Maintenance Procedure

Size: px
Start display at page:

Download "Maintenance Procedure"

Transcription

1 Maintenance Procedure Table Of Contents 1.0 Preparation for Excavation Trenching / Excavation Backfill and Compaction Site Restoration...14 Attachment A Duties and Responsibilities...15 Attachment B Safety and Precautions...19 Attachment C Job Hazard Analysis...22 Attachment D Site Specific Excavation and Backfill Plan...26 Purpose and Scope The purpose of this procedure is to provide direction to individuals involved in excavation and backfill activities at a Colonial worksite. This procedure describes the controls and methods used when performing excavation and backfill activities to support maintenance or inspection tasks on existing pipelines or facilities. This procedure does NOT cover excavations under the following conditions: Greater than twenty (20) feet in depth. (Requires the development of an excavation plan by a certified Professional Engineer. See Safety Awareness Manual Trenching and Excavation.) Under or adjacent to buildings, retaining walls, sidewalks or pavement. (Excavation MAY Not be Allowed by OSHA Standards OR May require the development of an excavation plan by a certified Professional Engineer of the appropriate discipline and background. See Sam Manual Trenching and Excavation, page 4, Safety Precautions Section.) Third-party activities that impacts Colonial right-of-way or facilities. (Refer to procedure NOP- ROW-005 Third Party Excavation and Backfill.) Installation of new lines or facilities (Refer to Engineering Standards, ES Trenches and Underground Lines.) Excavation that is too deep to locate the pipelines using two techniques including line finder, Probe rod, soft dig, and manual excavation tools. PAGE 1 OF 27

2 Duties and Responsibilities COLONIAL PIPELINE COMPANY CM Refer to Attachment A for Duties and Responsibilities Safety and Precautions 1. Refer to Attachment B for Safety and Precautions References CFR , OSHA Excavation Standard, 29 CFR COOQ (API Guidance Document Appendix D) 4. NOP-ROW-003, Line Locating and Marking 5. NOP-ROW-001, Exposed Piping 6. ES , Trenches and Underground Lines 7. Safety Awareness Manual 8. Environmental Compliance Manual 9. Contractor Safety Program 10. Alignment Sheets/Facility Drawings/Delivery Line Alignment Sheets 11. USGS Maps 12. Soil Erosion and Sediment Control best management practices for pipeline maintenance activities. 13. Conduct of Operations 14. Tool Run Data Feature List 3D profile Software Profiles from Tools equipped with Inertial Navigation Systems PAGE 2 OF 27

3 Special Equipment 1. Line locating device. 2. Atmospheric Monitor (If planned excavation will exceed 4 ft. in depth or there is a potential for encountering hazardous atmospheres). 3. Soft Dig Trucks, if necessary i.e. hydrovacs. 4. Temporary marking material (flags, marking paint, ribbon). Abnormal Operating Condition 1. The following situations may require entry into an Abnormal Operating Procedure (AOP) or Emergency Operation Procedure (EOP): Fire or explosion Hazardous liquid leaks Abnormal facility condition Component failure or component malfunction 2. IF an AOP or EOP entry condition is encountered while performing this procedure, ENSURE the appropriate individuals are notified. Prerequisites 1. Individuals performing activities covered by this procedure must have the appropriate Operator Qualifications. 2. Daily Work Permit and Safety Checklist have been completed with JSA. 3. Excavation Safety Form has been completed (if Option 1 is not selected). 4. The One-Call notification has been made in accordance with local laws and regulations. 5. Colonial s line has been located and marked in accordance with NOP-ROW-003, Line Locating and Marking. 6. There must be a Competent Person under OSHA s Excavation Standard, 29 CFR , or under local rules and regulations, if they are more stringent than the OSHA Standard, at the work site during excavation activities. It is preferred that the Excavating Contractor supplies the Competent Person for the excavation activities. 7. All Permits shall be obtained where required by state/local agencies, including roadways, DOT Right-of-ways, and counties that require excavation permits. 8. Attachment A Duties and Responsibilities has been reviewed by personnel filling the listed roles. 9. Attachment B Safety and Precautions has been reviewed by ALL personnel involved in the excavation activities. PAGE 3 OF 27

4 Procedure 1.0 Preparation for Excavation 1.1. VERIFY One-Call ticket has been processed VERIFY ALL foreign lines and company facilities, listed on the One-Call ticket, have been marked in the planned excavation area IF the planned excavation area changes, all activities shall cease, and this procedure shall be restarted. NOTE: Adequately marking the line should clearly identify the path of the buried line. However, if existing line markers adequately identify the path outside the work area, it is not necessary to install additional temporary markers further than the limits of the excavation, especially if additional hazards are involved (e.g., high traffic volume, stream crossings) that make the placement of additional markers impractical. This is an OQ covered task. NOTE: If excavation is within a company or shipper facility, refer to Section VERIFY company s pipeline has been adequately marked up to 100 feet in each direction from the planned excavation per NOP-ROW-003. In the event the pipelines are deep and cannot be located and this procedure cannot be followed, notification shall be made to the Project Manager and a written site specific excavation plan shall be developed and approved by the Project Manager before beginning any excavation activity. This plan may include using feature lists, surveyors with ILI profile, 3D graphics from ILI Data, extensive probing, etc. PAGE 4 OF 27

5 CAUTION Probe the area that is to be excavated even when sloping the ditch back or cleaning it out. DO NOT excavate outside the limits of the probed area COMPARE marked lines with Alignment Sheets. CAUTION Alignment sheets do not always reflect all pipe bends. Additional data should be used to identify all PIs, sag and over bends. Dig remediation list are excellent means of identifying pipeline features from past ILI Tool runs IF comparison reveals any of the following problems between Alignment Sheets and marked lines, RESOLVE problem before excavation activities begin IF discrepancy is due to inaccurate Alignment Sheets, COMPLETE a Change Diagram (Form C3331) Alignment sheets, Facility drawings and/or other available data such as feature lists, ILI Profiles, etc. MUST be reviewed prior to excavation for any appurtenances on the line(s) that may present a hazard during excavation IF planned excavation will impact property owners, ATTEMPT to contact owners, AND INFORM them of pending work. CAUTION Barbed wire must NOT be used for protection around excavations in highly populated areas unless livestock is present IMPLEMENT the following site security measures, as needed, based on the above walk down: Barbed wire (Minimum three strands) Warning barricades Safety fencing, strongly encouraged everywhere (Minimum height of three feet) Earth berms Flashing lights PAGE 5 OF 27

6 1.7. COMPLETE the following forms from the Safety Awareness Manual. Daily Work Permit and Safety Checklist Excavation Safety Form. It is not necessary to complete if type C soil is selected or excavation is less than 4 deep IMPLEMENT the following types of excavation protection, as needed, Shoring Sloping Trench boxes, with tabulated data Work Mats Soil moisture stabilization Water diversion (ditches, pumps, etc.) Leveled work areas for excavation equipment (in areas with significant cross slope) Entry and exit ramps or ladders (required if excavation will exceed 4 feet in depth) Reflective signs or flashing lights (potential traffic hazards) NOTE: Attachment D can be used as a guide to develop a Site-Specific Excavation and Backfill plan. However, the plan will need to be modified to address any maintenance or inspection work that will take place in the excavated area, as well as the excavation activities. NOTE: The Competent Person, whether Colonial or Contractor, is responsible for developing the Site-Specific Excavation and Backfill Plan. Input from the Excavation Operator and other team members should be obtained for the Site-Specific Excavation and Backfill Plan. (Review with Safety if Required by OSHA) 1.9. REVIEW AND APPROVE Site-Specific Excavation and Backfill Plan in Attachment D. PAGE 6 OF 27

7 1.10. IF excavation is in response to a known OR suspected leak, PERFORM the following actions: VERIFY the Line Controller (Control Center/Facility Operator) has completed the following procedures, as appropriate: Control Center AOP-CC-J01 Suspected Leak EOP-CC-K01 Leak Facility Operator AOP-CPC-J01 Suspected Leak EOP-CPC-K01 Leak ESTABLISH continuous Atmospheric Monitoring for oxygen and LEL levels. A plan shall be established for the monitoring of toxic chemicals ARRANGE for handling and disposal of contaminated soils OBTAIN Fire Extinguishers AND other safety equipment, as required ENSURE excavation equipment is in safe working order REMOVE OR STABILIZE any surface obstruction(s) that may create a hazard CONDUCT a Pre-Job Brief with ALL individuals involved in the excavation. PAGE 7 OF 27

