1 Scope of Work for Use of the Fish Bypass at New Savannah Bluff Lock and Dam for the Savannah Harbor Expansion Project Monitoring and Adaptive Management Program Savannah River, Georgia and South Carolina 1.0 INTRODUCTION. As part of the Savannah Harbor Expansion Project, the US Army Corps of Engineers, Savannah District (Corps) committed to monitor the use of sturgeon and anadromous fish of the offchannel rock ramp bypass that the project is constructing around the New Savannah Bluff Lock and Dam near Augusta, Georgia. The South Carolina Department of Natural Resources (SC DNR) will conduct telemetry studies as identified in this scope of work (SOW) to collect information on fish use of the structure, analyze the data, and provide reports to the Corps. 2.0 WORK TO BE PERFORMED. Telemetry Monitoring Atlantic and Shortnose sturgeon use of the off-channel rock ramp fish bypass at the New Savannah Bluff Lock and Dam will be accomplished through the use of telemetry and sonic transmitters. The work will identify the distribution of sturgeon in the upper Savannah River over the course of a year and identify seasonal habitats, migration patterns, and possibly spawning locations. The work would be conducted using the same type of transmitters and receivers as are presently being used by SC DNR in a study they are performing for NOAA Fisheries titled Research and Management of Endangered and Threatened Species in the Southeast: Riverine Movements of Shortnose and Atlantic sturgeon. Different models of transmitters and receivers may be used with prior permission from the Corps. For the pre-construction monitoring period, SC DNR would acquire and insert 10 sonic transmitters into Atlantic sturgeon in the Savannah River, 10 sonic transmitters into Shortnose sturgeon, and 20 sonic transmitters into other species representative of the NSBL&D area fish community (Striped bass, Robust redhorse, and American shad). If sufficient numbers of sturgeon are not available for capturing, tagging and tracking in the upper river, transmitters can be implanted in other species representative of the NSBL&D area fish community, preferably American shad. The Corps has committed to performing post-construction monitoring of sturgeon during years one, two, three, four, five, and nine of the post-construction monitoring period. This scope of Page 1 of 6

2 work only covers the first five years of work or work to be completed by the end of year 2018; it does not include work to be performed for the entire post-construction monitoring period. It is anticipated that transmitters must be deployed multiple times as outlined below. At the beginning of the post-construction monitoring period (Year 1), SC DNR would acquire and insert 10 sonic transmitters into Atlantic sturgeon, 10 sonic transmitters into Shortnose sturgeon, and 50 sonic transmitters into other species representative of the NSBL&D area fish community (Striped bass, Robust redhorse, and (preferably) American shad). If sufficient numbers of sturgeon are not available for capturing, tagging and tracking in the upper river, transmitters can be implanted in other species representative of the NSBL&D area fish community listed above. For the years in the post-construction monitoring period (2017 and 2018 for this scope of work), SC DNR would acquire and insert ten sonic transmitters into Atlantic sturgeon in the Savannah River and 10 sonic transmitters into Shortnose sturgeon. If sufficient numbers of sturgeon are not available for capturing, tagging and tracking in the upper river, transmitters can be implanted in other species representative of the NSBL&D area fish community (Striped bass, Robust redhorse, and American shad). If possible, fish would be captured within 1 km of the dam by hook and line, gill net, or other approved sampling gear. All fish implanted will be weighed, measured, Passive Integrated Transponder (PIT) tagged, and have a fin clip taken for genetic analysis before being released. Distribution monitoring would be performed using an array of fixed receivers deployed in the estuary and along the river to constantly monitor the location of the transmitted fish. The receivers would be downloaded as needed to ensure a continuous dataset is obtained of the location of transmitted fish. Acquisition, operation and maintenance of 20 receivers are included in this SOW, with an additional 10% (2 receivers) allowance to account for replacement of lost/inoperable receivers. The receivers funded by this SOW would be concentrated around the fish bypass at the NSBL&D. The focus of the distribution of the receivers is to be able to identify the movement of sturgeon through the off-channel rock ramp bypass. A receiver generally picks up a signal within several hundred yards of its location, so each receiver will effectively collect data across the entire river. However, the hydraulic conditions in the rock ramp bypass will be quite turbulent, potentially reducing the effectiveness of identifying specific locations of fish. In addition, since the rock ramp will provide habitats similar to natural riffles, fish may choose to spawn within the ramp and not proceed to natural spawning areas upstream (such as those at the Augusta Shoals). The location of fish within the rock ramp will also be useful information. Page 2 of 6

3 Therefore, to increase the ability to identify fish movement in and through the rock ramp, receivers should be located no more than 200 yards apart in the rock ramp and placed on both sides of the ramp to allow triangulation of fish locations. Additional receivers will be located in the Savannah River near the upstream and downstream end of the ramp, one additional receiver would be placed within 300 yards of the upstream end of the ramp and another located within 300 yards of the downstream end of the ramp. These would allow more precise locating of fish approaching and exiting the ramp. Based on the expected length for the rock ramp of between 1,300 to 1,900 feet, this spacing would result in the placement of 8 receivers to monitor fish movement through the rock ramp. Another 2 receivers would be needed to monitor fish movement near the entrance and exit of the rock ramp. The spacing of receivers should be much greater away from the rock ramp. To allow identification of fish movement upstream of the NSBL&D (between the L&D and Augusta Shoals), the contractor should locate 5 receivers between the NSBL&D and the Augusta Shoals. In general, 3 of those 5 should be located upstream of the Thirteen Street Bridge (River Mile 201). Another 5 receivers should be located downstream of the dam, extending down the Savannah River to Interstate 95. Prior to placement of the receivers, SC DNR will provide the Corps with a draft map for approval illustrating the proposed locations where receivers would be placed. Manual Tracking / Habitat Characterization Manual tracking of instrumented fish will occur in and near the rock ramp. This work would be performed one day a week for 6 weeks during the sturgeon spawning season. Water temperature will be determined at the location of at least 10 telemetered sturgeon during each manual tracking event. The objective of this work is to more precisely identify the location and habitats used by telemetered fish. Water Quality In addition to the monitoring described above, the Corps has committed to monitoring certain water quality parameters in the vicinity of the lock and dam. Temperature shall be recorded using temperature loggers established at fixed locations at NSBL&D, 1, 10, 50, 100 and 200 km below the dam, and 1 km above the dam. If existing monitors are already in place in similar locations, then the work may be accomplished using those monitors with prior approval from the Corps. Based on available information, it is anticipated that, for year 1, a new station must be installed for the 10km location. Dissolved oxygen concentration, turbidity, and river stage at NSBL&D would be recorded at least weekly. Dam discharge will be recorded daily. All data collected should be included in the reporting requirements described below in Section 6.0. Page 3 of 6

