Proceedings of the ASME th International Conference on Ocean, Offshore and Arctic Engineering

Size: px
Start display at page:

Download "Proceedings of the ASME th International Conference on Ocean, Offshore and Arctic Engineering"

Transcription

1 Proceedings of the ASME th International Conference on Ocean, Offshore and Arctic Engineering Proceedings of the ASME th International Conference on Ocean, Offshore and Arctic Engineering OMAE2011 June 19-24, 2011, Rotterdam, The Netherlands OMAE2011 June 19-24, 2011, Rotterdam, the Netherlands OMAE OMAE YEARS OLD JACKETS REMOVED AS A SINGLE PIECE Jochum C.G. van Hoof Heerema Marine Contractors Leiden, the Netherlands Ruben de Bruin Heerema Marine Contractors Leiden, the Netherlands ABSTRACT Heerema Marine Contractors (HMC) have removed and will be removing various platforms from the North Sea. For these projects Heerema has developed an unconventional method to remove and transport jackets: Jackets are lifted as one single piece and transported to the recycling yard whilst being suspended from both cranes of the Heavy Lift Vessel (HLV) Thialf. Two purpose built structures at the stern restrain the jackets from horizontal motions during transport. In summer 2010 three eight-legged jackets were removed and transported using this method (see Figure 1). The jackets weighed approximately 5,000 metric tonnes each and stood in 70-80m of water. The jacket removal resulted in load cases that were never considered during jacket design. Jacket strength appeared very marginal when cutting the jacket into several sections, but by lifting the jacket as one single section, all members remained connected and ensured a stable structure. Other benefits were reduction of the offshore project duration, the subsea cutting scope and the required vessel spread. Risk on weather downtime was reduced and safety improved by preventing back loading operations in an offshore environment. The transport distance with the jacket suspended from both Thialf cranes ranged from nautical miles (1½-2½ days sailing). The final cuts and the jacket lifting required relatively low sea states. The wave climate for transport was determined with the assumption of a preceding weather sensitive operation, which is different to a transport that assumes a start at a random time. Model tests for these design sea states have been performed to accurately assess the Thialf dynamic behavior at its shallow transit draught. Additional analyses were performed to confirm the vessel-jacket dynamic interaction. During transport the so called restraints gripped around the jacket corner legs, restraining the structure horizontally and preventing side loads on the cranes. During the three transports, motions have been measured and dynamic behavior corresponded well with the analyses. Removing and transporting these jackets as a single piece was a unique operation. The method worked well and resulted in a predictable, safe and time efficient jacket removal. This paper will address the removal method, including structural aspects, model tests and full scale verification. Figure 1 Heavy Lift Vessel Thialf transporting eight-legged jacket as a single piece, June 2010 (photo HMC) 1 Copyright 2011 by ASME

2 INTRODUCTION In the next twenty years many of the over five hundred installations in the North Sea will have to be removed partially or entirely due to international legislation [ref. 1]. Heerema Marine Contractors are currently contracted for one of the most extensive decommissioning projects to date. This project includes the decommissioning, removal, disposal and recycling of various platforms in the Central North Sea. For this project, Heerema s fleet of heavy lift vessels is used for the offshore removal operations that started in 2009 and are to be concluded in Topsides of three of these platforms were removed in 2009 by reversed installation. While the topsides were being removed, inspections and preparations were performed for the jacket removal scope. The year after, 2010, the three jackets were removed and transported to the recycling yard in Norway. To complete this scope, Heerema Marine Contractors developed an unconventional method to remove and transport these jackets as a single piece. The first part of this paper presents background information on the jackets including the structural aspects. The single piece removal and transport method is described next. Then the design sea state and the model tests for these design conditions are discussed. Finally the actual project execution is described including the full scale verification. NOMENCLATURE C.o.G. Centre of Gravity DGPS Differential Global Positioning System DNV Det Norske Veritas DP Dynamic Positioning F Cumulative probability distribution function GM Distance C.o.G. to metacenter HLV Heavy Lift Vessel HMC Heerema Marine Contractors H s Significant wave height MRU Motion Reference Unit mt metric tonnes P non Probability of non-exceedance RAO Response Amplitude Operator RP Recommended Practice Operation Reference Period T R JACKET INFORMATION All three jackets have eight legs arranged in a 2 x 4 grid vertically braced in the two longitudinal and four transverse planes. Horizontally the jackets are braced at six elevations (see Figure 2). The jackets were installed in the 1970s in meter of water. The jackets were launched from a barge and thereafter upended. After placement onto their position, piles were driven through and grouted to the jacket legs to ensure a sound connection to the seabed and to support the topsides. The piles and grout significantly increased the weight to approximately 5,000 metric tonnes per jacket as presented in Table 1. Combined with later modifications to the jacket, removal resulted in load cases that were never considered during jacket design. Jacket removal and transport was modeled and analyzed using a finite element structural analysis suite. The models included all structural and non-structural jacket items. Detailed sub sea surveys were performed during the preparation phases and all anomalies found were included in the model. Structural integrity calculations clearly showed that the jackets are quite weak structures, which have never been designed with removal in mind. If lifting the jacket in several sections, structural strength during lift and transport appeared very marginal. By lifting the jacket as one single vertical section, all members remained connected and ensured a stable structure. Table 1 Average Jacket Properties Property Value Unit Jacket base dimension 63 x 35 m Jacket top dimension 43 x 16 m Jacket Height 91 m Jacket Leg Diameter 1,400 mm Total Dry Weight 5,000 mt Structural Steel (excl. piles) 2,000 mt Piles and Grout Weight 2,000 mt Ancillary Items (e.g. caissons, 500 mt risers, anodes, boat bumpers) Marine Growth 500 mt Figure 2 Typical eight-legged jacket - Isometric view 2 Copyright 2011 by ASME

3 SINGLE PIECE REMOVAL AND TRANSPORT METHOD The jacket removal has been designed as a dual crane lift. The lifting equipment consisted of four doubled grommets, four lift points and two spreader bars that were welded to the top of the four corner jacket piles. The jacket piles were cut two meters below seabed. Subsequently the entire jacket was lifted above sea level and transported to shore whilst being suspended from both cranes of Heavy Lift Vessel Thialf (see Figure 3). During transport the jacket surge and sway motions were restrained to prevent side loads on the cranes. The so called restraints are purpose built structures on the stern that gripped around the corner legs (see Figure 16). The restraints were designed to transfer all horizontal transportation loads that could occur during this unrestricted transport. Transport distance Nm Figure 4 Transport route Figure 3 Jacket arriving in Norway (photo HMC) Benefits of removing and transporting these jackets as a single piece were: Shorter offshore project duration; Reduced subsea cutting scope; Subsea lift tools not required; Smaller marine spread; Improved safety due to fewer offshore operations and by preventing back loading operations to a barge at open sea; Less risk on weather downtime. On the other hand the onshore decommissioning and recycling scope increased as the jackets were delivered as one large section. DESIGN SEA STATE The transport distance with the jacket suspended from both cranes ranged from nautical miles (see Figure 4). The transport has been designed for removal in the period from May to August and involved approximately 1½ to 2½ days sailing. Unlike a transport scheduled for platform installation, this removal transport would be preceded by a period of relatively good weather to perform the final cut and lift of the jacket. DNV-RP-H102 [ref. 2] states that for unrestricted operations with duration less than five days (T R 120 hours), the design wave height and wind speed can be reduced using pure statistical methods. As successive sea states are not fully independent but show some persistence, the design wave height may very well be reduced. The persistence is captured in measured and modeled time series of wave heights. These time series were used to calculate the design wave height based on the condition that the transport can only start directly after jacket lifting (with a sea state below a certain value). The design sea state was based on extreme value statistics. A 10% probability of exceeding of the design value is acceptable during the operation reference period. The coinciding probability that the design value will not be exceeded during a 3 hour period for a 72 hour exposure is: 3 72 P = ( 1 0.1) = 99.56% (1) non and H design s 1 = F ( P ) (2) H s non 3 Copyright 2011 by ASME