8 2.0 Trenching / Excavation NOTE: Do not jack hammer concrete unless all sides of the concrete are exposed and the possibility of a power cable and/or piping running through the concrete can be eliminated. Red or Dyed concrete indicate high voltage, but the concrete may not look dyed, especially in red clay soils CONFIRM depth AND horizontal location of pipeline and adjacent underground structures in at least two places in the planned excavation work area using two of the following methods: Line locator Hand Excavation Probe Rod Soft Dig Technology (i.e. Hydrovac) 2.2. VISUALLY CONFIRM the location of the pipeline using Hand Excavation or Soft Dig Technology until the pipeline is exposed. IF THE PIPELINE IS NOT LOCATED AND VISUALLY CONFIRMED using these techniques, no mechanical excavation shall begin until a written site specific excavation plan, which may include a combination of mechanical excavation and soft excavation techniques, is approved by the Project Manager 2.3. In Permitted areas (i.e. Wetlands), ENSURE excavation remains in the permitted footprint. CAUTION The primary function of the Spotter is to spot for the Excavation Operator. The Spotter must NOT be distracted with other tasks while mechanical excavation is actually underway WHEN the location of the pipeline has been visually confirmed, ENSURE mechanical excavation is done parallel to pipeline, use caution around PI s and appurtenances (TOR, etc.) ENSURE excavation equipment is maintained a safe distance from the pipeline and to where the equipment operator can maintain eye contact with the swamper. Any and all equipment not involved in the excavation shall be maintained downhill and a minimum of 3 feet from the excavation. PAGE 8 OF 27

9 When digging a PI (bend), the outside of the bend should be dug first. If it is not feasible to do so, a site specific excavation plan is required. For multiple parallel PI s a Site Specific Excavation plan is required IF excavation affects an agricultural or residential area where topsoil must be protected, REMOVE top six inches of soil or until color change indicates subsoil reached, AND PLACE on a separate pile from the excavation spoil pile ENSURE spoil pile is maintained a MINIMUM of two feet from edge of excavation AND angle of repose is LESS THAN 45º from horizontal IF excavation involves soil contaminated with product, ENSURE spoil handling and disposal is conducted as directed by the District Environmental Team 2.7. REQUIRE hand excavation under any of the following conditions: Excavation closer than 2 feet from top or bottom of pipeline until pipeline has been exposed. Excavation closer than 2 feet from sides of pipeline until pipeline has been exposed Excavation closer than 1 foot from top or sides after pipeline has been exposed. This means that after the pipe has been exposed, no mechanical excavation is permitted within 1 foot around the pipe. Complex excavation involving tight quarters WHEN the pipeline(s) are in marshes, lakes, in shallow water, REQUIRE water lifting or jetting and under any of the following conditions: Excavation is closer than 3 feet from the top of the pipe. Excavation is closer than 2 feet from the side of the pipeline IF a line hit occurs OR an anomaly containing visible cracks is observed, TERMINATE all excavation activities, AND NOTIFY Line Controller (Control Center or Facility Operator) of condition IF excavation exceeds 4 feet in depth, ENSURE the following is implemented before allowing entry into excavation. Atmospheric Monitoring Entry and exit equipment Adequate and OSHA-compliant sloping or shoring PAGE 9 OF 27

10 2.11. TERMINATE all excavation activities if any of the following are encountered. Hazardous atmosphere Potential cave-ins Indications of failures of protective systems (sloping, shoring, etc.) Colonial s Representative (who, as defined in Attachment A is the person who has responsibility for performing inspection activities according to this Procedure (e.g., Project Inspector, Technician, etc. i ) and may be either a Colonial employee or a contractor)leaves the excavation site. Hazardous material is discovered in the ditch including blasting material, chemicals, potentially pressured vessels, medical waste, etc. Proceed only after consulting with Project Manager and/or safety personnel. Upon the initial discovery of excavation being located in a possible landfill or landfill material in excavation site, work must be stopped, update or develop a JHA before proceeding. Company representative must notify the District Environmental Team and HSS to identify possible materials that could be dangerous to life and health that has been discovered. It may be determined that an Industrial Hygienist may need to on site for the duration of the project. Identify the nearest hospitals and have GPS coordinates for the jobsite for easy location for medical personnel if needed IF excavation activities will be stopped for an extended period of time OR left unattended overnight, PERFORM the following actions NOTIFY Line Controller (Control Center or Facility Operator) ENSURE site security measures are in place Water control measures have been taken if necessary. NOTE: Do not pinch out from under the pipeline with the track-hoe arm extended over the pipeline WHEN excavating UNDER pipeline, EXCAVATE from NEAR SIDE of pipeline IF length of unsupported pipeline reaches twenty feet, INSTALL appropriate supports to prevent undue stress on line, OR OBTAIN Engineering evaluation that identifies MAXIMUM safe span. PAGE 10 OF 27

11 2.14. IF rock is being excavated, INSTALL mechanical shielding for the pipeline using oak planks, blasting mats, oversized pipe or sleeve, or similar whenever the pipe is exposed even if there is only a small portion of the pipe that is exposed IF rocks larger than the hoe bucket must be removed, PRIOR to removal, FRACTURE the rocks to a size that the hoe bucket can carry. Be sure to shield pipe as stated above before fracturing rock. PAGE 11 OF 27

12 3.0 Backfill and Compaction 3.1. ENSURE ALL inspection activities AND post-maintenance testing are complete ENSURE the excavation and backfill is free of any metal objects (cans, hand tools, clamps, scrap metal) and non-soil materials ENSURE that any material excavated from a landfill or identified as landfill type material shall not be placed back into the excavation. Clean backfill shall be used to support and pad the pipe ENSURE the pipe has been padded where necessary BEFORE beginning backfill operations, ENSURE that the Excavation Operator and Spotter have reviewed the Site Specific Excavation and Backfill Plan. CAUTION Backfill must be placed, NOT pushed. For example, the first 2-feet of backfill around and over the top of the pipe can be accomplished with a backhoe but NOT a bulldozer WHEN equipment is backfilling within 2-feet of any Colonial asset, ENSURE that the Colonial Representative, as defined above and in Attachment A, is in the work area. NOTE: Best compaction is attained when moisture content of the soil is at or near 10%. In some cases, adding lime to the backfill mixture or in severe conditions bringing in select back fill may be necessary to obtain proper compaction of the backfill. In some cases Fly Ash or Lime can be added to reduce the moisture content of the soil. Locations where compaction test are required a proctor will be required once the added material has been mixed with the soil IF compaction of backfill is necessary due to conditions at the location (e.g., steep slope or cross-slope, proximity to road or railroad crossings, or potential for heavy equipment traffic), ENSURE the following compaction guidelines are followed. Backfill is placed in MAXIMUM of 6-inch lifts AND compacted between lifts. WHEN backfilling under the pipeline, USE hydraulic, Pneumatic, and/or Mechanical compacting equipment for compaction until backfill comes up to pipe. PAGE 12 OF 27

13 CAUTION For long excavations such as recoating or casing removal, special monitoring of pipe settlement is required. Pipe support compaction plan will be required ENSURE that ONLY clean, soft backfill is placed into the excavation UNTIL 2-feet of good backfill material surrounds the pipe ENSURE backfill is placed equally along both sides of pipe and properly compacted, UNTIL pipe is covered ENSURE backfill is crowned, where appropriate, to compensate for settling CREATE diversion berms and cross ditches as cross-slope requires, preventing pooling along trench line. (Refer to ES for guidance.) ENSURE temporary erosion control methods are monitored once they have been installed and removed when the excavation and backfill activities are no longer a threat to the environment. PAGE 13 OF 27

14 4.0 Site Restoration 4.1. REPLACE any soil moved to provide level foundation for equipment REPLACE topsoil over spoil crown, AND RESEED with appropriate ground cover REMOVE all construction debris and other trash from work site INSTALL OR REPAIR Line markers as necessary END PAGE 14 OF 27

15 Attachment A Duties and Responsibilities The following list of duties and responsibilities represents the normal course of events. In some instances, the same individual may serve in the positions of Project Inspector and Competent Person. Additionally, some listed tasks may be performed by individuals other than those named below. However, the individual identified below remains responsible for ensuring that the tasks are properly performed. 1. Colonial Representative is the person who has the responsibility for performing inspection activities according to this Procedure (e.g., Project Inspector, Technician, etc.): Ensures the alignment sheets, ILI data or other material that identifies pipeline features have been reviewed and are available for reference. Ensures that he or she is at the work site anytime excavation activities are in progress. Ensures work activities are stopped if there is a concern for injury, pipeline integrity, public safety, or damage to Colonial facilities. Ensures proper one-calls have been made. Ensures compliance with all state one call laws. Ensures all necessary environmental permits are obtained or the proper notification is made to the agencies having jurisdiction. Ensures State/local permits have been obtained for excavations, if required. Ensures landowners have been notified. Ensures that the Site-Specific Excavation and Backfill Plan, if, required, has been reviewed and is followed Ensures that the following are completed before work begins: 1) Daily Work Permit and Safety Checklist. 2) Job Safety Analysis. 3) Excavation Safety Form, if required Conducts tailgate safety meetings. Ensures individuals who are performing Covered Tasks, as identified in the Operator Qualification manual, have appropriate OQ documentation. Coordinates commencement of work with Line Controller (Control Center and Facility Operator of nearest staffed facility). Ensures communications with Line Controller (Control Center and/or Facility Operator at nearest staffed facility) is available. PAGE 15 OF 27

