Large-scale Field Test

Size: px
Start display at page:

Download "Large-scale Field Test"

Transcription

1 Vaskinn 1 Large-scale Field Test Kjetil Arne Vaskinn kav@trh.statkraftgroner.no Statkraft Grøner AS SUMMARY The objective the controlled failure of large-scale embankment is to monitor and record the failure process and mechanisms in detail. This will provide valuable data to assist in understanding the fundamental failure process, for developing predictive models and for assessing the validity of smaller scale laboratory testing. The tests will take place in Nordland in Norway. The paper gives a short description of the test site and the plans for the tests in 2002 and the preliminary plan for the instrumentation. 1 INTRODUCTION Breach formation is the term used to cover the factors that lead to an uncontrolled release of water from a dam structure. It is well known that the most common causes of failure of an embankment are water overtopping the crest or internal erosion (so-called piping). Although there have been tests and analysis of homogeneous structures of non-cohesive material, the failure of multi-element structures incorporating impervious cores remain poorly understood. Experimental tests will be undertaken to support the theoretical development of models of the failure modes and rates of failure. Tests will include both large-scale fieldwork (failure of 6m high embankments) and smaller laboratory modelling (0.8m high). The large-scale experimental facilities will allow studies of the factors that govern the initiation and growth of breaches under controlled conditions. Also, the issue of scaling from the laboratory to the prototype scale will also be addressed. 2 OBJECTIVES The objective of this part of IMPACT is to undertake experiments of controlled failure of large-scale embankments in order to monitor and record the failure process and mechanisms in detail. This will provide valuable data to assist in understanding the fundamental failure process, for developing predictive models and for assessing the validity of smaller scale laboratory testing. 3 DESCRIPTION OF THE TEST SITE 3.1 Location The test site is located in the middle of Norway (Nordland), downstream of the reservoir Røssvatnet and upstream of the reservoir Stormyrsmagasinet. See map (Figure 1) and picture (Figure 2). The test embankments may be constructed to a height of 6m and subsequently force to failure under controlled conditions. The picture in Figure 2 is taken during a testing period of the gates at the dam Røssvassdammen. There is normally no water flowing in this part of the river.

2 Vaskinn 2 Pictures in Figures 3 and 4 show the test-dam used during the 2001 field-test in the Norwegian project: Stability and Breaching of Rockfill Dams. Figure 5 gives a view of the river reach downstream from the test-site. Figure 1 Test-site in Nordland Figure 2 Arial photo of the test-site

3 Vaskinn 3 Figure 3 The test-dam used in the Norwegian project Stability and Breaching of Rockfill Dams (2001) Figure 4 The test-dam used in the Norwegian project Stability and Breaching of Rockfill Dams (2001)

4 Vaskinn 4 Figure 5 The river reach downstream of test-site Water-level/discharge The gates at the dam Røssvassdammen have a total capacity up to 450m3/s. The gates are new and the operation of them is easy and flexible. The high capacity through the gates gives us the opportunity to simulate breaching in large reservoirs (slow reduction in the water level in the reservoir as a function of time) and small reservoirs. The release of water from the upstream-reservoir will be done in close co-operation with the dam-owner, Statkraft SF. The site is located such that there will be minimal impacts on the environment and no impacts on local infrastructure. 4 TEST-PROGRAM 4.1 Test dams There will be 5 tests in total. 3 of the tests will be done in 2002: Test 1: Homogeneous earthfill (minimal cohesive) dam / embankment with failure by overtopping. Test 2 Homogeneous (maximum cohesive) dam / embankment with failure by overtopping. Test 3 Composite (2 layers) embankment with failure by overtopping. Moraine core, rockfill support/protection layer. In addition to tests 1-3, a test of toe stability will be made at the test-site. The proposed geometry and layout of the test-dams are shown in Figures 6 9.

5 Vaskinn 5 Figure 6 Test-dam no.1 Figure 7 Test-dam no. 2 There is an option of two different tests with test-dam no. 1: First run a test with a protective layer downstream, then run the same test without the protective layer. The test planned in IMPACT is without the protective layer.

6 Vaskinn 6 Figure 8 Test-dam no. 3 Figure 9 Test-dam 4 (for dam-toe stability)

7 Vaskinn Field work-plan In outline, the plan for the field test is: 1. Preparing the site for the test dam 1.1 Building of transport road to the riverbed 1.2 Work at the riverbed/prepare the foundation of the test-dams. 1.3 Preparing the side-slopes 2. Selection and transport of the materials for dam building. 3. Building of test-dam #1 4. Test #1 5. Cleaning up at dam-site and preparing for test #2. Step 2-5 will be repeated for each test. A local contracting firm will undertake building of the dam. A call for tenders has already been made to select the firm to do the job. This is done to make ensure that the building/construction of the test-dam will be done according to our-plans. 5 INSTRUMENTATION FOR THE FIELD TEST 5.1 Data collection Based on discussions in the working group, the IMPACT meeting in Wallingford and during the workshop in Trondheim 17th and 18th of April 02 it is clear that the following data should be collected: 1. Breach formation geometry: 3D surface of breach at any time 2. Water levels: record level variation with time at: - Upstream reservoir 2 locations minimum - 3D surface through breach - Downstream water levels along the river 3. Gate Operation and Water level in Røssvassdammen (flow into test area) 4. Water pressure through embankment/dam 5. Flow / velocity patterns - Flow through the embankment/dam in the initial phase and at through the toe during testing of toe-stability - Flow through the embankment/dam during braking of the dam. - Flow in the river downstream of the test-dam 6. Sediment movement (materials from the test-dams) 7. Material properties: - Particle size distribution - Liquid / plastic limit - Type of clay - Compaction - Rock properties (interlocking effect) - (Clay will require further tests e.g. chemistry) - Permeability of the test-dam - Porosity of the test-dam

