MSE CONTROLLED DOCUMENT. Radiological HS&E Precautions for Dismantling Equipment
|
|
- Penelope Hodge
- 5 years ago
- Views:
Transcription
1 MSE CONTROLLED DOCUMENT Radiological HS&E Precautions for Dismantling Equipment Document No: Supersedes Revision no: 1 1/10/2004 Custodian: MSE/32 Revision no: 1 1/10/2006 Filename: NORMMGT. DOC Administered by: Verified: Verified: Approved: Approved: MSE/32 RPA OND/OSD UWD/GD 1/10/2004 Reason for revision: This document contains proprietary information and is intended for use by PDO and Contractor staff only. The contents of this controlled document shall not be changed without formal approval of the document custodian.
2 Contents 1. Introduction Objective Scope Responsibilities Permit Applicant Permit Holder (Work Supervisor) Responsible Supervisor Area Authority Contractor Performance PPE and auxiliaries Safety measures and work instruction General Dismantling Operations... 3 APPENDICES Appendix 1: Glossary of Abbreviations... 5 Page 1
3 1. Introduction Plant such as valves, pumps, flanges, piping etc may require dismantling for maintenance purposes. The equipment may be NORM contaminated and therefore radiological controls are required during such an operation under the Permit to Work System. 1.1 Objective To define the radiological precautions for dismantling equipment that has conveyed well fluids such as oil, produced water, natural gas and condensates. 1.2 Scope This procedure shall apply to all PDO and contractor personnel involved in dismantling well fluid/ gas conveying equipment. 2. Responsibilities 2.1 Permit Applicant The Permit Applicant is responsible for requesting a NORM Radiological Survey be conducted during maintenance/repair operations and is attached to the PTW. 2.2 Permit Holder (Work Supervisor) The Permit Holder is (usually the Permit Applicant as defined on the Work Permit) is responsible for the implementation of this procedure. Usually the Permit Holder will be the Work Supervisor and will be the trained RPT who undertakes the NORM Radiological Survey and outlines the system of work. 2.3 Responsible Supervisor The Responsible Supervisor is responsible for verifying that the Permit Applicant has requested a NORM Radiological Survey for all of the above maintenance activities. The Responsible Supervisor shall ensure that Contractor has the approved meter(s) to conduct the NORM Radiological Survey, the appropriate personal protective equipment and sealable drums for collecting NORM contaminated scale or soil. 2.4 Area Authority The Area Authority is responsible for verifying that the Contractor has an approved RPT or has arranged for a PDO RPT to undertake the NORM Radiological Survey. The Area Authority shall verify that the RPT attaches the NORM Radiological Survey to the PTW and the Contractor complies with the controls outlined in the Survey and these NORM Guidelines. Page 2
4 2.5 Contractor The maintenance contractor is responsible for ensuring that an appropriately trained RPT forms part of the maintenance crew or and is able to undertake radiation and contamination measurements and can advise on radiological controls. The controls shall be included in the NORM Radiological Survey attached to the PTW. The contractor is responsible for ensuring the correct monitors are available to undertake the NORM Radiological Survey. The Contractor is responsible for compliance with this procedure. 3. Performance 3.1 PPE and auxiliaries Prior to commencing work, the Permit Holder (Work Supervisor) shall ensure the availability of PPE and auxiliaries. 3.2 Safety measures and work instruction General All reservoir fluid/gas conveying equipment shall be treated as NORM contaminated until RPT measurements prove otherwise. All personnel shall attend a NORM awareness course and be familiar with the hazards and safeguards involved with NORM jobs. A tool box meeting shall be conducted prior to commencement of the work Dismantling Operations Supervision by the Permit Holder (Work Supervisor) (see Paragraph 2.4) or his nominated deputy is mandatory. Consider covering the surface below the item of plant with heavy duty (1000 gauge 250 micron) polyethylene plastic. RPT to specify to what extent a Supervised Area as per MSE.05 is required, as necessary. RPT shall monitor for Gamma radiation with the Mini 900 with 44A probe at and adjacent to the equipment prior to work commencing. The presence of Gamma radiation externally suggests higher levels inside and almost certainly Alpha and Beta radiation. Note: Equipment from gas only equipment may have high levels of lead-210 and both a Mini 900 with 444A probe and Mini 900 with EP15 probe are required. Neither of the Mini 900 series meters are intrinsically safe and continuous gas detection is necessary to prevent the risk of fire/explosion. (Add to PTW) If the external readings do not exceed 5 cps above background, there may still be low activity NORM inside and internal readings with the same meter must be performed. If the internal readings do not exceed 5 cps above background, there is no NORM contamination Page 3
