1 Identification and Screening of Scenarios for LOPA Ken First Dow Chemical Company Midland, MI 1

2 Layers of Protection Analysis (LOPA) LOPA is a semi-quantitative tool for analyzing and assessing risk. The primary purpose is to determine if there are sufficient layers of protection against an accident scenario (can the risk be tolerated?). Layers of Protection Analysis, Center for Chemical Process Safety, American Institute of Chemical Engineers, New York (2001) 2

3 Key Concerns with Implementation of LOPA Variability in identification of credible scenarios to enter into LOPA. Consistent evaluation of scenario consequences in understandable terms of damage severity or human harm. Overall effort for implementation and re-validation of LOPA. 3

4 Work Process Steps for Simplified Risk Analysis Select equipment items to include in hazard evaluation Compile chemical, process and plant information needed Identify event sequences that could lead to an incident Estimate the release quantity, rate and hazard distance Select potential incident outcome cases for review Quantify the Consequence in terms of potential damage or injury Estimate the frequency or likelihood of event sequence Estimate risk from consequence and frequency Is Risk Tolerable? Can Risk be Reduced? Yes No Identify and Assess Independent Protective Layers Manage Residual Risk Full Risk Assessment and/or Discontinue Activity 4

5 Select an Equipment Item to Include in Hazard Evaluation Most chemical process facilities utilize the same basic process equipment vessels, pumps, heat exchangers, columns, etc. Select an equipment item based on the potential for a chemical process hazard similar to selection of a HAZOP node to begin the process. 5

6 Types of Chemical Process Hazards Process Risk typically addresses acute hazards including: Flammability Toxicity (Inhalation) Reactivity (Chemical Energy) Pressure-Volume Energy 6

7 Recognition of Chemical Process Hazards The potential to harm people, damage property or the environment depends upon: Chemical Properties (flash point, etc.) Process Conditions (operating temp., etc.) Equipment Parameters (volume, etc.) Site and Plant Layout (distance to public, etc.) 7

8 Hazard Flammability Relationship between Chemical Properties and Process Conditions Chem. Property Flash Point LFL MIE Process Condition Temperature > FP Concentration > LFL Ignition Source > MIE Toxicity ERPG Concentrations Vapor Concentration > ERPG Reactivity Heat of Reaction Gas Generation Detected Onset Temperature Maximum Reaction Temp. and Pressure Temperature > T NR P-V Energy Pressure > Design Pressure 8

9 Common Categories of Process Upsets Through operational experience, incident and hazard evaluation history; common process upsets may be categorized and related to specific types of equipment. Pump Deadhead (Blocked in while running) Blocked in with Thermal Expansion Overfill Excessive Heat Input Uncontrolled Reaction Physical Damage Etc. 9

10 Scenario Identification Scenario Case A Scenario Case represents an unplanned sequence of events leading to an incident with undesired consequence. Initiating Event + Enabling Conditions Failure of Independent Protective Layers Incident Outcome with Undesired Consequence 10

11 Scenario Identification Sequence of Events Initiating Event starts an event sequence and is typically categorized as: Control system failure Human error Mechanical failure Incident is an unintended release of hazardous material or energy. Consequence is a measure of the potential Outcome in terms of injury, damage, or economic loss. 11

12 Categories of Chemical Process Incidents Hole Size release rate. Standardized hole sizes simplify the screening analysis, for example: - 5 to 10 mm to represent gasket failure mm to full bore diameter to represent pipe or equipment nozzle failure. Overflow rate estimated from feed or fill rate. Excessive Heat vapor release rate estimated from rate of heat input divided by heat of vaporization. Catastrophic Failure or Rupture as a sudden release of entire equipment contents and reaction or pressure-volume energy. 12

13 Scenario Identification Scenario Case A Scenario Case also represents a relationship between Process Upset, Initiating Event, Incident Category, and Outcome for a specific Equipment Type. These relationships may be used to pre-develop a list of scenario cases to consider. 13

14 Scenario Type Deadhead Overflow, Overfill, or Backflow Excessive Pressure Excessive Heating Loss of Containment Uncontrolled Reaction Scenario Identification Common Relationships Example Predetermined Scenario List Parameter/ Deviation Flow-None Temp-High Level-High Flow-Backflow Pressure-High Temp-High Heat Input-High Flow-Loss of Containment Temp-High Composition- Wrong Flow-Backflow Equipment Types Pump Compressor Vessel Column Vessel Column Vessel Column Exchanger All Vessel Exchanger Pump Initiating Events Control Failure Human Error Control Failure Human Error Control Failure Human Error Control Failure Human Error Mechanical Integrity Control Failure Human Error Utility Failure Incidents Rupture Overflow (thru Vent) Overflow (thru Relief) Overflow (thru Relief) Rupture Vapor Release (Relief) Rupture Small Hole Medium Hole Large Hole Vapor Release (Relief) Rupture Conditions Max. Pressure > Burst Pressure Inventory > Equip Volume and Feed Pressure > Op Pressure Inventory > Equip Volume and Max Pressure > Relief Pressure Max Pressure > Relief Set Pressure Max Pressure > Burst Pressure Max Pressure > Relief Set Pressure Max Pressure > Burst Pressure Frequency depends upon internal or external corrosion, screwed versus welded construction, etc. Max Pressure > Relief Pressure Max Pressure > Burst Pressure 14

15 Scenario Identification Analysis Team Use of a predetermined list of feasible scenarios may help the Analysis Team to quickly identify other cases to consider. The Team may find additional relationships between scenario type, initiating event, incident category, and outcome to extend the predetermined list. Elucidation of the initiating event ( How could this happen in my plant? ) may also help the Team identify scenario cases to consider. 15

16 Scenario Identification Scenario Description Process Upset Chemical Involved Equipment Type Overfill of T-127 acrylonitrile storage tank leading to a release at a rate equal to the fill rate caused by process control failure Incident Category resulting in... Initiating Event An Outcome must be selected based on the chemical process hazard and potential Consequence to complete the Scenario Description. 16

17 Simplified Analysis for Selection of Incident Outcome Simplified source models are used to estimate release rates, airborne quantities, and hazard distances as part of determining feasible incident Outcomes. z (x,0,0) x For simplicity, selection of a single wind speed, stability, and surface roughness may be appropriate for LOPA analysis. y H (x,-y, z) (x,-y,0) 17

