1 CONCEPT DESIGN COMMUNITY MEETING 3 JANUARY 28, 2010
2 AGENDA INTRODUCTION COMMUNITY INPUT ROADWAY STUDIES STREETSCAPE DESIGN STATIONS DISCUSSION SUMMARY AND DISCUSSION NEXT STEPS CLOSE
3 INTRODUCTION SCHEDULE
4 COMMUNITY INPUT COMMUNITY SURVEY 18 online 198 responses 117 written SUMMARY OF SURVEY KEY ISSUES PEDESTRIAN SAFETY Crossing, lighting VEHICULAR TRAFFIC Excessive speed, cut-through traffic BICYCLE FACILITIES IMAGE / IDENTITY Sense of place, historic character AS LOCAL AND REGIONAL DESTINATION STREETSCAPE Trees, medians, furnishings
5 COMMUNITY MEETING 2
6 COMMUNITY MEETING 2 SUMMARY IMPROVED PEDESTRIAN CROSSINGS 100% KEY INTERSECTIONS: University, Emory, Naglee, Magnolia/Pershing, Hanchett/W Julian, Martin/Race and Morrison PERCENTAGES BASED ON 10 GROUPS 50% yes GATEWAY Historic Way I-880/McKendrie 100% 100% Town Center Undercrossing/Stockton PUBLIC GATHERING SPACE Historic Way Town Center Race Intersection 70% 80% 60% BIKE LANES Historic Way Town Center 70% 80%
7 COMMUNITY MEETING 2 SUMMARY BIKE PARKING Historic Way 50% Town Center 60% PERCENTAGES BASED ON 10 GROUPS PLANTED MEDIAN Historic Way 50% Town Center 30% PARKING STRUCTURE Historic Way Town Center PARKING IMPROVEMENTS Historic Way 0% 70% Town Center 20% 50% LIGHTING- No consensus
8 ROADWAY STUDIES A B C1 C2 PHASE ONE PHASE TWO
9 FIXED DESIGN CRITERIA VEHICULAR ACCESS CRITERIA ELIMINATE LEFT TURNS INTO DRIVEWAYS U-TURNS FOR TRUCKS PROHIBITED TRAFFIC CONTROL LEFT TURN POCKETS REQUIRED NO NEW SIGNALS FOUR TRAVEL LANES TWO TRAVEL LANES POSSIBLE FUTURE OPTION TRANSIT INCORPORATE BRT STATIONS
10 FIXED DESIGN CRITERIA TREES PRESERVE EXISTING TREES PARKING CRITERIA MINIMIZE ON-STREET PARKING LOSS ESPECIALLY IN TOWN CENTER BALANCE LOSS AMONG BLOCKS BIKE LANE CRITERIA 5 MINIMUM STANDARD
11 ADDITIONAL PREFERRED DESIGN CRITERIA VEHICULAR ACCESS CRITERIA LEFT AND U-TURN MAXIMUM SPACING 1-3 BLOCKS PEDESTRIAN ACCESS CRITERIA CORNER BULBS-OUTS INCREASE NUMBER OF CROSSINGS TREES MAINTAIN OUTSIDE EXISTING CURB ALIGNMENT
12 ADDITIONAL PREFERRED DESIGN CRITERIA PEDESTRIAN ACCESS and SAFETY CRITERIA MAXIMIZE PEDESTRIAN MEDIAN REFUGE MIN. 6 WIDE LADDER CROSSINGS WHERE POSSIBLE PEDESTRIAN ACTIVATED CROSSING SIGNALS WHERE POSSIBLE PROTECTED INTERSECTIONS THROUGHOUT CORRIDOR MAXIMIZE CORNER BULBOUTS (22% CROSSING DISTANCE REDUCTION) BIKE LANE CRITERIA 8 WIDTH ENHANCE WITH COLOR POSSIBLE FUTURE OPTION
