PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS
|
|
- Leslie Higgins
- 5 years ago
- Views:
Transcription
1 PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS Project: Insert Client Repair/ Replacement of low level light units/ low level using ladder access up to a working height not exceeding 5 metres. Contractor: Planned Lighting Maintenance Ltd Accompanying Documentation to this Method Statement: 1. Planned Lighting Maintenance Ltd Health & Safety Policy Document Part I 2. Planned Lighting Maintenance Ltd Health & Safety Policy Document Part II 3. Planned Lighting Maintenance Ltd Health & Safety Policy Document Part III 4. Site Induction Talk Prompt Sheet Supervisor specific briefing 5. Lamp Breakages Form 1001 General Information: All work to be carried out in accordance with the contract documentation and good working practice as defined by the Part III Health & Safety Policy Document and specific Risk Assessment attached. Reference numbers throughout this document relate to in the main the Company Health & Safety Policy Document Part III (Safe Working Practices) as attached. Brief Description of Scope of Work: i) The PLM team will book in and obtain the site specific safety information including any restrictions or special instructions ii) iii) iv) An initial brief site/works inspection will be conducted by the PLM supervisor to survey the scope of works Once the scope of work is surveyed and understood the supervisor will agree any required electrical isolation, identify the electrical isolation point and the strategy for maintaining secure work areas with the store management The PLM supervisor will carry out a site induction for the PLM engineering team in line with the site induction prompt card and the agreed electrical isolation v) The access equipment (ladders) will be checked and an in date inspection label identified on each piece of equipment (quarterly inspection) vi) When the agreed electrical isolation and area barriers are in place the low level work will be carried out by the engineers 1 of 8
2 vii) When the works are complete and the lighting is checked for correct operation the works area will be made good and the work area and electrical isolation control handed back to the store management. Detailed Sequence of Work: While this list is the intended sequence of work some tasks will take place concurrently and/or others may be brought forward or delayed depending on unforeseen problems that may arise. However, where these may affect safety revised risk assessments will be carried out to reduce risk so far as reasonably practicable. During all visits to site to carry out work the induction, equipment inspection and site inspection process will be carried out. 1. On arrival at site the PLM team will sign in at the Admin office, complete the site permit to work and obtain the required specific site safety information which will be included in the PLM supervisor s site induction. 2. The team in conjunction with the site representative will walk the work area and identify and agree the scope of work to be completed. This will include briefing and agreeing with the store management the exclusion barrier strategy, identification of electrical isolation points and agreement with electrical isolation programme for the works period including how these will be locked out/ controlled at the isolation point. 3. Prior to any work being carried out the PLM supervisor will complete a site specific induction for the PLM engineering team in line with the site induction prompt sheet. 4. Materials and tools will be delivered to the site work area using the correct manual handling techniques as laid down in SWP No Manual Handling to working areas. All lamps and replacement fittings will be kept in a suitable protective container and/or areas to avoid potential damage, breakages or being an obstruction to others. 5. The access equipment ladders will be checked for safe operation. All engineers will be checked to ensure they are wearing the correct personal protective safety equipment. 6. The work area route will be inspected on foot prior to the access equipment being placed at the start work position. At all times an engineer will be appointed to control and ensure suitable barriers are put in place as required to maintain exclusion zones. The movement of these will be co-ordinated by the appointed engineer who will additionally control customer movement away from any hazardous area. Ladders will be used in line with SWP No. 30 Ladders, Stepladders & Stools Prior to work taking place the electrical supply isolation points will be identified in preparation for the works to be carried out. Note: Isolation is not normally required for lamp changing as long as it is confirmed suitable RCDs are in place on circuits. 9. During the works and as required the electrical circuit will be confirmed as isolated by the engineering supervisor using suitable test equipment. In line with SWP No.17 Electrical Safety. This is to ensure suitable light levels are maintained for shop areas. 10. In sequence as decided by the PLM supervisor the light unit cover will be unfastened and placed in a safe position and the old units/ lamps removed. 2 of 8