18 Example Outcome Selection Criteria Flash (or Jet) Fire Personnel exposure to 0.1 to 0.5 times LFL Vapor Cloud Explosion 1000 Kg flammable release (100 Kg for high flame speed) Building Explosion Indoor concentration exceeds LFL Physical Explosion (and BLEVE) Exposure to 1 psi overpressure (0.3 psi for fragmentation) Toxic Vapor Release (Indoor, Outdoor) Off-site exposure to > ERPG-2 concentration (60 min) On-site exposure to > ERPG-3 concentration A single incident may have several potential outcomes. 18

19 Simple Analysis of Outcome Consequence A simple Consequence Analysis may be based on Hazards originating from a point source such that the effect zone is estimated in terms of radial distance from the source. Personnel within the effect zone are assumed severely impacted while those outside of this area are assumed not affected. Probability of Severe Impact = 0 Wind Release Point Effect Zone (Probability of Severe Impact = 1) Cloud Plume 19

20 Quantification of Consequence Severity The number of personnel severely impacted may be estimated as impact area times population density. On-site population density should account for maintenance and other personnel in the process area and worst case wind direction. For scenario cases where personnel are anticipated to be in close proximity to the release point, the number of personnel at risk assumed as the number in attendance. 20

21 Quantification of Consequence Severity In some cases, the number of personnel severely impacted is significantly less than one. May indicate a relatively low probability of serious injury of fatality. May indicate that a minor injury is a more likely consequence than a serious injury or fatality. 21

22 Example Consequence Severity Categories The estimated number of people impacted is not precise such that a consequence category representing an order of magnitude range may be more appropriate. Consequence Severity Low Medium High Very High Catastrophic Description No impact on the public Minor on-site injury, no lost time Minor (non-reportable) environmental event Minimal equipment damage or production loss Public annoyance (odor, alert, etc.) Recordable on-site injury, not severe Offsite environmental impact or permit violation Equipment damage with some lost production One or more injuries to the public One or more severe on-site injuries or fatality Significant release/severe environmental impact Major damage to process equipment (>$1 MM) One or more serious injuries or fatality to the public Multiple severe on-site injuries or fatalities Long-term contamination and/or large kill of wildlife Major destruction and business loss (>$10 MM) Significant off-site disruption with multiple injuries/ fatalities resulting in public enquiry and prosecutions 22

23 Likelihood Evaluation Probability and Frequency Estimates of frequency and probability are inherent in risk analysis as many scenario cases represent rare, but catastrophic, event sequences. Initiating Events are represented as frequency (events per year). Enabling Events or Conditions are represented by probability (between zero and one). 23

24 Likelihood Evaluation Enabling Events Enabling Events must generally be present or met for the event sequence to proceed from initiating event to incident outcome. Probability of Ignition Fraction of Time at Risk based on mode of operation (start-up, specific operational step or procedure, etc.) Probability of Successful Evasive Action Others 24

25 Risk Estimation Consequence and Frequency Initiating Event + Enabling Conditions Failure of Independent Protective Layers Incident Outcome with Undesired Consequence Initiating Event Frequency X Enabling Condition Probability IPL Probability of Failure on Demand X < Tolerable Consequence Frequency to Meet Risk Target 25

26 Frequency Risk Estimation Example Risk Matrix The target frequency for a scenario case should be set conservatively compared with corporate or regulatory risk criteria Low Medium Consequence Severity High Very High Catastrophic 10-2 / Year Tolerable Intolerable Intolerable Intolerable Intolerable 10-3 / Year Tolerable Tolerable Intolerable Intolerable Intolerable 10-4 / Year Tolerable Tolerable Tolerable* Intolerable Intolerable 10-5 / Year Tolerable Tolerable Tolerable Tolerable* Intolerable 10-6 to 10-8 / Year Tolerable Tolerable Tolerable Tolerable Tolerable* * As low as reasonably practicable may apply. 26

27 LOPA Scenario Identification Summary and Conclusions A simple semi-quantitative risk analysis involving process upset (scenario type), incident category, and outcome is a promising means to identify and evaluate hazard scenario cases for LOPA. Estimates of release rate, hazard distance, and people impacted provide a means for reducing variability in quantifying consequence and setting target frequencies. Results may be validated against conventional quantitative risk analysis techniques and periodically updated to ensure they are appropriately conservative in meeting corporate or regulatory guidance. 27

28 LOPA Scenario Identification Key References Layers of Protection Analysis, Center for Chemical Process Safety, American Institute of Chemical Engineers, New York (2001). Guidelines for Hazard Evaluation Procedures, 2nd Edition, Center for Chemical Process Safety, American Institute of Chemical Engineers, New York (1992) Guidelines for Chemical Process Quantitative Risk Analysis, 2nd Edition, Center for Chemical Process Safety, American Institute of Chemical Engineers, New York (2000) Guidance on as low as reasonably practicable (ALARP) decisions in control of major accident hazards (COMAH), Health and Safety Executive, UK (2002), available at: Risk Management Program Guidance for Offsite Consequence Analysis, United States Environmental Protection Agency, available at: Freeman, R., Using Layer of Protection Analysis to Define Safety Integrity Level Requirements, Process Safety Progress, 26 (2007) 28

Using LOPA for Other Applications

Using LOPA for Other Applications 10 Using LOPA for Other Applications 10.1. Purpose LOPA is a tool used to perform risk assessments. Previous chapters described its use in assessing the risk level of process hazards scenarios and in evaluating

More information

Practical Modelling & Hazard Assessment of LPG & LNG Spills

Practical Modelling & Hazard Assessment of LPG & LNG Spills Practical Modelling & Hazard Assessment of LPG & LNG Spills UKELG 3 rd April 2012 Tony Ennis Introduction Refrigerated or pressurised Release scenarios & release rate Vaporisation Gas dispersion Consequences

More information

User Manual. Version: 1.1 Revision Date: 13 September 2018 Document Owner: Louisa Nara, CCPS Global Technical Director