13 EXISTING STREET SECTION VERSUS DESIRED STREET ELEMENTS CURB TO CURB WIDTH TOO NARROW ALL DESIRED ELEMENTS WOULD REMOVE TREES
14 A PEDESTRIAN REFUGE / MEDIAN, MAXIMUM POSSIBLE INTERSECTION LEFT TURNS
15 B BIKE LANES WITH PEDESTRIAN REFUGES AND OCCASIONAL LEFT TURNS AT INTERSECTIONS, LIMITED MEDIAN
16 C1 MAXIMUM PEDESTRIAN REFUGE / MEDIAN WITH RESTRICTED INTERSECTION LEFT TURNS
17 C2 PHASE TWO TWO TRAVEL LANES WITH BIKE LANES, MAXIMUM PEDESTRIAN REFUGE AND MEDIAN WITH RESTRICTED INTERSECTION LEFT TURNS
18 C2 PHASE TWO PROCESS ENVIRONMENTAL IMPACT REPORT TRAFFIC IMPACT ANALYSIS REPORT AND ANALYSIS WILL STUDY: TRAFFIC IMPACTS AT INTERSECTIONS REDISTRIBUTION OF EXISTING TRAFFIC POSSIBLE NEIGHBORHOOD CUT-THROUGH ACCESS IMPROVEMENTS AT OTHER ROADWAYS TO ACCOMMODATE ADDITIONAL TRAFFIC POSSIBLE PHASING FUNDING FOR EIR CITY WILL ASSIST NEIGHBORHOODS TO IDENTIFY FUNDING
19 PEDESTRIAN IMPROVEMENT LOCATIONS C1&C2
20 NEIGHBORHOOD ACCESS CONCEPT C1&C2
21 CHARACTERISTICS MATRIX CHARACTERISTICS A B C1 C2 PEDESTRIAN IMPROVEMENTS (more crossings and more bulb outs) BICYCLE LANES IMAGE / IDENTITY SIDEWALK ENHANCEMENTS (Bulb outs) PARKING QUANTITY LEGEND GOOD FAIR POOR *CHARACTERISTICS EVALUATED FOR TOWN CENTER ENLARGEMENT AREA ONLY
22 PARKING ANALYSIS TOWN CENTER CONCEPT C1 and C2 ITEM EXISTING TOTALS ON-STREET SPACES * 431 OFF-STREET SPACES * 471 TOTAL PARKING * 902 PARKING LOSS DUE TO BRT 13 PARKING LOSS DUE TO PEDESTRIAN IMPROVEMENTS 8 TOTAL PARKING LOSS 21 TOTAL PARKING 881 % REDUCTION FROM TOTAL PARKING SUPPLY 2.3% % REDUCTION DUE TO PEDESTRIAN IMPROVEMENTS >1% OCCUPANCY RATE MID WEEK * 67% *Fehr & Peers Parking Study September 2008
23 PARKING ANALYSIS HISTORIC WAY CONCEPT C1 and C2 ITEM EXISTING TOTALS ON-STREET PARKING ON ONLY 174 PARKING LOSS DUE TO BRT 5 PARKING LOSS DUE TO PEDESTRIAN IMPROVEMENTS 15 TOTAL PARKING LOSS 20 TOTAL PARKING 154 % REDUCTION FROM EXISTING PARKING SUPPLY 11.4% % REDUCTION DUE TO PEDESTRIAN IMPROVEMENTS 8.6%
24 STREETSCAPE DESIGN
25 STREETSCAPE CONCEPT ALAMEDA GATEWAY HISTORIC WAY NEIGHBORHOOD GATEWAY (TYP) TOWN CENTER RACE INTERSECTION ALAMEDA GATEWAY
26 LIGHTING CONCEPT ALAMEDA GATEWAY HISTORIC WAY NEIGHBORHOOD GATEWAY (TYP) TOWN CENTER RACE INTERSECTION ALAMEDA GATEWAY
27 STREETSCAPE LIGHTING
28 STREETSCAPE ACCENT LIGHTING
29 STREETSCAPE TREES AND MEDIAN HISTORIC WAY EXISTING MEDIAN WITH SHRUB PLANTING
