1 3800, 525 8th Avenue S.W. Calgary, Alberta T2P 1G1 Project Specific Information Package Kakwa Expansion Pipeline Project Pembina Pipeline Corporation ( Pembina ) plans to make an application to the Alberta Energy Regulator ( AER ) for approval to construct and operate the Kakwa Expansion Pipeline Project ( the Project ). The Project consists of the construction of approximately 69 km of 16-inch diameter pipeline from a tie-in point located at LSD W6M at the existing Kakwa Pump Station to a tie-in point located at LSD W5M. The Project is needed to connect existing and future supply of high vapour pressure ( HVP ) and low vapour pressure ( LVP ) hydrocarbon liquids from the Kakwa and Lator areas of Alberta into the 16 inch Simonette Expansion (currently under construction) that terminates at the Pembina Fox Creek facility. The Project will be under the jurisdiction of the Alberta Energy Regulator ( AER ). As per AER Directive 056 Energy Development Applications and Schedules requires that parties whose rights may be directly and/or adversely affected by the nature and extent of the proposed Project be consulted and/or notified of the Project-specific details. Project Description Pembina is committed to full disclosure of its planned projects so landowners, occupants, Crown disposition holders, local and urban authorities, Aboriginal communities and other groups or individuals with interests in the area are informed of the activities proposed. The following table summarizes Pembina s plans regarding the above noted Project. If you require any additional information or would like to talk with a Pembina representative regarding this Project, please do not hesitate to call the contacts listed at the end of this information package. AER Category and Type The Kakwa Expansion Pipeline Project is classified by the AER as a Category D, Type 530 pipeline. Location The Project will originate at a tie-in point located at LSD W6M at the existing Kakwa Pump Station and will terminate at a tie-in point located at LSD W5M. A map showing the Project location is attached. Page 1 of 6
2 Project Description The Project consists of the construction of approximately 69 km of 16-inch diameter pipeline from a tie-in point located at LSD W6M at the existing Kakwa Pump Station to a tie-in point located at LSD W5M. The pipeline will be designed to transport High Vapor Pressure liquids ( HVP ) and Low Vapour Pressure ( LVP ) liquids. HVP hydrocarbon liquids are a mix of ethane, propane, butane and pentanes plus. The LVP, liquids include condensate and crude oil. Pembina is currently completing its pipeline engineering design. Watercourses along the pipeline route are being assessed for the presence of fish and fish habitat by a Qualified Aquatic Environment Specialist. In consultation with Fisheries and Oceans Canada and Alberta Environment and Sustainable Resource Development, Pembina will determine the most appropriate crossing methods to minimize disturbance, which may include horizontal directional drilling and isolation techniques when water is flowing. Project Need The Project is needed to connect a growing supply of HVP and LVP hydrocarbon liquids in the Kakwa and Lator area of Alberta to existing processing facilities in the Edmonton/Fort Saskatchewan/Redwater area of Alberta. Currently, Pembina has incremental capacity available on the existing Peace Pipeline System from Fox Creek to the Edmonton/Fort Saskatchewan/Redwater area but does not have capacity on the pipelines between Kakwa and Fox Creek to deliver product beyond Fox Creek. Pembina previously consulted on and is currently constructing a project that will increase capacity between the Simonette area and Fox Creek. This Project will provide producers in the Kakwa and Lator/Karr areas with pipeline connectivity to transport volumes to the Simonette area and then ultimately to Edmonton/Fort Saskatchewan/Redwater on the existing Pembina pipeline system instead of trucking volumes to terminals in and around the Fox Creek area. The Project will ultimately reduce the number of trucks carrying hydrocarbon product on the local roads and will provide producers with a more efficient and safer means of transporting volumes to markets. In the future, the Project will be required to transport new volumes of HVP and LVP liquid hydrocarbons, that will be developed in the immediate area and the area west/northwest of the Kakwa river. Substance Type The product transported in the pipeline will include HVP and LVP hydrocarbon liquids. H 2 S There will be no hydrogen sulphide (H 2 S) in the product transported on the pipeline. Page 2 of 6
