RISK AND STANDARDS BASED APPROACH TO RIP RAP DESIGN ALTERNATIVES FOR GRAHAMSTOWN DAM STAGE 2 AUGMENTATION

Size: px
Start display at page:

Download "RISK AND STANDARDS BASED APPROACH TO RIP RAP DESIGN ALTERNATIVES FOR GRAHAMSTOWN DAM STAGE 2 AUGMENTATION"

Transcription

1 RISK AND STANDARDS BASED APPROACH TO RIP RAP DESIGN ALTERNATIVES FOR GRAHAMSTOWN DAM STAGE 2 AUGMENTATION M. B. Barker 1 and D. Holroyde 2 ABSTRACT. A detailed study was completed for the Stage 2 works of the Grahamstown Dam augmentation to investigate various alternatives for the slope protection of the Saddle Dam and Subsidiary Dam embankments, including a standards based and a risk management approach. The standards based approach required an evaluation of the slope protection level and least cost option based on the hazard rating of the dam. Due to the sand construction of the embankments, it was possible to apply a wave erosion model SBEACH to develop an economic risk model for optimising the slope protection alternatives. The erosion model included the effects of the wind direction, reservoir level and wind speed variation during flood events, embankment profile and material parameters. The risk management approach clearly showed that significant cost savings could be achieved by using the risk management approach. Furthermore, the cost curves indicated the sections of the embankments for which present capital works would not be economically justified and for which ongoing maintenance works would be economically advantageous. 1 Introduction Grahamstown Dam is a major water supply source for the Newcastle area and it is proposed to raise the present full supply by 2.4m from RL 10.4m to RL 12.8m. The dam, as shown on Figure 1 comprises the following embankments: The Pacific Highway to the north west of the reservoir The Main Dam to the West Figure 1 - Locality Plan 1 Principal Engineers Dams & Geotechnical, Gutteridge Haskins & Davey Pty Ltd, Brisbane, QLD 2 Water Resource Engineer, Planning, Hunter Water Corporation, Newcastle, NSW

2 The Subsidiary/Saddle Dam to the South The new embankment adjacent to the proposed spillway to the north west With the exception of the new embankment, all of the existing embankments have been constructed of sand. The main and saddle dam embankments have a central core while the subsidiary embankment has a bentonite sand cut-off. The raising is being completed in stages for which Stage 1 comprised raising the core level of the existing embankments to a level required for the Stage 2 full supply level and rip rap slope protection of the main embankment. The stage 2 works comprises construction of a new spillway and associated embankment, a culvert below the Pacific Highway to pass the new spillway flows, a protection bund for the Newline Road and pollution control works. To comply with the Supplementary Environmental Impact Statement for the Stage 2 works, approximately 3000m of the Saddle Dam and Subsidiary Dam upstream slopes required investigation and design of slope protection works. The objectives were to provide protection works in accordance with the ANCOLD 2000 Guidelines for Selection of Acceptable Flood Capacity for Dams to the satisfaction of the New South Wales Dam Safety Committee. 2 Hazard Classification The Main Dam has a hazard classification of High A due to the population at risk downstream of the main embankment and the high value of the stored water. This classification is applicable to the implementation of Surveillance and Operation and Maintenance procedures. Subject to New South Wales Dam Safety Committee approval, where there are distinct embankments comprising the dam, each structure may be considered separately for dam design. Based on the reduced consequences of Saddle Dam and Subsidiary Dam failure, the hazard rating to be used for design of the slope protection works for the Saddle Dam and Subsidiary Dam was assessed to be between Significant and High A. The acceptable flood capacity for a Significant Hazard Category Dam is in the range from 1:1000 to 1:10,000 AEP flood but not less than at least half the PMF while the acceptable flood capacity for the High A Hazard category dam is the PMF. As shown in Table 1, the calculated 1:10,000 AEP event is about half the PMF and was used for the standards based approach to the design of the Grahamstown Subsidiary and Saddle Dam slope protection works. Flood Event ARI (years) Outlfow (m 3 /s) Max RL (m) , PMF Table 1 - Grahamstown Dam Floodrouting Data 3 Embankment Descriptions The Saddle Dam and Subsidiary Dam from chainage 0m to 650m are sand embankments with an upstream slope of about 8H on 1V and a downstream slope of 4H on 1V. The Saddle Dam has a vertical impervious clay core of approximately 6.1m wide while the Subsidiary Dam has a 1.5m wide bentonite sand cut-off. Rip rap slope protection on these embankment sections was generally placed at a slope of about 2H on 1V up to RL 12.8m with a thickness of 910mm and a d 50 of 460mm. The Subsidiary Dam between chainage 650m to about 2000m comprises sand embankments on natural ground (sand). The upstream slope varies from about 14H on 1V for the natural ground surface to 6H on 1V for the placed embankment. The section profile and slope protection varies along this section of the embankment for which there are no design details. Rip rap slope protection has been placed in areas of the embankment which have suffered beach erosion in the past as well as a 300m length of the embankment (Embankment section 5 of Figure 3) where rip rap slope protection of about 2m width has been placed

3 along the embankment. The embankment sections are grassed on the upstream side above the level of any rip rap to the crest of the embankment. During the Stage 1 construction, the core sections of all embankemnts were raised using a 300mm wide bentonite/clay section placed along the centre line of the core and extending up to the crest level at about RL 14.8m. the existing embankment. Gabions placed on the existing rip rap with underlying geotextile on the embankment sand material to prevent washing out of the sand. 4. Slope Protection Options The following options were considered for the riprap protection as shown in Figure 2. RipRap layer placed along slope of the embankment with underlying filter or geotextile filter fabric to prevent washing out of sand from the existing embankment. Rip Rap Berm with underlying geotextile filter fabric to prevent washing out of sand from the existing embankment. Rip Rap Berm alternative design using a rip rap zone supported on earthfill with underlying geotextile filter fabric to prevent washing out of sand from the existing embankment. Reno Mattress placed on the embankment slope and keyed into the existing rip rap with a gabion at the top level for anchoring the mattress and underlying geotextile filter fabric to prevent washing out of sand form Figure 2 - Slope Protection Options The Saddle Dam and Subsidiary Dam vary in section along the embankment and typical cross sections and embankment lengths were selected for the study, as shown on Figure 3. Figure 3 - Location of Cross Sections used for Slope Protection Analysis

4 5 Standards Based Evaluation The standards based or deterministic approach to the design and selection of the preferred slope protection option was carried out as follows: Wind Data Analysis The 10minute, 3 hourly interval wind speed data for the Williamtown RAAF Base, which is located approximately 5km south east of the dam was analysed for the period from 1942 and The 1year, 10year and 100 year ARI peak wind speeds were estimated for various directions perpendicular to the embankments using Normal, Log-normal and Log Pearson III statistical methods. An alternative method of estimating wind speeds was carried out using the Australian Wind Code AS The maximum hourly wind speed obtained from the statistical analysis and the Australian Wind Code as well as the USBR design wind speed of 30m/s were used for the wave estimation and rip-rap design. Estimation of Wave Height and Run up The wave height and wave run up data for each embankment was calculated using the procedure given in the ACER Technical Memorandum No using the following steps: Calculation of the effective fetch for each embankment section; The effective fetch for the embankments was calcuated to be in the order of 4.8km Adjust the overland wind speed to obtain overwater speeds; The correction factors determined by USBR (1981) were used to select a wind velocity ratio of 1.26 for the effective fetch. Calculate the wind set up; The wind setup is the rise in the water level at the leeward end of the fetch resulting from the shear force of the wind over the water. Calculate the significant wave height, wave length and wave period; The significant wave height Hs, represents the average wave height of the highest one-third of the waves present in each interval. If the water depth is greater than one half the wave length, the waves can be considered to be deep water waves. In the case of Grahamstown Dam, which is a relatively shallow reservoir, the water depth was marginally less than half the wave length but the difference in the deep and shallow water wave heights for the Grahamstown Dam was not significant. Calculate the wave run-up on the embankment slope. Wave runup, R, which is the vertical difference between the maximum level attained by the rush of water up the slope and the stillwater elevation was estimated using the ACER formula: R = Where: H S 05. HS *cot( θ) L R = Wave runup (m) Hs = Significant Wave height (m) L = Wave length (m) θ = Angle of the dam face from the horizontal ( ) The wind set up and wave run up were calculated for upstream slopes of 2H:1V, 6H:1V, 8H:1V and 10H:1V using the 1, 10 and 100 year ARI wind speeds for the dominant wind directions as well as the USBR recommended over water wind speed of 30 m/s. The results of the analyses for the Saddle Dam with the USBR and 100yr North Westerly wind and an 8H on 1V slope are shown in Table 2. Similar results were obtained for the Subsidiary Dam which indicated that for the 8H on 1V slope, the minimum slope protection level for the rip rap or reno-mattress options should be RL 14.5m.