30 STREETSCAPE TREES AND MEDIAN HISTORIC WAY MEDIAN WITH FLOWERING TREES AND SHRUB PLANTING MEDIAN WITH SYCAMORES AND SHRUB PLANTING
31 STREETSCAPE TREES AND MEDIAN - TOWN CENTER EXISTING MEDIAN WITH SHRUB PLANTING
32 STREETSCAPE TREES AND MEDIAN - TOWN CENTER MEDIAN WITH FLOWERING TREES AND SHRUB PLANTING MEDIAN WITH SYCAMORES AND SHRUB PLANTING
33 STREETSCAPE GROUNDPLANE PLANTING AND STORMWATER MANAGEMENT
34 STREETSCAPE DESIGN MEDIAN ELEMENTS, IMAGE AND IDENTITY
35 STREETSCAPE DESIGN GATEWAYS
36 STREETSCAPE DESIGN INTERPRETIVE SIGNAGE
37 ILLUSTRATIVE ENLARGEMENT PLANS HISTORIC WAY STREETSCAPE ENHANCEMENTS
38 ILLUSTRATIVE ENLARGEMENT PLANS TOWN CENTER STREETSCAPE ENHANCEMENTS PLANTED MEDIAN
39 STREETSCAPE DESIGN PEDESTRIAN IMPROVEMENTS
40 RACE STREET INTERSECTION PLANS ROUNDABOUT STUDY
41 RACE STREET INTERSECTION PLANS MARTIN AVENUE PARTIAL CLOSURE ICONIC ARCHITECTURE, FOCAL POINTS DEFINE SENSE OF PLACE RIGHT-OF-WAY (TYP) PUBLIC GATHERING SPACE OPPORTUNITY PARKING LOT & NEIGHBORHOOD ACCESS
42 RACE STREET INTERSECTION PLANS MARTIN AVENUE FULL CLOSURE ICONIC ARCHITECTURE, FOCAL POINTS DEFINE SENSE OF PLACE RIGHT-OF-WAY (TYP) PUBLIC GATHERING SPACE OPPORTUNITY EMERGENCY VEHICLE ACCESS
43 STREETSCAPE DESIGN PUBLIC GATHERING SPACES
44 STREETSCAPE DESIGN PUBLIC GATHERING SPACES
45 STATIONS VEHICULAR CIRCULATION STREETSCAPE DESIGN URBAN DESIGN
46 SUMMARY & DISCUSSION
47 NEXT STEPS FINALIZE PLAN NEXT COMMUNITY MEETING END OF MARCH / BEGINNING OF APRIL APEX STRATEGIES
A Plan for The Beautiful Way NOVEMBER 16, 2009
COMMUNITY VISION WORKSHOP NOVEMBER 16, 2009 AGENDA INTRODUCTION COMMUNITY INPUT REVIEW AND SURVEY RESULTS VISIONING IMAGERY SMALL GROUP VISIONING SESSION NEXT STEPS CLOSE SCHEDULE COMMUNITY SURVEY 198
More informationBroad Street Bicycle Boulevard Design Guidelines
Broad Street Bicycle Boulevard Design Guidelines Building from the strategies introduced in the 2013 Bicycle Transportation Plan and community input received thus far, City Transportation Staff have identified
More informationMARTIN LUTHER KING JR. WAY
OCTOBER 2011 40 Vision and Goals The Martin Luther King, Jr. Way Illustrative Master Plan that follows has been developed through a process of community involvement. It expresses a long term vision for
More informationTonight is for you. Learn everything you can. Share all your ideas.
Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.