4 3.0 SCHEDULE. The period of performance to conduct work identified in this scope is one year (365 days) from award of the task order. Initial installation of transmitters would be conducted in the fall of 2013 and spring of The telemetry would begin in the spring of 2014 and continue for the remainder of the period of performance (one year). The monitoring in 2014 would serve as a baseline for additional studies that would be performed after the fish bypass is constructed. Under the current cooperative agreement, SC DNR would perform the telemetry and tracking work intermittently through It is expected that new task orders will be issued to SC DNR to perform the same telemetry and manual tracking/habitat characterization work described above each of the identified years (baseline and in years one, and two after the fish passage is available for use). Using the present schedule and a two year construction period for the bypass, the sturgeon monitoring would be performed in the spring of 2014, 2017, and Water quality would be monitored continuously. A new task order will be issued each year to fund this work. 4.0 QUALITY ASSURANCE. SC DNR will perform quality assurance on the sampling and data reporting process to ensure data integrity. 5.0 RESULTS. The contractor would present the telemetry data of Atlantic and Shortnose sturgeon, and other representative anadromous fish species near the New Savannah Bluff Lock and Dam collected through this SOW. At a minimum, each sturgeon location record will include date and time of location and this information will be used to determine the timing and rate of movement, and the amount of time each fish spent in various areas. The data should be presented by species. The presentation of the data will also include consideration of the water quality conditions determined during the manual tracking / habitat component of the work. 6.0 REPORTING. The data will be reported to the UGA Center for Remote Sensing and Mapping Science on a monthly basis using a format to be provided separately by the Corps. The data will also be reported to the Clemson University Intelligent River Program. Analysis of the data will be included in an annual report. The annual report will describe the equipment and techniques used, data collected, and analyses performed that year under this SOW. Figures will be used to show the locations of the tracked fish. A draft of this separate report will be provided within 60 days of the end of the FY. After receipt of comments from the Corps, the contractor will provide a final report within two weeks. Page 4 of 6

5 The report provided in the final year of the study will be a consolidated report that also summarizes the results found over the entire period of analysis. Page 5 of 6

6 7.0 PROJECT MANAGEMENT. The Points of Contact for this Scope of Work are as follows: SC DNR: Mr. William Post Diadromous Fishes Coordinator SC Department of Natural Resources P.O. Box Charleston, SC Phone: Fax: Corps Technical POC: Ms. Margarett McIntosh US Army Corps of Engineers, Savannah District ATTN: PD-E 100 West Oglethorpe Avenue Savannah, Georgia Phone: Fax: Corps Coordination POC: Mr. William Bailey US Army Corps of Engineers, Savannah District ATTN: PD 100 West Oglethorpe Avenue Savannah, Georgia Phone: PAYMENT. The funding will be provided through a Cooperative Agreement with SC DNR. Specific billing instructions are included in that Agreement. SC DNR will bill the Savannah District on a quarterly basis. The invoices will be sent to the Corps Coordination POC identified above. Page 6 of 6

Savannah Harbor Expansion Project

Savannah Harbor Expansion Project Savannah Harbor Expansion Project SHEP Progress Report April 1 st April 30 th 2016 Task 1: SCDNR would acquire and insert 10 sonic transmitters per year into Atlantic sturgeon in the Savannah River Estuary

More information

Evaluating Atlantic and Shortnose Sturgeon Behavior Related to the Savannah Harbor Expansion Project

Evaluating Atlantic and Shortnose Sturgeon Behavior Related to the Savannah Harbor Expansion Project Evaluating Atlantic and Shortnose Sturgeon Behavior Related to the Savannah Harbor Expansion Project Cooperative Agreement Numbers W912EP-13-2-0002-0004 & W912EP-13-2-0002-0003 Annual Report FY 2014 (November

More information

Performance Report. B. Project Title: Evaluating Atlantic and Shortnose Sturgeon Behavior Related to the Savannah Harbor Expansion Project

Performance Report. B. Project Title: Evaluating Atlantic and Shortnose Sturgeon Behavior Related to the Savannah Harbor Expansion Project Performance Report A. Grantee: S. C. Department of Natural Resources B. Project Title: Evaluating Atlantic and Shortnose Sturgeon Behavior Related to the Savannah Harbor Expansion Project C. Principle

More information

Restoration of Spawning Habitat for Native Fish in the Central Great Lakes

Restoration of Spawning Habitat for Native Fish in the Central Great Lakes Restoration of Spawning Habitat for Native Fish in the Central Great Lakes D. H. B E N N I O N 1, E. R O S E M A N 1, B. M A N N Y 1, G. K E N N E D Y 1, J. B O A S E 2, J C R A I G 1 1 U S G S - G R E

More information

Session B7 - Santee-Cooper: A Lock on Fish Passage Success

Session B7 - Santee-Cooper: A Lock on Fish Passage Success University of Massachusetts - Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish

More information

SALUDA HYDROELECTRIC PROJECT (FERC NO. 516) STUDY PLAN

SALUDA HYDROELECTRIC PROJECT (FERC NO. 516) STUDY PLAN SALUDA HYDROELECTRIC PROJECT (FERC NO. 516) STUDY PLAN Study Plan Name: Status of the Shortnose Sturgeon in the Lower Saluda and Upper Congaree Rivers Applicable Hydro Projects: Saluda Hydro FERC No. 516

More information

The Life History and Management of Alewife (Alosa pseudoharengus)

The Life History and Management of Alewife (Alosa pseudoharengus) The Life History and Management of Alewife (Alosa pseudoharengus) Abigail Franklin, University of Massachusetts, Amherst Department of Natural Resources Conservation The Biology and Management of Alewife

More information

Rhode Island Department of Environmental Management Division of Fish and Wildlife American Shad Habitat Plan for the Pawcatuck River

Rhode Island Department of Environmental Management Division of Fish and Wildlife American Shad Habitat Plan for the Pawcatuck River Rhode Island Department of Environmental Management Division of Fish and Wildlife American Shad Habitat Plan for the Pawcatuck River Prepared by: Phil Edwards, Rhode Island Department of Environmental