5 Description Unit 100yr USBR Wind vel. over land m/s Wind vel. over water m/s Minimum duration hour Significant wave ht. m Wave run-up m Wind set up m Total Wet Freeboard m Minimum Rip Rap Level for 10,000 yr Flood RL13.73m m Table 2 - Wave Data for Saddle Dam using NW Wind and Upstream Slope 8H:1V The analysis with the 2H on 1V slope indicated that the wave set up and run up would be significantly higher than the flatter slopes and further analysis was performed to develop a reservoir level frequency curve for combined wind and flood events for the 2H on 1V and 8H on 1V embankment slopes using the following wind speeds derived from the statistical analysis of the wind data. Speed (m/s) Wind ARI (years) , The 1000 and 10,000 year wind speeds were derived from extrapolation of the available data and were only used for this frequency analysis. Figure 3 shows the frequency versus reservoir level curve for the 2H on 1 V slope. Exceedence Probability 1.E+00 1.E-01 1.E-02 1.E-03 1.E-04 1.E-05 1.E-06 1.E-07 1.E-08 Independent wind and wave Maximum Water Level (m) Dependent wind and wave Assumed design curve with transition from independent to dependent Flood Level Rip Rap Option Reno Mattress Option Berm Option Saddle Berm Option Alternative Gabion Option Figure 3 - Slope Protection Exceedence Curve for Embankment Slope 2H on 1V 4,000,000 3,500,000 3,000,000 2,500,000 2,000,000 1,500,000 1,000, ,000 Figure 3 - Frequency Reservoir Level Curve for a 2:1 Slope The reservoir level frequency data indicated that the minimum levels for the slope protection should be 14.3m for the reno-mattress and rip rap options and 15.2m for the berm and gabion option. However, as the analyses could not account for the combined berm and beach effect 0 Cost (AUD) up-slope of the berm, it was assessed that a minimum slope protection level of RL 14.9m would be required for the berm and gabion options. Slope Protection Design The approach recommended by US Corps of Engineers Shore Protection Manual (1984) was used for the design of the rip rap. Assuming a Rayleigh distribution for the waves, the design wave height was taken to be 1.27 times the significant wave height Hs. The significant wave height was calculated using a wind velocity over water of 30 m/s for the Subsidiary Dam and 33.0 m/s for the Saddle Dam as these were the highest wind speeds found from the wind analyses. The weight of the graded rock in the riprap was calculated using the formula: W 50 = Where: K γ γ * H r r D * 1 *cot( θ ) γ W 3 3 W 50 = weight of the 50% percent size in the riprap (kn) γ r = unit weight of the riprap rock (kn/m 3 ) γ w = unit weight of the water (kn/m 3 ) H = θ = design wave height (m) Angle of the dam face from the horizontal ( ) K D = stability coefficient (2.5 for angular quarried rock and non breaking waves) The maximum weight of graded riprap (W 100 ) was taken to be 4W 50 and the minimum 0.125W 50. These are equivalent to the maximum size of 1.5 times the D 50, and minimum size 0.5 times D 50. The equivalent sieve size of the riprap is approximately 1.15(W/γ r ) The rip rap requirements were determined for the existing upstream slope of the subsidiary dam and saddle dam which varies from 6H:1V to 10H:1V. As one of the alternatives for the slope protection is a berm placed as a continuation of the existing rip rap slope, the rip rap requirements were also determined for the

6 Saddle Dam using a slope of 2H on 1V. The rip rap sizes for the 2H:1V and 8H:1V slopes are presented in Table 3. The design of the bedding layer below the riprap was carried out with reference to US Corps of Engineers (1995) and Fell et al (1992). In the case of the reno-mattress design, a runup correction factor was applied to the values Option Cost ($M) RL 14.3m RL 14.9m Rip Rap Berm > Berm Reno Mattress 2.89 >3.04 Gabion Table 4 - Slope Protection Option Costs calculated for the rip rap using the following roughness reduction factors: R reno-mattress = 0.77 R riprap = 0.61 The ratio of these roughness factors of 1.26 was applied to the wave run up and set up to calculate the thickness of a Maccaferri Reno- Mattress. A geotextile fabric below the renomattress was selected to prevent erosion of the underlying material through the reno-mattress. The analyses indicated that a reno-mattress thickness of 170mm was required. Description Unit 2:1 8:1 Unit Weight of Riprap kn/m Wind vel. over water m/s Significant wave ht m Design wave ht m Max wt of riprap kn % Wt of riprap kn Min. weight of riprap kn Max. size of riprap m % size of riprap m Min. size of riprap m Table 3 - Saddle dam Riprap Design Cost Estimation and Option Selection The quantities and costs for each slope protection option were estimated using the calculated rip rap layer thicknesses and berm dimensions for each slope protection option as shown on Figure 3 and Table 4 for the levels of protection at RL 14.3 and 14.9m. The rip rap option and the reno-mattress option were significantly more costly than the berm and gabion options. While the gabion option was the lowest cost alternative for all levels of slope protection, the wave run-up characteristics and erosion potential differ from the flatter slopes applicable to the other options. There was also some concern over the long term durability of the gabions. The reno-mattress, berm and gabion options were used for the risk analysis to determine the required protection level and preferred option for each section of the embankments. 6 Risk Analysis Due to the sand construction of the embankments, it was possible to apply a wave erosion model SBEACH to determine the likelihood of embankment failure or damage resulting from beaching of the sand in unprotected or partly protected areas and to produce a risk model to evaluate the least cost option for the slope protection. Risk Analysis Methodology 1. The wind and rain data were evaluated to determine the likely wind pattern for the 1, 10 and 100 year events and the coincidence of the peak winds and rainfall events; 2. The SBEACH model was checked for sensitivity to the input parameters and calibrated using historical erosion of the embankments; 3. The erosion potential of the waves on each embankment section was determined for a selected number of combined wind and flood events to evaluate the likelihood of embankment breach and damage and estimate the cost of erosion repair works; 4. A risk model was developed to derive the failure and damage likelihoods for each flood and wind event likely to occur using the reno-mattress, berm and gabion options constructed to various levels; 5. Annual risk costs for failure and erosion damage of the saddle dam and subsidiary

7 dam sections were determined and the present value of the annual risk cost calculated and compared with the capital cost of slope protection works required to prevent erosion or damage of the embankments; 6. The present value for the maintenance, if carried out on a five yearly basis, was calculated and the equivalent annual maintenance cost determined for each option to assess the effect of the reduced costs on the decision regarding the least cost option; 7. The results were used to determine rip rap level required to minimise the risk cost of failure and repair/maintenance for each embankment section considering annual and five yearly maintenance programmes. Wind Data Analysis The half hourly wind data available from the Bureau of Meteorology, was plotted together with the three hourly data to review the wind patterns which indicated the following: the wind direction for the more extreme events is generally within a 30 arc; Wind direction for the more frequent events (1 year ARI) can be in any direction. The maximum wind speeds generally occurred with the wind direction from the west (270 ) to the north west (315 ); The peak wind is not sustained for more that 3 hours for the higher wind speed events (30m/s) for the wind speeds in the order of 20m/s, the wind can oscillate about this peak for an extended period, as observed in 1956 where the speed varied between 18m/s to 23m/s for about 48 hours. It was clear from the data that two distinct wind patterns could be generated, as shown on Reservoir Level (m) Time (hrs) Figure 6 - Flood Hydrographs for 1:200,000 AEP Flood with various Storm Durations Figures 4 and 5 which were assessed to be likely 10 and 100 year ARI events respectively. From discussions with the Bureau of Meteorology, it was established that during major rainfall events, the wind direction is generally from the south east while the maximum wind speeds can occur during or after the peak rainfall event. Wind Speed (m/s) Wind Speed (m/s) Time (hrs) 12h 24h 36h 48h 72h Composite Figure 4 - Composite Maximum Wind Event 1 in 10 yr ARI Composite Time (hrs) Figure 5 - Composite Maximum Wind Event 1 in 100 yr ARI It was conservatively assumed that the wind direction would be normal to the embankments. The wind peak was assumed to occur six hours

8 after the flood peak. A sensitivity analysis on the coincidence of wind and flood peaks indicated that the selected offset of the peaks was likely to be the worst case scenario, however, longer duration peaks could result in about an additional 10% erosion. The longer duration storm events have extended periods of relatively high reservoir levels as shown on Figure 6 for the 200,000 year flood event hydrographs. Flood Event Storm Duration (hrs) Peak RL Max. Erosion PMF 12 or or 24 1:200, :2, : Table 5 - Critical Storm Durations for Flood Level and Erosion Model The storm durations shown in Table 5 were relevant to the reservoir level and erosion potential of the embankment slope for which the maximum erosion storm duration hydrographs were used for the risk analysis. Erosion Model The wave erosion was evaluated using the US Army Corps of Engineers Waterways Experiment Station program Storm Induced Beach Change (SBEACH 32 Version 2.0). SBEACH is an empirically based numerical model for simulating two dimensional cross shore beach change. The model was initially formulated using data from prototype scale laboratory experiments and further developed and verified on field measurements and sensitivity testing. In calculating the beach profile change, the model assumes that the cross-shore sediment transport is produced by breaking waves and changes in water level. Wave transformation and sediment transport rates are calculated using random wave properties. The random wave generation assumes that the wave height follows a Raleigh distribution with adjustments made for use of the significant wave height and wave decay over either a monotonic or nonmonotonic profile. In the case of the nonmonotonic profile, a predictive equation is included in the model to determine the number of waves that reform along the negatively sloping sections of the slope i.e. upslope of the berm options used for Grahamstown Dam. The random wave model uses the conservation of wave energy to solve wave energy flux equations and compute the wave height decay across the surf zone where the waves are breaking on the embankment slope. Wave and wind induced water level setup are included in the calculation by solving a cross-shore momentum equation. Computations of random wave parameters are performed across the profile at each time step based on input wave and water level information and the wave parameters are used to calculate the sediment transport rates. Figure 7 - Description of Shore Profile The input for the model included the flood hydrograph, wind speed and direction,, significant wave height and period, embankment section and embankment material properties including: Effective grain size diameter; Avalanching angle which defines the steepest profile that can develop before avalanching of the beaching material occurs and was assumed to be 45 for the well compacted material which had evidence of near vertical erosion faces. A transport rate coefficient (K) which influences the rate at which transport occurs when the energy dissipation per unit volume is greater than the equilibrium energy dissipation per unit volume. Slope Dependent Transport term (ε) which influences the slope of the eroded profile. Higher values of this parameter result in profiles with gentler slopes and flatter bars