4 In which F Hs is a cumulative distribution function approximated as a Weibull distribution using regression analysis. The design values were based on a 2-parameter Weibull regression on top 30% values. For clarity it shall be noted that for a 72 hour exposure the 10% exceedance value is equivalent to a 1 year monthly return condition. An operation period less than 72 hours shall not be used in this respect. The probability distribution was determined for a sea state population that meets following conditions (see also Figure 5): Sea state The operability limits for the preceding operation (jacket final cut, lifting and securing) have not been exceeded during the planned operation period of that preceding operation; Sea states need to be within reference period of the transportation; All possible arrival dates are simulated. For each arbitrary start time of the lift operation the first possible weather window is used. Wave data after the lift window are used for transport statistics. Threshold (precondition) Sea state time trace Restricted operation (final cut / lift) Unrestricted transport (with precondition) The transport distance; The considered season for transport. The average reduction of the design wave height for the single lift transport appeared to be approximately 10% for the summer period. The associated wave period range was calculated according to DNV [ref. 4]. FROM MODEL TESTS TO DESIGN CRITERIA The single lift transport was performed at a shallow vessel draught with the floaters of the heavy lift vessel just submerged. Numerical computations using diffraction theory will not result in accurate motion statistics of the Thialf at this draught. In order to accurately assess the transportation forces during the design sea state, it was therefore decided to perform sea keeping model tests (see Figure 6 and Figure 7). The vessel loading condition, vessel and jacket mass, roll and pitch inertia and the GM values were included in the model and calibrated prior to the model tests. The Thialf and jacket were modeled as one rigid body which combined with some post-processing, forms an accurate representation of the vessel - restrained jacket system. The scale of the Thialf model was 1:40 and sea states were of the JONSWAP spectrum. Various wave conditions were analyzed for five different headings. An interesting observation concerned the large damping for beam seas, possibly due to water running on and off the submerged floaters. At transit draught the floaters of the semi submersible column stabilized unit Thialf were just submerged (~0.9 m of water on top of the floaters). Time start 1 start 2 Extreme value analysis input Figure 5 Simulating unrestricted transport after a weather restricted operation (pre-condition) start n Calculating the design sea state using a pre-condition has lead to reduced design values, whilst the transport is still an unrestricted operation. The reduction in wave height varies pending: Figure 6 Sketch wave tank (Océanide) Duration of the preceding weather restricted operation 1 ; The limiting sea state for the preceding operation; 1 Durations of weather restricted operations are limited to the maximum reliable weather forecast which is currently set at 72 hours. DNV suggests that forecasts ranging up to 120 hours may be considered reliable [ref. 3]. 4 Copyright 2011 by ASME

5 The design accelerations were direct input in the finite element structural analysis suite. The jacket structural model included rigging and the correct spring stiffness for the restraints and crane tips. The finite element model was used to verify jacket structural integrity during lift, transport and setdown and to calculate design loads for the lift equipment and the restraints. Figure 7 Thialf sea keeping model tests (photo HMC) Figure 8 shows the RAO s for roll for different significant wave heights. The RAO s are lower for higher wave heights. This means that roll responses of the Thialf at this draft do not increase linearly with wave height. This non-linear behavior makes it impossible to predict motions using linear panel methods. TRANSPORT INCLUDING FULL SCALE VERIFICATION A motion monitoring system was installed on board the Thialf including wireless motion sensors that were installed on top of the jackets. This system provided the opportunity for real-time monitoring of jacket accelerations (six degrees of freedom) and angles (roll, pitch and yaw). In addition various other vessel sensors were connected to this system so this data could be monitored as well (see Figure 9). Besides real-time monitoring, data was logged for evaluation purposes. Roll RAO amplitude for beam seas for different significant wave heights RAO 0 Hs1 Hs2 Hs3 Hs4.3 Wave Period [s] Figure 8 Model test RAO s for roll motion Relative water elevation and jacket accelerations for the design sea states were therefore extracted from the model tests as directly as possible: Motions of the model at the location of the jacket C.o.G. were differentiated twice to yield the accelerations. Most probable maximum values were derived from the resulting acceleration time traces. On top of the accelerations derived from the model test results, following accelerations were added: Static wind heel angle (transverse acceleration); Relative pitch acceleration between jacket and vessel. The restraints prevented relative horizontal jacket motions between jacket and vessel. Relative pitch between jacket and vessel was however not restrained. Rigging was selected in such a way that the natural period for jacket pitch was only 4 seconds. As the Thialf will transfer very little energy at this frequency, relative pitch accelerations are limited. A dynamic analysis was performed to quantify this relative jacket pitch. Work Station on Bridge to log and display: Vessel information: o DGPS; o Gyro Compass; o Wind; o MRU Thialf DP system Motion sensors (wireless): o On jacket (2x); o On Thialf stern (1x) ; o On Thialf bridge (1x). Figure 9 Motion monitoring system on board HLV Thialf The weather during all three transports was relatively mild so the design sea state was not encountered. Nevertheless some higher sea states occurred which showed that the measured Thialf RAO s and the model test RAO s were very similar. RAO s calculated based on the motions measured during the offshore campaign are shown together with the model tests RAO s (Figure 10 to Figure 12). The full scale RAO s were calculated using the hindcasted wave spectrum. Note that the Thialf was sailing in near head-seas (15 degrees) during the full scale measurements. Roll motions were therefore very small which leads to a relative large influence of noise. 5 Copyright 2011 by ASME

6 Amplitude Heave motion Measured offshore Model test Hs = 2, Heading = 150 deg Model test Hs = 2, Heading = 180 deg Figure 10 Heave motion RAO Period [s] Roll motion The relative jacket pitch motions appeared very small which was in accordance with the dynamic analysis. Preparing the jackets, cutting the piles, lifting the jackets, engaging the jackets into the restraints and transporting the jackets was all executed according to the planning. The average duration of the offshore operations was around 15 days per jacket. This duration excludes (de)mobilization and weather downtime, but includes other removal activities which were performed simultaneously with the jacket removal (e.g. module support frame removal). Contingency procedures proved to be adequate, all restricted operations were finished well within the anticipated weather windows and the unrestricted transport delivered no surprises. Photos of the offshore execution are included in Annex A (Figure 13 to Figure 17). Amplitude Measured offshore Model test Hs = 2, Heading = 150 deg Model test Hs = 2, Heading = 180 deg Figure 11 Roll motion RAO Amplitude Figure 12 Pitch motion RAO Period [s] Pitch motion Measured offshore Model test Hs = 2, Heading = 150 deg Model test Hs = 2, Heading = 180 deg Period [s] CONCLUSION Removing and transporting jackets as a single piece resulted in a predictable, robust, safe and time efficient jacket removal. Heerema Marine Contractors successfully transported three jackets to a recycling yard with the jacket restrained horizontally whilst being suspended from both cranes of Heavy Lift Vessel Thialf. REFERENCES 1. OSPAR Commission (July 1998): Convention for the Protection of the Marine Environment of the North-East Atlantic, Annex III, Article 5, Sintra, Portugal. 2. Det Norske Veritas (April 2004): Marine Operations during Removal of Offshore Installations, DNV-RP-H102, Høvik, Norway. 3. Det Norske Veritas (June 2007): DNV Marine Operation Rules, Revised Alpha Factor JIP Project, rev. 03, Høvik, Norway. 4. Det Norske Veritas (April 2007): Environmental Conditions and Environmental Loads, DNV-RP-C205, Høvik, Norway. 6 Copyright 2011 by ASME

