1 Cruise Plan, Alford IWISE leg, June 10-20, 2011 version 2; dated 5/20/2011 Overview/Objectives The following is the updated cruise plan for the mooring deployment leg (6/10-6/20) of the Internal Waves in Straits Experiment (IWISE) project. We will be working between Taiwan and the Philippines (Figure 1). Our general plan is to deploy moorings, gliders and PIES, recover 4 PIES that were previously deployed, and then to use any time remaining to work around the moorings with a series of 36-hour-long yo-yo CTD/lowered ADCP stations while they profile P7 P lat 20.5 N1 N2 MPN P8 P10 A1 P P9 P MPS S7S6 S lon 3000 Figure 1: Broad view of our work area and moorings to be deployed. The 8 moorings are in red; the 7 PIES are in yellow. Not shown are m thermistor chain moorings (T1-T4) to be deployed near N2. Selected Philippines 12-nm limits are shown. Our objectives are Deploy a total of 12 moorings and 7 PIES at the locations shown (Figure 1). All assets will be recovered at a later date (most from the Alford IWISE leg on Revelle, 8/4/2011-8/11/2011. Recover four PIES that we deployed last summer (locations near P10, P11, 12 and P13). 1
2 Deploy two gliders near N1. Use remainder of time doing 36-hour yo-yo CTD stations while holding station at locations TBD, probably near A1. Table 1: IWISE 2011 Moorings. All positions are given in decimal degrees. After deployment, please maintain 0.25 nm radius from all moorings. Station Lat Lon Depth Comments MPS N E 3696m profiling moorings S N E 1837m S E 1822m S E 2233m N N E 2040m N N E 1830m MPN N E 3653m A N E 1450m stablemoor float T N m 1000-m T-chain moorings; 2 km W of N2 T N m 1 km W of N2 T N m 1 km E of N2 T N m 2 km E of N2 P N E PIES P N E P N E P N E P N E P N E P N E Loadout We ll begin loading at 0800 on Gordon s demob day (6/7) as his offload is small. He has agreed to this plan, but of course if he winds up needing the day we will wait. We ll complete the loadout on 6/8 and 6/9. We have two 40 containers and two 20 containers that should be there by that time, as well as a few smaller air shipments. Our basic plan is to unload the containers onto the dock and begin prepping instruments and spheres dockside while the ship begins to crane the other gear on board. We ll install all instruments into our syntactic spheres prior to loading since accessing them will be more difficult on deck. Deck Plan The proposed deck plan is shown in Figure 2. Notably, there will be about floats, and 12 anchor stacks (4-5 wheels each). Also, in addition to the TSE winch we will have a traction winch on 2
3 loan from R/V Wecoma. The traction winch will be our primary winch for the deployments, with the TSE as a backup. The two 20 vans on the main deck will house glass floats for our moorings and deck storage. We ll be primarily based in the main lab. Gear Profiling moorings We will deploy seven profiling moorings (Figure 1, red), which consist of one or two crawlers making repeated traverses of a taut vertical wire with two subsurface floats (one steel, one syntactic foam) for flotation. These (and all moorings deployed on the cruise) are anchor last deployments. We will be using a traction winch on loan from OSU/Wecoma, and will launch the anchors with the trawl wire. A sample mooring diagram is given in Figure 3. T-chain moorings Four 1000-m-long subsurface T-chain moorings will be deployed in the vicinity of N2. See Figure 4 for a diagram. The others are nearly identical. Inverted Echo Sounder with Pressure (PIES) Seven PIES (Figure 5) will be deployed at the locations shown (Figure 1, yellow). These are very simple deployments. We will simply lower them over the side to the waterline and release them with a mechanical release. They then sink to the bottom, which takes about an hour. We will also recover four PIES that we deployed last summer (locations near P10, P11, 12 and P13). Stablemoor mooring Mooring A-1 features a stablemoor by Flotec, a 16-foot-long syntactic torpedo-shaped float (Figure 6). Other than its size which will require care in deployment, and the heavy weight of the anchor (7800#), it is a standard mooring. Figure 7 shows the mooring diagram. Gliders Two gliders will be launched during our cruise near N1. These are very simple procedures and should only take an hour or so. CTD/lowered ADCP stations After the deployments (time allowing) we plan to conduct several continuous 36-hour yoyo time series, as well as others to be determined based on the results of these initial ones. Please note we would like to do these, conditions permitting, within 10 of the bottom. At times when working on a slope this depth will be deeper than the water depth beneath the ship. We would like to slow to 30 m/minute 100 m above the bottom, and continue to 10 meters above the bottom at this speed and not slower. We want to work with the restechs to come up with a compromise that will ensure the safety of the rosette and allow us to accomplish our science goals, which require repeated measurements close to the bottom. 3
