORKS 1 P age INTRODUCTION The goal of the Americans with Disabilities Act (ADA) Transition
More informationLegislative Update Williamsburg Residency
Hampton Roads District Legislative Update Williamsburg Residency Jim Brewer, Resident Administrator 757-253-5140 Projects Under Way Warwick Boulevard Project http://www.warwickboulevard.org/ Contractors:
More informationShoreline Studies Program, Department of Physical Sciences, VIMS
Living Shoreline Training Class 2017 1 Demonstration sites discussed in this talk. 2 A shoreline management plan for the entire creek made conceptual shoreline management recommendations along every stretch
More informationLake Lackawanna Investment Company, Inc.
Post Office 89 Byram Township, New Jersey 07874 Rules and Regulations for the Use of Facilities 1) INTRODUCTION - The rules, regulations and definitions listed on this and the following pages are designed
More informationATLANTIC COAST OF LONG ISLAND, JONES INLET TO EAST ROCKAWAY INLET, LONG BEACH ISLAND, NY. Contract #2 Construction Scope. April 18th-19th 2018
ATLANTIC COAST OF LONG ISLAND, JONES INLET TO EAST ROCKAWAY INLET, LONG BEACH ISLAND, NY Contract #2 Construction Scope April 18th-19th 2018 New York District PLAN COMPONENTS Length of Beachfill 35,000
More informationHabitat Development: Habitat Boulders Lawson Pier Foreshore Enhancement
Habitat Development: Habitat Boulders Improve the existing habitat by stabilising beach sediments. Increase biodiversity by creating new habitats and colonisation opportunities. Loose cobble is unstable;
More informationTownship of Springwater
Township of Springwater Approved: November 2008 Effective: Date of Passing Next Review: TBD Department: Public Works Subject: Sidewalks Policy Number: A09 SI A. Authority This policy shall be approved
More information01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS
01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS Existing Bus Stop Existing US101 On-ramp Existing POC Old Redwood Highway Rich Street City ROW Environmental Study Limit Industrial Way NO DESIGNATED
More informationSAFETY GUIDELINES: Oregon Association of Rowers Revised October 2017
INTRODUCTION These Safety Guidelines are to help educate members regarding their responsibility for their own safety at all times. See also OAR Policies & Procedures Manual for additional information.
More informationFebruary 11, 2016 TPO Board Presentation
February 11, 2016 TPO Board Presentation SR A1A (Highway A1A) US 192 to SR 404 (Pineda Causeway), Brevard County, Florida Financial Project Number: 428753-1-32-01 Project Limits US 192 to SR 404 (428753-1)
More informationWillamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge Citizen Advisory Committee
Portland - Milwaukie Light Rail Willamette River Bridge Citizen Advisory Committee 05.21.09 Bridge Type Status Update Bicycle Pedestrian Path Width Bridge Type Status Update WRBAC Recommendation: Cable
More informationCITY OF SAINT JOHN TRAFFIC CALMING POLICY
CITY OF SAINT JOHN TRAFFIC CALMING POLICY VERSION: 1.0 April 10, 2012 Pedestrians, Cyclists and Motorists Sharing Street Spaces CONTENTS INTRODUCTION... 3 POLICY GOAL... 3 POLICY OBJECTIVES... 3 GUIDING
More informationTULSA CITY COUNCIL CAPITAL IMPROVEMENT PROGRAM TASK FORCE MEETING JANUARY
CITY OF TULSA BICYCLE & PEDESTRIAN INFRASTRUCTURE TULSA CITY COUNCIL CAPITAL IMPROVEMENT PROGRAM TASK FORCE MEETING JANUARY 31, 2013 CITY OF TULSA ENGINEERING SERVICES DEPARTMENT CITY OF TULSA ADA TRANSITION
More informationTOWN OF AURORA. Pool Enclosure Permit Guide. PLANNING AND BUILDING SERVICES Building Division
TOWN OF AURORA Pool Enclosure Permit Guide PLANNING AND BUILDING SERVICES Building Division Phone: 905-727-3123 ext. 4388 Fax: 905-726-4731 Email: building@aurora.ca Town of Aurora 100 John West Way, Box
More informationCounty of Greenville South Carolina. Traffic Calming Program Neighborhood Traffic Education Program and Speed Hump Program
County of Greenville South Carolina Traffic Calming Program Neighborhood Traffic Education Program and Speed Hump Program (rev) August 2008 I. PURPOSE The potential negative impacts from vehicular traffic
More informationLAKE TROY DOUGLAS ~~~RULES and REGULATIONS~~~
McLendon Hills Property Owners Association P. O. Box 178, Eagle Springs, NC 27242 LAKE and WILDLIFE COMMITTEE LAKE TROY DOUGLAS ~~~RULES and REGULATIONS~~~ INTRODUCTION The following rules and regulations
More informationRC-67M has been updated to include more details to be consistent with both ADAAG and PROWAG. The following slides discusses the general notes found
RC-67M has been updated to include more details to be consistent with both ADAAG and PROWAG. The following slides discusses the general notes found on Sheet 1. RC-67M note Construct curb ramps with a minimum
More informationBuilding Great Neighbourhoods BELLEVUE AND VIRGINIA PARK
Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK This is Meeting 2 Unfortunately, some residents in Bellevue and Virginia Park received the wrong information for this public open house (Meeting
More informationPedestrian Project List and Prioritization
To: Kyle Wagenschutz, City of Memphis CC: From: Anne Conlon and John Cock, Alta Planning + Design Date: December, 2014 Re: Project List Development (Task 3.1-3.2) and Project List Prioritization (Task
More informationBOAT HANDLING METHODS FOR YARD SPACE EFFICIENCY
BOAT HANDLING METHODS FOR YARD SPACE EFFICIENCY May 2008 PRESENT SITUATION Increasing value of coastal real estate Increase number of boats Increasing labor cost Liability DEFINE THE MARKET: Boats handled
More informationDRAFT. System Components. Greenway Trails. Introduction. Trail Types. Zebulon Greenway Master Plan
5 System Components Wakefield Street Photo Simulation showing Sharrows Introduction The Master Plan identifies various system components that, together, create a comprehensive greenway system. These components
More informationTrans-Canada Highway 1 RW Bruhn Bridge Replacement
Trans-Canada Highway 1 RW Bruhn Bridge Replacement May 2016 RW Bruhn Bridge Project Objectives Improve safety, traffic flow and movement of goods Improve safety for pedestrians and cyclists Replace the
More information