7 ANNEX A: PHOTOS OFFSHORE EXECUTION Figure 13 Welding lift points on top of jacket leg (photo HMC) Figure 14 Lift points installed: Jacket ready for single piece removal and transport (photo HMC) 7 Copyright 2011 by ASME

8 A B C D E Figure 15 A) Subsea diamond wire cutting final jacket leg; B) Rigging hook on; C) Final jacket leg cut jacket lift-off; D) Happy Heerema crew; E) Jacket lift-off (photos HMC) 8 Copyright 2011 by ASME

9 A B C Figure 16 A) Restraint connected to Thialf stern; B) Engaging jacket leg into restraint; C) Jacket leg secured to the Thialf (photos HMC) 9 Copyright 2011 by ASME

10 Figure 17 Heerema transports eight legged jacket as a single piece to Norway for recycling (photo HMC) 10 Copyright 2011 by ASME

Development of Self-Installing Deepwater Spar. Ashit Jadav February 2017

Development of Self-Installing Deepwater Spar. Ashit Jadav February 2017 Development of Self-Installing Deepwater Spar Ashit Jadav February 2017 Contents Introduction & Background ACE Spar breakdown Installation Sequence Main particulars, Hull design and Weight control Stability

More information

WIND TURBINE SHUTTLE HUISMAN PRODUCT BROCHURE

WIND TURBINE SHUTTLE HUISMAN PRODUCT BROCHURE WIND TURBINE SHUTTLE HUISMAN PRODUCT BROCHURE WIND TURBINE HUTTLE TABLE OF CONTENTS 01 DESCRIPTION 03 1.1 Vessel General 03 1. Purpose of the Vessel 0 1.3 High Workability 0 1. Installation Scenarios 05

More information

Wind Turbine Shuttle. Ferdinand van Heerd

Wind Turbine Shuttle. Ferdinand van Heerd Wind Turbine Shuttle Ferdinand van Heerd Contents Introduction Concept Resistance Seakeeping Vessel motion compensation system Hoisting motion compensation system Landing the wind turbine Workability Efficiency

More information

Deepwater Floating Production Systems An Overview

Deepwater Floating Production Systems An Overview Deepwater Floating Production Systems An Overview Introduction In addition to the mono hull, three floating structure designs Tension leg Platform (TLP), Semisubmersible (Semi), and Truss Spar have been

More information

Hydrodynamic Analysis of a Heavy Lift Vessel during Offshore Installation Operations

Hydrodynamic Analysis of a Heavy Lift Vessel during Offshore Installation Operations Presentation for Defense of Master Thesis Hydrodynamic Analysis of a Heavy Lift Vessel during Offshore Installation Operations Speaker: Bin Wang Supervisor: Prof. Robert Bronsart 23 rd Feb, 2015 Nantes

More information

ITTC Recommended Procedures and Guidelines

ITTC Recommended Procedures and Guidelines Page 1 of 6 Table of Contents 1. PURPOSE...2 2. PARAMETERS...2 2.1 General Considerations...2 3 DESCRIPTION OF PROCEDURE...2 3.1 Model Design and Construction...2 3.2 Measurements...3 3.5 Execution of

More information

Minimal Structures for Marginal Nova Scotia Developments

Minimal Structures for Marginal Nova Scotia Developments Minimal Structures for Marginal Nova Scotia Developments May 12, 2009 Cameron Dunn Martec is a member of the Lloyd s Register Group 1 2 Minimal Structures Project NSDOE working to make the Nova Scotia

More information

A Novel Platform for Drilling in Harsh High-Latitude Environments.

A Novel Platform for Drilling in Harsh High-Latitude Environments. AADE-7-NTCE-73 A Novel Platform for Drilling in Harsh High-Latitude Environments. Brian Roberts, Technip; Chunqun Ji, Technip; Jim O Sullivan, Technip and Terje Eilertsen, Technip. Copyright 27, AADE This

More information

OMAE INVESTIGATION ON THE USE OF DIFFERENT APPROACHES TO MOORING ANALYSIS AND APPROPRIATE SAFETY FACTORS

OMAE INVESTIGATION ON THE USE OF DIFFERENT APPROACHES TO MOORING ANALYSIS AND APPROPRIATE SAFETY FACTORS Proceedings of the ASME 212 31 st International Conference on Ocean, Offshore and Arctic Engineering OMAE212 June 1-15, 212, Rio de Janeiro, Brazil OMAE212-84121 INVESTIGATION ON THE USE OF DIFFERENT APPROACHES

More information

MASTER S THESIS. Faculty of Science and Technology. Study program/ Specialization: Offshore technology: Marine and Subsea Spring semester, 2015.

MASTER S THESIS. Faculty of Science and Technology. Study program/ Specialization: Offshore technology: Marine and Subsea Spring semester, 2015. Faculty of Science and Technology MASTER S THESIS Study program/ Specialization: Offshore technology: Marine and Subsea Spring semester, 2015 Open Writer: Aron Amundsen (Writer s signature) Faculty supervisor:

More information

UNIFIED INTERPRETATION OF PROVISIONS OF IMO SAFETY, SECURITY AND ENVIRONMENT-RELATED CONVENTIONS

UNIFIED INTERPRETATION OF PROVISIONS OF IMO SAFETY, SECURITY AND ENVIRONMENT-RELATED CONVENTIONS E SUB-COMMITTEE ON CARRIAGE OF CARGOES AND CONTAINERS 3rd session Agenda item 10 CCC 3/10/4 30 June 2016 Original: ENGLISH UNIFIED INTERPRETATION OF PROVISIONS OF IMO SAFETY, SECURITY AND ENVIRONMENT-RELATED

More information

TLP Minimum tendon tension design and tendon down-stroke investigation

TLP Minimum tendon tension design and tendon down-stroke investigation Published by International Association of Ocean Engineers Journal of Offshore Engineering and Technology Available online at www.iaoejoet.org TLP Minimum tendon tension design and tendon down-stroke investigation

More information

Offshore Stabilization Pontoon for a heavy lift vessel Concept design & workability

Offshore Stabilization Pontoon for a heavy lift vessel Concept design & workability Offshore Stabilization Pontoon for a heavy lift vessel A.M. ten Klooster Delft University of Technology OFFSHORE STABILIZATION PONTOON FOR A HEAVY LIFT VESSEL CONCEPT DESIGN & WORKABILITY by A.M. ten Klooster

More information

Trine Risøy, Bergen,

Trine Risøy, Bergen, part of Aker The Installation of Subsea Structures without Offshore Crane Vessel Trine Risøy, Bergen, 04.06.2008 2008 Aker Solutions AKER MARINE CONTRACTORS (AMC) 35 years experience worldwide: Subsea