3 11. The new fitting/ lamps will be installed and connected. At the conclusion of the installation the electrical power will be switched back on where isolation was required. 12. The light unit will be switched on and checked for correct operation. 13. At the end of the works all equipment/ lamps, etc will be removed for onward disposal and the area made good. SITE SPECIFIC SAFETY 14. Engineers will park in the designated areas and report to the site reception/ admin office before starting works. 15. Low level works will be conducted mostly during normal operating hours and suitable exclusion zones set around the working area. Where the risk assessment walk round inspection indicates the risks are high the supervisor may advise the store management that the works may need to be carried out when the store is closed. 16. Areas in close proximity to the works that could be potentially contaminated will be fitted with a suitable protective cover. 17. When required electrical works will be carried out under controlled isolation by trained competent engineers. 18. Suitable and sufficient personal protective equipment (PPE) will be worn by operatives to include safety footwear, cotton gloves and hi-visibility waistcoat. 19. The Planned Lighting Maintenance Ltd supervisor will carry out a simple toolbox talk at the beginning of each shift where the work period exceeds one day to include: a reminder of site safety rules and emergency procedures. 20. All waste, lamps, fittings, etc will be returned to the vehicle for removal from site and appropriate Hazardous Waste streaming. 21. Any breakages to lamps during the works will be reported and recorded on PLM Form Isolation of electrical circuits will be carried out either under the Clients system (where this exists) or the Company Permit to Work System using PTW/F No re-lamping works are to be completed in food preparation areas or the petrol filling station without compliance with the safe working procedures. 24. The café tables will be cleaned of any debris caused during the relamping work, however the client will be responsible for cleaning/sanitising the surfaces before customer use. Welfare 25. All welfare, toilet, first aid facilities and emergency evacuation procedures will be established at the survey stage and details passed on to the team during the induction. 26. Engineers must ensure they maintain good hygiene standards by washing before eating, drinking, etc. 27. No drink or food will be consumed outside of the designated areas and/or where they might be cross-contaminated. 28. No smoking is permitted on site at any time. 3 of 8
4 Security 29. Equipment, tools, etc will be secured in the vehicle when not in use and removed from site daily. The elevated work platform will be parked in the agreed designated area. Emergency Evacuation 30. The emergency evacuation procedures for the area are to be detailed during the site induction and employees reminded by the Team Supervisor on the daily toolbox talks. Miscellaneous 31. Prior to any works a copy of the building asbestos register should be obtained to confirm the presence or otherwise of asbestos containing materials. Where these have been identified and affect the working areas these will either be removed or suitable control measures implemented. Throughout the works if any hazardous materials are discovered work will cease and be reported immediately. An investigation will take place and risk assessments carried out by the Planned Lighting Maintenance Ltd Safety Officer. (See SWP No.20 Asbestos Awareness) Storage 32. No items will be stored on site where they can become a trip hazard or nuisance to others. No potentially combustible packaging materials or materials which could cause an obstruction will be left on site overnight other than in authorised areas. Originally prepared by: GMD Associates June 2017 UNDER NO CIRCUMSTANCES WILL OPERATION CONSIDERATIONS TAKE PRIORITY OVER SAFETY. UNDER NO CIRCUMSTANCES WILL HAZARDOUS MACHINERY, EQUIPMENT OR WORK AREAS BE LEFT UNATTENDED. 4 of 8
5 RISK ASSESSMENT Site: Assessor GMD Associates Date June 2017 Serial Hazard With No Control Measures Hazard With Control Measures Working in close proximity to site employees/ Where practicable carry out works out of normal staff and members of the public operating hours Keep employees, members of public away from working areas by setting suitable exclusion zones Policy Reference Number Comments Falls from height when using stepladder Use correct safe working procedures Policy Nos: 29 Working at Train engineers Use stepladders for short duration works only and only up to 5 metres Height and 30 Ladders, Stepladders and Stools 03 Injury while manual handling materials Train engineers Policy No: 15 Manual Use risk assessment procedure Handling Wear appropriate PPE gloves/ safety boots 04 Injury from incorrect use of handtools and Use correct safe working procedures Policy Nos: 14 Handtools Power tools Wear appropriate PPE and 35 Portable Power Tools Select tools of high quality and power tools without residual risks (noise, vibration) use battery powered DC equipment 5 of 8 Rev
6 RISK ASSESSMENT Serial Hazard With No Control Measures Hazard With Control Measures Policy Reference Number Comments Working with electrical equipment Engineers to isolate electrical supply and confirm Policy No. 17 Electrical Safety using appropriate test equipment Permit to Work 03 Permit to work system to be used, otherwise for lamp changing only, engineers to confirm light unit fitted with MCB/RCD prior to work Conduct work out of hours if no MCB/RCD fitted and isolate electrical supply Use non-conductive stepladder Handling of hot lamps Switch off where practicable and allow lamp to cool before handling Engineers to wear suitable gloves Handling of broken lamps Store lamps in suitable container Engineers to wear suitable gloves Broken lamps to be removed to sharps bin or similar for correct disposal Contamination or damage to product Where practical areas to be cleared of products by Clients staff Engineers to fit suitable protective covers Exposure to asbestos containing materials Consult building asbestos register prior to works Policy No. 20 Asbestos and implement suitable controls Use safe working procedure Awareness 6 of 8 Rev
