1 Doc No.: NG-USA EOP D001 Page: 1 of 5 ELECTRIC OPERATING PROCEDURES SUBJECT: Cutouts Open/Enclosed Type SECTION: Distribution/Overhead REFERENCE: National Grid Retail Company Safety Manuals National Grid Safety and Health Policies & Procedures OSHA National Grid Distribution Construction Standards National Electric Safety Code (NESC) Applicable Work Procedures GENERAL INFORMATION: The purpose of this procedure is to provide information and work methods for working on (operation or replacement) or in the vicinity of open or enclosed cutouts. Failure of any in-service distribution equipment is an eventuality. Adherence to proper work procedures must always occur to minimize the risk of any hazard that could occur from failure. National Grid continues to evaluate improved or alternate materials and designs for distribution equipment requirements. PROGRAM ADMINISTRATOR: SCOPE: Distribution Engineering Services I. Background Open or Enclosed Type Fused Cutouts II. Jobsite Hazard Evaluation III. Work Process Requirements IV. Cutout Removal/Replacement APPLICABILITY: This procedure will apply to all qualified workers (see definition) who may perform work on or near exposed energized parts. DEFINITIONS: Qualified Workers (as defined in ) Workers shall be trained in and familiar with the safety related work practices, safety procedures and other safety requirements that pertain to their respective job assignments. Workers shall also be trained in and familiar with any other safety practices, including applicable emergency procedures (such as pole top/bucket rescue). Qualified workers shall be trained and competent in: Supersedes Document Dated: 08/01/06 Authorized By: Director-Distribution Engineering Svcs. Approved By: VP- Engineering Services.

2 Skills and techniques necessary to distinguish exposed live parts. Determining nominal voltage of exposed live parts. Knowledge of minimum approach distances. Proper use of precautionary techniques, use of PPE including insulating and shielding materials and properly rated insulated tools for working on or near energized parts of electrical equipment. I. BACKGROUND OPEN OR ENCLOSED TYPE FUSED CUTOUTS The general design of cutouts has undergone modification over time. This work procedure is intended to highlight the progression and limitation resulting in the transition from enclosed style cutouts, to banded style cutouts, to potted style cutouts, and finally polymeric style cutouts. Enclosed cutouts are designed to enclose the fuse tube with top, bottom and center mounting assemblies cemented into the cavity in the porcelain body. Banded style cutouts have the center mounting pin, top, and bottom assemblies U bolted to the porcelain fuse body. Potted style cutouts have the top, bottom and center mounting assemblies cemented into a cavity in the porcelain body. The Polymeric cutout is designed using a fiberglass rod with attachments either bolted or molded to the rod with a covering of polymeric material (silicone rubber and/or EDPM). The failure mode of each type of cutout differs; however, all have a finite life expectancy. General failure modes for the different types of cutouts are as follows: Enclosed type cutouts fail due to internal contamination/tracking and porcelain breakage. Banded type cutouts fail with fuse tube burning up. Potted type cutouts fail due to tracking, cracking, and porcelain breakage. The failure mode for Polymeric type cutouts has not been established, but may be via leakage/tracking. Enclosed Porcelain Banded Cutout Potted Cutout Polymeric Due to the mechanical failure mode and potential hazard associated with potted porcelain cutouts, National Grid is no longer purchasing this style of cutout. National Grid s preferred cutout style is the polymeric style. These materials have performed well in electrical testing, and do not exhibit the mechanical failure mode seen in the potted porcelain cutouts. Page 2 of 5

3 II. JOB SITE HAZARD EVALUATION Whether the job entails routine line work, operating a cutout, replacing a cutout, or work on or near a cutout due to an emergency situation, a thorough inspection of poles and pole top must be conducted and documented on a written job brief. Any defective equipment found as part of the job site hazard evaluation must be repaired or replaced. At a minimum, the following items shall be reviewed/evaluated/during the hazard evaluation: All appropriate Personal Protective Equipment, which includes, but is not limited to hard hat, eye protection, flame retardant clothing, and rubber gloves and sleeves must be utilized as required by the National Grid Retail Company Safety Manuals and applicable work procedures. Insulating protective equipment such as rubber blankets, line hose and fiberglass barrier guards must be utilized as required. Minimum approach distance and proximity of equipment to be worked on. The condition and location of all cutouts on the pole/poles with particular attention to the tap lead length and possible items that could be contacted during a cutout failure. Condition of the cutout (inspect for cracks or fractures, tracking evidence or discolored connections). The condition of the crossarms and pole top with particular attention to any signs of burning. Any hazards from non-standard construction. Delta system or potential back-feed. Upon completion of the Job Site Evaluation the qualified worker will be prepared to take the necessary precautions to eliminate, avoid or mitigate any foreseeable or unforeseeable hazards. The qualified worker will be prepared to take additional electrical safeguards, including the use of hot stick/live line equipment, the use of additional line and equipment cover-up, the placement of circuits or portions of circuits on non-reclosing/hot line tag, or the de-energization of customers, circuits, or parts of circuits, in order to safely complete the work. III. WORK PROCESS REQUIREMENTS The replacement of both good and defective potted porcelain cutouts will be accomplished as part of any work performed on poles or structures. Specific conditions and work requirements for cutout replacements are listed below: Prior to performing routine or emergency work in the primary area, all potted porcelain cutouts on poles or structures shall be thoroughly inspected for visible hazards and replaced. Additional precautions should be taken if defects were identified as part of the inspection process.. Prior to performing routine or emergency work in the secondary area all potted porcelain cutouts on the poles or structures shall be thoroughly inspected for visible hazards. A defective cutout must be replaced prior to work being performed. When no apparent defects are visible the cutout should be replaced, provided equipment, material, and crew qualification allow. Work can proceed at or below the secondary level using class O gloves when no apparent cutout defects or hazards associated with the cutout are found. Page 3 of 5