More information

GEA FOR ADVANCED STRUCTURAL DYNAMIC ANALYSIS

GEA FOR ADVANCED STRUCTURAL DYNAMIC ANALYSIS SMART SOLUTIONS FOR VIBRATION MONITORING GEA FOR ADVANCED STRUCTURAL DYNAMIC ANALYSIS ANALYSIS OF CIVIL STRUCTURES - EXPO MERLATA PEDESTRIAN BRIDGE ABSTRACT Civil structures and in particular bridges and

More information

Fully Submersible Heavy Lift Vessel

Fully Submersible Heavy Lift Vessel Fully Submersible Heavy Lift Vessel Arnbjorn Joensen Oil and Gas Authority (OGA) (15th February 2016) CONTENT Leadon structures demobilisation Competitiveness (case studies) Decommissioning options Installation

More information

Effect of Wave Steepness on Yaw Motions of a Weathervaning Floating Platform

Effect of Wave Steepness on Yaw Motions of a Weathervaning Floating Platform 16 th Australasian Fluid Mechanics Conference Crown Plaza, Gold Coast, Australia 2-7 December 27 Effect of Wave Steepness on Yaw Motions of a Weathervaning Floating Platform Jayanth Munipalli, and Krish

More information

RESPONSE BASED WEATHER-ROUTING AND OPERATION PLANNING OF HEAVY TRANSPORT VESSELS

RESPONSE BASED WEATHER-ROUTING AND OPERATION PLANNING OF HEAVY TRANSPORT VESSELS RESPONSE BASED WEATHER-ROUTING AND OPERATION PLANNING OF HEAVY TRANSPORT VESSELS L J M Adegeest, AMARCON, The Netherlands SUMMARY Using the dynamic characteristics of the vessel in combination with weather

More information

STRIDE PROJECT Steel Risers in Deepwater Environments Achievements

STRIDE PROJECT Steel Risers in Deepwater Environments Achievements STRIDE PROJECT Steel Risers in Deepwater Environments Achievements 1999-21 Neil Willis Principal Engineer 2H Offshore Engineering 6 th Annual Deepwater Technologies and Developments Conference 21 The presentation

More information

Pile Gripper Systems

Pile Gripper Systems Pile Gripper Systems Accurate positioning and restraint of offshore construction piles + + Accurate handling of piles up to 8.0m in diameter + + Pile positioning and adjustment within large envelopes +

More information

Seakeeping Tests (with ships) Experimental Methods in Marine Hydrodynamics Lecture in week 43

Seakeeping Tests (with ships) Experimental Methods in Marine Hydrodynamics Lecture in week 43 Seakeeping Tests (with ships) Experimental Methods in Marine Hydrodynamics Lecture in week 43 1 Topics Why do seakeeping tests? What to do? Activities Details of model test set-up and instrumentation Waves

More information

IMO REVISION OF THE INTACT STABILITY CODE. Proposal of methodology of direct assessment for stability under dead ship condition. Submitted by Japan

IMO REVISION OF THE INTACT STABILITY CODE. Proposal of methodology of direct assessment for stability under dead ship condition. Submitted by Japan INTERNATIONAL MARITIME ORGANIZATION E IMO SUB-COMMITTEE ON STABILITY AND LOAD LINES AND ON FISHING VESSELS SAFETY 49th session Agenda item 5 SLF 49/5/5 19 May 2006 Original: ENGLISH REVISION OF THE INTACT

More information

CALCULATIONS OF THE MOTIONS OF A SHIP MOORED WITH MOORMASTER UNITS

CALCULATIONS OF THE MOTIONS OF A SHIP MOORED WITH MOORMASTER UNITS CALCULATIONS OF THE MOTIONS OF A SHIP MOORED WITH MOORMASTER UNITS By J. de Bont 1, W. van der Molen 2, J. van der Lem 3, H. Ligteringen 4, D. Mühlestein 5 and M. Howie 6 ABSTRACT Container ships should

More information

Edit this text for your title

Edit this text for your title Edit this text for your title MEK 4450 Marine Operations Edit this text for your sub-title Presenter name, location, date etc. Kværner ASA / DNV, Fall 2013 Lesson 2/3 Lift phases Load out Transportation

More information

Offshore Oil and Gas Platforms for Deep Waters

Offshore Oil and Gas Platforms for Deep Waters Offshore Oil and Gas Platforms for Deep Waters Atilla Incecik Department of Naval Architecture, Ocean and Marine Engineering University of Strathclyde, Glasgow, UK (atilla.incecik@strath.ac.uk) Summary

More information

An Investigation of a Safety Level in Terms of. Excessive Acceleration in Rough Seas

An Investigation of a Safety Level in Terms of. Excessive Acceleration in Rough Seas Proceedings of the h International Conference on the Stability of Ships and Ocean Vehicles, 4-9 June 5, Glasgow, UK. An Investigation of a Safety Level in Terms of Excessive Acceleration in Rough Seas

More information

Slamming Analysis on a 35,000 Ton Class of Drillship

Slamming Analysis on a 35,000 Ton Class of Drillship Slamming Analysis on a 35,000 Ton Class of Drillship Mahasin M. Ahmad, a,* Eko B. Djatmiko, b, and Handayanu, b a) Master Degree Student, Marine Technology Post-Graduate Program, Institut Teknologi Sepuluh

More information

REVISITING GLOBAL RESPONSE OF FPSOS IN SHALLOW WATER AND THE RISER ANALYSIS REQUIREMENTS

REVISITING GLOBAL RESPONSE OF FPSOS IN SHALLOW WATER AND THE RISER ANALYSIS REQUIREMENTS REVISITING GLOBAL RESPONSE OF FPSOS IN SHALLOW WATER AND THE RISER ANALYSIS REQUIREMENTS AMIR H. IZADPARAST SENIOR RESEARCH ENGINEER, HYDRODYNAMICS AND MOORING TECHNOLOGY, SOFEC JIAXING CHEN RESEARCH ENGINEER,

More information

ITTC - Recommended Procedures and Guidelines

ITTC - Recommended Procedures and Guidelines 7.5 Page 1 of 5 Table of Contents 1. PURPOSE OF PROCEDURE... 2 2. DESCRIPTION OF PROCEDURE... 2 4. DOCUMENTATION... 4 5. REFERENCES... 4 3. PARAMETERS... 4 Updated by Approved Manoeuvring Committee of

More information

EXPERIMENTAL INVESTIGATIONS OF BARGE FLOATER WITH MOONPOOL FOR 5 MW WIND TURBINE

EXPERIMENTAL INVESTIGATIONS OF BARGE FLOATER WITH MOONPOOL FOR 5 MW WIND TURBINE EXPERIMENTAL INVESTIGATIONS OF BARGE FLOATER WITH MOONPOOL FOR 5 MW WIND TURBINE 1 MR. G.VIJAYA KUMAR, 2 DR. R. PANNEER SELVAM 1 M.S. Research Scholar, Department of Ocean Engineering, IIT Madras, Chennai,

More information

RIGID RISERS FOR TANKER FPSOs

RIGID RISERS FOR TANKER FPSOs RIGID RISERS FOR TANKER FPSOs Stephen A. Hatton 2H Offshore Engineering Ltd. SUMMARY Recent development work on the subject of dynamic rigid (steel pipe) risers demonstrates that their scope of application