9 while lower values result in steeper near shore profiles and steeper bars. Depth of Foreshore Parameter DFS which defines the landward end of the surf zone in the model and affects the magnitude of transport in the swash zone. A higher value, corresponding to a greater depth at the boundary between the surf and swash zones, typically increases the transport rates in the swash zone producing more erosion at the foreshore. Erosion Model Sensitivity and Calibration Sensitivity analyses and model calibration were carried out on a section of the Subsidiary Dam using the annual wind with the reservoir at the FSL and a sand size of 0.35mm. The following parameters were used: Grid spacing 5m, 3m, 2m, 1m. The model was found to be particularly sensitive to the grid spacing for which a 1m spacing was required to correctly model the gabion and berm options. Larger grid spacing underestimated the erosion potential. Particle Size Sensitivity analysis was performed with particle sizes from 0.25mm to 0.35mm. The particle size of 0.25mm is consistent with wind blown material in the area while the 0.35mm was the average of the main embankment particle size. Transport Rate Coefficient The transport rate coefficient (K) was varied and finally selected to provide a reasonable depth of erosion. Slope Dependent Transport term (ε) The slope dependent transport term had a significant impact on the erosion potential and was reduced from the default value of 0.002m 2 /s to 0.001m 2 /s to improve the erosion prediction. Depth of Foreshore Parameter DFS Level (m) The erosion was found to be relatively insensitive to this parameter which was kept Figure 10 - Subsidiary Dam Section 1 Erosion Plot for FSL & Existing Slope Protection at the default value of 0.3m Erosion Analysis The wave erosion model was run for each of the representative embankment sections using the PMF; 200,000 year; 2,000 year; and 10 year ARI flood events and the FSL using the 100, 10 and 1 year ARI wind events. In the case of the FSL condition, the erosion was analysed using a 10,000year ARI wind event for each embankment to determine the likelihood of failure under this extreme event. A typical input hydrograph and wind speed data for the 200yr flood and the 10yr wind is shown on Figure 8. RL (m) Level (m) Original Profile 100 yr Wind (Sand 0.25mm) 100 yr Wind (Sand 0.3mm) 100 yr Wind (Sand 0.35mm) 10 yr Wind (Sand 0.25mm) 10 yr Wind (Sand 0.3mm) 10 yr Wind (Sand 0.35mm) 1 yr Wind (Sand 0.25mm) 1 yr Wind (Sand 0.3mm) 1 yr Wind (Sand 0.35mm) Original Profile 10,000 yr Wind (Sand 0.3mm) 100 yr Wind (Sand 0.25mm) 100 yr Wind (Sand 0.3mm) 100 yr Wind (Sand 0.35mm) 10 yr Wind (Sand 0.25mm) 10 yr Wind (Sand 0.3mm) 10 yr Wind (Sand 0.35mm) 1 yr Wind (Sand 0.25mm) 1 yr Wind (Sand 0.3mm) 1 yr Wind (Sand 0.35mm) Chainage (m) Time (hrs) Flood Level Wind Velocity over Water Figure yr Flood and 10 yr Wind Chainage (m) Figure 9 - Saddle Dam Erosion Plots for FSL & Existing Slope Protection Wind Velocity (m/s)

10 The models were run using the existing embankment configuration and at least two levels of slope protection for each option in order to provide data for the risk analysis and cost optimisation. Repair Costs ($) 16,000 14,000 12,000 10,000 8,000 6,000 Subsidiary Dam Section 1 - Repair Costs versus Flood Frequency Berm Slope Protection at RL 13.0m 100yr Wind 10yr Wind 1yr Wind and the cost for the repairs calculated using a rate for replacement of eroded sand. Repair cost versus frequency curves were developed for each embankment section and level of slope protection for all of the options. A typical plot is shown on Figure 12 for Section 1 of the Subsidiary Dam with the Berm protection option to RL 13.0m. Risk Model The following assumptions and limitations applied to the risk analysis. 1.E-06 1.E-05 1.E-04 1.E-03 1.E-02 1.E-01 1.E Flood Frequency 13 Figure 12 - Typical Plot of Repair Cost versus 12 Level (m) 4, , Frequency Original Profile 100yr Wind 10yr Wind 1yr Wind Chainage (m) Figure 11 - Subsidiary Dam Section 1 Erosion Plot for FSL & Berm Slope Protection Erosion Analysis Results Typical erosion plots are shown on Figures 9, 10 and 11 for the Full Supply Level conditions and the annual wind for the existing Saddle Dam and Section 1 of the Subsidiary Dam with and without the proposed slope protection in this embankment section. The models showed that the beach erosion forms relatively rapidly and then maintains a stable profile. The erosion of the embankment does not extend through the core zone below the FSL of RL12.8m, however, considerable damage occurs for a number of flood events. The erosion for the full supply level condition indicated that the erosion will progress about 5m to 10m into the face of the embankments to a depth of up to 1m. The volume of material eroded was calculated for each embankment using the level difference at each 1m grid point between the original profile and the eroded profile. A damage factor was used to account for the non uniformity of the erosion along the full length of each section The likelihood of coincident winds occurring with floods increases with flood magnitude to the point where at the PMF, the 100 year wind may be coincident with the peak flow ( Met. Bureau). The peak flood levels for the PMF event occur during the 12hr or 24hr storm event. The PMF event was also evaluated using a 72 hour storm duration. Peak winds occur at about 6hrs after the peak flood level. Sensitivity analysis to the occurrence of the wind was carried out. The annual wind speed occurrs continuously for 30% of the year. Only the critical storm durations for each flood have been used. The risk assessment applies only to the flood and wind events. Slope Protection PMF to 100, ,000 to 10,000 10,000 to 1,000 1,000 to to to 1 100yr Wind 10 yr Wind 1 yr Wind Damage No Damage Figure 13 - Part Event Tree Failure No Failure

11 The risk model combined the likelihood of the flood and wind events with the potential damage and failure probabilities assessed using the wave erosion results. A typical model, as shown in Figure 13 for the Saddle Dam existing slope protection, included the following event sequences occurring during a flood event. Flood and Wind The flood and wind combinations are shown on Table 6. Erosion Damage Embankment Failure Embankment OK The model was run for each embankment section with the slope protection levels appropriate to each option. Flood Event Interval (years) Wind ARI (years) 1 to 10 1, 10, to 100 1, 10, to , 10, 100 1,000 to 10,000 10, ,000 to 100, ,000 to PMF 100 Table 6 - Flood and Wind Event Combinations for Risk Analysis The total annual risk cost of damage or failure and the present value of each was calculated using a discount rate of 8% and lifetime of 100years. The present value maintenance risk cost was also determined using a 5 yearly interval for the annual risk cost and the equivalent annual series costs determined for this maintenance cost. Risk Analysis Results and Evaluation The risk analysis provided failure and damage risk costs and total risk cost for each flood and wind event range for present conditions. The results for each flood range are shown in Tables 7 for Section 1 of the Subsidiary Dam. The capital cost, annual and present value failure and maintenance costs for each slope protection option were obtained for the embankment sections. The results for the Section 1 of the Subsidiary Dam are shown on Table 8 and the data for the berm option of this embankment section is shown on Figure 14. Risk Cost ($) 180, , , , ,000 80,000 60,000 40,000 20,000 Failure and Maintenance Total PV Risk Cost Maintenance Annual Risk Cost Maintenance PV Risk Cost Capital + PV Maintenance Initial Capital Cost Slope Protection Level (m) 180, , , , ,000 80,000 60,000 40,000 20,000 Figure 14 - Risk Analysis Berm Option The results for this embankment are typical of the other embankments and showed the following: The majority of the damage risk cost with the existing conditions occurs with the more frequent annual flood events. The majority of the damage risk costs for the wind events occurs as a result of the annual wind event. This is due to the extended duration of the wind events and the high percentage damage expected from the annual wind; Increasing the slope protection level results in increased present value costs for Capital + PV Maintenace Risk Cost ($) Flood Event Range Failure Risk Cost Damage Risk Cost Total Risk Cost (years) Risk Cost ($) Percent of Total Risk Cost ($) Percent of Total Risk Cost ($) Percent of Total 10 to % 12, % 12, % 100 to % % % 1,000 to % % % 10,000 to 1, % % % 100,000 to 10, % 2 0.0% % PMF to 100, % 0 0.0% 8 0.1% Totals $ 1, % $ 12, % 13, % $ 13,979 Table 7 - Summary of Risk Costs for Subsidiary Dam Section 1 with Existing Conditions