8 Vaskinn Instrumentation for data collection There are a number of approaches that could be taken for collecting data. The methods that are chosen are considered to be simple, well tested and documented and cost effective D surface of the breach at any time A grid will be painted across whole of embankment, including crest and upstream face to aid video and photography. The following methods will be used: Video Photo Photogrammerty Sonar upstream Point measurement within the dam-body either through wires or balls. Measurement in the dam is done to provide information to calibrate and verify data from the other methods. Video will be taken from: Downstream: 3 camera stations (2001-2) Above: 1 camera Upstream: 1 camera Still camera shots can be taken from video footage as the qualities of the photos are high enough, but as a security additional camera will be used. Photogrammetry is a possible method for identifying movement of embankment material. This requires at least two cameras, firing simultaneously, at a fixed spacing. Possible camera-positions are shown in figure 10. Figure 10 Possible positions for the cameras

9 Vaskinn 9 Sonar offers a possible means of monitoring breach growth underwater. Sonar is however not appropriate for downstream conditions, but could be placed underwater upstream to show growth of breach through upstream face. Sonar has been used for monitoring/mapping of dams in Norway. Figure 11 show an example of a Norwegian dam. Figure 11 Sonar picture of a dam A possible solution to monitor the growth of the breach is to use movement sensors e.g. floating balls. These can be buried within the dam and are released as erosion occurs. These sensors need to be uniquely identifiable, unrestricted by cables, traceable or disposable Water levels Water level will be recorded through automatic recording (pressure sensors): 2 points upstream of the test-dam several points downstream to monitor the flood wave Automated system will be complemented with some manual readings of staff-gauges Pressure sensors in the dam. There will be place at least 10 pressure sensors in the test-dam. See Figures Inflow rate into the test-reservoir Discharge through the gates at Røssvassdammen is equal to the inflow to the reservoir upstream of the test-dam. The discharge will be measured through measuring the gate opening at every minute. The waterlevel in the lake Røssvassdammen will be recorded.

10 Vaskinn Discharge There are two different situations in which monitoring of the discharge is necessary: During testing of the toe-stability During the breach The discharge may be monitored through readings of calibrated staff-gauges in addition to automatic sampling of water pressure/water levels. Discharge will also be recorded through an Acoustic Doppler Current Profiler (ADCP). The ADCP is either mounted on the bottom looking upward (will be used for monitor the discharges during the breach or the ADCP can be floating on the surface looking downwards. (EasyQ) Sediment movements The sediment movement will be recorded by survey only. Based on the changes in bed surface elevation, calculation of sediment transport will be done Properties of the Materials Details still to be decided.

PRELIMINARY RISK ASSESSMENT RIDM PROJECT FOR A DAM WITH A VEGETATION- LINED SPILLWAY AND FERC PILOT

PRELIMINARY RISK ASSESSMENT RIDM PROJECT FOR A DAM WITH A VEGETATION- LINED SPILLWAY AND FERC PILOT PRELIMINARY RISK ASSESSMENT FOR A DAM WITH A VEGETATION- LINED SPILLWAY AND FERC PILOT RIDM PROJECT MAY 3, 2018 DAVID S. BOWLES AND LOREN R. ANDERSON RAC ENGINEERS AND ECONOMISTS, LLC AND UTAH STATE UNIVERSITY

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Fly Ash Reservoir II Cardinal Plant Brilliant, Ohio October, 2016 Prepared for: Cardinal Operating Company Cardinal Plant Brilliant, Ohio Prepared by: Geotechnical

More information

NUMERICAL AND PHYSICAL MODELING

NUMERICAL AND PHYSICAL MODELING POINTE DU BOIS GENERATING STATION SPILLWAY REPLACEMENT PROJECT NUMERICAL AND PHYSICAL MODELING Kara Hurtig, Northwest Hydraulic Consultants, North Vancouver, BC, Canada David S. Brown, KGS Group, Winnipeg,

More information

Plan B Dam Breach Assessment

Plan B Dam Breach Assessment Plan B Dam Breach Assessment Introduction In support of the Local Sponsor permit applications to the states of Minnesota and North Dakota, a dam breach analysis for the Plan B alignment of the Fargo-Moorhead

More information

COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION

COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION Abstract Lonie I * Tailings and Dams, GHD Brisbane, QLD, Australia Queensland Alumina Limited operates

More information

DAIVÕES DAM SPILLWAY: A NOVEL SOLUTION FOR THE STILLING BASIN

DAIVÕES DAM SPILLWAY: A NOVEL SOLUTION FOR THE STILLING BASIN DAIVÕES DAM SPILLWAY: A NOVEL SOLUTION FOR THE STILLING BASIN Elsa Alves *, Felix Hernando and Rafael Chacón * Laboratório Nacional de Engenharia Civil (LNEC) Av. do Brasil, 101, 1700-066 Lisboa, Portugal

More information

Journal of Applied Fluid Transients, Vol 1-1, April 2014 (3-1)

Journal of Applied Fluid Transients, Vol 1-1, April 2014 (3-1) Modeling and Field Verification Study of Air Slam Conditions on kalanit Pipeline System By Yiftach Brunner & Sathish Kumar ir valves are integral part of long water transmission mains and are essential

More information

Flow transients in multiphase pipelines

Flow transients in multiphase pipelines Flow transients in multiphase pipelines David Wiszniewski School of Mechanical Engineering, University of Western Australia Prof. Ole Jørgen Nydal Multiphase Flow Laboratory, Norwegian University of Science

More information

REVETMENTS. Purposes and Operational Constraints. Purposes Erosion control o o. Revetment Design 4/5/2016. CE A676 Coastal Engineering

REVETMENTS. Purposes and Operational Constraints. Purposes Erosion control o o. Revetment Design 4/5/2016. CE A676 Coastal Engineering REVETMENTS Ijsseldam, the Netherlands Orson P. Smith, PE, Ph.D. Instructor Purposes and Operational Constraints Purposes Erosion control o o Embankment Toe protection for a seawall, retaining wall or other

More information

Khosla's theory. After studying a lot of dam failure constructed based on Bligh s theory, Khosla came out with the following;

Khosla's theory. After studying a lot of dam failure constructed based on Bligh s theory, Khosla came out with the following; Khosla's theory After studying a lot of dam failure constructed based on Bligh s theory, Khosla came out with the following; Following are some of the main points from Khosla's Theory From observation

More information

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011 APPENDIX C VEGETATED EMERGENCY SPILLWAY VERSION 1.0 March 1, 2011 [NOTE: Could use a better photo more clearly showing the emergency spillway in the context of the dam.] SECTION C-1: DESCRIPTION OF PRACTICE