4 Cut and kick pole work shall require a thorough inspection of the potted porcelain cutouts. If the inspection reveals that the potted porcelain cutout is defective, then the cutout must be replaced prior to the cut and kick process. In the rare case where a defective cutout of any type is NOT immediately replaced, no work shall be performed at this pole or structure. The worker (authorized person) shall immediately report the condition to the system operator and notify his/her supervisor. A hold tag must also be placed at the location per NG-USA EOP G014, and the cutout is to be scheduled for replacement within 48 hours. Potted porcelain or enclosed porcelain cutouts shall not be used as a visable open for grounding or isolation. When the requirement to replace potted porcelain cutouts impact safety to the worker or public, or compromises system continuity (storm restoration), or customer business continuity, work may proceed, provided a thorough inspection of the cutout shows no apparent defects. Replacement of energized primary cutouts requires a minimum of two qualified workers. Cutouts may be de-energized by a single worker using hot stick/live line tools as shown below in the single worker excerpt from Standard 29 CFR (1) (ii) A, B, C. A) Routine switching of circuits, if the employer can demonstrate that conditions of the site allow this work to be performed safely. B) Work performed with live-line tools if the employee is positioned so that he or she is neither within reach of nor otherwise exposed to contact with energized parts, and C) Emergency repairs to the extent necessary to safeguard the general public. Jumpers of any type shall not be used to keep transformers, or transformer banks energized for the purpose of changing potted porcelain cutouts. Where practical, approved 15kV jumpers can be utilized for bypassing a cutout when replacing main line cutouts or cutouts feeding tap lines. (Jumpers must not be placed on cutout tap conductors). Refer to National Grid Retail Company Safety Manual and Work Procedures to determine when it may be necessary to place a circuit or portion of a circuit on non-reclosing/hot line tag and obtain a NRA. IV. CUTOUT REMOVAL/REPLACEMENT Removal All exposed energized conductors, grounds and neutrals within reaching and falling distance shall be rubbered-up or guarded. The cutout fuse holder will be opened and removed. (The condition of the cutout and the results of the inspection will dictate whether this can be done safely). When disconnecting the cutout from an energized circuit by means of a conducting wire, employees shall remove the source end first from the source conductor. (Note: delta transformer configurations will have both source and load connection points energized with door removed). Care must be taken to control any loose lead from contacting conductors, parts or equipment that are at a different potential. The alternate method is to remove the source lead from the cutout body using hot stick tools (Method is dictated by configuration and condition of installation). The lead must be controlled at all times. The method of removal and replacement of the lead must be discussed in detail during the documented Job Brief. All leads must be kept as short as possible and controlled. After removal and prior to replacing the new cutout, the position of the cutout must also be evaluated to ensure that the mounting location is in the least hazardous space. Page 4 of 5

5 Replacement Install the load side lead first and then install the source side lead, keeping the tap lead controlled and as short as possible. Depending on the configuration of the pole top construction, remove rubber and/or barriers. Install the fuse holder in the cutout and close using a hot stick/live line tool. If a line jumper has been applied, remove the jumper after closing the cutout. RESPONSIBILITIES: TRAINING: 1. Distribution Engineering Services A. Update procedure as necessary. B. Provide T&D personnel guidance when requested. 2. Customer Operations A. Ensure the components of the procedure are implemented. B. Ensure T&D personnel are trained in this procedure. C. Provide revision input as necessary. 3. Employee A. Demonstrate the understanding of the procedure. B. Comply with the requirements of the procedure. Provided by appropriate National Grid Training Program. Page 5 of 5

6 NG-USA EOP D001 Cutouts Open/Enclosed Type 11/01/06 This document is revised throughout.

Original Date of Issue: 04/09

Original Date of Issue: 04/09 POLICIES AND PROCEDURES DEPARTMENT: Environmental Health and Safety SUBJECT: Electrical Safety Program Original Date of Issue: 04/09 Reviewed 12/2011 Revised 12/2011 BACKGROUND ELECTRIC SHOCK It is well

More information

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , ,

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , , ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR 1910.331 335-29 CFR 1926.302, 1926.416, 1926.417 BASIS: The National Safety Council estimates that there are at least 300 deaths

More information

Lockout/Tagout - Energy Control Program

Lockout/Tagout - Energy Control Program Lockout/Tagout - Energy Control Program Lockout and Tagging of ELECTRICAL Circuits This portion of the K.R. Miller Contractors, Inc. safety program has been created to maintain a written copy of procedures

More information

: Electric Power Generation, Transmission, and Distribution. Region IV - OSHA

: Electric Power Generation, Transmission, and Distribution. Region IV - OSHA 1910.269: Electric Power Generation, Transmission, and Distribution Region IV - OSHA Scope This standard covers the operation and maintenance of electric power generation, control, transformation transmission,

More information

Control of Hazardous Energy Lockout / Tagout Program

Control of Hazardous Energy Lockout / Tagout Program Control of Hazardous Energy Lockout / Tagout Program August 2016 Table of Contents Purpose... 1 Scope and Application... 1 Responsibilities... 1 Environmental Health and Safety Personnel (EH&S)... 1 Directors

More information

2. The purpose of this program is to achieve the following objectives:

2. The purpose of this program is to achieve the following objectives: Section 16A. Lockout and Tagout Program 1. In the course of their duties, personnel at the TFREC may need to secure controls, switches, and equipment in order to prevent injury caused by the sudden, unexpected