More informationVision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods
N D. Focus Area II Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods Transit Road Focus Area II is located in the Hamlet
More informationOcean Park Boulevard Green Street Project Alternatives & Trade Offs
Planning Commission March 4, 2009 Ocean Park Boulevard Green Street Project Alternatives & Trade Offs Purpose of Tonight s Meeting Review concept plans and options Provide input on alternatives and trade-offs
More informationEl Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018
El Camino Real Specific Plan TAC/CAC Meeting #2 Aug 1, 2018 Land Use Alternatives Goals and Tradeoffs Parks & open space Housing Retail & services Civic spaces Parking Community gathering spaces 3 Alternatives
More informationMiami Health District
Miami Health District Streetscapes, Gateways, and Signage Basis of Design Report Study Miami Partnership Meeting July 21, 2008 Gannett Fleming EDAW The Corradino Group Sponsored by the Miami Partnership:
More informationSTONY PLAIN ROAD STREETSCAPE
Jasper Place Revitalization Strategy: Vision The people involved in the Jasper Place Revitalization Strategy envision: Goal 1: Feeling safe in our community Create a community where feeling safe is common--where
More informationCommunity Task Force November 15, 2017
Community Task Force November 15, 2017 Welcome and Introductions Project Partners Regional Transportation District (RTD) Colorado Department of Transportation (CDOT) Denver Regional Council of Governments
More informationCommunity Meeting February 27, 2007 Dorchester Avenue Transportation & Streetscape Improvements Action Plan February 27, 2007
Community Meeting Tonight s Agenda 6:00 Introductions South Boston/Dot Ave Improvement Study Background 6:15 Consultant Introductions Review of Scope and Schedule Review of Proposed Corridor Wide Guidelines
More informationCOWETA HIGH SCHOOL AND EAST HIGHWAY 51
COWETA HIGH SCHOOL AND EAST HIGHWAY 51 Lack of sidewalks along Ben Lumpkin Rd. Lack of crosswalks and ramps at intersection. Hwy 51 is wide to cross as a pedestrian. No ADA compliance or connection to
More informationTRANSPORTATION STANDARDS
INTRODUCTION LOCAL STREETS ON-STREET PARKING SIDEWALKS STREET LIGHTING STREET FURNISHINGS TRAFFIC CALMING STREET TREES MEDIAN PLANTING BOULEVARD LOCATIONS VILLAGE CENTER STREET LOCATIONS RESIDENTIAL STREET
More information6.4 RECOMMENDED IMPROVEMENTS
6.4 RECOMMENDED IMPROVEMENTS 6.4.1 Williston Road Recommendations While all alternatives would be an improvement over existing conditions, Alternative 3B is recommended over the others because it provides
More informationOcean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs
City Council Study Session January 27, 2009 Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs Scope of Work Purpose of Tonight s Meeting Review work to date and direct staff
More informationMission-Geneva Transportation Study Community Workshop 2 July 8, 2006
Community Workshop 2 July 8, 2006 Small Group Workbook 1 Basic Improvements on Mission Street Streetscape. Pedestrian-scale lighting; landscaping; community art on utility boxes; more (possibly unique)
More informationDowntown Naples Mobility and Connectivity Study. Naples City Council Presentation January 2017
Downtown Naples Mobility and Connectivity Study Naples City Council Presentation January 2017 Agenda 1. Introduction 2. Scope Review 3. Project Schedule 4. Existing Conditions 5. Public Charrette 6. Mobility
More informationOmaha s Complete Streets Policy
Omaha s Complete Streets Policy (Adopted August 2015) VISION To create great places and enhance our quality of life, the City of Omaha will provide safe, accessible streets for all users. Complete Streets
More information122 Avenue: 107 Street to Fort Road
: 107 Street to Fort Road November 24, 2015 4:30 8:00 p.m. Meeting Purpose Summarize project work completed to date Share results of public input from Phase 1 Share the draft concept plan and proposed
More informationSTREETSCAPE CONCEPTS
STREETSCAPE S CARGO WAY CARGO WAY CYCLE TRACK Streetscape Concepts JENNINGS ST Illustrative Plan EVANS AVE PG&E BAY TRAIL HERON S HEAD PARK The recommended improvements build off the planned improvements
More informationLawrence Avenue Streetscape Concepts August 30, 2011
Lawrence Avenue Streetscape Concepts August 30, 2011 Neighborhood Context Phase II: River to Western Ave. Phase I: Western Ave. to Clark St. Key Map Lawrence Ave. Existing Streetscape Conditions East of
More informationPRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN
PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations
More information12/4/2016 VIA . RE: Grocery Outlet Del Paso (DR16-328)
12/4/2016 VIA EMAIL Ethan Meltzer, Assistant Planner City of Sacramento Community Development Department 300 Richards Blvd, 3 rd Floor Sacramento, CA 95811 RE: Grocery Outlet Del Paso (DR16-328) Dear Mr.
