OVERHEAD DESIGN MANUAL

Size: px
Start display at page:

Download "OVERHEAD DESIGN MANUAL"

Transcription

1 OVERHED DESIGN MNUL Section 2 Poles pproved by: F. Zaini ENERGEX 2015 MNUL 00302

2

3

4

5

6

7

8 Length (m) POLE DESCRIPTION MINIMUM POLE DIMETERS (mm) MX. DIMETER at GL Nominal GL Strength Rating (kn) Strength Group Strength Group Strength Group Distance from Butt (mm) (Note 1) S1 S2 S3 S1 S2 S3 Ultimate Limit State Max. Working 2m from butt t head 2m from butt t head 2m from butt t head N/ N/ N/ N/ F. ZINI REC D 20/10/2015 Note 1: llowable pole tip load under Limit State & Maximum Working Wind Conditions Note 2: Data taken from Technical Specification TS415C Vacuum Pressure Impregnated Hardwood Poles POLES WOOD POLES - CURRENT TYPE MINIMUM & MXIMUM DIMETERS ORIGINL ISSUE COPYRIGHT 2015 Energex This drawing must not be reproduced in part or whole without written permission from ENERGEX P.RELF K.GOSDEN WORD SEC SUB 2 3 SHT 4 REV

9

10

11

12

13 TIP LOD CPCITY OF NILED POLES WIND CONDITION (kn) Rebutted Poles can be assumed to be reinstated to their full original strength. Nailed or Staked Poles are often reinstated to less than their original strength, but adequate to carry the applied tip load at the time of reinstatement. Nails are currently stamped with the Ultimate Bending Moment Capacity of the pole and the year of installation. (Older nails may not be stamped in this way refer section 2.7. Use the tables below to determine Tip Load Capacity of the reinstated pole. Note: Even if the nail is of a large capacity, the tip load of the reinstated pole must NOT exceed the original tip load of the pole. Poles where the Nail is ligned with the Resultant Conductor Load Nail Resultant ULTIMTE BENDING MOMENT CPCITY OF NIL POLE LENGTH (m) Maximum Tip Load Wind Condition (kn) The above table assumes a ground line pole diameter equivalent to 3% of pole length. Sinking Depth is taken to be 0.1 x Pole Length + 0.8m. ORIGINL ISSUE REC D COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX F. ZINI 20/10/2015 P. RELF K. GOSDEN SECT SUB SHT REV WORD POLES REINSTTED (NILED) WOOD POLES CURRENT TYPES

14 Poles where the Nail is NOT ligned with the Resultant Conductor Loads Nail Resultant ULTIMTE BENDING MOMENT CPCITY OF NIL POLE LENGTH (m) Maximum Tip Load Wind Condition (kn) The above table assumes a ground line pole diameter equivalent to 3% of pole length. Sinking Depth is taken to be 0.1 x Pole Length + 0.8m. ORIGINL ISSUE REC D COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX F. ZINI 20/10/2015 P. RELF K. GOSDEN SECT SUB SHT REV WORD POLES REINSTTED (NILED) WOOD POLES CURRENT TYPES

15

16 BENDING MOMENT CPCITY OF WOOD POLES NOTES: 1. ll Bending Moment values are in kn.m. 2. Dia (mm) is typically ground line diameter but may be applied to any part of the pole. 3. The following Modulus of Rupture values have been used in accordance with S S1: 100Pa, S2: 80MPa, S3: 65MPa. 4. To convert from Bending Moment to Tip Load Capacity in kilo-newtons, divide by height in metres. For wind condition, de-rate by self-windage of pole: i.e. height (m) x width (m) x 1.3 x To obtain Energex allowable No Wind bending moments, multiply the No Wind value by Refer section 2-12 for more information. Diameter (mm) Ult S1 S2 S3 No Wind (5) Wind Ult No Wind (5) Wind Ult No Wind (5) Wind REC D F. ZINI 20/10/2015 POLES BENDING MOMENT CPCITY OF TIMBER POLES ORIGINL ISSUE COPYRIGHT 2015 Energex This drawing must not be reproduced in part or whole without written permission from ENERGEX P. RELF K.GOSDEN WORD SEC SUB 2 8 SHT 1 REV

17 NOTES: 1. ll Bending Moment values are in kn.m. 2. Dia (mm) is typically ground line diameter but may be applied to any part of the pole. 3. The following Modulus of Rupture values have been used in accordance with S S1: 100Pa, S2: 80MPa, S3: 65MPa. 4. To convert from Bending Moment to Tip Load Capacity in kilo-newtons, divide by height in metres. For wind condition, de-rate by self-windage of pole: i.e. height (m) x width (m) x 1.3 x To obtain Energex allowable No Wind bending moments, multiply the No Wind value by Refer section 2-12 for more information. Diameter (mm) Ult S1 S2 S3 No Wind (5) Wind Ult No Wind (5) Wind Ult No Wind (5) Wind REC D F. ZINI 20/10/2015 POLES BENDING MOMENT CPCITY OF TIMBER POLES ORIGINL ISSUE COPYRIGHT 2015 Energex This drawing must not be reproduced in part or whole without written permission from ENERGEX P. RELF K.GOSDEN WORD SEC SUB 2 8 SHT 2 REV

18 1. POLE INSPECTION FOR IN-SERVICE POLES Whenever the tip load of an in-service pole is increased by more than 1kN (No Wind condition), an assessment of the residual strength of the pole is required. Poles that are less than 10 years old, or that have been reinstated (ie nailed or rebutted) within the last 10 years, shall be exempt from this procedure. The designer shall complete Section 1 of Form 1271 Pole Inspection for ltered Tip Loads supplying the pole site ID and address. This should be forwarded to the Network Maintenance Contract Department. The Contract Officer shall arrange for a pole inspector under the current contract to inspect the pole and obtain the necessary field measurements for wood poles ground line diameter, height and dimensions of any internal hollows completing Section 2 of the form. The form is returned to the designer. For wood poles, the designer should then calculate a revised pole tip load rating using the measurements provided and the PoleStrength program within the mains design application package. Only the Limit State (LST) and Everyday (EDT) values are to be used to determine the remaining design strength of the pole. This strength is to be compared with the proposed LST tip load to determine the suitability of the existing pole. External designers have the option of liaising directly with a rated Pole Inspector to obtain the required measurements. For wood poles without any internal hollows, the table in Section 2.8 Bending Moment Capacity Of Timber Poles may be used in lieu of the PoleStrength program. Ensure any external decay is taken into account when determining diameter of pole For reinstated poles that are assessed as sound by the pole inspector, the designer shall compare the strength of the reinforcing system with the proposed tip load (refer Page 2-6 and Maintenance Instruction MI-069). 2. POLE PEGGING Poles and stays shall be pegged at the centre of the proposed position. Only ORNGE fluorescent paint (Stock Code 14010) will be used for temporary marking of pole and stay positions and pegs. Refer S 1345 for temporary marking of electrical services in road reserves Check for services clashes DBYD (phone 1100, fax ). 3. POLE LIGNMENTS Poles located within road reserves shall be installed on an alignment approved by the authority controlling the roadway generally the Department of Transport and Main roads or the local authority (council). Standard pole alignments for authorities within the ENERGEX franchise area are tabulated below. Note that certain authorities reference the alignment to the real property boundary, others behind the face of the kerb (BFK) or behind the kerb invert (BKI). Note that local authorities may have additional restrictions on pole placement, eg clearances from walking paths and bike paths. Restrictions concerning streetlight pole placement are also found in S/NZS Road Lighting. s a general guideline, ensure that there is at least 0.7m between the outside of the pole and the kerb to minimise damage from vehicle ORIGINL ISSUE COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX REC D F. ZINI 20/10/2015 P. RELF K. GOSDEN WORD POLES POLE INSPECTION FOR IN-SERVICE POLES & POLE LIGNMENTS SEC SUB 2 9 SHT 1 REV