7 Where risks are identified their likelihood of occurrence will be classed as 1 to 5 as follows: 1. REMOTE Very Unlikely to Occur 2. POSSIBLE Unlikely to Occur 3. PROBABLE Probably Will Occur 4. FREQUENT Very Likely to Occur 5. CERTAIN Extremely Likely to Occur Where risks are identified they will further be assessed for potential severity as 2 to 10 as follows: 2. NEGLIGIBLE Negligible Injury or Consequence 4. MINOR Minor Injury or Consequence 6. SIGNIFICANT Significant Injury or Consequence 8. MAJOR Major Injury or Consequence 10. CRITICAL Critical Injury or Consequence These will then be transposed to the Risk Assessment Form where each figure is multiplied by the other to assess risk before and after control measures are employed. 7 of 7 Rev
PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS
PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS Project: (insert Client) Replacement/ Repair of high level light units/ high
More informationInstructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading
Instructions for the Use of the Excel Spreadsheet There are Three tabs at the bottom of this worksheet Instructions tab is the one you are reading H&S Plan Tab The Plan Tab is the front cover pages of
More informationMethod Statement Author
Plan Bee Limited 3.3 Etna Industrial estate Clamp Road Motherwell Scotland ML2 7XQ Tel: 01698580572 Method Statement Method Statement Details Method Statement Number 7 Method Statement Date Monday 3rd
More information2.0 Management Systems and Documentation
SHE Rules BOW142.3 1.0 Introduction This document details the safety, health and environment rules that apply to anyone accessing Arqiva sites and describes the standards of performance expected. This
More informationPre-control risk estimate. Likelihood Risk
Activity Consequence s mitigation measures Site Access & Egress Slips, trips & falls al injury by falling. Sprains & broken bones. Site operatives 3 4 12 Ensure access to site is kept clear of plant &
More informationSafe Work Method Statement
Title Skid Steer Operation (Bobcat) SWMS No. 14 Authorized and email Signed by the (Managing Director / CEO / Partner / Proprietor) on Date 01/08 /2016 Safe Work Procedure for the Work:- Yes No Employees
More informationB S Glass Ltd Safety procedures- outsourced Workplaces
B S Glass Ltd Jan 17 B S Glass Ltd Safety procedures- outsourced Workplaces Index - - - - - - - - Page No On Site safety - - - - - - - - - - - - - - - - - - - Content 3. 1.00 Health and Safety Mission
More informationSection J. How to develop safety elements for project safety management system. How to develop safety elements for project SMS
Section J How to develop safety elements for project safety management system 1. Once the project management has developed or adopted a safety policy, it needs to develop safety elements to meet the objectives
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Working at eight SWMS No. 16 Authorized and email Signed by the (Managing
More informationPocklington Town Council Risk Assessment Christmas Festival Wednesday Assessor: Gordon Scaife Date
Activity: Christmas Festival Wednesday Assessor: Gordon Scaife Date 16/07/2018 5 December Completed: Persons At Risk: PTC Staff, Volunteers & Public Reference: 180716 Public Events Review Date: 16/07/2019
More informationWaste Industry Safety & Health
Waste Industry Safety & Health A practical pocket guide for the Waste industry Supported by: Delivering the Solution Together Introduction The Waste Industry Safety and Health (WISH) forum is supporting
More informationThe Sample Company Pty Ltd
Job Safety and Environmental Analysis (JSEA) / Safe Work Method Statement (SWMS) Part 1: Project and Task Identification Process Initiators of SWMSs are responsible for consulting the Project Supervisor,
More informationSpecific Safety Legislation/Codes of Practice/Australian Standards applicable to this JSA (Tick those applicable).
OCCUPATIONAL HEALTH & SAFETY MANUAL Section OHS-005, Job Safety Analysis SCORESBY, VIC 3179 GEELONG, VIC 3218 MALAGA, WA 6090 DUDLEY PARK, SA 5008 MANSFIELD, QLD 4122 NORTH ROCKS, NSW, 2641 ACT 2609 LAVINGTON,
More informationLEVEL 2 CERTIFICATE OF COMPETENCE IN THE SAFE USE AND OPERATION OF MOBILE ELEVATED WORK PLATFORMS
NPTC Registered Charity No. 1096429 NATIONAL AGRICULTURAL CENTRE STONELEIGH PARK, WARWICKSHIRE CV8 2LG Tel: 024 7669 6553 Fax: 024 7669 6128 Email: information@nptc.org.uk LEVEL 2 CERTIFICATE OF COMPETENCE
More informationSUMBSE01 - SQA Code HC85 04 Apply health and safety and environmental legislation in the building services engineering sector
Overview This standard is about establishing and maintaining working practices and procedures across a specified range of installation and/or maintenance activities that give consideration to health and
More informationTHE CONTROLLED COPY OF THIS DOCUMENT IS ON THE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR THE DATE AT THE BOTTOM OF THE PAGE.