4 The CTD will be fitted with a lowered ADCP system. We plan on using the ship s brackets (the restech is already aware of this) and upward and downward 300-KHz workhorse ADCP s and a battery pack to the CTD frame. We will also likely attach a vane to allow special microstructure sensors on the package to face the flow past the cage as we did last August in the pilot (see Figure 8). We plan to use the SIO serial uplink CTD to send ADCP data up the wire, with the normal system as a backup. Timeline The primary goal is to get the moorings in the water, so we will work as quickly as safely possible. We ll rely on Meghan to tell us when we are working her too hard! A strawman order of events assuming all deployments go smoothly is given below. If things go slower than this then the 3.75 days of CTD yoyo work will be reduced. Table 2: Timeline. Date/Time What Comments 6/ depart KS 6/ arrive P11 recover PIES, deploy PIES 6/ arrive A1 deploy A1 6/ arrive MPN Deploy MPN 6/ arrive P10 Recover PIES, deploy PIES 6/ arrive N2 Deploy N2, T1, T2, T3, T4, N1 6/ finish above deploy P8 6/ arrive P9 deploy PIES 6/ arrive MPS Deploy MPS, S7 6/ arrive S6 Deploy S6, S9 6/ arrive P12 recover PIES, deploy PIES 6/ arrive P13 recover PIES, deploy PIES 6/ return to A1 Begin CTD yoyos 6/ arrive N1 deploy gliders 6/ depart for KS deploy P7 on way home 6/ arrive KS Personnel Science party and affiliations are as follows listed in Table 3. Note David Black (SIOglider tech) will be present for the loadout but will not sail, so please add him to the security lists so he can get a badge. 4
5 Table 3: Science Personnel. Who Role Inst. Matthew Alford Chief Scientist APL/UW Andy Pickering Grad Student APL/UW Zoe Parsons Technician APL/UW Eric Boget Engineer APL/UW Paul Aguilar Engineer APL/UW John Mickett Oceanographer APL/UW Jonathan Nash PI OSU Amy Waterhouse postdoc SIO Ke-Hsien Fu student NSYSU Chung-Wei Lu student NSYSU Val Borja clearance observer Philippines 5
6 5 PIES STANDS 5 5 ANCHORS JN capstain TSE winch ft container SPOOLS 20-ft container stablemoor traction winch spooler cast ANCHORS wire cage wire cage Mooring Gear Box wire cage wire cage wire cage Figure 2: Deck plan. 6
7 Top of float (60m depth) Flotec / Longranger (300m depth) IWISE S Thermister Chain (240m) Target: Actual: 'N 'E Depth: 2233m Depth: m m m m m m m m (2) 1/2 shackle 1/2 sling link (1) 1/2" shackle 1/2 Long link chain (2m) (1)1/2" shackle (1) (1) 5/8" shackle (1) 5/8" shackle (1) (1) 1/2 shackle 1/2 Long link chain (1m) (1) 5/8" shackle (1) 5/8" shackle 1/2 Long link chain (2m) (1) 5/8" shackles 3 ton swivel (1) (1) 1/2" shackle MP stopper ARGOS Beacon O.M.L. model 265 / Flasher S ARGOS ID# Beep? ARGOS On Time: ? Flasher On Time: Flash? ADCP model RDI 75Khz Long Ranger w/press. (Depth 300m) Start Time: Pinging? 45" Syntactic Foam Float 261 kg buoyancy (1500m) 5/16" 3x19 PP jacket wire rope (7m; 1.49kg) " Syntactic Foam Float kg buoyancy MP stopper (Depth 317m) Moored Profiler (s/n H1) Profile Range: MP Set-up: MP Start Time/Date: Line out: 0.393" PP jacket cortland line (1900m; 59.45kg 1881m cut) MP stopper (Depth m) 967.5m MP stopper MP stopper (Depth m) 966.5m MP stopper Moored Profiler (s/n H2) Profile Range: MP Set-up: MP Start Time/Date: Line out: MP stopper (Depth 2215m) 18.0m MP stopper SBE 37 MicroCat (Depth 2216m; 2.3 kg) Start time: 17.0m 16.0m 11.0m 9.5m (1) 1/2" shackle (1) (1) 1/2 shackle (1) 1/2" shackle 0.5m LL chain (1) (5) 1/2" shackle (3) 5/8" shackle (2) 3 links LL chain Drop link chain 5/8" shackle & 5" ring (8) Benthos model V glass floats (25.4 kg buoy. ea.) mounted in pairs on ½" long link chain (1m; 2.76 kg) SBE39 Temp. ext. w/press.; Att. to rel. (Depth 2222m; 0.70 kg) Logging? Start time: Benthos model 865 double acoustic release (25 kg each) Enable: Release: 1/2 Long link chain (1.5m) RX(khz): TX(khz): 8.0m (1) 3/4" shackle 3.0m 3/4 dia. Nylon line (5m) (1) 3/4" shackle (1) (1) 5/8" shackle 1/2 Long link chain (2m) (3) 5/8" shackle (2) 3 links LL chain 5 wheel RX(khz): Enable: TX(khz): Release: 1632 kg anchor plus Danforth (1420 kg in water) Start Deploy: Drop Anchor: Date: Time: Wind Dir / Spd: 7 Date: Time: Hdg / Spd: Figure 3: Mooring diagram for S9, a typical profiling mooring.
8 IWISE JN T-CHAIN #1 MOORING 2011 Target: 'N 'E Depth: 1594m Actual: Depth: m Top of float (571m depth) 1" shackle 5/8" shackle 3 ton swivel (2) 5/8" shackle m 60# lead strongback 5/8" shackle 1/2" shackle 1/2 Long link chain (1/2m) m m (2) 1/2" shackle (2) 1/2" shackle " Syntactic Foam Float kg buoyancy ARGOS ID# Flasher On Time: Beep / ? Flash? SBE 37 MicroCat (Depth 575m; 2.3 kg) Start time: SBE56 Temperature Logger Serial # Depth Distance Deploy Time 3/8" aramid line - Harper (1000m; 10.4kg) (4) Benthos model V glass floats (25.4 kg buoy. ea.) mounted in pairs on ½" long link chain (1m; 2.76 kg) 18.0m 16.0m (1) (3) 1/2" shackle (3) 5/8" shackle (2) 3 links LL chain ORE Acoustic Release model 8242XS (28 kg each) Enable: Release: Disable: Int (khz): 11 Rep (khz): m 13.0m Drop link chain 5/8" shackle & 5" ring 1/2 Long link chain (1.5m) 5/8" shackle 3/4 dia. Nylon line (10m) Enable: Release: Disable: Int (khz): 11 Rep (khz): m 1.0m (2) 5/8" shackle 5/8 sling link 1/2 Long link chain (2m) (3) 5/8" shackle (2) 3 links LL chain 4 wheel 1590 kg anchor plus Danforth (1384 kg in water) Start Deploy: Date: Time: Wind Dir / Spd: Drop Anchor: Date: Time: Hdg / Spd: 8 Figure 4: Mooring diagram for moorings T1-T4, to be deployed near N2.
