Benefits of Proper Route Engineering to Mitigate Risk During the Design Life of Submarine Cable Systems

Size: px
Start display at page:

Download "Benefits of Proper Route Engineering to Mitigate Risk During the Design Life of Submarine Cable Systems"

Transcription

1 Benefits of Proper Route Engineering to Mitigate Risk During the Design Life of Submarine Cable Systems Simon Cooper TATA Communications International Gordon Lucas Alcatel-Lucent Submarine Networks Ron Rapp TE SubCom Graham Evans EGS Survey Group

2 Agenda Critical Infrastructure Consequence of Cable Outage Real Cost of Ownership Route Planning Tools and Risk Identification Physical and Political Routing Constraints Marine Route Survey Cable Protection and Installation Maintenance Considerations

3 Concept to Reality Key Phases Development of Business Model Definition of Key Project Milestones Project Concept & Initial Investors Feasibility Study & Initial Engineering Define Permitting Requirements Formation of Interim Management Team Pre Survey Desk Study Secure System Permits in Principle Supply Contract Processes Route Survey & Burial Assessment Marine Operations Permitting Route Survey Contract Process System Installation

4 Topics for A Submarine Cable Planning Discussion

5 Why are Submarine Cables important? International Commerce Freedom of Communication Information Sharing Lowest Cost Solution Sustainable and Footprint Lite

6 What do you want from your route? (Oh, and what don t you want?) Diversity versus Latency Market Coverage versus Permitting Complexity Risk & USP s versus Known & Me Too Big Enough versus Biggest Ever New Technology versus The Proven Local Factors versus Network Integration

7 The TGN Intra-Asia System TGN-Pacific (Japan Guam) is an existing system Singapore Vietnam Hong Kong Philippines Japan

8 TGN-IA s Resilient Architecture

9 Early Life Information

10 TGN-Intra Asia: The Re-Route

11 Total Cost of Ownership TCO translates to: What will you have to spend and when? A high quality Desk Top Survey High value $$ If it drives the survey PoW and Rt Eng pre-planning The Survey Who represents you? What are the goals and acceptable compromises? How to reduce the TCO? Cable Armour that may reduce repair volume: obvious value? Deep burial: can you afford not to? Deep water: who cares? Project Costs: Plan, Predict and Keep Under Control Future Costs: Replacement, Marine Ops, Reputation & Revenue

12 Route Planning Tools Use of a GIS based system is essential and facilitates the display of key information Existing in service and out of service cables Planned systems system deconfliction! Maritime boundaries, navigation charts and coastal data Sea bed assets associated with offshore energy Concession blocks Restricted areas such as marine parks, areas of SSI General seabed bathymetry and other survey data sets Marine Route Survey results

13 Risk Identification A thorough Cable Route Study (DTS) is crucial A comprehensive study of all potential threats: Fishing, anchoring, mineral extraction, slopes, seismic etc Fault histories of nearby cables and their status Landing point selection Influenced by risk and not by infrastructure or real estate Typical issues include crossing reefs in the surf zone, proximity to charted anchorages, high energy beaches Route Diversity from potential restoration cables Avoid areas of known seismic activity (fault histories) Political risk: permit lead times for repairs

14 Risk Mitigation It may not be possible to route away from all risks Engineer the system with appropriate protection In shallow water bury the cable or up-armour In deep water increase protection (LWP,DWP) Increase burial depth according to seabed type Deep burial in selected high risk areas Exploit the potential of available tools Increase near-shore protection Horizontal directional drilling (HDD) Articulated pipe and pinning

15 Physical Routing Constraints 15

16 Physical Routing Constraints Pattern of Single Fault Incidents Multiple Fault Incidents Single Faults widespread but manageable Multiple Faults in choke points and critical 16

17 Physical Routing Constraints Landing points Proximity to cable station and terrestrial infrastructure Established cable corridors usually preferred except when diversity is important Low energy, stable beach not prone to erosion Direct landing from a cable ship preferred (15m WD < 2km)depending on currents and seabed. Access for shore end team and equipment to land the cable Route perpendicular to beach (allows more cables, shortest distance to deepwater) Avoid anchorage, harbor, dredging, environmentally sensitive areas Shelf routing Lowest fishing and anchoring risk; avoid hydrocarbon lease blocks and dredging Short distance to deepwater to minimize armor, burial and risk. Avoid rocky, abrasive seabed Find route suitable for burial if external aggression is a risk Suitable distance from active cables, crossing near 90 deg; congestion is often an issue. Limit alter course angle to 15 deg in burial, economic distance between PLUP & PLDN. 17

18 Physical Routing Constraints 18

19 conference & convention Physical Routing Illustrated 19

20 Physical Routing Constraints (Cont) Deepwater routing Great circle for shortest cable length Look for smooth flat seabed away from slopes and seamounts, avoid steep slopes and side slopes Keep suitable distance (2 x WD min) from active cables; congestion often also in deep water Avoid crossings to extent possible, cable crossing angles > 45 deg, cross away from other cable repeaters Avoid abrasive seabed and currents, use of SPA cable is such area Prefer final splice and BU placement in deeper water away from burial (1500m ideal depth) Consider using out-of-service cable route Bottom slack 2.5 to 3% plus fill slack Limit A/C to 30 deg otherwise vessel must slow to reduce layback Consider repeater placements either side of deep trench Economic cable length between transitions Consider installation and future maintenance in your routing and cable engineering 20

21 Physical Routing Constraints Earthquake Resulting Severe 300 km Mud Flow 21

22 Physical Routing Constraints Special Problems Ensuring all pipelines are known and found Databases are not complete; must rely of surveys Meeting ICPC recommendations in congested areas Not possible in many locations Accuracy of cable databases, also with regard to repair bights Owners often reluctant to disclose 22

23 Political Routing Constraints 23

24 Political Routing Constraints Minimize the number of coastal state claims especially Territorial Sea (TS) transited by the route Consider disputed claims and need for permits in overlapping claims Investigate coastal state s interpretation of UNCLOS and regulation for survey and use of foreign flag vessels Minimize length in TS (and CZ, EEZ) Consider taxes on cable and repeaters) Consider coastal state regulations in TS, CZ, EEZ. What is strength of fishing unions and expected compensation both shallow and deepwater Feedback from fishing unions is important especially in shelf routing Minimize number of active hydrocarbon lease blocks crossed 24