3 Project Schedule and Duration After receipt of all applicable regulatory approvals, Pembina plans to initiate clearing and construction of the Project sometime in Q Pembina estimates the Project will be in operation starting Q Safety / Environment Pembina is committed to health, safety and environmental stewardship throughout the life of this and all its projects. Pembina has a strong reputation for constructing and operating facilities designed to meet or exceed AER safety and environmental protection regulations and guidelines. Pembina commits to continue to meet or exceed these guidelines and regulations. Pembina encourages a workplace that places a high priority on the health and safety of employees, contractors and the public at large, and ensures its pipelines and facilities meet the highest standards. Pipeline Integrity Pembina s integrity management program is founded on quality management principles, technical programs and system-specific analysis. It incorporates industry best practices that are designed to meet or exceed regulatory requirements. A strict focus on safe and reliable operations lessens the likelihood of pipeline incidents, sustains Pembina s license to operate, and ultimately reduces the cost of operations. The cornerstone of Pembina s pipeline integrity management program is the use of in-line inspection technologies to detect corrosion and ultrasonic devices to detect cracks. Pembina also employs customized Supervisory Control and Data Acquisition (SCADA) technology to monitor pipeline flow and operating conditions. Operators oversee the SCADA system and associated leak detection software 24-hours a day, 365 days per year. Pembina maintains a geotechnical database designed to help minimize integrity hazards associated with ground movement and watercourse channelling. Such technologies allow Pembina to proactively identify potential pipeline threats and prevent spills from occurring. To further protect the integrity of Pembina s pipelines against possible damage by third-party excavators or construction activity, Pembina maintains routine aerial patrols and is a long-standing member of the Alberta One-Call system. Pembina continues to enhance its public awareness program by regularly meeting with local first-responders and visiting with landowners. Page 3 of 6
4 Emergency Response Plan Emergency Response Planning Zone Pembina is dedicated to protecting the health and safety of the public as well as its employees and contractors. Operations will be conducted in strict accordance with industry best practices and in compliance with all applicable technical and safety standards and regulations. Pembina personnel are trained to recognize hazards and deal with emergency situations so that any abnormal situation that might arise can be quickly detected and corrected. A Emergency Response Plan ( ERP ) covering this Project will be developed, approved and implemented prior to the commencement of operation of the Project. The ERP will meet the requirements of the AER s Directive 071 Emergency Preparedness and Response Planning for the Petroleum Industry. Pembina will adopt an Emergency Planning Zone ( EPZ ) of 1600 metres for this Project measured from either side of the centre line of the pipeline based on the CAPP Guide Companion Planning Guide to ERCB Directive 071 for a 16-inch diameter pipeline. Setbacks As with all pipelines and facilities, there are minimum setback distances required between an energy facility or pipeline and a dwelling, public facility, rural housing project or urban centre. Simply put, setbacks prevent populated areas from developing too close to energy facilities or pipelines and prevent energy facilities and pipelines from getting too close to people. The setback distance for this Project is the pipeline right-of-way which will be 25 meters. Traffic As with any construction project, there will be a temporary increase in intermittent noise and traffic due to the movement of equipment and construction personnel to and from the construction site. If there are any concerns regarding excessive traffic during construction they should be reported to one of the contacts listed at the end of this information package. There will be no increase in traffic during the operation of the Project as the pipeline will be operated and maintained by the personnel who currently work on the existing Pembina Pipeline system. The Project will ultimately reduce the number of trucks carrying hydrocarbon product on the local roads and will provide producers with a safer means of transporting volumes to markets. Page 4 of 6
5 Noise During construction, there will be a temporary increase in noise due to the movement of traffic and equipment to and from the right-of-way. Pembina will work with its neighbours to address noise-related concerns during construction, should they arise. If there are concerns regarding excessive noise during construction, please contact one of the Pembina representatives listed at the end of this information package. There will be no new sources of noise during the operation of the Project. Noise levels will comply with the AER requirements of Directive 038 Noise Control. Odours/Emissions Pembina does not expect any odours from the operation of the Project. Pembina asks that any unusual odours be reported immediately to its local operations representative or call its 24-hour emergency number Pembina will promptly investigate and ensure any problems are corrected. Continuous Venting/Flaring There will be no continuous permanent flaring associated with the Project. Additional