9 Figure 5: A PIES ready for deployment. Figure 6: Stablemoor being deployed from R/V Wecoma. 9
10 IWISE JN STABLE MOORING 2011 Target: Depth: Actual: xx -xx.xxx'n xxx -xx.xxx'e Depth: 1447m m Top of float (80m depth) 45" Syntactic Foam Float 309 kg buoyancy (JN) ARGOS ID# Beep? ARGOS On Time: ? m (2) 1/2 316 shackle 0.5m x 1/2" 316 chain 1/2 316 shackle 1/2 shackle 1/2 shackle Flasher On Time: Flash? ADCP model RDI 300Khz Workhorse w/press. (Depth 80m) Start Time: Pinging? Cover? 3/8" aramid line - Harper (235m; 0.6kg 233m cut length) m m (2) 1/2" shackle (2) 1/2" shackle SBE 37 MicroCat (Depth 319m; 2.3 kg) Start time: 3/8" aramid line - Harper (235m; 0.6kg 233m cut length) Chipod OSU deep (Depth???m; 1.0kg) 893.0m (2) 1/2" shackle 5/16" 3x19 PP shakedown jacket wire rope (150m; 31.9kg) Chipod OSU deep (Depth???m; 1.0kg) Stablemoor 1500 Syntactic Foam Float 765 kg buoyancy (JN) SABLE ID# ? 743.0m 1/2" shackle 5/8" shackle Flasher On Time: UP - ADCP RDI 75Khz Long Ranger w/press. (Depth 705m) Start Time: Flash? Pinging? 740.0m (2) 5/8" shackles 3 ton swivel (2) 5/8" shackle 60# lead strongback (2) 5/8" shackle DN - ADCP RDI 75Khz Long Ranger w/press. (Depth 706m) Start Time: Pinging? SBE 37 MicroCat (Depth 705m; 2.3 kg) Start time: 5/16" 3x19 PP shakedown jacket wire rope (520m; 110.7kg) 220m (1) (2) 5/8" shackle 3/8" aramid line - Harper (190m; 2.0kg 188m cut length) (8) Benthos model V glass floats (25.4 kg buoy. ea.) mounted in pairs on ½" long link chain (1m; 2.76 kg) ORE Acoustic Release model 8242XS (28 kg each) 30.0m (1) (5) 5/8" shackle 8 8 Enable: Release: 26.0m (3) 5/8" shackle (2) 3 links LL chain 8 8 Disable: Int (khz): 11 Rep (khz): m Drop link chain 3/4" shackle & 5" ring Enable: Release: 23.0m 1/2 Long link chain (1.5m) 3/4" shackle Disable: Int (khz): 11 Rep (khz): 12 1 dia. Nylon line (20m) 3.0m (2) 3/4" shackle 3/4 sling link 1/2 Long link chain (2m) 7800# cast anchor 1.0m 3/4" shackle Mace Start Deploy: Date: Time: Wind Dir / Spd: Drop Anchor: Date: Time: Hdg / Spd: 10 Figure 7: Mooring diagram for the Stablemoor (A1).
11 Figure 8: The CTD system as configured on our Revelle cruise last August. 11
Cruise Plan for QPE (R/V Revelle Sept/ 12-16, 2009)
Cruise Plan for QPE (R/V Revelle Sept/ 12-16, 2009) Objectives In this cruise we will recover six subsurface ADCP/TC moorings (Lien), five restrained ADCP (Centurioni), and perform shipboard ADCP, Revelle
More informationRR10106 Cruise Plan ITOP Mooring Recovery and PhilSea10 Seaglider Operation (R/V Revelle November 6-26, 2010)
RR10106 Cruise Plan ITOP Mooring Recovery and PhilSea10 Seaglider Operation (R/V Revelle November 6-26, 2010) Chief Scientist: Ren-Chieh Lien, Applied Physics Lab, University of Washington Co-Chief Scientist:
More informationDraft of OKMC Cruise Plan (R/V Revelle June 1-14, 2012 RR1205)
Draft of OKMC Cruise Plan (R/V Revelle June 1-14, 2012 RR1205) Ren-Chieh Lien and Thomas B Sanford 1. Objectives In the RR1205 cruise, we will deploy five subsurface moorings, one surface mooring (TBD),
More informationApplication for Consent to Conduct Marine Scientific Research. F Internal Waves in Straits (IWISE) Institution Contact Information Director
1. General Information 1.1 Reference ID: Application for Consent to Conduct Marine Scientific Research Application number: Project name: F2010-111 Internal Waves in Straits (IWISE) 1.2 Sponsoring institution(s):
More information1 Module A (uniform topography) survey lines Module B (topographic wake) survey lines Module C (submesoscale soup) survey lines...