More information

Abstract. 1 Introduction

Abstract. 1 Introduction A computational method for calculatingthe instantaneous restoring coefficients for a ship moving in waves N. El-Simillawy College of Engineering and Technology, Arab Academyfor Science and Technology,

More information

DUKC DYNAMIC UNDER KEEL CLEARANCE

DUKC DYNAMIC UNDER KEEL CLEARANCE DUKC DYNAMIC UNDER KEEL CLEARANCE Information Booklet Prepared in association with Marine Services Department 10/10/2005 Dynamic Under Keel Clearance (DUKC) integrates real time measurement of tides and

More information

Modelling of Extreme Waves Related to Stability Research

Modelling of Extreme Waves Related to Stability Research Modelling of Extreme Waves Related to Stability Research Janou Hennig 1 and Frans van Walree 1 1. Maritime Research Institute Netherlands,(MARIN), Wageningen, the Netherlands Abstract: The paper deals

More information

Development of TEU Type Mega Container Carrier

Development of TEU Type Mega Container Carrier Development of 8 700 TEU Type Mega Container Carrier SAKAGUCHI Katsunori : P. E. Jp, Manager, Ship & Offshore Basic Design Department, IHI Marine United Inc. TOYODA Masanobu : P. E, Jp, Ship & Offshore

More information

Fully Submersible Heavy Lift Vessel

Fully Submersible Heavy Lift Vessel Fully Submersible Heavy Lift Vessel Arnbjorn Joensen Aberdeen Maritime Branch (28th January 2015) PRESENTATION Introduction to the Subsea Deployment Vessel Installation method Tank test video Potential

More information

Background material and considerations of sea-state limitations for helicopter landing and take-off on passenger ships and ferries are undertaken.

Background material and considerations of sea-state limitations for helicopter landing and take-off on passenger ships and ferries are undertaken. 1 Annex 7 Weather Conditions and Helicopter Landing Background material and considerations of sea-state limitations for helicopter landing and take-off on passenger ships and ferries are undertaken. 1

More information

Sea State Estimation from an Advancing Ship

Sea State Estimation from an Advancing Ship Sea State Estimation from an Advancing Ship The wave buoy analogy Ulrik Dam Nielsen and Ingrid Marie Vincent Andersen Technical University of Denmark Presentation at Skibsteknisk Selskab March 5 th, 2012,

More information

STATION KEEPING EXTENSIVE MODEL TESTING OF A DRY-TREE SPREAD-MOORED BARGE IN BRAZILLIAN WATERS

STATION KEEPING EXTENSIVE MODEL TESTING OF A DRY-TREE SPREAD-MOORED BARGE IN BRAZILLIAN WATERS STATION KEEPING EXTENSIVE MODEL TESTING OF A DRY-TREE SPREAD-MOORED BARGE IN BRAZILLIAN WATERS Arjan Voogt (MARIN) and Mamoun Naciri (SBM) Deep Offshore Technology XIV (DOT-2002) ABSTRACT This paper describes

More information

MINIMUM DECK HEIGHT OF A SEMI-SUBMERSIBLE PLATFORM ACCORDING TO BLACK SEA ENVIRONMENT

MINIMUM DECK HEIGHT OF A SEMI-SUBMERSIBLE PLATFORM ACCORDING TO BLACK SEA ENVIRONMENT MINIMUM DECK HEIGHT OF A SEMI-SUBMERSIBLE PLATFORM ACCORDING TO BLACK SEA ENVIRONMENT Ionuț-Cristian SCURTU Principal instructor, Navy Academy Mircea cel Batran Constanta, Romania Abstract-The fast evolution

More information

Impact of Passive Heave Compensator on Offshore Lifting

Impact of Passive Heave Compensator on Offshore Lifting Journal of Shipping and Ocean Engineering 5 (2015) 166-180 doi: 10.17265/2159-5879/2015.04.003 D DAVID PUBLISHING Impact of Passive Heave Compensator on Offshore Lifting Arvind Keprate Department of Mechanical

More information

SOFTWARE. Sesam user course. 02 May 2016 HydroD Input. Ungraded SAFER, SMARTER, GREENER DNV GL 2016

SOFTWARE. Sesam user course. 02 May 2016 HydroD Input. Ungraded SAFER, SMARTER, GREENER DNV GL 2016 SOFTWARE Sesam user course DNV GL 1 SAFER, SMARTER, GREENER About the presenter Name: Torgeir Kirkhorn Vada Position: Product Manager for floating structures Background: PhD in Applied mathematics/hydrodynamics

More information

TRACK RECORD SEP. 2018

TRACK RECORD SEP. 2018 TRACK RECORD SEP. 2018 TABLE OF CONTENTS 1 INTRODUCTION... 3 2 MOTION COMPENSATED GANGWAY... 5 2.1 In operation at Walney Extension... 6 2.2 In operation at Borkum Riffgrund II... 7 3 MOTION COMPENSATED

More information

SOFTWARE. Sesam user course. 12 May 2016 HydroD Hydrostatics & Stability. Ungraded SAFER, SMARTER, GREENER DNV GL 2016

SOFTWARE. Sesam user course. 12 May 2016 HydroD Hydrostatics & Stability. Ungraded SAFER, SMARTER, GREENER DNV GL 2016 SOFTWARE Sesam user course DNV GL 1 SAFER, SMARTER, GREENER Scope of presentation Describe features & commands for performing a hydrostatic analysis, and their concepts Analysis setup Code-checking Reporting

More information

Planning of Drilling Operations in Extreme Ocean Currents

Planning of Drilling Operations in Extreme Ocean Currents DYNAMIC POSITIONING CONFERENCE October 11-12, 2016 OPERATIONS Planning of Drilling Operations in Extreme Ocean Currents Luca Pivano - Marine Cybernetics/DNV GL Kristopher Eide - Marine Cybernetics/DNV

More information

1. Outline of the newly developed control technologies

1. Outline of the newly developed control technologies This paper describes a vertical lifting control and level luffing control design for newly developed, fully hydraulicdriven floating cranes. Unlike lattice boom crawler cranes for land use, the floating

More information

Dynamic Positioning: Method for Disaster Prevention and Risk Management

Dynamic Positioning: Method for Disaster Prevention and Risk Management Available online at www.sciencedirect.com ScienceDirect Procedia Earth and Planetary Science 11 ( 2015 ) 216 223 Global Challenges, Policy Framework & Sustainable Development for Mining of Mineral and

More information

The SDS Skip. Subsea Deployment Systems Ltd.

The SDS Skip. Subsea Deployment Systems Ltd. The SDS Skip SUBSEA SKIP An alternative to enhance the recovery of structures, spool pieces, mattresses etc. during decommissioning work Can be used to transport complex structures or spool pieces to field

More information

Subj: Explanation of Upper Level Capacity and Stability Characteristics for Rolling Boat, Inc. Vessels.