25 Political Routing Constraints 25

26 The Route Survey Provides information required to confirm or amend the preliminary pre survey DTS route Defines and documents the final route Enables final cable engineering to be defined Provides the system installer with the data required to finalize installation procedures Identifies potential post installation/residual hazards including unmitigated risks from potential tectonic activity during the system design life

27 conference & convention Route Survey Offshore Vessel

28 Route Survey Data Sets Data is collected along a strip of seabed, typically 500m to 3 x water depth wide and includes: Bathymetric data seabed topography Sonar imagery data seabed surface features Sub-bottom profiling data shallow sub surface soil profile Burial assessment data mechanical properties of the seabed soils within the planned burial profile (typically 1m to 3m) Geophysical and soils data usually only collected where cable protection by burial is planned typically up to a maximum water depth of 1,000m; rarely up to 2,000m Only bathymetric data collected in deep water

29 Multibeam Bathymetry Bathymetry and colocated back-scatter data Digital data output can be rapidly processed and analysed Data used to develop seabed terrain model Resolution of multibeam systems is altitude dependant

30 High Resolution in Shallow Water

31 High Resolution in Shallow Water

32 Deep water data Philippine Trench maximum depth 10,400m

33 Side Scan Sonar Imagery Towed systems Depth range up to 3000m Provide images of seabed surface features Surface back-scatter intensity can be used as indicator of seabed hardness

34 Side Scan Sonar Imagery

35 Sub-bottom data

36 Burial Assessment Gravity coring Cone Penetrometer Tests measure Tip resistance Sleeve friction Resistivity Typically to 3m below seabed Used to predict and categorize cable plough burial performance

37 Short reporting leadtimes have led to: On-board data acquisition, processing & charting Telemetry of processed data to shore based offices Data output direct to route planning software (Makai) Final reporting typically office based

38

39

40

41 Cable Protection The Threat All External Aggression Faults (%) 70% 60% 50% 40% 30% 20% 10% 0% Fishing Anchors Other Abrasion Tyco Data ASN Data Dredge Geological Crushing M. Kordahi, S. Shapiro, G. Lucas, Trends in submarine Cable System Faults, SubOptic 2007 Fishing and anchoring pose the greatest risk to cable security. Cable burial remains the most effective and economical method of protection against these threats. 41

42 Cable Protection Desktop Study Route Selection Survey, Seabed Assessment, Route Refinement Burial Feasibility Study Burial Operations Cable Awareness Program Elements of of cable protection span the full project cycle! 42

43 Burial Category: A: Cable burial to a target cover depth of m; B: Cable burial to a target cover depth greater than 0.4m but less than 0.8m; C: Cable burial to a target cover depth of less than 0.4m; D: Risk of uncontrolled cable burial to a cover depth of greater than 0.8m; E: Cable burial to a target cover depth of 1.5 m in water depths of m; F: Cable burial to a target cover depth of 3 m in water depths of less than 10 m; G: Cable burial to a target cover depth of 3 m. Cable Protection Burial Example Only Deeper burial may be required in many cases Risk Category: 1: No identified risk of damage to the burial equipment due to seabed conditions; 2: Possible risk of damage to burial equipment due to seabed conditions. Scale of possible damage to be repairable on the installation vessel using shipboard equipment; 3: High risk of damage to the burial equipment due to seabed conditions. Scale of possible damage in excess of category 2. Key Elements of the BFS Seabed description Core and CPT penetration depth Hazards such as slopes, rock, boulders, coral, sand waves, soft sediment, pock marks Cable or pipeline crossings Currents that may affect plow or ROV deployment or operations Results of the integrated survey and analyses form the Burial Feasibility Study BFS is a guideline to predict burial likelihood and plow risk along the route Where seabed not conducive to burial, consider uparmor only if warranted by risk of external aggression 43

44 Cable Protection Burial Towed cable plows remain the industry standard for cable burial. Sea Stallion 3 m Plow MD3 3 m Plow Improved capability allow deeper burial and in more challenging seabed. The burial will be dictated by plow operations and reasonable endeavors ROV for Jet burial guidelines. Sea Plow 7-1.5m Plow 44

45 Maintenance Considerations Effective maintenance solution to minimise outage Club (zone) vs Private Maintenance Speed of response Base location Transit speed Strategic spares onboard not in depot Vessel performance Weather capability Maintenance and training, outside work?

46 Maintenance Considerations Post repair burial performance Age and power of ROV Enhanced burial protection protection Permitting track record Speed of response Fault prioritisation Fibre vs shunt; isolated branches vs ring systems Transmission performance Repairs should not affect upgrade-ability

47 Maintenance Considerations Commercial aspects Direct Measures Of Quality (DMOQs or SLAs) Pooling of joint kits and spare cables Tailored contracts vs standard terms Additional Services Fisheries Liaison Spare plant testing Shallow water repairs Land cable repairs

48 2010 conference & convention The 7th International Conference & Convention on Undersea Telecommunications Pacifico Convention Plaza Yokohama & InterContinental The Grand Yokohama 11 ~ 14 May

Marine Survey & Cable Routing

Marine Survey & Cable Routing Marine Survey & Cable Routing Sub Optic 2004 Short Course Ron RAPP, Mark LAWRENCE, Dick BORWICK, Takuo KUWABARA Topics Introduction/Objectives/Project Cycle Ron Rapp Desktop Study and Cable Route Study

More information

Protection for Vessels Engaged in Servicing Submarine Cables

Protection for Vessels Engaged in Servicing Submarine Cables Protection for Vessels Engaged in Servicing Submarine Cables Proposed Amendments to COLREGS Brief to Navigation Safety Advisory Council November 28, 2012 Tampa, FL Dr. Ronald J. Rapp TE SubCom and Representing

More information

from ocean to cloud PARAMETRIC SUB-BOTTOM PROFILER, A NEW APPROACH FOR AN OLD PROBLEM

from ocean to cloud PARAMETRIC SUB-BOTTOM PROFILER, A NEW APPROACH FOR AN OLD PROBLEM PARAMETRIC SUB-BOTTOM PROFILER, A NEW APPROACH FOR AN OLD PROBLEM Geoff Holland, Alcatel-Lucent Submarine Networks Geoff.holland@alcatel-lucent.com Alcatel-Lucent Submarine Networks Ltd, Christchurch Way,

More information

Utilizing Vessel Based Mobile LiDAR & Bathymetry Survey Techniques for Survey of Four Southern California Breakwaters

Utilizing Vessel Based Mobile LiDAR & Bathymetry Survey Techniques for Survey of Four Southern California Breakwaters Utilizing Vessel Based Mobile LiDAR & Bathymetry Survey Techniques for Survey of Four Southern California Breakwaters Western Dredging Association: Pacific Chapter September 2012 Insert: Pipe Location

More information

Scottish Hydro Electric Power Distribution Operation, Inspection, Maintenance and Decommissioning Strategy Bute Cumbrae Cable Replacement

Scottish Hydro Electric Power Distribution Operation, Inspection, Maintenance and Decommissioning Strategy Bute Cumbrae Cable Replacement SHEPD Section ID 154 Scottish Hydro Electric Power Distribution Operation, Inspection, Maintenance and Decommissioning Strategy Bute Cumbrae Cable Replacement Contents Definitions and Abbreviations...