More information

TDLP INC. The Dam & Levee Professionals. Kevin Chancey Sarah Edens. Monica Murie Jason Unruh

TDLP INC. The Dam & Levee Professionals. Kevin Chancey Sarah Edens. Monica Murie Jason Unruh TDLP INC The Dam & Levee Professionals Kevin Chancey Sarah Edens Monica Murie Jason Unruh The Dam & Levee Professionals Prevention and Protection of Floodwall Overtopping Scour The Dam & Levee Professionals

More information

3D NUMERICAL MODELLING OF THE CAPACITY FOR A PARTIALLY PRESSURIZED SPILLWAY

3D NUMERICAL MODELLING OF THE CAPACITY FOR A PARTIALLY PRESSURIZED SPILLWAY 3D NUMERICAL MODELLING OF THE CAPACITY FOR A PARTIALLY PRESSURIZED SPILLWAY Samuel Vingerhagen 1 & Nils Reidar B. Olsen 1 1 Department of Hydraulic and Environmental Engineering, The Norwegian Univeristy

More information

Attached as Exhibit B-2 is BC Hydro's presentation from the Stave Falls Spillway Gates Project Workshop held on January 18, 2010.

Attached as Exhibit B-2 is BC Hydro's presentation from the Stave Falls Spillway Gates Project Workshop held on January 18, 2010. BChydro CD FOR GEf\lE IONS B-2 Joanna Sofield Chief Regulatory Officer Phone: (604) 623-4046 Fax: (604) 623-4407 bchydroregulatorygroup@bchydro.com January 19, 2010 Ms. Erica M. Hamilton Commission Secretary

More information

CROSS-SHORE SEDIMENT PROCESSES

CROSS-SHORE SEDIMENT PROCESSES The University of the West Indies Organization of American States PROFESSIONAL DEVELOPMENT PROGRAMME: COASTAL INFRASTRUCTURE DESIGN, CONSTRUCTION AND MAINTENANCE A COURSE IN COASTAL DEFENSE SYSTEMS I CHAPTER

More information

The Hydraulic Design of an Arced Labyrinth Weir at Isabella Dam

The Hydraulic Design of an Arced Labyrinth Weir at Isabella Dam Utah State University DigitalCommons@USU International Symposium on Hydraulic Structures Jun 28th, 1:30 PM The Hydraulic Design of an Arced Labyrinth Weir at Isabella Dam E. A. Thompson Sacramento District

More information

OECS Regional Engineering Workshop September 29 October 3, 2014

OECS Regional Engineering Workshop September 29 October 3, 2014 B E A C H E S. M A R I N A S. D E S I G N. C O N S T R U C T I O N. OECS Regional Engineering Workshop September 29 October 3, 2014 Coastal Erosion and Sea Defense: Introduction to Coastal/Marine Structures

More information

AMEC010570_0001. Via . Mt. Polley Mine Tailings Facility Optimization Potential- Follow Up from Dam Safety Review 1.

AMEC010570_0001. Via  . Mt. Polley Mine Tailings Facility Optimization Potential- Follow Up from Dam Safety Review 1. { TIME\@ "d MMMM yyyy" } AMEC Project Number VM00448 Via EMAIL Imperial Metals Corporation 200-580 Hornby Street Vancouver, B.C. V6C 3B6 Attention: Mr. Ron Martel Environmental Superintendent Reference:

More information

Huntington District. For More Information Contact (304)

Huntington District. For More Information Contact (304) Zoar Levee & Diversion Dam are located in the Muskingum River Basin highlighted in green to left. The Muskingum River Basin is the site of Ohio s first multiple purpose water management and land conservation

More information

Dams as Systems. Pat Regan Federal Energy Regulatory Commission (FERC)

Dams as Systems. Pat Regan Federal Energy Regulatory Commission (FERC) Dams as Systems Pat Regan Federal Energy Regulatory Commission (FERC) FERC >2,500 jurisdictional dams 770 feet to 0.5 feet high Five Regions Atlanta, Chicago, New York, Portland, San Francisco ~120 staff

More information

STRUCTURE S-65 PURPOSE SPILLWAY OPERATION

STRUCTURE S-65 PURPOSE SPILLWAY OPERATION STRUCTURE S-65 This structure is a reinforced concrete, gated spillway with discharge controlled by three cable operated, vertical lift gates, and a reinforced concrete lock structure with two pairs of

More information

+)) Lower Churchill Project RIPRAP DESIGN FOR WIND-GENERATED WAVES SNC LAVALIN. SLI Document No HER

+)) Lower Churchill Project RIPRAP DESIGN FOR WIND-GENERATED WAVES SNC LAVALIN. SLI Document No HER +)) SNC LAVALIN Lower Churchill Project RIPRAP DESIGN FOR SLI Document No. 505573-3001-4HER-0011-00 Nalcor Reference No. MFA-SN-CD-0000-CV-RP-0006-01 Rev. 81 Date: 07 -Dec-2012 Prepared by: Checked by:

More information

AIR-WATER FLOW STRUCTURES AT AN ABRUPT DROP WITH SUPERCRITICAL FLOW

AIR-WATER FLOW STRUCTURES AT AN ABRUPT DROP WITH SUPERCRITICAL FLOW AIR-WATER FLOW STRUCTURES AT AN ABRUPT DROP WITH SUPERCRITICAL FLOW H. CHANSON and L. TOOMBES Department of Civil Engineering, The University of Queensland, Brisbane QLD 4072, Australia 1. Introduction

More information

Ermenek Dam and HEPP: Spillway Test & 3D Numeric-Hydraulic Analysis of Jet Collision

Ermenek Dam and HEPP: Spillway Test & 3D Numeric-Hydraulic Analysis of Jet Collision Ermenek Dam and HEPP: Spillway Test & 3D Numeric-Hydraulic Analysis of Jet Collision J.Linortner & R.Faber Pöyry Energy GmbH, Turkey-Austria E.Üzücek & T.Dinçergök General Directorate of State Hydraulic

More information

MIKE Release General product news for Marine software products, tools & features. Nov 2018

MIKE Release General product news for Marine software products, tools & features. Nov 2018 MIKE Release 2019 General product news for Marine software products, tools & features Nov 2018 DHI 2012 MIKE 3 Wave FM New advanced phase-resolving 3D wave modelling product A MIKE 3 FM Wave model - why?