Subj: Explanation of Upper Level Capacity and Stability Characteristics for Rolling Boat, Inc. Vessels. 23 Apr, 2009 From: Tullio Celano III P.E. To: Underwriters of Rolling Boat, Inc. Via: Phil Kazmierowicz, President, Rolling Boat, Inc. Subj: Explanation of Upper Level Capacity and Stability Characteristics

More information

OTC Copyright 2003, Offshore Technology Conference

OTC Copyright 2003, Offshore Technology Conference OTC 54 Model Test Experience on Vortex Induced Vibrations of Truss Spars Radboud van Dijk, Maritime Research Institute Netherlands, Allan Magee, Technip Offshore, Inc., Steve Perryman, BP Americas, Inc.,

More information

INCREASE OPERATING DAYS ENHANCE DECK SAFETY AND SPEED MINIMIZE SEA SICKNESS HEAVY DUTY GYROSTABILIZERS FOR COMMERCIAL & DEFENCE APPLICATIONS

INCREASE OPERATING DAYS ENHANCE DECK SAFETY AND SPEED MINIMIZE SEA SICKNESS HEAVY DUTY GYROSTABILIZERS FOR COMMERCIAL & DEFENCE APPLICATIONS LESS MOTION MORE OCEAN HEAVY DUTY GYROSTABILIZERS FOR COMMERCIAL & DEFENCE APPLICATIONS INCREASE OPERATING DAYS ENHANCE DECK SAFETY AND SPEED MINIMIZE SEA SICKNESS 2 VEEM Gyro DEFENCE Image courtesy of

More information

THE BEHAVIOUR OF TUGS IN WAVES ASSISTING LNG CARRIERS DURING BERTHING ALONG OFFSHORE LNG TERMINALS

THE BEHAVIOUR OF TUGS IN WAVES ASSISTING LNG CARRIERS DURING BERTHING ALONG OFFSHORE LNG TERMINALS Proceedings of OMAE 5 4 th International Conference on Offshore Mechanics and Arctic Engineering -7 June 5 Halkidiki, Greece THE BEHAVIOUR OF TUGS IN WAVES ASSISTING LNG CARRIERS DURING BERTHING ALONG

More information

Alternative Installation Methods for. Offshore Wind Substations

Alternative Installation Methods for. Offshore Wind Substations Department of Mechanical and Aerospace Engineering Alternative Installation Methods for Offshore Wind Substations Author: Justo Aguiar Quintana Supervisor: Mr Cameron Johnstone A thesis submitted in partial

More information

U S F O S B u o y a n c y And Hydrodynamic M a s s

U S F O S B u o y a n c y And Hydrodynamic M a s s 1 U S F O S B u o y a n c y And Hydrodynamic M a s s 2 CONTENTS: 1 INTRODUCTION... 3 2 ACCURACY LEVELS... 3 2.1 LEVEL-0... 3 2.2 LEVEL-1... 3 2.3 PANEL MODEL... 3 3 EX 1. SINGLE PIPE. NON FLOODED... 4

More information

An Investigation into the Capsizing Accident of a Pusher Tug Boat

An Investigation into the Capsizing Accident of a Pusher Tug Boat An Investigation into the Capsizing Accident of a Pusher Tug Boat Harukuni Taguchi, National Maritime Research Institute (NMRI) taguchi@nmri.go.jp Tomihiro Haraguchi, National Maritime Research Institute

More information

The Benefits Of Composite Materials In Deepwater Riser Applications. 26 th March 2015 Hassan Saleh Senior Engineer 2H Offshore Engineering Ltd

The Benefits Of Composite Materials In Deepwater Riser Applications. 26 th March 2015 Hassan Saleh Senior Engineer 2H Offshore Engineering Ltd The Benefits Of Composite Materials In Deepwater Riser Applications 26 th March 2015 Hassan Saleh Senior Engineer 2H Offshore Engineering Ltd Composite Benefits and Challenges Composite Materials offer

More information

COUPLED DYNAMIC ANALYSIS OF MOORING LINES FOR DEEP WATER FLOATING SYSTEMS

COUPLED DYNAMIC ANALYSIS OF MOORING LINES FOR DEEP WATER FLOATING SYSTEMS Proceedings of International Conference in Ocean Engineering, ICOE Proceedings 2009 of ICOE 2009 Coupled Dynamic Analysis IIT Madras, of Chennai, Mooring India. Lines for Deep Water Floating Systems 1-5

More information

Learn more at

Learn more at Full scale model tests of a steel catenary riser C. Bridge 1, H. Howells 1, N. Toy 2, G. Parke 2, R. Woods 2 1 2H Offshore Engineering Ltd, Woking, Surrey, UK 2 School of Engineering, University of Surrey,

More information

Corrosion problems in seawater pump caissons. Practical solutions.

Corrosion problems in seawater pump caissons. Practical solutions. Corrosion problems in seawater pump caissons. Practical solutions. Svenn Magne Wigen FORCE Technology Norway AS Hornebergveien 7 7038 Trondheim, Norway Harald Osvoll FORCE Technology Norway AS Hornebergveien

More information

ITTC Recommended Procedures Testing and Extrapolation Methods Loads and Responses, Seakeeping Experiments on Rarely Occurring Events

ITTC Recommended Procedures Testing and Extrapolation Methods Loads and Responses, Seakeeping Experiments on Rarely Occurring Events Loads and Responses, Seakeeping Page 1 of 5 CONTENTS 1. PURPOSE OF PROCEDURE 2. STANDARDS FOR EXPERIMENTS ON RARELY OCCURRING EVENTS 2.1 Previous Recommendations of ITTC 2.2 Model Design and Construction

More information

OVERVIEW. Capabilities & Services

OVERVIEW. Capabilities & Services +1.713.467.0505 Sales@boamarine.com www.boamarine.com OVERVIEW Capabilities & Services BOA MARINE SERVICES provides engineering, construction and contracting services related to fi xed and fl oating offshore

More information

THE EFFECTS OF THE HULL VANE ON SHIP MOTIONS OF FERRIES AND ROPAX VESSELS

THE EFFECTS OF THE HULL VANE ON SHIP MOTIONS OF FERRIES AND ROPAX VESSELS THE EFFECTS OF THE HULL VANE ON SHIP MOTIONS OF FERRIES AND ROPAX VESSELS K Uithof, B Bouckaert, P G van Oossanen, and N Moerke, Hull Vane B.V., van Oossanen Naval Architecture, and van Oossanen Fluid

More information

Description of Underwater Noise Attenuation System Design Unit 2. New NY Bridge Project

Description of Underwater Noise Attenuation System Design Unit 2. New NY Bridge Project New NY Bridge Project Description of Underwater Noise Attenuation System (NAS) Design Unit 2 Description of Underwater Noise Attenuation System Design Unit 2 for the New NY Bridge Project Revision 1 May

More information

FAST SUPPLY INTERVENTION and CREW TRANSFER VESSEL M P 6 2 5

FAST SUPPLY INTERVENTION and CREW TRANSFER VESSEL M P 6 2 5 FAST SUPPLY INTERVENTION and CREW TRANSFER VESSEL M P 6 2 5 MAIN PARTICULARS LENGTH OVER ALL 60.68 m LENGTH WATER LINE 59.35 m BREADTH MAX 20.80 m DRAUGHT MAX 3.10 m DEPTH 6.70 m MAX SPEED 37.0 knots @

More information

Dynamic Positioning Control Augmentation for Jack-up Vessels

Dynamic Positioning Control Augmentation for Jack-up Vessels DYNAMIC POSITIONING CONFERENCE October 9-10, 2012 Design and Control Session Dynamic Positioning Control Augmentation for Jack-up Vessels By Bradley Deghuee L-3 Communications 1 Introduction Specialized

More information

Sea state estimation from an advancing ship - The wave buoy analogy Presentation at Skibsteknisk Selskab