More information

APPENDIX A-6 SALUDA HYDROELECTRIC PROJECT STURGEON PROTECTION AND ADAPTIVE MANAGEMENT PROGRAM

APPENDIX A-6 SALUDA HYDROELECTRIC PROJECT STURGEON PROTECTION AND ADAPTIVE MANAGEMENT PROGRAM APPENDIX A-6 SALUDA HYDROELECTRIC PROJECT STURGEON PROTECTION AND ADAPTIVE MANAGEMENT PROGRAM SOUTH CAROLINA ELECTRIC & GAS COMPANY COLUMBIA, SOUTH CAROLINA SALUDA HYDROELECTRIC PROJECT (FERC NO. 516)

More information

Near-Field Sturgeon Monitoring for the New NY Bridge at Tappan Zee. Quarterly Report July 1 September 30, 2014

Near-Field Sturgeon Monitoring for the New NY Bridge at Tappan Zee. Quarterly Report July 1 September 30, 2014 Near-Field Sturgeon Monitoring for the New NY Bridge at Tappan Zee Quarterly Report July 1 September 30, 2014 Prepared by AKRF, Inc. 7250 Parkway Drive, Suite 210 Hanover, MD 21076 for New York State Thruway

More information

VIDEO AUDIO Slide 1. Slide 2 Old timey 18 th century map of east coast

VIDEO AUDIO Slide 1. Slide 2 Old timey 18 th century map of east coast VIDEO AUDIO Slide 1 1A Welcome to the Cooper River Rediversion Project at St. Stephen, Montage of exteriors of facility, South Carolina! Since 1985, this boating, fish runs, fishing, facility has served

More information

San Joaquin River Chinook Salmon Trap and Haul Donald E. Portz, PhD Bureau of Reclamation Fisheries & Wildlife Resources Group

San Joaquin River Chinook Salmon Trap and Haul Donald E. Portz, PhD Bureau of Reclamation Fisheries & Wildlife Resources Group San Joaquin River Chinook Salmon Trap and Haul Donald E. Portz, PhD Bureau of Reclamation Fisheries & Wildlife Resources Group Water Management Technical Feedback Group Visalia, CA Adult Chinook Salmon

More information

SOUTH ATLANTIC FISHERY MANAGEMENT COUNCIL

SOUTH ATLANTIC FISHERY MANAGEMENT COUNCIL 1 SOUTH ATLANTIC FISHERY MANAGEMENT COUNCIL ONE SOUTHPARK CIRCLE, SUITE 306 CHARLESTON, SOUTH CAROLINA 29407-4699 TEL 843/571-4366 or FAX 843/769-4520 Toll Free 1-866/SAFMC-10 E-mail: safmc@safmc.net Web

More information

Recreational Sturgeon Commercial Shad MANAGEMENT GUIDELINES

Recreational Sturgeon Commercial Shad MANAGEMENT GUIDELINES OREGON AND WASHINGTON DEPARTMENTS OF FISH AND WILDLIFE JOINT STAFF REPORT - SUMMER FACT SHEET NO. 2 Columbia River Compact/Joint State Hearing June 28, 2005 Fisheries under consideration: Recreational

More information

FISH PROTECTION ACTIVITIES AT PRADO DAM, CORONA, CA.

FISH PROTECTION ACTIVITIES AT PRADO DAM, CORONA, CA. San Marino Environmental Associates 560 South Greenwood Avenue, San Marino, CA 91108 (626) 792-2382 FAX (626) 792-8233 s FISH PROTECTION ACTIVITIES AT PRADO DAM, CORONA, CA. Prepared for: U. S. Army Corps

More information

Study 9.5 Fish Distribution and Abundance in the Upper Susitna River

Study 9.5 Fish Distribution and Abundance in the Upper Susitna River Initial Study Report Meeting Study 9.5 Fish Distribution and Abundance in the Upper Susitna River October 15, 2014 Prepared by R2 Resource Consultants, Inc. 10/15/2014 1 Study 9.5 Objectives 1. Describe

More information

Atlantic Sturgeon Workshop

Atlantic Sturgeon Workshop Atlantic Sturgeon Workshop Emily B. Hughes Wilmington Regulatory Field Office September 3, 2013 US Army Corps of Engineers Introduction The Atlantic sturgeon (Acipenser oxyrinchus; means "sharp snout )

More information

Endangered Species Act and FERC Hydroelectric Projects. Jeff Murphy & Julie Crocker NHA New England Meeting November 16, 2010

Endangered Species Act and FERC Hydroelectric Projects. Jeff Murphy & Julie Crocker NHA New England Meeting November 16, 2010 Endangered Species Act and FERC Hydroelectric Projects Jeff Murphy & Julie Crocker NHA New England Meeting November 16, 2010 Shortnose Sturgeon Federally listed as endangered in 1967 Listed under the sole

More information

Patterns of migration and delay observed in Summer Steelhead from the Upper Columbia and Snake River Basins from PIT tag data

Patterns of migration and delay observed in Summer Steelhead from the Upper Columbia and Snake River Basins from PIT tag data West Coast Region Patterns of migration and delay observed in Summer Steelhead from the Upper Columbia and Snake River Basins from PIT tag data Blane Bellerud August, 2015 Columbia River Basin Columbia

More information

Appendix F: Ecology F-6 Methodology for Estimating Potential Hydroacoustic Impacts to Abundant Hudson River Fish Species and Shortnose Sturgeon from

Appendix F: Ecology F-6 Methodology for Estimating Potential Hydroacoustic Impacts to Abundant Hudson River Fish Species and Shortnose Sturgeon from Appendix F: Ecology F-6 Methodology for Estimating Potential Hydroacoustic Impacts to Abundant Hudson River Fish Species and Shortnose Sturgeon from Pile-driving Activities during Construction of the Tappan

More information

ASMFC American Shad Sustainable Fishing Plan for Georgia

ASMFC American Shad Sustainable Fishing Plan for Georgia ASMFC American Shad Sustainable Fishing Plan for Georgia Introduction: Submitted by Don Harrison Georgia Department of Natural Resources Wildlife Resources Division P.O. Box 289, 18 Darling Avenue Waycross,

More information

E.D. Chapman, A.R. Hearn, A.P. Klimley, P.E. LaCivita, W.N. Brostoff & A.M. Bremner

E.D. Chapman, A.R. Hearn, A.P. Klimley, P.E. LaCivita, W.N. Brostoff & A.M. Bremner Migration of late-fall Chinook and steelhead smolts relative to dredge removal and disposal sites in San Francisco Bay US Army Corps of Engineers E.D. Chapman, A.R. Hearn, A.P. Klimley, P.E. LaCivita,