5 If the external readings exceed 5 cps above background, this indicates the presence of NORM inside the equipment and the task becomes a NORM risk job. If the equipment is to be opened, a cordoned off Supervised Area must be determined by the RPT and PPE must be worn by workers once work begins. Plastic sheeting can be placed under the equipment to catch loose scale, however it may be easier to monitor the area under the equipment once the task is completed and contaminated soil can be collected and placed into dedicated NORM drums for disposal. RPT to check the equipment and immediate area for radiation and contamination, and record measurements and any specify NORM precautions on a NORM Radiological Survey Report Appendix A SP1170 Special NORM precautions are required if any measurements above the levels specified are found. All persons shall be checked for contamination on exit from the Supervised Area. If contamination is found it shall be registered and MSE.09 followed. Equipment used inside the Supervised Area shall be checked for contamination prior to removal. Any equipment which can not be cleaned shall be bagged, sealed and marked externally as NORM contaminated with activity levels and logged as per MSE.06. Any waste generated shall be checked for NORM contamination and if activity is found, placed in drums and logged prior to transportation to the Bahja NORM Yard. NORM Contaminated waste shall be transported to the nearest NORM yard attached with the transport Forms in SP1170 Appendix B and C. Page 4
6 Glossary of Abbreviations Appendix 1 PPE RPT Personal Protective Equipment Radiation Protection Technician Page 5
MSE CONTROLLED DOCUMENT. Radiological HSE Precautions for Pigging Operations
MSE CONTROLLED DOCUMENT Radiological HSE Precautions for Pigging Operations Document No: Supersedes Revision no: 1 1/10/2004 Custodian: MSE Revision no: 1 1/10/2006 Filename: NORMMGT. DOC Administered
More informationMSE CONTROLLED DOCUMENT. Radiological HS&E Precautions for NORM Contaminated Tanks, Vessels & Separators
MSE CONTROLLED DOCUMENT Radiological HS&E Precautions for NORM Document No: Supersedes Revision no: 1 Date:1/10/2004 Custodian: MSE/32 Revision no: 1 Date: 1/10/2006 Filename: NORMMGT. DOC Administered
More informationMSE CONTROLLED DOCUMENT. Decontamination of NORM Contaminated Equipment
MSE CONTROLLED DOCUMENT Decontamination of NORM Contaminated Equipment Document No: Supersedes Revision no: 1 Date:1/10/2004 Custodian: MSE/32 Revision no: 1 Date: 1/10/2006 Filename: NORMMGT. DOC Administered
More informationMSE CONTROLLED DOCUMENT. Decontamination of Personnel
MSE CONTROLLED DOCUMENT Decontamination of Personnel Document No: Supersedes Revision no: 1 Date:1/10/2004 Custodian: MSE Revision no: 1 Date: 1/10/2006 Filename: NORMMGT. DOC Administered by: Verified:
More informationPetroleum Development Oman L.L.C.
RESTRICTED Document ID: SP-1170 Oct 2014 Apr-15 Petroleum Development Oman L.L.C. Natural Occurring Radioactive Material (NORM) Specification Document ID SP-1170 Document Type Specification Security Restricted
More informationNaturally Occurring Radioactive Material (NORM) Supersedes: 05/30/08 (Rev.01) Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager
Procedure No.: PA-020-0021 Page: 1 of 8 Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager Document Revision Change Table Revision Number Revision Description Revised By Revision Date
More informationHealth, Safety and Environment Management System. HSE-PRO-008 HSE Responsibilities Procedure
Health, Safety and Environment Management System HSE-PRO-008 HSE Responsibilities Procedure 1 Table of Contents 1 Intent... 3 2 Scope... 3 3 Definitions... 3 4 Duty, Obligations and Responsibilities...
More informationRemoval of Lead-Based Paint
Safety Management System SP24-61 Process Authority: HS Manager Removal of Lead-Based Paint Approval: Chief Operating Officer Version Date:30/03/2015 Revision: B 1 Purpose To define the requirements for
More informationHazardous Materials Management. Presented by. James E. Roughton, MS, CSP, CRSP, CHMM.