16 Ensures that all excavation and backfill activities are performed in accordance with this Procedure and all applicable pipeline safety regulations. Remains in the work area and continuously monitors all excavation and backfill activities. Ensures permanent pipe support and backfill material are satisfactory and meet Colonial specifications. Conducts inspections of excavations daily, before starting work, as needed throughout the workday, and after rainstorms or other change in conditions that may impact the excavation. Inspects excavations for potential cave-ins, indications of failures of protective systems (sloping, shoring, etc.), and hazardous atmospheres or other hazardous conditions. If hazardous conditions are encountered, ensure exposed individuals are removed from the hazardous area until necessary safety precautions have been taken. Ensures spoil material is safely stored at least 2-feet from the edge of excavation. Ensures mechanical equipment not directly involved with the work at the excavation site does not operate closer than 3-feet from the edge of the excavation and is securely parked when not in use. Monitors excavation activities, equipment and water removal, as necessary. Ensures that soil classifications are performed and the need for shoring or similar protective systems is evaluated. Records data, as required. Determines the effects of operating equipment, traffic, etc. around the excavation. Ensures excavations are clearly marked and properly barricaded, if left open. 2. Competent Person Is capable of identifying existing and predictable hazards in the surroundings, or working conditions that are unsanitary, hazardous, or dangerous to employees and has authorization to take prompt corrective measures to eliminate them. Develops the Site-Specific Excavation and Backfill Plan with input from the Excavation Operator and Spotter (Swamper). Ensures spoil material is safely stored at least 2-feet from the edge of excavation. Ensures mechanical equipment not directly involved with the work at the excavation site does not operate closer than 3-feet from the edge of the excavation and is securely parked when not in use. Monitors excavation activities, equipment and water removal, as necessary. Determines soil classifications and the need for shoring or similar protective systems. PAGE 16 OF 27

17 3. Line Controller (Control Center/Facility Operator) Takes measures, if appropriate, to mitigate the consequences should an accident occur (isolate line, reduce line pressure, etc.). 4. Excavation Operator The Excavation Operator is the contractor employee operating the excavation equipment. Is responsible for an accident free workplace. Shall perform a Job Hazard Analysis to identify and mitigate hazards in the area of excavation. Ensures work activities are stopped if there is a concern for injury, pipeline integrity, public safety, or damage to Colonial facilities. Confirms the location of the pipeline using a line locator, probe rod, hand excavation or soft dig techniques prior to mechanically excavating the planned excavation area. Seeks guidance from the Spotter to prevent pipeline damage. Safely stores spoil material at least 2-feet from the edge of excavation. Provides significant assistance and input in the development of Site-specific Excavation and Backfill Plan. Reviews and understands this procedure. 5. Spotter (Swamper) The Spotter is the person spotting the Excavation Operator. The Spotter shall NOT perform other duties if they interfere with the ability to perform the duties listed below. Is responsible for an accident free workplace. Shall be Operator Qualified to perform all covered tasks associated with excavation and backfilling or shall be immediately supervised by a Qualified Individual. Ensures work activities are stopped if there is a concern for injury, pipeline integrity, public safety, or damage to Colonial facilities. Using two methods, confirms the location of the pipeline using a line locator, probe rod, hand excavation or soft dig techniques prior to allowing any mechanically excavating in the planned excavation area. The Spotter s most important responsibility is to direct the Excavation Operator to prevent pipeline damage. He/She is responsible for maintaining top and side clearances. Remains vigilant as to the potential for hazardous conditions and damage to the line. Observes excavation progress and remains vigilant to potential hazards. During excavation uses a line locator and a probe rod to verify pipe location. PAGE 17 OF 27

18 Reviews and understands this procedure. Shall be responsible for guiding and directing backhoe while mobilizing and demobilizing to prevent hitting power lines or other obstructions. This is especially necessary when working in congested areas, around power lines and when moving track hoes and cranes around the worksite. PAGE 18 OF 27

19 Attachment B Safety and Precautions Refer to the Operations Section of the Safety Awareness Manual, under Trenching and Excavation, for additional information regarding safety concerns. Colonial personnel must maintain a high level of concern for the safety of contractors and subcontractors performing work for Colonial. Contractors must comply with the Colonial Contractor s Safety Plan. 1. Individuals must wear appropriate safety equipment (hard hat, safety shoes, etc.). 2. Individuals who are exposed to public vehicular traffic must wear warning vests or other suitable garments marked with or made of reflective or high-visibility material. 3. Individuals should NOT operate equipment without first being properly trained to handle it and being fully alerted to its potential hazards. 4. Fire extinguishers must be in place (hand held). 5. The Line Controller (Control Center/ Facility Operator) must be informed of all actions performed that may potentially affect pipeline operations. 6. Support systems, (e.g., shoring, bracing, or underpinning) must be used to ensure the stability of adjacent structures such as buildings, walls, sidewalks, or pavements (OSHA requirement). 7. Excavation below the level of the base or footing of any foundation or retaining wall is prohibited unless one of the following conditions is met (OSHA requirement): A support system or underpinning is provided. The excavation is in stable rock. A registered professional engineer determines that the structure is sufficiently removed from the excavation and that the excavation will not pose a hazard to employees. 8. Excavations under sidewalks or pavement are prohibited unless an appropriately designed support system is provided or other effective method is used (OSHA requirement). 9. Before a person enters excavations greater than 4-feet in depth or excavations where an oxygen deficient atmosphere exists or could possibly be expected to exist, a Competent Person must test the atmosphere using an oxygen/lel monitor extended down in the excavation (OSHA requirement). 10. If any controls are used to reduce atmospheric contaminants to acceptable levels, the excavation shall be tested continuously for deficiencies in oxygen, toxic vapors, and an explosive atmosphere (OSHA requirement). 11. Unknown or unidentifiable materials work will cease until notifications have been made to the District Environmental Manager and HSSE. This will require developing a new Site Specific Excavation and Backfill Plan along with all of the Safety paperwork. PAGE 19 OF 27

20 12. Access and Egress (OSHA requirement) COLONIAL PIPELINE COMPANY CM-102 Where individuals are required to be in excavations greater than 4-feet deep, adequate means of egress, such as ramps (maximum 20% grade for ramp), ladders, steps, or other safe means, must be provided within 25-feet of lateral travel. If structural ramps are used as a means of access or egress, they must be designed by a competent person. Structural members used to form ramps must be of uniform thickness and joined in a manner to prevent tripping or displacement. 13. Sloping (OSHA requirement) Sloping of the walls of the excavation should be performed in accordance with OSHA guidelines depending on the class of soil and soil conditions, such as: 1) Water 2) Silty materials 3) Loose boulders 4) Evidence of erosion, deep frost action, or slide planes Another option is to use what is called OPTION 1, which means you do not classify the soil, but slope or shore to the most stringent requirements. 14. Shoring (OSHA requirement) When an excavation requires shoring, refer to the guidance provided in ES Trenching and Underground Lines on the materials and methods that should be used. 15. Falls and Equipment Material or equipment that might fall or roll into an excavation must be kept at least 2- feet from the edge of the excavation, or provide retaining barriers, or both. Where necessary, scaling must be provided to remove loose rock or install protective barricades to protect individuals against falling rock, soil, or other materials. Work on faces of sloped or benched excavations at levels above other individuals is prohibited unless individuals at lower levels are adequately protected from the hazard of falling, rolling, or sliding material or equipment. Individuals are NOT allowed under loads that are handled by lifting or digging equipment. Individuals working around equipment should be aware of equipment movements (swinging, lifting, bucket movements, etc.) Spotter(s) watch equipment as it moves around job site. PAGE 20 OF 27

21 16. Water Accumulation COLONIAL PIPELINE COMPANY CM-102 Individuals are prohibited from working in excavations where water has accumulated unless adequate protective measures have been taken. Where necessary, diversion ditches, dikes, or other suitable methods will be used to prevent surface water from entering the excavation and to provide adequate drainage of the area adjacent to the excavation. 17. Factors Affecting Soil Stability. CAUTION must be exercised under the following conditions, where soil stability may be significantly degraded: Soil expansion due to freezing or thawing decreases its stability and may result in shoring or support systems not performing adequately. Large excavations that are left open for extended periods are particularly subject to wall collapse due to changes in weather producing either an increase or a decrease in soil moisture content. Structures in the vicinity of excavations increase the forces at the excavation walls, particularly if close to the excavation. Examples of such structures are heavy equipment, vehicles, and materials (pipes, timber, or spoil piles). Passing vehicles, blasting, and operation of excavation equipment or certain tools can loosen soil and increase the possibility of cave-ins. Soils subjected to prior excavation and backfilling may take years to regain the cohesive nature of undisturbed soil. PAGE 21 OF 27