19 4. STNDRD POLE ND UNDERGROUND LIGNMENTS LOCL UTHORITY POLE LIGNMENT U/G LIGNMENT SITUTION DRWING REF. COMMENTS NORTH SUNSHINE COST REGIONL COUNCIL Formerly: 0-0.9m from RP lign SEQ STD Electrical 3.0m centre from RP lign For all footpath widths Caloundra City Council (with Gas) conditions pdf Formerly: Maroochydore City Council 3.0m centre from RP lign 0-0.9m from RP lign For all footpath widths Formerly: Noosa Shire Council 3.0m centre from RP lign 0-0.9m from RP lign For all footpath widths GYMPIE REGIONL COUNCIL Council considering pole Formerly: m from RP alignment 1.0m behind 3.0m centre from RP lign R-08 Cooloola Shire Council lign kerb for footpaths exceeding 4.0m wide MORETON BY REGIONL COUNCIL Formerly: 0-1.0m from RP lign 3.2m centre from RP lign Caboolture Shire Council (with Gas) 4/01-64 Formerly: For standard footpath 4.0m 3.3m centre from RP lign 0-0.9m from RP lign Redcliffe City Council wide S m centre from RP lign 0-0.9m from RP lign For footpaths 3.5m wide Formerly: Pine Rivers Shire Council 0.45m from face of kerb 0-0.9m from RP lign 2.75m centre from RP lign For footpaths exceeding 3.5m wide For footpaths without kerbing Unnumbered sketch ORIGINL ISSUE COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX REC D F. ZINI 20/10/2015 P. RELF K. GOSDEN WORD POLES POLE INSPECTION FOR IN-SERVICE POLES & POLE LIGNMENTS SEC SUB 2 9 SHT 2 REV

20 LOCL UTHORITY POLE LIGNMENT U/G LIGNMENT SITUTION DRWING REF. COMMENTS BRISBNE 3.25m centre from RP lign Unnumbered BCC. Licensing For footpaths 3.66m wide to (was 3.43m to road face of m from RP lign drawing pre 1973 Compliance Officer, kerb face installed pre 1973 pole) and post 1973 ph For footpaths3.75m wide to Dan Maher, 2.9m centre from RP lign m from RP lign kerb face installed after W106/1E Road and Traffic Design. High side** 1973 Ph For footpaths3.75m wide to 2.74m centre from RP lign BRISBNE CITY m from RP lign kerb face installed after Low side** COUNCIL 1973 W106/1E 1.75m centre from RP lign m from RP lign For footpaths 2.44m wide 0.3m from back of kerb to For footpath width pole face exceeding 4.0m New Subdivisions 2.95m centre from RP lign 0.8m centre behind face of kerb 0-0.9m from RP lign For 3.75m standard width footpath. For footpaths exceeding 4.75m wide WS10-1,WS m centre from RP lign For 4.25m standard width High side 0-0.9m from RP lign footpath 3.27m centre from RP lign WS10-2, Fig B8.4 Low side (1) and (2) 0.8m centre behind face of For footpath exceeding kerb 5.25m ORIGINL ISSUE COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX REC D F. ZINI 20/10/2015 P. RELF K. GOSDEN WORD POLES POLE INSPECTION FOR IN-SERVICE POLES & POLE LIGNMENTS SEC SUB 2 9 SHT 3 REV

21 LOCL UTHORITY POLE LIGNMENT U/G LIGNMENT SITUTION DRWING REF. COMMENTS WESTERN LOCKYER VLLEY REGIONL COUNCIL Use existing alignment in Formerly: 3.05m centre from RP lign 0-1.2m from RP lign For footpaths 4.0m wide EROC-19, established areas if Gatton Shire Council 5.0m centre from RP lign (with Gas) For footpaths 6.0m wide unnumbered plan alignment is non standard Formerly: m from RP lign For footpaths 4.0m min 3.2m centre from RP lign Laidley Shire Council (with Gas) wide LSC-04 SOMERSET REGIONL COUNCIL Formerly: Esk & Kilcoy Shire Council IPSWICH CITY COUNCIL 3.0m centre from RP lign 0-0.9m from RP lign 3.2m centre from RP lign in Ipswich City council area 3.4m centre from RP lign in ex-moreton Shire area 0-0.9m from RP lign 0-0.9m from RP lign 2.95m centre from RP lign m from RP lign Existing established locations Existing established locations For new subdivisions with footpaths 3.75m wide STD.R010 & STD.R011 Use existing alignment in established areas if alignment is non standard Use existing alignment in established areas if alignment is non standard ORIGINL ISSUE COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX REC D F. ZINI 20/10/2015 P. RELF K. GOSDEN WORD POLES POLE INSPECTION FOR IN-SERVICE POLES & POLE LIGNMENTS SEC SUB 2 9 SHT 4 REV

22 LOCL UTHORITY POLE LIGNMENT U/G LIGNMENT SITUTION DRWING REF. COMMENTS SOUTHERN BEUDESERT REGIONL COUNCIL For footpaths 4.0m min Formerly: 0-1.2m from RP lign 3.05m centre from RP lign wide Boonah Shire Council (with Sewer) Formerly: Beaudesert Shire Council 3.05m centre from RP lign 0-1.2m from RP lign (with Gas) For footpaths 4.5m wide and RURL areas without kerbs , REDLND CITY COUNCIL 2.95m centre from RP lign 0-0.9m from RP lign For all footpath widths 1038 LOGN CITY COUNCIL 3.075m centre from RP lign m from RP lign For footpaths min 3.5m wide , , GOLD COST CITY COUNCIL 0.7m from face of kerb 0-0.9m from RP lign For footpaths m wide m centre from RP lign 0-0.9m from RP lign For footpaths in RURL areas ORIGINL ISSUE COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX REC D F. ZINI 20/10/2015 P. RELF K. GOSDEN WORD POLES POLE INSPECTION FOR IN-SERVICE POLES & POLE LIGNMENTS SEC SUB 2 9 SHT 5 REV

23

24

25 PROBLEM FIND THE TIP LOD FOR THE POLE SHOWN BELOW. Side View No Wind Condition 10.5m (GL) 3 x MRS (11 kv) T m (GL) 4 x MOON (LV) T m Refer Mechanical Loads (Section 6) - No Wind, C. For a 20 deviation: 11kV T110 MRS : 0.90 kn per Conductor x kn LV T220 MOON : 0.73 kn per Conductor x kn Since the LV is attached below the tip of the pole, we reduce its load in proportion to its height. LV resolved to tip 2.92 x 8.0 = 2.92 x = 2.23 kn 10.5 Therefore the total tip load is: 11 kv : 2.70 kn + LV resolved to tip : 2.23 kn Resultant Force Plan View Tip Height TOTL TIP LOD 4.93 kn No Wind Condition 20 ttachment Height 105 m Wind Condition Refer Mechanical Loads (Section 6) Wind, C. Note that both the span lengths of 90m and 105m are best approximated the Medium Span Length for T110. For a 20 deviation: 11kV T110M MRS : 3.86 kn per Conductor x kn LV T220 MOON : 4.19 kn per Conductor x kn Since the LV is attached below the tip of the pole, we reduce its load in proportion to its height. LV resolved to tip x 8.0 = x = kn 10.5 Therefore the total tip load is: 11 kv : kn + LV resolved to tip : kn TOTL TIP LOD kn Wind Condition The No Wind and Wind results may be compared with the tip load ratings for 12.5m poles to determine pole size and whether staying is required. Notes: ttachment Height Tip Height Only conductor loads need be considered. There is no need to include pole wind load, since this is accounted for in the pole strength rating. ORIGINL ISSUE COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX REC D F. ZINI 20/10/2015 P. RELF K. GOSDEN WORD POLES POLE INSPECTION FOR IN-SERVICE POLES & POLE LIGNMENTS SEC SUB 2 11 SHT 2 REV