User Manual. Version: 1.1 Revision Date: 13 September 2018 Document Owner: Louisa Nara, CCPS Global Technical Director User Manual Version: 1.1 Revision Date: 13 September 2018 Document Owner: Louisa Nara, CCPS Global Technical Director Risk Analysis Screening Tool (RAST) User Manual Purpose This document provides a reference

More information

Inherently Safer Design Analysis Approaches

Inherently Safer Design Analysis Approaches Inherently Safer Design Analysis Approaches There are a number of ways inherent safety can be analyzed. In any case, the intent is to formalize the consideration of inherent safety rather than to include

More information

Expert System for LOPA - Incident Scenario Development -

Expert System for LOPA - Incident Scenario Development - Expert System for LOPA - Incident Scenario Development - Adam Markowski a, Jaffee Suardin b, and M.Sam Mannan b a Process and Ecological Safety Division, Technical University of Lodz, Poland b Mary Kay

More information

Impact on People. A minor injury with no permanent health damage

Impact on People. A minor injury with no permanent health damage Practical Experience of applying Layer of Protection Analysis For Safety Instrumented Systems (SIS) to comply with IEC 61511. Richard Gowland. Director European Process Safety Centre. (Rtgowland@aol.com,

More information

Rail Car Unloading Case Study

Rail Car Unloading Case Study Rail Car Unloading Case Study Hazard Identification and Risk Analysis using RAST Version: 1.0 Revision Date: 13 September 2018 Document Owner: Louisa Nara, CCPS Global Technical Director Page 1 of 11 Process

More information

Introduction to Emergency Response & Contingency Planning

Introduction to Emergency Response & Contingency Planning & Contingency Planning Rationale Why is it important for you to learn this material? Designed for those who may witness a release, this is an introductory course designed to help ensure those who are likely

More information

Improving Accuracy of Frequency Estimation of Major Vapor Cloud Explosions for Evaluating Control Room Location through Quantitative Risk Assessment

Improving Accuracy of Frequency Estimation of Major Vapor Cloud Explosions for Evaluating Control Room Location through Quantitative Risk Assessment Improving Accuracy of Frequency Estimation of Major Vapor Cloud Explosions for Evaluating Control Room Location through Quantitative Risk Assessment Naser Badri 1, Farshad Nourai 2 and Davod Rashtchian

More information

A large Layer of Protection Analysis for a Gas terminal scenarios/ cause consequence pairs

A large Layer of Protection Analysis for a Gas terminal scenarios/ cause consequence pairs A large Layer of Protection Analysis for a Gas terminal 2000+ scenarios/ cause consequence pairs Richard Gowland European process Safety Centre The scope of the study was a large gas terminal handling

More information

SAFETY SEMINAR Rio de Janeiro, Brazil - August 3-7, Authors: Francisco Carlos da Costa Barros Edson Romano Marins

SAFETY SEMINAR Rio de Janeiro, Brazil - August 3-7, Authors: Francisco Carlos da Costa Barros Edson Romano Marins SAFETY SEINAR Rio de Janeiro, Brazil - August 3-7, 2009 Using HAZOP and LOPA ethodologies to Improve Safety in the Coke Drums Cycles Authors: Gilsa Pacheco onteiro Francisco Carlos da Costa Barros Edson

More information

Safety Engineering - Hazard Identification Techniques - M. Jahoda

Safety Engineering - Hazard Identification Techniques - M. Jahoda Safety Engineering - Hazard Identification Techniques - M. Jahoda Hazard identification The risk management of a plant 2 Identification of the hazards involved in the operation of the plant, due to the

More information

DETERMINATION OF SAFETY REQUIREMENTS FOR SAFETY- RELATED PROTECTION AND CONTROL SYSTEMS - IEC 61508

DETERMINATION OF SAFETY REQUIREMENTS FOR SAFETY- RELATED PROTECTION AND CONTROL SYSTEMS - IEC 61508 DETERMINATION OF SAFETY REQUIREMENTS FOR SAFETY- RELATED PROTECTION AND CONTROL SYSTEMS - IEC 61508 Simon J Brown Technology Division, Health & Safety Executive, Bootle, Merseyside L20 3QZ, UK Crown Copyright

More information

Annexure 2: Rapid Risk Assesment RISK ANALYSIS

Annexure 2: Rapid Risk Assesment RISK ANALYSIS RISK ANALYSIS (I) Catastrophic Rupture of LPG Bullet Truck (18 MT) At the LPG bottling plant, LPG will be transported by Bullet Truck tank. In the event of fire in LPG bullet truck in parking area, BLEVE

More information

Absorption - The process of contacting a vapor and gas stream with an absorbing liquid to remove specific materials from the gas stream.

Absorption - The process of contacting a vapor and gas stream with an absorbing liquid to remove specific materials from the gas stream. Sufe Design and Optvation ofpi-oc.ess Vents and Emission Contid $wteins by Center for Chemical Process Safety Copyright 0 2006 John Wiley & Sons, Tnc. APPENDIX B GLOSSARY Absorption - The process of contacting

More information

innova-ve entrepreneurial global 1

innova-ve entrepreneurial global 1 www.utm.my innova-ve entrepreneurial global Safety Integrity Level (SIL) is defined as: Relative level of risk-reduction provided by a safety function to specify a target level of risk reduction. SIL is

More information

Engineering Safety into the Design

Engineering Safety into the Design Engineering safety into the design Peter Scantlebury P.Eng Technical Safety Manager Amec Foster Wheeler, Oil & Gas Canada Abstract Safety by design is Amec Foster Wheeler s systematic approach to engineering

More information

3 rd Year Design Module Scope

3 rd Year Design Module Scope LOSS PREVENTION & Process Safety PROCESS HAZARDS ANALYSIS -3 rd Year Design Module - 3 rd Year Design Module Scope Hazard Identification In the Process 1. Identify the major hazards that are present 2.