Sea state estimation from an advancing ship - The wave buoy analogy Presentation at Skibsteknisk Selskab Downloaded from orbit.dtu.dk on: Nov 17, 2018 Sea state estimation from an advancing ship - The wave buoy analogy Presentation at Skibsteknisk Selskab Nielsen, Ulrik Dam; Andersen, Ingrid Marie Vincent

More information

High-Energy Ship Collision with Jacket Legs

High-Energy Ship Collision with Jacket Legs High-Energy Ship Collision with Jacket Legs Jørgen Amdahl Department of Marine Structures, NTNU, Trondheim, Norway Atle Johansen MARINTEK, Trondheim, Norway ABSTRACT Risk analysis of planned jacket installations

More information

for Naval Aircraft Operations

for Naval Aircraft Operations Seakeeping Assessment of Large Seakeeping Assessment of Large Trimaran Trimaran for Naval Aircraft Operations for Naval Aircraft Operations Presented by Mr. Boyden Williams, Mr. Lars Henriksen (Viking

More information

INCLINOMETER DEVICE FOR SHIP STABILITY EVALUATION

INCLINOMETER DEVICE FOR SHIP STABILITY EVALUATION Proceedings of COBEM 2009 Copyright 2009 by ABCM 20th International Congress of Mechanical Engineering November 15-20, 2009, Gramado, RS, Brazil INCLINOMETER DEVICE FOR SHIP STABILITY EVALUATION Helena

More information

NIS/NOR Circular. Category: Circular no.: 07/2007

NIS/NOR Circular. Category: Circular no.: 07/2007 NIS/NOR Circular Category: Circular no.: 07/2007 Operational Nautical Our ref. and file no.: Technical Other Date: 7 September 2007 GUIDELINES FOR REVISION OF ISM-MANUALS ON SUPPLY SHIPS AND TUGS USED

More information

A comprehensive method for the structural design and verification of the INNWIND 10MW tri-spar floater

A comprehensive method for the structural design and verification of the INNWIND 10MW tri-spar floater NATIONAL TECHNICAL UNIVERSITY of ATHENS (NTUA) A comprehensive method for the structural design and verification of the INNWIND 10MW tri-spar floater DI Manolas, CG Karvelas, IA Kapogiannis, VA Riziotis,

More information

Lab test 4 Seakeeping test with a model of an oil tanker

Lab test 4 Seakeeping test with a model of an oil tanker Lab test 4 Seakeeping test with a model of an oil tanker The response amplitude operators (RAO) in head seas of a 1:100 scale model of a 257 m long oil tanker shall be determined by model testing in the

More information

Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico Field Development

Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico Field Development Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico Field Development 10121-4404-03 Jelena Vidic-Perunovic, Doris, Inc. Lars Ødeskaug, Sevan Marine ASA RPSEA Ultra-Deepwater Technology

More information

VESSEL DESIGNS HUISMAN PRODUCT BROCHURE

VESSEL DESIGNS HUISMAN PRODUCT BROCHURE VESSEL DESIGNS HUISMAN PRODUCT BROCHURE VESSEL ESIGNS TABLE OF CONTENTS 01 GENERAL 03 1.1 Introduction 03 1.2 Development 03 02 DRILL SHIPS 06 2.1 HuisDrill 12000 06 03 MOBILE OFFSHORE DRILLING UNITS 07

More information

EFFECT OF DIFFERENT MOORING SYSTEMS ON HYDRODYNAMIC ANALYSIS OF AN OFFSHORE WIND TURBINE

EFFECT OF DIFFERENT MOORING SYSTEMS ON HYDRODYNAMIC ANALYSIS OF AN OFFSHORE WIND TURBINE EFFECT OF DIFFERENT MOORING SYSTEMS ON HYDRODYNAMIC ANALYSIS OF AN OFFSHORE WIND TURBINE Sabri ALKAN 1, Ayhan Mentes 2, Ismail H. Helvacioglu 2, Nagihan Turkoglu 2 1 Department of Mechanical Engineering,

More information

ShipRight. Additional Design Procedures. Comparative Sloshing Analysis of LNG Ship Containment Systems. Design and construction

ShipRight. Additional Design Procedures. Comparative Sloshing Analysis of LNG Ship Containment Systems. Design and construction ShipRight Design and construction Additional Design Procedures Comparative Sloshing Analysis of LNG Ship Containment Systems April 2005 ABCD Lloyd s Register Marine Business Stream 71 Fenchurch Street

More information

RESOLUTION MSC.141(76) (adopted on 5 December 2002) REVISED MODEL TEST METHOD UNDER RESOLUTION 14 OF THE 1995 SOLAS CONFERENCE

RESOLUTION MSC.141(76) (adopted on 5 December 2002) REVISED MODEL TEST METHOD UNDER RESOLUTION 14 OF THE 1995 SOLAS CONFERENCE MSC 76/23/Add.1 RESOLUTION MSC.141(76) THE MARITIME SAFETY COMMITTEE, RECALLING Article 38(c) of the Convention on the International Maritime Organization concerning the functions of the Committee, RECALLING

More information

DP Ice Model Test of Arctic Drillship

DP Ice Model Test of Arctic Drillship Author s Name Name of the Paper Session DYNAMIC POSITIONING CONFERENCE October 11-12, 211 ICE TESTING SESSION DP Ice Model Test of Arctic Drillship Torbjørn Hals Kongsberg Maritime, Kongsberg, Norway Fredrik

More information

Sea Gyro SG series K. Technical Information 2011

Sea Gyro SG series K. Technical Information 2011 Sea Gyro SG series K Technical Information 2011 Manufacturing company: Gyro Technologies Sdn. Bhd. 90 Jalan Waja Indah 2, Taman Waja Indah. Kulim. Malaysia. 09000 Phone +604 5000137 Fax +604 5000139 Email:

More information

FORECASTING OF ROLLING MOTION OF SMALL FISHING VESSELS UNDER FISHING OPERATION APPLYING A NON-DETERMINISTIC METHOD

FORECASTING OF ROLLING MOTION OF SMALL FISHING VESSELS UNDER FISHING OPERATION APPLYING A NON-DETERMINISTIC METHOD 8 th International Conference on 633 FORECASTING OF ROLLING MOTION OF SMALL FISHING VESSELS UNDER FISHING OPERATION APPLYING A NON-DETERMINISTIC METHOD Nobuo Kimura, Kiyoshi Amagai Graduate School of Fisheries

More information

Chapter 2 Hydrostatics and Control

Chapter 2 Hydrostatics and Control Chapter 2 Hydrostatics and Control Abstract A submarine must conform to Archimedes Principle, which states that a body immersed in a fluid has an upward force on it (buoyancy) equal to the weight of the

More information

MIL-STD-883G METHOD

MIL-STD-883G METHOD STEADY-STATE LIFE 1. PURPOSE. The steady-state life test is performed for the purpose of demonstrating the quality or reliability of devices subjected to the specified conditions over an extended time

More information

Determination of the Design Load for Structural Safety Assessment against Gas Explosion in Offshore Topside

Determination of the Design Load for Structural Safety Assessment against Gas Explosion in Offshore Topside Determination of the Design Load for Structural Safety Assessment against Gas Explosion in Offshore Topside Migyeong Kim a, Gyusung Kim a, *, Jongjin Jung a and Wooseung Sim a a Advanced Technology Institute,