..................................................................................... point Sal Coastal circulation Experiment (SCoNE) / SP1723 CRUISE PLAN ANDRÉ PALÓCZY R/V Robert Gordon Sproul, September/10
More informationINSTANT. Makassar Mooring Deployments Baruna Jaya I January 14-20, Mooring diagrams, component lists, release codes, and triangulation data
Makaar Mooring Deployment January 14-20, 2004 Mooring diagram, component lit, releae code, and triangulation data Prepared by Bruce Huber Lamont-Doherty Earth Obervatory MAK Eat Initial Deployment Date:
More informationARG Mooring Deployment
ARG Mooring Deployment The acoustic releases are lifted over the stern during the mooring deployment. The mooring deployment was scheduled for early November as the rainy season in southwestern Greece
More informationNoise Experiment #2. Marine Physical Laboratory Scripps Institution of Oceanography La Jolla, CA February 22 February 2010
Noise Experiment #2 Marine Physical Laboratory Scripps Institution of Oceanography La Jolla, CA 92093-0701 16 February 22 February 2010 1. Objective The objective of the noise experiment is to observe
More informationCMORE HOE DYLAN October 2012 Draft cruise plan
CMORE HOE DYLAN 11 1 4 October 2012 Draft cruise plan Cruise ID: KM12-21 Vessel: R/V KILO MOANA University of Hawaii Master of the Vessel: Captain Gray Drewry Chief Scientist: Tara Clemente (UH) OTG Marine
More informationWHOTS Mooring Subsurface Instrumentation
UH Contributions to WHOTS-13 Cruise Report by Fernando Santiago-Mandujano, Daniel McCoy, Jefrey Snyder, R. Walter Deppe, Kellen Rosburg, Glenn Carter, Katrina Berry, and Roger Lukas WHOTS Mooring Subsurface
More informationCB-40 Data Buoy Quick Start Guide
CB-40 Data Buoy Quick Start Guide The NexSens CB-40 Data Buoy offers a compact and affordable platform for deploying water quality sondes and other instruments that integrate power and data logging. The
More informationR/V Point Sur Pre-Cruise Questionnaire
R/V Point Sur Pre-Cruise Questionnaire Please fill this out and return at least 40 days prior to your cruise to ensure that all of your technical needs can be met BASIC INFO Purpose of Cruise: Submitter's
More informationvoyageplan SS Itinerary Principal Investigator(s) RV Southern Surveyor program
2008 RV Southern Surveyor program voyageplan SS04-2008 RESEARCH CHARTER Deep-Ocean Tsunami Detection Buoy (DART) Scheduled Maintenance Replacement for the Australian Tsunami Warning System (ATWS) Itinerary
More informationRV Southern Surveyor program
2011 RV Southern Surveyor program voyageplan SS2011_c01 Tsunami Detection Buoy Maintenance for Australian Tsunami Warning System (ATWS) Itinerary Mobilise 0700 Sydney, Tuesday 5 April 2011 Depart Sydney
More informationContents. 1. Cruise information Outline of YK17-E KEO buoy mooring work 12. Acknowledgment 19
Contents 1. Cruise information 2 2. Outline of YK17-E01 4 3. KEO buoy mooring work 12 Acknowledgment 19 1 YK17-E01 Preliminary Cruise Report 1. Cruise information Makio Honda (JAMSTEC) (1) Cruise designation
More informationPrince Madog cruise 25/06 POL Coastal Observatory cruise August 2006
Prince Madog cruise 25/06 POL Coastal Observatory cruise 38 15-16 August 2006 1. Objectives 1. At 53º 32 N 3º 21.8 W, half a mile west of the Mersey Bar Light Vessel (site A) To recover a) A sea bed frame
More informationWave Glider: Liege Colloquium. Colloquium April 27
The The Wave Wave Glider: Glider: Enabling Enabling aa New New Approach Approach to to Persistent Persistent Ocean Ocean Observation Observation and and Research Research nd Liege 42 42nd Liege Colloquium
More informationPioneer Array Micro-siting Public Input Process Frequently Asked Questions
Pioneer Array Micro-siting Public Input Process Frequently Asked Questions The National Science Foundation (NSF) has completed the micro-siting of the moored array of the Ocean Observatories Initiative
More informationLocation: Barkley Canyon Date: September 9, 2013 Constraints: none
Page 1 of 11 DIVE PLAN R1650 Location: Barkley Canyon Date: September 9, 2013 Constraints: none Objectives Deploy POD 1 autonomous CTD Survey POD 3 for sediment enrichment sites; deposit cages; collect
More information3 Solutions Found for Irish Research Vessels. A CTD Davit design
3 Solutions Found for Irish Research Vessels A CTD Davit design A Vibration Damping Solution Managing mooring chain on a small vessel Bill Dwyer, P&O Maritime Services Ltd Celtic Voyager & Celtic Explorer
More informationThe Wave Glider: A Mobile Buoy Concept for Ocean Science. 009 Liquid Robotics Inc.
The Wave Glider: A Mobile Buoy Concept for Ocean Science 009 Liquid Robotics Inc. J. Manley & T. Richardson: Liquid Robotics Inc. DBCP XXV Paris September 28, 2009 1 Wave Glider Overview Unique Two Part
More informationCruise Plan Coastal Pioneer 4 Deployment Leg 1: R/V Atlantis Cruise AT April - 5 May 2015 Leg 2: R/V Atlantis Cruise AT-27 7 May - 14 May 2015
Cruise Plan Coastal Pioneer 4 Deployment Leg 1: R/V Atlantis Cruise AT-27 28 April - 5 May 2015 Leg 2: R/V Atlantis Cruise AT-27 7 May - 14 May 2015 Control Number: Version: 0-03 Author: A. Plueddemann
More informationQUICK START GUIDE CB-150 DATA BUOY PLATFORM
What s Included (1) Buoy hull with data well, 150 lb buoyancy (1) Buoy tower (3) 6W Solar panels (1) Data well lid (isic-cb or pass-through) (3) Top-side lifting eyes (3) Bottom-side mooring eyes Common
More informationQUICK START GUIDE CB-950 DATA BUOY PLATFORM