More information

Atlantic Sturgeon Update NER Protected Resources

Atlantic Sturgeon Update NER Protected Resources Atlantic Sturgeon Update NER Protected Resources June 18, 2013 Outline Brief background Update on information available for Atlantic sturgeon Overview of draft batched fisheries Biological Opinion (BiOp)

More information

Upstream Passage Assessment of American Shad Using 3D Acoustic Telemetry

Upstream Passage Assessment of American Shad Using 3D Acoustic Telemetry Upstream Passage Assessment of American Shad Using 3D Acoustic Telemetry Timothy Hogan, Alden Research Laboratory Corey Wright, Blue Leaf Environmental Skip Medford, Enel Green Power North America Abstract

More information

Klamath River Green Sturgeon Acoustic Biotelemetry Monitoring 2008 FINAL Technical Memorandum

Klamath River Green Sturgeon Acoustic Biotelemetry Monitoring 2008 FINAL Technical Memorandum Klamath River Green Sturgeon Acoustic Biotelemetry Monitoring Barry W. McCovey Jr. January 2009 Yurok Tribal Fisheries Program Klamath River Division Box 196 Hwy. 96, Weitchpec Rt. Hoopa, CA, 95546 Introduction

More information

I. Project Title: Annual Operation and Maintenance of the Fish Passage Structure at the Government Highline Diversion Dam on the Upper Colorado River

I. Project Title: Annual Operation and Maintenance of the Fish Passage Structure at the Government Highline Diversion Dam on the Upper Colorado River COLORADO RIVER RECOVERY PROGRAM FY 2011 ANNUAL PROJECT REPORT RECOVERY PROGRAM PROJECT NUMBER: C4b-GVP I. Project Title: Annual Operation and Maintenance of the Fish Passage Structure at the Government

More information

Within Phase I, researchers have identified four tasks that they think are essential for designing the most informative study.

Within Phase I, researchers have identified four tasks that they think are essential for designing the most informative study. Revised Study Plan June 30, 2005 I. Introduction The Merwin upstream fish passage facility was originally completed with construction of the Merwin Dam. This trapping facility historically operated with

More information

Technical Report 99-6 EVALUATION OF RUNNING TURBINE 1 AT MAXIMUM CAPACITY ON PASSAGE OF ADULT SALMON AND STEELHEAD AT JOHN DAY DAM

Technical Report 99-6 EVALUATION OF RUNNING TURBINE 1 AT MAXIMUM CAPACITY ON PASSAGE OF ADULT SALMON AND STEELHEAD AT JOHN DAY DAM Technical Report 99-6 EVALUATION OF RUNNING TURBINE 1 AT MAXIMUM CAPACITY ON PASSAGE OF ADULT SALMON AND STEELHEAD AT JOHN DAY DAM - 1997 A report for Project MPE-P-95-1 by T.C. Bjornn, C.A. Peery, K.R.

More information

Proposed Critical Habitat for Atlantic Sturgeon. Atlantic States Marine Fisheries Commission August 2, 2016

Proposed Critical Habitat for Atlantic Sturgeon. Atlantic States Marine Fisheries Commission August 2, 2016 Proposed Critical Habitat for Atlantic Sturgeon Atlantic States Marine Fisheries Commission August 2, 2016 Proposed Rules Federal Register, June 3, 2016 Two Rules with the same public comment period 81

More information

Summary Report of the North Carolina Division of Marine Fisheries Cobia (Rachycentron canadum) Acoustic Tagging. Stephen J. Poland SEDAR58-SID-06

Summary Report of the North Carolina Division of Marine Fisheries Cobia (Rachycentron canadum) Acoustic Tagging. Stephen J. Poland SEDAR58-SID-06 Summary Report of the North Carolina Division of Marine Fisheries Cobia (Rachycentron canadum) Acoustic Tagging Stephen J. Poland SEDAR58-SID-06 Submitted: 29 March 2018 This information is distributed

More information

BULL TROUT OPERATIONAL PLAN

BULL TROUT OPERATIONAL PLAN BULL TROUT OPERATIONAL PLAN ROCKY REACH HYDROELECTRIC PROJECT FERC Project No. 2145 April 10, 2001 Public Utility District No. 1 of Chelan County Wenatchee, Washington BULL TROUT OPERATIONAL PLAN This

More information

Rahway River Fish Passage Feasibility Evaluation. Weston Solutions, Inc. February 5, 2009

Rahway River Fish Passage Feasibility Evaluation. Weston Solutions, Inc. February 5, 2009 Rahway River Fish Passage Feasibility Evaluation Weston Solutions, Inc. February 5, 2009 Project Impetus Learned of the potential for fish passage on the Rahway River during meetings with the HEP and local

More information

Job 1 Part JOB 1, PART 2: SUMMARY OF CONOWINGO DAM WEST FISH LIFT OPERATIONS, 2009

Job 1 Part JOB 1, PART 2: SUMMARY OF CONOWINGO DAM WEST FISH LIFT OPERATIONS, 2009 2.0 JOB 1, PART 2: SUMMARY OF CONOWINGO DAM WEST FISH LIFT OPERATIONS, 2009 Lawrence M. Miller Normandeau Associates U. S. Fish and Wildlife Service 1921 River Road Harrisburg, Pennsylvania Drumore, Pennsylvania

More information

Essential Fish Habitat: An overview of the consultation requirement for the American Association of Port Authorities

Essential Fish Habitat: An overview of the consultation requirement for the American Association of Port Authorities Essential Fish Habitat: An overview of the consultation requirement for the American Association of Port Authorities National Marine Fisheries Service, Southeast Regional Office Habitat Conservation Division,

More information

Listed species under the jurisdiction of NOAA Fisheries that occur in the geographic area of responsibility of the Wilmington District are:

Listed species under the jurisdiction of NOAA Fisheries that occur in the geographic area of responsibility of the Wilmington District are: Information to assist in compliance with Nationwide Permit General Condition 18, Endangered Species Required Reporting via Pre-Construction Notification The purpose of this document is to provide information

More information

Agenda Item 7.1 For Information. Council CNL(10)24. Annual Report on Actions Taken Under Implementation Plans USA

Agenda Item 7.1 For Information. Council CNL(10)24. Annual Report on Actions Taken Under Implementation Plans USA Agenda Item 7.1 For Information Council CNL(10)24 Annual Report on Actions Taken Under Implementation Plans USA Annual Report on actions taken under the US Implementation Plan for the Calendar Year 2009

More information

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By:

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By: FINAL REPORT Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County Submitted By: Del Norte County Community Development Department Yonkers Creek Migration Barrier Removal Project