More information

SECTION 51 NFPA 70E POLICY. Health & Safety Policy and Procedures Manual

SECTION 51 NFPA 70E POLICY. Health & Safety Policy and Procedures Manual SECTION 51 NFPA 70E POLICY Health & Safety Policy and 1. Protection Against Arc Flash A. Policy: An arc flash is a dangerous condition associated with the release of energy caused by an electric arc. An

More information

Preparer: Owner: Approver: EHS Team Member TES Manager Site Manager

Preparer: Owner: Approver: EHS Team Member TES Manager Site Manager Procedure No.: BMEHS-002.033 Page: 1 of 10 Preparer: Owner: Approver: EHS Team Member TES Manager Site Manager Document Revision Change Table Revision Revision Description Revised Revision Number New By

More information

LEADER NOTES FOR MAY 2012 STAND-DOWN

LEADER NOTES FOR MAY 2012 STAND-DOWN LEADER NOTES FOR MAY 2012 STAND-DOWN BEST PRACTICES PHILOSOPHY Properly executed Insulate and Isolate ( I&I ) techniques allow line workers to safely work on and/or around energized parts. The Best Practices

More information

Health & Safety Policy and Procedures Manual SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY

Health & Safety Policy and Procedures Manual SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY 1. CONTROL OF HAZARDOUS ENERGY POLICY AND PROCEDURES A. OSHA References: 29 CFR 1910.147, 29 CFR 1910.332, 29 CFR 1910.333, 29 CFR 1926.417 B.

More information

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell:

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell: Energy Control Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: 905.577.0303 cell: 905.977.0210 consultant@staffaid.ca www.staffaid.com Safety, Energy Control, Power Lockout & Function Test Procedures

More information

KMU SUBSTATION WORKSHOP

KMU SUBSTATION WORKSHOP Rick Aguilar, Director of Job Training & Safety KMU SUBSTATION WORKSHOP JUNE 29-30, 2016 OTTAWA, KS Hazards & Safety Rules Qualified Personnel & Task-Based Hazard Mitigation Worksite Applications & Considerations

More information

Electrical Safety PPT-SM-ELECTSFTY V.A.0.0

Electrical Safety PPT-SM-ELECTSFTY V.A.0.0 Electrical Safety 1 Electrical Safety OSHA s electrical safety standard covers Work on or near exposed energized equipment Proper use of electrical protective equipment Safe use of portable electric equipment

More information

MISSOURI UNIVERSITY OF SCIENCE & TECHNOLOGY Procedure: 3.6

MISSOURI UNIVERSITY OF SCIENCE & TECHNOLOGY Procedure: 3.6 Procedure This electrical safety procedure structures safety procedures to meet the requirements of the NFPA-70E Standard. The program is designed for qualified employees who occasionally must perform

More information

Definitions found in several locations:

Definitions found in several locations: Definitions found in several locations: NFPA 70 - National Electric Code NFPA 70B Recommended Practice for Electrical Equipment Maintenance. NFPA 70E Electrical Safety in the Workplace OSHA 1910 Subpart

More information

LO/TO LOCKOUT/TAGOUT PROGRAM

LO/TO LOCKOUT/TAGOUT PROGRAM LO/TO LOCKOUT/TAGOUT PROGRAM April 2017 CONTENTS Section 1: Introduction...1 Section 2: Purpose... 1 Section 3: Application... 1 Section 4: Definitions... 2 Section 5: Roles and Responsibilities... 4 Section

More information

Management Plan for Electrical Safety ISD #535

Management Plan for Electrical Safety ISD #535 Management Plan for Electrical Safety ISD #535 Health & Safety Office Maintenance Service Building 10 SE 9 ½ Street Rochester, MN 55904 507-328-4507 MANAGEMENT PLAN FOR ELECTRICAL SAFETY Table of Contents

More information

VERIFICATION OF EMPLOYEE TRAINING

VERIFICATION OF EMPLOYEE TRAINING VERIFICATION OF EMPLOYEE TRAINING I, (Full Name) official representative of (Utility Name), certify that the employees listed below, have received proper training and are qualified to participate in the

More information

Electrical Safety Work Practices

Electrical Safety Work Practices Work Practices I. SCOPE This program covers any SOUTHWESTERN COMMUNITY COLLEGE employee that may work or be exposed to exposed electrical systems: To assure that employees are not exposed to potentially

More information

Lockout / Tag out Program

Lockout / Tag out Program Lockout / Tag out Program Presented by DOSHTI www.doshti.com You will learn Purpose of Lockout- Tag out Requirements for LOTO Types of Hazardous Energy Procedures for LOTO The OSHA Standard for the Control

More information

Elements of a Lockout/Tagout Program OSHA

Elements of a Lockout/Tagout Program OSHA September 15, 2015 Elements of a Lockout/Tagout Program OSHA 1910.147 Dayna Noble Industrial Safety Consultant Specialist Ohio BWC 567-204-8917 Dayna.noble@bwc.state.oh.us Top 10 most frequently cited

More information

Lockout/Tagout Program

Lockout/Tagout Program Purpose Hazardous energy appears in the workplace in the form electrical, mechanical, pneumatic, hydraulic and thermal energy and includes chemical, water, steam and gaseous energy systems. Lockout/Tagout

More information

Electrical. Version 1.0

Electrical. Version 1.0 This document is intended to provide basic safety guidelines for the Physical Plant Department at Community College of Allegheny County. The information provided in this guide may vary by site. Version

More information

LOCKOUT/TAGOUT PROGRAM

LOCKOUT/TAGOUT PROGRAM LOCKOUT/TAGOUT PROGRAM HOW CLIMATE ENGINEERS INC. COMPLIES WITH THELO/TO STANDARD It is the intent of Climate Engineers Inc. to comply with OSHA s Control of Hazardous Energy Standard (1910.147). The following