More information

Greenup Lock Filling and Emptying System Study

Greenup Lock Filling and Emptying System Study Fourth LACCEI International Latin American and Caribbean Conference for Engineering and Technology (LACCET 2006) Breaking Frontiers and Barriers in Engineering: Education, Research and Practice 21-23 June

More information

HYDRAULIC JUMP AND WEIR FLOW

HYDRAULIC JUMP AND WEIR FLOW HYDRAULIC JUMP AND WEIR FLOW 1 Condition for formation of hydraulic jump When depth of flow is forced to change from a supercritical depth to a subcritical depth Or Froude number decreases from greater

More information

USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY. Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1

USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY. Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1 USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1 Plum Creek Floodwater Retarding Structure No. 6 is located in an area of Kyle, Texas, that is currently

More information

Sensor Platform Project Marine Trials Bidders Conference. Fundy Ocean Research Center for Energy fundyforce.ca

Sensor Platform Project Marine Trials Bidders Conference. Fundy Ocean Research Center for Energy fundyforce.ca Sensor Platform Project Marine Trials Bidders Conference Fundy Ocean Research Center for Energy fundyforce.ca 1 Project Team FORCE OceanWorks International Preliminary Design, Operational Procedures Murray

More information

SeaSmart. Jonathan Evans

SeaSmart. Jonathan Evans SeaSmart A new approach for rapid, on-site resource assessment at potential tidal stream energy array sites using MAS Marine Solutions for the Deep Data World Jonathan Evans Presentation Outline Marine

More information

CLOSURE PLAN. CFR (b) Bottom Ash Pond Complex Cardinal Plant Brilliant, Ohio. September, 2016

CLOSURE PLAN. CFR (b) Bottom Ash Pond Complex Cardinal Plant Brilliant, Ohio. September, 2016 CLOSURE PLAN CFR 257.102(b) Bottom Ash Pond Complex Cardinal Plant Brilliant, Ohio September, 2016 Prepared for: Cardinal Operating Company Cardinal Plant Brilliant, Ohio Prepared by: Geotechnical Engineering

More information

As temporary grade control facilities along waterways until final stabilization is established.

As temporary grade control facilities along waterways until final stabilization is established. Check Dams (CD) EC-12 Description Check dams are temporary grade control structures placed in drainage channels to limit the erosivity of stormwater by reducing flow velocity. Check dams are typically

More information

Illinois State Water Survey

Illinois State Water Survey Illinois State Water Survey HYDROLOGY DIVISION SWS Contract Report 508 COMPARISON OF 1987 AND 1989 BED PROFILE SURVEYS OF THE LOWER CACHE RIVER by Richard Allgire Office of Sediment and Wetland Studies

More information

Aalborg Universitet. Published in: Proceedings of Offshore Wind 2007 Conference & Exhibition. Publication date: 2007

Aalborg Universitet. Published in: Proceedings of Offshore Wind 2007 Conference & Exhibition. Publication date: 2007 Aalborg Universitet Design Loads on Platforms on Offshore wind Turbine Foundations with Respect to Vertical Wave Run-up Damsgaard, Mathilde L.; Gravesen, Helge; Andersen, Thomas Lykke Published in: Proceedings

More information

Technical Report Culvert A Hydraulic Analysis

Technical Report Culvert A Hydraulic Analysis DATE: November 3, 2011 Technical Report Culvert A Hydraulic Analysis TO: FROM: RE: Jim Reiser, P.E. Project Manager Parsons Brinckerhoff, Inc. Kurt Killian, P.E., CFM Parsons Brinckerhoff, Inc. Design

More information

SPILLWAY REPLACEMENT PROJECT NUMERICAL AND PHYSICAL MODELING. Kara Hurtig, Water Resources Engineer, Northwest Hydraulic Consultants, BC, Canada

SPILLWAY REPLACEMENT PROJECT NUMERICAL AND PHYSICAL MODELING. Kara Hurtig, Water Resources Engineer, Northwest Hydraulic Consultants, BC, Canada POINTE DU BOIS GENERATING STATION SPILLWAY REPLACEMENT PROJECT NUMERICAL AND PHYSICAL MODELING Kara Hurtig, Water Resources Engineer, Northwest Hydraulic Consultants, BC, Canada David S. Brown, Senior

More information

Row / Distance from centerline, m. Fan side Distance behind spreader, m 0.5. Reference point. Center line

Row / Distance from centerline, m. Fan side Distance behind spreader, m 0.5. Reference point. Center line 1 Standardisation of test method for salt spreader: Air flow experiments Report 7: Effect of crosswind on salt distribution by Jan S. Strøm, Consultant Aarhus University, Engineering Centre Bygholm, Test

More information

HISTORY OF CONSTRUCTION

HISTORY OF CONSTRUCTION HISTORY OF CONSTRUCTION CFR 257.73(c)(1) West Boiler Slag Pond Clifty Creek Plant Madison, Indiana October, 2016 Prepared for: Indiana Kentucky Electric Corporation Prepared by: American Electric Power

More information

ANALYSIS OF THE POSITIVE FORCES EXHIBITING ON THE MOORING LINE OF COMPOSITE-TYPE SEA CAGE

ANALYSIS OF THE POSITIVE FORCES EXHIBITING ON THE MOORING LINE OF COMPOSITE-TYPE SEA CAGE 194 He, W., Li, C.: Analysis of the positive forces exhibiting on ANALYSIS OF THE POSITIVE FORCES EXHIBITING ON THE MOORING LINE OF COMPOSITE-TYPE SEA CAGE Wei He 1* Chunliu Li 2 1 Ocean College, Agricultural

More information

WAVE OVERTOPPING AND RUBBLE MOUND STABILITY UNDER COMBINED LOADING OF WAVES AND CURRENT

WAVE OVERTOPPING AND RUBBLE MOUND STABILITY UNDER COMBINED LOADING OF WAVES AND CURRENT WAVE OVERTOPPING AND RUBBLE MOUND STABILITY UNDER COMBINED LOADING OF WAVES AND CURRENT Sepehr Eslami A. and Marcel R.A. van Gent Coastal structures such as breakwaters are usually studied under wave loading