More information

STURGEON CONSERVATION

STURGEON CONSERVATION MIDDLE SCHOOL DISCUSSION GUIDE DISCUSSION GUIDE STURGEON CONSERVATION Natural Resource Science DISCUSSION GUIDE OVERVIEW GRADE LEVELS - Grades 6-8 ENDURING KNOWLEDGE Students should know the history of

More information

Fish Passage Studies I: Sea Lamprey Behaviour During Negotaiton of Technical and Nature-Like Fish Passes

Fish Passage Studies I: Sea Lamprey Behaviour During Negotaiton of Technical and Nature-Like Fish Passes University of Massachusetts - Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish

More information

Alberta Conservation Association 2009/10 Project Summary Report. Project Name: North Saskatchewan and Ram Rivers Bull Trout Spawning Stock Assessment

Alberta Conservation Association 2009/10 Project Summary Report. Project Name: North Saskatchewan and Ram Rivers Bull Trout Spawning Stock Assessment Alberta Conservation Association 2009/10 Project Summary Report Project Name: North Saskatchewan and Ram Rivers Bull Trout Spawning Stock Assessment Fisheries Program Manager: Peter Aku Project Leader:

More information

ENTRANCES USED AND PASSAGE THROUGH FISHWAYS FOR ADULT CHINOOK SALMON AND STEELHEAD

ENTRANCES USED AND PASSAGE THROUGH FISHWAYS FOR ADULT CHINOOK SALMON AND STEELHEAD ENTRANCES USED AND PASSAGE THROUGH FISHWAYS FOR ADULT CHINOOK SALMON AND STEELHEAD Part III of Final Report for MIGRATION OF ADULT CHINOOK SALMON AND STEELHEAD PAST DAMS AND THROUGH RESERVOIRS IN THE LOWER

More information

Tuolumne River Gravel Introduction

Tuolumne River Gravel Introduction Tuolumne River Gravel Introduction 2000 2003 Tuolumne River La Grange Gravel Addition, Phase II Course Sediment Replenishment Program Tuolumne River Salmonid Habitat Improvement Project River Mile 49.9

More information

Attraction and Passage Efficiency of a Vertical-Slot Fish Pass for Sea Lamprey

Attraction and Passage Efficiency of a Vertical-Slot Fish Pass for Sea Lamprey University of Massachusetts Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish

More information

Pallid Sturgeon. Pallid sturgeon. Life history

Pallid Sturgeon. Pallid sturgeon. Life history Pallid Sturgeon Pallid Sturgeon: biology & techniques for monitoring a large river fish Actinopterygii (ray finned fishes) Acipenseriformes (Sturg. & paddlefishes) Acipenseridae (Sturgeons) Scaphirhynchinae

More information

Resources and Guidance for writing a River Herring Management Plan

Resources and Guidance for writing a River Herring Management Plan Resources and Guidance for writing a River Herring Management Plan In 2011 members of the River Herring Network brainstormed a list of questions that should be answered in order to develop a plan for herring

More information

Date: 25 September Introduction

Date: 25 September Introduction To: David Clugston, USACE Portland District From: Matt Keefer, Eric Johnson, Tami Clabough, Mike Jepson, Chris Caudill, Mary Moser RE: Preliminary evaluation of radiotelemetry and half-duplex PIT tag data

More information

SUMMARY OF CONOWINGO DAM WEST FISH LIFT OPERATIONS 2012

SUMMARY OF CONOWINGO DAM WEST FISH LIFT OPERATIONS 2012 SUMMARY OF CONOWINGO DAM WEST FISH LIFT OPERATIONS 2012 Michael L. Hendricks Pennsylvania Fish and Boat Commission 1735 Shiloh Rd. State College, Pa 16801 INTRODUCTION The shore-based trapping device at

More information

Technical Report 99-4 EFFECTS OF A SHAD FISHERY ON PASSAGE OF ADULT CHINOOK SALMON THROUGH THE OREGON-SHORE FISHWAY LADDER AT THE DALLES DAM

Technical Report 99-4 EFFECTS OF A SHAD FISHERY ON PASSAGE OF ADULT CHINOOK SALMON THROUGH THE OREGON-SHORE FISHWAY LADDER AT THE DALLES DAM Technical Report 99-4 EFFECTS OF A SHAD FISHERY ON PASSAGE OF ADULT CHINOOK SALMON THROUGH THE OREGON-SHORE FISHWAY LADDER AT THE DALLES DAM - 1996 A report for Project MPE-P-95-1 by C.A. Peery, T.C. Bjornn,

More information

Spilling Water at Hydroelectric Projects in the Columbia and Snake Rivers How Does It Benefit Salmon?

Spilling Water at Hydroelectric Projects in the Columbia and Snake Rivers How Does It Benefit Salmon? Spilling Water at Hydroelectric Projects in the Columbia and Snake Rivers How Does It Benefit Salmon? Hydropower development in the Columbia and Snake rivers has left its mark on salmonid populations,

More information

Consigned to the deep: requiem or recovery of VR2W receivers in a freshwater river gorge after a 1:2-3 3 year ARI flood

Consigned to the deep: requiem or recovery of VR2W receivers in a freshwater river gorge after a 1:2-3 3 year ARI flood Consigned to the deep: requiem or recovery of VR2W receivers in a freshwater river gorge after a 1:2-3 3 year ARI flood 1 Ivars Reinfelds, 2,3 Chris Walsh and 1 Tim Haeusler 1 Department of Water and Energy,

More information

Feasibility Report and Environmental Impact Statement. Coastal Storm Damage Reduction SURF CITY AND NORTH TOPSAIL BEACH, NORTH CAROLINA.