More informationTechnical Working Group November 15, 2017
Technical Working Group November 15, 2017 Welcome and Introductions Project Partners Regional Transportation District (RTD) Colorado Department of Transportation (CDOT) Denver Regional Council of Governments
More informationMINERAL AVENUE CORRIDOR ASSESSMENT STUDY IMPLEMENTATION STRATEGY
MINERAL AVENUE CORRIDOR ASSESSMENT STUDY IMPLEMENTATION STRATEGY INTRODUCTION City Personnel Sign-in Sheet Comment Forms Please Write Down Any Feedback INTRODUCTION List of Topics for Presentation Study
More informationCOMPLETE STREETS PLANNER S PORTFOLIO
COMPLETE STREETS PLANNER S PORTFOLIO ISSUE 3 APRIL 2016 PLANNER S PORTFOLIO COMPLETE STREETS 1 2 6 10 14 OVERVIEW MATURE NEIGHBORHOODS GROWING SUBURBS CENTRAL PLACES ACTIVITY CORRIDORS Planner s Portfolio
More informationSouthview Blvd & 3 rd Avenue Improvement Project. Public Open House December 4, to 7pm
Southview Blvd & 3 rd Avenue Improvement Project Public Open House December 4, 2014 5 to 7pm Southview Blvd & 3 rd Avenue Public Information Meeting Agenda Presentation 5:30 to 6:15 pm Purpose of Project
More informationItem to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines
Passaic County Complete Streets Checklist - Concept Development Project Name Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines Existing Plans Have
More informationChapter 3 BUS IMPROVEMENT CONCEPTS
Chapter 3 BUS IMPROVEMENT CONCEPTS The purpose of this chapter is to describe potential bus improvement strategies and potential impacts or implications associated with BRT implementation within the existing
More informationFONTAINE AVENUE STUDY Final Report
FONTAINE AVENUE STUDY Final Report March 28, 2005 FONTAINE AVENUE STUDY City of Charlottesville March 28, 2005 Renaissance Planning Group Kenneth Schwartz, FAIA, AICP Director of Design Leigh Wilkerson,
More informationAppendix C. TRAFFIC CALMING PROGRAM TOOLBOX
Appendix C. TRAFFIC CALMING PROGRAM TOOLBOX PHASE I...2 Do Not Enter Sign...3 One-Way Sign...4 Turn Prohibition...5 Pavement Markings...6 Speed Monitoring Trailer...7 Neighborhood Speed Watch...8 Police
More informationMeade Street Bridge Design Alternative Study
Meade Street Bridge Design Alternative Study Preferred Alternative Presentation Stakeholder Meeting #3 June 23, 2011 Presented by: Dan Biggs, RLA Meeting Agenda Purpose: 1. Review Meeting #2 Feedback 2.
More informationReport. Typical Sections. City of Middleton, WI
Report Typical Sections City of Middleton, WI December 2006 Report for City of Middleton, Wisconsin Typical Sections repared by: Traffic Associates LLC and STRAND ASSOCIATES, INC. 910 West Wingra Drive
More informationPUBLIC REALM MASTER PLAN
WESTSHORE BUSINESS DISTRICT PUBLIC REALM MASTER PLAN MASTER PLAN COMMITTEE MEETING MARCH 20, 2013 WESTSHORE BUSINESS DISTRCT PUBLIC REALM MASTER PLAN MACRO-SCALE CONCEPT: A PUBLIC REALM FRAMEWORK DEFINED
More informationChapter 3: Multi-Modal Circulation and Streetscapes
CHAPTER 3: MULTI-MODAL CIRCULATION AND STREETSCAPES Chapter 3: Multi-Modal Circulation and Streetscapes Overview Streetscape improvements have already been completed for Depot Street between Main Avenue
More informationA Guide to Great Streets: The Basics. September 25, 2009
A Guide to Great Streets: The Basics September 25, 2009 Streets are more than connectors, they are the city 2 Streets are the glue that hold a city together 3 Streets are the means in which a city is perceived
More informationCOMMUNITY MEETING AGENDA
COMMUNITY MEETING AGENDA Welcome and Introductions SAFE Presentation Project Presentation Priorities Feedback Next Steps Q&A Santa Cruz Avenue Corridor Study 1 Santa Cruz Avenue Corridor Study Community
More informationCommunity Task Force March 14, 2018
Community Task Force March 14, 2018 Welcome and Introductions Project Partners Regional Transportation District (RTD) City of Aurora Colorado Department of Transportation (CDOT) Denver Regional Council
More informationAtwood Avenue Fair Oaks Avenue Cottage Grove Road