26 ENGINEERING BCKGROUND 1. POLE STRENGTH When calculating wood pole strengths from first principles using the methods in ppendix F of S/NZS7000:2010, the following factors have been selected for Energex Poles: Factor No Wind (EDT) Wind (LST) k 1 -Duration of Load Factor k d -Degradation Factor Capacity Factor Note these values are for reference only and designers are not required to use these for designs done in accordance to this manual. For a more in depth understanding of pole strength calculations, please refer to S/NZS7000. basic description of the method used follows The tip load capacity of a solid, round, wood pole planted in firm ground can be assumed to be: F T = f D 3 gl / 32 h where: F T is tip load capacity of the pole (kn) f is the ultimate bending stress, or modulus of rupture of the timber (kpa, or kn/m 2 ) D gl is ground line diameter of the pole (m) is the component strength factor h is pole height above ground (m). Strength Group Modulus of Rupture (kpa) S1 100,000 (103,000) S2 80,000 (86,000) S3 65,000 (73,000) Values shown are from S & are repeated in S/NZS7000. Values in parentheses taken from S/NZS 2878:2000 Component Strength Factor ( ) Pole Type New Poles No Wind * Wind Wood Concrete Note that only the Wind Condition needs to be considered for concrete poles. * For the No Wind condition, F T will also need to be multiplied by This will provide an equivalent strength factor comparable to the previous working stress design methods used in Energex. For the wind condition, the result, F T, should have the wind load on the pole itself, F P, deducted. The self wind loading of the pole, resolved to its tip, can be assumed to be: F P = 0.5 h D gl P wp where: is tip load due to wind on pole and fittings (kn) F p P wp Uncontrolled document when printed is design wind pressure (kpa), kpa 0.5 is included since the centre of pressure is midway up the pole. Note that the taper of the pole can be ignored, since it is offset by the constructions/fittings at the pole top. Refer S/NZS 7000:2010 for further information. F. ZINI 20/10/2015 POLES ENGINEERING BCKGROUND REC D ORIGINL ISSUE COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX P. RELF K. GOSDEN WORD SEC SUB 2 12 SHT 1 REV

27 Note: Bending Moment is the product of load (kn) and distance (m) from the pivot point to the point at which the force is applied. When determining allowable conductor loads, remember to allow for the wind load on the pole itself F h For the Wind Condition, we must deduct the wind load on the pole itself: Pole Wind Load = 0.5 x Wind Pressure x height x GL diameter = 0.5 x x 9 x 0.22 = 1.29 kn Thus Wind Condition tip load capacity is revised to: Uncontrolled document when printed Example: = 5.40 kn. pole of species GB has a ground-line diameter of 220mm. The pole is 9m high (above ground). What is its tip load capacity? GB is strength group S2. Looking at the table in Section 2.8, we observe that for a strength group S2 and diameter 220mm, the maximum bending moment is: No Wind: kn.m Wind: kn.m The No Wind bending moment value now needs to be multiplied by the 0.57 factor: No Wind: x 0.57 = 19.07kN.m Dividing by the pole height of 9m, we can obtain pole tip load capacities: No Wind: 2.12 kn Wind: 6.69 kn F. ZINI 20/10/2015 POLES ENGINEERING BCKGROUND REC D ORIGINL ISSUE COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX P. RELF K. GOSDEN WORD SEC SUB 2 12 SHT 2 REV

28 2. NILED POLE STRENGTH To determine pole tip load capacity under wind conditions (1300Pa) from the value of ultimate strength for a nail, use the following formula: F T = M U / h - F P = 0.72 M U / h h D gl where: F T is tip load capacity of the pole (kn) M U is the ultimate bending moment capacity of the pole nail h is the height of the pole above ground (m) F p is tip load due to wind on pole and fittings (kn) D gl is ground line diameter of the pole (m) is component strength factor 3. FOUNDTIONS Foundation strengths are matched to pole strengths rather than the applied tip load. There were 2 methods used to derive these values, which are both detailed in the document ES C(b)1:1991: 1) Section 7.1: Embedment depth = 0.6m +1/10 of Pole length 2) ppendix C: F T = k D gl J 3 / 12 (h J) where: F T is tip load capacity of the pole (kn) k is the passive soil reaction per unit depth (kpa/m) D gl is ground line diameter of the pole (m) J is the sinking depth of the pole (m) h is pole height above ground (m) The depth used in this manual is the greater of the 2 values calculated using these methods. Imported foundation materials such as concrete effectively increase the bearing area of the pole against the natural ground. lso refer to S/NZS 7000:2010 and Handbook HB331 Section 9.1. The foundation depths shown on Pages & are based on values used in the previous versions of the OHDM. These have been successfully used for a long period of time and have provided good service performance. F. ZINI 20/10/2015 POLES ENGINEERING BCKGROUND REC D ORIGINL ISSUE COPYRIGHT 2015 ENERGEX This drawing must not be reproduced in part or whole without written permission from ENERGEX P. RELF K. GOSDEN WORD SEC SUB 2 12 SHT 3 REV

Works on Local Government Controlled Roads. & Traffic Control Permit No

Works on Local Government Controlled Roads. & Traffic Control Permit No Works on Local Government Controlled Roads & Traffic Control Permit No. 171219-000220 Pursuant to Local Government Act 2009 (Section 75) This permit is valid for the following purpose(s) at the locations,

More information

pdf WATER RETICULATION STANDARD VENTILATION LOUVRE BOXES SINGLE AND DOUBLE DUCT SYSTEMS

pdf WATER RETICULATION STANDARD VENTILATION LOUVRE BOXES SINGLE AND DOUBLE DUCT SYSTEMS Drawing Index Name Doc.No Document Description 2001979.061H.pdf 2001979.061 WATER RETICULATION STANDARD SCOUR VALVE CHAMBER WITH CIRCULAR COVER AND FRAME SHEET NO1 OF 2 2001979.062F.pdf 2001979.062 WATER

More information

ADA Operations Contact Info

ADA Operations Contact Info Intro ADA Operations Contact Info Todd Grugel ph: 651-366-3531 email: todd.grugel@state.mn.us Joe Zilka ph: 651-366-3311 email: joseph.zilka@state.mn.us Harvey Unruh ph: 651-216-2912 email: harvey.unruh@state.mn.us

More information

Policy Statement. Objective. Context. References and Supporting Documentation

Policy Statement. Objective. Context. References and Supporting Documentation Policy Statement Subject Placement of Distribution Poles Along Roads With Speed Limits Not Exceeding 70km/h Approved by Robert Rogerson Signature & Date Distribution Standards and Policy Manager Authorised

More information

Item 404 Driving Piling

Item 404 Driving Piling Item Driving Piling 1. DESCRIPTION Drive piling. 2. EQUIPMENT 2.1. Driving Equipment. Use power hammers for driving piling with specified bearing resistance. Use power hammers that comply with Table 1.