Feasibility Report and Environmental Impact Statement. Coastal Storm Damage Reduction SURF CITY AND NORTH TOPSAIL BEACH, NORTH CAROLINA. Feasibility Report and Environmental Impact Statement on Coastal Storm Damage Reduction SURF CITY AND NORTH TOPSAIL BEACH, NORTH CAROLINA Appendix H Correspondence Appendix H Correspondence This appendix

More information

EXECUTIVE SUMMARY FISH COMMUNITY AND HABITAT EXISTING CONDITIONS REPORT

EXECUTIVE SUMMARY FISH COMMUNITY AND HABITAT EXISTING CONDITIONS REPORT EXECUTIVE SUMMARY FISH COMMUNITY AND HABITAT EXISTING CONDITIONS REPORT First Mining Gold (First Mining) has completed a comprehensive Fish Community and Habitat Existing Conditions Report which has utilized

More information

July 17, Fish and Wildlife Resource Conservation Group Members Saluda Hydro Relicensing Team

July 17, Fish and Wildlife Resource Conservation Group Members Saluda Hydro Relicensing Team July 17, 2006 Fish and Wildlife Resource Conservation Group Members Saluda Hydro Relicensing Team South Carolina Electric & Gas Company FERC Project No. 516 2005 Lower Saluda River Crayfish Assessment

More information

2016 Diadromous Migration Season on the Presumpscot A R E P O RT F R OM THE GMR I FIS HE R IE S E C O L OGY LAB ON CB AS S

2016 Diadromous Migration Season on the Presumpscot A R E P O RT F R OM THE GMR I FIS HE R IE S E C O L OGY LAB ON CB AS S 2016 Diadromous Migration Season on the Presumpscot A R E P O RT F R OM THE GMR I FIS HE R IE S E C O L OGY LAB ON CB AS S SEPTEMBER 2016 2016 Diadromous Migration Season on the Presumpscot 1 Beginning

More information

SOUTH CAROLINA ELECTRIC & GAS COMPANY COLUMBIA, SOUTH CAROLINA

SOUTH CAROLINA ELECTRIC & GAS COMPANY COLUMBIA, SOUTH CAROLINA SOUTH CAROLINA ELECTRIC & GAS COMPANY COLUMBIA, SOUTH CAROLINA SALUDA HYDROELECTRIC PROJECT FERC NO. 516 DOWNSTREAM TEMPERATURE STUDY DRAFT REPORT MAY 28 Prepared by: SOUTH CAROLINA ELECTRIC & GAS COMPANY

More information

Columbia Lake Dam Removal Project

Columbia Lake Dam Removal Project Columbia Lake Dam Removal Project The Columbia Lake dam located 1/4 mile upstream of the Paulins Kill River's confluence with the Delaware River in Knowlton Township, Warren County has been proposed for

More information

Dry Creek Project. The Dry Creek Habitat Enhancement Project provides a. Slowing velocity, creating refuge are key to habitat project

Dry Creek Project. The Dry Creek Habitat Enhancement Project provides a. Slowing velocity, creating refuge are key to habitat project Dry Creek Habitat Enhancement Bulletin The Dry Creek Habitat Enhancement Project provides a unique opportunity for the Sonoma County Water Agency (Water Agency) and landowners to protect endangered fish

More information

Saluda Hydroelectric Project (FERC No. 516) Study Plan

Saluda Hydroelectric Project (FERC No. 516) Study Plan Saluda Hydroelectric Project (FERC No. 516) Study Plan Study Plan Name: 2005 Diadromous Fish Studies Applicable Hydro Projects: Saluda Hydro FERC No. 516 I. Study Objective The objectives of this study

More information

Monitoring the Behavior of Acoustically Tagged Chinook and Steelhead Smolts Approaching Rocky Reach Dam on the Columbia River

Monitoring the Behavior of Acoustically Tagged Chinook and Steelhead Smolts Approaching Rocky Reach Dam on the Columbia River Presented at Waterpower XII, July 9-11, 2001, Salt Lake City, Utah, USA Monitoring the Behavior of Acoustically Tagged Chinook and Steelhead Smolts Approaching Rocky Reach Dam on the Columbia River ABSTRACT

More information

Dave Clugston U.S. Army, Corps of Engineers, Portland District. Tami Clabough, Eric Johnson, Dan Joosten, and Chris Peery

Dave Clugston U.S. Army, Corps of Engineers, Portland District. Tami Clabough, Eric Johnson, Dan Joosten, and Chris Peery College of Natural Resources Department of Fish and Wildlife Resources P.O. Box 443141 Moscow, Idaho 83844-3141 Phone: 8-885-64 Fax: 8-885-98 To: From: RE: Dave Clugston U.S. Army, Corps of Engineers,

More information

107 FERC 61,282 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

107 FERC 61,282 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION 107 FERC 61,282 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Before Commissioners: Pat Wood, III, Chairman; Nora Mead Brownell, and Joseph T. Kelliher. Public Utility District No. 1 of

More information

Threatened and Endangered Species Issues on the Kennebec River, Maine

Threatened and Endangered Species Issues on the Kennebec River, Maine Acipenser brevirostrum Photo: Nancy Haley, NOAA http://digitalmedia.fws.gov/ Atlantic sturgeon photo courtesy of Robert Michelson http://www.nmfs.noaa.gov/stories/2012/01/31_atlantic_sturgeon.html Threatened

More information

R & E Grant Application Biennium

R & E Grant Application Biennium R & E Grant Application 05-07 Biennium Project #: 05-141 Project Information R&E Project Request: $50,000.00 Match Funding: $36,500.00 Total Project: $86,500.00 Start Date: 3/1/2007 End Date: 6/30/2007

More information

Atlantic States Marine Fisheries Commission

Atlantic States Marine Fisheries Commission Atlantic States Marine Fisheries Commission DRAFT ADDENDUM I TO THE OMNIBUS AMENDMENT TO THE INTERSTATE FISHERY MANAGEMENT PLANS FOR SPANISH MACKEREL, SPOT, AND SPOTTED SEATROUT FOR PUBLIC COMMENT Spanish

More information

A BLUEPRINT FOR THE PENOBSCOT RIVER WATERSHED

A BLUEPRINT FOR THE PENOBSCOT RIVER WATERSHED A BLUEPRINT FOR THE PENOBSCOT RIVER WATERSHED About this series 2 # for a healthy Penobscot watershed M aine rivers used to be full of fish swimming upstream from the ocean every year on their spawning

More information

Dave Clugston U.S. Army, Corps of Engineers, Portland District. Tami Clabough, Eric Johnson, Dan Joosten, and Chris Peery

Dave Clugston U.S. Army, Corps of Engineers, Portland District. Tami Clabough, Eric Johnson, Dan Joosten, and Chris Peery College of Natural Resources Department of Fish and Wildlife Resources P.O. Box 443141 Moscow, Idaho 83844-3141 Phone: 28-885-64 Fax: 28-885-98 To: From: Dave Clugston U.S. Army, Corps of Engineers, Portland

More information

To link to this article:

To link to this article: This article was downloaded by: [University of Georgia] On: 21 November 2013, At: 10:42 Publisher: Taylor & Francis Informa Ltd Registered in England and Wales Registered Number: 1072954 Registered office:

More information

Columbia Lake Dam Removal Project

Columbia Lake Dam Removal Project Columbia Lake Dam Removal Project Major Goals of the Columbia Lake Dam Removal: Reconnect 10 miles of the Paulins Kill River to the Delaware River, restoring natural flow regime and sediment transport.