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Using Angle Grinders SWMS No. 8 Authorized and email Signed by the
More informationFIRE HYDRANT TESTING METHOD STATEMENT.
SUBJECT: TASK: FIRE HYDRANT INSPECTION & TESTING. 1. Location....1 2. The Scope of Works.... 1 3. Description of Task.... 1 4. Access & Egress to & from Work Area.... 2 5. Safety Hazard Identification....
More informationSAFE WORK METHOD STATEMENT CARPENTER
HOST EMPLOYER DECLARATION I declare the worker/s named on this work authority have been provided with a site specific safety induction that complies with the requirements of the Workplace Health & Safety
More informationPotential hazards People at risk and how? Actions already in place Further action required Action by
Risk Assessment Flat Roof Repair Prepared by Oracle Managed Services For: BAM FM On: 24/02/2017 Review date: N/A Potential hazards People at risk and how? Actions already in place Further action required
More informationSafety Risk Assessment Working at Height: Mobile Tower Scaffold
Persons at (Groups) Assessor Appointment Tel. No. Description of Task or Activity A One Direct employees Mark Bloxidge H&S Manager 0208 821 5197 Working at height from Mobile Tower B Contractors/Sub contractors
More informationCONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA
RECOMMENDED ADDITIONAL CONTROLS TASK / ACTIVITY/ EQUIPMENT/ FACILITY HAZARDS UNWANTED EVENT MINIMUM CONTROLS REQUIRED RISK NO. LIKELI-HOOD CONSE-QUENCE RISK VALUE Project Risk Assessment Page 1 of 16 All
More informationWorking at Height - MEWPS & Ladders. Your company details Address Tel: Fax: Mobile:
Project/Contract Contractor Site Address Project Start Date Expected Duration Projected Completion Date Your company details Address Tel: Fax: Mobile: Document Author Authorised by Name Title Signature
More informationSWMS No 007 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6
Samark North Qld Pty Ltd SWMS Manual SWMS No 007 Samark North Qld Pty Ltd ABN : 99 082 958 487 Electrical Contractors License C37121 Page 2 of 6 Safe Work Method Statement Title: SWMS:007 WORKING ON ENERGISED
More informationInstructions: Use this format to prepare the security plans for ACP contracts. EVERY point has to be covered; if they do not apply, write N/A.
APPENDIX F - RISK CONTROL PLAN FORMAT FOR CONTRACTORS OF THE PANAMA CANAL Instructions: Use this format to prepare the security plans for ACP contracts. EVERY point has to be covered; if they do not apply,
More informationHS329 Risk Management Procedure
HS329 Risk Management Procedure Work Health and Safety Act 2011 Policy hierarchy link Work Health and Safety Regulation 2011 Work Health and Safety Policy Code of Practice How to Manage Work Health and
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Dogging of Crane General Loading and Unloading SWMS No. 20 Authorized
More informationSAFE WORK METHOD STATEMENT SWMS No Version
SAFE WORK METHOD STATEMENT SWMS No Version Company Name: Hunter Readymixed Concrete Pty Ltd 00 004 Location: Thornton Cessnock Tea Gardens Gateshead ABN: 6 076 08 695 SWMS Developed By: Duane Harrison
More informationProcedure: Work health and safety hazard management
Procedure: Work health and safety hazard management Purpose This procedure describes how the Australian National University (ANU) manages Work Health Safety hazards for the health, safety, rehabilitation
More informationSH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH M ABN
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH 07 3265 6537 M 0411 756 719 ABN 45 081 359 613 OHS-FRM-100 Rev 11 (07/18) Page 1 SH&EWMS No.: F-C-QLD-30
More informationIMMANUEL CHURCH, CHICHESTER HEALTH AND SAFETY POLICY
IMMANUEL CHURCH, CHICHESTER HEALTH AND SAFETY POLICY Approved by the Trustees: November 2016 Health and Safety Policy Introduction The main piece of health and safety legislation is the Health and Safety
More informationSUPPLIER HEALTH AND SAFETY. Supporting a healthy and safe working environment for our people and customers
SUPPLIER HEALTH AND SAFETY Supporting a healthy and safe working environment for our people and customers Document Template Control Prepared by Georgina East May 2017 Date Approved by May 2017 Mark Beder