22 Attachment C Job Hazard Analysis Attachment C can be used as a guide to develop a Job Hazard Analysis. This is not the JHA. However, the JHA will also need to identify any hazards associated with the maintenance or inspection work that will take place in the excavated area. EXCAVATION HAZARDS Proper communication / notification Unknown utilities Traffic Soil conditions ACTIONS / CONSIDERATIONS Make one-call, notify landowners, and proper authorities (Colonial or non-colonial) Proper working equipment (radio, cell phone, satellite phone, etc. Identify Hospitals and medical facilities prior to beginning work. Check strip map Check surrounding area for markers Additional probing Check community for location of gas, electric, and water lines Make the proper one-calls Road at work/injection site to be closed and barricaded only authorized personnel posted Traffic control personnel (someone to watch for vehicles entering and leaving work site) Limit access of vehicles to work site Designated parking area Construction signs and flashers installed at entrances to work sites Proper sloping, shoring or trench boxes, if needed Fill out proper excavation safety form (Colonial form C7020) Refer to Colonial Excavation and Backfill Standard Excavation and handling of soil Store per Colonial environmental standard Groundwater Adjacent pipelines Equipment close to excavation Mud at roadsides at work site entrances Terrain conditions Egress and Ingress Have pumps available and pump water to area according to Colonial Pipeline Co. Environmental Specifications Diversion (Flumes, Coffer damns, etc.) Locate, mark and ensure proper cover and protection for other pipelines Limit amount of activity over pipelines Have Spotter observe equipment, as it is moving Have safety personnel monitor equipment movement Have Excavation Operator follow Colonial Excavation and Backfill Standard Monitor road condition, and handle as necessary All personnel are responsible for keeping road clean Make sure there is good footing in ditches for worker to move around Use caution on hillsides, creek banks, etc. Incorporate protective measures in excavation and backfill plan Mark and define escape routes Keep egress routes free of obstructions Backfilling Refer to Colonial Excavation and Backfill Standard PAGE 22 OF 27

23 Rev. 4 01/03/2012 EXCAVATION HAZARDS Possible atmospheric contamination Site security Fenced areas vs. non-fenced areas ACTIONS / CONSIDERATIONS Sniffing atmospheric check Monitor oxygen and LEL during N2 injection, cut out sites, and bleed off sites If LEL is above 3% at work sites a sphere will be installed or controls will be put in place to reduce LEL below 3% before work can progress in the excavation. This is due to the toxicity level of hydrocarbons. Refer to Colonial Excavation and Backfill Standard Erosion control Install proper erosion control as needed for weather conditions Weather conditions Be aware of weather conditions and prepare as necessary Pipe supports Support every 20-feet unless special conditions exist Removal and disposal of coating Critter/Wildlife factor Water hazards Tripping hazard Improperly marked pipe size / lamination Product Spill Overhead Power Lines Waste or Hazardous Material Wear proper PPE when removing coating Dispose of coating per colonial environmental specifications Pay attention to surroundings Have first aid kit available Life jackets required near water bodies Refer to Accident Prevention Manual Be aware of potential tripping hazards (welding leads and extension cords) Maintain proper house keeping Ultrasound location to be welded Mag- particle after welding X-Ray after tie-ins During Blowdown, open valves slowly to check for product. Before starting cold cut, check for product in the line (dipstick), have vacuum truck on site Caution operators against contacting overhead power lines Identify on excavation and backfill plan Set up barriers if practical Spotter to watch for them with equipment is moving Shutdown and consult with safety personnel to determine specific needs including monitoring, PPE, etc. Work must be stopped, update or develop a JHA before proceeding. Company representative must notify the District Environmental Manager and HSSE to identify possible materials that could be dangerous to life and health that has been discovered. It may be determined that an Industrial Hygienist may need to on site for the duration of the project. Identify the nearest hospitals and have GPS coordinates for the jobsite for easy location for medical personnel if needed. PAGE 23 OF 27

24 Rev. 4 01/03/2012 OTHER TASKS WITH ADDITIONAL HAZARDS: WELDING / TAPPING Flying debris Ignition source Burns Cutting and Grinding Electrical hazard Tapping failure Drill steel binds Laminated pipe ABRASIVE CLEANING Flying debris LIFTING / RIGGING AND PILING / SHORING Overhead Hazard Pinch points CASING REMOVAL / ARCH GOUGE ADDITIONAL HAZARDS ACTIONS / CONSIDERATIONS Proper eye protection Face shields and goggles Lower Explosive Limit (LEL) / Oxygen monitoring Manned fire extinguishers Proper procedures and PPE First Aid Kit available See flying debris See ignition source Proper PPE Proper Grinding Disc for Grinder Guards on Grinder Inspect cords and equipment Proper grounding Notify Controller Follow Emergency Response Plan Inspect drill steel for wear Use proper tapping procedures Ultrasound area where cutting or welding for proper pipe thickness Mag- particle area after welding for cracks Proper eye protection Face shields and goggles PAGE 24 OF 27 ACTIONS / CONSIDERATIONS ACTIONS / CONSIDERATIONS Be aware of overhead obstructions Ensure tag lines are in place Be aware of possible pinch point locations such as sleeve material, line-up clamps, etc. Stay away from moving equipment and only move in to rig once the operator has stopped operating the equipment and is ready to hook up. Use tag lines to clear yourself from objects being moved. ACTIONS / CONSIDERATIONS Pipeline not properly shielded Install shield between pipeline and casing Flying debris Ignition source Proper eye protection Face shields and goggles Lower Explosive Limit (LEL) / Oxygen monitoring Manned fire extinguishers

25 Rev. 4 01/03/2012 ADDITIONAL HAZARDS WELDING / TAPPING Burns Cutting and Grinding Electrical hazard DIGGING ON WORK MATS Slide off mats onto pipeline Drop mats on pipeline when moving them ACTIONS / CONSIDERATIONS Proper procedures and PPE First Aid Kit available See flying debris See ignition source Proper PPE Inspect cords and equipment Proper grounding ACTIONS / CONSIDERATIONS Ensure mats are level and secure to dig on Ensure area for mats will support equipment Ensure mat hook is secure Ensure mat cables are in good condition CONSEQUENCES OF HAZARDS: Environmental Damage Personal injury Pipeline damage Property damage Equipment damage PAGE 25 OF 27

26 CM-102 Rev. 4 01/03/2012 Attachment D Site Specific Excavation and Backfill Plan Attachment D can be used as a guide to develop a Site-Specific Excavation and Backfill plan. However, the plan will need to be modified to address any maintenance or inspection work that will take place in the excavated area, as well as the excavation activities. The Competent Person, whether Colonial or Contractor, is responsible for developing the Site- Specific Excavation and Backfill Plan. Input from the Excavation Operator and other team members should be obtained for the Site-Specific Excavation and Backfill Plan. Upon the discovery of landfill material a new Site-Specific Excavation and Backfill Plan will be developed or conditions warrant procedure not valid for the excavation. Date: Line: Location: Reason for Excavation: Size, Depth, Drawing All excavations meeting any of the following conditions must be planned and designed by a registered professional engineer trained in an appropriate discipline: Excavations in excess of 20 feet in depth. Excavations adjacent to structures/improvements. One Call Ticket # Locate Methods used: Excavation Equipment Used Make: Model: EXCAVATION PLAN Method of excavation: Method of ingress and egress: Method of pipe support: Protective measures applied to excavation walls: Type of pipe shield used: Placement of spoil: COMMENTS (or N/A if appropriate) SITE SPECIFIC CONSIDERATIONS Traffic Adjacent structures & their condition Overhead & underground utilities Soil type Livestock / wildlife Surface/ground water Weather Topography (slopes, working area, etc.) Residential area children Adequate room for spoil piles Work mats COMMENTS (or N/A if appropriate) PAGE 26 OF 27

27 CM-102 Rev. 4 01/03/2012 Description of area (rural, city, farm, livestock, etc.) Barriers or signs used Abnormal events PI s Other: INSPECTOR: EXCAVATION OPERATOR SPOTTER: OQ PERSONNEL PERFORMING TASK: Location No. State Map No. One Call Ticket No. Task Before excavation begins the Colonial Pipeline Company and the contractor and contractor s workers will review the Colonial Pipeline Company Excavation and Backfill Standard and check equipment for good working order. Excavations will be made on Colonial s The excavation will be approximately ft. deep with sloping or appropriate shoring as needed. The bottom of the ditch will be approximately ft. wide. The amount of pipe to be uncovered will be determined by a Colonial Pipeline Company representative. The spoil will be stored adjacent to the excavation at a distance to provide safe walking around the edge of the excavation and according to Colonial Pipeline Company Excavation and Backfill Standard. Ingress and egress of the trench will be ladders and other means of exit every 25 ft. and on both sides of the excavation. Pipe supports will be dirt plugs or other mechanical means of support. Clean soft backfill material will be placed, not pushed in the excavation until 2 ft. of good backfill material surrounds the pipe. Backfill will be performed with the use of a backhoe, or track hoe. i Nothing in this Procedure or any of its attachments is intended to create any type of employment or agency relationship between Colonial and any individual or entity that provides services to Colonial as an independent contractor, including any contractor who fulfills the role of the Colonial Representative, as that term is defined in Exhibit A and used throughout this Procedure. PAGE 27 OF 27

This section applies to all open excavations made in the earth's surface. Excavations are defined to include trenches.