More information

Background Paper: Surveys. Nord Stream 2 AG Sep-17

Background Paper: Surveys. Nord Stream 2 AG Sep-17 Nord Stream 2 AG Sep-17 Table of Contents Introduction... 3 Advanced Technology... 4 Survey Stages... 4 2 Introduction Survey operations are the cornerstone of massive international infrastructure projects

More information

THE CHALLENGES OF A LARGE-AREA BATHYMETRIC SURVEY

THE CHALLENGES OF A LARGE-AREA BATHYMETRIC SURVEY THE CHALLENGES OF A LARGE-AREA BATHYMETRIC SURVEY Agenda: - Introduction - Tender - Project Planning - Survey - Processing - Delivery - Conclusion 2 Introduction We know less of the oceans at our feet,

More information

Certified Professionals in Hydrographic Solutions

Certified Professionals in Hydrographic Solutions Certified Professionals in Hydrographic Solutions Client Satisfaction is our Deliverable Port of Brisbane Pty Ltd Port Surveys Certified Professionals in Hydrographic Surveying Tel +61 (0) 7 3258 4820

More information

Acoustic Pipeline Inspection Mind The Gap

Acoustic Pipeline Inspection Mind The Gap Acoustic Pipeline Inspection Mind The Gap Mike Liddell Chief Surveyor, Fugro Survey Limited UUVS @ Oceanology 2012 13 th March 2012 Contents Menu Introduction to Pipeline Inspection The Current Toolkit

More information

Preliminary Survey Notification and Information for Fisheries Interests.

Preliminary Survey Notification and Information for Fisheries Interests. 1) Viking Link Project The Viking Link project is a proposal to build a high voltage direct current (HVDC) electricity interconnector between the Lincolnshire Coast in the UK and Southern Jutland in Denmark

More information

OFFSHORE SURVEY IN DEVELOPMENT PROJECTS. Ian Douglas Head, Offshore Surveys, Shell Projects & Technology Europe

OFFSHORE SURVEY IN DEVELOPMENT PROJECTS. Ian Douglas Head, Offshore Surveys, Shell Projects & Technology Europe OFFSHORE SURVEY IN DEVELOPMENT PROJECTS Ian Douglas Head, Offshore Surveys, Shell Projects & Technology Europe THE PROJECT: GOLDENEYE GOLDENEYE FACTS ST. FERGUS GOLDENEYE PLATFORM Gas Condensate Field

More information

Emerging Subsea Networks

Emerging Subsea Networks THE FUTURE OF MARINE SURVEY APPLICATIONS FOR SUBMARINE CABLES Ryan Wopschall (Fugro) Email: rwopschall@fugro.com Fugro Pelagos, Inc. - 3574 Ruffin Road, San Diego, California 92123 USA Abstract: New advances

More information

from ocean to cloud HEAVY DUTY PLOUGH PERFORMANCE IN VERY SOFT COHESIVE SEDIMENTS

from ocean to cloud HEAVY DUTY PLOUGH PERFORMANCE IN VERY SOFT COHESIVE SEDIMENTS HEAVY DUTY PLOUGH PERFORMANCE IN VERY SOFT COHESIVE SEDIMENTS Geoff Holland, Sarah Dzinbal (Alcatel-Lucent Submarine Networks) Email: geoff.holland@alcatel-lucent.com Alcatel-Lucent Submarine Networks

More information

RAMSTM. 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs

RAMSTM. 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs RAMS 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs Introduction to RAMS Tritech s RAMS is a 360 anchor-chain and riser integrity monitoring system for Floating Production Storage and Offloading

More information

Marine Renewables Industry Association. Marine Renewables Industry: Requirements for Oceanographic Measurements, Data Processing and Modelling

Marine Renewables Industry Association. Marine Renewables Industry: Requirements for Oceanographic Measurements, Data Processing and Modelling Marine Renewables Industry Association Marine Renewables Industry: Requirements for Oceanographic Measurements, Data Processing and Modelling October 2009 Table of Contents 1. Introduction... 1 2. Measurements

More information

Failure of Wide Bay Pipeline in the Burnett River

Failure of Wide Bay Pipeline in the Burnett River APGA Paper Date: 29 August 2015 Subject: Risk Mitigation for Trench Pipeline Under Shallow River Crossings Prepared by: Derek Boo Manager Planning and Engineering Company: APA Group Background: Beginning

More information

Evolution of Deepwater Coral Protection in the Southeast U.S

Evolution of Deepwater Coral Protection in the Southeast U.S Evolution of Deepwater Coral Protection in the Southeast U.S Tina Udouj, Florida Fish and Wildlife Conservation Commission Roger Pugliese, South Atlantic Fishery Management Council Overview Deepwater Corals

More information

HELCOM Submerged and The Nairobi International Convention. HELCOM Submerged Expert Group meeting in Bonn, Germany, 22 nd of April 2015

HELCOM Submerged and The Nairobi International Convention. HELCOM Submerged Expert Group meeting in Bonn, Germany, 22 nd of April 2015 HELCOM Submerged and The Nairobi International Convention HELCOM Submerged Expert Group meeting in Bonn, Germany, 22 nd of April 2015 The Nairobi International Convention on the Removal of Wrecks 2007

More information

page - Laboratory Exercise #5 Shoreline Processes

page - Laboratory Exercise #5 Shoreline Processes page - Laboratory Exercise #5 Shoreline Processes Section A Shoreline Processes: Overview of Waves The ocean s surface is influenced by three types of motion (waves, tides and surface currents). Shorelines

More information

Design and Planning Considerations For a Seabed Survey

Design and Planning Considerations For a Seabed Survey Design and Planning Considerations For a Seabed Survey Vera Quinlan Hydrographer & Data Processor Seabed Survey Overview Survey Platform - What boat do I use? Survey Area / depth of water / objective &