What s Included (1) Buoy hull with data well, 950 lb buoyancy (1) Buoy tower (3) 40W Solar panels (1) Data well lid (isic-cb or pass-through) (3) Top-side lifting eyes (3) Bottom-side mooring eyes (1)
More informationDeep SOLO. Nathalie Zilberman, Dean Roemmich, and SIO float lab. 1. Deep SOLO float characteristics. 2. Deep SOLO float Deployment
Deep SOLO Nathalie Zilberman, Dean Roemmich, and SIO float lab 1. Deep SOLO float characteristics 2. Deep SOLO float Deployment 3. Deep SOLO temperature and salinity Deep SOLO Float deployment, R/V Tangaroa
More informationFully Submersible Heavy Lift Vessel
Fully Submersible Heavy Lift Vessel Arnbjorn Joensen Aberdeen Maritime Branch (28th January 2015) PRESENTATION Introduction to the Subsea Deployment Vessel Installation method Tank test video Potential
More informationMAPCO2 Buoy Metadata Report Project Title:
MAPCO2 Buoy Metadata Report Project Title: Autonomous Multi-parameter Measurements from a Drifting Buoy During the SO GasEx Experiment Funding Agency: NOAA Global Carbon Cycle program PI(s): Christopher
More informationQUICK START GUIDE CB-450 DATA BUOY PLATFORM
What s Included (1) Buoy hull with data well, 450 lb buoyancy (1) Buoy tower (3) 10W Solar panels (1) Data well lid (isic-cb or pass-through) (3) Top-side lifting eyes (3) Bottom-side mooring eyes (1)
More informationWoods Hole Oceanographic Institution
Woods Hole Oceanographic Institution WHOI-2009-04 WHOI Hawaii Ocean Timeseries Station (WHOTS): WHOTS-5 2008 Mooring Turnaround Cruise Report by Sean P. Whelan, Jeffrey Lord, Robert Weller, Roger Lukas,
More informationBACKGROUND TO STUDY CASE
BACKGROUND TO STUDY CASE German Aerospace Center (DLR) is using Andøya Rocket Range for a sounding rocket campaign. On 27th October 2005 a 300 kg payload (SHEFEX) was launched Due do a technical problems
More informationNSF's Ocean Observatories Initiative: Building Research Infrastructure for the Pacific Northwest and the Broader Community
Agenda Item B.3.b Supplemental OOI PowerPoint April 2013 Ocean Observatories Initiative NSF's Ocean Observatories Initiative: Building Research Infrastructure for the Pacific Northwest and the Broader
More informationR/V HUGH R. SHARP University of Delaware 2016
R/V HUGH R. SHARP R/V HUGH R. SHARP University of Delaware 2016 GENERAL DESCRIPTION: The R/V HUGH R. SHARP is an acoustically quiet, state of the art, general-purpose, regional class research vessel operated
More informationCB-50 Data Buoy Quick Start Guide
CB-50 Data Buoy Quick Start Guide The NexSens CB-50 Data Buoy is designed for quick deployment in emergency response situations including industrial spills and natural disasters. The buoy can be deployed
More informationCascadia Initiative. Cruise OC1208B R/V Oceanus (Cascadia 2012 Leg 5) August 31, 2012 September 6, 2012 Newport, Oregon to Newport, Oregon
Cascadia Initiative Cruise OC1208B R/V Oceanus (Cascadia 2012 Leg 5) August 31, 2012 September 6, 2012 Newport, Oregon to Newport, Oregon Douglas Toomey, University of Oregon Susan Schwartz, University
More informationAppendix 11-B Anchor Handling Systems, Set Up and Handling
Revision History Revision Date Section Changes Number 1 Sept 1 Permanent Chaser Pendant (PCP) Drawing updated 2018 2 Pennant Buoy System Drawing updated 3 Working Wire/Chaser Termination on Drawing updated
More informationOriginal URI Scanfish MKII
Scanfish MKII URI s Scanfish MKII Sensors include CTD, Fluorometer, Dissolved Oxygen and Seabird Fast Temperature and Conductivity Sensors logging at 400 Hz and sending 50 Hz data via 9600 Baud uplink
More informationTechnical Guideline No. 06 Deployment of current meter moorings
Technical Guideline No. 06 Deployment of current meter moorings James Parker and Jon Rees 2014 To be used in conjunction with: GUIDELINES FOR THE ENVIRONMENTAL MONITORING AND IMPACT ASSESSMENT ASSOCIATED
More informationOcean Observatories Initiative (OOI) Moorings: New Capabilities for Seagoing Science
Ocean Observatories Initiative Ocean Observatories Initiative (OOI) Moorings: New Capabilities for Seagoing Science presented by Ed Dever and Walt Waldorf November 20, 2014 OOI Science Themes Coastal and
More informationOVER-SIDE OVERBOARD HANDLING SYSTEM R/V SIKULIAQ Top Level Maximum Capability Document
OVER-SIDE OVERBOARD HANDLING SSTEM R/V SIKULIAQ Top Level Maximum Capability Document Manufactured By: XXX Reference Drawing Number: XXX-XXX Prepared By: [Company Name] [Engineer s Name/Stamp] [Date] Page
More informationPRELIMINARY CRUISE REPORT, W9909C R/V WECOMA, September 1999 GLOBEC/ENSO Long-Term Observations off Oregon
Submitted by Jane Fleischbein College of Oceanic & Atmospheric Sciences Oregon State University Corvallis, Oregon 97331-553 flei@oce.orst.edu, 541.737.5698 FILING DATE: 1 October 1999 PRELIMINARY CRUISE
More informationMLV Mast Series Sectional Tripod Mast, 10-34m (32-110ft)
MLV Mast Series Sectional Tripod Mast, 10-34m (32-110ft) Overview Fully deployed heights of 10, 15, 20, 30 and 34m (32, 49, 65, 98 and 110ft) Heavy duty composite sectional tripod masts capable of supporting
More informationPROUDMAN OCEANOGRAPHIC LABORATORY CRUISE REPORT NO. 42. ASOF: Inverted Echo Sounders in the Denmark Strait. As part of FS METEOR CRUISE 59/1
PROUDMAN OCEANOGRAPHIC LABORATORY CRUISE REPORT NO. 42 ASOF: Inverted Echo Sounders in the Denmark Strait As part of FS METEOR CRUISE 59/1 JUNE 27, 2003 JULY 20, 2003 G.W. Hargreaves 2003 DOCUMENT DATA
More informationWEBB RESEARCH CORPORATION