More information

PSM TRAINING COURSES. Courses can be conducted in multi-languages

PSM TRAINING COURSES. Courses can be conducted in multi-languages Courses can be conducted in multi-languages One set of hardcopy course notes will be sent to client for printing and distribution to course participants. The courses will be held at the client s training

More information

INHERENTLY SAFER DESIGN CASE STUDY OF RAPID BLOW DOWN ON OFFSHORE PLATFORM

INHERENTLY SAFER DESIGN CASE STUDY OF RAPID BLOW DOWN ON OFFSHORE PLATFORM INHERENTLY SAFER DESIGN CASE STUDY OF RAPID BLOW DOWN ON OFFSHORE PLATFORM Volton Edwards bptt Angus Lyon DNV Energy Alastair Bird DNV Energy INTRODUCTION A term now in common usage within the oil & gas

More information

Using Consequence Modeling to Help Make Emergency Decisions

Using Consequence Modeling to Help Make Emergency Decisions Using Consequence Modeling to Help Make Emergency Decisions Della Wong / Nova Chemicals & Robert B. Gerow / SAFER-ERMC CSChE 2002 Conference October 20-23, 23, 2002 Vancouver B.C. If auto safety was like

More information

BASF Flash Fire FRC Assessment Tool

BASF Flash Fire FRC Assessment Tool BASF Flash Fire FRC Assessment Tool Introduction The assessment tool offered in this document was developed to assist BASF manufacturing units in evaluating the potential for flash fire occurrence and

More information

USING PREDICTIVE RISK ASSESSMENTS TO DEVELOP USER-FRIENDLY TOOLS FOR ON- AND OFF-SITE EMERGENCY PLANNING

USING PREDICTIVE RISK ASSESSMENTS TO DEVELOP USER-FRIENDLY TOOLS FOR ON- AND OFF-SITE EMERGENCY PLANNING USING PREDICTIVE RISK ASSESSMENTS TO DEVELOP USER-FRIENDLY TOOLS FOR ON- AND OFF-SITE EMERGENCY PLANNING Jo Fearnley and SreeRaj R Nair Aker Solutions, Phoenix House, 3 Surtees Way, Surtees Business Park,

More information

Challenges in Relief Design for Pilot Plants

Challenges in Relief Design for Pilot Plants Challenges in Relief Design for Pilot Plants Published on July 5, 2017 Michael Trainor Relief system design at the pilot scale presents unique challenges that don t always apply at the commercial scale.

More information

Understanding safety life cycles

Understanding safety life cycles Understanding safety life cycles IEC/EN 61508 is the basis for the specification, design, and operation of safety instrumented systems (SIS) Fast Forward: IEC/EN 61508 standards need to be implemented

More information

USING HAZOP TO IDENTIFY AND MINIMISE HUMAN ERRORS IN OPERATING PROCESS PLANT

USING HAZOP TO IDENTIFY AND MINIMISE HUMAN ERRORS IN OPERATING PROCESS PLANT USING HAZOP TO IDENTIFY AND MINIMISE HUMAN ERRORS IN OPERATING PROCESS PLANT Chris Lyth, Tracerco, Billingham, Cleveland, UK Ian Bradby, ABB Engineering Services, Billingham Cleveland, UK This joint paper

More information

Hazard Operability Analysis

Hazard Operability Analysis Hazard Operability Analysis Politecnico di Milano Dipartimento di Energia HAZOP Qualitative Deductive (search for causes) Inductive (consequence analysis) AIM: Identification of possible process anomalies

More information

Dow s New Practice for Locating Temporary Portable Buildings. P. Partridge 9/29/05 UNRESTRICTED - May be shared with anyone Slide 1

Dow s New Practice for Locating Temporary Portable Buildings. P. Partridge 9/29/05 UNRESTRICTED - May be shared with anyone Slide 1 Dow s New Practice for Locating Temporary Portable Buildings P. Partridge 9/29/05 UNRESTRICTED - May be shared with anyone Slide 1 Dow guidelines issued following the explosion at BP s Texas City facility

More information

Designing to proposed API WHB tube failure document

Designing to proposed API WHB tube failure document Designing to proposed API WHB tube failure document Dennis H. Martens Consultant and Technical Advisor (martensdh@pm-engr.com) Porter McGuffie Inc. Lon Stern Consultant (lhstern@earthlink.net) Stern Treating

More information

General Duty Clause. Section 112(r)(1) of CAA. Chris Rascher, EPA Region 1

General Duty Clause. Section 112(r)(1) of CAA. Chris Rascher, EPA Region 1 General Duty Clause Section 112(r)(1) of CAA Chris Rascher, EPA Region 1 Background on the General Duty Clause General Duty Clause 112(r)(1) of CAA Prevention of Accidental Releases Purpose and General

More information

INFORMATION FOR THE PUBLIC ABOUT A COMAH ESTABLISHMENT

INFORMATION FOR THE PUBLIC ABOUT A COMAH ESTABLISHMENT INFORMATION FOR THE PUBLIC ABOUT A COMAH ESTABLISHMENT Information for the public about an establishment subject to the Control of Major Accident Hazards Regulations 2015 (COMAH) The system to provide

More information

Part 2.5 Dispersion Modeling Using ALOHA

Part 2.5 Dispersion Modeling Using ALOHA Part 2.5 Dispersion Modeling Using ALOHA Dr. Arshad Ahmad Email: arshad@utm.my 1 Software Commonly used for Risk Analysis Software SAFETI SFU CAFTAN ETRA HAZSEC. HAZTRAC. PHAST. WHAZAN EFFECTS. DAMAGE

More information

The Relationship Between Automation Complexity and Operator Error

The Relationship Between Automation Complexity and Operator Error The Relationship Between Automation Complexity and Operator Error presented by Russell Ogle, Ph.D., P.E., CSP rogle@exponent.com (630) 274-3215 Chemical Plant Control Control physical and chemical processes

More information

A quantitative risk analysis method for the natural gas pipeline network

A quantitative risk analysis method for the natural gas pipeline network PI-195 A quantitative risk analysis method for the natural gas pipeline network Y.-D. Jo1, K.-S. Park1, H.-S. Kim1, J.-J. Kim1, J.-Y. Kim2 & J. W. Ko3 1 Institute of Gas Safety Technology, Korea Gas Safety

More information

Process Safety Management Of Highly Hazardous Chemicals OSHA 29 CFR

Process Safety Management Of Highly Hazardous Chemicals OSHA 29 CFR Process Safety Management Of Highly Hazardous Chemicals OSHA 29 CFR 1910.119 PSM - Definition Not all refining hazards are caused by the same factors or involve ve the same degree of potential damage.