More information

POWER PLANT RELAY REPLACEMENT DELIVERABLE ARC FLASH

POWER PLANT RELAY REPLACEMENT DELIVERABLE ARC FLASH POWER PLANT RELAY REPLACEMENT DELIVERABLE ARC FLASH ISU Senior Design Group: Dec15-22 Dan Dye Project Web Site: http://dec1522.sd.ece.iastate.edu/ Project Sponsor: CIPCO Project Advisor: Professor Mani

More information

Safety Meeting Topic #6 Working Around /On Energized Equipment

Safety Meeting Topic #6 Working Around /On Energized Equipment Safety Meeting Topic #6 Working Around /On Energized Equipment Employees shall become familiar with the following general guidelines: 1. Only qualified personnel shall work on electrical equipment, systems,

More information

LOCKOUT/TAGOUT PLAN August 2015

LOCKOUT/TAGOUT PLAN August 2015 LOCKOUT/TAGOUT PLAN August 2015 Office of Environmental Health and Safety 423-354-5224 TABLE OF CONTENTS Purpose and Intended Use... 2 A. Types of Energy Sources... 2 B. Activities Requiring Lockout/Tagout

More information

Lockout / Tagout Safety Program

Lockout / Tagout Safety Program Lockout / Tagout Safety Program Prepared by: The Ohio State University Environmental Health and Safety Occupational Safety & Industrial Hygiene 1314 Kinnear Road Columbus, OH 43212-1168 614-292-1284 Phone

More information

POWER DELIVERY. Contractor Health & Safety General Terms and Conditions. Appendix B Personal Protective Equipment

POWER DELIVERY. Contractor Health & Safety General Terms and Conditions. Appendix B Personal Protective Equipment Personal Protective Equipment ( PPE ): All PPE worn on IPL job sites must have ANSI and/or approval ratings. Hard hats and safety glasses with side shields (including prescription eyewear) shall be worn

More information

University of Arkansas Office of Environmental Health and Safety

University of Arkansas Office of Environmental Health and Safety University of Arkansas Office of Environmental Health and Safety Procedure Name: Lockout / Tagout Procedure Number: 600.26 Effective Date: 12-1-2015 Procedure: Developed in accordance with the OSHA Control

More information

LOCK-OUT/TAG-OUT (LO/TO) SAFETY PROGRAM

LOCK-OUT/TAG-OUT (LO/TO) SAFETY PROGRAM LOCK-OUT/TAG-OUT (LO/TO) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR 1910.147 BASIS: Approximately three million workers in the United States face risks from uncontrolled energy when servicing machinery

More information

Hazardous Energy Control (Lockout-Tagout)

Hazardous Energy Control (Lockout-Tagout) Hazardous Energy Control (Lockout-Tagout) The purpose of this program is to prevent inadvertent operation or energization of machines, equipment, or processes in order to protect employees and establish

More information

Electrical Safety Program

Electrical Safety Program Electrical Safety Program For Adopted LC-1005 Rev. 06/16 Page 1 I. Introduction As part of Organization s overall safety and health program, an

More information

Facilities Management

Facilities Management Facilities Management Policy Number: 700.6 Title: Lockout/Tag Out Policy Implementation Date: 2004 Last Audited: July 2 nd, 2018 Last Revised: March 25 th, 2015 Introduction This policy contains the necessary

More information

D Square Construction LLC

D Square Construction LLC D Square Construction LLC Lock Out-Tag Out (LOTO) and Zero Voltage Verification (ZVV) Process and Plan Energized Work Process and Permit - 1 - Table of Contents 1) Instruction for using Decision Tree Analysis

More information

COOPER POWER SERIES. D-73P3 bypass switches installation instructions. Switches MN008005EN. Effective April 2016 Supersedes S June 2013

COOPER POWER SERIES. D-73P3 bypass switches installation instructions. Switches MN008005EN. Effective April 2016 Supersedes S June 2013 Switches MN008005EN Effective April 2016 Supersedes S328-120-1 June 2013 D-73P3 bypass switches installation instructions COOPER POWER SERIES DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITY The information,

More information

DuPage County Environmental, Safety, Health & Property Loss Control Program Hazardous Energy Control (Lockout/Tagout)

DuPage County Environmental, Safety, Health & Property Loss Control Program Hazardous Energy Control (Lockout/Tagout) Purpose: To provide the minimum requirements for the lockout or tagout of energy isolating devices whenever work is performed or servicing is done on County of DuPage machinery, equipment, vehicles and

More information

SAFETY DIRECTIVE 2.0 DEPARTMENTS AFFECTED. This Administrative Directive shall apply to all Town of Marana departments and employees.

SAFETY DIRECTIVE 2.0 DEPARTMENTS AFFECTED. This Administrative Directive shall apply to all Town of Marana departments and employees. SAFETY DIRECTIVE Title: Control of Hazardous Energy Lock-out/Tag-out/Try-out Issuing Department: Town Manager s Safety Office Effective Date: July 1, 2014 Approved: Gilbert Davidson, Town Manager Type

More information

Lockout/Tagout Program Occupation Safety & Health Standards for General Industry 29 CFR

Lockout/Tagout Program Occupation Safety & Health Standards for General Industry 29 CFR Volunteer State Community College Lockout/Tagout Program Occupation Safety & Health Standards for General Industry 29 CFR 1910.147 The information contained in this maual documents the policies and procedures

More information

Safe Work Practices / Procedures / Instruction CONFINED SPACE

Safe Work Practices / Procedures / Instruction CONFINED SPACE CONFINED SPACE Entry into and work in a confined space poses health and safety problems which may include: Presence or possible build up of a hazardous atmosphere Unexpected movement of equipment or materials

More information

LOCKOUT/TAGOUT PROGRAM

LOCKOUT/TAGOUT PROGRAM Santa Clarita Community College District LOCKOUT/TAGOUT PROGRAM Revised March 2018 TABLE OF CONTENTS PURPOSE... 3 COMPLIANCE...4 DEFINITIONS...5 SECTION I - ENERGY CONTROL PROCEDURES... 7 SECTION II -

More information

LOCKOUT/TAGOUT PROGRAM

LOCKOUT/TAGOUT PROGRAM 0 Appendix C OCCUPATIONAL SAFETY AND HEALTH PROGRAM LOCKOUT/TAGOUT PROGRAM Hazardous Energy Control Lockout/Tagout Program TABLE OF CONTENTS Section Page I. Purpose and Scope. 1 II. Definitions 1 III.