More information

# Post Consultation and Submissions Resource Consent Conditions for Surfing Impact Mitigation August 2016

# Post Consultation and Submissions Resource Consent Conditions for Surfing Impact Mitigation August 2016 # Post Consultation and Submissions Resource Consent Conditions for Surfing Impact Mitigation August 2016 Surf Mitigation Management Plan 1 1 Not less than 6 months prior to the commencement of the construction

More information

Potential applications of AUVs and Gliders in Offshore Windfarm Site Surveys

Potential applications of AUVs and Gliders in Offshore Windfarm Site Surveys Potential applications of AUVs and Gliders in Offshore Windfarm Site Surveys Dr James Hunt (National Oceanography Centre, Southampton) MREKE Internship in partnership with MARS at NOCS Introduction to

More information

Dauphin Island East End Beach and Barrier Island Restoration Project. Beau Buhring South Coast Engineers

Dauphin Island East End Beach and Barrier Island Restoration Project. Beau Buhring South Coast Engineers Dauphin Island East End Beach and Barrier Island Restoration Project Beau Buhring South Coast Engineers Funding Funded with qualified outer continental shelf oil and gas revenues by the Coastal Impact

More information

MPA proposals West of Scotland

MPA proposals West of Scotland MPA proposals West of Scotland Purpose of this presentation Support Consultation Sites, features and management options Basis for advice WoS Site options Answer any questions Scottish MPA proposals Nov

More information

14/10/2013' Bathymetric Survey. egm502 seafloor mapping

14/10/2013' Bathymetric Survey. egm502 seafloor mapping egm502 seafloor mapping lecture 10 single-beam echo-sounders Bathymetric Survey Bathymetry is the measurement of water depths - bathymetry is the underwater equivalent of terrestrial topography. A transect

More information

UTEC Survey Pipeline Inspection Using Low Logistic AUV June 2016

UTEC Survey Pipeline Inspection Using Low Logistic AUV June 2016 SUCCESS YOU CAN MEASURE UTEC Survey Pipeline Inspection Using Low Logistic AUV June 2016 Chris Erni Product Line Manager E T H I C S P E R F O R M A N C E E X C E L L E N C E P E O P L E GLOBAL FOOTPRINT

More information

Vieques Underwater Demonstration Project

Vieques Underwater Demonstration Project Vieques Underwater Demonstration Project NOAA Office of Response and Restoration National Ocean Service 2006-2007 2007 University of New Hampshire Joint Hydrographic Center 2006 Science Application International

More information

LiDAR My favourite tool in the bag 2011 St Kitts & Nevis

LiDAR My favourite tool in the bag 2011 St Kitts & Nevis LiDAR My favourite tool in the bag 2011 St Kitts & Nevis Lt Cdr Rupert Forester-Bennett RN (ret d) December 5 th to 11 th 2011 Content Collection of geospatial data reasons Overcoming the White Ribbon

More information

ACCESS the BLUE ECONOMY ALL OCEANS Engineering Ltd

ACCESS the BLUE ECONOMY ALL OCEANS Engineering Ltd Subsea Expo 2018 ROV Conference 07.02.2018 ACCESS the BLUE ECONOMY The BLUE ECONOMY - DEFINITION The Blue Economy is a book by Gunter Pauli publish in 2010 based on the idea that he developed in 2004 In

More information

Hydrographic Surveying Methods, Applications and Uses

Hydrographic Surveying Methods, Applications and Uses Definition: Hydrographic Surveying Methods, Applications and Uses It is the branch of surveying which deals with any body of still or running water such as a lake, harbor, stream or river. Hydrographic

More information

MINE SAFETY TARGETED ASSESSMENT PROGRAM. Ground or strata failure NSW metalliferous mines. April

MINE SAFETY TARGETED ASSESSMENT PROGRAM. Ground or strata failure NSW metalliferous mines. April MINE SAFETY TARGETED ASSESSMENT PROGRAM Ground or strata failure NSW metalliferous mines April 2017 www.resourcesandenergy.nsw.gov.au Document control Publication title: Ground or strata failure NSW metalliferous

More information

Coastal management has lagged behind the growth in population leading to problems with pollution

Coastal management has lagged behind the growth in population leading to problems with pollution Fifty percent of the population of the industrialized world lives within 100 km of a coast. Coastal management has lagged behind the growth in population leading to problems with pollution and natural

More information

OECS Regional Engineering Workshop September 29 October 3, 2014

OECS Regional Engineering Workshop September 29 October 3, 2014 B E A C H E S. M A R I N A S. D E S I G N. C O N S T R U C T I O N. OECS Regional Engineering Workshop September 29 October 3, 2014 Coastal Erosion and Sea Defense: Introduction to Coastal Dynamics David

More information

KY10-15 KAIYO / HYPER-DOLPHIN

KY10-15 KAIYO / HYPER-DOLPHIN KY10-15 KAIYO / HYPER-DOLPHIN Kumano-Nada January 2011 Earthquake and Tsunami Research Project for Disaster Prevention JAMSTEC TABLE OF CONTENTS 1. INTRODUCTION 2. SCHEDULE 3. DIVE RESULTS 4. CONCLUSIONS

More information

Cook Inlet pipeline crossing is about making the best choices

Cook Inlet pipeline crossing is about making the best choices Cook Inlet pipeline crossing is about making the best choices By Larry Persily lpersily@kpb.us Aug. 26, 2015 (This update, provided by the Kenai Peninsula Borough mayor s office, is part of an ongoing

More information

Concepts & Phenomena

Concepts & Phenomena Concepts & Phenomena in coastal and port sedimentation R. Kamalian Ports and Maritime Organization of Iran and PIANC-Iran 7 9 December 2015 What is the problem? Many harbours have sedimentation problems

More information

ScanFish Katria. Intelligent wide-sweep ROTV for magnetometer surveys

ScanFish Katria. Intelligent wide-sweep ROTV for magnetometer surveys ScanFish Katria Intelligent wide-sweep ROTV for magnetometer surveys User-friendly control and monitoring software solution The ScanFish Katria comes with the ScanFish III Flight software, which is an

More information

Department. «Ships and on-board Equipment» lfremer. (Head : Marc Nokin)

Department. «Ships and on-board Equipment» lfremer. (Head : Marc Nokin) Department «Ships and on-board Equipment» (Head : Marc Nokin) 1 Structuration and activities of NSE department Scope Construction and modernisation of Ifremer oceanographic ships Development of softwares

More information

Protectingpipelinesfor

Protectingpipelinesfor 24 Protectingpipelinesfor Michael Paulin, Damien Humby and Joseph Cocker, INTECSEA Canada, and Glenn Lanan, INTECSEA Inc., describe the process of trenching for the protection of pipelines in ice environments.