More information

Purpose. Scope. Process flow OPERATING PROCEDURE 07: HAZARD LOG MANAGEMENT

Purpose. Scope. Process flow OPERATING PROCEDURE 07: HAZARD LOG MANAGEMENT SYDNEY TRAINS SAFETY MANAGEMENT SYSTEM OPERATING PROCEDURE 07: HAZARD LOG MANAGEMENT Purpose Scope Process flow This operating procedure supports SMS-07-SP-3067 Manage Safety Change and establishes the

More information

The Risk of LOPA and SIL Classification in the process industry

The Risk of LOPA and SIL Classification in the process industry The Risk of LOPA and SIL Classification in the process industry Mary Kay O Connor Process Safety Center International Symposium Beyond Regulatory Compliance, Making Safety Second Nature October 28-29,

More information

Marine Risk Assessment

Marine Risk Assessment Marine Risk Assessment Waraporn Srimoon (B.Sc., M.Sc.).) 10 December 2007 What is Risk assessment? Risk assessment is a review as to acceptability of risk based on comparison with risk standards or criteria,

More information

Introduction to HAZOP Study. Dr. AA Process Control and Safety Group

Introduction to HAZOP Study. Dr. AA Process Control and Safety Group Introduction to HAZOP Study Dr. AA Process Control and Safety Group A scenario You and your family are on a road trip by using a car in the middle of the night. You were replying a text message while driving

More information

Risk Based Method to Establish Inspection Intervals for Pressure Relief Devices

Risk Based Method to Establish Inspection Intervals for Pressure Relief Devices Risk Based Method to Establish Inspection Intervals for Pressure Relief Devices Mary Kay O Connor Process Safety Symposium College Station, TX October 27, 2010 Philip A. Henry, P.E. Principal Engineer

More information

Every things under control High-Integrity Pressure Protection System (HIPPS)

Every things under control High-Integrity Pressure Protection System (HIPPS) Every things under control www.adico.co info@adico.co Table Of Contents 1. Introduction... 2 2. Standards... 3 3. HIPPS vs Emergency Shut Down... 4 4. Safety Requirement Specification... 4 5. Device Integrity

More information

Methods of Determining Safety Integrity Level (SIL) Requirements - Pros and Cons

Methods of Determining Safety Integrity Level (SIL) Requirements - Pros and Cons Methods of Determining Safety Integrity Level (SIL) Requirements - Pros and Cons Faeq Azam Khan & Dr. Nihal A. Siddiqui HSE Department, University of Petroleum & Energy Studies, Dehradun, Uttarakhand,

More information

Major Hazard Facilities. Major Accident Identification and Risk Assessment

Major Hazard Facilities. Major Accident Identification and Risk Assessment Major Hazard Facilities Major Accident Identification and Risk Assessment Overview This seminar has been developed in the context of the MHF regulations to provide: An overview of MA identification and

More information

MAHB. INSPECTION Process Hazard Analysis

MAHB. INSPECTION Process Hazard Analysis Number 5 2016 seveso common MAHB INSPECTION s e r i e s criteria Process Hazard Analysis Major Accident Hazards Bureau Security Technology Assessment Unit This publication of the European community on

More information

Hazardous Materials Management Guidelines

Hazardous Materials Management Guidelines Environmental, Health and Safety Guidelines Hazardous Materials Management Guidelines Applicability These guidelines apply to facilities and activities involving the transportation, production, handling,

More information

Hazardous material transport accidents: analysis of the D.G.A.I.S. database

Hazardous material transport accidents: analysis of the D.G.A.I.S. database Environmental Health Risk II 131 Hazardous material transport accidents: analysis of the D.G.A.I.S. database S. Bonvicini & G. Spadoni Department of Chemical, Mining Engineering and Environmental Technologies,

More information

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011 AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF SEMS HAZARD ANALYSIS TRAINING September 29, 2011 Purpose The purpose of this meeting is to provide guidelines for determination of hazard

More information

HOW LAYER OF PROTECTION ANALYSIS IN EUROPE IS AFFECTED BY THE GUIDANCE DRAWN UP AFTER THE BUNCEFIELD ACCIDENT

HOW LAYER OF PROTECTION ANALYSIS IN EUROPE IS AFFECTED BY THE GUIDANCE DRAWN UP AFTER THE BUNCEFIELD ACCIDENT HO LAYER OF PROTECTION ANALYSIS IN EUROPE IS AFFECTED BY THE GUIDANCE DRAN UP AFTER THE BUNCEFIELD ACCIDENT Richard Gowland, European Process Safety Centre, Rugby, UK Prior to the Buncefield explosion,

More information

Application of fuzzy logic to explosion risk assessment

Application of fuzzy logic to explosion risk assessment International Symposium MKOPSC, 2010 College Station, TX, USA Application of fuzzy logic to explosion risk assessment A.S. Markowski*, M.S. Mannan**, A. Kotynia* * Process and Ecological Safety Division,

More information

NORMAL OPERATING PROCEDURES Operating Parameter Information

NORMAL OPERATING PROCEDURES Operating Parameter Information Operating Parameter Information Each operator performing the normal operating procedures (routine checks) of the facility should be familiar with the current normal operating parameters of all systems

More information

Proposed Abstract for the 2011 Texas A&M Instrumentation Symposium for the Process Industries

Proposed Abstract for the 2011 Texas A&M Instrumentation Symposium for the Process Industries Proposed Abstract for the 2011 Texas A&M Instrumentation Symposium for the Process Industries Focus Area: Automation HMI Title: Author: Shared Field Instruments in SIS: Incidents Caused by Poor Design

More information

Uncertainty in the analysis of the risk of BLEVE Fireball in process plants and in transportation

Uncertainty in the analysis of the risk of BLEVE Fireball in process plants and in transportation Uncertainty in the analysis of the risk of BLEVE Fireball in process plants and in transportation Joaquim Casal Centre for Studies on Technological Risk (CERTEC) EEBE, Universitat Politècnica de Catalunya

More information

Relief Systems. 11/6/ Fall

Relief Systems. 11/6/ Fall Relief Systems 1 Relief Scenarios o A single relief event requires a particulate vent area and valve size o Relief scenarios are determined based on a PHA o For each scenario, a vent area is calculated

More information

Technical Standards and Legislation: Risk Based Inspection. Presenter: Pierre Swart

Technical Standards and Legislation: Risk Based Inspection. Presenter: Pierre Swart Technical Standards and Legislation: Risk Based Inspection Presenter: Pierre Swart Agenda Change in Legislation. Where RBI fits in. Application to implement RBI. RBI concepts. Elements of an RBI analysis.