More information

CONTROL OF HAZARDOUS ENERGY IN THE WORKPLACE

CONTROL OF HAZARDOUS ENERGY IN THE WORKPLACE Office of Environmental Health & Safety CONTROL OF HAZARDOUS ENERGY IN THE WORKPLACE LOCK OUT/TAG OUT OSHA 29 CFR 1910.147 rev. 3 2014 Director of Environmental Health & Safety Control of Hazardous Energy

More information

Lock Out - Tag Out Safety Program

Lock Out - Tag Out Safety Program Lock Out - Tag Out Safety Program Daniel Schmid 4-22-15 Pam Schmid 4-22-15 Dan Schmid Pam Schmid Safety Director Quality Director Table of Contents DOCUMENT REVISION TABLE... 3 PURPOSE... 4 RESPONSIBILITY...

More information

Lockout/Tagout Training Overview. Safety Fest 2013

Lockout/Tagout Training Overview. Safety Fest 2013 Lockout/Tagout Training Overview Safety Fest 2013 Purpose of Lockout/Tagout The standard covers the servicing and maintenance of machine and equipment in which the unexpected energization or start up of

More information

11/2/2017. Course Objectives. Overview

11/2/2017. Course Objectives. Overview Course Objectives The objective of this CBT module is to insure that personnel receive basic training in electrical safety. Every employee's work involves electricity. This may vary from typical electrical

More information

ARKANSAS TECH UNIVERSITY FACILITIES MANAGEMENT HEALTH AND SAFETY MANUAL (LOCKOUT/TAGOUT) 30.0

ARKANSAS TECH UNIVERSITY FACILITIES MANAGEMENT HEALTH AND SAFETY MANUAL (LOCKOUT/TAGOUT) 30.0 () 30.0 The purpose of the Energy Control Policy (Lockout/Tagout) is to ensure that before any employee performs any servicing and/or maintenance on machinery or equipment, where the unexpected energizing,

More information

Page: 7/15/2009. Energy control procedures Use of lockout/tagout equipment to ensure safe work practices.

Page: 7/15/2009. Energy control procedures Use of lockout/tagout equipment to ensure safe work practices. 1 of 6 1.0 PURPOSE This program applies to the installation, service, maintenance, or removal of any type of machinery, equipment, or components, in which the unexpected start up or release of stored energy

More information

Lock Out/Tag Out Control of Hazardous Energy

Lock Out/Tag Out Control of Hazardous Energy Lock Out/Tag Out Control of Hazardous Energy University Facilities Internal Procedure: July 1, 2013 Effective date: July 1, 2013 Last Modified: April 2013 Approved by: Bob Wells 1.0 Program Objective UF

More information

Lockout Tagout Policy

Lockout Tagout Policy Office of Environmental Health & Safety www.moreheadstate.edu/ehs 606-783-2584 Lockout Tagout Policy PURPOSE To establish procedures for the de-energization and isolation of energy sources or the lockout

More information

Document Owner: Name: Phil Langlois Position: Lead Electrical Engineer

Document Owner: Name: Phil Langlois Position: Lead Electrical Engineer Department 015-07-08 Page 1 of 10 Training Code: EL306 (5 year renewal) Document Owner: Name: Phil Langlois Position: Lead Engineer Sud = Sudbury, Ontario, PC = Port Colborne, Thom = Thompson, Manitoba,

More information

Lockout/Tagout - Control of Hazardous Energy Program

Lockout/Tagout - Control of Hazardous Energy Program Lockout/Tagout - Control of Hazardous Energy Program The University Of Iowa Environmental Health & Safety 122 Grand Avenue Court Iowa City, IA 52242-1000 Phone: 319-335-8501 Date Revised/Reviewed: 6/8/2018

More information

PAGE 1 OF 7 HEALTH, SAFETY & ENVIROMENTAL MANUAL PROCEDURE: S230 Lock-Out Tag-Out (LOTO) Program REV 4.0 8/13/2012

PAGE 1 OF 7 HEALTH, SAFETY & ENVIROMENTAL MANUAL PROCEDURE: S230 Lock-Out Tag-Out (LOTO) Program REV 4.0 8/13/2012 PAGE 1 OF 7 LOCK-OUT TAG-OUT (LOTO) THE CONTROL OF HAZARDOUS ENERGY LOCKOUT/TAGOUT PROGRAM PURPOSE: 1. This standard establishes lockout/tagout (LOTO) procedures for the safety of personnel working on

More information

Control of Hazardous Energy. Environmental Health and Safety

Control of Hazardous Energy. Environmental Health and Safety Control of Hazardous Energy Environmental Health and Safety 11/01/2014 1 CONTROL OF HAZARDOUS ENERGY (LOCKOUT-TAGOUT) OSHA CFR 1910.147 Revised Date: November 2014 STATEMENT OF POLICY Ball State University

More information

Electrical Safety Program

Electrical Safety Program Electrical Safety Program The University Of Iowa Environmental Health & Safety 122 Grand Avenue Court Iowa City, IA 52242-1000 Phone: 319-335-8501 Date Revised/Reviewed: 6/8/2018 Table of Contents 1. Summary...