More informationSCOPE OF WORK, SAFETY METHOD STATEMENT & RISK ASSESSMENT
SCOPE OF WORK, SAFETY METHOD STATEMENT & RISK ASSESSMENT Prepared for:- Date:- Work Scheduled:- SCOPE OF WORK Carry out installation of flow meters / pressure sensors. Installation of flow meter procedure
More informationRefresher Licensed Asbestos Supervisor Training
TRAINING SYLLABUS LICENSED WORK WITH ASBESTOS Refresher Licensed Asbestos Supervisor Training This unit has nineteen learning outcomes. 1. Recognise the types, uses and risks of asbestos containing materials
More informationPermit-To-Work Guidance and Templates
Managing Contractors Policy - Appendix E Permit-To-Work Guidance and Templates This document has been constructed to provide guidance in how to use a permit to work correctly. The first part explains the
More informationSafety Risk Assessment Hand and Power Tools
One Direct aintenance td Persons at (Groups) Assessor Appointment Tel. No. Description of Task or Activity A One Direct employees ark Bloxidge H&S anager 0208 821 5197 Use of hand and power tools B Contractors/Sub
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-02 Task: Concreting, Formwork and Steel Fixing This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia)
More informationHealth & Safety Policy and Procedures Manual SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY
SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY 1. CONTROL OF HAZARDOUS ENERGY POLICY AND PROCEDURES A. OSHA References: 29 CFR 1910.147, 29 CFR 1910.332, 29 CFR 1910.333, 29 CFR 1926.417 B.
More informationSWMS No 001 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 5
Samark North Qld Pty Ltd SWMS Manual SWMS No 00 Samark North Qld Pty Ltd ABN : 99 082 98 87 Electrical Contractors License C372 Page 2 of Safe Work Method Statement Title: SWMS:00 USING PORTABLE LADDERS
More informationHEALTH & SAFETY ARRANGEMENTS FOR MANAGEMENT OF WORK AT HEIGHT
HEALTH & SAFETY ARRANGEMENTS FOR MANAGEMENT OF WORK AT HEIGHT INTRODUCTION Cwmni CYNNAL recognises that accidents can arise from working at height. Falls from height can be a cause of injury and absence
More informationMethod Statement. Method Statement Details. Signatures. Emergency Contact Details 1/5
Highway Traffic Safety Ltd Lakeside House, 1 Furzeground Way Stockley Business Park Heathrow London UB11 1BD Tel: 02071 111655 Method Statement Method Statement Details Method statement number 4 Method
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-0 Task: Line Marking This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised
More informationContractor OHS Induction. AOHS-05-GUI September 2016
Contractor OHS Induction AOHS-05-GUI-002 8 September 2016 1 About AQWEST AQWEST is a Government Trading Enterprise responsible for supplying drinking water to Bunbury. Formed in 1906 as the Bunbury Water
More informationSafety Risk Assessment Carpentry
One Direct aintenance td Persons at (Groups) Assessor Appointment Tel. No. Description of Task or Activity A One Direct employees ark Bloxidge H&S anager 0208 821 5197 General carpentry activities including,
More informationLeicester City Council Health & Safety Risk Assessment Form Ref:
Division/Section: Bridges Team Work Activity: Structural Repairs Activity Location: 8 Minehead Street, Leicester Persons Affected: Manager: Date of Assessment: Property Occupiers and Site Operatives Abul
More informationS31 Opening Statement Working at Height
S31 Opening Statement Working at Height Falls from height are by far the most common cause of workplace deaths and one of the main causes of major injury in the workplace. Latest figures reveal that 46
More informationContractor / Exhibitor Handbook
Contractor / Exhibitor Handbook Health and Safety This booklet outlines the basic rules that must be followed by contractors and other visitors working on Live Promotions Events sites. The contractors
More informationSafe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN
JOB NO: PROJECT: DATE: 1/1/2018 SWMS NO: SWMS 001.1 PREPARED BY: LUKE BLINCO REVISED BY: ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS
More informationList all key terms and acronyms used in the procedure, and their definitions.