Use spacebar or arrow keys to advance slide show WEBB RESEARCH CORPORATION Falmouth, MA APEX Profiler SLOCUM Glider Rev: 06/22/08 WEBB RESEARCH CORPORATION Specialists in neutrally buoyant drifters and
More informationWoods Hole Oceanographic Institution
Woods Hole Oceanographic Institution WHOI-2008-04 WHOI Hawaii Ocean Timeseries Station (WHOTS): WHOTS-4 2007 Mooring Turnaround Cruise Report by Sean P. Whelan, Al Plueddemann, Roger Lukas, Jeffrey Lord,
More informationSurface Tracking Feature
TELEDYNE RD INSTRUM ENTS A Teledyne Technologies Company Application Note FSA-022 (June 2008) Surface Tracking Feature 1 Introduction The following Application Note serves as a guide of how to use the
More informationChapter 9: Sea operations
Chapter 9: Sea operations ANTARES takes advice from IFREMER for the sea operations, which concern the installation and recovery of the different components of the detector : Junction Box, Strings, Interconnecting
More informationDIVE PLAN Leg 1 Dive 11 Recover Wally 1
DIVE PLAN Leg 1 Dive 11 Recover Wally 1 Page 1 of 6 Location: Barkley Canyon Date: 9 May, 2014 14:00 Constraints: Weather, Sufficient deck space ROV Dive # OE 114 Objectives Prepare Wally I cable for recovery
More informationCRUISE REPORT FOR UW BERING STRAIT MOORING PROJECT 2005 Rebecca Woodgate, University of
CRUISE REPORT FOR UW BERING STRAIT MOORING PROJECT 2005 Rebecca Woodgate, University of Washington,woodgate@apl.washington.edu CCGC Sir Wilfrid Laurier 2005-05 Kodiak, 8 th July 2005 Barrow, 22nd July
More informationColumbia River Plume 2006 OSU Ocean Mixing Nash, Kilcher, Moum et al. CR05 Cruise Report (RISE Pt. Sur, May )
CR05 Cruise Report (RISE Pt. Sur, May 21-31 2006) Group Summary: Participants: Pt. Sur Ocean Mixing Group: Jonathan Nash, Levi Kilcher, Alexander Perlin, Greg Avicola; Pt. Sur UW: Emily Spahn (Alex Horner-Devine;
More informationLong-Term Autonomous Measurement of Ocean Dissipation with EPS-MAPPER
Long-Term Autonomous Measurement of Ocean Dissipation with EPS-MAPPER Neil S. Oakey Bedford Institute of Oceanography Dartmouth, Nova Scotia Canada B2Y 4A2 phone: (902) 426-3147 fax: (902) 426-7827 e-mail:
More informationOcean Observatories Initiative Cabled Array Observatory Extension Cables/Connectors
Ocean Observatories Initiative Cabled Array Observatory Extension Cables/Connectors Mike Harrington mikeh@apl.washington.edu Infrastructure Cable Laying Problem: Get to the interesting stuff. Laying interconnection
More informationAtmospheric Forcing and the Structure and Evolution of the Upper Ocean in the Bay of Bengal
DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. Atmospheric Forcing and the Structure and Evolution of the Upper Ocean in the Bay of Bengal J. Thomas Farrar and Robert
More informationR/V POINT SUR Pre-Cruise Questionnaire
R/V POINT SUR Pre-Cruise Questionnaire Please fill this out and return at least 40 days prior to your cruise to ensure that all of your technical needs can be met BASIC INFO Briefly Describe the main objective(s)
More informationEric J. Aronchick, B.S. Oceanographic Field Technician
, B.S. Oceanographic Field Technician EXPERTISE Experienced in conducting offshore shallow, mid, and deep water deployment and recovery operations of oceanographic instrumentation and equipment. Skilled
More informationTRIAXYS Acoustic Doppler Current Profiler Comparison Study
TRIAXYS Acoustic Doppler Current Profiler Comparison Study By Randolph Kashino, Axys Technologies Inc. Tony Ethier, Axys Technologies Inc. Reo Phillips, Axys Technologies Inc. February 2 Figure 1. Nortek
More informationMooring Modifications for the Reduction of Losses to Vandalism
Mooring Modifications for the Reduction of Losses to Vandalism H. Paul Freitag Chris Meinig Andrew J. Shepherd Pacific Marine Environmental Laboratory Seattle, Washington, USA Linda D. Stratton JISAO/University
More informationCB-150 Data Buoy Quick Start Guide
CB-150 Data Buoy Quick Start Guide The NexSens CB-150 Data Buoy is designed for deployment in lakes, rivers, coastal waters, harbors, estuaries and other freshwater or marine environments. The floating
More information"Real-Time Vertical Temperature, and Velocity Profiles from a Wave Glider"
DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited. "Real-Time Vertical Temperature, and Velocity Profiles from a Wave Glider" Luca Centurioni Scripps Institution of Oceanography
More informationENVIRONMENTAL DATA BUOYS
ENVIRONMENTAL DATA BUOYS COMPACT. VERSATILE. POWERFUL NexSens CB-Series Data Buoys are designed for deployment in lakes, rivers, coastal waters, harbors, estuaries and other freshwater or marine environments.
More informationSVP-B drifter built by METOCEAN Use and deployment instructions
Centre de Meteorologie Marine Tel: +33 2 98 22 18 52 Meteo-France Fax: +33 2 98 22 18 49 13, rue du Chatellier E-mail: Pierre.Blouch@meteo.fr BP 90411 29604 BREST CEDEX France SVP-B drifter built by METOCEAN
More informationRope-less Fishing: A vision for how it can work
Rope-less Fishing: A vision for how it can work Mark Baumgartner (WHOI), Tim Werner (NEAq), Amy Knowlton (NEAq), Michael Moore (WHOI), and Scott Kraus (NEAq) The need The latest assessment of the North
More informationCLIENT NAME: LOCATION: CALM BUOY INSPECTION:
INSPECTOR REVIEWED INSPECTION OF CALM BUOY OVERALL PHOTO REVISION DESCRIPTION: Preliminary / Final Page: 1 TABLE OF CONTENT 1. MANAGEMENT SUMMARY... 3 1.1. SCOPE OF WORK:... 3 1.2. CORRECTIVE ACTIONS...
More informationF.S. POSEIDON CRUISE 328 TORSHAVN ABERDEEN 6 SEPTEMBER SEPTEMBER Dr. J.M. HUTHNANCE SLOPE MIXING CRUISE REPORT NO.