More information

Preview to the 2018 NFPA 70E, the Standard for Electrical Safety in the Workplace

Preview to the 2018 NFPA 70E, the Standard for Electrical Safety in the Workplace Preview to the 2018 NFPA 70E, the Standard for Electrical Safety in the Workplace Preview to the 2018 NFPA 70E, the Standard for Electrical Safety in the Workplace Technical Committee Members James Dollard,

More information

WESTERN CONNECTICUT STATE UNIVERSITY LOCKOUT/TAGOUT PROCEDURE S-107

WESTERN CONNECTICUT STATE UNIVERSITY LOCKOUT/TAGOUT PROCEDURE S-107 WESTERN CONNECTICUT STATE UNIVERSITY LOCKOUT/TAGOUT PROCEDURE S-107 Draft Issued 12/97 Revised 11/00 Please direct any questions or comments about the applicability of this document to Luigi Marcone, WCSU

More information

Product Information Report Lockout/Tagout Hazardous Energy Control

Product Information Report Lockout/Tagout Hazardous Energy Control Overview A properly implemented (LOTO) program is designed to protect workers involved in the maintenance and servicing of equipment from the dangerous effects of hazardous energy caused by the unexpected

More information

University of Vermont Department of Physical Plant Personal Protective Equipment Program

University of Vermont Department of Physical Plant Personal Protective Equipment Program University of Vermont Department of Physical Plant Personal Protective Equipment Program REVISED AND DISTRIBUTED BY: THE UNIVERSITY OF VERMONT DEPARTMENT OF PHYSICAL PLANT TRAINING AND COMPLIANCE OFFICE

More information

University of Tennessee Safety Program

University of Tennessee Safety Program University of Tennessee Safety Program Policy Subject: Lockout/Tagout Program Effective Date: 4/22/98 Area Affected: All areas on campus where equipment can be locked out for service. Contact Information:

More information

ARC FLASH HAZARD ANALYSIS

ARC FLASH HAZARD ANALYSIS I. ARC FLASH HAZARD ANALYSIS IS REQUIRED ARC FLASH HAZARD ANALYSIS By Mike Lang Principal Field Engineer OSHA s 29 CFR Part 1910.132(d) states: The employer shall assess the workplace to determine if hazards

More information

Journeyman Team Events

Journeyman Team Events Journeyman Team Events Journeyman Team Rules Journeymen Teams Journeymen teams for the Florida Lineman Competition are comprised of three participants: 1. At least one of the climbers must be a Lineman

More information

SAINT MARY S COLLEGE OF CALIFORNIA STANDARD HAZARDOUS ENERGY CONTROL PROGRAM INCLUDING LOCKOUT/TAGOUT. Prepared by

SAINT MARY S COLLEGE OF CALIFORNIA STANDARD HAZARDOUS ENERGY CONTROL PROGRAM INCLUDING LOCKOUT/TAGOUT. Prepared by SAINT MARY S COLLEGE OF CALIFORNIA STANDARD 1.1.4 HAZARDOUS ENERGY CONTROL PROGRAM INCLUDING LOCKOUT/TAGOUT Prepared by SAINT MARY S COLLEGE OF CA MORAGA, California KAREN LAURICELLA Original Date: 1 JULY

More information

NECA Personal Protective Equipment (PPE) Selector

NECA Personal Protective Equipment (PPE) Selector NECA Personal Protective Equipment (PPE) Selector Objectives Explain why electrical contractors should follow the precautions set forth in NFPA 70E List the hazards which demonstrate why an arc flash risk

More information

Leader s Guide ERI Safety Videos

Leader s Guide ERI Safety Videos 1717 SAFE ELECTRICAL WORK PRACTICES & THE 2018 NFPA 70E Leader s Guide ERI Safety Videos SAFE ELECTRICAL WORK PRACTICES & THE 2018 NFPA 70E This easy-to-use Leader s Guide is provided to assist in conducting

More information

DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM

DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Purpose 1 Scope 1 Introduction 2 Regulatory Requirements 2 Protective Materials

More information

This is (Enter Company Name Here) Arc Flash Prevention policy. (Enter Name Here) will be responsible for overall direction of the Safety Program.

This is (Enter Company Name Here) Arc Flash Prevention policy. (Enter Name Here) will be responsible for overall direction of the Safety Program. Company Name: Policy/Procedure ID Number: 222 Date: Grainger Safety Services Inc. 2012 Arc Flash Prevention Policy This is (Enter Company Name Here) Arc Flash Prevention policy. (Enter Name Here) will

More information

THE UNIVERSITY OF NORTH CAROLINA

THE UNIVERSITY OF NORTH CAROLINA THE UNIVERSITY OF NORTH CAROLINA AT CHAPEL HILL CHILLED WATER DEPARTMENT ENERGY CONTROL PROCEDURE The purpose of this document is to establish minimum requirements for the manual isolation and securing

More information

Health and Fire Safety Review 2/15

Health and Fire Safety Review 2/15 Health and Fire Safety Review 2/15 1 TABLE OF CONTENTS Page 3 Scope 3 Control of Hazardous Energy (Introduction) 3 Authorized Employee 3 Employer Responsibility 4 Tagout Devices 4 Lockout Devices 5 General

More information

Lockout/Tagout Program

Lockout/Tagout Program Lockout/Tagout Program Control of Hazardous Energy Subpart J - 29 CFR 1910.147 29 CFR 1926.417 OSHA Standard All industries must comply Estimated to prevent Approximately 120 fatalities per year 28,000

More information

CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAG OUT PROGRAM) Washington State University Tri-Cities (all departments)

CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAG OUT PROGRAM) Washington State University Tri-Cities (all departments) CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAG OUT PROGRAM) Washington State University Tri-Cities (all departments) PURPOSE This program establishes the general and specific requirements for the control of

More information

CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT) PROGRAM

CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT) PROGRAM Page: 1 of 15 1.0 Purpose and Applicability 2.0 Scope 1.1 It is the policy of the University of Pennsylvania in coordination with the Office of Environmental Health and Radiation Safety to provide the

More information

H. Control of Hazardous Energy: Lockout/Tag Out

H. Control of Hazardous Energy: Lockout/Tag Out H. Control of Hazardous Energy: Lockout/Tag Out 1. Purpose Control of Hazardous energy is the purpose of the Lockout- Tagout Program. This program establishes the requirements for isolation of both kinetic

More information

Low Voltage Electricity System Safety Rules & Associated Safety Guidance

Low Voltage Electricity System Safety Rules & Associated Safety Guidance Annex J To Loughborough University Facilities Management (FM) Health and Safety Policy Low Voltage Electricity System Safety Rules & Associated Safety Guidance 1. Introduction a. These Safety Rules are

More information

MARINE CORPS BASE CAMP LEJEUNE PUBLIC WORKS DIVISION UTILITIES BRANCH STANDARD OPERATING PROCEDURE SHOP 82, ELECTRICAL DISTRIBUTION

MARINE CORPS BASE CAMP LEJEUNE PUBLIC WORKS DIVISION UTILITIES BRANCH STANDARD OPERATING PROCEDURE SHOP 82, ELECTRICAL DISTRIBUTION MARINE CORPS BASE CAMP LEJEUNE PUBLIC WORKS DIVISION UTILITIES BRANCH STANDARD OPERATING PROCEDURE SHOP 82, ELECTRICAL DISTRIBUTION SUPERVISOR, SHOP 82: (DATE) UTILITIES DIRECTOR: (DATE) PUBLIC WORKS SAFETY:

More information

University of Vermont Department of Physical Plant Burlington, Vermont

University of Vermont Department of Physical Plant Burlington, Vermont University of Vermont Department of Physical Plant Burlington, Vermont CONTROL OF HAZARDOUS ENERGY SOURCES AND ELECTRICAL HAZARDS LOCKOUT AND TAGOUT PROGRAM in accordance with OSHA 29 CFR 1910.147 REVISED

More information

PART Q CONTROL OF HAZARDOUS ENERGY (LOCKOUT-TAGOUT)

PART Q CONTROL OF HAZARDOUS ENERGY (LOCKOUT-TAGOUT) PART Q CONTROL OF HAZARDOUS ENERGY (LOCKOUT-TAGOUT) WAC Page 296-307-320 Control of hazardous energy (lockout-tagout). 1 296-307-32001 What does this section cover? 1 296-307-32003 When does this section

More information

OKLAHOMA CITY COMMUNITY COLLEGE CONTROL OF HAZARDOUS ENERGY PROGRAM. Environmental Health and Safety. Established:

OKLAHOMA CITY COMMUNITY COLLEGE CONTROL OF HAZARDOUS ENERGY PROGRAM. Environmental Health and Safety. Established: OKLAHOMA CITY COMMUNITY COLLEGE CONTROL OF HAZARDOUS ENERGY PROGRAM Environmental Health and Safety Established: Developed in accordance with OSHA Standard 29 CFR 1910.147 1 1.0 SCOPE. Oklahoma City Community

More information

LOCKOUT / TAGOUT PROGRAM

LOCKOUT / TAGOUT PROGRAM LOCKOUT / TAGOUT PROGRAM Developed in accordance with the OSHA Control of Hazardous Energy Standard, 29 CFR 1910.147 DECEMBER 7, 2017 SKIDMORE COLLEGE 815 NORTH BROADWAY, SARATOGA SPRINGS, NY 12866 Table

More information

Hazardous Energy Control

Hazardous Energy Control Lockout Tagout This program has been prepared to provide assistance in compliance with USA OSHA standards and/or Best Management Practices. It should not be used without consideration of the unique conditions

More information

Electrical Safety For Managers Updated For E. ElectricalTrainingPro.com

Electrical Safety For Managers Updated For E. ElectricalTrainingPro.com Electrical Safety For Managers Updated For 2018 70E Daryn Lewellyn daryn@electricaltrainingpro.com ElectricalTrainingPro.com 877.393.9901 1 Fatalities From Exposure To Electricity 1992-334 Bureau of Labor

More information

Selection of Electrical PPE Tables

Selection of Electrical PPE Tables Selection of Electrical PPE Tables Instructions Table 1 - Starting with Table 1, select the task you plan to do (right-hand column) and the condition of the equipment you will be working on, (center column).

More information

230-LOCKOUT/TAGOUT PROGRAM

230-LOCKOUT/TAGOUT PROGRAM 230.1 PURPOSE A. To confirm implementation, operation, and recordkeeping of Central New Mexico Community College(CNM) lockout/tagout program in compliance with 29 CFR 1910.147. 230.2 SCOPE A. The requirements

More information

Lockout/Tagout Plan Environmental Health & Safety Office July 2017

Lockout/Tagout Plan Environmental Health & Safety Office July 2017 July 2017 Table of Contents Acronyms... iii Foreword... iv Document History... iv 1.0 Introduction... 1 1.1 Purpose... 1 1.2 Scope... 1 1.3 Lockout/Tagout Program... 1 2.0 Roles and Responsibilities...