More information

APPENDIX C SANITARY SEWER PEAK DESIGN FACTOR

APPENDIX C SANITARY SEWER PEAK DESIGN FACTOR PPENDIX C SNITRY SEWER PEK DESIGN FCTOR ll gravity sewers will be designed to accommodate the peak flow from the contributing drainage area. The peak flow will be computed using the appropriate peaking

More information

Appendix Work Zone Traffic Control

Appendix Work Zone Traffic Control ppendix Work Zone Traffic Control The purpose of this appendix is to present basic guidelines for work zone traffic control and to supplement the Highway Work Zone Safety Checklist. This appendix presents

More information

Infrastructure Requirements for Personal Safety in Respect of Clearances and Access

Infrastructure Requirements for Personal Safety in Respect of Clearances and Access Infrastructure Requirements for Personal Safety in Respect of Clearances and Access Synopsis This document sets out the design, construction and maintenance requirements for means of access onto, along

More information

Structural Design and Analysis of the New Mobile Refuge Chamber

Structural Design and Analysis of the New Mobile Refuge Chamber Key Engineering Materials Online: 2013-09-10 ISSN: 1662-9795, Vol. 584, pp 175-178 doi:10.4028/www.scientific.net/kem.584.175 2014 Trans Tech Publications, Switzerland Structural Design and Analysis of

More information

Part B Design Guidance / Principles _

Part B Design Guidance / Principles _ Part B Design Guidance / Principles www. landlab.co.nz Queenstown Town Centre Public Realm Design Guidelines Version 7 14 June 2018 Page 006 B1 Design Guidance & Best Practice The Queenstown Town Centre

More information

VEHICLE CROSSING AND PEDESTRIAN CUTDOWN SET OUT

VEHICLE CROSSING AND PEDESTRIAN CUTDOWN SET OUT Crossing Width 0 min./5 max. - Residential Vehicle Crossing 0 min./7 max. - Commercial/Industrial Vehicle Crossing 1800 min./2400 Des. - Pedestrian Cut Down Crossing Width 0 min./5 max. - Residential 0

More information

m v = 1.04 x 10-4 m 2 /kn, C v = 1.29 x 10-2 cm 2 /min

m v = 1.04 x 10-4 m 2 /kn, C v = 1.29 x 10-2 cm 2 /min 2.10 Problems Example 2.1: Design of Shallow Foundation in Saturated Clay Design a square footing to support a column load of 667 kn. The base of the footing will be located 1 m below the ground level

More information

Level 3 Cambridge Technical in Engineering 05822/05823/05824/05825/05873 Unit 3: Principles of mechanical engineering

Level 3 Cambridge Technical in Engineering 05822/05823/05824/05825/05873 Unit 3: Principles of mechanical engineering Level 3 Cambridge Technical in Engineering 05822/05823/05824/05825/05873 Unit 3: Principles of mechanical engineering Monday 16 January 2017 Afternoon Time allowed: 1 hour 30 minutes You must have: the

More information

WELCOME to CAUx Local India 2018

WELCOME to CAUx Local India 2018 WELCOME to CAUx Local India 2018 Flange Design In Detail Prepared by Sachin Pol and Fauzan Badiwale Some Typical Flange Images 3 Some Typical Gasket Images 4 Flange Design As Per ASME Sec.VIII Div.1 Mandatory

More information

Originally Issued: 10/08/2010 Revised: 10/30/2015 Valid Through: 10/31/2016

Originally Issued: 10/08/2010 Revised: 10/30/2015 Valid Through: 10/31/2016 EVALUATION SUBJECT: ITW ALPINE HANGERS AND ANCHORS REPORT HOLDER: ITW Building Components Group Inc. 13825 W. Business Center Dr. Unit A Lake Forest, IL 60045 (800) 521-9790 www.alpineitw.com CSI Division:

More information

Chapter 5 Site Considerations and Set-ups Table of Contents

Chapter 5 Site Considerations and Set-ups Table of Contents WI-750-074 Rev C Page 1 of 9 Chapter 5 Site Considerations and Set-ups Table of Contents 1. PURPOSE... 1 2. SCOPE... 2 3. DEFINITIONS... 2 4. ASSOCIATED DOCUMENTS... 2 5. SITE CONSIDERATIONS... 2 5.1.

More information

The New Anchor Post Product

The New Anchor Post Product The New Anchor Post Product From Anchor Systems This revolutionary foundation system is new to the Garden Room market. Benefit by using a foundation solution that is quicker, more efficient, less costly

More information

DESIGN OF AXIALLY LOADED STEPPED FOOTING DATA :- SBC of soil =200 KN /m 2 Concrete Mix =M20 Steel Grade = Fe 415 Clear cover of bottom slab =50 mm

DESIGN OF AXIALLY LOADED STEPPED FOOTING DATA :- SBC of soil =200 KN /m 2 Concrete Mix =M20 Steel Grade = Fe 415 Clear cover of bottom slab =50 mm STEPPED FOOTING The construction of sloped footing is sometimes difficult and when the slope of the top face of footing is more, say more than 1 vertically to 3 horizontally, it may be difficult to finish

More information

DIVISION: 06--WOOD AND PLASTICS SECTION: Wood, Plastic and Composite Fastenings

DIVISION: 06--WOOD AND PLASTICS SECTION: Wood, Plastic and Composite Fastenings DIVISION: 06--WOOD AND PLASTICS SECTION: 060523 -- Wood, Plastic and Composite Fastenings REPORT HOLDER: ITW BUILDING COMPONENTS GROUP, INC. 2400 LAKE ORANGE DRIVE, SUITE 150 ORLANDO, FLORIDA 32837 (800)

More information

ISO 1977 INTERNATIONAL STANDARD. Conveyor chains, attachments and sprockets. Chaînes de manutention, plaques-attaches et roues dentées

ISO 1977 INTERNATIONAL STANDARD. Conveyor chains, attachments and sprockets. Chaînes de manutention, plaques-attaches et roues dentées INTERNATIONAL STANDARD ISO 1977 Second edition 2006-08-15 Conveyor chains, attachments and sprockets Chaînes de manutention, plaques-attaches et roues dentées Reference number ISO 1977:2006(E) ISO 2006

More information

Originally Issued: 10/08/2010 Revised: 10/27/2017 Valid Through: 10/31/2018

Originally Issued: 10/08/2010 Revised: 10/27/2017 Valid Through: 10/31/2018 ITW BUILDING COMPONENTS GROUP INC. ITW ALPINE HANGERS AND ANCHORS CSI Section: 06 05 23 Wood, Plastic and Composite Fastenings 1.0 RECOGNITION ITW Alpine Hangers and Anchors recognized in this report has

More information

Hatch cover securing and tightness

Hatch cover securing and tightness (1986) (Rev 1 1996) (Corr.1 June 2000) (Rev.2 July 2005) (Corr.1 Oct 2005) Hatch cover securing and tightness 1. Application 1.1 The following recommendations apply to steel hatch covers that are fitted

More information

CHAPTER 8 STAKING SIGNALS AND LIGHTING FIELD GUIDE. 8.1 Staking Traffic Control Signal Systems

CHAPTER 8 STAKING SIGNALS AND LIGHTING FIELD GUIDE. 8.1 Staking Traffic Control Signal Systems CHAPTER 8 STAKING STAKING Correct staking of traffic control signal or lighting systems is critical to the appropriate placement of system components. 8.1 Traffic Control Signal Systems Locating the components

More information

PLAN 20 PUBLIC TRANSPORT NETWORK

PLAN 20 PUBLIC TRANSPORT NETWORK KEY Bus Route / 400m Coverage Existing Recommended Secondary Potential Secondary Indicative Stop Locations Principle Standard Sub-regional Transit Corridor Reservation PLAN 0 PUBLIC TRANSPORT NETWORK Date:

More information

6.0 ENGINEERING. Build Anything Better. REPRINTED 2017

6.0 ENGINEERING. Build Anything Better.  REPRINTED 2017 6.0 ENGINEERING TABLE OF CONTENTS 6.1 U.S. ENGINEERING ANALYSIS REPORT... P. 6-3 BELOW-GRADE WALL REINFORCEMENT TABLES... P. 6-5 ABOVE-GRADE WALL REINFORCEMENT TABLES.. P. 6-21 LINTEL REINFORCEMENT TABLES...P.