Information Thank you for taking the time to read this handout. If you have questions or concerns, please do not hesitate to the Pembina representative listed in the Contacts section below. In addition, the Alberta Energy Regulator ( AER ) has developed additional information about energy development in Alberta. As per AER Directive 56 please find enclosed a copy of the Letter from the Chairman of the AER. Upon request, Pembina would be pleased to provide copies of: AER brochure Understanding Oil and Gas Development in Alberta EnerFAQ No. 7 Proposed Oil and Gas Development: A Landowner guide EnerFAQ No. 15 Objecting to an Energy Resource Project, and form Objecting to an Energy Resource Project. You are encouraged to contact Pembina or the AER directly through their website, by telephone, or fax, to obtain additional AER EnerFAQs, Information Directives or General Bulletins pertaining to oil and gas operations. Page 5 of 6
6 ALBERTA ENERGY REGULATOR - CALGARY MAIN OFFICE To call toll-free, dial or , and then the Calgary number, with area code Alberta Energy Regulator Suite 1000, th Street SW Calgary Alberta, T2P 0R4 Toll-free inquiries@aer.ca Website: Contacts If you have questions or concerns, please do not hesitate to call any of the Pembina representatives listed below. If you are calling outside of business hours, please leave a message with one of the representatives and your call will be returned the next business day. If this is an emergency please contact the Pembina 24 Hour Emergency Number at Please note this number is for emergencies only. Surface Landman, Chad Dalke directly at (587) Aboriginal Relations, Wolf Schroeder directly at (403) Pembina 24 Hour Emergency Number: Page 6 of 6
Project Specific Information Package Simonette Expansion Pipeline Project
Date of Handout: 3800, 525 8th Avenue S.W. Calgary, Alberta T2P 1G1 File #: Project Specific Information Package Simonette Expansion Pipeline Project Pembina Pipeline Corporation ( Pembina ) plans to make
More informationSAFETY PIPELINE. Simonette Expansion Pipeline Project
Simonette Expansion Pipeline Project PIPELINE SAFETY You have received this brochure because we have identified that you live or work near one of Pembina Pipeline Corporation s natural gas liquids (NGL)
More informationSAFETY PIPELINE. Kakwa Pipeline Expansion Project
Kakwa Pipeline Expansion Project PIPELINE SAFETY You have received this brochure because we have identified that you live or work near one of Pembina Pipeline Corporation s natural gas liquids (NGL) or
More informationPembina Pipeline Corporation Crude Oil Pipeline Failure Licence No. 1386, Line No. 003 June 15, 2008
Pembina Pipeline Corporation Crude Oil Pipeline Failure Licence No. 1386, Line No. 003 June 15, 2008 ERCB Investigation Report February 11, 2009 Report prepared by Brian Temple (Incident Investigator),
More informationPEMBINA PIPELINE CORPORATION
PEMBINA PIPELINE CORPORATION PETROLEUM TOLL SCHEDULE TOLLS APPLYING TO THE TRANSPORTATION OF PETROLEUM ON THE PEACE HVP PIPELINE SYSTEM Effective: January 1, 2016 ISSUED BY: Pembina Pipeline Corporation
More informationACTION PLAN FOR AER DECISION PEMBINA PIPELINE CORPORATION APPLICATIONS FOR TWO PIPELINES - PIPELINE EXPANSION PROJECT, FOX CREEK TO NAMAO
ACTION PLAN FOR AER DECISION PEMBINA PIPELINE CORPORATION APPLICATIONS FOR TWO PIPELINES - PIPELINE EXPANSION PROJECT, FOX CREEK TO NAMAO ACTION ITEM 1 Mr. Nielsen s Property Pembina must reduce the permanent
More informationCEPA Initiative: Response Time Guideline 2015 EMERGENCY SECURITY MANAGEMENT WORK GROUP
CEPA Initiative: Response Time Guideline 2015 EMERGENCY SECURITY MANAGEMENT WORK GROUP Response Time Guideline aboutpipelines.com 1 of 8 Contents Table of Contents 1.0 Background 3 Purpose 3 Scope 3 Definitions
More informationFlammable Environments Guideline
GUIDE Flammable Environments Guideline 2014-0004 The Canadian Association of Petroleum Producers (CAPP) represents companies, large and small, that explore for, develop and produce natural gas and crude
More informationIntroduction to Emergency Response & Contingency Planning
& Contingency Planning Rationale Why is it important for you to learn this material? Designed for those who may witness a release, this is an introductory course designed to help ensure those who are likely
More informationResponding to Natural Gas Pipeline Emergencies
Responding to Natural Gas Pipeline Emergencies Who is Florida Gas Transmission? Florida Gas Transmission operates nearly 5,000-miles of interstate natural gas transmission pipelines, a system that extends
More informationHEALTH AND SAFETY PROGRAM 201 HOT TAP PERMIT/FILLET WELD REPAIRS
Page 1 of 15 1.0 PURPOSE 1.1. Axiall, Plaquemine Complex, has developed this Hot Tap Permit Program to eliminate potential accidents, injuries, and to enhance employee protection. 1.2. To provide for the
More informationTAQA North Ltd. Well Blowout W4M June 8, 2009
TAQA North Ltd. Well Blowout 10-10-28-29W4M June 8, 2009 ERCB Investigation Report January 11, 2010 Report prepared by Brian Temple (Incident Investigator), Rondine Cabot (Field Surveillance), Mark R.