More information

Welcome! Did You Know...? Aquatic Centre Dock Rebuild. Key Objectives

Welcome! Did You Know...? Aquatic Centre Dock Rebuild. Key Objectives 1 Welcome! Aquatic Centre Dock Rebuild The City of Vancouver is improving the dock at the Vancouver Aquatic Centre, which is nearing the end of its service life and is in need of replacement. This creates

More information

Exploration and Mine Site Model Applied to Seamount Lease-Block Selection for Cobalt-Rich Crusts. James R. Hein U.S. Geological Survey For the ISA

Exploration and Mine Site Model Applied to Seamount Lease-Block Selection for Cobalt-Rich Crusts. James R. Hein U.S. Geological Survey For the ISA Exploration and Mine Site Model Applied to Seamount Lease-Block Selection for Cobalt-Rich Crusts James R. Hein U.S. Geological Survey For the ISA Introduction Parameters that ultimately will be used to

More information

THE LIGHTS GO OUT The Ultimate Protection Technology for Protecting Submarine Cables

THE LIGHTS GO OUT The Ultimate Protection Technology for Protecting Submarine Cables THE LIGHTS GO OUT The Ultimate Protection Technology for Protecting Submarine Cables Rene van Kessel, Cor-Jan Stam (Van Oord Offshore) Email: Van Oord Offshore, 2 Jan Blankenweg, 4207HN

More information

PIG MOTION AND DYNAMICS IN COMPLEX GAS NETWORKS. Dr Aidan O Donoghue, Pipeline Research Limited, Glasgow

PIG MOTION AND DYNAMICS IN COMPLEX GAS NETWORKS. Dr Aidan O Donoghue, Pipeline Research Limited, Glasgow PIG MOTION AND DYNAMICS IN COMPLEX GAS NETWORKS Dr Aidan O Donoghue, Pipeline Research Limited, Glasgow A model to examine pigging and inspection of gas networks with multiple pipelines, connections and

More information

Advanced PMA Capabilities for MCM

Advanced PMA Capabilities for MCM Advanced PMA Capabilities for MCM Shorten the sensor-to-shooter timeline New sensor technology deployed on off-board underwater systems provides navies with improved imagery and data for the purposes of

More information

Sensor Platform Project Marine Trials Bidders Conference. Fundy Ocean Research Center for Energy fundyforce.ca

Sensor Platform Project Marine Trials Bidders Conference. Fundy Ocean Research Center for Energy fundyforce.ca Sensor Platform Project Marine Trials Bidders Conference Fundy Ocean Research Center for Energy fundyforce.ca 1 Project Team FORCE OceanWorks International Preliminary Design, Operational Procedures Murray

More information

PIPELINE SAFETY. Darin Burk, Manager Pipeline Safety. January 28, 2014

PIPELINE SAFETY. Darin Burk, Manager Pipeline Safety. January 28, 2014 PIPELINE SAFETY Darin Burk, Manager Pipeline Safety January 28, 2014 Congressional Delegation of Authority Pipeline Safety Act of 1968 Congress Delegated Inspection and Enforcement Authority to the Secretary

More information

Recommended operating guidelines (ROG) for sidescan Sidescan sonar ROG in wrapper.doc English Number of pages: 9 Summary:

Recommended operating guidelines (ROG) for sidescan Sidescan sonar ROG in wrapper.doc English Number of pages: 9 Summary: Title: Author(s): Document owner: Recommended operating guidelines (ROG) for sidescan sonar Dave Long (BGS) Dave Long (BGS) Reviewed by: Janine Guinan (MI) 07/09/07 Workgroup: MESH action: 2.1 Version:

More information

Offshore grid NL. Hollandse Kust (noord) & Hollandse Kust (west Alpha) General project introduction. 14 september 2018

Offshore grid NL. Hollandse Kust (noord) & Hollandse Kust (west Alpha) General project introduction. 14 september 2018 1 Offshore grid NL Hollandse Kust (noord) & Hollandse Kust (west Alpha) General project introduction 14 september 2018 Offshore grid developer Four wind areas of 700 MW Planning of the Energy Agreement

More information

Comments of Southern Cross Cables Limited on the International Seabed Authority s Exploitation Regulations

Comments of Southern Cross Cables Limited on the International Seabed Authority s Exploitation Regulations Southern Cross Cable Network Level 5, Resimac House 45 Johnston Street, Wellington 6011 PO Box 5340 Wellington 6140, New Zealand Facsimile +64 4 499 7232 Telephone +64 4 496 3250 20 December 2017 BY ELECTRONIC

More information

Imagine that you can see a side view of a wave as it approaches a beach. Describe how the wave changes as the wave approaches the beach.

Imagine that you can see a side view of a wave as it approaches a beach. Describe how the wave changes as the wave approaches the beach. Geology 101 Name Reading Guide for Ch. 19: Shores and Coastal Processes (p. 612) Waves, Currents, and Tides (p. 614) Waves and Currents (p. 614) Imagine that you can see a side view of a wave as it approaches

More information

NEED FOR SUPPLEMENTAL BATHYMETRIC SURVEY DATA COLLECTION

NEED FOR SUPPLEMENTAL BATHYMETRIC SURVEY DATA COLLECTION 305 West Grand Avenue, Suite 300 Montvale, New Jersey 07645 Phone 201.930.9890 Fax 201.930.9805 www.anchorqea.com M EMORANDUM To: Caroline Kwan and Nica Klaber U.S. Environmental Protection Agency Region

More information

Beach Wizard: Development of an Operational Nowcast, Short-Term Forecast System for Nearshore Hydrodynamics and Bathymetric Evolution

Beach Wizard: Development of an Operational Nowcast, Short-Term Forecast System for Nearshore Hydrodynamics and Bathymetric Evolution Beach Wizard: Development of an Operational Nowcast, Short-Term Forecast System for Nearshore Hydrodynamics and Bathymetric Evolution Ad Reniers Civil Engineering and Geosciences, Delft University of Technology

More information

INTERNATIONAL HYDROGRAPHIC SURVEY STANDARDS

INTERNATIONAL HYDROGRAPHIC SURVEY STANDARDS INTERNATIONAL HYDROGRAPHIC SURVEY STANDARDS by Gerald B. MILLS 1 I. Background The International Hydrographic Organization (IHO) traces its origin to the establishment of the International Hydrographic