More information

Earthen Embankments. turning into larger, more costly repairs. The following. The State Dam Safety Program has inspection

Earthen Embankments. turning into larger, more costly repairs. The following. The State Dam Safety Program has inspection TOPIC: COMMON PROBLEMS FOR SMALL DAMS WITH CONCRETE CHANNEL SPILLWAYS The State Dam Safety Program has inspection requirements for state regulated dams. A dam, like any man-made structure, will change

More information

Water Storage for Agriculture

Water Storage for Agriculture Water Storage for Agriculture Ted van der Gulik, P.Eng. Partnership for Water Sustainability in BC Water Storage Options Dam! usually constructed within a watercourse! must follow the dam safety regulation!

More information

Démocratisation des modèles hydrauliques CFD 3D : plusieurs exemples réalisés avec ANSYS CFX

Démocratisation des modèles hydrauliques CFD 3D : plusieurs exemples réalisés avec ANSYS CFX DEMOCRATIZATION OF 3D CFD HYDRAULIC MODELS : SEVERAL EXAMPLES PERFORMED WITH ANSYS CFX Démocratisation des modèles hydrauliques CFD 3D : plusieurs exemples réalisés avec ANSYS CFX Gwenaël CHEVALLET 1,

More information

Chutes Part 2: Synthetic linings

Chutes Part 2: Synthetic linings s Part 2: Synthetic linings DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent [2] [1] s can

More information

SPH applied to coastal engineering problems

SPH applied to coastal engineering problems 2 nd Iberian Workshop Ourense, 3 rd and 4 th December 2015 SPH applied to coastal engineering problems (validating the SPH concept) ALTOMARE, CRESPO, DOMINGUEZ, SUZUKI http://www.flandershydraulicsresearch.be/

More information

Control of Nuclear Gloveboxes and Enclosures Using the No- Moving-Part Vortex Amplifier (VXA)

Control of Nuclear Gloveboxes and Enclosures Using the No- Moving-Part Vortex Amplifier (VXA) Control of Nuclear Gloveboxes and Enclosures Using the No- Moving-Part Vortex Amplifier (VXA) ABSTRACT M.J. Crossley AEA Technology ES. Inc. 1100 Jadwin Ave, Richland, WA 99352, USA This paper describes

More information

INTERACTION BETWEEN WIND-DRIVEN AND BUOYANCY-DRIVEN NATURAL VENTILATION Bo Wang, Foster and Partners, London, UK

INTERACTION BETWEEN WIND-DRIVEN AND BUOYANCY-DRIVEN NATURAL VENTILATION Bo Wang, Foster and Partners, London, UK INTERACTION BETWEEN WIND-DRIVEN AND BUOYANCY-DRIVEN NATURAL VENTILATION Bo Wang, Foster and Partners, London, UK ABSTRACT Ventilation stacks are becoming increasingly common in the design of naturally

More information

Drilling Efficiency Utilizing Coriolis Flow Technology

Drilling Efficiency Utilizing Coriolis Flow Technology Session 12: Drilling Efficiency Utilizing Coriolis Flow Technology Clement Cabanayan Emerson Process Management Abstract Continuous, accurate and reliable measurement of drilling fluid volumes and densities

More information

BILLY BISHOP TORONTO CITY AIRPORT PRELIMINARY RUNWAY DESIGN COASTAL ENGINEERING STUDY

BILLY BISHOP TORONTO CITY AIRPORT PRELIMINARY RUNWAY DESIGN COASTAL ENGINEERING STUDY Bâtiment Infrastructures municipales Transport Industriel Énergie Environnement BILLY BISHOP TORONTO CITY AIRPORT PRELIMINARY RUNWAY DESIGN COASTAL ENGINEERING STUDY N. Guillemette 1, C. Glodowski 1, P.

More information

Figure 1 - Photo of Surveyed Area. Figure 2 - Void Survey Results

Figure 1 - Photo of Surveyed Area. Figure 2 - Void Survey Results We have received the first PRELIMINARY results from several tests (science) conducted on the dam area. Per the engineers they are still refining the depths of the void areas (holes under the concrete areas).

More information

High Frequency Acoustical Propagation and Scattering in Coastal Waters

High Frequency Acoustical Propagation and Scattering in Coastal Waters High Frequency Acoustical Propagation and Scattering in Coastal Waters David M. Farmer Graduate School of Oceanography (educational) University of Rhode Island Narragansett, RI 02882 phone: (401) 874-6222

More information

A Depletion Compensated Wet Bath Simulator For Calibrating Evidential Breath Alcohol Analyzers

A Depletion Compensated Wet Bath Simulator For Calibrating Evidential Breath Alcohol Analyzers A Depletion Compensated Wet Bath Simulator For Calibrating Evidential Breath Alcohol Analyzers Slemeyer, A. University of Applied Sciences of Giessen, Dept. of Electrical Engineering 1 Wiesenstr. 14, D-35390

More information

Compaction, Permeability, and Fluid Flow in Brent-type Reservoirs Under Depletion and Pressure Blowdown

Compaction, Permeability, and Fluid Flow in Brent-type Reservoirs Under Depletion and Pressure Blowdown Compaction, Permeability, and Fluid Flow in Brent-type Reservoirs Under Depletion and Pressure Blowdown by Øystein Pettersen, CIPR CIPR Technology Seminar 2010 Outline Experimental & Field Observations

More information

LABORATORY EXPERIMENTS ON WAVE OVERTOPPING OVER SMOOTH AND STEPPED GENTLE SLOPE SEAWALLS

LABORATORY EXPERIMENTS ON WAVE OVERTOPPING OVER SMOOTH AND STEPPED GENTLE SLOPE SEAWALLS Asian and Pacific Coasts 23 LABORATORY EXPERIMENTS ON WAVE OVERTOPPING OVER SMOOTH AND STEPPED GENTLE SLOPE SEAWALLS Takayuki Suzuki 1, Masashi Tanaka 2 and Akio Okayasu 3 Wave overtopping on gentle slope