More informationBP U.S. Pipelines & Logistics (USPL) Safety Manual Page 1 of 8
Safety Manual Page 1 of 8 1. Purpose The purpose of this policy is to protect USPL employees and contractors from overexposure to benzene. 2. Scope This policy applies to all USPL employees and contractors
More information2. IMMEDIATE RESPONSE ACTIONS AND NOTIFICATION PROCEDURES
2. IMMEDIATE RESPONSE ACTIONS AND NOTIFICATION PROCEDURES This section of the GOSRP provides the general procedures to be followed at the time of an incident. The section is distinctively marked by a RED
More informationPEMBINA PIPELINE CORPORATION
PEMBINA PIPELINE CORPORATION PETROLEUM TOLL SCHEDULE TOLLS APPLYING TO THE TRANSPORTATION OF PETROLEUM ON THE PEACE LVP PIPELINE SYSTEM Effective: June 1, 2018 ISSUED BY: Pembina Pipeline Corporation 4000,
More informationPEMBINA PIPELINE CORPORATION
PEMBINA PIPELINE CORPORATION PETROLEUM TOLL SCHEDULE TOLLS APPLYING TO THE TRANSPORTATION OF PETROLEUM ON THE PEACE LVP PIPELINE SYSTEM Effective: July 1, 2017 ISSUED BY: Pembina Pipeline Corporation 4000,
More informationPembina Pipeline Corporation Pipeline Failures Licence No. 2349, Line No. 10 July 20 and August 15, 2011
Pembina Pipeline Corporation Pipeline Failures Licence No. 2349, Line No. 10 July 20 and August 15, 2011 ERCB Investigation Report February 26, 2013 ENERGY RESOURCES CONSERVATION BOARD ERCB Investigation
More informationFAQs about Directive PNG017: Measurement Requirements for Oil and Gas Operations
FAQs about Directive PNG017: Measurement Requirements for Oil and Gas Operations General Is it acceptable to report no gas production? All associated gas (gas produced from an oil well) or non-associated
More informationINADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD)
INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) FACILITY OPERATOR: NextEra Energy Resources, LLC 700 Universe Boulevard Juno Beach, FL 33408 For Horizontal Directional Drilling Contents
More informationSection J. How to develop safety elements for project safety management system. How to develop safety elements for project SMS
Section J How to develop safety elements for project safety management system 1. Once the project management has developed or adopted a safety policy, it needs to develop safety elements to meet the objectives
More informationSITE INSPECTION PROCEDURE FORM
SITE INSPECTION PROCEDURE FORM The Oil and Gas Commission, as regulators of British Columbia s oil and gas industry focuses on effectively regulating and managing the Provinces oil and gas sector. The
More information1995 Metric CSJ SPECIAL PROVISION ITEM 7. Legal Relations And Responsibilities To The Public
1995 Metric CSJ 0915-12-242 SPECIAL PROVISION TO ITEM 7 Legal Relations And Responsibilities To The Public For this project, Item 7 "Legal Relations and Responsibilities to the Public", of the Standard
More informationSITE REGISTRATION INFORMATION PACKAGE
SITE REGISTRATION INFORMATION PACKAGE STARS EMERGENCY LINK CENTRE The STARS Emergency Link Centre (ELC) was established in 1996 to meet the needs of Industry working in remote locations. The resulting
More informationAUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011
AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF SEMS HAZARD ANALYSIS TRAINING September 29, 2011 Purpose The purpose of this meeting is to provide guidelines for determination of hazard
More informationAPI MPMS Chapter 17.6 Guidelines for Determining the Fullness of Pipelines between Vessels and Shore Tanks
API MPMS Chapter 17.6 Guidelines for Determining the Fullness of Pipelines between Vessels and Shore Tanks 1. Scope This document describes procedures for determining or confirming the fill condition of
More informationDelaware State University
Delaware State University University Area Responsible: Risk and Safety Management Policy Number and Name: 7-06: Confined Space Policy Approval Date: 7/28/11 Revisions: _8/8/2013 Reviewed: 7/26/2013 Related
More informationTEMPLE UNIVERSITY ENVIRONMENTAL HEALTH AND RADIATION SAFETY
Purpose In accordance with applicable regulations and Temple University, this policy was developed to minimize exposure to glutaraldehyde. Applicability This policy is applicable to all Temple University
More informationSEMS II: BSEE should focus on eliminating human error
SEMS II: BSEE should focus on eliminating human error How US companies can prevent accidents on start-ups and shut-downs by using valve interlocks The proposed changes to BSEE s SEMS (Safety and Environmental
More informationAddendum 4 Levels of Response
Addendum 4 Levels of Response Levels of Response to a Hazardous Materials Incident A. Criteria for Categorization Hazardous materials incidents are categorized as Level I, II, or III depending on the severity
More informationPandemic / All Hazards Planning
Pandemic / All Hazards Planning Community Advisory Council Meeting: 1/4/2010 This presentation summarizes FHR s strategies for pandemic and all hazard planning for our Pine Bend Refinery. Pandemic Planning
More informationCONTROL OF SUBSTANCES HAZARDOUS TO HEALTH PROCEDURE
CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH PROCEDURE 1. INTRODUCTION The University uses substances hazardous to health in many of its operations, and accepts that it has a duty of care to reduce exposure