More information

ADA PRESENTATION (CURB RAMPS)

ADA PRESENTATION (CURB RAMPS) ADA PRESENTATION (CURB RAMPS) ACECNJ/NJDOT/FHWA DESIGN SUMMIT Warren Howard New Jersey Department of Transportation May 21, 2013 ADA Curb Ramps NJDOT wants curb ramps to be designed & constructed properly

More information

MSC Guidelines for Pressure Vessels

MSC Guidelines for Pressure Vessels References: a. 46 CFR Part 54 Pressure Vessels S. T. Brady, CDR, Chief, Engineering Division b. ASME Boiler and Pressure Vessel Code (BPVC), Section VIII, Division 1, (1998 Edition) c. Navigation and Inspection

More information

WEDGE-ALL Wedge Anchors

WEDGE-ALL Wedge Anchors WEDGE-ALL Wedge Anchors The Wedge-All wedge anchors are a non-bottom bearing, wedge-style expansion anchor for use in solid concrete or grout-fi lled masonry. A one-piece clip ensures uniform holding capacity

More information

COUNCIL POLICY. Document No: CPL260.5 Approval Date: 23 March 2010 Obstruction

COUNCIL POLICY. Document No: CPL260.5 Approval Date: 23 March 2010 Obstruction COUNCIL POLICY Road Reserve and Footpath Document No: CPL260.5 Approval Date: 23 March 2010 Obstruction Approved By: Council Review Date: 31 December 2013 Responsible Officer: Version No: 02 General Manager

More information

Technical Briefing Note

Technical Briefing Note Technical Briefing Note Subject Date Issued Revision Glossary of Terms 14th Nov 2017 Rev 3 The purpose of this Technical Briefing Note is to provide a glossary of terms commonly used in fall injury prevention

More information

P-04 Stainless Steel Corrugated Hoses and Metal Bellows Expansion Joints

P-04 Stainless Steel Corrugated Hoses and Metal Bellows Expansion Joints Guideline No.P-04 (201510) P-04 Stainless Steel Corrugated Hoses and Metal Bellows Expansion Joints Issued date: 20 th October 2015 China Classification Society Foreword This Guideline is a part of CCS

More information

LAMINATED POLES. engineered to solve problems. Coastal Douglas-fir. Field Raked and Tangent Poles

LAMINATED POLES. engineered to solve problems. Coastal Douglas-fir. Field Raked and Tangent Poles Coastal Douglas-fir Field Raked and Tangent Poles LAMINATED POLES engineered to solve problems 1 Design Criteria Submission Form You can either fax this information to 253-627-4188 or submit your drawings

More information

STAKING TRAFFIC CONTROL SIGNAL SYSTEMS

STAKING TRAFFIC CONTROL SIGNAL SYSTEMS Locating the components of a traffic control signal is not an exact science; many factors influence the location of the components. These factors include: lane widths, radii, pedestrian curb ramp requirements,

More information

TRADESMAN DRAINLAYER

TRADESMAN DRAINLAYER No. 9197 REGISTRATION EXAMINATION, NOVEMBER 2017 TRADESMAN DRAINLAYER ANSWER SCHEDULE Plumbers, Gasfitters and Drainlayers Board, 2017. All rights reserved. No part of this publication may be reproduced

More information

Inspection Chambers Project

Inspection Chambers Project Inspection Chamber Project Details Project Name Inspection Chambers Project Client Name Wavin Site ddress Parsonage Way, Chippenham, SN15 5PN Produced y dmin 3 Date 29/03/2017 Your components - Calc Ref

More information

A5.1 Permitted activities

A5.1 Permitted activities Section A5 Transportation A5.1 Permitted activities A5.1.1 Activities within roads Note: Refer to Section D for the definition of road (a) Any activity associated with the movement of traffic and the functioning

More information

BARRIER OFFSET 0" A 6" 6" A 12" 12" A 26" A 26" 3A OR 4A L OR S * ** L OR S L OR S

BARRIER OFFSET 0 A 6 6 A 12 12 A 26 A 26 3A OR 4A L OR S * ** L OR S L OR S ACCEPTABLE (TCB) TYPES AND ANCHORING DETAILS BASED ON UNDERLYING SURFACE TYPE AND BARRIER OFFSET FROM DROP-OFF BARRIER OFFSET UNDERLYING SURFACE 0" A 6" 6" A 12" 12" A 26" A 26" TCB TYPE DETAIL TCB TYPE

More information

Submittal / Substitution Request

Submittal / Substitution Request Submittal / Substitution Request SUBMITTED TO: To: Firm: Project: Submitted Product: SIMPSON STRONG-TIE WEDGE-ALL WEDGE ANCHOR Specified Product: Section: Page: Detail/Sheet No.: Description of Application:

More information

SECTION 48 - TRAFFIC STRIPES AND PAVEMENT MARKINGS TABLE OF CONTENTS

SECTION 48 - TRAFFIC STRIPES AND PAVEMENT MARKINGS TABLE OF CONTENTS SECTION 48 - TRAFFIC STRIPES AND PAVEMENT MARKINGS TABLE OF CONTENTS Section Page 48-1 GENERAL...48.1 48-2 THERMOPLASTIC TRAFFIC STRIPES AND PAVEMENT MARKINGS...48.1 48-3 PAINTED TRAFFIC STRIPES AND PAVEMENT

More information

SCOPE Application, Design, Operations,

SCOPE Application, Design, Operations, SCOPE Application, Design, Operations, Maintenance, etc.: Typical Traffic Control Signals Pedestrian Hybrid Beacons Emergency Vehicle One-Lane/Two-Way Facilities, Freeway Entrance Ramps, and Movable Bridges

More information

City of Margate, Florida. Neighborhood Traffic Management Manual

City of Margate, Florida. Neighborhood Traffic Management Manual City of Margate, Florida Neighborhood Traffic Management Manual Table of Contents Page No. I. INTRODUCTION... 1 II. TRAFFIC CALMING REQUEST AND PROCESSING PROCEDURES... 2 1. COMPLETE AND SUBMIT PROJECT

More information

Design Overview. Section 4 Standard Plans for Design. Pedestrian Access Routes. Pedestrian Access Routes. Overview. Cross Slope

Design Overview. Section 4 Standard Plans for Design. Pedestrian Access Routes. Pedestrian Access Routes. Overview. Cross Slope Design Overview Section 4 Standard Plans for Design Fall, 2017 Ann Johnson, PE Services Brady Rutman, SRF Consulting Group Overview Design Basics Recommendations: The Zone System Driveway Crossings Pedestrian

More information

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad - 500 043 CIVIL ENGINEERING Tutorial Question Bank Name : FOUNDATION ENGINEERING Code : A60126 Class : III B. Tech II Semester Branch

More information

Rhebogue Neighbourhood Greenway. Road Safety Audit Stage 2

Rhebogue Neighbourhood Greenway. Road Safety Audit Stage 2 Rhebogue Neighbourhood Greenway Road Safety Audit Stage 2 Report Number: 12/007/00/00057 July 2014 Mid West National Road Design Office Lissanalta House, Dooradoyle County Limerick Tel: 061 496 800 Fax:

More information

EVALUATION SUBJECT: DIVISION: HEATING, VENTILATING AND AIR CONDITIONING (HVAC) SECTION: HVAC DUCTS AND CASINGS.