Purpose The purpose of this procedure is to provide guidelines for electrical safety in general within Seqwater in compliance with the Electrical Safety Act 2002, Industry Codes of Practice, Regulations,
More informationPROCEDURES FOR STANDBY
1 SCOPE This Procedure details both the circumstances in which standby shall be provided and the responsibilities borne by the Standby Man in such circumstances. 2 ISSUE RECORD This is a maintained/controlled
More informationHAZARD MANAGEMENT PROCEDURE
TABLE OF CONTENTS 1. OBJECTIVE... 2 2. SCOPE... 2 3. DEFINITIONS... 2 4. RESPONSIBILITIES... 2 5. HAZARD IDENTIFICATION... 3 5.1 HAZARD AND RISK IDENTIFICATION TOOLS AND METHODS... 3 5.1.1 Take 5 Risk
More informationHealth and Safety Inspection Procedure
Template v4 WILTSHIRE POLICE FORCE PROCEDURE Health and Safety Inspection Procedure Effective from: 25.03.2012 Last Review Date: 10.05.2015 Version: 2.0 Next Review Date: 10.05.2018 TABLE OF CONTENTS PROCEDURE
More informationControl of Work. Introduction This procedure describes the management of Asbestos. Definitions
Home Knowledge Control of Work Search Asbestos Introduction This procedure describes the management of Asbestos. The management approach shall be in accordance with the requirements of the Control of Asbestos
More informationWork Activity (e.g. Road Work): Work Location:.
Working with Cranes Work Activity (e.g. Road Work): Work Location:. GENERAL INFORMATION Hinchinbrook Shire Council Lannercost Street Ingham Qld, 4850 ABN 46 291 971 168 Ph: 47764610 All personnel conducting
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Use of a Mobile Elevated Work Platform (MEWP) Boom SWMS No. 19 Authorized
More informationHazard Management Making your workplace safer
Hazard Management Making your workplace safer A Guide to Hazard Identification, Risk Assessment, Control and Reviewing 1 What is a hazard? A hazard is something which has the potential to harm the health,
More informationSafety, Health & Environment Contractor Induction. IT Contractor
Safety, Health & Environment Contractor Induction IT Contractor Contents 1. Contents 2. Welcome to Woolworths 3. Safety & Health Policy 4. Arrival at Site/Store 5. Hazards & Incidents 6. Emergency Preparedness
More informationP N J CLEANERS LTD. Ventilation only Risk Assessments and Method Statements
Church Farm Wychor, Alrewas, Burton on Trent, Staffordshire. DE13 8BY P N J CLEANERS LTD Telephone 01283791953 Mobile 07585127242 Email admin@pnjcleaning.co.uk Ventilation only Risk Assessments and Method
More informationCSU Channel Islands Lead Operations and Maintenance Program
CSU Channel Islands Lead Operations and Maintenance Program 1.0 Policy It is the policy of California State University Channel Islands to provide employees and visitors with a safe and healthful environment.
More informationTo comply with the OHS Act, the responsible manager must carry out and document the following:
Owner: Manager Health, Wellbeing and Safety Last Update: 10 January 2018 Contents 1. Purpose... 1 2. Minimum Compliance Requirements... 1 3. Definitions... 2 4. Legislative requirements under the OHS Act
More informationSWMS No 012 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6
Samark North Qld Pty Ltd SWMS SWMS No 0 Samark North Qld Pty Ltd ABN : 99 08 98 87 Electrical Contractors License C37 Page of 6 Safe Work Method Statement Title: SWMS:0 INSTALLING LIGHT POLES Work Method
More informationThe purpose of this document is to establish the procedures for accident prevention and investigation at (Insert Company Name) jobsites.
CORPORATE SAFETY MANUAL ENVIRONMENTAL, HEALTH AND SAFETY STANDARDS TITLE: Document Number: * Issue Date: Revision Date: * 1 Purpose The purpose of this document is to establish the procedures for accident
More informationBogo Operations Pollution Incident Response Management Plan
Bogo Operations Pollution Incident Response Management Plan Rhyolite Hard Rock Aggregate Quarry 134 Paynes Road BOOKHAM NSW 2582 PO Box 426 COWRA NSW 2794 p: 02 6227 7260 p: 02 6345 4253 e: info@bogoquarry.com.au
More informationWork Health & Safety Event Safety Checklist Small Event
Note: This checklist relates to the Bedford Park site and contains information specific to that site. Other sites can use the checklist but may need to adapt the information. This documentation must be
More informationContractor/Visitor Safety Orientation UNBC
Contractor/Visitor Safety Orientation UNBC 3333 University Way, Prince George, BC V2N 4Z9 Revised: October 2015 For All Emergencies call Security 250-960-7058 ***DO NOT DIAL 911*** Important UNBC Telephone
More informationHazard Identification and Risk Assessment Form. Risk Assessment
Identification and Assessment Form Assessment Tool & Machine Work General Various injuries (including potential fatalities) All staff complete safety induction programme at the start of the module. instructed
More informationHealth & Safety Policy & Plan. Rightway Roofing.