More information

QUANTIFYING THE TOLERABILITY OF POTENTIAL IGNITION SOURCES FROM UNCERTIFIED MECHANICAL EQUIPMENT INSTALLED IN HAZARDOUS AREAS

QUANTIFYING THE TOLERABILITY OF POTENTIAL IGNITION SOURCES FROM UNCERTIFIED MECHANICAL EQUIPMENT INSTALLED IN HAZARDOUS AREAS QUANTIFYING THE TOLERABILITY OF POTENTIAL IGNITION SOURCES FROM UNCERTIFIED MECHANICAL EQUIPMENT INSTALLED IN HAZARDOUS AREAS Steve Sherwen Senior Consultant, ABB Engineering Services, Daresbury Park,

More information

Abstract. 1 Introduction

Abstract. 1 Introduction Risk assessment study of the mutual interactive influence of working procedures on terminals handling dangerous goods in port of Koper (Slovenia) L. Battelino Water Management Institute, Maritime Engineering

More information

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS Annex 3, page 2 ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS The text of existing chapter 15 is replaced by the following: "1 Application This

More information

PRAGMATIC ASSESSMENT OF EXPLOSION RISKS TO THE CONTROL ROOM BUILDING OF A VINYL CHLORIDE PLANT

PRAGMATIC ASSESSMENT OF EXPLOSION RISKS TO THE CONTROL ROOM BUILDING OF A VINYL CHLORIDE PLANT PRAGMATIC ASSESSMENT OF EXPLOSION RISKS TO THE CONTROL ROOM BUILDING OF A VINYL CHLORIDE PLANT L.P. Sluijs 1, B.J. Haitsma 1 and P. Beaufort 2 1 Vectra Group Ltd. 2 Shin-Etsu (contact details: Vectra Group

More information

WIKA INSTRUMENT CORPORATION

WIKA INSTRUMENT CORPORATION WIKA INSTRUMENT CORPORATION Instruction Manual DIFFERENTIAL PRESSURE GAUGE Series 1500 Series 1000 Series 300 WIKA Instrument Corporation 1000 Wiegand Boulevard Lawrenceville, GA 30043 1-888-945-2872 http://www.wika.com

More information

Guide for Evaluating Your Hose Assembly Supplier

Guide for Evaluating Your Hose Assembly Supplier Guide for Evaluating Your Hose Assembly Supplier Supplier Evaluation Checklist, and How to Clearly Define Application Requirements Safe, reliable hose assemblies require appropriate specification work

More information

Knowledge, Certification, Networking

Knowledge, Certification, Networking www.iacpe.com Knowledge, Certification, Networking Page :1 of 71 Rev 01 Sept 2016 IACPE No 19, Jalan Bilal Mahmood 80100 Johor Bahru Malaysia The International of is providing the introduction to the Training

More information

5.2. Techniques Used to Evaluate Hazards to Buildings In Process Plants

5.2. Techniques Used to Evaluate Hazards to Buildings In Process Plants 5 Risk Assessment Chapters 3 and 4 described a series of screening tools that can be used to evaluate the design and siting of buildings in process plants. The results from the screening for a particular

More information

State of the Art in the Technical Assessment of DOMINO EFFECT

State of the Art in the Technical Assessment of DOMINO EFFECT State of the Art in the Technical Assessment of DOMINO EFFECT Valerio Cozzani LISES - DICAM, Alma Mater Studiorum - Università di Bologna, Bologna, Italy DOMINO EFFECT: Requirements for the control of

More information

Proposal title: Biogas robust processing with combined catalytic reformer and trap. Acronym: BioRobur

Proposal title: Biogas robust processing with combined catalytic reformer and trap. Acronym: BioRobur Proposal title: Biogas robust processing with combined catalytic reformer and trap Acronym: BioRobur Initiative: Fuel Cells and Hydrogen Joint Undertaking (FCH-JU) Funding scheme: Collaborative project

More information

Title: Pressure Relieving and Venting Devices Function: Ecology & Safety No.: BC Page: 1 of 7 Reviewed: 6/30/12 Effective: 7/1/12 (Rev.

Title: Pressure Relieving and Venting Devices Function: Ecology & Safety No.: BC Page: 1 of 7 Reviewed: 6/30/12 Effective: 7/1/12 (Rev. Preparer: Team Member, North America, Process Safety Center of Expertise No.: BC032.020 Page: 1 of 7 Owner: Manager, North America Process Safety Center of Expertise Approver: Sr. Vice President, Ecology

More information

HSE Management in Petroleum and offshore industries. Key to Tutorials. (Please refer the key along with the tutorial questions)

HSE Management in Petroleum and offshore industries. Key to Tutorials. (Please refer the key along with the tutorial questions) Health safety and Environmental Management in Petroleum and Offshore Industries Key to Tutorials (Please refer the key along with the tutorial questions) COURSE CORDINATOR Prof. SRINIVASAN CHANDARSEKARAN

More information

Advanced LOPA Topics

Advanced LOPA Topics 11 Advanced LOPA Topics 11.1. Purpose The purpose of this chapter is to discuss more complex methods for using the LOPA technique. It is intended for analysts who are competent with applying the basic

More information

USE OF THE EXCEEDANCE CURVE APPROACH IN OCCUPIED BUILDING RISK ASSESSMENT

USE OF THE EXCEEDANCE CURVE APPROACH IN OCCUPIED BUILDING RISK ASSESSMENT USE OF THE EXCEEDANCE CURVE APPROACH IN OCCUPIED BUILDING RISK ASSESSMENT Kieran J Glynn, Advisor Major Accident Risk, BP, UK The exceedance curve approach was developed following the issue of the 2003