Atwood Avenue Fair Oaks Avenue Cottage Grove Road Agenda Purpose Review project scope & goals Present design alternatives Gather feedback Answer Questions Format Open House Presentation Q&A Open House
More informationSaskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening
Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening We are here today to present the draft plan for the Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening project
More information5 CIRCULATION AND STREET DESIGN
5 CIRCULATION AND STREET DESIGN This chapter describes circulation and streetscape improvements proposed for the Northwest Chico Specific Plan Area. It includes detailed design specifications for existing
More informationBicycle and Pedestrian Advisory Committee (BPAC) November 21, 2013
Bicycle and Pedestrian Advisory Committee (BPAC) November 21, 2013 OVERALL LAND USE CONCEPT Overall Broadway Valdez District: 95.5 acres (35.1 acres right-of ways + 60.4 acres developable land) Plan Subareas:
More informationPublic Information Centre
WELCOME Public Information Centre Father Tobin Road Lougheed Middle School - Library Wednesday November 7, 2012 7:00 p.m.to 9:00 p.m. Please sign in Neighbourhood Traffic Calming Guide Background The City
More informationNeighborhood Pedestrian Safety and Traffic Calming Study
Neighborhood Pedestrian Safety and Traffic Calming Study for the area bounded by Foster Avenue, Bedford Avenue, Farragut Road and Ocean Avenue Flatbush, Brooklyn, New York prepared by Michael King, miking@trafficcalmer.com
More informationColumbia Pike Implementation Team (CPIT) Meeting
Columbia Pike Implementation Team (CPIT) Meeting November 30, 2010 Agenda Introductions / Purpose of Meeting Review of project goals Multimodal project: 10% street design between the curbs Discussion Multimodal
More informationOcean Park Boulevard Green Street Project Community Workshop
Ocean Park Boulevard Green Street Project Community Workshop 2.2.10 Project Objectives Community Priority: reclaim OPB for public open space. Build upon LUCE principles; neighborhood enhancement, connectivity,
More informationCONTEXT SENSITIVE STREETS STANDARDS COMMITTEE
CONTEXT SENSITIVE STREETS STANDARDS COMMITTEE February 23, 2015 Prepared by: Denise Chaplick, AICP City Jacksonville Bicycle and Pedestrian Coordinator Source: NCDOT Complete Streets Planning and Design
More informationObservations and Ideas: Toomer s Corner Streetscape Improvements
Observations and Ideas: Toomer s Corner Streetscape Improvements AUBURN DOWNTOWN MASTER PLAN planning downtown s future August 26, 2013 Observations: Vertical Clutter at Corners 6 3 7 5 9 2 8 4 1 Excess
More informationCURBSIDE ACTIVITY DESIGN
5 CURBSIDE ACTIVITY DESIGN This chapter provides design guidance for separated bike lanes adjacent to curbside activities including parking, loading and bus stops. Typical configurations are presented
More informationLos Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation
Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto
More informationChapter 4 TOOLBOX AND SAMPLE BIKE BOULEVARD LAYOUT
Chapter 4 TOOLBOX AND SAMPLE BIKE BOULEVARD LAYOUT OVERVIEW This chapter describes a cohesive set of strategies to create a bicycle boulevard, namely to make streets safer and more efficient for bicycle
More informationCLOSED. Highlights of the Final Concept Design:
The final Concept Design is the result of many months of listening, learning, creating, balancing, and understanding different needs and viewpoints, as well as incorporating technical requirements and
More informationCitizen Advisory Group Meeting #8 May 5, Welcome. Today s meeting will focus on: Land Use & Transportation CHARLOTTEPLANNING.
Citizen Advisory Group Meeting #8 May 5, 2010 Welcome. Today s meeting will focus on: Land Use & Transportation CHARLOTTEPLANNING.ORG Meeting Agenda Handouts: o Meeting Agenda o Summary of East Seventh
More informationDesign Public Hearing MassDOT Project # February 19, 2015 Chatham Town Hall Annex 7:00 P.M.