This section applies to all open excavations made in the earth's surface. Excavations are defined to include trenches. Appendix H Specific Excavation Requirements This section applies to all open excavations made in the earth's surface. Excavations are defined to include trenches. Surface encumbrances All surface encumbrances

More information

Excavations and Trenches

Excavations and Trenches Purpose Excavation and trenching are among the most hazardous work activities undertaken by the TNRD. This document outlines general requirements and specific safe work procedures to ensure the health

More information

BP OIL -- TOLEDO REFINERY

BP OIL -- TOLEDO REFINERY BP OIL -- TOLEDO REFINERY Toledo Refinery Procedure No.: SAF 054 Effective Date: June 29, 2017 Ground Disturbance Rev. No.: 11 Revised By: Mario Rizo Auth. By: Chris Conley (Signature of file) Page 1 of

More information

TAO Safety Policy No. HS-5.1 Page 1 of 15 Revision No. 2 Revision Date: July 19, 2005

TAO Safety Policy No. HS-5.1 Page 1 of 15 Revision No. 2 Revision Date: July 19, 2005 TAO Safety Policy No. HS-5.1 Page 1 of 15 Revision No. 2 1.0 OVERVIEW This safety policy provides guidance for conducting trenching and excavation activities at project sites. Emphasis is placed on sloping

More information

TRENCHING/SHORING/EXCAVATIONS Revision Date: 04/2017

TRENCHING/SHORING/EXCAVATIONS Revision Date: 04/2017 TRENCHING/SHORING/EXCAVATIONS 41.1 PURPOSE 41.1.1 The purpose of this policy is to provide guidance and instruction to safely perform work around or in excavations or trenches and protect employees from

More information

MODULAR ALUMINUM PANEL SHIELDS MAPS

MODULAR ALUMINUM PANEL SHIELDS MAPS MODULAR ALUMINUM PANEL SHIELDS MAPS 3330 S. SAM HOUSTON PKWY E. HOUSTON, TEXAS 77047 Phone: 713.943.0750 Toll Free: 800.231.6662 Fax: 713. 943.8483 April 16, 2009 MODULAR ALUMINUM PANEL SHIELDS Page 2

More information

STEEL TRENCH SHIELDS DW MODELS

STEEL TRENCH SHIELDS DW MODELS STEEL TRENCH SHIELDS DW MODELS 3330 S. SAM HOUSTON PKWY E. HOUSTON, TEXAS 77047 Phone: 713.943.0750 Toll Free: 800.231.6662 Fax: 713. 943.8483 COPYRIGHT, U.S.A., SPEED SHORE CORPORATION, 2009 April 16,

More information

STEEL TRENCH SHIELDS TUFF-LITE MODELS

STEEL TRENCH SHIELDS TUFF-LITE MODELS STEEL TRENCH SHIELDS TUFF-LITE MODELS 3330 S. SAM HOUSTON PKWY E. HOUSTON, TEXAS 77047 Phone: 713.943.0750 Toll Free: 800.231.6662 Fax: 713. 943.8483 April 16, 2009 TRENCH SHIELDS TUFF-LITE TM Page 2 of

More information

"STEEL FRAMED" ALUMINUM PANEL SHIELDS

STEEL FRAMED ALUMINUM PANEL SHIELDS "STEEL FRAMED" ALUMINUM PANEL SHIELDS MANUFACTURE S TABULATED DATA 3330 S. Sam Houston Pkwy Houston, Texas 77047 (713)943-0750 USA Toll Free 1-800-231-6662 Fax (713)943-8483 Www.speedshore.com PRINTED

More information

SPEED SHORE MANUFACTURER S TABULATED DATA "MHS" MODELS. STEEL MANHOLE SHIELDS 4 Single Wall 4 Double Wall 4 Double Wall with Cut-Outs

SPEED SHORE MANUFACTURER S TABULATED DATA MHS MODELS. STEEL MANHOLE SHIELDS 4 Single Wall 4 Double Wall 4 Double Wall with Cut-Outs SPEED SHORE MANUFACTURER S TABULATED DATA "MHS" MODELS STEEL MANHOLE SHIELDS 4 Single Wall 4 Double Wall 4 Double Wall with Cut-Outs January 01, 2005 3330 S. SAM HOUSTON PKWY E. HOUSTON, TEXAS 77047 Tel:

More information

SPEED SHORE MANUFACTURER S TABULATED DATA MANGUARDS. October 31, 2005

SPEED SHORE MANUFACTURER S TABULATED DATA MANGUARDS. October 31, 2005 SPEED SHORE MANUFACTURER S TABULATED DATA MANGUARDS October 31, 2005 3330 S. SAM HOUSTON PKWY E. HOUSTON, TEXAS 77047 Tel: (713) 943-0750 U.S.A. Toll Free: (800) 231-6662 Fax: (713) 943-8483 COPYRIGHT,

More information

Minimum Safety Requirements for Contractors Working on Railway Property

Minimum Safety Requirements for Contractors Working on Railway Property Minimum Safety Requirements for Contractors Working on Railway Property Effective_ April 1, 2007 Introduction Canadian Pacific is committed to provide a Safe and Healthy working environment for all Railway

More information

APPENDIX A. Appendix A: Fall Hazards Lesson Test Instructor Copy (answers bold/italic), Student copy to distribute follows

APPENDIX A. Appendix A: Fall Hazards Lesson Test Instructor Copy (answers bold/italic), Student copy to distribute follows APPENDIX A Appendix A: Fall Hazards Lesson Test Instructor Copy (answers bold/italic), Student copy to distribute follows 1. In general, fall protection must be provided to construction workers who are

More information

Appendix 4C - Sample SWMS Trenching

Appendix 4C - Sample SWMS Trenching Appendix 4C - Sample SWMS Trenching SAFE WORK METHOD STATEMENT SWMS Reference : Insert document number : Version A Date : Workplace / Project : Company Address: Work Activity / Job / Task or Process :

More information

Striking an underground pipeline or underground electric line can lead to serious injury or death. If you hit either, call (800) , even if

Striking an underground pipeline or underground electric line can lead to serious injury or death. If you hit either, call (800) , even if 1 Striking an underground pipeline or underground electric line can lead to serious injury or death. If you hit either, call (800) 477-5050, even if there is no apparent damage. Call 911 if gas is blowing

More information

Excavation and Trenching

Excavation and Trenching Excavation and Trenching An excavation is defined as any man-made cut, cavity, trench, or depression in the earth s surface formed by earth removal. Trenches are narrow, underground excavations that are

More information

Vacuum Excavation in the vicinity of the Wellington Electricity Network

Vacuum Excavation in the vicinity of the Wellington Electricity Network Vacuum Excavation in the vicinity of the Network. Document no: ENG-116 Document Rev: 1 Issue Status: Final Issue Date: 14/05/2015 Page 1 of 9 Contents 1. PURPOSE... 3 2. POLICY... 3 3. SCOPE... 3 4. REFERENCES...

More information

Safety Policy and Procedure

Safety Policy and Procedure Safety Policy and Procedure Policy Number 004 Authorized By: The Cianbro Companies Alan Burton Title: Excavation Safety Effective Date: 01/01/75 Page 1 of 16 1 Status 1.1 Update of existing policy, effective

More information

Electric and Natural Gas Safety Slide Show Presenter s Notes

Electric and Natural Gas Safety Slide Show Presenter s Notes Contractor Beware Electric and Natural Gas Safety Slide Show Presenter s Notes Slide 1 Before darkening the room, offer a welcome and overview. Begin by introducing the program and its topic: Today s training

More information

New Hampshire Public Utilities Commission CFR 49 Part 192 Regulations. MINIMUM Pipeline Safety Regulations

New Hampshire Public Utilities Commission CFR 49 Part 192 Regulations. MINIMUM Pipeline Safety Regulations New Hampshire Public Utilities Commission CFR 49 Part 192 Regulations MINIMUM Pipeline Safety Regulations Application for Jurisdictional LPG Operators 1 Pipeline Safety Regulations 49 CFR Part 192 (NOTE:

More information

ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL

ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL AFTER MARCH 1, 2012 ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL 400.1 Description. This item shall govern for all excavation required for the construction of all structures, except pipe or box sewers for

More information

Scope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such activities.