More informationSection Decanting Response Tool
Section 9411 Decanting Response Tool T able of Contents Section Page 9411 Decanting Response Tool... 9411-1 9411.1 Introduction... 9411-1 9411.2 Decanting Policy... 9411-1 9411.2.1 Criteria... 9411-1 9411.2.2
More informationO&M MANUAL HIGHLIGHTS
O&M MANUAL HIGHLIGHTS GENERAL PROVISIONS Each pipeline must be operated according to this SUBPART 192.603(a) RECORDS 192.603(b) Keep records necessary to administer the procedures of 192.605 RECORDS Life
More informationPIPELINE SAFETY. Darin Burk, Manager Pipeline Safety. January 28, 2014
PIPELINE SAFETY Darin Burk, Manager Pipeline Safety January 28, 2014 Congressional Delegation of Authority Pipeline Safety Act of 1968 Congress Delegated Inspection and Enforcement Authority to the Secretary
More informationPEMBINA PIPELINE CORPORATION
PEMBINA PIPELINE CORPORATION PETROLEUM TOLL SCHEDULE TOLLS APPLYING TO THE TRANSPORTATION OF PETROLEUM ON THE DRAYTON VALLEY PIPELINE SYSTEM Effective: January 1, 2018 ISSUED BY: Pembina Pipeline Corporation
More informationEUSMUNC06 (SQA Unit Code - FG2W 04) Locate and avoid supply apparatus for Utilities Network Construction
Locate and avoid supply apparatus for Utilities Network Construction Overview This national occupational standard defines the competence involved in locating and avoiding supply apparatus by using appropriate
More information<:\_J Senior Manager- Safety, Security & Emergency Response. Ell ORIGINAL DELIVERED BY COURIER. June 7, 2017
ORIGINAL DELIVERED BY COURIER June 7, 2017 National Energy Board Suite 210, 517-10 th Avenue SW Calgary, Alberta T2R 0A8 Ell J 111 ' - 7 I Attention: Ms. Sheri Young Secretary of the Board Dear Ms. Young:
More informationConfined Space Program
Insert City Name Page 1 of 6 Purpose Regularly, confined spaces must be entered for inspection, cleaning or repair. Such spaces can present unusual hazards such as lack of sufficient oxygen, special mechanical
More informationNew Hampshire Public Utilities Commission CFR 49 Part 192 Regulations. MINIMUM Pipeline Safety Regulations
New Hampshire Public Utilities Commission CFR 49 Part 192 Regulations MINIMUM Pipeline Safety Regulations Application for Jurisdictional LPG Operators 1 Pipeline Safety Regulations 49 CFR Part 192 (NOTE:
More informationScope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such activities.
11/13/1995 4 5/20/2013 1 of 10 Authority and Scope Regulation: 29 CFR 1910.146 Scope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such
More informationRelease: 1. UEPOPL002A Licence to operate a reciprocating steam engine
Release: 1 UEPOPL002A Licence to operate a reciprocating steam engine UEPOPL002A Licence to operate a reciprocating steam engine Modification History Not applicable. Unit Descriptor Unit Descriptor 1)
More informationBSR GPTC Z TR GM References and Reporting Page 1 of 8
Page 1 of 8 PRIMARY: 192.605 SECONDARY: 191.23 PURPOSE: Review guide material added by TR 2009-17 to 5.1(e) and consider restructuring the guide material under 192.605 as discussed further below. ORIGIN/RATIONALE
More informationFAQs about Directive 017
FAQs about Directive 017 General What measurement points are covered in this directive? The requirements in this directive cover all measurement points required by the Oil and Gas Conservation Regulations
More informationRegulated Oil and Gas Companies under National Energy Board Jurisdiction
File 185-A000-41 8 August 2003 Regulated Oil and Gas Companies under National Energy Board Jurisdiction Dear Sir / Madam: Guidance Notes for Pressure Equipment under National Energy Board Jurisdiction
More informationMisuse of Combustible Gas Meters
Misuse of Combustible Gas Meters An incident investigation raised concerns that users of combustible gas meters may be greatly underestimating fire and explosion hazards. Errors result when meters calibrated
More informationTo comply with the OHS Act, the responsible manager must carry out and document the following:
Owner: Manager Health, Wellbeing and Safety Last Update: 10 January 2018 Contents 1. Purpose... 1 2. Minimum Compliance Requirements... 1 3. Definitions... 2 4. Legislative requirements under the OHS Act
More informationBe our partner in safe, reliable natural gas delivery
Wide Web at. pipeline operators. The industry has a proven record of safety. Por favor visite para Main, House Main Wide Web at. pipeline operators. The industry has a proven record of safety. Por favor
More informationHAZARDOUS SUBSTANCE AND DANGEROUS GOODS
The Barro Group is committed to continuously improving the management and standards of Occupational Health and Safety. This commitment extends to minimising exposure of employees, contractors, visitors
More informationPSM TRAINING COURSES. Courses can be conducted in multi-languages
Courses can be conducted in multi-languages One set of hardcopy course notes will be sent to client for printing and distribution to course participants. The courses will be held at the client s training
More informationSection Decanting Response Tool
Section 9411 Decanting Response Tool T able of Contents Section Page 9411 Decanting Response Tool... 9411-1 9411.1 Introduction... 9411-1 9411.2 Decanting Policy... 9411-1 9411.2.1 Criteria... 9411-1 9411.2.2
More informationERCBH2S Frequently Asked Questions.