More information

Change Crossarm Insulator with Hotsticks

Change Crossarm Insulator with Hotsticks Change Crossarm Insulator with Hotsticks S T U D E N T M A N U A L March 31, 2005 2 STUDENT TRAINING MANUAL Prerequisites: Introduction to Hotsticks module Use and Care of Hotsticks module Weights & Forces

More information

APPENDIX D HYDRO-VAC

APPENDIX D HYDRO-VAC The City of Winnipeg Bid Opportunity No. 33-2018 Template Version: C420160226 - RW APPENDIX D HYDRO-VAC Corporate Safety & Health Division GUIDELINES FOR EXCAVATION OF CABLES BY WATER PRESSURE/VACUUM SYSTEMS

More information

RiskTopics. Lockout/Tagout October 2017

RiskTopics. Lockout/Tagout October 2017 RiskTopics Lockout/Tagout October 2017 This Risktopic is designed to outline guidelines for lockout/tagout and provide assistance in developing a management program to reduce the risk of injury from unintended

More information

PROGRAM: Control of Hazardous Energy (LOCKOUT) Chapter 5

PROGRAM: Control of Hazardous Energy (LOCKOUT) Chapter 5 Classroom, Occupational Safety & Health Plan Date: August 5, 2017 PROGRAM: Control of Hazardous Energy (LOCKOUT) Chapter 5 1. Purpose This document establishes the Lockout Program for Tidewater Community

More information

Lockout Tagout Program

Lockout Tagout Program Lockout Tagout Program RIM of the World Unified School District 27315 North Bay Road Blue Jay, CA 92352 (909) 336-4100 July 2016 Safety and Risk Management Department RIM of the World Unified School District

More information

The Best Use of Lockout/Tagout and Control Reliable Circuits

The Best Use of Lockout/Tagout and Control Reliable Circuits Session No. 565 The Best Use of Lockout/Tagout and Control Reliable Circuits Introduction L. Tyson Ross, P.E., C.S.P. Principal LJB Inc. Dayton, Ohio Anyone involved in the design, installation, operation,

More information

2-1- Shipping Receiving Lifting Location on Site Installation Stages 6

2-1- Shipping Receiving Lifting Location on Site Installation Stages 6 NEUTRAL GROUNDING RESISTORS INSTALLATION, OPERATION & MAINTENANCE MANUAL Contents 1- SAFETY INSTRUCTIONS... 3 1-1- Compliance with Instructions in this Manual. 3 1-2- Guidance Notes Installation.... 3

More information

Sample Written Program for The Control of Hazardous Energy (Lockout/Tagout)

Sample Written Program for The Control of Hazardous Energy (Lockout/Tagout) USAG Bavaria Safety Office Sample Written Program for The Control of Hazardous Energy (Lockout/Tagout) Nov 2016 1910.147 The Control of Hazardous Energy (Lockout/Tagout) The following lockout/tagout program

More information

Why do I need to do an Arc-Flash Analysis?

Why do I need to do an Arc-Flash Analysis? Why do I need to do an Arc-Flash Analysis? Presented By Tom Norwood for Alexander Nizov, P.E. Principal/Manager Electrical Engineering Division TRAINING INSTITUTE, INC. A SUBSIDIARY OF MEGGER Hazards Analysis

More information

HSE guidelines. SMay 2015 ELECTRICAL SAFETY HSE LIFE THE NATIONAL OIL&GAS INDUSTRY STANDARD FOR PROFESSIONALS

HSE guidelines. SMay 2015 ELECTRICAL SAFETY HSE LIFE THE NATIONAL OIL&GAS INDUSTRY STANDARD FOR PROFESSIONALS HSE guidelines SMay 2015 ELECTRICAL SAFETY HSE LIFE THE NATIONAL OIL&GAS INDUSTRY STANDARD FOR PROFESSIONALS Work safely or do not work at all There are strict procedures when working on electrical installations

More information

Lockout/Tagout Manual

Lockout/Tagout Manual Manual 2408 Wanda Daley Drive Ames, Iowa 50011-3602 (515) 294-5359 www.ehs.iastate.edu Copyright Environmental Health and Safety 2809 Daley Drive Ames, IA 50011-3660 Ph: (515) 294-5359 www.ehs.iastate.edu

More information

NFPA 70E Policies and Best Practices

NFPA 70E Policies and Best Practices NFPA 70E Policies and Best Practices Overview o Understand Compliance Requirements o Provide guidelines for a safe work environment o Effectively communicate policies to employees and customers o Express

More information

Families are encouraged to attend and support their favorite lineworkers. This year family friendly activities will be scheduled throughout the day.

Families are encouraged to attend and support their favorite lineworkers. This year family friendly activities will be scheduled throughout the day. The 2017 Lineworkers Rodeo will be held on March 31 st and April 1 st at Horry-Georgetown Technical College. The Apprentice Written Test will take place at 1:00PM on Friday afternoon following the vendor

More information

UNIVERSITY OF NOTRE DAME CONFINED SPACE ENTRY POLICY

UNIVERSITY OF NOTRE DAME CONFINED SPACE ENTRY POLICY UNIVERSITY OF NOTRE DAME CONFINED SPACE ENTRY POLICY Revised: February 2004 TABLE OF CONTENTS I. Introduction.. -4- II. Definition of a Confined Space -4- III. Responsibilities -5- A. University of Notre

More information

Removing Yourself from Hazards During Equipment Operation

Removing Yourself from Hazards During Equipment Operation Removing Yourself from Hazards During Equipment Operation The safest way to work around electrical equipment is to turn it off. This is usually required by OSHA and NFPA 70E, but with some exceptions.

More information

MCW s Control of Hazardous Energy Program

MCW s Control of Hazardous Energy Program 2018 MCW s Control of Hazardous Energy Program - Lockout Tagout Program This document is MCW s written program for managing the lockout and tagout of hazardous energy, and identifies roles and responsibilities

More information