Health & Safety Policy & Plan. Rightway Roofing. Valid: 02/2012-02/2013 Contents ( 1 ) Policy Statement. ( 2 ) Hazard Identification. ( 3 ) Hazard Management. ( 4 ) Induction & Training. ( 5 ) Monitoring
More informationWORK METHOD STATEMENT ELECTRICAL
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationSafe Work Procedure for installation of external cladding
Safe Work Procedure for installation of external cladding This procedure has been formulated to cover safe systems of work for the installation of external cladding. This instruction will be used to reduce
More informationTRADE AREA: ELECTRICAL INDUSTRY
TRADE AREA: ELECTRICAL INDUSTRY Some possible workplace hazards and possible ways for Host employers and Apprentices/Trainees in controlling these hazards. What are possible hazards? What could be possible
More informationWINDMILL (pre-start) HAZARD INSPECTION CHECKLIST
Windmill Hazard Inspection Checklist WINDMILL (pre-start) HAZARD INSPECTION CHECKLIST Authorised by: LOCATION OF INSPECTION...... Inspected By (1)........... (2)..... PRINT PRINT Signature (1):. (2)....
More informationContractor Control Procedures. Contractor Control Procedures. Working Together. November Borders College 24/11/2014.
Working Together Contractor Control Procedures November 2014 Borders College 24/11/2014 1 Working Together 1. Introduction This procedure aims to control the health and safety of contractors working on
More informationCompany Health and Safety Policy
Company Health and Safety Policy LDM Installers Ltd. Document reference: H&SP0B5-00 Document by: Radu N. Lupsa Date: 25.08.2010 Review date: 25.02.2011 36 CASTLEVIEW GARDENS, LONDON, IG1 3QB. TEL/FAX:
More informationAPPENDIX A: Risk Assessment for all activities at Farm
APPENDIX A: Risk Assessment for all activities at Farm Sheet No...of...... Drafted by Nick Laister Date of Revision: January 08 Location: Southcombe, Chipping Norton Heading: General Organisation L C R
More informationThis document provides guidance to conducting health and safety inspections at the University, to ensure Hazards are identified and controlled.
Health and Safety Guideline: HSG 10.1 Health and Safety Inspections and Testing 1. Purpose This document provides guidance to conducting health and safety inspections at the University, to ensure Hazards
More informationWork Health and Safety Risk Management Procedures
Work Health and Safety Risk Management Procedures Table of Contents 1. Governing Policy 2. Purpose 3. Scope 4. Definitions 5. Responsibilities 6. Risk Management Process 6.1. Process summary 6.2. Hazard
More informationHow severely could the risk hurt someone?
Safe Work Method Statement No: WMS-08 Task: Install Drainage This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised
More informationRISK ASSESSMENT Installation of electrically operated service lifts (non passenger type)
RISK ASSESSMENT 2011 WALLINGTON LIFT MAINTENANCE CO LTD Installation of electrically operated service lifts (non passenger type) 1 1 L a k e s i d e, W a l l i n g t o n, S u r r e y, S M 6 7 J Y T e l
More informationLOCKOUT/TAGOUT POLICY
NAVAJO COUNTY Safety Procedures Reference: PERSONNEL POLICIES & PROCEDURE SECTION: 5.4 Approved: Brett Starns Subject: LOCKOUT/ RM-Safety 09/04/2014 TAGOUT POLICY Revised: 9/16/2014 Initiating Department:
More informationSAFE WORK METHOD STATEMENT Part B
SAFE WORK METHOD STATEMENT Part B SWMS No.: 01 WORK ACTIVITY DESCRIPTION: Door Installation All FORESEEABLE OHS & ENVIRONMENTAL HAZARDS & RISKS ASSOSSIATED WITH THE WORKS MUST BE ASSESSED & ALLOCATED CONTROLS
More informationTUDOR PARK EDUCATION TRUST. Working at Heights and Risk Assessment
TUDOR PARK EDUCATION TRUST Working at Heights and Risk Assessment Person(s) responsible for updating the policy: Chief Executive Officer Date Approved: Board of Directors on 7 July 2016 Period of Review:
More informationJOB SAFETY ANALYSIS. How to use the Risk Assessment Charts. Likelihood A (Almost Certain) B (Likely) C (Possible)
Page 1 of 6 How to use the Assessment Charts 1. Determine the Likelihood on the Qualitative Assessment Process Chart (pick a letter applicable to the task). 2. Determine the Consequence on the Qualitative
More informationEMPLOYEE SAFETY ORIENTATION - PHYSICAL PLANT, RESIDENCE
Name Department Initial Orientation Date Supervisor Review Instructions: Check off each section once you have read and discussed it with your Supervisor. EMPLOYEE SAFETY ORIENTATION - PHYSICAL PLANT, RESIDENCE
More informationApplication of rope access methods in the construction, inspection, repair and maintenance of wind turbines
Application of rope access methods in the construction, inspection, repair and maintenance of wind turbines Introduction IRATA International s rope access system is a safe method of working at height,
More informationTHICKNESSER RISK ASSESSMENT (U003ra)
Task Being Carried Out: Area: Persons at Risk: Operation of T500 Thicknesser Brindle Mill Operatives, Maintenance engineers Description of Equipment: Wadkin T500 Thicknesser Serial No.: T500 82240 (Machine
More informationStandards of Practice Personal Protective Equipment
Document Authority: I. PURPOSE Standards of Practice Personal Protective Equipment Whenever feasible, hazards must be eliminated through engineering, and/or administrative controls, prior to resorting
More informationCONTRACTOR SAFETY INDUCTION HANDBOOK
CONTRACTOR SAFETY INDUCTION HANDBOOK As a valued contractor for Total Group we would ask that you read and carefully consider the details included in this document. Total Group carry out work for a number
More informationHow to plan an event. Step 1: First things first. Step 2: How to make it all happen?