More information

Marine Kit 4 Marine Kit 4 Sail Smooth, Sail Safe

Marine Kit 4 Marine Kit 4 Sail Smooth, Sail Safe Marine Kit 4 Marine Kit 4 Sail Smooth, Sail Safe Includes Basic ship Terminologies and Investigation Check list Index 1. Ship Terminology 03 2. Motions of a Floating Body...09 3. Ship Stability.10 4. Free

More information

DEVELOPMENT OF OPERATIONAL LIMIT DIAGRAMS FOR OFFSHORE LIFTING PROCEDURES

DEVELOPMENT OF OPERATIONAL LIMIT DIAGRAMS FOR OFFSHORE LIFTING PROCEDURES Proceedings of the th International Conference on Ocean, Offshore and Arctic Engineering OMAE 0 May -June, 0, St. John's, NL, Canada DRAFT OMAE0-70 DEVELOPMENT OF OPERATIONAL LIMIT DIAGRAMS FOR OFFSHORE

More information

Challenges in estimating the vessel station-keeping performance

Challenges in estimating the vessel station-keeping performance Challenges in estimating the vessel station-keeping performance Luca Pivano, Brede Børhaug and Øyvind Smogeli Marine Cybernetics, Trondheim, Norway E-mail: lp@marinecyb.com One of the challenges in the

More information

DECOMMISSIONING. Mark Couwenberg Naval Architect Damen Offshore & Transport 12 May 2017

DECOMMISSIONING. Mark Couwenberg Naval Architect Damen Offshore & Transport 12 May 2017 DECOMMISSIONING Mark Couwenberg Naval Architect Damen Offshore & Transport 12 May 2017 FEELINGS AGENDA BACKGROUND THE VESSEL THE FUNCTIONS PARTNERS BACKGROUND BACKGROUND BACKGROUND OLSO PARIS CONVENTION

More information

Semi-Submersible Offshore Platform Simulation Using ANSA & META

Semi-Submersible Offshore Platform Simulation Using ANSA & META Semi-Submersible Offshore Platform Simulation Using ANSA & META Offshore platforms are large structures designed to withstand extreme weather conditions and have a lifespan of at least 40 years. Million

More information

Innovative and Robust Design. With Full Extension of Offshore Engineering and Design Experiences.

Innovative and Robust Design. With Full Extension of Offshore Engineering and Design Experiences. Innovative and Robust Design by VL Offshore With Full Extension of Offshore Engineering and Design Experiences www.vloffshore.com Y Wind Semi Designed by VL Offshore The Y Wind Semi platform (foundation)

More information

Abstract. 1. Introduction. 2. Design Requirements. Naval Engineer - INTERMOOR DO BRASIL 2. Petroleum Engineer INTERMOOR DO BRASIL 3

Abstract. 1. Introduction. 2. Design Requirements. Naval Engineer - INTERMOOR DO BRASIL 2. Petroleum Engineer INTERMOOR DO BRASIL 3 IBP1687_14 MOORING SYSTEM FOR A SEMI-SUBMERSIBLE RIG IN ULTRA-DEEPWATER AND UNDER SEVERE CURRENTS Debora C. B. Ralha 1, Manuela C. Corrêa 2, Jeremy Abercrombie 3 and Karina G. Pinheiro 1 Copyright 2014,

More information

WAVE IMPACTS DUE TO STEEP FRONTED WAVES

WAVE IMPACTS DUE TO STEEP FRONTED WAVES WAVE IMPACTS DUE TO STEEP FRONTED WAVES Bas Buchner and Arjan Voogt Maritime Research Institute Netherlands (MARIN) b.buchner@marin.nl, a.j.voogt@marin.nl INTRODUCTION It is the question whether Rogue

More information

BIBBY POLARIS MULTI PURPOSE DIVE SUPPORT & OFFSHORE CONSTRUCTION VESSEL

BIBBY POLARIS MULTI PURPOSE DIVE SUPPORT & OFFSHORE CONSTRUCTION VESSEL BIBBY POLARIS MULTI PURPOSE DIVE SUPPORT & OFFSHORE CONSTRUCTION VESSEL Saturation & Air Diving Support Structure Installation Flexible, Flowline & Umbilical Installation Inspection, Repair & Maintenance

More information

IACS URS11 defines the dimensioning wave load for ship design, but what does it mean from a statistical point of view?

IACS URS11 defines the dimensioning wave load for ship design, but what does it mean from a statistical point of view? IACS URS11 defines the dimensioning wave load for ship design, but what does it mean from a statistical point of view? Seamocs meeting in Malta Gaute Storhaug, DNV Maritime 19th of March 2009 Overview

More information

WAVE MECHANICS FOR OCEAN ENGINEERING

WAVE MECHANICS FOR OCEAN ENGINEERING Elsevier Oceanography Series, 64 WAVE MECHANICS FOR OCEAN ENGINEERING P. Boccotti Faculty of Engineering University of Reggio-Calabria Feo di Vito 1-89060 Reggio-Calabria Italy 2000 ELSEVIER Amsterdam

More information

Study of Passing Ship Effects along a Bank by Delft3D-FLOW and XBeach1

Study of Passing Ship Effects along a Bank by Delft3D-FLOW and XBeach1 Study of Passing Ship Effects along a Bank by Delft3D-FLOW and XBeach1 Minggui Zhou 1, Dano Roelvink 2,4, Henk Verheij 3,4 and Han Ligteringen 2,3 1 School of Naval Architecture, Ocean and Civil Engineering,

More information

Dynamic analysis of offshore floating wind turbines

Dynamic analysis of offshore floating wind turbines Dynamic analysis of offshore floating wind turbines Hasan Bagbanci Centre for Marine Technology and Engineering (CENTEC), Instituto Superior Técnico Technical University of Lisbon, Lisboa, Portugal ABSTRACT:

More information

A Wave Basin Model Test Study for a Jackup Moored on the Dock

A Wave Basin Model Test Study for a Jackup Moored on the Dock Proceedings of the Twenty-fifth (2015) International Ocean and Polar Engineering Conference Kona, Big Island, Hawaii, USA, June 21-26, 2015 Copyright 2015 by the International Society of Offshore and Polar

More information

Learn more at

Learn more at IBP1833_06 COST EFFICIENT ARTIFICIAL BUOYANT SEABED DRILLING SOLUTION Dan Moutrey 1, Frank Lim 2 Copyright 2006, Instituto Brasileiro de Petróleo e Gás - IBP This Technical Paper was prepared for presentation

More information

Offshore Pipeline Installation SEABED INTERVENTION THE GAME-CHANGING EFFECT DISRUPTION TO HEAVY LIFTING HOW DO YOU MAKE THE SEABED?

Offshore Pipeline Installation SEABED INTERVENTION THE GAME-CHANGING EFFECT DISRUPTION TO HEAVY LIFTING HOW DO YOU MAKE THE SEABED? OSI 2016 VOLUME 9 ISSUE 1 OSI VOL. 9 ISSUE 1 2016 i n d u s t r y DECOMMISSIONING THE GAME-CHANGING EFFECT DISRUPTION TO HEAVY LIFTING OFFSHORE-INDUSTRY.EU SEABED INTERVENTION HOW DO YOU MAKE THE SEABED?

More information

Design of Offshore Structures Prof. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras

Design of Offshore Structures Prof. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras (Refer Slide Time: 00:32) Design of Offshore Structures Prof. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras Module - 2 Lecture - 1 Concepts of Fixed Offshore Platform

More information