Hazardous Materials Management Presented by. James E. Roughton, MS, CSP, CRSP, CHMM. Hazardous Waste Operations And Emergency Response (HAZWOPER) 29 CFR 1910.120 Scope Clean-up Operations At Uncontrolled
More informationHealth, Safety, Security and Environment
Document owner and change code Document Owner Aaron Perronne Title HSSE Manager Mark X Change Code Description X N/A First Issue A Typographical/Grammatical correction; formatting change; text clarification-no
More informationDate Issued: January 2012 Revision Date: December 2012 Review Date: December 2015 Revision #
SUNCOR ENERGY PRODUCTS DISTRIBUTION TERMINAL OPERATING MANUAL STANDARD OPERATING PROCEDURE MAINTENANCE TASKS Date Issued: January 2012 Revision Date: December 2012 Review Date: December 2015 Revision #
More informationConfined Spaces. This procedure applies to all workers of the Diocese of Maitland Newcastle (DoMN).
Purpose To provide guidance in controlling the risks associated with confined spaces including identifying confined spaces, working in a confined space and issuing confined space entry permits. Scope This
More informationHEALTH AND SAFETY PROGRAM 201 HOT TAP PERMIT/FILLET WELD REPAIRS
Page 1 of 15 1.0 PURPOSE 1.1. Axiall, Plaquemine Complex, has developed this Hot Tap Permit Program to eliminate potential accidents, injuries, and to enhance employee protection. 1.2. To provide for the
More informationDate Issued: November 2011 Revision Date: December 2012 Review Date: December 2015 Revision #
SUNCOR ENERGY PRODUCTS DISTRIBUTION TERMINAL OPERATING MANUAL STANDARD OPERATING PROCEDURE MAINTENANCE TASKS Date Issued: November 2011 Revision Date: December 2012 Review Date: December 2015 Revision
More informationB&B Gas Well Services, LLC HEALTH, SAFETY AND ENVRONMENTAL MANUAL HAZARD COMMUNICATION PROGRAM
B&B Gas Well Services, LLC HEALTH, SAFETY AND ENVRONMENTAL MANUAL HAZARD COMMUNICATION PROGRAM 1 HAZARD COMMUNICATION PROGRAM Table of Contents Topic Page 1.0 Objective 3 2.0 Scope 3 3.0 References 3 4.0
More informationINDUSTRIAL HYGIENE GROUP Standard Operating Procedure. TVA-1000 PID/FID Portable Toxic Vapor analyzer. 1 of 9. Contents
1 of 9 1.0 Purpose & Scope 2.0 Responsibilities 3.0 Definitions 4.0 Prerequisites 5.0 Precautions 6.0 Procedure 7.0 Implementation And Training 8.0 References 9.0 Attachments 10.0 Documentation Contents
More informationPlant Isolation Lock out/tag out Procedure
Plant Isolation Lock out/tag out Procedure Related Policy Responsible Officer Approved by Work Health and Safety Policy Approved and commenced November, 2014 Review by November, 2017 Responsible Organisational
More informationScope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such activities.
11/13/1995 4 5/20/2013 1 of 10 Authority and Scope Regulation: 29 CFR 1910.146 Scope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such
More informationSafe Work Practices and Permit-to-Work System
CHAPTER 24 Safe Work Practices and Permit-to-Work System 24.1 INTRODUCTION OSHA s Process Safety Management (PSM) Standard (OSHA, 1992) requires employers to develop and implement safe work practices (SWPs)
More informationSafe Work Practices / Procedures / Instruction CONFINED SPACE
CONFINED SPACE Entry into and work in a confined space poses health and safety problems which may include: Presence or possible build up of a hazardous atmosphere Unexpected movement of equipment or materials
More informationInternational Association of Drilling Contractors North Sea Chapter HPHT Guidance on MODU Safety Case Content
International Association of Drilling Contractors North Sea Chapter HPHT Guidance on MODU Safety Case Content Contents 1. Abbreviations 2. Background 3. Definition 4. Well Conditions 5. HPHT Safety Case
More informationMANUFACTURING TECHNICAL INSTRUCTIONS - SAFETY FALL HAZARD CONTROL REQUIREMENTS SERIES & NO. SMI - 157
1 of 6 1.0 PURPOSE To establish minimum requirements and guidelines for controlling hazardous exposure of personnel to falls from working elevations in conformance with Federal and State OSHA rules and
More informationControl of Energy - Isolation Process