More information

BURIAL OF INSTRUMENTED CYLINDERS IN THE SINGAPORE STRAIT

BURIAL OF INSTRUMENTED CYLINDERS IN THE SINGAPORE STRAIT BURIAL OF INSTRUMENTED CYLINDERS IN THE SINGAPORE STRAIT Michael D. Richardson a, Karanam A.P. Roopsekhar b, Eng Soon Chan b, Edward F. Braithwaite a, Monty Spearman a, Paul A. Elmore a, and Shen Linwei

More information

TECHNICAL MEMORANDUM 002 EMORANNO. 001

TECHNICAL MEMORANDUM 002 EMORANNO. 001 TECHNICAL MEMORANDUM 002 EMORANNO. 001 To: Jack Synder, P.E. EES Consulting From: Mort McMillen, P.E. Paul Larson, SE Date: October 13, 2010 Project: Cc: Taylor Bowen Subject: Technical Memorandum (TM)

More information

SUMMARY OF THE EXPERIMENTAL STUDIES OF COLD HELIUM PROPAGATION ALONG A SCALE MODEL OF THE LHC TUNNEL

SUMMARY OF THE EXPERIMENTAL STUDIES OF COLD HELIUM PROPAGATION ALONG A SCALE MODEL OF THE LHC TUNNEL EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 684 SUMMARY OF THE EXPERIMENTAL STUDIES OF COLD HELIUM PROPAGATION ALONG

More information

VW Liquid Settlement System VWLSS-200

VW Liquid Settlement System VWLSS-200 DATASHEET VW Liquid Settlement System VWLSS-200 The Geosense VWLSS-200 Vibrating Wire Liquid Settlement System is used to monitor settlement or heave in soils and other structures such as embankments,

More information

Suitable Applications Check dams may be appropriate in the following situations: To promote sedimentation behind the dam.

Suitable Applications Check dams may be appropriate in the following situations: To promote sedimentation behind the dam. Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category

More information

Door County, WI Coastal Hazard Analysis Flood Risk Review Meeting. August 21, 2017

Door County, WI Coastal Hazard Analysis Flood Risk Review Meeting. August 21, 2017 Door County, WI Coastal Hazard Analysis Flood Risk Review Meeting August 21, 2017 Agenda Introductions Coastal Flood Risk Study and Mapping Program Current Status Technical Overview of Study and Mapping

More information

Physical Model Study of the San Antonio River Lock System

Physical Model Study of the San Antonio River Lock System ST. ANTHONY FALLS LABORATORY Engineering, Environmental and Geophysical Fluid Dynamics PROJECT REPORT 471 Physical Model Study of the San Antonio River Lock System By Omid Mohseni, Richard Christopher,

More information

Measuring Discharge in Shallower Rivers: ADCPs go from Rio to Pro

Measuring Discharge in Shallower Rivers: ADCPs go from Rio to Pro Measuring Discharge in Shallower Rivers: ADCPs go from Rio to Pro River monitoring supports many different activities from determining water reserves to designing flood defenses, and even to sports / leisure

More information

High Frequency Acoustical Propagation and Scattering in Coastal Waters

High Frequency Acoustical Propagation and Scattering in Coastal Waters High Frequency Acoustical Propagation and Scattering in Coastal Waters David M. Farmer Graduate School of Oceanography (educational) University of Rhode Island Narragansett, RI 02882 Phone: (401) 874-6222

More information

APPLICANT: Pacific Northwest National Laboratory Attention: Mr. Charles Brandt 1529 West Sequim Bay Road Sequim, Washington 98382

APPLICANT: Pacific Northwest National Laboratory Attention: Mr. Charles Brandt 1529 West Sequim Bay Road Sequim, Washington 98382 US Army Corps of Engineers Seattle District Joint Public Notice Application for a Department of the Army Permit and a Washington Department of Ecology Water Quality Certification and/or Coastal Zone Management

More information

FROTH: Fundamentals and Reliability of Offshore Structure Hydrodynamics EPSRC

FROTH: Fundamentals and Reliability of Offshore Structure Hydrodynamics EPSRC FROTH: Fundamentals and Reliability of Offshore Structure Hydrodynamics EPSRC 2012-2015 Drop Tests: experiments and numerical modelling T. Mai, D. Greaves & A. Raby School of Marine Science and Engineering

More information

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland Abstract Flooding, cleaning, gauging, dewatering and venting of offshore oil and gas pipelines

More information

APPLICATION NOTE. AN-9608 July 2001 SEEPAGE MEASUREMENT IN AN OPEN CHANNEL THROUGH A WEIR

APPLICATION NOTE. AN-9608 July 2001 SEEPAGE MEASUREMENT IN AN OPEN CHANNEL THROUGH A WEIR APPLICATION NOTE AN-9608 July 2001 SEEPAGE MEASUREMENT IN AN OPEN CHANNEL THROUGH A WEIR 1 Introduction Seepage of water through, around or under a dam is expected in all embankment dams and even in concrete

More information

Historic dam failures and recent incidents. Tracey Williamson Associate Director Water (Dams & Reservoirs) British Dam Society Chairman

Historic dam failures and recent incidents. Tracey Williamson Associate Director Water (Dams & Reservoirs) British Dam Society Chairman Historic dam failures and recent incidents Tracey Williamson Associate Director Water (Dams & Reservoirs) British Dam Society Chairman 1 Agenda 1. Dams in all their beauty 2. Hazards associated with dams

More information

Northern Indiana Public Service Company Michigan City Generating Station Primary Settling Pond Number Annual RCRA CCR Unit Inspection Report

Northern Indiana Public Service Company Michigan City Generating Station Primary Settling Pond Number Annual RCRA CCR Unit Inspection Report REPORT Northern Indiana Public Service Company Michigan City Generating Station Primary Settling Pond Number 2 2018 Annual RCRA CCR Unit Inspection Report Submitted to: Northern Indiana Public Service

More information

Remote sensing standards: their current status and significance for offshore projects

Remote sensing standards: their current status and significance for offshore projects Remote sensing standards: their current status and significance for offshore projects Peter J M Clive Technical Development Consultant SgurrEnergy Ltd 225 Bath Street Glasgow G2 4GZ E: peter.clive@sgurrenergy.com