ERCBHS Frequently Asked Questions. Issue: Sweet pipeline tie-in to a sour gathering system A company is tying a sweet pipeline into one containing HS. Since the model assumes flow from either end of the
More informationTown of Berwick Maine. Request for Proposal Ambulance Services. July 1, June 30, 2014
Town of Berwick Maine Request for Proposal Ambulance Services July 1, 2013 - June 30, 2014 1. General No less than 10 copies of the proposal shall be received by the Town before close of business on March
More informationProvince of Alberta Rat Control Plan
Province of Alberta Rat Control Plan Appendix I - Rat Control Plan Objective Alberta s rat free status is important to Alberta s Agricultural Industry and to the urban communities economically. This protocol
More information1.1 EMERGENCY PLAN PURPOSE AND OBJECTIVE...
TABLE OF CONTENTS 1.1 EMERGENCY PLAN PURPOSE AND OBJECTIVE... 1 1.1.1 PURPOSE... 1 1.1.2 OBJECTIVES... 1 1.2 PLAN SCOPE & POLICY... 2 1.3 EMERGENCY RESPONSE PHILOSOPHY... 2 1.4 DISCLAIMER... 3 1.5 MANUAL
More informationthe annulus between the second casing string and the surface casing [must be] open to the atmosphere in the manner described in subsection (2).
Bulletin 2011-35 December 20, 2011 Surface Casing Vent Requirements for Wells This bulletin clarifies Section 6.100(4) of the Oil and Gas Conservation Regulations (OGCR) and provide additional surface
More informationHAZARD MANAGEMENT PROCEDURE
TABLE OF CONTENTS 1. OBJECTIVE... 2 2. SCOPE... 2 3. DEFINITIONS... 2 4. RESPONSIBILITIES... 2 5. HAZARD IDENTIFICATION... 3 5.1 HAZARD AND RISK IDENTIFICATION TOOLS AND METHODS... 3 5.1.1 Take 5 Risk
More informationHEALTH AND SAFETY MANUAL
HEALTH AND SAFETY MANUAL Title: Benzene Exposure Control Program Approved by: Greg Savoy Rev. 4/1/08 1 Purpose/Scope: The purpose of this program is to define work practices, administrative procedures
More informationThe ERCB Directive 017 Overview
The ERCB Directive 017 Overview November 4, 2009 By Bill Cheung Why measure and report production, flaring, and venting? Public Safety and Environment Understand and monitor emissions Reservoir Engineering
More information(b) Venting or flaring shall only be authorized by the Commission under the following circumstances:
Chapter 3, Section 39. Authorization for Flaring and Venting of Gas. (a) Venting or flaring must be in accordance with Commission requirements to prevent waste as specified in W.S. 30-5-101(a)(i)(G), 102(a),
More informationCONFINED SPACE ENTRY PROGRAM
CONFINED SPACE ENTRY PROGRAM 2003 ENVIRONMENTAL HEALTH AND SAFETY/RISK MANAGEMENT p1 Rev. 01/07/2003 wrk Environmental Health and Safety/Risk Management CSUCI Confined Space Entry Program TABLE OF CONTENTS
More informationVermin, Insects and Scavenging Birds Management Plan
VIRIDOR WASTE MANAGEMENT LIMITED Lostock Waste Treatment Plant Vermin, Insects and Scavenging Birds Management Plan CONTENTS 1 Introduction... 2 2 Sources, Releases and Impacts... 3 3 Vermin, Insects and
More information! Subpart D - Contingency Plans and Emergency Procedures (40 CFR to ) (EPA regulations adopted by NJDEP); and
APPENDIX D EMERGENCY PROCEDURES IN PUBLIC SECONDARY SCHOOLS IN THE EVENT OF A CHEMICAL SPILL There are five major sources of regulations that are potentially applicable to emergencies involving a chemical
More informationHow HSE regulates onshore oil and gas
Health and Safety Executive How HSE regulates onshore oil and gas Paul Bradley (Operations Manager Wells and Mines) Craig Norman (Well Engineering and Operations Inspector) Health & Safety Executive Health
More informationManaging Positive Pathogen Results. Safe Food California April 20, 2016 Frederick Cook, Ph.D. Post Consumer Brands
Managing Positive Pathogen Results Safe Food California April 20, 2016 Frederick Cook, Ph.D. Post Consumer Brands Managing Positive Pathogen Results Requires immediate and effective response Establish
More informationSPILL CONTINGENCY AND EMERGENCY RESPONSE PLAN
SPILL CONTINGENCY AND EMERGENCY RESPONSE PLAN All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means, electronic or mechanical, without the written
More informationEmergency Response Policy
EIS for 2010-2029 FSP Section 14-170 October 1, 2001 Emergency Response Policy The Tembec Forest Resource Management Pine Falls Operations is committed to the highest level of emergency preparedness to
More informationSAFE GUIDE DIGGING FOR RESIDENTS.