Issue Date: 24/03/17 Last Reviewed: 24/03/17 Next Review Date: 24/03/18 Authorised By: Mike Muir Safe Operating Procedure Control of Energy - Isolation Process Purpose: This SOP is based on a Generic 12-step
More information1995 Metric CSJ SPECIAL PROVISION ITEM 7. Legal Relations And Responsibilities To The Public
1995 Metric CSJ 0915-12-242 SPECIAL PROVISION TO ITEM 7 Legal Relations And Responsibilities To The Public For this project, Item 7 "Legal Relations and Responsibilities to the Public", of the Standard
More informationHealth and Safety Inspection Procedure
Template v4 WILTSHIRE POLICE FORCE PROCEDURE Health and Safety Inspection Procedure Effective from: 25.03.2012 Last Review Date: 10.05.2015 Version: 2.0 Next Review Date: 10.05.2018 TABLE OF CONTENTS PROCEDURE
More informationCONFINED SPACE WRITTEN PROGRAM
CONFINED SPACE WRITTEN PROGRAM Maple River Public Schools ISD#2135 Confined Space Entry Plan (Permit Required) Maple River Public School Plan last updated: October, 2014 Authority and Scope Regulation:
More informationPROCEDURES FOR STANDBY
1 SCOPE This Procedure details both the circumstances in which standby shall be provided and the responsibilities borne by the Standby Man in such circumstances. 2 ISSUE RECORD This is a maintained/controlled
More informationSEMEMI SQA Unit Code H2AX 04 Carrying out scheduled maintenance tasks on fluid power equipment
Carrying out scheduled maintenance tasks on fluid power equipment Overview This unit identifies the competences you need to carry out scheduled maintenance tasks on fluid power equipment on mobile or static
More information1.0 PURPOSE 2.0 SCOPE 3.0 DEFINITIONS. ANSI: American National Standards Institute. CCC: Chemical Control Centre
Revision Date: 5/17/2016 Page: 1 of 13 Health & Safety has developed the emergency eyewash & safety shower equipment procedure which will be implemented in 3 phases over the next four years. Phase 1 will
More informationEnergy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell:
Energy Control Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: 905.577.0303 cell: 905.977.0210 consultant@staffaid.ca www.staffaid.com Safety, Energy Control, Power Lockout & Function Test Procedures
More informationBitumen Delivery Driver Inductions Eurobitume UK
Bitumen Delivery Driver Inductions Eurobitume UK The information in this module is given in good faith and belief in its accuracy at the time of publication, but does not imply any legal liability or responsibility
More informationHazardous Waste Training Plan. Supersedes: 02/15/16 (Rev.02) Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager
Procedure No.: PA-033-0006 Page: 1 of 19 Port Arthur, TX. Reviewed: 02/18 Effective: 02/06/18 (Rev.03) Supersedes: 02/15/16 Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager Document
More information(2) but does not include a shaft, trench or tunnel that is a mine or is part of the workings of a mine.
Health and Safety Procedure - Confined Spaces Section 1 - Background and Purpose (1) Confined spaces are, for the purposes of this procedure, defined as the following which is the definition under the
More informationSUP 15 Health & Safety Management Pressure Systems. Unified procedures for use within NHS Scotland
SUP 15 Health & Safety Management Pressure Systems Unified procedures for use within NHS Scotland September 2015 Contents Page Acknowledgements... 3 1. Introduction... 4 2. Purpose of this Procedure...
More informationMAINTENANCE AND SAFETY OF CNG REFUELLING STATIONS
ISSN 1172-3416 NZ GCP 2 : 1993 NEW ZEALAND GAS CODE OF PRACTICE for MAINTENANCE AND SAFETY OF CNG REFUELLING STATIONS Issued by the Secretary of Commerce in accordance with the Gas Act 1992 THE GAS ACT
More informationGuidance on the Ionising Radiations Regulations 1999 (IRR99)
Guidance on the Ionising Radiations Regulations 1999 (IRR99) These regulations came into force on 1 st January 2000. A copy of the regulations can be freely downloaded from the following web page:- http://www.legislation.hmso.gov.uk/si/si1999/19993232.htm
More informationPROCEDURE NUMBER: PRC-SAF-16 (Preparation of Piping and Equipment for Repair) Page 1 of 10 Rev. 1.4 Date: 10/17/2016 Rev. 2.