More information

Stormy Phillips BASICS OF LEASE AUTOMATIC CUSTODY TRANSFER (LACT) SYSTEMS

Stormy Phillips BASICS OF LEASE AUTOMATIC CUSTODY TRANSFER (LACT) SYSTEMS Stormy Phillips BASICS OF LEASE AUTOMATIC CUSTODY TRANSFER (LACT) SYSTEMS Why is Stormy Walking Funny?? What is a LACT system? Introduction A LACT unit is a group of equipment designed specifically for

More information

Sontek RiverSurveyor Test Plan Prepared by David S. Mueller, OSW February 20, 2004

Sontek RiverSurveyor Test Plan Prepared by David S. Mueller, OSW February 20, 2004 Sontek RiverSurveyor Test Plan Prepared by David S. Mueller, OSW February 20, 2004 INTRODUCTION Sontek/YSI has introduced new firmware and software for their RiverSurveyor product line. Firmware changes

More information

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply 4.1.1 General The primary function of a system for handling fuel oil is to transfer oil from the storage tank to the oil burner at specified conditions

More information

APPENDIX J HYDROLOGY AND WATER QUALITY

APPENDIX J HYDROLOGY AND WATER QUALITY APPENDIX J HYDROLOGY AND WATER QUALITY J-1 Technical Report on Airport Drainage, Northern Sector Airport and Ordinance Creek Watershed / Preliminary Creek Constructed Natural Channel Culvert J-2 Preliminary

More information

INTRODUCTION TO COASTAL ENGINEERING

INTRODUCTION TO COASTAL ENGINEERING The University of the West Indies Organization of American States PROFESSIONAL DEVELOPMENT PROGRAMME: COASTAL INFRASTRUCTURE DESIGN, CONSTRUCTION AND MAINTENANCE A COURSE IN COASTAL DEFENSE SYSTEMS I CHAPTER

More information

PROPOSING A NEW PORTABLE DEVICE FOR BRIDGE SCOUR INSPECTION

PROPOSING A NEW PORTABLE DEVICE FOR BRIDGE SCOUR INSPECTION PROPOSING A NEW PORTABLE DEVICE FOR BRIDGE SCOUR INSPECTION KISEOK KWAK Senior Researcher, Geotech. Eng. Res. Dept., Korea Institute of Construction Technology, 2311 Daehwa-dong, Ilsan-gu, Koyang City,

More information

Installation Operation Maintenance. Bermad Level Control Valve with Modulating Horizontal Float Pilot valve One Way Flow IOM.

Installation Operation Maintenance. Bermad Level Control Valve with Modulating Horizontal Float Pilot valve One Way Flow IOM. Bermad Level Control Valve with Modulating Horizontal Float Pilot valve One Way Flow Model: FP 450-80 Installation Operation Maintenance PAGE 1 OF 5 1. Safety First BERMAD believes that the safety of personnel

More information

Full scale VIV response measurements of a drill pipe in Gulf of Mexico loop currents (OMAE )

Full scale VIV response measurements of a drill pipe in Gulf of Mexico loop currents (OMAE ) Full scale VIV response measurements of a drill pipe in Gulf of Mexico loop currents (OMAE2008-57610) Beynet, Shilling, Campbell, Tellier, Howells Estoril Portugal - June 2008 The Test September 2004 Test

More information

St. Louis County, MN Coastal Hazard Analysis Flood Risk Review Meeting. May 2, 2018

St. Louis County, MN Coastal Hazard Analysis Flood Risk Review Meeting. May 2, 2018 St. Louis County, MN Coastal Hazard Analysis Flood Risk Review Meeting May 2, 2018 Agenda Introductions Coastal Flood Risk Study and Mapping Program Current Status Technical Overview of Study and Mapping

More information

A Computational Assessment of Gas Jets in a Bubbly Co-Flow 1

A Computational Assessment of Gas Jets in a Bubbly Co-Flow 1 A Computational Assessment of Gas Jets in a Bubbly Co-Flow 1 Melissa Fronzeo*, 1 Michael Kinzel 1 The Pennsylvania State University, University Park, PA, USA Abstract In this effort, Computational Fluid

More information

Acoustic Focusing in Shallow Water and Bubble Radiation Effects

Acoustic Focusing in Shallow Water and Bubble Radiation Effects Acoustic Focusing in Shallow Water and Bubble Radiation Effects Grant B. Deane Marine Physical Laboratory, Scripps Institution of Oceanography UCSD, La Jolla, CA 92093-0238 Phone: (858) 534-0536 fax: (858)

More information

Vehicle- or rack-mounted liquefied gas meters, pump supplied

Vehicle- or rack-mounted liquefied gas meters, pump supplied Purpose This inspection procedure outline (IPO) defines the minimum tests which must be performed to ensure that basic volumetric measuring devices comply with the legislation. Application Rack/fixed metering

More information

CHAPTER 5 CULVERT DESIGN

CHAPTER 5 CULVERT DESIGN CHAPTER 5 CULVERT DESIGN HYDRAULICS OF CULVERTS There are two major types of culvert flow: 1) flow with inlet control, and 2) flow with outlet control. For each type, different factors and formulas are

More information

HEC 26 Aquatic Organism Passage Design Manual Evolution & Application

HEC 26 Aquatic Organism Passage Design Manual Evolution & Application HEC 26 Aquatic Organism Passage Design Manual Evolution & Application Sven Leon, P.E., Hydraulics Engineer Federal Highway Administration 2015 Alaska Fish Passage Meeting October 13 14, 2015 VTRC, Juneau,

More information

Annex E Bridge Pier Protection Plan

Annex E Bridge Pier Protection Plan Annex E Bridge Pier Protection Plan Table E1 Bridge Types and Locations Table E2 Flow Conditions For River Sections Figure E1 Bridge Abutment Protection Figure E2 Bridge Pier Protection Figure E3 Central

More information

Effect of Fluid Density and Temperature on Discharge Coefficient of Ogee Spillways Using Physical Models