As an event organiser, you have a legal responsibility to ensure the health, safety and welfare of all those involved in your event - all employees, volunteer helpers and contractors as well as members
More informationUniversity College Dublin Machinery/Equipment Risk Assessment Template
1. General Information Name of Person(s) carrying out assessment and their position Principal Investigator / Supervisor / Head of School or Unit (Person responsible for ensuring safety) Date of assessment
More informationSafety Management System. Initial Revision Date: Version Revision No. 02 GENERAL SAFETY HEALTH PROVISION
Revision Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 5 Purpose This program is written to be in compliance with local regulatory requirements and provide directives
More informationNUS Safety & Health Guidelines Procedure No: OSHE/SOP/GL/08
Page: Page 1 of 5 Prepared By Approved By Review Date Swapan Kanti Biswas Dr Peck Thian Guan 1.0 OBJECTIVE The objective of this document is to provide guidance on the selection and use of (PPE). This
More informationa. identify hazardous conditions and potential accidents; b. provide information with which effective control measures can be established;
APPENDIX 2 TO ANNEX E TO SECTION 13 JOB HAZARD ANALYSIS PROCESS 1. The JHA process is an excellent starting point to evaluate the actual way a job is performed. This process may identify specific improvements
More informationContractor Hazard Identification and Control Guide
Exposure to Asbestos Containing Materials (ACM) Accidental disturbance or removal of ACM. Asbestos Containing Materials are to be removed outside school hours. No DET employees, students or visitors are
More informationGeneric Health and Safety Risk Assessment
Generic Health and Safety Risk Assessment Acheta Consulting Ltd Assessment completed by: Dr John Simmons (Managing Director), April 2017 Review date: May 2018 Introduction During the course of your work
More informationCOSHH Hazardous Substances Health & Safety Management Standard Issue 2 (September, 2010)
COSHH Hazardous Substances Health & Safety Management Standard Issue 2 (September, 2010) Introduction This document contains corporate standards and guidance on the management of risks arising from the
More informationResponsibilities / Accountability
Responsibilities / Accountability What we will cover Brief history of OPP safety program OPP s commitment to safety Safety responsibilities Accountability for safety Employee expectations History of Safety
More informationHEALTH AND SAFETY METHOD STATEMENT AIR CONDITIONING/REFRIGERATION MAINTENANCE/SERVICE. 2. Clean filters and screens when necessary
HEALTH AND SAFETY METHOD STATEMENT AIR CONDITIONING/REFRIGERATION MAINTENANCE/SERVICE Air Conditioning Indoor/Outdoor Unit as applicable 1. Check Pressures 2. Clean filters and screens when necessary 3.
More informationBasketball Risk Assessment for AoC Sport National Championships 2018 Nottingham University
Trivial Minor Moderate Serious Very Serious Basketball Risk Assessment for AoC Sport National Championships 2018 Nottingham University The assessor can assign values for the hazard severity (a) and likelihood
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT AUGER / POST HOLE DIGGER Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationMcKay Moore Drainage Ltd. Health and Safety Policy
McKay Moore Drainage Ltd Health and Safety Policy Table of Contents 1) Health & Safety Policy 2) Hazard Identification 3) Hazard Management 4) Training 5) Site Induction 6) Monitoring and Review 7) Site
More informationMANUFACTURING TECHNICAL INSTRUCTIONS - SAFETY FALL HAZARD CONTROL REQUIREMENTS SERIES & NO. SMI - 157
1 of 6 1.0 PURPOSE To establish minimum requirements and guidelines for controlling hazardous exposure of personnel to falls from working elevations in conformance with Federal and State OSHA rules and
More information