ZACHARY SITE PROCEDURE NUMBER: PRC-SAF-16 (Preparation of Piping and Equipment for Repair) Page 1 of 10 Rev. 1.4 Date: 10/17/2016 Rev. 2.0 Date: 11/7/18 PRC-SAF-16 Zachary Site SAFETY POLICIES and PROCEDURES
More informationThe Airfield Volunteer Fire Service
The Airfield Volunteer Fire Service Breathing Apparatus Deployment Policy Policy Number: P23 Origin: KP Date: 25/06/2015 1 Contents Breathing Apparatus Deployment Policy Page Contents 3 Introduction 3
More informationReviewed: DD Month Management of Closed Radioactive Sources
Safety Office Reviewed: 17 July 2012 Reviewed: DD Month Management of Closed Radioactive Sources A Closed Radioactive Source is a discrete source, i.e. a physically entire source that performs a specific
More informationHAZARDOUS WASTE OPERATIONS AND EMERGENCY RESPONSE
Page 1 of 10 HAZARDOUS WASTE OPERATIONS AND EMERGENCY RESPONSE 1.0 SCOPE This Performance Assessment Guide for Hazardous Waste Operations and Emergency Response (HAZWOPER) will be used to carry out the
More informationManagement Plan for Electrical Safety ISD #535
Management Plan for Electrical Safety ISD #535 Health & Safety Office Maintenance Service Building 10 SE 9 ½ Street Rochester, MN 55904 507-328-4507 MANAGEMENT PLAN FOR ELECTRICAL SAFETY Table of Contents
More informationHazard Communication Plan (HCP) 29 CFR
Hazard Communication Plan (HCP) 29 CFR 1910.1200 METHODIST UNIVERSITY Environmental Health and Safety Office Hazard Communication Plan (HCP) 1910.1200 OSHA Hazard Communication Revision 3 May 2018 Estimated
More informationOBJECTIVE 22: EMERGENCY WORKERS, EQUIPMENT, AND VEHICLES - MONITORING AND DECONTAMINATION
OBJECTIVE Demonstrate the adequacy of procedures for the monitoring and decontamination of emergency workers, equipment, and vehicles. INTENT This objective is derived from NUREG-0654 which provides that
More informationSignificant Change to Dairy Heat Treatment Equipment and Systems
Significant to Dairy Heat Treatment September 2008 Page 1 Significant to Dairy Heat Treatment Equipment and Systems September 2008 1 Background Requirements for the assessment of dairy heat treatment equipment
More informationa) Identify and maintain Worksite Access and Task-specific Safety Training Requirements to ensure job duties are completed in a safe manner.
1. PURPOSE: This standard applies to all Suncor Energy employees, contractors, vendors and visitors working at any In Situ worksite. The mandate of this standard is to identify all critical EHS training
More informationPolicy Redesign Project. Plant Safety Policy. Table of Contents
Policy Redesign Project All policies and procedures are being reviewed as part of this project. This document is pending review, but remains in effect until the review is carried out. Plant Safety Policy
More informationSection: Property WRITTEN HAZARD COMMUNICATION PROGRAM AND ADMINISTRATION Date Created: September, 2006 Date Edited: September, 2006
Deptford Township Board of Education Section: Property 7431. WRITTEN HAZARD COMMUNICATION PROGRAM AND ADMINISTRATION Date Created: September, 2006 Date Edited: September, 2006 POLICY 7431- WRITTEN HAZARD
More informationOBJECTIVE 6: FIELD RADIOLOGICAL MONITORING - AMBIENT RADIATION MONITORING
OBJECTIVE 6: FIELD RADIOLOGICAL MONITORING - AMBIENT RADIATION MONITORING OBJECTIVE Demonstrate the appropriate use of equipment and procedures for determining field radiation measurements. INTENT This
More informationSafe working practices to ensure the integrity of gas assets and associated installations
Communication 1828 Safe working practices to ensure the integrity of gas assets and associated installations Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen Communication 1828 Safe working
More informationHampstead Hill School Health and Safety Policy: Confined Spaces
All Hampstead Hill School Policies are always to be read and considered in conjunction with Equal Opportunities, Race Equality and Inclusion Policies. This Policy of Hampstead Hill School applies to all
More informationSAFEWORK PRACTICES EQUIVALENCY PROCEDURE FOR ACCESSING FLOATING ROOF TANKS ON STORAGE TANKS IN SERVICE CAT A-2 SOP #33
SUNCOR ENERGY PRODUCTS DISTRIBUTION TERMINAL OPERATING MANUAL STANDARD OPERATING PROCEDURE SAFEWORK PRACTICES EQUIVALENCY PROCEDURE FOR ACCESSING FLOATING ROOF TANKS ON STORAGE TANKS IN SERVICE Date Issued:
More informationCVS10 Sanitary Check Valves
0299050/4 IM-P029-11 ST Issue 4 CVS10 Sanitary Check Valves Installation and Maintenance Instructions 1. Safety information CVS10 with soft seat 2. General product information 3. Operation 4. Installation
More informationLEGIONELLA POLICY OUR LADY & ST JOSEPH CATHOLIC PRIMARY SCHOOL
LEGIONELLA POLICY OUR LADY & ST JOSEPH CATHOLIC PRIMARY SCHOOL PREPARED BY: APPROVED BY: DATE: REVIEW DATE: This policy sets out the control of legionella in hot and cold water systems in school, including
More informationUnderground Mine Signs Guideline Underground Fires Major Hazard Standard
WMC Environment, Health & Safety Management System Guideline Underground Fires Major Hazard Standard MHS-02 DocsOpen Ref: 57228, 01/03/2001 Uncontrolled copy check web for latest revision Revision Reviewed
More informationEMA, Inc. SITE SAFETY PLAN
EMA, Inc. SITE SAFETY PLAN A. SITE DESCRIPTION JOB NAME: JOB NUMBER: DATE: PLAN REVISION NUMBER: SITE ADDRESS: Additional Site / Project Information: B. SCOPE OF WORK 1. 2. 3. 4. 5. 6. C. ONSITE ORGANIZATION
More informationEssential Standard No. 16. Streetworks - Short duration static works carried out from a vehicle
Key Messages Short duration static works must not exceed 60 mins, including setting up and dismantling traffic management. A vehicle or vehicles should be used whenever possible to protect the workforce.