More information

OTC MS. Free Span Rectification by Pipeline Lowering (PL) Method N. I. Thusyanthan, K. Sivanesan & G. Murphy

OTC MS. Free Span Rectification by Pipeline Lowering (PL) Method N. I. Thusyanthan, K. Sivanesan & G. Murphy OTC-24699-MS Free Span Rectification by Pipeline Lowering (PL) Method N. I. Thusyanthan, K. Sivanesan & G. Murphy Copyright 2014, Offshore Technology Conference This paper was prepared for presentation

More information

HARBOUR SEDIMENTATION - COMPARISON WITH MODEL

HARBOUR SEDIMENTATION - COMPARISON WITH MODEL HARBOUR SEDIMENTATION - COMPARISON WITH MODEL ABSTRACT A mobile-bed model study of Pointe Sapin Harbour, in the Gulf of St. Lawrence, resulted in construction of a detached breakwater and sand trap to

More information

Physical Modeling of Nearshore Placed Dredged Material Rusty Permenter, Ernie Smith, Michael C. Mohr, Shanon Chader

Physical Modeling of Nearshore Placed Dredged Material Rusty Permenter, Ernie Smith, Michael C. Mohr, Shanon Chader Physical Modeling of Nearshore Placed Dredged Material Rusty Permenter, Ernie Smith, Michael C. Mohr, Shanon Chader Research Hydraulic Engineer ERDC-Coastal Hydraulics Laboratory October 25,2012 Study

More information

The Evolution of an Autonomous Unmanned Surface Vessel and Software for Hydrographic Survey

The Evolution of an Autonomous Unmanned Surface Vessel and Software for Hydrographic Survey The Evolution of an Autonomous Unmanned Surface Vessel and Software for Hydrographic Survey Paul Donaldson In 2017, Leidos, Inc. participated in both the Gulf of Mexico Unmanned Systems Operational Demonstration

More information

An Integrated Marine Gradiometer Array System (MGA)

An Integrated Marine Gradiometer Array System (MGA) An Integrated Marine Gradiometer Array System (MGA) For Detection and Location of Chemical and Conventional UXO/MEC in Shallow to Deep Marine and Freshwater Environments Introduction Tetra Tech EC, Inc.

More information

Body Search and Recovery Using Sonar

Body Search and Recovery Using Sonar Body Search and Recovery Using Sonar Photos Mark W. Atherton Mark W. Atherton, Echoes and Images Image courtesy FBI Dive Team Images not for distribution. All photographs and drawings courtesy and Mark

More information

CHAPTER 7.0 IMPLEMENTATION

CHAPTER 7.0 IMPLEMENTATION CHAPTER 7.0 IMPLEMENTATION Achieving the vision of the Better Streets Plan will rely on the ability to effectively fund, build and maintain improvements, and to sustain improvements over time. CHAPTER

More information

TAT 14 (Segment K) North Western Approaches

TAT 14 (Segment K) North Western Approaches Cable Awareness & Emergency Procedures Please keep clear and do not damage submarine telecoms cables. You risk the loss of your gear and catch, and international communications can be disrupted. These

More information

INTRODUCTION TO COASTAL ENGINEERING

INTRODUCTION TO COASTAL ENGINEERING The University of the West Indies Organization of American States PROFESSIONAL DEVELOPMENT PROGRAMME: COASTAL INFRASTRUCTURE DESIGN, CONSTRUCTION AND MAINTENANCE A COURSE IN COASTAL DEFENSE SYSTEMS I CHAPTER

More information

Shorelines Earth - Chapter 20 Stan Hatfield Southwestern Illinois College

Shorelines Earth - Chapter 20 Stan Hatfield Southwestern Illinois College Shorelines Earth - Chapter 20 Stan Hatfield Southwestern Illinois College The Shoreline A Dynamic Interface The shoreline is a dynamic interface (common boundary) among air, land, and the ocean. The shoreline

More information

MECHANICAL ASPECTS OF SUBMARINE CABLE ARMOUR

MECHANICAL ASPECTS OF SUBMARINE CABLE ARMOUR MECHANICAL ASPECTS OF SUBMARINE CABLE ARMOUR Ernesto Zaccone ARMORING OF SUBMARINE CABLES Submarine cables must be robust Mechanical aspects are at least as important as the electrical o nes Must withstand

More information

Point LaBarbe/McGulpin Point Response April 2 May 8, 2018 Regional Response Team 3 Meeting November, 2018

Point LaBarbe/McGulpin Point Response April 2 May 8, 2018 Regional Response Team 3 Meeting November, 2018 Point LaBarbe/McGulpin Point Response April 2 May 8, 2018 Regional Response Team 3 Meeting November, 2018 TJ Mangoni District Response Advisory Team Supervisor Ninth Coast Guard District 216-214-4285 Summary

More information

Evaluation of the Klein HydroChart 3500 Interferometric Bathymetry Sonar for NOAA Sea Floor Mapping

Evaluation of the Klein HydroChart 3500 Interferometric Bathymetry Sonar for NOAA Sea Floor Mapping Evaluation of the Klein HydroChart 3500 Interferometric Bathymetry Sonar for NOAA Sea Floor Mapping Yuhui Ai, Straud Armstrong and Dean Fleury L-3 Communications Klein Associates, Inc. 11 Klein Dr. Salem,

More information

Oceans and Coasts. Chapter 18

Oceans and Coasts. Chapter 18 Oceans and Coasts Chapter 18 Exploring the oceans The ocean floor Sediments thicken and the age of the seafloor increases from ridge to shore The continental shelf off the northeast United States Constituent

More information

Deep-sea coral protection zones and management measures

Deep-sea coral protection zones and management measures Deep-sea coral protection zones and management measures This presentation was originally provided to the New England Fishery Management Council on April 26, 2012 in Mystic, CT. Recent updates related to

More information

AGGREGATE DREDGING AND THE MARINE ENVIRONMENT

AGGREGATE DREDGING AND THE MARINE ENVIRONMENT AGGREGATE DREDGING AND THE MARINE ENVIRONMENT The marine Aggregate Levy Sustainability Fund ( marine ALSF ) programme represents one of the most substantial investments in UK marine research. The research

More information

Taranaki Tsunami Inundation Analysis. Prepared for Taranaki Civil Defence Emergency Management Group. Final Version