EVALUATION SUBJECT: DIVISION: HEATING, VENTILATING AND AIR CONDITIONING (HVAC) SECTION: HVAC DUCTS AND CASINGS. ICC-ES Report PMG-1171 Reissued 11/2018 This report is subject to renewal 11/2019 EVALUATION SUBJECT: UNDERGROUND SINGLE WALL & DOUBLE WALL INSULATED DUCT FOR HVAC DIRECT BURIAL APPLICATIONS AND UNDERGROUND

More information

PROWAG/ADAAG Standards Guidance For Temporary Pedestrian Access Route (TPAR) Facilities and Devices

PROWAG/ADAAG Standards Guidance For Temporary Pedestrian Access Route (TPAR) Facilities and Devices INTRODUCTION: PROWAG/ADAAG Standards Guidance For Temporary Pedestrian Access Route (TPAR) Facilities and Devices Minnesota Department of Transportation DRAFT Document DRAFT This document was developed

More information

APPENDIX A. F107 & 380 Lines OYSTER RIVER DURHAM, NH

APPENDIX A. F107 & 380 Lines OYSTER RIVER DURHAM, NH APPENDIX A F107 & 380 Lines OYSTER RIVER DURHAM, NH 1. The design and proposed construction of this crossing is shown on the attached PSNH Transmission Business Drawing entitled DOUBLE CKT F107 & 380 BETWEEN

More information

CENGRS GEOTECHNICA PVT. LTD. Job No Sheet No. 1

CENGRS GEOTECHNICA PVT. LTD. Job No Sheet No. 1 CENGRS GEOTECHNICA PVT. LTD. Job No. 214030 Sheet No. 1 INTERIM REPORT ON GEOTECHNICAL INVESTIGATION FOR PROPOSED 66 KV GRID PLOT AT G-7, DWARKA, NEW DELHI. 1.0 INTRODUCTION 1.1 Project Description M/s.

More information

10 SHERFORD Town Code

10 SHERFORD Town Code Key Fixes (Ref: Masterplan Book, section 4a. Land Use Budget and Key Fixes ) The Town Plan designs and allocates buildings, streets and spaces as accurately as possible in the understandable absence of

More information

Hewson Planning 35 Corbett Road RD2 Whangarei 082. Attachment 5. Traffic Assessment

Hewson Planning 35 Corbett Road RD2 Whangarei 082. Attachment 5. Traffic Assessment Hewson Planning 35 Corbett Road RD2 Whangarei 082 Attachment 5. Traffic Assessment 1 Engineering Outcomes, Limited 132 Beach Road PO Box 3048, Onerahi Whangarei New Zealand Telephone 09 436 5534 Mobile

More information

COMPFIRE CCFT-FP_550_55_ September 2010 Fin Plate Connection to Circular Concrete-Filled Tube Test Result

COMPFIRE CCFT-FP_550_55_ September 2010 Fin Plate Connection to Circular Concrete-Filled Tube Test Result Reaction Frame Macalloy Bars Camera 3 Support Beam α Oven Bar Camera 2 Link Bar Camera 1 Tested Connection Jack Bar Electrical Furnace Reaction Frame Load Jack v2_5 April 2011 1 Oven Bar Link Bar View

More information

CASE STUDY OXLEY HIGHWAY SLIP STABILISATION

CASE STUDY OXLEY HIGHWAY SLIP STABILISATION MAY 2015 CASE STUDY OXLEY HIGHWAY SLIP STABILISATION IRF & ROADS AUSTRALIA REGIONAL CONFERENCE ASIA AND AUSTRALASIA DR SUDAR ARYAL LOCATION STOPPING BAY, OXLEY HIGHWAY 2 Armidale Nambucca Heads Tamworth

More information

Model NDA Differential pressure transmitter. Deltapi N Series A complete range of pneumatic pressure transmitters

Model NDA Differential pressure transmitter. Deltapi N Series A complete range of pneumatic pressure transmitters Data Sheet DS/NDA-EN Rev. H Model NDA Differential pressure transmitter Deltapi N Series A complete range of pneumatic pressure transmitters Introduction The blind type differential pressure transmitter

More information

OPENINGS AND REINFORCEMENTS 26

OPENINGS AND REINFORCEMENTS 26 ASME BPVC.VIII.1-2015 UG-35.2 UG-36 (4) It is recognized that it is impractical to write requirements to cover the multiplicity of devices used for quick access, or to prevent negligent operation or the

More information

Intelligent Traffic Systems:

Intelligent Traffic Systems: Printed on Cocoon Silk. Made with 100% FSC postconsumer waste. Cocoon Silk is 100% FSC recycled paper, process chlorine free. Please read and recycle Siemens Intelligent Traffic Systems Sopers Lane Poole

More information

C-M Precast Traffic Islands Index

C-M Precast Traffic Islands Index C-M Precast Traffic Islands Index Selecting Left or Right Hand Islands Product Range Splitter Islands Single Splitter Islands 1072 Chicane Splitter Islands 1075 Pedestrian Refuge 1082 Tweed Pedestrian

More information

REPORT HOLDER: FRAMECAD LICENSING LTD. POST OFFICE BOX 1292 AUCKLAND 1140 NEW ZEALAND EVALUATION SUBJECT: COLD FORMED STEEL C SHAPES AND TRACKS

REPORT HOLDER: FRAMECAD LICENSING LTD. POST OFFICE BOX 1292 AUCKLAND 1140 NEW ZEALAND EVALUATION SUBJECT: COLD FORMED STEEL C SHAPES AND TRACKS 0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 2361 Reissued 05/2017 This report is subject to renewal 05/2019. DIVISION: 05 00

More information

PALMERSTON NORTH CITY PALMERSTON NORTH SIGNS AND USE OF PUBLIC PLACES BYLAW Administration Manual

PALMERSTON NORTH CITY PALMERSTON NORTH SIGNS AND USE OF PUBLIC PLACES BYLAW Administration Manual PALMERSTON NORTH CITY PALMERSTON NORTH SIGNS AND USE OF PUBLIC PLACES BYLAW 2015 Administration Manual Document control Version No. Reason for amendment Date 1 Adopted by Council 1 October 2015 2 Correct

More information

ABB measurement & analytics data sheet. JAA, JAF and JAG Pneumatic indicating controllers

ABB measurement & analytics data sheet. JAA, JAF and JAG Pneumatic indicating controllers ABB measurement & analytics data sheet JAA, JAF and JAG Pneumatic indicating controllers 2 JA A, JAF an d JAG P N EUMATI C I ndicating cont rollers DS/JAx_DBT_DTE-EN Rev. H Measurement made easy Engineered

More information

CONSTRUCTION ENCROACHMENT PERMIT APPLICATION AND PROCESSING INSTRUCTIONS

CONSTRUCTION ENCROACHMENT PERMIT APPLICATION AND PROCESSING INSTRUCTIONS 'HYHORSPHQW (QJLQHHULQJ 5LFKDUGV %OYG UG )ORRU 6DFUDPHQWR &$ Phone: 916-808-8300 Fax: 916-808-1984 (QJLQHHULQJ 6HUYLFHV 'LYLVLRQ CONSTRUCTION ENCROACHMENT PERMIT APPLICATION AND PROCESSING INSTRUCTIONS

More information

H8 Signs, Supports and Poles

H8 Signs, Supports and Poles Alberta Infrastructure and Transportation Roadside Design Guide November 2007 H8 Signs, Supports and Poles H8.1 Introduction This section identifies the appropriate roadside safety treatment for signs,

More information

Driveway Design Criteria

Driveway Design Criteria Design Manual Chapter 5 - Roadway Design 5L - Access Management 5L-4 Driveway Design Criteria A. General For efficient and safe operations, access drives and minor public street intersections can be improved

More information

Excavation safety around natural gas

Excavation safety around natural gas Excavation safety around natural gas Table of contents You could damage much more than a gas line 3 Your responsibilities 4 Guidelines for locating and hand digging 4 Safety laws and regulations 6 Line