12 maintenance and initial capital cost. As the beach erosion model indicated that the beaching is likely to be stable and not progress to failure, it was considered appropriate to extend the maintenance period to a 5 yearly interval which significantly reduced the total maintenance risk cost taken over a 50 year lifetime. As shown on Table 8, the capital and present value of the risk cost for the Subsidiary Dam Section 1 was reduced from $154,241 to $26,291. Of all of the embankment areas analysed, only Section 1 of the Subsidiary Dam could be shown to have similar capital costs for the slope protection option compared with ongoing maintenance of the do-nothing option. The results for the remainder of the embankments indicated that the present value of the reduced maintenance cost and capital cost was significantly higher than the maintenance costs for the do-nothing option. Based on the results of the risk analysis, the following recommendations were made for the Slope Protection works for the Grahamstown Saddle Dam and Subsidiary Dam: provide additional slope protection for the Section 1 of the Subsidiary Dam from the present level of RL 11.5m to RL 13.0m during the present Stage 2 augmentation works. The slope protection will be required over a length of about 100m of the embankment at a cost of about $35,000; apart from Section 1 of the Subsidiary Dam, provide no additional slope protection for the Saddle Dam or the Subsidiary Dam during the present Stage 2 augmentation works; perform maintenance and remedial works at five yearly intervals; monitor the embankments for signs of excessive erosion beyond that predicted by the erosion model. If this occurs, slope protection should be constructed using either the berm or gabion options to a level considered appropriate to the observed damage and as necessary to minimise the total risk cost; Plant water resistant grass between RL 10.4m and RL 12.8m along Section 2 of the Subsidiary Dam and between RL 11.5m Protection Level (m) Initial Capital Cost ($) Failure and Maintenance Cost Annual PV Risk Risk Cost Cost ($) ($) Annual Risk Cost Reno Mattress Maintenance Cost ($) PV PV Risk Annual Risk Cost - 5yr Maint. for Cost Interval 5yr Risk Cost Capital + PV Maint. ($) , ,011 12, ,241 26,291 2, , ,018 2,274 27, ,043 1, , , , , ,280 Berm , ,011 12, ,241 26,291 2, , ,523 1,666 20, , , , , ,510 Gabion (Risk Model Assumed to be the same as the Berm Option) , ,011 12, ,241 26,291 2, , ,000 1,666 20, , , , , ,687 Table 8 - Risk Analysis Results Subsidiary Dam Section 1

13 to 12.8m along Section 1 of the Subsidiary Dam; Where required, grass of the runner type should be planted above the existing rip rap or the water resistant grass up to the embankment crest level to bind the sand together and provide some resistance to wind and wave erosion. 7 Summary and Conclusions An economic risk model was developed for the Grahamstown Dam Saddle and Subsidiary embankment sections with various types and levels of slope protection. The costs for slope protection options were developed using slope protection levels based on a standards approach for slope protection. A risk management approach was then used to develop damage risk costs for each slope protection level and a present value analysis performed to provide cost curves of total cost versus slope protection level. The cost curves were finally used to determine the required slope protection measure and the level to which the protection was required for each of the representative embankment sections. The risk management approach clearly showed that a significant cost savings in the order of $1M could be achieved by using the risk management approach rather than the standards approach. Furthermore, the cost curves clearly showed the sections of the embankments for which present capital works would not be economically justified and for which ongoing maintenance works would be economically advantageous. References Risk View Palisade Corporation, Windows Version 1996 ANCOLD (2000) Guidelines on Selection of Acceptable Flood Capacity for Dams, March 2000 CEC (1993), Augmentation of Lake Grahamstown Report on Final Spillway Layout, Civil Engineering Consulting, February 1993 SBEACH (1996), SBEACH Numerical Model for Simulating Storm Induced Beach Change Report 4, US Army Corps of Engineers, Waterways Experiment Station, Technical Report CERC-89-9, April 1996 Decision Tools (1996), Decision Tools Suite Precision Tree, Top Rank, Best Fit and

COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION

COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION Abstract Lonie I * Tailings and Dams, GHD Brisbane, QLD, Australia Queensland Alumina Limited operates

More information

HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX D SBEACH MODELING

HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX D SBEACH MODELING HURRICANE SANDY LIMITED REEVALUATION REPORT UNION BEACH, NEW JERSEY DRAFT ENGINEERING APPENDIX SUB APPENDIX D SBEACH MODELING Rev. 18 Feb 2015 1 SBEACH Modeling 1.0 Introduction Following the methodology

More information

TABLE OF CONTENTS EXECUTIVE SUMMARY 1

TABLE OF CONTENTS EXECUTIVE SUMMARY 1 SLI Doc. No. 505573-3001-4HER-0001 00 12-Sept-2012 ii TABLE OF CONTENTS PAGE EXECUTIVE SUMMARY 1 1 INTRODUCTION... 3 2 OBJECTIVES... 5 3 WIND DATA... 6 3.1 Wind Rose... 7 4 SOCIÉTÉ D ÉNERGIE DE LA BAIE

More information

REVETMENTS. Purposes and Operational Constraints. Purposes Erosion control o o. Revetment Design 4/5/2016. CE A676 Coastal Engineering

REVETMENTS. Purposes and Operational Constraints. Purposes Erosion control o o. Revetment Design 4/5/2016. CE A676 Coastal Engineering REVETMENTS Ijsseldam, the Netherlands Orson P. Smith, PE, Ph.D. Instructor Purposes and Operational Constraints Purposes Erosion control o o Embankment Toe protection for a seawall, retaining wall or other

More information

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011 APPENDIX C VEGETATED EMERGENCY SPILLWAY VERSION 1.0 March 1, 2011 [NOTE: Could use a better photo more clearly showing the emergency spillway in the context of the dam.] SECTION C-1: DESCRIPTION OF PRACTICE

More information

Plan B Dam Breach Assessment

Plan B Dam Breach Assessment Plan B Dam Breach Assessment Introduction In support of the Local Sponsor permit applications to the states of Minnesota and North Dakota, a dam breach analysis for the Plan B alignment of the Fargo-Moorhead

More information

+)) Lower Churchill Project RIPRAP DESIGN FOR WIND-GENERATED WAVES SNC LAVALIN. SLI Document No HER

+)) Lower Churchill Project RIPRAP DESIGN FOR WIND-GENERATED WAVES SNC LAVALIN. SLI Document No HER +)) SNC LAVALIN Lower Churchill Project RIPRAP DESIGN FOR SLI Document No. 505573-3001-4HER-0011-00 Nalcor Reference No. MFA-SN-CD-0000-CV-RP-0006-01 Rev. 81 Date: 07 -Dec-2012 Prepared by: Checked by:

More information

Technical Brief - Wave Uprush Analysis Island Harbour Club, Gananoque, Ontario

Technical Brief - Wave Uprush Analysis Island Harbour Club, Gananoque, Ontario Technical Brief - Wave Uprush Analysis RIGGS ENGINEERING LTD. 1240 Commissioners Road West Suite 205 London, Ontario N6K 1C7 October 31, 2014 Table of Contents Section Page Table of Contents... i List

More information

Technical Brief - Wave Uprush Analysis 129 South Street, Gananoque

Technical Brief - Wave Uprush Analysis 129 South Street, Gananoque Technical Brief - Wave Uprush Analysis 129 South Street, Gananoque RIGGS ENGINEERING LTD. 1240 Commissioners Road West Suite 205 London, Ontario N6K 1C7 June 12, 2013 Table of Contents Section Page Table

More information

2. Water levels and wave conditions. 2.1 Introduction

2. Water levels and wave conditions. 2.1 Introduction 18 2. Water levels and wave conditions 2.1 Introduction This Overtopping Manual has a focus on the aspects of wave run-up and wave overtopping only. It is not a design manual, giving the whole design process

More information

MEMORANDUM. TNC Fisher Slough Final Design and Permitting Subject: DRAFT Technical Memorandum: Levee Emergency Spillway Design

MEMORANDUM. TNC Fisher Slough Final Design and Permitting Subject: DRAFT Technical Memorandum: Levee Emergency Spillway Design MEMORANUM TNC Fisher Slough Final esign and Permitting Subject: RAFT Technical Memorandum: Levee Emergency Spillway esign To: From: Internal Memorandum For Record Yen Hsu Chen (Tetra Tech) avid Cline (Tetra

More information

Beach Profiles. Topics. Module 9b Beach Profiles and Crossshore Sediment Transport 3/23/2016. CE A676 Coastal Engineering