F.S. POSEIDON CRUISE 328 TORSHAVN to ABERDEEN 6 SEPTEMBER 2005 to 25 SEPTEMBER 2005 Dr. J.M. HUTHNANCE SLOPE MIXING CRUISE REPORT NO. 48 2005 POL CRUISE REPORT NUMBER 48 F.S. POSEIDON CRUISE 328 SLOPE
More informationWelcome to PolarConnect
Welcome to PolarConnect with Lisa Seff and the Oceanographic Conditions of Bowhead Whale Habitat 2012 PolarTREC Expedition Friday 7 September 2012 7:15 a.m. AKDT (8:15 am PDT, 9:15 am MDT, 10:15 am CDT,
More informationThe Wave Glider: A Persistent Platform for Ocean Science
The Wave Glider: A Persistent Platform for Ocean Science Justin Manley and Scott Willcox Liquid Robotics - Sunnyvale, CA justin.manley@liquidr.com, http://www.liquidr.com Abstract The Wave Glider is an
More informationNational Report of China
National Report of China Yu Ting (NMDIS), State Oceanic Administration (SOA), China DBCP 29, 27 Sep. 2013, Paris, France Contents 1 Current program status 2 Future deployment plan 3 Technical development
More informationDraft ANDRILL SMS Mooring Deployment Report Richard Limeburner, David Harwood and Peter Webb October 27, 2006
Draft ANDRILL SMS Mooring Deployment Report Richard Limeburner, David Harwood and Peter Webb October 27, 2006 Introduction A current meter mooring was deployed on October 25, 2006 on the frozen surface
More informationBUYER S GUIDE AQUAlogger 520
OCEAN & ENVIRONMENTAL BUYER S GUIDE AQUAlogger 520 Mini Temperature and Pressure Logger AQUAlogger 520 Aquatec s primary temperature and depth model, the AQUAlogger 520, combines years of product development
More informationInstitute of Marine Research
Institute of Marine Research CRUISE REPORT NO. ** R/V G.O. Sars Cruise No. 2005108 9 th June 24 th June 2005 Coral survey off Northern Norway Principal Scientist J. H. Fosså 2005 Benthic Habitat Research
More informationSensor Platform Project Marine Trials Bidders Conference. Fundy Ocean Research Center for Energy fundyforce.ca
Sensor Platform Project Marine Trials Bidders Conference Fundy Ocean Research Center for Energy fundyforce.ca 1 Project Team FORCE OceanWorks International Preliminary Design, Operational Procedures Murray
More informationSummary of NABOS/CABOS mooring operations
IARC Technical Report # 8 Report of the NABOS/CABOS 2010-2011 Arctic Ocean mooring recovery Summary of NABOS/CABOS mooring operations With support from: NSF 1 TABLE OF CONTENTS PREFACE ( I.Polyalov ).........
More informationFully Submersible Heavy Lift Vessel
Fully Submersible Heavy Lift Vessel Arnbjorn Joensen Oil and Gas Authority (OGA) (15th February 2016) CONTENT Leadon structures demobilisation Competitiveness (case studies) Decommissioning options Installation
More information2013 NABOS CRUISE BLOG
2013 NABOS CRUISE BLOG By Lindsey Bartholomew September 23, 2013 Our ninth NABOS cruise is over, the ship is in Kirkenes for disembarkation and downloading all gear. Thanks to all participants for their
More informationNUI Overview. Mike Jakuba Woods Hole Oceanographic Institution
NUI Overview Mike Jakuba Woods Hole Oceanographic Institution Optics Co-Registered Multibeam Fluorometry C. Katlein (AWI) Katlein et. Al, 2015, JGR Still-Camera S. Laney (WHOI) H.Singh (WHOI) 2.5m NUI
More informationTelescopic winch handle Speedfriend"
Winch handles, jib furlers JIB FURLERS - WINCH HANDLES - SPREADER COVERS 57 Floating winch handles Floating universal size winch handles Fitted with "Lock In" winch system; universal size for any winch;
More informationWoods Hole Oceanographic Institution
R Woods Hole Oceanographic Institution WHOI-2009-03 Stratus 9/VOCALS Ninth Setting of the Stratus Ocean Reference Station & VOCALS Regional Experiment Cruise RB-08-06 September 29 December 2, 2008 Leg
More informationWestern Canadian Spill Services Ltd. Field Testing Exercise Report
Western Canadian Spill Services Ltd. Field Testing Exercise Report Wednesday, July 15, 2009 Clearwater River, Rocky Mountain House, AB Background Western Canadian Spill Services Ltd. (WCSS) held a field
More informationSOUTH TOTO ACOUSTIC MEASUREMENT FACILITY (STAFAC) IN-WATER SYSTEMS DESIGN
SOUTH TOTO ACOUSTIC MEASUREMENT FACILITY (STAFAC) IN-WATER SYSTEMS DESIGN Phil DeNolfo Mike Harrison Naval Undersea Warfare Center Division Sound & Sea Technology Newport, RI Ventura, CA Hugh Thomson Naval
More informationCanadian Arctic Through-flow
Canadian Arctic Through-flow 2012 Cruise to Nares Strait CCGS Henry Larsen August 2-17, 2012 Institute of Ocean Sciences Cruise 2012-20 Humfrey Melling Chief Scientist Fisheries & Oceans Canada Collaborating
More informationHigh Ping Rate Profile Water Mode 12
Application Note FSA-014 (October 2008) Revised October 2008 High Ping Rate Profile Water Mode 12 Introduction Water Mode 12 is the result of the continued evolution of the signal processing within our
More informationXRAY GLIDER Underwater Video Cruise Plan May 21, 22, 23, 2007 R. G. Sproul
XRAY GLIDER Underwater Video Cruise Plan May 21, 22, 23, 2007 R. G. Sproul Purpose The ONR program manager for the XRAY/Liberdade underwater flying wing glider has requested that an underwater video of
More informationDeep-Sea Research I 58 (2011) Contents lists available at SciVerse ScienceDirect. Deep-Sea Research I
Deep-Sea Research I 58 (2011) 1158 1162 Contents lists available at SciVerse ScienceDirect Deep-Sea Research I journal homepage: www.elsevier.com/locate/dsri Autonomous and rapid deployment of a compact
More informationShort evaluation of GusT progress to end of 2016
Generated using the official AMS LATEX template two-column layout. FOR AUTHOR USE ONLY, NOT FOR SUBMISSION! Short evaluation of GusT progress to end of 2016 JAMES N. MOUM, JOHANNES BECHERER & JONATHAN
More informationN. Robinson and A. Pyne
ISSN 0375 8192 March 2004 Antarctic Data Series No 26 WATER COLUMN CURRENT PROFILE ANALYSIS FROM BENEATH THE MCMURDO ICE SHELF AT WINDLESS BIGHT AND UNDER THE SEA ICE IN GRANITE HARBOUR, ANTARCTICA N.