SAFE DIGGING GUIDE FOR RESIDENTS www.marathonpipeline.com 1 A MESSAGE FOR RESIDENTS Over 300,000 incidents of underground utility damage were reported in the United States in 2016*. Digging into underground
More informationGulfstream Natural Gas System
Website: www.gulfstreamgas.com Gulfstream has prepared this fact sheet as a guide for emergency response officials who may be asked to respond to an incident involving a Gulfstream natural gas pipeline
More informationOverview EUSSAM12. Carry out tightness testing and direct purging of gas installations
Overview This standard covers tightness testing and direct purging of low or medium pressure gas, in accordance with approved procedures and practices. It covers the standards required to meet the requirements
More informationHazardous Materials Management Guidelines
Environmental, Health and Safety Guidelines Hazardous Materials Management Guidelines Applicability These guidelines apply to facilities and activities involving the transportation, production, handling,
More informationSustainability Report
2018 Sustainability Report Pembina Pipeline Corporation 1 2 3 4 6 Table of Contents List of Figures and Tables About this Report Message from our President and CEO Performance at a Glance Our Approach
More informationCalibration Requirements for Direct Reading Confined Space Gas Detectors
: Calibration Requirements for Direct Reading Confined Space Gas Detectors However, the definition of bump test has always been a little slippery. Some manufacturers differentiate between a bump test that
More informationHazardous Materials Management. Presented by. James E. Roughton, MS, CSP, CRSP, CHMM.
Hazardous Materials Management Presented by. James E. Roughton, MS, CSP, CRSP, CHMM. Hazardous Waste Operations And Emergency Response (HAZWOPER) 29 CFR 1910.120 Scope Clean-up Operations At Uncontrolled
More informationHEALTH AND SAFETY MANUAL
HEALTH AND SAFETY MANUAL Title: Hydrogen Sulfide (H 2 S) Safety Approved by: Greg Savoy Rev. 4/1/08 1 Purpose/Scope: The purpose of this program is to establish minimum requirements for site specific H
More informationCCR Certification: Fugitive Dust Control Plan (b) for the. West Ash Pond. at the. F. B. Culley Generating Station.
Submitted to Southern Indiana Gas & Electric Company dba Vectren Power Supply, Inc. (SIGECO) One Vectren Square Evansville, IN 47708 Submitted by AECOM 9400 Amberglen Boulevard Austin, Texas 78729 CCR
More informationCONFINED SPACE WRITTEN PROGRAM
CONFINED SPACE WRITTEN PROGRAM Maple River Public Schools ISD#2135 Confined Space Entry Plan (Permit Required) Maple River Public School Plan last updated: October, 2014 Authority and Scope Regulation:
More informationAccident/Incident Reporting and Investigation Procedures
Accident/Incident Reporting and Investigation Procedures Policy reference Workplace Health and Safety Policy Procedure reference Workplace Health and Safety Risk Assessment Procedures Procedure It is imperative
More informationOPERATING PROCEDURES
OPERATING PROCEDURES 1.0 Purpose This element identifies Petsec s Operating Procedures for its Safety and Environmental Management System (SEMS) Program; it applies to all Petsec operations. Petsec is
More informationHAZARD RECOGNITION EVALUATION and CONTROL
What is a hazard? HAZARD RECOGNITION EVALUATION and CONTROL Hazard - a dangerous object, event, behaviour or condition (in the workplace) which has the potential to cause injury, illness or property damage.
More informationEast Building, PHH-30 U.S. Department New Jersey Avenue S.E. of Transportation Washington, D.C DOT-SP (TWENTY-THIRD REVISION)
East Building, PHH-30 U.S. Department 1200 New Jersey Avenue S.E. of Transportation Washington, D.C. 20590 Pipeline and Hazardous Materials Safety Administration DOT-SP 11054 (TWENTY-THIRD REVISION) EXPIRATION
More information4.3 Objectionable Properties. The gas received and delivered hereunder:
Page 1 of 5 4. QUALITY OF GAS 4.1 Composition of Gas. The gas received by Algonquin for Customer's account, or delivered by Algonquin to Customer, shall be a combustible gas consisting wholly of, or a
More informationFlare Gas Measurement in B.C., Alberta, and Saskatchewan Using GE Ultrasonic Metering Technology
November 2017 Flare Gas Measurement in B.C., Alberta, and Saskatchewan Blaine Barnes Tundra Process Solutions www.tundrasolutions.ca 1 MEASUREMENT REGULATIONS With the creation of Directive PNG017 by the
More information1. UPDATE 12/12/2014: What wells are regulated under the MIA Program? Must they be drilled, stimulated, and completed? Must they be in production?