Taranaki Tsunami Inundation Analysis. Prepared for Taranaki Civil Defence Emergency Management Group. Final Version Taranaki Tsunami Inundation Analysis Prepared for Taranaki Civil Defence Emergency Management Group Final Version June 2012 AM 12/07 HBRC Plan Number 4362 Asset Management Group Technical Report Prepared

More information

TECHNICAL BULLETIN PINPOINT CONDUIT COUPLING AND SPLICING RECOMMENDATIONS

TECHNICAL BULLETIN PINPOINT CONDUIT COUPLING AND SPLICING RECOMMENDATIONS TECHNICAL BULLETIN PINPOINT CONDUIT COUPLING AND SPLICING RECOMMENDATIONS CONTENTS: 1.0 General Information 2.0 Preparation and Splicing of PinPoint Wire 3.0 PinPoint Direct Bury Splice Kit Specifications

More information

Submarine Cables as a Sustainable Use of the Deep Sea Environment

Submarine Cables as a Sustainable Use of the Deep Sea Environment Submarine Cables as a Sustainable Use of the Deep Sea Environment International Cable Protection Committee ( ICPC ) BBNJ IGC 1 Side Event September 13, 2018 1 About ICPC Founded in 1958, ICPC is the world

More information

Hydrographic Surveying at The Port of London

Hydrographic Surveying at The Port of London Hydrographic Surveying at The Port of London John Dillon-Leetch Port and Terminal Technology 2009 14 th October, Antwerp Overview Introduction Surveying the Thames Navigational Charting High Resolution

More information

Door County, WI Coastal Hazard Analysis Flood Risk Review Meeting. August 21, 2017

Door County, WI Coastal Hazard Analysis Flood Risk Review Meeting. August 21, 2017 Door County, WI Coastal Hazard Analysis Flood Risk Review Meeting August 21, 2017 Agenda Introductions Coastal Flood Risk Study and Mapping Program Current Status Technical Overview of Study and Mapping

More information

BOTTOM MAPPING WITH EM1002 /EM300 /TOPAS Calibration of the Simrad EM300 and EM1002 Multibeam Echo Sounders in the Langryggene calibration area.

BOTTOM MAPPING WITH EM1002 /EM300 /TOPAS Calibration of the Simrad EM300 and EM1002 Multibeam Echo Sounders in the Langryggene calibration area. BOTTOM MAPPING WITH EM1002 /EM300 /TOPAS Calibration of the Simrad EM300 and EM1002 Multibeam Echo Sounders in the Langryggene calibration area. by Igor Kazantsev Haflidi Haflidason Asgeir Steinsland Introduction

More information

Town of Duck, North Carolina

Town of Duck, North Carolina Tracking No. 00.00.2010 Erosion Mitigation And Shoreline Management Feasibility Study Town of Duck, North Carolina Coastal Planning & Engineering of North Carolina August 15, 2012 Tom Jarrett Robert Neal

More information

Morphodynamics of Borssele Wind Farm Zone

Morphodynamics of Borssele Wind Farm Zone Morphodynamics of Borssele Wind Farm Zone Meeting Tender Borssele Hendrik Jan Riezebos Tommer Vermaas Robert Hasselaar Tim Raaijmakers 17 November 2014, SER Den Haag Contents of presentation Introduction

More information

1 st Tidal and Water Level Working Group Meeting DHN, Niteroi, Brazil 31/03/09 02/04/09 Vertical Offshore Reference Framework (VORF) Chris Jones

1 st Tidal and Water Level Working Group Meeting DHN, Niteroi, Brazil 31/03/09 02/04/09 Vertical Offshore Reference Framework (VORF) Chris Jones 1 st Tidal and Water Level Working Group Meeting DHN, Niteroi, Brazil 31/03/09 02/04/09 Vertical Offshore Reference Framework (VORF) Chris Jones United Kingdom Hydrographic Office Presentation Structure

More information

W I L D W E L L C O N T R O L PRESSURE BASICS AND CONCEPTS

W I L D W E L L C O N T R O L PRESSURE BASICS AND CONCEPTS PRESSURE BASICS AND CONCEPTS Pressure Basics and Concepts Learning Objectives You will be familiarized with the following basic pressure concepts: Defining pressure Hydrostatic pressure Pressure gradient

More information

Comparison of Predicted and Measured Shoaling at Morro Bay Harbor Entrance, California

Comparison of Predicted and Measured Shoaling at Morro Bay Harbor Entrance, California Comparison of Predicted and Measured Shoaling at Morro Bay Harbor Entrance, California by Edward F. Thompson, Inocencio P. DiRamos, and Robert R. Bottin, Jr. PURPOSE: This Coastal and Hydraulics Engineering

More information

COMPENSATION LAKE DESIGN CONCEPTS AND CONSTRUCTION LESSONS LEARNED

COMPENSATION LAKE DESIGN CONCEPTS AND CONSTRUCTION LESSONS LEARNED SMA Environmental Forum 2016 COMPENSATION LAKE DESIGN CONCEPTS AND CONSTRUCTION LESSONS LEARNED Month A Tale DD, of YYYY Two Lakes Pamela Kuipers, P.Eng., MSc EXPLORE the Depths of our Experience www.norwestcorp.com

More information

from ocean to cloud SHORELINE EROSION AND IMPACT TO CABLE PROTECTION

from ocean to cloud SHORELINE EROSION AND IMPACT TO CABLE PROTECTION SHORELINE EROSION AND IMPACT TO CABLE PROTECTION Thomas E. Schaefer Jr. (TE SubCom), David Blau (TE SubCom), Ana Chamon (TE SubCom), Agustin Gutierrez Arroyo (Telefónica Global Solutions) Email: teschaefer@subcom.com

More information

3.9 FROM ISLANDS TO ATOLLS

3.9 FROM ISLANDS TO ATOLLS 3.9 1 3.9 FROM ISLANDS TO ATOLLS OBJECTIVES The students Listen to a description of the formation of volcanic islands, fringing reefs, barrier reefs, and atolls. Observe and participate in a simulation

More information

Polar Research Vessel Operational Requirements and Summary of Technical Studies

Polar Research Vessel Operational Requirements and Summary of Technical Studies Polar Research Vessel Operational Requirements and Summary of Technical Studies Presentation to UNOLS by Jim St John Science and Technology Corporation - Polar Technology Office Why a New Antarctic Research