Beach Profiles. Topics. Module 9b Beach Profiles and Crossshore Sediment Transport 3/23/2016. CE A676 Coastal Engineering Beach Profiles AND CROSS-SHORE TRANSPORT Orson P. Smith, PE, Ph.D., Professor Emeritus Topics Features of beach and nearshore profiles Equilibrium profiles Cross-shore transport References Text (Sorensen)

More information

CROSS-SHORE SEDIMENT PROCESSES

CROSS-SHORE SEDIMENT PROCESSES The University of the West Indies Organization of American States PROFESSIONAL DEVELOPMENT PROGRAMME: COASTAL INFRASTRUCTURE DESIGN, CONSTRUCTION AND MAINTENANCE A COURSE IN COASTAL DEFENSE SYSTEMS I CHAPTER

More information

Ermenek Dam and HEPP: Spillway Test & 3D Numeric-Hydraulic Analysis of Jet Collision

Ermenek Dam and HEPP: Spillway Test & 3D Numeric-Hydraulic Analysis of Jet Collision Ermenek Dam and HEPP: Spillway Test & 3D Numeric-Hydraulic Analysis of Jet Collision J.Linortner & R.Faber Pöyry Energy GmbH, Turkey-Austria E.Üzücek & T.Dinçergök General Directorate of State Hydraulic

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] Check Dams DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] Though not generally considered

More information

PRELIMINARY RISK ASSESSMENT RIDM PROJECT FOR A DAM WITH A VEGETATION- LINED SPILLWAY AND FERC PILOT

PRELIMINARY RISK ASSESSMENT RIDM PROJECT FOR A DAM WITH A VEGETATION- LINED SPILLWAY AND FERC PILOT PRELIMINARY RISK ASSESSMENT FOR A DAM WITH A VEGETATION- LINED SPILLWAY AND FERC PILOT RIDM PROJECT MAY 3, 2018 DAVID S. BOWLES AND LOREN R. ANDERSON RAC ENGINEERS AND ECONOMISTS, LLC AND UTAH STATE UNIVERSITY

More information

INTRODUCTION TO COASTAL ENGINEERING

INTRODUCTION TO COASTAL ENGINEERING The University of the West Indies Organization of American States PROFESSIONAL DEVELOPMENT PROGRAMME: COASTAL INFRASTRUCTURE DESIGN, CONSTRUCTION AND MAINTENANCE A COURSE IN COASTAL DEFENSE SYSTEMS I CHAPTER

More information

Appendix E Cat Island Borrow Area Analysis

Appendix E Cat Island Borrow Area Analysis Appendix E Cat Island Borrow Area Analysis ERDC/CHL Letter Report 1 Cat Island Borrow Area Analysis Multiple borrow area configurations were considered for Cat Island restoration. Borrow area CI1 is located

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Fly Ash Reservoir II Cardinal Plant Brilliant, Ohio October, 2016 Prepared for: Cardinal Operating Company Cardinal Plant Brilliant, Ohio Prepared by: Geotechnical

More information

Large-scale Field Test

Large-scale Field Test Vaskinn 1 Large-scale Field Test Kjetil Arne Vaskinn kav@trh.statkraftgroner.no Statkraft Grøner AS SUMMARY The objective the controlled failure of large-scale embankment is to monitor and record the failure

More information

IMPACTS OF COASTAL PROTECTION STRATEGIES ON THE COASTS OF CRETE: NUMERICAL EXPERIMENTS

IMPACTS OF COASTAL PROTECTION STRATEGIES ON THE COASTS OF CRETE: NUMERICAL EXPERIMENTS IMPACTS OF COASTAL PROTECTION STRATEGIES ON THE COASTS OF CRETE: NUMERICAL EXPERIMENTS Tsanis, I.K., Saied, U.M., Valavanis V. Department of Environmental Engineering, Technical University of Crete, Chania,

More information

Advanced Hydraulics Prof. Dr. Suresh A. Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati

Advanced Hydraulics Prof. Dr. Suresh A. Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati Advanced Hydraulics Prof. Dr. Suresh A. Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati Module - 4 Hydraulics Jumps Lecture - 4 Features of Hydraulic Jumps (Refer Slide

More information

INTRODUCTION TO COASTAL ENGINEERING AND MANAGEMENT

INTRODUCTION TO COASTAL ENGINEERING AND MANAGEMENT Advanced Series on Ocean Engineering Volume 16 INTRODUCTION TO COASTAL ENGINEERING AND MANAGEMENT J. William Kamphuis Queen's University, Canada World Scientific Singapore New Jersey London Hong Kong Contents

More information

Appendix M: Durras Lake Tailwater Conditions

Appendix M: Durras Lake Tailwater Conditions Appendix M: Durras Lake Tailwater Conditions M.1 Preamble WRL has completed a tailwater condition assessment for the entrance to Durras Lake, to be used as an ocean boundary condition for a future flood

More information

IMO REVISION OF THE INTACT STABILITY CODE. Proposal of methodology of direct assessment for stability under dead ship condition. Submitted by Japan

IMO REVISION OF THE INTACT STABILITY CODE. Proposal of methodology of direct assessment for stability under dead ship condition. Submitted by Japan INTERNATIONAL MARITIME ORGANIZATION E IMO SUB-COMMITTEE ON STABILITY AND LOAD LINES AND ON FISHING VESSELS SAFETY 49th session Agenda item 5 SLF 49/5/5 19 May 2006 Original: ENGLISH REVISION OF THE INTACT

More information

DESIGN OF BELL-MOUTH SPILLWAY AT BARVI DAM

DESIGN OF BELL-MOUTH SPILLWAY AT BARVI DAM DESIGN OF BELL-MOUTH SPILLWAY AT BARVI DAM Akshay Haldankar 1, Mahesh Bhadra 2, Rahul Harad 3, Darpan Kapre 4, Dipali Patil 5 1,2,3,4 Under graduate,dept. of Civil Engineering, DRIEMS Neral. 5Assistant

More information

ANSWERS TO QUESTIONS IN THE NOTES AUTUMN 2018

ANSWERS TO QUESTIONS IN THE NOTES AUTUMN 2018 ANSWERS TO QUESTIONS IN THE NOTES AUTUMN 2018 Section 1.2 Example. The discharge in a channel with bottom width 3 m is 12 m 3 s 1. If Manning s n is 0.013 m -1/3 s and the streamwise slope is 1 in 200,

More information

E. Agu, M. Kasperski Ruhr-University Bochum Department of Civil and Environmental Engineering Sciences

E. Agu, M. Kasperski Ruhr-University Bochum Department of Civil and Environmental Engineering Sciences EACWE 5 Florence, Italy 19 th 23 rd July 29 Flying Sphere image Museo Ideale L. Da Vinci Chasing gust fronts - wind measurements at the airport Munich, Germany E. Agu, M. Kasperski Ruhr-University Bochum

More information

A Preliminary Review of Beach Profile and Hardbottom Interactions

A Preliminary Review of Beach Profile and Hardbottom Interactions A Preliminary Review of Beach Profile and Hardbottom Interactions Douglas W. Mann, P.E., D.CE. CB&I A World of Solutions Presentation Goal Lead to a better understanding of the challenges regarding the

More information

Dam Modification Report Stingy Run Fly Ash Reservoir Appendix E Spillway System Design Calculations E1: Spillway/Energy Dissipater Design for 100-year Event CHE8273 8 September 4, 2014 Written by: CJW

More information

Steven A. Hughes. Ph.D., P.E. David R. Basco. Ph.D., P.E.

Steven A. Hughes. Ph.D., P.E. David R. Basco. Ph.D., P.E. Steven A. Hughes. Ph.D., P.E. Coastal and Hydraulics Laboratory US Army Engineer Research and Development Center David R. Basco. Ph.D., P.E. Coastal Engineering Center Old Dominion University Overview

More information

2016 NC Coastal Local Governments Annual Meeting

2016 NC Coastal Local Governments Annual Meeting 2016 NC Coastal Local Governments Annual Meeting Coastal Flood Study Modeling and Mapping 101 April 21, 2016 Tom Langan, PE, CFM Engineering Supervisor NCEM Floodplain Mapping Program FEMA Coastal Flood

More information

Discussion on the Selection of the Recommended Fish Passage Design Discharge

Discussion on the Selection of the Recommended Fish Passage Design Discharge Discussion on the Selection of the Recommended Fish Passage Design Discharge Introduction The provision of fish passage is a requirement for most proposed culvert and bridge installations in Alberta, depending

More information

Modeling Sediment Transport Along the Upper Texas Coast

Modeling Sediment Transport Along the Upper Texas Coast Modeling Sediment Transport Along the Upper Texas Coast David B. King Jr. Jeffery P. Waters William R. Curtis Highway 87 roadbed, Jefferson County Galveston District Corps Sabine Pass to San Luis Pass

More information

Rock Ramp Design Guidelines. David Mooney MS Chris Holmquist-Johnson MS Drew Baird Ph.D. P.E. Kent Collins P.E.