More informationStevpris installation
chaser Stevpris deployment for MODUs Introduction Typical methods for deployment and retrieval of Stevpris anchors with an anchor handling vessel (AHV) are described, focusing on the use of chasers for
More informationAlvin Debrief Summary Seven Cruises for 91 dives. Southern California Juan de Fuca Costa Rica Guaymas Basin Galapagos
Seven Cruises for 91 dives Southern California Juan de Fuca Costa Rica Guaymas Basin Galapagos Overview All the PIs were very satisfied with their Alvin experience and felt that their scientific goals
More informationWHOTS Mooring Subsurface Instrumentation
UH Contributions to WHOTS-15 Cruise Report by Fernando Santiago-Mandujano, Jefrey Snyder, Svetlana Natarov, Kelsey Maloney, Noah Howins, Garrett Hebert, and Roger Lukas WHOTS Mooring Subsurface Instrumentation
More informationCOMPARISON OF DEEP-WATER ADCP AND NDBC BUOY MEASUREMENTS TO HINDCAST PARAMETERS. William R. Dally and Daniel A. Osiecki
COMPARISON OF DEEP-WATER ADCP AND NDBC BUOY MEASUREMENTS TO HINDCAST PARAMETERS William R. Dally and Daniel A. Osiecki Surfbreak Engineering Sciences, Inc. 207 Surf Road Melbourne Beach, Florida, 32951
More informationGOVERNMENT GAZETTE REPUBLIC OF NAMIBIA
GOVERNMENT GAZETTE OF THE REPUBLIC OF NAMIBIA N$4.00 WINDHOEK - 19 November 2015 No. 5877 CONTENTS Page GOVERNMENT NOTICES No. 269 No. 270 Regulations to reduce incidental by-catch of seabirds in the hake
More informationAFT OVERBOARD HANDLING SYSTEM R/V SIKULIAQ Top Level Maximum Capability Document
AFT OVERBOARD HANDLING SYSTEM R/V SIKULIAQ Top Level Maximum Capability Document Manufactured By: XXX Reference Drawing Number: XXX-XXX Prepared By: [Company Name] [Engineer s Name/Stamp] [Date] Page 1
More informationMECHANICAL MINESWEEPING
CHAPTER 8 MECHANICAL MINESWEEPING LEARNING OBJECTIVES Upon completing this chapter, you should be able to do the following: 1. State the principles and the objective of mechanical minesweeping. 2. Describe
More informationThe SDS Skip. Subsea Deployment Systems Ltd.
The SDS Skip SUBSEA SKIP An alternative to enhance the recovery of structures, spool pieces, mattresses etc. during decommissioning work Can be used to transport complex structures or spool pieces to field
More informationX-03 EMERGENCY TOWING ARRANGEMENTS
Guideline No.: X-03(201510) X-03 EMERGENCY TOWING ARRANGEMENTS Issued date: October 20,2015 China Classification Society Foreword: This Guide is a part of CCS Rules, which contains technical requirements,
More informationMooring & towing. 9. Mooring & towing. Index
Mooring & towing 9. Mooring & towing 1 General 1.1 About Hendrik Veder Group 1.2 Trade names 1.3 Certified Quality 1.4 Certificates 1.5 Key suppliers & brands 1.6 Contact information 1.7 Locations 1.8
More informationCruise Report Towed ADCP Bay of Biscay R/V Pelagia cruise 64PE April 2005 Texel - Vigo
Reference: van Haren, H., 2005. Towed ADCP- Bay of Biscay: R/V Pelagia cruise 64PE235, 20-27 April 2005, NIOZ, 15 pp. Cruise Report Towed ADCP Bay of Biscay R/V Pelagia cruise 64PE235 20-27 April 2005
More informationTravel-Lift Operating Procedure. To that end, we would like to introduce the following procedure for HMPC lifting operations.
Travel-Lift Operating Procedure The Board of Directors for the Holyrood Marina Park Corporation is responsible for the operation and development of the Holyrood Marina complex including the Marine Travel-Lift.
More informationCTD General Practices: System Description, Deployment, Data Acquisition, & Maintenance
CTD General Practices: System Description, Deployment, Data Acquisition, & Maintenance SUMMARY: Since 1993, the CalCOFI program has deployed a Seabird 911 CTD mounted on a 24-bottle rosette during seasonal,
More informationUnderstanding the Dynamics of Shallow-Water Oceanographic Moorings
Understanding the Dynamics of Shallow-Water Oceanographic Moorings Mark A. Grosenbaugh Department of Applied Ocean Physics & Engineering Woods Hole Oceanographic Institution Woods Hole, MA 02543 phone:
More informationThe Next Generation Easy-to-Deploy (ETD) Tsunami Assessment Buoy
The Next Generation Easy-to-Deploy (ETD) Tsunami Assessment Buoy R.A. Lawson and D. Graham Science Applications International Corporation 4025 Hancock Street San Diego, CA 92110 USA S. Stalin, C. Meinig,
More informationProcedure for Setting a Mooring
The information below was provided by DSC member Jim Simons. Procedure for Setting a Mooring Here's a note he sent to Good Old Boat magazine a couple of years ago, which hits the high points. 1. All components
More information