More information

Case Study 3. Case Study 3: Cebu Island, Philippines MPA Network 10

Case Study 3. Case Study 3: Cebu Island, Philippines MPA Network 10 Case studies of mpa networks Case Study 3: Cebu Island, Philippines MPA Network 10 Location and background Cebu Island in the Philippines lies in the center of the Visayan Islands, known as an area high

More information

City of Burnaby Environmental Review Committee (ERC) Guide for Applicants

City of Burnaby Environmental Review Committee (ERC) Guide for Applicants City of Burnaby Environmental Review Committee (ERC) Guide for Applicants 2017-2018 This Guide summarizes the ERC process for project review including applications for a relaxation (variance) to the development

More information

Nemo Link s puxo campaign

Nemo Link s puxo campaign BLOCK 3 BLOCK 2 U e c n France 400000 570000 KP 0 KP 10 KP 20 KP 30 a r F 565000 BLOCK 1 450000 Belgique 0 5 ONGOING 10 15 20 km N 565000 t i n g n i K Nearshore BE Fra m o d ed KP 50 KP 60 KP 70 KP 80

More information

Moving beyond BACI: What do to when science and reality clash in marine reserve monitoring? Workshop Held: June 10 th, 2015

Moving beyond BACI: What do to when science and reality clash in marine reserve monitoring? Workshop Held: June 10 th, 2015 Moving beyond BACI: What do to when science and reality clash in marine reserve monitoring? Workshop Held: June 10 th, 2015 Challenges have arisen when implementing a BACI (Before-After-Control-Impact)

More information

Challenges in determining water surface in airborne LiDAR topobathymetry. Amar Nayegandhi, Dewberry 15 th Annual JALBTCX Workshop, June 11 th 2014

Challenges in determining water surface in airborne LiDAR topobathymetry. Amar Nayegandhi, Dewberry 15 th Annual JALBTCX Workshop, June 11 th 2014 Challenges in determining water surface in airborne LiDAR topobathymetry Amar Nayegandhi, Dewberry 15 th Annual JALBTCX Workshop, June 11 th 2014 Why topobathy LiDAR? Complements acoustic (multi-beam sonar)

More information

COMPARISON OF DEEP-WATER ADCP AND NDBC BUOY MEASUREMENTS TO HINDCAST PARAMETERS. William R. Dally and Daniel A. Osiecki

COMPARISON OF DEEP-WATER ADCP AND NDBC BUOY MEASUREMENTS TO HINDCAST PARAMETERS. William R. Dally and Daniel A. Osiecki COMPARISON OF DEEP-WATER ADCP AND NDBC BUOY MEASUREMENTS TO HINDCAST PARAMETERS William R. Dally and Daniel A. Osiecki Surfbreak Engineering Sciences, Inc. 207 Surf Road Melbourne Beach, Florida, 32951

More information

SHUTTLE-SUBs ALL OCEANS Engineering Ltd

SHUTTLE-SUBs ALL OCEANS Engineering Ltd SUK Underwater Vehicles Conference 21.11.17 SHUTTLE-SUBs AC-ROV 3000m Fly-out System Introduced in 2011 MAC-ROV 6000m Fly-out System (2017) 6000m, 4k and HD cameras, SM fibre telemetry Expandable architecture,

More information

Offshore engineering science

Offshore engineering science Offshore engineering science In this research stream theoretical models advanced geotechnical models and new numerical techniques were used in applied offshore engineering topics such as loading, design

More information

S-44 edition 5 The IHO s New Standard For Hydrographic Surveys Chris Howlett Head of Seabed Data Centre United Kingdom Hydrographic Office

S-44 edition 5 The IHO s New Standard For Hydrographic Surveys Chris Howlett Head of Seabed Data Centre United Kingdom Hydrographic Office S-44 edition 5 The IHO s New Standard For Hydrographic Surveys Chris Howlett Head of Seabed Data Centre United Kingdom Hydrographic Office Chairman of IHO Working Group that created S-44 edition 5 S-44

More information

Learn more at

Learn more at Full scale model tests of a steel catenary riser C. Bridge 1, H. Howells 1, N. Toy 2, G. Parke 2, R. Woods 2 1 2H Offshore Engineering Ltd, Woking, Surrey, UK 2 School of Engineering, University of Surrey,

More information

Advanced Surf Kayak Leader Training Notes

Advanced Surf Kayak Leader Training Notes Advanced Surf Kayak Leader Training Notes Part A Personal Paddling Skills A.1 Lifting, carrying, launching and landing The type of break surfed at this level will mean the application of a large variation

More information

Geospatial Positioning Accuracy Standards Part 5: Standards for Nautical Charting Hydrographic Surveys - Public Review Draft

Geospatial Positioning Accuracy Standards Part 5: Standards for Nautical Charting Hydrographic Surveys - Public Review Draft Appendix B FGDC Hydrographic Accuracy Standard Geospatial Positioning Accuracy Standards Part 5: Standards for Nautical Charting Hydrographic Surveys - Public Review Draft Subcommittee on Marine and Coastal

More information

Seal Extension Guidelines. Asset Management and Systems

Seal Extension Guidelines. Asset Management and Systems Seal Extension Guidelines 1. Guideline Definitions AADT - Annual Average Daily Traffic is measured at regular annual (or greater) intervals and adjusted for seasonal effects, using an approved traffic

More information

CONDUCT OF MOBILE DRILLING RIG SITE SURVEYS. Volume 2

CONDUCT OF MOBILE DRILLING RIG SITE SURVEYS. Volume 2 UK OFFSHORE OPERATORS ASSOCIATION LIMITED (SURVEYING & POSITIONING COMMITTEE) Guidelines for CONDUCT OF MOBILE DRILLING RIG SITE SURVEYS Volume 2 Issue 1 While Regulations clearly establish a requirement

More information

Implications of proposed Whanganui Port and lower Whanganui River dredging

Implications of proposed Whanganui Port and lower Whanganui River dredging PO Box 637 Wanganui 4540 Attention: Rowan McGregor Dear Rowan 1 Summary We understand that it has been proposed to bring large vessels into the Port at Whanganui requiring the excavation of a channel up

More information

An IOOS Operational Wave Observation Plan Supported by NOAA IOOS Program & USACE

An IOOS Operational Wave Observation Plan Supported by NOAA IOOS Program & USACE An IOOS Operational Wave Observation Plan Supported by NOAA IOOS Program & USACE R.E. Jensen, W.A. Birkemeier and W. Burnett JCOMM-Workshop on Wave Measurements from Buoys Wave Information to Application

More information