More information

A Generic Model To Assess Major Incident Frequencies For Offshore Assets

A Generic Model To Assess Major Incident Frequencies For Offshore Assets A Generic Model To Assess Major Incident Frequencies For Offshore Assets Richard Emery, MMI Engineering Ltd, The Brew House, Wilderspool Park, Greenall s Avenue, Warrington, WA4 6HL. Quantitative risk

More information

THE BAKER REPORT HOW FINDINGS HAVE BEEN USED BY JOHNSON MATTHEY TO REVIEW THEIR MANUFACTURING OPERATIONS

THE BAKER REPORT HOW FINDINGS HAVE BEEN USED BY JOHNSON MATTHEY TO REVIEW THEIR MANUFACTURING OPERATIONS THE BAKER REPORT HOW FINDINGS HAVE BEEN USED BY JOHNSON MATTHEY TO REVIEW THEIR MANUFACTURING OPERATIONS Colin P. Lynas, Elizabeth Campbell and Hendrik J. Koornhof Johnson Matthey Catalysts This paper

More information

Quantitative Risk Analysis (QRA)

Quantitative Risk Analysis (QRA) Quantitative Risk Analysis (QRA) A realistic approach to relief header and flare system design Siemens AG 2017, All rights reserved 1 Quantitative Risk Analysis Introduction Most existing pressure relief

More information

API MPMS Chapter 17.6 Guidelines for Determining the Fullness of Pipelines between Vessels and Shore Tanks

API MPMS Chapter 17.6 Guidelines for Determining the Fullness of Pipelines between Vessels and Shore Tanks API MPMS Chapter 17.6 Guidelines for Determining the Fullness of Pipelines between Vessels and Shore Tanks 1. Scope This document describes procedures for determining or confirming the fill condition of

More information

Transient Analyses In Relief Systems

Transient Analyses In Relief Systems Transient Analyses In Relief Systems Dirk Deboer, Brady Haneman and Quoc-Khanh Tran Kaiser Engineers Pty Ltd ABSTRACT Analyses of pressure relief systems are concerned with transient process disturbances

More information

American Chemical Society (ACS) 246th ACS National Meeting Indianapolis, Indiana September 9, 2013

American Chemical Society (ACS) 246th ACS National Meeting Indianapolis, Indiana September 9, 2013 American Chemical Society (ACS) 246th ACS National Meeting Indianapolis, Indiana September 9, 2013 J. Kelly Thomas, Ph.D. Baker Engineering and Risk Consultants San Antonio, TX (KThomas@BakerRisk.com)

More information

Safety in Petroleum Industry

Safety in Petroleum Industry Chemical ( Industrial ) Disaster Management Conference, Bangalore 30 January 2014 Safety in Petroleum Industry Refineries and Petrochemical plants are highly energyintensive Handle highly inflammable and

More information

By Roger T. Hill, BTech CEng FIMechE, Director, Arthur D. Little Limited, Cambridge CB4 4DW, England

By Roger T. Hill, BTech CEng FIMechE, Director, Arthur D. Little Limited, Cambridge CB4 4DW, England Pipeline Risk Analysis By Roger T. Hill, BTech CEng FIMechE, Director, Arthur D. Little Limited, Cambridge CB4 4DW, England For almost a century, pipelines have been used to transport oil, gas and petroleum

More information

Risk-Based Inspection Requirements for Pressure Equipment

Risk-Based Inspection Requirements for Pressure Equipment the pressure equipment safety authority Risk-Based Inspection Requirements for Pressure Equipment AB 505 Edition 2, Revision 2 Issued 2017-08-24 Table of Contents FOREWORD... ii 1.0 INTRODUCTION... 1 2.0

More information

Title of Paper Interpretation of IP15 in Process Plant Design: a Commonsense Approach ---------------------------------------------------------------------------------------------------------------------------

More information

BSR GPTC Z TR GM References and Reporting Page 1 of 8

BSR GPTC Z TR GM References and Reporting Page 1 of 8 Page 1 of 8 PRIMARY: 192.605 SECONDARY: 191.23 PURPOSE: Review guide material added by TR 2009-17 to 5.1(e) and consider restructuring the guide material under 192.605 as discussed further below. ORIGIN/RATIONALE

More information

Average Rate of Death (ROD): The average number of fatalities that might be expected per unit time from all possible incidents. Averaging Time: The

Average Rate of Death (ROD): The average number of fatalities that might be expected per unit time from all possible incidents. Averaging Time: The Glossary Absolute Application (of TRA): The application of TRA in which the results of the analysis are compared against predetermined risk targets. Acute Risk: A risk arising from a short-term event such

More information

DOW CORNING CORPORATION Material Safety Data Sheet MOLYKOTE(R) Z POWDER

DOW CORNING CORPORATION Material Safety Data Sheet MOLYKOTE(R) Z POWDER Page: 1 of 7 1. IDENTIFICATION OF THE SUBSTANCE AND OF THE COMPANY Dow Corning Corporation South Saginaw Road Midland, Michigan 48686 24 Hour Emergency Telephone: Customer Service: Product Disposal Information:

More information

A Method of Quantitative Risk Assessment for Transmission Pipeline Carrying Natural Gas

A Method of Quantitative Risk Assessment for Transmission Pipeline Carrying Natural Gas A Method of Quantitative Risk Assessment for Transmission Pipeline Carrying Natural Gas Abstract Regulatory authorities in many countries are moving away from prescriptive approaches for keeping natural

More information

7/27/2011. How Things Can Go Wrong In The Drilling Of Oil / Gas Wells

7/27/2011. How Things Can Go Wrong In The Drilling Of Oil / Gas Wells How Things Can Go Wrong In The Drilling Of Oil / Gas Wells Provide a general background of the various risks inherent in the drilling of oil / gas wells. The participants will have a better knowledge and

More information

Refined Glycerine Kosher 99.50% Minimum CAS No

Refined Glycerine Kosher 99.50% Minimum CAS No Material Safety Data Sheet Effectivity Date : 26 August 2008 Page 1 of 6 Revision No. : 01 Refined Glycerine Kosher 99.50% Minimum CAS No. 56-81-5 1. Chemical Identification & Company Information Chemical

More information

Scope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such activities.