Effect of Fluid Density and Temperature on Discharge Coefficient of Ogee Spillways Using Physical Models RESEARCH ARTICLE Effect of Fluid Density and Temperature on Discharge Coefficient of Ogee Spillways Using Physical Models M. SREENIVASULU REDDY 1 DR Y. RAMALINGA REDDY 2 Assistant Professor, School of

More information

Low-crested offshore breakwaters: a functional tool for beach management

Low-crested offshore breakwaters: a functional tool for beach management Environmental Problems in Coastal Regions VI 237 Low-crested offshore breakwaters: a functional tool for beach management K. Spyropoulos & E. Andrianis TRITON Consulting Engineers, Greece Abstract Beach

More information

Pneumatic blending in a bin or silo that is, aerating. Saving time, labor, and money with pneumatic batch blending

Pneumatic blending in a bin or silo that is, aerating. Saving time, labor, and money with pneumatic batch blending As appeared in January 2013 PBE www.powderbulk.com Saving time, labor, and money with pneumatic batch blending Mike Weyandt Nol-Tec Systems With a pneumatic blender, you can mix batches of dry bulk materials

More information

INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 3, No 1, 2012

INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 3, No 1, 2012 INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 3, No 1, 2012 Copyright by the authors - Licensee IPA- Under Creative Commons license 3.0 Research article ISSN 0976 4399 ABSTRACT Scour

More information

RISK AND STANDARDS BASED APPROACH TO RIP RAP DESIGN ALTERNATIVES FOR GRAHAMSTOWN DAM STAGE 2 AUGMENTATION

RISK AND STANDARDS BASED APPROACH TO RIP RAP DESIGN ALTERNATIVES FOR GRAHAMSTOWN DAM STAGE 2 AUGMENTATION RISK AND STANDARDS BASED APPROACH TO RIP RAP DESIGN ALTERNATIVES FOR GRAHAMSTOWN DAM STAGE 2 AUGMENTATION M. B. Barker 1 and D. Holroyde 2 ABSTRACT. A detailed study was completed for the Stage 2 works

More information

Structure Failure Modes

Structure Failure Modes US Army Corps Monitoring and Maintenance of Coastal Infrastructure Structure Failure Modes Steven A. Hughes, PhD, PE Coastal and Hydraulics Laboratory US Army Engineer Research and Development Center Waterways

More information

Bayfield & Ashland Counties, WI Coastal Hazard Analysis Flood Risk Review Meeting. June 05, 2018

Bayfield & Ashland Counties, WI Coastal Hazard Analysis Flood Risk Review Meeting. June 05, 2018 Bayfield & Ashland Counties, WI Coastal Hazard Analysis Flood Risk Review Meeting June 05, 2018 Agenda Introductions Coastal Flood Risk Study and Mapping Program Current Status Technical Overview of Study

More information

Project to Refine a Prototype Unmanned, Tethered ADCP Platform for Measuring Streamflow

Project to Refine a Prototype Unmanned, Tethered ADCP Platform for Measuring Streamflow Pagina 1 di 5 Project to Refine a Prototype Unmanned, Tethered ADCP Platform for Measuring Streamflow The use of trade, firm, or product names is for descriptive purposes only and does not imply endorsement

More information

Pneumatic blending in a bin or silo that is, aerating. Saving time, labor, and money with pneumatic batch blending. Copyright CSC Publishing

Pneumatic blending in a bin or silo that is, aerating. Saving time, labor, and money with pneumatic batch blending. Copyright CSC Publishing As appeared in January 2013 PBE Copyright CSC Publishing www.powderbulk.com Saving time, labor, and money with pneumatic batch blending Mike Weyandt Nol-Tec Systems With a pneumatic blender, you can mix

More information

Waves, Bubbles, Noise, and Underwater Communications

Waves, Bubbles, Noise, and Underwater Communications Waves, Bubbles, Noise, and Underwater Communications Grant B. Deane Marine Physical Laboratory, Scripps Institution of Oceanography UCSD, La Jolla, CA 92093-0238 phone: (858) 534-0536 fax: (858) 534-7641

More information

EXAMINATION OF AE WAVE PROPAGATION ROUTES IN A SMALL MODEL TANK

EXAMINATION OF AE WAVE PROPAGATION ROUTES IN A SMALL MODEL TANK EXAMINATION OF AE WAVE PROPAGATION ROUTES IN A SMALL MODEL TANK HIDEYUKI NAKAMURA 1, TAKAHIRO ARAKAWA 2, MINORU YAMADA 3 1) System Divisions, Ishikawajima Inspection & Instrumentation Co., 1720 Kamai,

More information

Bay County, MI Coastal Hazard Analysis Flood Risk Review Meeting. May 14, 2018

Bay County, MI Coastal Hazard Analysis Flood Risk Review Meeting. May 14, 2018 Bay County, MI Coastal Hazard Analysis Flood Risk Review Meeting May 14, 2018 Agenda Introductions Coastal Flood Risk Study and Mapping Program Current Status Technical Overview of Study and Mapping Floodplain

More information

Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop San Antonio, Texas Project No

Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop San Antonio, Texas Project No October 17, 2016 Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop 100406 San Antonio, Texas 78296 Project No. 0352436 Subject: Compilation of Construction History Calaveras Power Station San

More information

Profile LFR-43 HELENA ITALY. Italian National Agency for New Technologies, Energy and Sustainable Economic Development, C.R. ENEA Brasimone, Italy

Profile LFR-43 HELENA ITALY. Italian National Agency for New Technologies, Energy and Sustainable Economic Development, C.R. ENEA Brasimone, Italy Profile LFR-43 HELENA ITALY GENERAL INFORMATION NAME OF THE FACILITY ACRONYM COOLANT(S) OF THE FACILITY LOCATION (address): OPERATOR CONTACT PERSON (name, address, institute, function, telephone, email):

More information

THE WAVE OVERTOPPING SIMULATOR IN ACTION

THE WAVE OVERTOPPING SIMULATOR IN ACTION THE WAVE OVERTOPPING SIMULATOR IN ACTION Jentsje W. van der Meer 1, Patrizia Bernardini 2, Gosse Jan Steendam 3, Gert Jan Akkerman 4 and Gijs Hoffmans 5 The wave overtopping simulator is a device which

More information