More information

SUMMARY REPORT FOR LAKE ST. MALO FISHERIES ASSESSMENT. Prepared for the St. Malo and District Wildlife Association

SUMMARY REPORT FOR LAKE ST. MALO FISHERIES ASSESSMENT. Prepared for the St. Malo and District Wildlife Association SUMMARY REPORT FOR LAKE ST. MALO FISHERIES ASSESSMENT Prepared for the St. Malo and District Wildlife Association Presented by August 25, 2014 Study dates thus far: Date Tasks February 16 Fishing derby;

More information

Diadromous Fish Assemblage Assessment in the Saco River Estuary, ME

Diadromous Fish Assemblage Assessment in the Saco River Estuary, ME Diadromous Fish Assemblage Assessment in the Saco River Estuary, ME Kayla Smith James Sulikowski, Ph.D. and Carrie Byron, Ph.D. Dept of Marine Sciences Saco River Estuary Nursery ground Foraging stop-over

More information

N. Tay Evans Marine Fisheries Biologist & Technical Review Coordinator

N. Tay Evans Marine Fisheries Biologist & Technical Review Coordinator Massachusetts Division of Marine Fisheries Marine Fisheries Resource Recommendations: Time-of-Year Restrictions N. Tay Evans Marine Fisheries Biologist & Technical Review Coordinator Massachusetts Division

More information

New two-lane bridge to replace the existing structure spanning the Maple River just south of the Village s central business district

New two-lane bridge to replace the existing structure spanning the Maple River just south of the Village s central business district New two-lane bridge to replace the existing structure spanning the Maple River just south of the Village s central business district Rehabilitate the old bridge Convert to a nonmotorized trail Restore

More information

Finding the Way Home

Finding the Way Home Finding the Way Home Adapted from: Activity 27 The Great Anadromous Fish Game Living in Water. The National Aquarium in Baltimore, 1997. Migration Grade Level: Intermediate Duration: 1-2 class periods

More information

Build It and They Will Come

Build It and They Will Come 7 American Currents Vol. 37, No. 1 Build It and They Will Come Fritz Rohde 2000 Trinity Avenue,Wilmington, NC 28411 fritz.rohde@gmail.com Y es, it is a cheesy title ripped straight from the movie Field

More information

2016 Milltown Fishway Research Trap Report St. Croix River, New Brunswick and Maine R. Goreham and H. Almeda Summary 1

2016 Milltown Fishway Research Trap Report St. Croix River, New Brunswick and Maine R. Goreham and H. Almeda Summary 1 Summary 2016 Milltown Fishway Research Trap Report St. Croix River, New Brunswick and Maine R. Goreham and H. Almeda St. Croix International Waterway Commission P.O. Box 610, Calais, ME 04619 and P. O.

More information

Final Report to Cornell Water Resources Institute

Final Report to Cornell Water Resources Institute Final Report to Cornell Water Resources Institute Relative Abundance of Blueback Herring (Alosa aestivalis) in Relation to Permanent and Removable Dams on the Mohawk River To: Water Resources Institute,

More information

JOB 1, PART 2. SUMMARY OF CONOWINGO DAM WEST FISH LIFT OPERATIONS 2011

JOB 1, PART 2. SUMMARY OF CONOWINGO DAM WEST FISH LIFT OPERATIONS 2011 JOB 1, PART 2. SUMMARY OF CONOWINGO DAM WEST FISH LIFT OPERATIONS 2011 Michael L. Hendricks Pennsylvania Fish and Boat Commission 1735 Shiloh Rd. State College, Pa 16801 INTRODUCTION The shore-based trapping

More information

Enclosure 9. Memorandum for Record, meeting with FWS on August 12, 2002

Enclosure 9. Memorandum for Record, meeting with FWS on August 12, 2002 Enclosure 9 Memorandum for Record, meeting with FWS on August 12, 2002 CESAM-PD-EI Brandt/690-3260/23 August 2002 MEMORANDUM FOR RECORD SUBJECT: Meeting with USFWS and FWCC to Discuss ACF Water Control

More information

Success through Stewardship: White Sturgeon Monitoring and Assessment in the Lower Fraser River, B.C.

Success through Stewardship: White Sturgeon Monitoring and Assessment in the Lower Fraser River, B.C. Success through Stewardship: White Sturgeon Monitoring and Assessment in the Lower Fraser River, B.C. TROY C. NELSON 1,2, WILLIAM J. GAZEY 3, KARL K. ENGLISH 2, AND MARVIN L. ROSENAU 4 1 Fraser River Sturgeon

More information

Susitna-Watana Hydroelectric Project (FERC No ) Salmon Escapement Study Study Plan Section 9.7

Susitna-Watana Hydroelectric Project (FERC No ) Salmon Escapement Study Study Plan Section 9.7 (FERC No. 14241) Salmon Escapement Study Study Plan Section 9.7 Initial Study Report Part C: Executive Summary and Section 7 Prepared for Prepared by LGL Alaska Research Associates, Inc. & Alaska Department

More information

Distribution of Shortnose Sturgeon in the Lower Savannah River

Distribution of Shortnose Sturgeon in the Lower Savannah River Distribution of Shortnose Sturgeon in the Lower Savannah River Results of Research Conducted 1999-2000 Final Report to Georgia Ports Authority Mark R. Collins, William C. Post, and Daniel C. Russ South

More information

KEEYASK FISH PASSAGE IDENTIFICATION OF DESIGN CONCEPTS

KEEYASK FISH PASSAGE IDENTIFICATION OF DESIGN CONCEPTS KEEYASK FISH PASSAGE IDENTIFICATION OF DESIGN CONCEPTS NOVEMBER 29 TH, 2012 Executive Summary A Keeyask fish passage feasibility study was undertaken with the goal of developing and evaluating a suite

More information

California Steelhead: Management, Monitoring and Recovery Efforts

California Steelhead: Management, Monitoring and Recovery Efforts California Steelhead: Management, Monitoring and Recovery Efforts Jonathan Nelson Steelhead Restoration & Management Program Oncorhynchus mykiss irideus California Steelhead Distinct Population Segments

More information

ATLANTIC STURGEON. Consultations on listing under the Species at Risk Act

ATLANTIC STURGEON. Consultations on listing under the Species at Risk Act ATLANTIC STURGEON Consultations on listing under the Species at Risk Act Information summary and questionnaire for consultations on adding two Atlantic Sturgeon populations to the List of Wildlife Species