Scope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such activities. 11/13/1995 4 5/20/2013 1 of 10 Authority and Scope Regulation: 29 CFR 1910.146 Scope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such

More information

MATERIAL SAFETY DATA SHEET

MATERIAL SAFETY DATA SHEET 7730 Medical Adhesive Spray REG-HOLLISTER MATERIAL SAFETY DATA SHEET Section 1 Product and Company Information Hollister Medical Adhesive Spray Product Code: 7730 Company Information: Hollister Incorporated

More information

4-sight Consulting. IEC case study.doc

4-sight Consulting. IEC case study.doc 4-sight Consulting IEC 61511 / 61508 Case study 1 Contents 1 SUMMARY 4 2 INTRODUCTION 5 3 SCOPE OF THE STUDY 5 4 METHOD USED FOR THE STUDY 5 5 OPERATION OF THE TERMINAL 5 6 DESCRIPTION OF OVERFILL PREVENTION

More information

NPTEL CERETIFICATE EXAMINATION HSE practices in offshore & petroleum industries- SET 2

NPTEL CERETIFICATE EXAMINATION HSE practices in offshore & petroleum industries- SET 2 - SET 2 This question paper contains three sections. Answer all sections. No codes and additional support material is allowed for reference. Any data missing, may be suitably assumed and stated. Use of

More information

COMMITTEE DRAFT. API 520 Part I 10 th Edition Ballot Item 2.1. This ballot covers the following item:

COMMITTEE DRAFT. API 520 Part I 10 th Edition Ballot Item 2.1. This ballot covers the following item: This ballot covers the following item: API 520 Part I 10 th Edition Ballot Item 2.1 2008 12 Modify guidance to PRV datasheets (Line 17) to assist user s with determining the temperature to use for selecting

More information

Rapid Risk Assessment Of. Proposed Expansion for the Manufacturing of Pigment and Intermediate Products, Clariant Chemicals (India) Limited

Rapid Risk Assessment Of. Proposed Expansion for the Manufacturing of Pigment and Intermediate Products, Clariant Chemicals (India) Limited Rapid Risk Assessment Of Proposed Expansion for the Manufacturing of Pigment and Intermediate Products, Clariant Chemicals (India) Limited Conducted by Cholamandalam MS Risk Services Ltd. (An ISO 9001:2008

More information

Faculty/School: Pharmacy Initial Issue Date: Oct Dr. Alpesh Patel and Padmaja Dhanvate

Faculty/School: Pharmacy Initial Issue Date: Oct Dr. Alpesh Patel and Padmaja Dhanvate Use this form to assist you to complete risk assessments for hazardous activities and processes. Any serious or ongoing hazards should be reported via RiskWare to ensure that appropriate corrective actions

More information

INDUSTRIAL RISK ASSESSMENT FOR ROMANIAN SEVESO II SITES (RESULTS OF AN EC TWINNING LIGHT PROJECT)

INDUSTRIAL RISK ASSESSMENT FOR ROMANIAN SEVESO II SITES (RESULTS OF AN EC TWINNING LIGHT PROJECT) INDUSTRIAL RISK ASSESSMENT FOR ROMANIAN SEVESO II SITES (RESULTS OF AN EC TWINNING LIGHT PROJECT) Dr. R. Preiss, TUV, Austria Dr. M. Struckl, Federal Ministry of Economics, Austria In 2009 the European

More information

BPZM-MRD Nitrogen Injection System

BPZM-MRD Nitrogen Injection System BPZM-MRD Nitrogen Injection System (Transformer protector) Overview BPZM-MRD Nitrogen Injection Explosion Prevention & Fire Protection System became more advanced fire protection and explosion prevention

More information

UNSATURATED POLYESTER RESIN Version: 1.8 Print Date: 06/04/2006

UNSATURATED POLYESTER RESIN Version: 1.8 Print Date: 06/04/2006 1. CHEMICAL PRODUCT AND COMPANY IDENTIFICATION Product Name Product Identification Number(s) 7311010 Manufacturer/Supplier/Importer Hexion Specialty Chemicals, Inc. 100 Cottage Place CARPENTERSVILLE Illinois

More information

SIL Allocation. - Deterministic vs. risk-based approach - Layer Of Protection Analysis (LOPA) overview

SIL Allocation. - Deterministic vs. risk-based approach - Layer Of Protection Analysis (LOPA) overview SIL Allocation - Deterministic vs. risk-based approach - Layer Of Protection Analysis (LOPA) overview Origin and causes of accidents involving control system failure 44% Specification 20% Changes after

More information

Carter Healthcare, Inc

Carter Healthcare, Inc Training Requirements for the Revised Hazard Communication Standard December 1st, 2013 Questions and Answers Q. What is the Globally Harmonized System? A. The Globally Harmonized System (GHS) is an international

More information

Minimum standard of competence in advanced training for liquefied gas tanker cargo operations (STCW Reg V/1-2)

Minimum standard of competence in advanced training for liquefied gas tanker cargo operations (STCW Reg V/1-2) Minimum standard of in advanced training for liquefied gas tanker cargo operations (STCW Reg V/1-2) Column 2 Knowledge, understanding and proficiency Design and characteristics of a liquefied gas tanker

More information

Drum / cylinder handling

Drum / cylinder handling Page 1 of 8 Drum / cylinder handling This Technical Measures Document covers the storage and handling of toxic and flammable substances in drums and cylinders and refers to relevant codes of practice and

More information

6.6 Relief Devices. Introduction

6.6 Relief Devices. Introduction 6.6 Relief Devices Introduction Relief devices are used to help prevent a catastrophic failure of equipment and/or minimize the effects of any unanticipated or uncontrolled events. As such, relief devices

More information

Blast Damage Consideratons for Horizontal Pressure Vessel and Potential for Domino Effects

Blast Damage Consideratons for Horizontal Pressure Vessel and Potential for Domino Effects A publication of CHEMICAL ENGINEERING TRANSACTIONS VOL. 26, 2012 Guest Editors: Valerio Cozzani, Eddy De Rademaeker Copyright 2012, AIDIC Servizi S.r.l., ISBN 978-88-95608-17-4; ISSN 1974-9791 The Italian

More information