More information

CONSTRUCTION SPECIFICATION

CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES CONTROL OF TRAFFIC C201 CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES C201 ISSUE: NO:1 October 2007 TABLE OF CONTENTS CLAUSE CONTENTS

More information

Chapter 11. Culverts and Bridges Design Checklist for Culvert Design

Chapter 11. Culverts and Bridges Design Checklist for Culvert Design Yes No N/A Design Requirements I. GENERAL DESIGN GUIDELINES Chapter 11. Culverts and Bridges A. Culvert design is in accordance with the Culverts chapter of Volume 2 of the UDFCD Manual for additional

More information

CLEANING, INSPECTION, AND TESTING OF SEWERS

CLEANING, INSPECTION, AND TESTING OF SEWERS CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and

More information

Access Management Guidelines February 2013 THE CITY OF

Access Management Guidelines February 2013 THE CITY OF Access Management Guidelines February 2013 THE CITY OF Table of Contents Introduction 2 Review and Approval Process 5 Technical Guidelines 9... 10... 12 3. Separation Distance: Non-Signalized All-Turns

More information

Chapter Twenty-eight SIGHT DISTANCE BUREAU OF LOCAL ROADS AND STREETS MANUAL

Chapter Twenty-eight SIGHT DISTANCE BUREAU OF LOCAL ROADS AND STREETS MANUAL Chapter Twenty-eight SIGHT DISTANCE BUREAU OF LOCAL ROADS AND STREETS MANUAL Jan 2006 SIGHT DISTANCE 28(i) Chapter Twenty-eight SIGHT DISTANCE Table of Contents Section Page 28-1 STOPPING SIGHT DISTANCE

More information

Guide for Assessing Hull-Girder Residual Strength for Tankers. July 1995

Guide for Assessing Hull-Girder Residual Strength for Tankers. July 1995 AMERICAN BUREAU OF SHIPPING 8, AFFILIATED COMPANIES Guide for Assessing Hull-Girder Residual Strength for Tankers July 1995 American Bureau of Shipping Incorporated by the Legislature of the State of New

More information

Intermediate Angle, 0-25, Drilling detail. Angle 26-50, Baulk Plates, Pole Details. Termination Poles, ABC Details

Intermediate Angle, 0-25, Drilling detail. Angle 26-50, Baulk Plates, Pole Details. Termination Poles, ABC Details Part 7 LVABC Overhead Drawing Register Number A1 A2 A3 A4 A5 A6 A8 A9 Description Intermediate Angle, 0-25, Drilling detail Angle 26-50, Baulk Plates, Pole Details Termination Poles, ABC Details Inline

More information

PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES

PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES NB16 0603 NR Task Group 1 9 16 1. One update by NR task group page 3: 7/17/19 2. Two updates to S6.1 and S6.3 on page 1: 7/19/17 SUPPLEMENT 6 PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES

More information

Instruction Manual Contact Pressure Vacuum Gauge

Instruction Manual Contact Pressure Vacuum Gauge MS10 Instruction Manual Contact Pressure Vacuum Gauge Table of Contents 1. Safety Instructions 2. Intended Applications 3. Product Description and Functions 4. Installation 5. Commissioning 6. Maintenance

More information

Also suitable for: Concrete C12/15. For fixing of: Steel constructions Railings Consoles Ladders Wooden constructions Cable trays Machines Staircases

Also suitable for: Concrete C12/15. For fixing of: Steel constructions Railings Consoles Ladders Wooden constructions Cable trays Machines Staircases 28 Highbond anchor FHB II Flexible installation and highest loads in the cracked tensile zone. OVERVIEW FHB II-A S (standard), zinc plated steel FHB II-A L (performance optimised), zinc-plated steel Resin

More information

PLACEMENT OF SIGNS RECOMMENDED PRACTICES SUB-SECTION

PLACEMENT OF SIGNS RECOMMENDED PRACTICES SUB-SECTION Page 1 of 6 RECOMMENDED PRACTICES PART SECTION SUB-SECTION HIGHWAY SIGNS GENERAL General Proper positioning of signs is an important element in the overall control of traffic within a roadway network.

More information

PROCEDURE FOR ACCOMMODATING PEDESTRIANS IN WORK ZONES FOR CONSTRUCTION AND MAINTENANCE

PROCEDURE FOR ACCOMMODATING PEDESTRIANS IN WORK ZONES FOR CONSTRUCTION AND MAINTENANCE PROCEDURE FOR ACCOMMODATING PEDESTRIANS IN WORK ZONES FOR CONSTRUCTION AND MAINTENANCE A.1 STANDARD Measures shall be taken to accommodate pedestrian traffic through and/or around Work Zones for Construction

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION 6" X 8" (NOMINAL POST) 3-1/2" DIA. 2 HOLES TAPERED HARD WOOD WEDGES (HARDWOOD WEDGE

MICHIGAN DEPARTMENT OF TRANSPORTATION 6 X 8 (NOMINAL POST) 3-1/2 DIA. 2 HOLES TAPERED HARD WOOD WEDGES (HARDWOOD WEDGE X (NOMINAL POST) 1-1/ DIA. 2 HOLES X 8" (NOMINAL POST) 3-1/ DIA. 2 HOLES TAPERED HARD WOOD WEDGES (HARDWOOD WEDGE TO BE OAK, MAPLE OR OTHER APPROVED DENSE HARDWOODS) TO HOLD POST IN A STABLE POSITION AFTER

More information

Address: City: State: Zip:

Address: City: State: Zip: Permit Application MONUMENT SIGNS Installation Address: Applicant: Tenant/Business: Phone No.: SIGN COMPANY Company Name: Contact Name: Address: City: State: Zip: Phone No.: Email: Fax: ELECTRICAL CONTRACTOR

More information

Working with Grantors

Working with Grantors Working with Grantors Introduction Welcome to this Grantors Code of Practice. SSE s core purpose is to provide the energy that people need in a reliable and sustainable way. A key component of this is

More information

SAFETY JOURNAL FOR GIPFEL WEDGE ROCK ANCHOR BOLTS

SAFETY JOURNAL FOR GIPFEL WEDGE ROCK ANCHOR BOLTS SAFETY JOURNAL FOR GIPFEL WEDGE ROCK ANCHOR BOLTS NOTE: Here we are only talking about the wedge type expansion bolts. How do rock anchors fail? A rock anchor assembly mainly comprises of a Hanger and

More information

Review of Guidelines for Cycleway Safety Fencing

Review of Guidelines for Cycleway Safety Fencing Review of Guidelines for Cycleway 1.0 PURPOSE 1.1 This document is meant to provide a review of available reference documents for determining appropriate fencing requirements for cycleway paths and shared

More information

AUSTRALIAN ARROW AND ARAFURA CADET ASSOCIATION ARROW CATAMARAN RESTRICTIONS AND MEASUREMENT CERTIFICATE

AUSTRALIAN ARROW AND ARAFURA CADET ASSOCIATION ARROW CATAMARAN RESTRICTIONS AND MEASUREMENT CERTIFICATE AUSTRALIAN ARROW AND ARAFURA CADET ASSOCIATION ARROW CATAMARAN RESTRICTIONS AND MEASUREMENT CERTIFICATE 1 NOTE: The object of these restrictions is to provide uniform specifications and restrictions for

More information

Hospital Link Project Project Update September 2017

Hospital Link Project Project Update September 2017 Hospital Link Project Project Update September 2017 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction is well underway. Read on for important