Rock Ramp Design Guidelines. David Mooney MS Chris Holmquist-Johnson MS Drew Baird Ph.D. P.E. Kent Collins P.E. Rock Ramp Design Guidelines David Mooney MS Chris Holmquist-Johnson MS Drew Baird Ph.D. P.E. Kent Collins P.E. Rock Ramp Design Guidelines OUTLINE Local and System Interactions with Rock Ramps Ramp Geometry

More information

Undertow - Zonation of Flow in Broken Wave Bores

Undertow - Zonation of Flow in Broken Wave Bores Nearshore Circulation Undertow and Rip Cells Undertow - Zonation of Flow in Broken Wave Bores In the wave breaking process, the landward transfer of water, associated with bore and surface roller decay

More information

CHAPTER 5: VACUUM TEST WITH VERTICAL DRAINS

CHAPTER 5: VACUUM TEST WITH VERTICAL DRAINS CHAPTER 5: VACUUM TEST WITH VERTICAL DRAINS 5.1 Introduction Using surcharging as the sole soil consolidation mean can take a long time to reach the desired soil settlement. Soil consolidation using prefabricated

More information

Aalborg Universitet. Published in: Proceedings of Offshore Wind 2007 Conference & Exhibition. Publication date: 2007

Aalborg Universitet. Published in: Proceedings of Offshore Wind 2007 Conference & Exhibition. Publication date: 2007 Aalborg Universitet Design Loads on Platforms on Offshore wind Turbine Foundations with Respect to Vertical Wave Run-up Damsgaard, Mathilde L.; Gravesen, Helge; Andersen, Thomas Lykke Published in: Proceedings

More information

THE WAVE CLIMATE IN THE BELGIAN COASTAL ZONE

THE WAVE CLIMATE IN THE BELGIAN COASTAL ZONE THE WAVE CLIMATE IN THE BELGIAN COASTAL ZONE Toon Verwaest, Flanders Hydraulics Research, toon.verwaest@mow.vlaanderen.be Sarah Doorme, IMDC, sarah.doorme@imdc.be Kristof Verelst, Flanders Hydraulics Research,

More information

Nearshore Morphodynamics. Bars and Nearshore Bathymetry. Sediment packages parallel to shore, that store beach sediment

Nearshore Morphodynamics. Bars and Nearshore Bathymetry. Sediment packages parallel to shore, that store beach sediment Nearshore Morphodynamics http://coastal.er.usgs.gov/bier/images/chandeleur-xbeach-lg.jpg Bars and Nearshore Bathymetry Sediment packages parallel to shore, that store beach sediment Can be up to 50 km

More information

HISTORY OF CONSTRUCTION

HISTORY OF CONSTRUCTION HISTORY OF CONSTRUCTION CFR 257.73(c)(1) West Boiler Slag Pond Clifty Creek Plant Madison, Indiana October, 2016 Prepared for: Indiana Kentucky Electric Corporation Prepared by: American Electric Power

More information

Chutes Part 2: Synthetic linings

Chutes Part 2: Synthetic linings s Part 2: Synthetic linings DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent [2] [1] s can

More information

Study of Passing Ship Effects along a Bank by Delft3D-FLOW and XBeach1

Study of Passing Ship Effects along a Bank by Delft3D-FLOW and XBeach1 Study of Passing Ship Effects along a Bank by Delft3D-FLOW and XBeach1 Minggui Zhou 1, Dano Roelvink 2,4, Henk Verheij 3,4 and Han Ligteringen 2,3 1 School of Naval Architecture, Ocean and Civil Engineering,

More information

Model Test Setup and Program for Experimental Estimation of Surface Loads of the SSG Kvitsøy Pilot Plant from Extreme Wave Conditions

Model Test Setup and Program for Experimental Estimation of Surface Loads of the SSG Kvitsøy Pilot Plant from Extreme Wave Conditions Model Test Setup and Program for Experimental Estimation of Surface Loads of the SSG Kvitsøy Pilot Plant from Extreme Wave Conditions according to Co-operation Agreement (phase 4) between WAVEenergy (Norway)

More information

Wind Regimes 1. 1 Wind Regimes

Wind Regimes 1. 1 Wind Regimes Wind Regimes 1 1 Wind Regimes The proper design of a wind turbine for a site requires an accurate characterization of the wind at the site where it will operate. This requires an understanding of the sources

More information

MODELING OF CLIMATE CHANGE IMPACTS ON COASTAL STRUCTURES - CONTRIBUTION TO THEIR RE-DESIGN

MODELING OF CLIMATE CHANGE IMPACTS ON COASTAL STRUCTURES - CONTRIBUTION TO THEIR RE-DESIGN Proceedings of the 14 th International Conference on Environmental Science and Technology Rhodes, Greece, 3-5 September 2015 MODELING OF CLIMATE CHANGE IMPACTS ON COASTAL STRUCTURES - CONTRIBUTION TO THEIR

More information

Summary of HEC 18, Evaluating Scour at Bridges FHWA NHI Should really follow HEC 18, but this summary will get you the main points.

Summary of HEC 18, Evaluating Scour at Bridges FHWA NHI Should really follow HEC 18, but this summary will get you the main points. Summary of HEC 18, Evaluating Scour at Bridges FHWA NHI 01-001 Should really follow HEC 18, but this summary will get you the main points. 1: Determine scour analysis variables 2: Analyze long-term bed

More information

Period of Record from No data was available from 1955 to 1962, but the remaining 57 years of data was available. 2

Period of Record from No data was available from 1955 to 1962, but the remaining 57 years of data was available. 2 TECHNICAL MEMORANDUM analyzed from the shared National Oceanic and Atmospheric Administration (NOAA) and Western Regional Climate Center (WCRR) weather station at the Stockton Metropolitan Airport 1. Prior

More information

MONITORING SEDIMENT TRANSPORT PROCESSES AT MANAVGAT RIVER MOUTH, ANTALYA TURKEY

MONITORING SEDIMENT TRANSPORT PROCESSES AT MANAVGAT RIVER MOUTH, ANTALYA TURKEY COPEDEC VI, 2003 in Colombo, Sri Lanka MONITORING SEDIMENT TRANSPORT PROCESSES AT MANAVGAT RIVER MOUTH, ANTALYA TURKEY Isikhan GULER 1, Aysen ERGIN 2, Ahmet Cevdet YALCINER 3 ABSTRACT Manavgat River, where

More information

HARBOUR SEDIMENTATION - COMPARISON WITH MODEL

HARBOUR SEDIMENTATION - COMPARISON WITH MODEL HARBOUR SEDIMENTATION - COMPARISON WITH MODEL ABSTRACT A mobile-bed model study of Pointe Sapin Harbour, in the Gulf of St. Lawrence, resulted in construction of a detached breakwater and sand trap to

More information

Currents measurements in the coast of Montevideo, Uruguay

Currents measurements in the coast of Montevideo, Uruguay Currents measurements in the coast of Montevideo, Uruguay M. Fossati, D. Bellón, E. Lorenzo & I. Piedra-Cueva Fluid Mechanics and Environmental Engineering Institute (IMFIA), School of Engineering, Research

More information

STABLE DYNAMIC BEACH MODELLING FRAMEWORK

STABLE DYNAMIC BEACH MODELLING FRAMEWORK GEOMORPHIC SOLUTIONS 141 Brunel Road Mississauga, ON L4Z 1X3 T 416 213 7121 F 95 89 8499 www.geomorphicsolutions.ca STABLE DYNAMIC BEACH MODELLING FRAMEWORK Geomorphic & Environmental Sciences Hazard Land

More information

Wind Analysis. Technical Memorandum. Wind Direction and Fetch Length. Water Depth

Wind Analysis. Technical Memorandum. Wind Direction and Fetch Length. Water Depth standardized to a 10m observation level and corrected for increased overwater wind speed. The CEM procedures for adjusting observed winds were used to correct for the elevation of the CIMIS weather station

More information

Reading Material. Inshore oceanography, Anikouchine and Sternberg The World Ocean, Prentice-Hall

Reading Material. Inshore oceanography, Anikouchine and Sternberg The World Ocean, Prentice-Hall Reading Material Inshore oceanography, Anikouchine and Sternberg The World Ocean, Prentice-Hall BEACH PROCESSES AND COASTAL ENVIRONMENTS COASTAL FEATURES Cross section Map view Terminology for Coastal

More information

BILLY BISHOP TORONTO CITY AIRPORT PRELIMINARY RUNWAY DESIGN COASTAL ENGINEERING STUDY

BILLY BISHOP TORONTO CITY AIRPORT PRELIMINARY RUNWAY DESIGN COASTAL ENGINEERING STUDY Bâtiment Infrastructures municipales Transport Industriel Énergie Environnement BILLY BISHOP TORONTO CITY AIRPORT PRELIMINARY RUNWAY DESIGN COASTAL ENGINEERING STUDY N. Guillemette 1, C. Glodowski 1, P.