PLEASE NOTE THAT ALL USES OF THE WORD OPERATOR IN THIS DOCUMENT REFER TO THE ACT 13 DEFINITION OF WELL OPERATOR AND THUS, REFERENCE THE PERMIT HOLDER (PERMITEE) FOR THE WELL. ANY ENFORCEMENT ACTIONS UNDER
More informationGAS SAFETY Information Bulletin
GAS SAFETY Information Bulletin June 2016 G-03-11-ABSA [Rev2] Page 1 of 7 Fuel Gas Pressure Piping in Plants This bulletin has been jointly developed by Safety Services, the Pressure Equipment Sub- Council,
More informationBusiness Plan Presentation
2019 Department of Water Resources Business Plan Presentation Wednesday, August 29, 2018 Mission To Provide Superior Water Services at an Excellent Value Vision To be widely recognized as a leader in the
More informationConfined Space Entry Program 8 CCR 5157
TABLE OF CONTENTS 1. POLICY... 2 2. PURPOSE... 2 3. SCOPE... 2 4. DEFINITIONS... 2 5. CONFINED SPACES IN THE SACRAMENTO STATE... 4 6. PERMIT SPACE ENTRY - PERSONNEL RESPONSIBILITIES... 4 6.1. CONFINED
More informationThe Alberta Energy Regulator (AER) has approved this directive on January 31, Introduction Purpose of This Directive...
Directive 008 Release date: January 31, 2018 Effective date: January 31, 2018 Replaces previous edition issued February 29, 2016 Surface Casing Depth Requirements The Alberta Energy Regulator (AER) has
More informationIssue Date 11/21/13 Revision Date 01/04/18 Benzene
PURPOSE The purpose of this program is to define work practices, administrative procedures and engineering controls to reduce employee exposure to or below the PEL of benzene. This plan shall be implemented
More informationVerification Of Calibration for Direct-Reading Portable Gas Monitors
U. S. Department of Labor Occupational Safety and Health Administration Directorate of Science, Technology and Medicine Office of Science and Technology Assessment Verification Of Calibration for Direct-Reading
More informationIron Ore Company of Canada Health, Safety & Environment
Hazardous Materials 1 PURPOSE The entry of all substances onto site is controlled, Banned substances are not admitted, Potential health effects and hazards are identified and controlled, All products are
More information2.0 Management Systems and Documentation
SHE Rules BOW142.3 1.0 Introduction This document details the safety, health and environment rules that apply to anyone accessing Arqiva sites and describes the standards of performance expected. This
More informationWork Activity (e.g. Road Work): Work Location:.
Working with Cranes Work Activity (e.g. Road Work): Work Location:. GENERAL INFORMATION Hinchinbrook Shire Council Lannercost Street Ingham Qld, 4850 ABN 46 291 971 168 Ph: 47764610 All personnel conducting
More informationPipeline Pigging and Hydrostatic Test
Project Engineering Standard Solutions, Standards and Software www.klmtechgroup.com Page 1 of 20 Rev: 01 KLM #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia. KLM
More informationProcess Safety Management Of Highly Hazardous Chemicals OSHA 29 CFR
Process Safety Management Of Highly Hazardous Chemicals OSHA 29 CFR 1910.119 PSM - Definition Not all refining hazards are caused by the same factors or involve ve the same degree of potential damage.
More informationWell Failure at Todd Energy Canada Ltd. January 2019
Failure Investigation Report Well Failure at Todd Energy Canada Ltd. January 2019 Table of Contents 1 Investigation Procedures...03 2 Incident Summary...03 3 Relevant Information...06 4 Analysis...10 5
More informationHAZARDOUS SUBSTANCES / DANGEROUS GOODS
HAZARDOUS SUBSTANCES / DANGEROUS GOODS Golden Brown is committed to continuously improving the management and standards of Occupational health and Safety. This commitment extends to minimising exposure
More information3. PURPOSE: To establish the minimum safety content of swimming pool Operations Manuals.
GO.. TITLE: OPERATIONS MANUALS 2. DATE ISSUED: July 996 ISSUE: 2 3. PURPOSE: To establish the minimum safety content of swimming pool Operations Manuals. 4. (a) An Operations Manual should be prepared
More informationWorkers Guide to Hand Signals for Directing Vehicles. EDITION» 2.0 REVISED» February 2014 RELEASE DATE» February 2014
Workers Guide to Hand Signals for Directing Vehicles EDITION» 2.0 REVISED» February 2014 RELEASE DATE» February 2014 ENDORSEMENT This document was developed by industry for industry. Enform gratefully
More informationThe Cameroonian regulation on pressure equipment (PE) is based on a set of official laws especially :
INTRODUCTION The Cameroonian regulation on pressure equipment (PE) is based on a set of official laws especially : Act N 98/020 dated 24/12/1998 regulating gas pressure operated equipments (APG) and water
More informationLPG TANK INFORMATION An energy company that puts
LPG TANK INFORMATION An energy company that puts Safety first. LPG TANKS Thanks Thank you for choosing Kleenheat for your LPG supply. We consider safety our number one priority, so please make time to
More information