More informationCONTROL OF LEGIONELLA POLICY
CONTROL OF LEGIONELLA POLICY DATE OF REVIEW: April 2017 DATE OF NEXT REVIEW: Summer 2020 TO BE REVIEWED BY: Finance Personnel and Premises The school also refers to the guidance laid down in Devon County
More informationHAZWOPER A SAFETY STANDARD FOR EMPLOYEES RESPONDING TO EMERGENCY RELEASES
PAPER HAZWOPER A SAFETY STANDARD FOR EMPLOYEES RESPONDING TO EMERGENCY RELEASES HAZWOPER A Safety Standard for Employees Responding to Emergency Releases Toxic gas clouds, broken pipes spraying liquids
More informationFlammable Environments Guideline
GUIDE Flammable Environments Guideline 2014-0004 The Canadian Association of Petroleum Producers (CAPP) represents companies, large and small, that explore for, develop and produce natural gas and crude
More informationRP COP003 Contamination Monitoring Procedures in Research Laboratories
RP COP003 Contamination Monitoring Procedures in Research Laboratories 1. Introduction When working with radiation it is vitally important that some form of monitoring is undertaken to determine and check
More information"DEALING WITH HAZARDOUS SPILLS"
PRESENTER'S GUIDE "DEALING WITH HAZARDOUS SPILLS" Part of the "SAFETY MEETING KIT" Series Quality Safety and Health Products, for Today...and Tomorrow OUTLINE OF MAJOR PROGRAM POINTS OUTLINE OF MAJOR PROGRAM
More informationIGEM/SR/4 Edition 3 Communication 1752 Variable volume gasholders storing lighter than air gases
Communication 1752 Variable volume gasholders storing lighter than air gases Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen Communication 1752 Variable volume gasholders storing lighter
More informationHealth & Safety Policy & Plan. Rightway Roofing.
Health & Safety Policy & Plan. Rightway Roofing. Valid: 02/2012-02/2013 Contents ( 1 ) Policy Statement. ( 2 ) Hazard Identification. ( 3 ) Hazard Management. ( 4 ) Induction & Training. ( 5 ) Monitoring
More informationSEMEM3-65 Servicing anaesthetic and ventilation equipment
Overview This unit identifies the competences you need to carry out servicing activities on anaesthetic and ventilation equipment, in accordance with approved procedures. You will be required to service
More informationAssessment of Ships and Managers for the Acceptance of Extended Interval Between Bottom Surveys in Dry-Dock
CLASSIFICATION NOTES No. 72.2 Assessment of Ships and Managers for the Acceptance of Extended Interval Between Bottom Surveys in Dry-Dock MAY 2012 The electronic pdf version of this document found through
More informationControl of Allergies to Laboratory Animals
Health and Safety Policy Control of Allergies to Laboratory Animals UHSP/21/CALA/03 This document sets out in more detail the arrangements for compliance with University Health and Safety Policy at Budget
More informationBHC-P-07.2 Health Hazards in Construction
BHC-P-07.2 Health Hazards in Construction Contents 1.0 Purpose 2.0 Scope 3.0 Definitions 4.0 Main requirements 5.0 Guidance documents and references 6.0 Appendices Revision Register Date Version Description
More informationBMA INFORMATION BULLETIN No. 96
BMA INFORMATION BULLETIN No. 96 MAINTAINING PASSENGER SHIPS WATERTIGHT DOORS OPEN DURING NAVIGATION Guidance and Instructions for Ship-owners, Managers, Masters, Bahamas Recognised Organisations and Bahamas
More informationIGEM/TD/2 Edition 2 with amendments July 2015 Communication 1779 Assessing the risks from high pressure Natural Gas pipelines
Communication 1779 Assessing the risks from high pressure Natural Gas pipelines Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen Communication 1779 Assessing the risks from high pressure Natural
More informationWHS PROCEDURE P Confined Spaces. Approved by: Ruth Hampton Review Date: 6 th December 2015
5 WHS PROCEDURE P21-01 Page 1 of 7 Issue: 2 1. Intent The Salvation Army Australia Eastern Territory (TSA-AUE) is committed to the provision of a safe, healthy and injury free environment for all persons
More informationASPEC Engineering HSE Management System. Work Instruction. 1 Objective. 2 Working in confined spaces. 2.1 What is a confined space?