Scope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such activities. 11/13/1995 4 5/20/2013 1 of 10 Authority and Scope Regulation: 29 CFR 1910.146 Scope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such

More information

OSHA Federal Standards October 1, 2016 September 30, 2017

OSHA Federal Standards October 1, 2016 September 30, 2017 OSHA Federal Standards October 1, 2016 September 30, 2017 29 CFR 1926 SUBPARTS 29 CFR 1926. C M L L E M M E X M MOST FREQUENTLY CITED SERIOUS VIOLATIONS IN CONSTRUCTION 2017.501(b)(13) FALL PROTECTION

More information

HEALTH AND SAFETY PROGRAM 201 HOT TAP PERMIT/FILLET WELD REPAIRS

HEALTH AND SAFETY PROGRAM 201 HOT TAP PERMIT/FILLET WELD REPAIRS Page 1 of 15 1.0 PURPOSE 1.1. Axiall, Plaquemine Complex, has developed this Hot Tap Permit Program to eliminate potential accidents, injuries, and to enhance employee protection. 1.2. To provide for the

More information

BUTTERFLY VALVES Series 800

BUTTERFLY VALVES Series 800 BUTTERFLY VALVES Series 800 WARNING Before proceeding read ALL instructions and become familiar with the equipment and associated drawings. Follow ALL applicable safety regulations and codes for pressurized

More information

Barricades and Falling Object Protection Plans

Barricades and Falling Object Protection Plans Title: Barricades and Falling Object Protection Plans Freeport Site Function: Environmental, Health & Standard No.: BCF020.042 Rev 7 Page: 1 of 7 REVISION HISTORY Date Revision Number Details of Change

More information

CONFINED SPACE WRITTEN PROGRAM

CONFINED SPACE WRITTEN PROGRAM CONFINED SPACE WRITTEN PROGRAM Maple River Public Schools ISD#2135 Confined Space Entry Plan (Permit Required) Maple River Public School Plan last updated: October, 2014 Authority and Scope Regulation:

More information

U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL

U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL SAFE -14 Page 1 of 8 U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL FUNCTION Safety TOPIC Hotwork Permit Program OBJECTIVE(S): GENERAL POLICY: To provide a work atmosphere that is conducive to

More information

CONTRACTOR SAFETY RULES

CONTRACTOR SAFETY RULES CONTRACTOR SAFETY RULES CONTRACTOR SAFETY RULES AND REGULATIONS This manual sets forth policy with regards to contractor safety. Each Quinn facility consists of one or several diverse operations under

More information

NATURAL GAS MAINTENANCE. Part 192 Subpart "M"

NATURAL GAS MAINTENANCE. Part 192 Subpart M NATURAL GAS MAINTENANCE Part 192 Subpart "M" CONTACT INFORMATION Pamela West Pipeline Safety Specialist U.S. Department of Transportation PHMSA Inspector Training and Qualifications Main: (405) 686-2310

More information

PACIFIC SHORING, LLC ALUMINUM SHORING PRODUCTS PSH HEAVY DUTY HYDRAULIC WALER RAIL SYSTEM. TABULATED DATA Effective December 10, 2013

PACIFIC SHORING, LLC ALUMINUM SHORING PRODUCTS PSH HEAVY DUTY HYDRAULIC WALER RAIL SYSTEM. TABULATED DATA Effective December 10, 2013 1 HEAVY DUTY HYDRAULIC WALER RAIL SYSTEM Effective December 10, 2013 PSH 265 Roberts Avenue Santa Rosa, Ca. 95407 (707) 575-9014 Construction Engineering Resource 1837 Wright Street Santa Rosa, Ca. 95404

More information

PACIFIC SHORING, LLC ALUMINUM SHORING PRODUCTS HEAVY DUTY HYDRAULIC WALER RAIL SYSTEM. TABULATED DATA Effective August 25, 2015

PACIFIC SHORING, LLC ALUMINUM SHORING PRODUCTS HEAVY DUTY HYDRAULIC WALER RAIL SYSTEM. TABULATED DATA Effective August 25, 2015 1 HEAVY DUTY HYDRAULIC WALER RAIL SYSTEM Effective August 25, 2015 PSH 265 Roberts Avenue Santa Rosa, Ca. 95407 (707) 575-9014 Construction Engineering Resource 1837 Wright Street Santa Rosa, Ca. 95404

More information

SAFE WORK METHOD STATEMENT TRENCHING OPERATIONS

SAFE WORK METHOD STATEMENT TRENCHING OPERATIONS SAFE WORK METHOD STATEMENT TRENCHING OPETIONS Personal Protective Equipment Foot Protection Hearing Protection High Visibility Head Protection Eye Protection Breathing Protection Day Operations Normal

More information

Lisle-Woodridge Fire District Trench Rescue STANDARD OPERATING GUIDELINES

Lisle-Woodridge Fire District Trench Rescue STANDARD OPERATING GUIDELINES Lisle-Woodridge Fire District Trench Rescue STANDARD OPERATING GUIDELINES Purpose Scope Definition S.O.P. Rescue Sector Site Control Sector Equip. & Rigging Sector Air Quality Sector Entry Sector Technical

More information

Proper use of the JOB SAFETY ANALYSIS (JSA) FORM

Proper use of the JOB SAFETY ANALYSIS (JSA) FORM Safety Review & Tool Box Talk Company: Supervisor: Topic: Proper use of the JOB SAFETY ANALYSIS (JSA) FORM Participants Please Fill in this form and fax to (905) 847-1275 or scan and e-mail to tessa@camacc.com

More information

CONSTRUCTION SAFETY PROGRAM FOR. Golder Acoustics Inc.

CONSTRUCTION SAFETY PROGRAM FOR. Golder Acoustics Inc. CONSTRUCTION SAFETY PROGRAM FOR Golder Acoustics Inc. TABLE OF CONTENTS Topic... Page Safety and Health Policy... 2 Safety and Health Objectives... 3 Job Site Inspections... 4 Contractor Safety Administrator...

More information

CIRCULAR NO. O-13. Recommended Practices for Manual Protection of Highway/Railway Grade Crossings

CIRCULAR NO. O-13. Recommended Practices for Manual Protection of Highway/Railway Grade Crossings CIRCULAR NO. O-13 Recommended Practices for Manual Protection of Highway/Railway Grade Crossings Effective: October 1, 2004 CONTENTS 1. SCOPE 2. GENERAL PRINCIPLES 3. DEFINITIONS 4. PROTECTION REQUIRED

More information

Committee Input No. 35-NFPA [ Chapter 1 ] Submitter Information Verification. Committee Statement

Committee Input No. 35-NFPA [ Chapter 1 ] Submitter Information Verification. Committee Statement Committee Input No. 35-NFPA 1670-2015 [ Chapter 1 ] Chapter 1 Administration 1.1 Scope. 1.1.1* This standard shall identify and establish levels of functional capability for conducting operations at technical

More information

Aluminum Sheeting Guide (ASG)

Aluminum Sheeting Guide (ASG) Tabulated Data Aluminum Sheeting Guide (ASG) February 2016 Copyright, U.S.A.,Griswold Machine & Eng., 2016 594 Mendon Road, Union City, MI 49094 (800) 248 2054 Fax: (517) 741 7483 CAUTION EXCAVATION PROCEDURES

More information

1. What is the top priority when working on Canadian Pacific (CP) property? 2. When working on CP property what must all Contractors comply with?

1. What is the top priority when working on Canadian Pacific (CP) property? 2. When working on CP property what must all Contractors comply with? 1. What is the top priority when working on Canadian Pacific (CP) property? A. Production B. Safety C. Quality D. Project deadline 2. When working on CP property what must all Contractors comply with?

More information

Monitoring excavation in the highway

Monitoring excavation in the highway This unit covers the requirements that you must meet when monitoring excavation work in the highway. You must ensure that you act in accordance with all current specifications and procedures and that you

More information

ROAD OCCUPANCY PERMIT APPLICATION # Damascus Township, 60 Conklin Hill Road, Damascus, PA Tel Fax

ROAD OCCUPANCY PERMIT APPLICATION # Damascus Township, 60 Conklin Hill Road, Damascus, PA Tel Fax Instructions: For a driveway access permit, fill in sections 1, 2, 3 and 4, and the appropriate drawings and sign. For a Utility access, fill in sections 1, 2, 3 and 5, and figures 1 and 3. Prepare a detailed

More information

General Safety and Health Provisions for Construction Self Inspection Checklist

General Safety and Health Provisions for Construction Self Inspection Checklist Optional Information Name of School: Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: General Safety and Health Provisions for Construction Self Inspection Checklist Instructions:

More information

How severely could the risk hurt someone?

How severely could the risk hurt someone? Safe Work Method Statement No: WMS-08 Task: Install Drainage This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised

More information

SAFEWORK PRACTICES EQUIVALENCY PROCEDURE FOR ACCESSING FLOATING ROOF TANKS ON STORAGE TANKS IN SERVICE CAT A-2 SOP #33

SAFEWORK PRACTICES EQUIVALENCY PROCEDURE FOR ACCESSING FLOATING ROOF TANKS ON STORAGE TANKS IN SERVICE CAT A-2 SOP #33 SUNCOR ENERGY PRODUCTS DISTRIBUTION TERMINAL OPERATING MANUAL STANDARD OPERATING PROCEDURE SAFEWORK PRACTICES EQUIVALENCY PROCEDURE FOR ACCESSING FLOATING ROOF TANKS ON STORAGE TANKS IN SERVICE Date Issued:

More information

Permit-Required Confined Spaces...29CFR

Permit-Required Confined Spaces...29CFR (Compliance Audit) Section (c) General Requirements 1) Has the employer performed a workplace inspection to determine if there are Yes No NA permit-required confined spaces (PRCS) present? 2) If the workplace

More information

Original Date of Issue: 04/09

Original Date of Issue: 04/09 POLICIES AND PROCEDURES DEPARTMENT: Environmental Health and Safety SUBJECT: Electrical Safety Program Original Date of Issue: 04/09 Reviewed 12/2011 Revised 12/2011 BACKGROUND ELECTRIC SHOCK It is well

More information

Dry Hydrants. The installation of a non-pressurized pipe system into local water sources provides a ready means of supplying water to fire engines.