More information

San Joaquin River Restoration Program Juvenile Salmonid Survival and Migration Preliminary Report July 2011

San Joaquin River Restoration Program Juvenile Salmonid Survival and Migration Preliminary Report July 2011 San Joaquin River Restoration Program Juvenile Salmonid Survival and Migration Preliminary Report July 2011 1 2011 Juvenile Salmonid Survival and Migration Study 1.1 Introduction The Fisheries Management

More information

APPENDIX A AGENCY COORDINATION

APPENDIX A AGENCY COORDINATION APPENDIX A AGENCY COORDINATION Page left blank intentionally Paul J. Diodati Director August 25, 2010 Commonwealth of Massachusetts Division of Marine Fisheries Annisquam River Marine Fisheries Station

More information

FINAL Caples Lake Fisheries Management Plan. Version 4.0

FINAL Caples Lake Fisheries Management Plan. Version 4.0 FINAL Caples Lake Fisheries Management Plan Version 4.0 August 15, 2008 Purpose The Caples Lake Fisheries Management Plan (Plan) outlines the stocking plan to reestablish a sport fishery in Caples Lake

More information

Project Webpage:

Project Webpage: Project Webpage: http://nature.ly/marinesatlanticbightera Coastal Data and Full Metadata: http://easterndivision.s3.amazonaws.com/marine/sab MA/SABMACoastalEcosystems.zip Coastal Chapter: http://easterndivision.s3.amazonaws.com/marine/sab

More information

2006 Progress Report. Bull Trout X Brook Trout Hybrid captured in Swan Lake. Swan Lake

2006 Progress Report. Bull Trout X Brook Trout Hybrid captured in Swan Lake. Swan Lake 2006 Progress Report Bull Trout X Brook Trout Hybrid captured in Swan Lake Swan Lake Swan Valley Bull Trout Working Group May, 2007 Background The Swan Valley has historically been home to a stable, healthy

More information

Susitna-Watana Hydroelectric Project (FERC No ) Salmon Escapement Study Study Plan Section 9.7

Susitna-Watana Hydroelectric Project (FERC No ) Salmon Escapement Study Study Plan Section 9.7 (FERC No. 14241) Salmon Escapement Study Study Plan Section 9.7 Part D: Supplemental Information to June 2014 Initial Study Report Prepared for Prepared by LGL Alaska Research Associates, Inc. & Alaska

More information

Tracking Juvenile Summer Flounder

Tracking Juvenile Summer Flounder Tracking Juvenile Summer Flounder East Coast MARE Materials For the leader: Whiteboard Markers (different colors) For each group: Copies of student group packets Copies of student worksheet Overview Scientists

More information

Study Update Fish Distribution and Species Composition

Study Update Fish Distribution and Species Composition Study Update Fish Distribution and Species Composition Goals and Study Area Gain a better understanding of fish species composition and abundance in waters associated with the Packwood Lake Hydroelectric

More information

Ecology of Columbia River redband trout (Oncorhynchus mykiss gairdneri) in high desert streams

Ecology of Columbia River redband trout (Oncorhynchus mykiss gairdneri) in high desert streams Ecology of Columbia River redband trout (Oncorhynchus mykiss gairdneri) in high desert streams Dry Creek October 2012 Chris A. Walser Ph.D., Professor of Biology Department of Biology and Environmental

More information

Steve Hemstrom Sr. Fisheries Biologist Chelan PUD Natural Resources Desk: Cell:

Steve Hemstrom Sr. Fisheries Biologist Chelan PUD Natural Resources Desk: Cell: From: To: Cc: Subject: Date: Attachments: Hemstrom, Steven "Lewis, Stephen" Sokolowski, Rosana 2014 Rocky Reach Bull Trout Report Wednesday, June 18, 2014 3:01:07 PM Final 2014 Rocky Reach Bull Trout Observations

More information

JIMAR PFRP ANNUAL REPORT FOR FY 2006

JIMAR PFRP ANNUAL REPORT FOR FY 2006 JIMAR PFRP ANNUAL REPORT FOR FY 2006 P.I./Sponsor Name: Michael P. Seki and Jeffrey J. Polovina Project Proposal Title: Oceanographic Characterization of the American Samoa Longline Fishing Grounds for

More information

U. S. Fish and Wildlife Service Connecticut River Coordinator s Office. Ken Sprankle Connecticut River Coordinator

U. S. Fish and Wildlife Service Connecticut River Coordinator s Office. Ken Sprankle Connecticut River Coordinator U. S. Fish and Wildlife Service Connecticut River Coordinator s Office Ken Sprankle Connecticut River Coordinator Largest river basin in New England 400 miles long 11,250 mile 2 area Over 2,700 dams identified

More information

Jason Blackburn, Paul Hvenegaard, Dave Jackson, Tyler Johns, Chad Judd, Scott Seward and Juanna Thompson

Jason Blackburn, Paul Hvenegaard, Dave Jackson, Tyler Johns, Chad Judd, Scott Seward and Juanna Thompson Alberta Conservation Association (ACA) Date: 2014-2015 Project Name: Owl River Walleye and Aquatic Habitat Assessment Fisheries Program Manager: Peter Aku Project Leader: Tyler Johns Primary ACA staff

More information

Retention of Coded Wire Tags in Juvenile Shortnose Sturgeon

Retention of Coded Wire Tags in Juvenile Shortnose Sturgeon North American Journal of Fisheries Management ISSN: 0275-5947 (Print) 1548-8675 (Online) Journal homepage: http://www.tandfonline.com/loi/ujfm20 Retention of Coded Wire Tags in Juvenile Shortnose Sturgeon

More information

Connecticut River American Shad Sustainability Plan Update

Connecticut River American Shad Sustainability Plan Update Connecticut River American Shad Sustainability Plan Update September 2017 Connecticut Department of Energy and Environmental Protection Introduction Update to Initial Connecticut Plan implemented beginning

More information

Meeting Summary Fisheries Management Technical Feedback Group Meeting Friday, November 2, 2012

Meeting Summary Fisheries Management Technical Feedback Group Meeting Friday, November 2, 2012 Meeting Summary Fisheries Management Technical Feedback Group Meeting Friday, November 2, 2012 Bureau of Reclamation, 2800 Cottage Way, Sacramento, CA 95825 Cafeteria Conference Room C1003 FINAL: 2013.1.14

More information