More information

FEMA Region V. Great Lakes Coastal Flood Study. Pilot Study Webinar. Berrien County, Michigan. February 26, 2014

FEMA Region V. Great Lakes Coastal Flood Study. Pilot Study Webinar. Berrien County, Michigan. February 26, 2014 FEMA Region V Great Lakes Coastal Flood Study Pilot Study Webinar Berrien County, Michigan February 26, 2014 2 Pilot Study Webinar Agenda Great Lakes Coastal Flood Study Background Demonstration Project

More information

Evaluating Surge Potential in CSO Tunnels

Evaluating Surge Potential in CSO Tunnels 14 Evaluating Surge Potential in CSO Tunnels Karen E. Ridgway Tunnels are being proposed to control combined sewer overflow (CSO) in numerous cities in the United States and Canada. The tunnels are intended

More information

Volume and Shoreline Changes along Pinellas County Beaches during Tropical Storm Debby

Volume and Shoreline Changes along Pinellas County Beaches during Tropical Storm Debby Volume and Shoreline Changes along Pinellas County Beaches during Tropical Storm Debby Ping Wang and Tiffany M. Roberts Coastal Research Laboratory University of South Florida July 24, 2012 Introduction

More information

Annex E Bridge Pier Protection Plan

Annex E Bridge Pier Protection Plan Annex E Bridge Pier Protection Plan Table E1 Bridge Types and Locations Table E2 Flow Conditions For River Sections Figure E1 Bridge Abutment Protection Figure E2 Bridge Pier Protection Figure E3 Central

More information

OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 11 APPENDIX B TIDEROUT 2 USERS MANUAL

OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 11 APPENDIX B TIDEROUT 2 USERS MANUAL OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 11 APPENDIX B TIDEROUT 2 USERS MANUAL APRIL 2011 APRIL 2011 Page 1 Preface TIDEROUT 2, Build 1.22 dated June 29, 2006 is the current

More information

Yasuyuki Hirose 1. Abstract

Yasuyuki Hirose 1. Abstract Study on Tsunami force for PC box girder Yasuyuki Hirose 1 Abstract In this study, a waterway experiment was performed in order to understand the influence of tsunami forms on tsunami forces acting on

More information

Undertow - Zonation of Flow in Broken Wave Bores

Undertow - Zonation of Flow in Broken Wave Bores Lecture 22 Nearshore Circulation Undertow - Zonation of Flow in Broken Wave Bores In the wave breaking process, the landward transfer of water, associated with bore and surface roller decay within the

More information

Greenup Lock Filling and Emptying System Study

Greenup Lock Filling and Emptying System Study Fourth LACCEI International Latin American and Caribbean Conference for Engineering and Technology (LACCET 2006) Breaking Frontiers and Barriers in Engineering: Education, Research and Practice 21-23 June

More information

SELECTION OF THE PREFERRED MANAGEMENT OPTION FOR STOCKTON BEACH APPLICATION OF 2D COASTAL PROCESSES MODELLING

SELECTION OF THE PREFERRED MANAGEMENT OPTION FOR STOCKTON BEACH APPLICATION OF 2D COASTAL PROCESSES MODELLING SELECTION OF THE PREFERRED MANAGEMENT OPTION FOR STOCKTON BEACH APPLICATION OF 2D COASTAL PROCESSES MODELLING C Allery 1 1 DHI Water and Environment, Sydney, NSW Abstract This paper presents an approach

More information

Bob Battalio, PE Chief Engineer, ESA September 8, 2016

Bob Battalio, PE Chief Engineer, ESA September 8, 2016 RELATING FUTURE COASTAL CONDITIONS TO EXISTING FEMA FLOOD HAZARD MAPS Technical Methods Manual Bob Battalio, PE Chief Engineer, ESA September 8, 2016 FMA 2016 Sacramento, California DWR-OST-SIO PILOTING

More information

The History of Coastal Flood Hazard Assessments in the Great Lakes

The History of Coastal Flood Hazard Assessments in the Great Lakes The History of Coastal Flood Hazard Assessments in the Great Lakes Brian A. Caufield, P.E., CFM June 23, 2016 2 The Great Lakes Some Statistics Courtesy of Great Lakes Information Network One-fifth of

More information

Appendix D: SWAN Wave Modelling

Appendix D: SWAN Wave Modelling Appendix D: SWAN Wave Modelling D.1 Preamble The Eurobodalla Shire Council area is subject to extreme waves originating from offshore storms. When swell waves approach the coast, they are modified by the

More information

SACO RIVER AND CAMP ELLIS BEACH SACO, MAINE SECTION 111 SHORE DAMAGE MITIGATION PROJECT APPENDIX F ECONOMIC ASSESSMENT

SACO RIVER AND CAMP ELLIS BEACH SACO, MAINE SECTION 111 SHORE DAMAGE MITIGATION PROJECT APPENDIX F ECONOMIC ASSESSMENT SACO RIVER AND CAMP ELLIS BEACH SACO, MAINE SECTION 111 SHORE DAMAGE MITIGATION PROJECT APPENDIX F ECONOMIC ASSESSMENT Department of the Army New England District, Corps of Engineers 696 Virginia Road

More information

BEACH NOURISHMENT COMBINED WITH SIC VERTICAL DRAIN IN MALAYSIA. Claus Brøgger 1 and Poul Jakobsen 2

BEACH NOURISHMENT COMBINED WITH SIC VERTICAL DRAIN IN MALAYSIA. Claus Brøgger 1 and Poul Jakobsen 2 BEACH NOURISHMENT COMBINED WITH SIC VERTICAL DRAIN IN MALAYSIA. Claus Brøgger 1 and Poul Jakobsen 2 The present paper presents measurements and results from a three year full scale Pilot Project with the

More information

MESSOLOGI LAGOON AREA (GREECE)

MESSOLOGI LAGOON AREA (GREECE) MESSOLOGI LAGOON AREA (GREECE) 20 Contact: Kyriakos SPYROPOULOS TRITON Consulting Engineers 90 Pratinou Str. 11634 Athens (GREECE) Tel: +32 10 729 57 61 Fax: +32 10 724 33 58 e-mail: kspyropoulos@tritonsa.gr

More information

CHAPTER 68. RANDOM BREAKING WAVES HORIZONTAL SEABED 2 HANS PETER RIEDEl. & ANTHONY PAUL BYRNE

CHAPTER 68. RANDOM BREAKING WAVES HORIZONTAL SEABED 2 HANS PETER RIEDEl. & ANTHONY PAUL BYRNE CHAPTER 68 RANDOM BREAKING WAVES HORIZONTAL SEABED 2 HANS PETER RIEDEl. & ANTHONY PAUL BYRNE ABSTRACT According to wave theories the depth limited wave height over a horizontal seabed has a wave height

More information

Wave Assessment on Loch Ericht

Wave Assessment on Loch Ericht Wave Assessment on Loch Ericht DEBBIE HAY-SMITH, JBA Consulting, previously FaberMaunsell RICHARD DOAKE, FaberMaunsell WILLIAM ALLSOP, H R Wallingford KIRSTY McCONNELL, H R Wallingford SYNOPSIS. This paper

More information

Effects of directionality on wind load and response predictions

Effects of directionality on wind load and response predictions Effects of directionality on wind load and response predictions Seifu A. Bekele 1), John D. Holmes 2) 1) Global Wind Technology Services, 205B, 434 St Kilda Road, Melbourne, Victoria 3004, Australia, seifu@gwts.com.au

More information

STUDY ON TSUNAMI PROPAGATION INTO RIVERS

STUDY ON TSUNAMI PROPAGATION INTO RIVERS ABSTRACT STUDY ON TSUNAMI PROPAGATION INTO RIVERS Min Roh 1, Xuan Tinh Nguyen 2, Hitoshi Tanaka 3 When tsunami wave propagation from the narrow river mouth, water surface is raised and fluctuated by long

More information

Notice of Intent to Close Inactive CCR Surface Impoundments

Notice of Intent to Close Inactive CCR Surface Impoundments Notice of Intent to Close Inactive CCR Surface Impoundments Virginia Electric and Power Company Possum Point Power Station Coal Combustion Residual Surface Impoundments A, B, C, D, and E Dumfries, Virginia

More information

Exemplar for Internal Assessment Resource Geography Level 3. Resource title: The Coastal Environment Kaikoura

Exemplar for Internal Assessment Resource Geography Level 3. Resource title: The Coastal Environment Kaikoura Exemplar for internal assessment resource Geography 3.5A for Achievement Standard 91430 Exemplar for Internal Assessment Resource Geography Level 3 Resource title: The Coastal Environment Kaikoura This

More information

Advanced Hydraulics Prof. Dr. Suresh A. Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati

Advanced Hydraulics Prof. Dr. Suresh A. Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati Advanced Hydraulics Prof. Dr. Suresh A. Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati Module - 4 Hydraulic Jumps Lecture - 1 Rapidly Varied Flow- Introduction Welcome

More information

Concepts & Phenomena

Concepts & Phenomena Concepts & Phenomena in coastal and port sedimentation R. Kamalian Ports and Maritime Organization of Iran and PIANC-Iran 7 9 December 2015 What is the problem? Many harbours have sedimentation problems

More information

APPENDIX J HYDROLOGY AND WATER QUALITY

APPENDIX J HYDROLOGY AND WATER QUALITY APPENDIX J HYDROLOGY AND WATER QUALITY J-1 Technical Report on Airport Drainage, Northern Sector Airport and Ordinance Creek Watershed / Preliminary Creek Constructed Natural Channel Culvert J-2 Preliminary

More information

Sediment Basin 7E-12. Design Manual Chapter 7 - Erosion and Sediment Control 7E - Design Information for ESC Measures BENEFITS.