Dry Hydrants. The installation of a non-pressurized pipe system into local water sources provides a ready means of supplying water to fire engines. Dry Hydrants What is a Dry Hydrant? A dry hydrant is a non-pressurized pipe system permanently installed in existing lakes, ponds and streams that provides a suction supply of water to a fire department

More information

In addition to this SOP, the policies and procedures of each operating company will be strictly observed by Rockwater personnel.

In addition to this SOP, the policies and procedures of each operating company will be strictly observed by Rockwater personnel. SOP FB-08 (Revised MAR 2014) STANDARD OPERATING PROCEDURES-FLOWBACK Hydrogen Sulfide Operations Section 1.0 Introduction and Background Rockwater Energy Solutions, Inc. (and all its affiliated and subsidiary

More information

HAZARDOUS WASTE OPERATIONS AND EMERGENCY RESPONSE

HAZARDOUS WASTE OPERATIONS AND EMERGENCY RESPONSE Page 1 of 10 HAZARDOUS WASTE OPERATIONS AND EMERGENCY RESPONSE 1.0 SCOPE This Performance Assessment Guide for Hazardous Waste Operations and Emergency Response (HAZWOPER) will be used to carry out the

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT EXCAVATION OR TRENCHING Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES

More information

6. Each mitigation was verified and individually documented

6. Each mitigation was verified and individually documented CHESM/MSW Field Verification Instructions: All information in sections A, B and C must be completed. Information in section B related to subcontractors should be obtained from the work crew if possible.

More information

OSHA 30 Syllabus. Laborers Training School. Time: 40 hours. Maximum Class Size: 30. Prerequisites: None

OSHA 30 Syllabus. Laborers Training School. Time: 40 hours. Maximum Class Size: 30. Prerequisites: None Time: 40 hours Maximum Class Size: 30 Prerequisites: None Course Description: The 40-hour OSHA Outreach Training Program provides training for workers and employers on the recognition, avoidance, abatement,

More information

RULES OF THE OIL AND GAS PROGRAM DIVISION OF WATER RESOURCES CHAPTER DRILLING WELLS TABLE OF CONTENTS

RULES OF THE OIL AND GAS PROGRAM DIVISION OF WATER RESOURCES CHAPTER DRILLING WELLS TABLE OF CONTENTS RULES OF THE OIL AND GAS PROGRAM DIVISION OF WATER RESOURCES CHAPTER 0400-52-06 DRILLING WELLS TABLE OF CONTENTS 0400-52-06-.01 Drilling Equipment 0400-52-06-.03 Casingheads 0400-52-06-.02 Blowout Prevention

More information

DAILY EXCAVATION CHECKLIST

DAILY EXCAVATION CHECKLIST Appendix 2 Forms DAILY EXCAVATION CHECKLIST Client Project Name Project Location Job Number Excavation Size (Length x Width x Depth) Protective System Used Activities In Excavation Competent Person Date

More information

GAS PIPELINE SAFETY GUIDE.

GAS PIPELINE SAFETY GUIDE. GAS PIPELINE SAFETY GUIDE. Date of issue 27/02/2017 Date of next review 27/02/2018 Page 1 Vector Limited 2017 Gas Pipeline Safety Guide February 2017 CONTENTS CONTENTS...2 WORKING SAFELY... 3 Your Legal

More information

DIRECTIONAL DRILLING SAFE WORK PRACTICE

DIRECTIONAL DRILLING SAFE WORK PRACTICE NORSEMAN SAFE WORK RACTICES DIRECTIONAL DRILLING SAFE WORK RACTICE UROSE The purpose of this practice is to promote compliance with both government and company guidelines regarding directional drilling

More information

Responsibilities / Accountability

Responsibilities / Accountability Responsibilities / Accountability What we will cover Brief history of OPP safety program OPP s commitment to safety Safety responsibilities Accountability for safety Employee expectations History of Safety

More information

Tabulated Data Lite-Shield 20 System

Tabulated Data Lite-Shield 20 System Tabulated Data Lite-Shield 20 System November, 2014 Copyright, U.S.A.,Griswold Machine & Eng., 2012 594 Mendon Road, Union City, MI 49094 (800) 248-2054 Fax: (517) 741-7483 CAUTION EXCAVATION PROCEDURES

More information

Confined Space Entry

Confined Space Entry Confined Space Entry Purpose The purpose of this document is to establish methods to identify confined spaces, classify them according to their risks, and establish guidelines necessary for the safe preparation,

More information

3M Eyewear Fit System

3M Eyewear Fit System 3M Eyewear Fit System Background Occupational use of safety eyewear must be in compliance with applicable health and safety standards. In the U.S., employers must comply with the OSHA personal protective

More information

SLIDE RAIL INSTALLATION GUIDE MANUFACTURE S TABULATED DATA

SLIDE RAIL INSTALLATION GUIDE MANUFACTURE S TABULATED DATA SLIDE RAIL INSTALLATION GUIDE MANUFACTURE S TABULATED DATA 3330 S. Sam Houston Pkwy Houston, Texas 77047 (713)943-0750 USA Toll Free 1-800-231-6662 Fax (713)943-8483 Www.speedshore.com PRINTED IN U.S.A.

More information

EQUIPMENT AND MATERIALS

EQUIPMENT AND MATERIALS SCUD Procedure # EMER004 Page 1 of 5 SCOPE AND PURPOSE This procedure is to provide performing outside leak investigations with the necessary procedures for prompt and effective response and to protect

More information

Version 1.0 March 2016

Version 1.0 March 2016 POL Permit to Work Information for Shipping Agents Version 1.0 March 2016 Page 1 of 9 Introduction The objective of the Permit to Work process is to ensure Port Otago Limited and its operational Staff,

More information

UNIVERSITY OF NOTRE DAME CONFINED SPACE ENTRY POLICY

UNIVERSITY OF NOTRE DAME CONFINED SPACE ENTRY POLICY UNIVERSITY OF NOTRE DAME CONFINED SPACE ENTRY POLICY Revised: February 2004 TABLE OF CONTENTS I. Introduction.. -4- II. Definition of a Confined Space -4- III. Responsibilities -5- A. University of Notre

More information

TRENCH AND EXCAVATION COLLAPSE

TRENCH AND EXCAVATION COLLAPSE TRENCH AND EXCAVATION COLLAPSE A. GENERAL This guideline provides operational guidance at rescue incidents that involve the location, disentanglement and removal of victims from sub-surface trench and

More information

Safety Manual Section 6 Confined Space

Safety Manual Section 6 Confined Space 6. CONFINED SPACE ENTRY Introduction The following sections provide general guidelines and procedures for confined space entry. This section covers the following topics: Topic Page 6.1 Types of s... 6-2

More information

Proper Operation of Heath Consultants Incorporated Plunger Bar

Proper Operation of Heath Consultants Incorporated Plunger Bar Proper Operation of Heath Consultants Incorporated Plunger Bar Heath Consultants Incorporated 9030 Monroe Road Houston, TX 77061 (800) HEATH-US www.heathus.com Notice The contents of this manual are proprietary

More information

Health & Safety Policy and Procedures Manual SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY

Health & Safety Policy and Procedures Manual SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY 1. CONTROL OF HAZARDOUS ENERGY POLICY AND PROCEDURES A. OSHA References: 29 CFR 1910.147, 29 CFR 1910.332, 29 CFR 1910.333, 29 CFR 1926.417 B.

More information

The Johns Hopkins University/The Johns Hopkins Hospital Health, Safety and Environment Manual Safety Policies:

The Johns Hopkins University/The Johns Hopkins Hospital Health, Safety and Environment Manual Safety Policies: Page 1 of 6 Keywords: Airborne Combustible, Atmospheric Monitoring, Atmospheric Oxygen, Authorized Entrant, Body Harness, Combustible Gas Meter, Communication Procedure, Confined Space, CPR, Entry, Entry

More information

Confined Space Entry

Confined Space Entry Confined Space Entry Purpose The purpose of this chapter is to establish methods to identify confined spaces, classify them according to their risks, and establish guidelines necessary for the safe preparation,

More information

Confined Space Entry Procedure

Confined Space Entry Procedure Purpose The purpose of this chapter is to establish methods to identify confined spaces, classify them according to their risks, and establish guidelines necessary for the safe preparation, entry and rescue

More information

Orchard Farm Fire Protection District Standard Operating Procedure

Orchard Farm Fire Protection District Standard Operating Procedure Orchard Farm Fire Protection District Standard Operating Procedure Division: 200 Emergency Operations Section: 202 Fire & Rescue Subject: Supersedes: N/A Approved By: Page: 1 of 6 Date Last Reviewed: N/A

More information

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , ,

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , , ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR 1910.331 335-29 CFR 1926.302, 1926.416, 1926.417 BASIS: The National Safety Council estimates that there are at least 300 deaths