More information

MILITARY SPECIFICATION SHEET SCREW, MACHINE, PAN HEAD, CROSS-RECESSED, CORROSION RESISTANT STEEL, UNC-2A

MILITARY SPECIFICATION SHEET SCREW, MACHINE, PAN HEAD, CROSS-RECESSED, CORROSION RESISTANT STEEL, UNC-2A INCH-POUND MS19D April 199 Superseding MS19C 18 July 198 MILITARY SPECIFICATION SHEET SCREW, MACHINE, PAN HEAD, CROSS-RECESSED, CORROSION RESISTANT STEEL, UNC-A This specification is approved for use by

More information

MILITARY SPECIFICATION SHEET SCREW, MACHINE, PAN HEAD, CROSS-RECESSED, CORROSION RESISTANT STEEL, UNC-2A

MILITARY SPECIFICATION SHEET SCREW, MACHINE, PAN HEAD, CROSS-RECESSED, CORROSION RESISTANT STEEL, UNC-2A INCH-POUND MS19D April 199 Superseding MS19C 18 July 198 MILITARY SPECIFICATION SHEET SCREW, MACHINE, PAN HEAD, CROSS-RECESSED, CORROSION RESISTANT STEEL, UNC-A This specification is approved for use by

More information

: 70 YEARS OF DESIGN & INNOVATION BELL & AVECTOR BOLLARDS

: 70 YEARS OF DESIGN & INNOVATION BELL & AVECTOR BOLLARDS 1946-2016: 70 YEARS OF DESIGN & INNOVATION e-brochure REF:E-007-03-16 BELL & AVECTOR BOLLARDS BELL & AVECTOR BOLLARD RANGE Ref: S-079-02-16 INTRODUCTION The original robust traffic calming solution Large

More information

Magnetic Tape Installation Straight guide tape, embedded magnetic bar, curve segments HG A

Magnetic Tape Installation Straight guide tape, embedded magnetic bar, curve segments HG A Installation Instructions HG 19600-A Magnetic Tape Installation Straight guide tape, embedded magnetic bar, curve segments HG 19600-A English, Revision 01 Dev. by: TE Date: 25.06.2015 Author(s): RAD Götting

More information

LYSAGHT W-DEK. Design and Construction Manual. Structural steel decking system

LYSAGHT W-DEK. Design and Construction Manual. Structural steel decking system LYSAGHT W-DEK Structural steel decking system Design and Construction Manual ptimised to bring greater efficiency, speed of construction and economy. Exceptional spanning characteristics (up to 4.1m) reduces

More information

SECTION 3 STREET DESIGN

SECTION 3 STREET DESIGN 3.01 GENERAL SECTION 3 STREET DESIGN For purposes of geometric and structural design, streets shall be classified according to the following table. The City Engineer will determine the class of all proposed

More information

DESIGN CODE. Enterprise West Harlow London Road North Design Code 21

DESIGN CODE. Enterprise West Harlow London Road North Design Code 21 DESIGN CODE Enterprise West Essex @ Harlow London Road North Design Code 21 4 MAXIMUM BUILDING HEIGHTS 4.1 Table 4A sets out maximum building height standards for each character area within the LDO boundary.

More information

TEMPORARY TRAFFIC CONTROL GUIDELINES FOR HIGHWAY-RAIL GRADE CROSSINGS

TEMPORARY TRAFFIC CONTROL GUIDELINES FOR HIGHWAY-RAIL GRADE CROSSINGS TEMPORARY TRAFFIC CONTROL GUIDELINES FOR HIGHWAY-RAIL GRADE CROSSINGS 1.0 INTRODUCTION 1.1 Purpose The Southern California Regional Rail Authority (SCRRA) is the designated track owner of the Metrolink

More information

Field Instruction. Protect Horizon Power employees and contractors from a potential hazard.

Field Instruction. Protect Horizon Power employees and contractors from a potential hazard. 2.15 Temporary Safety Barriers and/or Warning Signs Purpose This instruction sets out the minimum requirements for the installation and erection of temporary safety barriers and/or warning signs to: Protect

More information

CERTIFICATION OF COMPLIANCE OF THE USER S DESIGN SPECIFICATION

CERTIFICATION OF COMPLIANCE OF THE USER S DESIGN SPECIFICATION CERTIFICATION OF COMPLIANCE OF THE USER S DESIGN SPECIFICATION I, the undersigned, being experienced and competent in the applicable field of design related to pressure vessel requirements relative to

More information

TEMPORARY OCCUPANCY PERMITS. Street Space, Additional Street Space and Temporary Occupancy Permits PUBLIC WORKS CODE : ARTICLE 15, SEC.

TEMPORARY OCCUPANCY PERMITS. Street Space, Additional Street Space and Temporary Occupancy Permits PUBLIC WORKS CODE : ARTICLE 15, SEC. TEMPORARY OCCUPANCY PERMITS Street Space, Additional Street Space and Temporary Occupancy Permits PUBLIC WORKS CODE : ARTICLE 15, SEC. 724 Difference between the 3 permits. Who would apply for the permit?

More information

Operations and Instruction Manual Might Swivel Model # Concrete and Steel Anchorage Connector ANSI Z ,000 lbs / 44kn

Operations and Instruction Manual Might Swivel Model # Concrete and Steel Anchorage Connector ANSI Z ,000 lbs / 44kn Operations and Instruction Manual Might Swivel Model # 00238 Concrete and Steel Anchorage Connector ANSI Z359.1 10,000 lbs / 44kn Description: Zinc plated forged heat treated steel, Special design gives

More information

Anchor Component Material Standard Mechanical Properties

Anchor Component Material Standard Mechanical Properties SECTION 4.1 PAGE 1 / 5 l description The UCAN sleeve anchor is a light-medium duty anchor ideal for applications in concrete, hollow block and brick. It is a mechanical expansion anchor assembled with

More information

INTRODUCTION TABLE OF CONTENTS

INTRODUCTION TABLE OF CONTENTS 2 INTRODUCTION Thank you for choosing Servometer to design and manufacture your unique, new electrodeposited bellows for your particular application. The definitions, formulas and design parameters inside

More information

ISO 4081 INTERNATIONAL STANDARD. Rubber hoses and tubing for cooling systems for internal-combustion engines Specification

ISO 4081 INTERNATIONAL STANDARD. Rubber hoses and tubing for cooling systems for internal-combustion engines Specification Provläsningsexemplar / Preview INTERNATIONAL STANDARD ISO 4081 Third edition 2010-06-01 Rubber hoses and tubing for cooling systems for internal-combustion engines Specification Tubes et tuyaux en caoutchouc

More information

GUIDELINE: Roadside Worksites

GUIDELINE: Roadside Worksites Title: GUIDELINE: Roadside Worksites Version 1.0 Short description Relevant to Authority Responsible officer Responsible office A guideline on ensuring a safe method of works on or near roadways within

More information

Sponsored by Mrs. Gina Gregory and Mr. Reggie Copeland.

Sponsored by Mrs. Gina Gregory and Mr. Reggie Copeland. AN ORDINANCE REGULATION TO AMEND THE SUBDIVISION REGULATIONS FOR THE CITY OF MOBILE, ALBAMA CODES TO CREATE NEW WALKABLE STREET STANDARDS THAT ENABLES TRADITIONAL, WALKABLE VILLAGE AND NEIGHBORHOOD CENTERS

More information

FIRE PREVENTION METHOD FOR 275KV OIL-FILLED CABLE IN TEPCO

FIRE PREVENTION METHOD FOR 275KV OIL-FILLED CABLE IN TEPCO FIRE PREVENTION METHOD FOR 275KV OIL-FILLED CABLE IN TEPCO Atsushi Toya, Tokyo Electric Power Company, (Japan), toya.atsushi@tepco.co.jp Shinsuke Nasukawa, Tokyo Electric Power Company, (Japan), nasukawa.shinsuke@tepco.co.jp

More information