Sediment Basin 7E-12. Design Manual Chapter 7 - Erosion and Sediment Control 7E - Design Information for ESC Measures BENEFITS. 7E-12 Design Manual Chapter 7 - Erosion and Sediment Control 7E - Design Information for ESC Measures Sediment Basin BENEFITS Flow Control Erosion Control Sediment Control Runoff Reduction Flow Diversion

More information

ST LEONARDS COASTAL HAZARD VULNERABILITY ASSESSMENT

ST LEONARDS COASTAL HAZARD VULNERABILITY ASSESSMENT Level 12, 333 Collins Street Melbourne VIC 3000 Australia Telephone: +61 3 8676 3500 Facsimile: +61 3 8676 3505 www.worleyparsons.com WorleyParsons Services Pty Ltd ABN 61 001 279 812 23 November 2011

More information

Note: Design of beach-dune system for coastal protection Date: 24 August 2018 DESIGN OF BEACH-DUNE SYSTEM FOR COASTAL PROTECTION.

Note: Design of beach-dune system for coastal protection Date: 24 August 2018 DESIGN OF BEACH-DUNE SYSTEM FOR COASTAL PROTECTION. DESIGN OF BEACH-DUNE SYSTEM FOR COASTAL PROTECTION Content 1. Introduction 2. Hydrodynamic conditions 3. Beach and dune characteristics 4. Design of cross-shore beach-dune profile 4.1 Definition of erosion

More information

Design Assessment Checklist: Infiltration / Detention Basin

Design Assessment Checklist: Infiltration / Detention Basin Design Assessment Checklist: Infiltration / Detention Basin Objectives This checklist can be used by the organisation approving the drainage scheme (drainage approving body) to help assess submissions

More information

Design and Installation of two Permanent Booms at La Romaine-2 to resist Ice, retain Debris and serve as Safety Booms.

Design and Installation of two Permanent Booms at La Romaine-2 to resist Ice, retain Debris and serve as Safety Booms. CGU HS Committee on River Ice Processes and the Environment 18 th Workshop on the Hydraulics of Ice Covered Rivers Quebec City, QC, Canada, August 18-20, 2015 Design and Installation of two Permanent Booms

More information

COASTAL ENVIRONMENTS. 454 lecture 12

COASTAL ENVIRONMENTS. 454 lecture 12 COASTAL ENVIRONMENTS Repeated movement of sediment & water constructs a beach profile reflecting the balance between average daily or seasonal wave forces and resistance of landmass to wave action Coasts

More information

Nearshore Placed Mound Physical Model Experiment

Nearshore Placed Mound Physical Model Experiment Nearshore Placed Mound Physical Model Experiment PURPOSE: This technical note describes the migration and dispersion of a nearshore mound subjected to waves in a physical model. The summary includes recommendations

More information

CHAPTER 132. Roundhead Stability of Berm Breakwaters

CHAPTER 132. Roundhead Stability of Berm Breakwaters CHAPTER 132 Roundhead Stability of Berm Breakwaters Jergen Juhl 1, Amir Alikham, Peter Sloth, Renata Archetti Abstract Three-dimensional (3D) model tests were carried out for studying the stability of

More information

Technical Report Culvert A Hydraulic Analysis

Technical Report Culvert A Hydraulic Analysis DATE: November 3, 2011 Technical Report Culvert A Hydraulic Analysis TO: FROM: RE: Jim Reiser, P.E. Project Manager Parsons Brinckerhoff, Inc. Kurt Killian, P.E., CFM Parsons Brinckerhoff, Inc. Design

More information

Culvert Design for Low and High Gradient Streams in the Midwest. Dale Higgins, Hydrologist Chequamegon-Nicolet National Forest

Culvert Design for Low and High Gradient Streams in the Midwest. Dale Higgins, Hydrologist Chequamegon-Nicolet National Forest Culvert Design for Low and High Gradient Streams in the Midwest Dale Higgins, Hydrologist Chequamegon-Nicolet National Forest Overview Culvert Design Considerations Hydraulic Terms Culvert Impacts Low

More information

Longshore sediment transport

Longshore sediment transport and Orson P. Smith, PE, Ph.D., Professor Emeritus Longshore transport Waves breaking at an angle to shore Sediment under breakers lifted by saltation Drops back to sea bed a little down drift Swash (runup)

More information

Shorelines Earth - Chapter 20 Stan Hatfield Southwestern Illinois College

Shorelines Earth - Chapter 20 Stan Hatfield Southwestern Illinois College Shorelines Earth - Chapter 20 Stan Hatfield Southwestern Illinois College The Shoreline A Dynamic Interface The shoreline is a dynamic interface (common boundary) among air, land, and the ocean. The shoreline

More information

EXAMPLES (OPEN-CHANNEL FLOW) AUTUMN 2018

EXAMPLES (OPEN-CHANNEL FLOW) AUTUMN 2018 EXAMPLES (OPEN-CHANNEL FLOW) AUTUMN 2018 Normal and Critical Depths Q1. If the discharge in a channel of width 5 m is 20 m 3 s 1 and Manning s n is 0.02 m 1/3 s, find: (a) the normal depth and Froude number

More information

USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY. Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1

USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY. Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1 USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1 Plum Creek Floodwater Retarding Structure No. 6 is located in an area of Kyle, Texas, that is currently

More information

CHAPTER 163 PREDICTION OF BEACH PROFILE CHANGE AT MESOSCALE UNDER RANDOM WAVES. Magnus Larson 1

CHAPTER 163 PREDICTION OF BEACH PROFILE CHANGE AT MESOSCALE UNDER RANDOM WAVES. Magnus Larson 1 CHAPTER 163 PREDICTION OF BEACH PROFILE CHANGE AT MESOSCALE UNDER RANDOM WAVES Magnus Larson 1 ABSTRACT: A mesoscale model is presented to calculate the average net crossshore transport rate and beach

More information

PHYSICAL AND NUMERICAL MODELLING OF WAVE FIELD IN FRONT OF THE CONTAINER TERMINAL PEAR - PORT OF RIJEKA (ADRIATIC SEA)

PHYSICAL AND NUMERICAL MODELLING OF WAVE FIELD IN FRONT OF THE CONTAINER TERMINAL PEAR - PORT OF RIJEKA (ADRIATIC SEA) PHYSICAL AND NUMERICAL MODELLING OF WAVE FIELD IN FRONT OF THE CONTAINER TERMINAL PEAR - PORT OF RIJEKA (ADRIATIC SEA) DALIBOR CAREVIĆ (1), GORAN LONČAR (1), VLADIMIR ANDROČEC (1) & MARIN PALADIN (1) 1.

More information

DESIGN OF SCOUR PROTECTION FOR THE BRIDGE PIERS OF THE 0RESUND LINK

DESIGN OF SCOUR PROTECTION FOR THE BRIDGE PIERS OF THE 0RESUND LINK DESIGN OF SCOUR PROTECTION FOR THE BRIDGE PIERS OF THE 0RESUND LINK Lars Kirkegaard 1, Mogens Hebsgaard 2 and Ole Juul Jensen 3 Abstract The 0resund Link between Denmark and Sweden consists of a cable

More information

ValidatingWindProfileEquationsduringTropicalStormDebbyin2012

ValidatingWindProfileEquationsduringTropicalStormDebbyin2012 Global Journal of Researches in Engineering: e Civil And Structural Engineering Volume 4 Issue Version. Year 24 Type: Double Blind Peer Reviewed International Research Journal Publisher: Global Journals

More information

A Review of the Bed Roughness Variable in MIKE 21 FLOW MODEL FM, Hydrodynamic (HD) and Sediment Transport (ST) modules

A Review of the Bed Roughness Variable in MIKE 21 FLOW MODEL FM, Hydrodynamic (HD) and Sediment Transport (ST) modules A Review of the Bed Roughness Variable in MIKE 1 FLOW MODEL FM, Hydrodynamic (HD) and Sediment Transport (ST) modules by David Lambkin, University of Southampton, UK 1 Bed roughness is considered a primary

More information

Evaluation of June 9, 2014 Federal Emergency Management Agency Flood Insurance Study for Town of Weymouth, Norfolk, Co, MA

Evaluation of June 9, 2014 Federal Emergency Management Agency Flood Insurance Study for Town of Weymouth, Norfolk, Co, MA Evaluation of June 9, 2014 Federal Emergency Management Agency Flood Insurance Study for Town of Weymouth, Norfolk, Co, MA Prepared For: Woodard & Curran 95 Cedar Street, Suite 100 Providence, RI 02903

More information

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay 43 Module 3: Lecture - 5 on Compressibility and Consolidation Contents Stresses in soil from surface loads; Terzaghi s 1-D consolidation theory; Application in different boundary conditions; Ramp loading;

More information