1 Objective This work instruction has been developed to abide by the WHS Regulations (2011) and AS/NZ 2865 Safe working in a confined space. It has been developed around Hadden s typology for risk management,
More informationESSENTIAL SAFETY RESOURCES
ESSENTIAL SAFETY RESOURCES GS-3018 HAZARD IDENTIFICATION AND RISK ASSESSMENT Originator: Safety Advisor s Signature: Type Name Approval: HSE Manager s Signature: Type Name Approval: Operations Manager
More informationCabinet. 1.0 POLICY It is the policy of Calvin College to comply with the MIOSHA Respiratory Protection Standard Part 451.
Calvin College Respiratory Protection Program Prepared by: Date: Heather Chapman 10/7/10 Approved by: Cabinet Revision 2 Date: 1.0 POLICY It is the policy of Calvin College to comply with the MIOSHA Respiratory
More informationA MESSAGE FROM THE MD
A MESSAGE FROM THE MD The Life Saving Rules set out clear and simple dos and don ts covering activities with the highest potential safety risk and apply to all employees and contractors. The best-performing
More informationPipeline Pigging and Hydrostatic Test
Project Engineering Standard Solutions, Standards and Software www.klmtechgroup.com Page 1 of 20 Rev: 01 KLM #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia. KLM
More informationANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS
Annex 3, page 2 ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS The text of existing chapter 15 is replaced by the following: "1 Application This
More informationPRESSURE SYSTEMS POLICY
PRESSURE SYSTEMS POLICY PRESSURE SYSTEMS POLICY 1. Introduction 2. Policy Statement 3. Scope 4. Background 5. Roles & Responsibilities 6. Training 7. Contractors 8. Policy Review 1. Introduction The Kilmarnock
More information2.0 Management Systems and Documentation
SHE Rules BOW142.3 1.0 Introduction This document details the safety, health and environment rules that apply to anyone accessing Arqiva sites and describes the standards of performance expected. This
More informationCompetency type. positions. All workers (including contractors), higher degree students and volunteers
Appendix A Training Required for Work Health & Safety Training WHS general and/or site/work specific induction of the emergency procedures and assembly areas Local first aid provisions. of hazards and
More informationSEMEM3-73 Maintaining medical gas pipeline systems and equipment
Maintaining medical gas pipeline systems and equipment Overview This unit identifies the competences you need to carry out maintenance activities on medical gas pipeline systems and equipment, in accordance
More informationCONFINED SPACE AWARENESS
Document Number: HSE09-001 June 1, 2013 AWARENESS Author: A Holland MAPP Construction - Corporate 344 Third Street Baton Rouge, LA 70801 (225) 757-0111 MAPP Construction - Houston 1511 Katy Freeway, Suite
More informationIMMANUEL CHURCH, CHICHESTER HEALTH AND SAFETY POLICY
IMMANUEL CHURCH, CHICHESTER HEALTH AND SAFETY POLICY Approved by the Trustees: November 2016 Health and Safety Policy Introduction The main piece of health and safety legislation is the Health and Safety
More information! Subpart D - Contingency Plans and Emergency Procedures (40 CFR to ) (EPA regulations adopted by NJDEP); and
APPENDIX D EMERGENCY PROCEDURES IN PUBLIC SECONDARY SCHOOLS IN THE EVENT OF A CHEMICAL SPILL There are five major sources of regulations that are potentially applicable to emergencies involving a chemical
More informationStandards of Practice Personal Protective Equipment
Document Authority: I. PURPOSE Standards of Practice Personal Protective Equipment Whenever feasible, hazards must be eliminated through engineering, and/or administrative controls, prior to resorting
More informationBT6HC Hygienic Sanitary Balanced Pressure Steam Trap for High Capacity and CIP/SIP Applications