More information

Permit-Required Confined Space Entry Program

Permit-Required Confined Space Entry Program Safety & Health Program Permit-Required Confined Space Entry Program General Company Policy 10627 Midwest Industrial Boulevard, St. Louis, MO Phone: 314-785-6425 Fax: 314-785-6426 The purpose of this program

More information

Lockout/Tagout - Energy Control Program

Lockout/Tagout - Energy Control Program Lockout/Tagout - Energy Control Program Lockout and Tagging of ELECTRICAL Circuits This portion of the K.R. Miller Contractors, Inc. safety program has been created to maintain a written copy of procedures

More information

University of Vermont Department of Physical Plant Personal Protective Equipment Program

University of Vermont Department of Physical Plant Personal Protective Equipment Program University of Vermont Department of Physical Plant Personal Protective Equipment Program REVISED AND DISTRIBUTED BY: THE UNIVERSITY OF VERMONT DEPARTMENT OF PHYSICAL PLANT TRAINING AND COMPLIANCE OFFICE

More information

INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD)

INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) FACILITY OPERATOR: NextEra Energy Resources, LLC 700 Universe Boulevard Juno Beach, FL 33408 For Horizontal Directional Drilling Contents

More information

How severely could the risk hurt someone? Low/Insignificant First aid

How severely could the risk hurt someone? Low/Insignificant First aid Safe Work Method Statement No: WMS-02 Task: Concreting, Formwork and Steel Fixing This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia)

More information

Confined Space Program

Confined Space Program Insert City Name Page 1 of 6 Purpose Regularly, confined spaces must be entered for inspection, cleaning or repair. Such spaces can present unusual hazards such as lack of sufficient oxygen, special mechanical

More information

CONFINED SPACES. Procedures for Permit-required ALTERNATIVE TO A FULL PERMIT ENTRY. Written Programs

CONFINED SPACES. Procedures for Permit-required ALTERNATIVE TO A FULL PERMIT ENTRY. Written Programs THEME nº17: RESPONSIBLE: Confined Spaces (OSHA) Werson Monteiro ALTERNATIVE TO A FULL PERMIT ENTRY Under certain conditions described in the stard, the employer may use alternate procedures for worker

More information

SPECIAL OPERATIONS COMMAND (SOC) SUPPORT LADDER COMPANIES

SPECIAL OPERATIONS COMMAND (SOC) SUPPORT LADDER COMPANIES FIRE TACTICS AND PROCEDURES November 3, 2003 SPECIAL OPERATIONS COMMAND (SOC) SUPPORT LADDER COMPANIES 1. INTRODUCTION 1.1 Special Operations Command (SOC) Support Ladder Companies have been formed to

More information

SITE SPECIFIC SAFETY PLAN (SSSP)

SITE SPECIFIC SAFETY PLAN (SSSP) SITE SPECIFIC SAFETY PLAN (SSSP) This plan shall be completed and reviewed with the Corporate Safety Department before work commences. Completed plans shall be maintained and kept on site with the project

More information

CONFINED SPACE PROGRAM

CONFINED SPACE PROGRAM CONFINED SPACE PROGRAM Last updated: November 2017 1.0 PURPOSE Entry into a confined space represents a significant risk of serious injury or death to individuals not prepared for the hazards they may

More information

Work Activity (e.g. Road Work): Work Location:.

Work Activity (e.g. Road Work): Work Location:. Working with Cranes Work Activity (e.g. Road Work): Work Location:. GENERAL INFORMATION Hinchinbrook Shire Council Lannercost Street Ingham Qld, 4850 ABN 46 291 971 168 Ph: 47764610 All personnel conducting

More information

SUMMIT COUNTY SPECIAL OPERATIONS RESCUE TEAM TRENCH RESCUE BRANCH TRENCH RESCUE OPERATIONS

SUMMIT COUNTY SPECIAL OPERATIONS RESCUE TEAM TRENCH RESCUE BRANCH TRENCH RESCUE OPERATIONS SUMMIT COUNTY SPECIAL OPERATIONS RESCUE TEAM TRENCH RESCUE BRANCH TRENCH RESCUE OPERATIONS I. INTRODUCTION Summit County SORT Trench Rescue Branch shall assist the local jurisdiction with command and control

More information

Confined Space Entry Program 8 CCR 5157

Confined Space Entry Program 8 CCR 5157 TABLE OF CONTENTS 1. POLICY... 2 2. PURPOSE... 2 3. SCOPE... 2 4. DEFINITIONS... 2 5. CONFINED SPACES IN THE SACRAMENTO STATE... 4 6. PERMIT SPACE ENTRY - PERSONNEL RESPONSIBILITIES... 4 6.1. CONFINED

More information

SECTION TRAFFIC REGULATIONS

SECTION TRAFFIC REGULATIONS SECTION 01550 TRAFFIC REGULATIONS PART 1 - GENERAL 1.01 OBJECTIVES A. The Contractor shall provide for safe movement of vehicular, bicycle and pedestrian traffic, including persons with disabilities in

More information

ELECTRIC OPERATING PROCEDURES Date: 11/01/06

ELECTRIC OPERATING PROCEDURES Date: 11/01/06 Doc No.: NG-USA EOP D001 Page: 1 of 5 ELECTRIC OPERATING PROCEDURES SUBJECT: Cutouts Open/Enclosed Type SECTION: Distribution/Overhead REFERENCE: National Grid Retail Company Safety Manuals National Grid

More information

CONFINED SPACE POLICY

CONFINED SPACE POLICY Policy No. 6 THE CITY OF POMONA SAFETY POLICIES AND PROCEDURES CONFINED SPACE POLICY City Manager I. PURPOSE The purpose of the City of Pomona Confined Space Policy is to ensure that employees are adequately

More information

CONFINED SPACE PROGRAM

CONFINED SPACE PROGRAM CONFINED SPACE PROGRAM I. Purpose This Confined Space Program has been developed in accordance with the Occupational Safety and Health Administration (OSHA) regulations 29 CFR 1910.146. The purpose of

More information

Total s Golden rules

Total s Golden rules Total s Golden rules Golden rule No. 9: Excavation works Excavation works The many risks we regularly face in our activities include those related to excavation works. It s wrong to think that only people

More information

State University of New York College at Oneonta

State University of New York College at Oneonta State University of New York College at Oneonta CONFINED SPACE ENTRY POLICY - PROCEDURE REVIEWED 05/11/17 CONFINED SPACE ENTRY - WRITTEN PLAN POLICY The State University College at Oneonta is committed

More information

ISD #535 Rochester Public Schools

ISD #535 Rochester Public Schools ISD #535 Rochester Public Schools Health & Safety Office Maintenance Service Building 10 9½ St SE Rochester, MN 55904 507-328-4507 Management Plan for Machine Guarding Modification Date Document Modification

More information

CONFINED SPACE PROGRAM

CONFINED SPACE PROGRAM CONFINED SPACE PROGRAM A confined space, as defined in 29 CFR 1910.146: Is large enough and so configured that an employee can bodily enter and perform assigned work AND Has limited or restricted means

More information

OPERATING PROCEDURES

OPERATING PROCEDURES OPERATING PROCEDURES 1.0 Purpose This element identifies Petsec s Operating Procedures for its Safety and Environmental Management System (SEMS) Program; it applies to all Petsec operations. Petsec is

More information

WORKPLACE SAFETY INSPECTIONS TABLE OF CONTENTS INTRODUCTION...2 OBJECTIVE...2 REFERENCES...2 PREREQUISITES...2 PRECAUTIONS...2 CHECKLISTS...

WORKPLACE SAFETY INSPECTIONS TABLE OF CONTENTS INTRODUCTION...2 OBJECTIVE...2 REFERENCES...2 PREREQUISITES...2 PRECAUTIONS...2 CHECKLISTS... REVISION 0 PAGE 1 OF 8 TABLE OF CONTENTS SECTION PAGE INTRODUCTION...2 OBJECTIVE...2 REFERENCES...2 PREREQUISITES...2 PRECAUTIONS...2 CHECKLISTS...2 PROCEDURE...3 Responsibilities...3 Work Area Safety

More information

Annual CCR Landfill Inspection OML Existing Landfill OML Expansion Phase 1

Annual CCR Landfill Inspection OML Existing Landfill OML Expansion Phase 1 Annual CCR Landfill Inspection OML Existing Landfill OML Expansion Phase 1 Ottumwa-Midland Landfill Prepared for: Ottumwa-Midland Landfill 15300 130 th Street Ottumwa, Iowa 52501 Prepared by: SCS ENGINEERS

More information

Confined Spaces OSHA 1926 AA

Confined Spaces OSHA 1926 AA Confined Spaces OSHA 1926 AA 1926.1201-1213 Confined Spaces Objectives: Understanding why the OSHA requirements are needed Identify four categories of hazards that may be present entering in confined spaces

More information

Clear up confusion between the requirements for confined spaces and grain storage structures.

Clear up confusion between the requirements for confined spaces and grain storage structures. 1 Clear up confusion between the requirements for confined spaces and grain storage structures. Discuss safe methods of entry. Keep employees safe during entry! 2 3 4 Work to identify ways to eliminate

More information