1800350/6 IM-P180-12 ST Issue 6 BT6HC Hygienic Sanitary Balanced Pressure Steam Trap for High Capacity and CIP/SIP Applications Installation and Maintenance Instructions 1. Safety information 2. General
More informationEVENT SAFETY RISK ASSESSMENT - (SMALL TO MEDIUM SIZED COMMUNITY EVENTS) 1
EVENT SAFETY RISK ASSESSMENT (SMALL TO MEDIUM SIZED COMMUNITY EVENTS) EVENT SAFETY MANAGEMENT INFORMATION SHEET September 2010 #3 RISK ASSESSMENT IT S A MUST The success of your event is measured in many
More informationMethod Statement Author
Plan Bee Limited 3.3 Etna Industrial estate Clamp Road Motherwell Scotland ML2 7XQ Tel: 01698580572 Method Statement Method Statement Details Method Statement Number 7 Method Statement Date Monday 3rd
More informationTo ensure compliance to WorkSafeBC Regulation Part 9 Confined Space Entry which states:
Manufacturing SS No. 4 Safety Standard Confined Space Purpose: These procedures were developed to protect employees from the serious hazards associated with.entering and working within confined spaces.
More informationCONTRACTOR WHS HAZARD STANDARD HAZARDOUS CHEMICALS EXTERNAL USE ONLY
CONTRACTOR WHS HAZARD STANDARD HAZARDOUS CHEMICALS EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition
More informationSafe work method statements
Information about Safe work method statements How to prepare and use a safe work method statement (SWMS) for high risk construction work (HRCW) and who needs to prepare one. October 2018 Key concepts Hazard
More informationMANAGING INDUSTRIAL SITE RADIOGRAPHY WORK
S R P THE SOCIETY FOR RADIOLOGICAL PROTECTION MANAGING INDUSTRIAL SITE RADIOGRAPHY WORK What is Site Radiography? Industrial radiography involves the use of industrial X-ray sets and/or high-activity gamma
More informationSOUTHBANK PLACE Asbestos Removal (Brief Guide)
SOUTHBANK PLACE Asbestos Removal (Brief Guide) The removal of asbestos is regulated by the Control of Asbestos Regulations 2012 and is only undertaken by licensed contractors. The licensing procedures
More informationDF1 and DF2 Diffusers
1550650/4 IM-P155-07 ST Issue 4 and Diffusers Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Commissioning 5. Operation 6. Maintenance
More informationQarn Alam & Saih Rawl Hazard Hunt 8 th - 11 th April 2018
MSEM Partnership in HSE 2018 Top9 HSE exposures Hazard Hunt 1 Qarn Alam team Hazard Hunt Kick Off Meeting Kick Off Meeting 2 Qarn Alam Steam PDO Mechanical Crew Hazard Hunt Team Engagement Coaching Moments
More informationContractor/Visitor Safety Orientation UNBC
Contractor/Visitor Safety Orientation UNBC 3333 University Way, Prince George, BC V2N 4Z9 Revised: October 2015 For All Emergencies call Security 250-960-7058 ***DO NOT DIAL 911*** Important UNBC Telephone
More informationGeotechnics, Face and Stockpile Operations
Quarries National Joint Advisory Committee (QNJAC) Geotechnics, Face and Stockpile Operations Information Sheet 4 October 2012 Duties of the Operator This information sheet has been developed by the Quarries
More informationIn an emergency the safety of all personnel and the public is of priority.
P272 : Emergency Planning & Response This DOCUMENT and any linked FORMS have been created to provide specific requirements under the Amalgamated Operating System. For additional information and guidance,
More informationTitle/Description: Fuel Cell Fill Procedure
Fuel Cell Procedure Document No.: Author: Kurt Stiffel Title/Description: Approved by: Revision: 1-00 Effective Date: 1.0 Reference Documents All released OOI documents in Alfresco 3161-20000 Fuel Cell
More informationApplication of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines
Communication 1737 Application of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen
More informationSEMIC05 Installing mechanical equipment
Overview This unit identifies the competences you need to install mechanical equipment, in accordance with approved procedures. This will require you to survey the site for the proposed installation, and
More information