Design Public Hearing MassDOT Project #606596 February 19, 2015 Chatham Town Hall Annex 7:00 P.M. Overview Process to date Project goals Data collection results Existing conditions Alternative analysis
More informationMake Lincoln Highway an economically vibrant corridor that is safe, efficient, and beautiful for local residents and visitors.
Lincoln Highway Streetscape Plan Stakeholder Workshop #2 Handout Contents Introduction and Project Vision Planning Principles Specific Recommendations including a Proposed Typical Roadway Section Renderings
More informationFOLSOM-HOWARD STREETSCAPE OVERVIEW
FOLSOM-HOWARD STREETSCAPE OVERVIEW SoMa residents should have the same kinds of amenities that other neighborhoods have. The Folsom- Howard Streetscape Project will make SoMa more livable by making it
More informationMASONIC AVENUE STREET DESIGN STUDY Community Workshop 2. Masonic Ave Street Design Study Community Workshop 2 August 10, 2010
Masonic Ave Street Design Study Community Workshop 2 August 10, 2010 Introduction MASONIC AVENUE STREET DESIGN STUDY Community Workshop 2 SF Municipal Transportation Agency Javad Mirabdal, Project Manager
More informationAnn Arbor Downtown Street Plan
1 Ann Arbor Downtown Street Plan Public Workshop #1 We know that. 2 Public right-of-way (streets, sidewalks, and alleys) make up 30% of the total District area of downtown. Streets need to provide mobility
More informationDesigning Complete Streets: What you need to know
Designing Complete Streets: What you need to know Getting from this to this. Continuous sidewalk Buffer w/trees Bicycle lane Raised median Buildings close to the street Flexibility in design Design and
More informationTOWN OF MORAGA MORAGA WAY AND CAMINO PABLO/CANYON ROAD IMPROVEMENTS Town Council Meeting March 13, 2019
TOWN OF MORAGA MORAGA WAY AND CAMINO PABLO/CANYON ROAD IMPROVEMENTS Town Council Meeting March 13, 2019 1 Edric Kwan, Public Works Director Josh Peterman, Principal, Fehr and Peers Shawn Knapp, Senior
More informationBrooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017
Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn
More informationSouthbend to Prima Vista. October 30, Floresta Corridor Master Plan
Application of a Complete Street initiative and how it might function operationally 8 8 Southbend to Prima Vista October 30, 2017 Presentation Agenda 2 Perspective and History Traffic projections, Levels
More informationTelegraph Avenue Complete Streets DRAFT Recommendations. Oakland Public Works Department September 11 and 13, 2014 Open Houses
Telegraph Avenue Complete Streets DRAFT Recommendations Oakland Public Works Department September 11 and 13, 2014 Open Houses Presentation Overview What are complete streets? What problem are we trying
More informationCommunity Workshop #1 Summary October 2017
Community Workshop #1 Summary October 2017 1 Background Pleasure Point has a unique character and strong community identity. In 2008, the community and the County developed the Pleasure Point Community
More informationWELCOME Public Information Centre
WELCOME Public Information Centre Fernforest Drive Brampton Soccer Centre Community Room #2 Tuesday January 19, 2016 6:30 p.m.to 9:00 p.m. Please sign in Neighbourhood Traffic Calming Guide Background
More informationUS 278 Corridor Concept Presentation. Avondale Estates Intersection Improvement/Roundabout and Road Diet Feasibility Study March 19, 2015
US 278 Corridor Concept Presentation Avondale Estates Intersection Improvement/Roundabout and Road Diet Feasibility Study March 19, 2015 Thanks to our Partners Atlanta Regional Commission Georgia Department
More informationOrg Chart. Steering. Committee. Project Advisory. Committee. Nicole Losch, PTP Senior Transportation. Bryan Davis, AICP Senior Transportation
1 Org Chart Project Advisory Committee Steering Committee Nicole Losch, PTP Senior Transportation Planner Bryan Davis, AICP Senior Transportation Planner Jonathan Slason, PE Project Manager Diane Meyerhoff
More informationTransportation Planning Division
Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meetings Data Collected Focus Areas within Study Limits Design Principles Tool Box Recommended Concepts Schedule Moving
More informationA CHANGING CITY. of Edmonton, it is essential that it reflects the long-term vision of the City.
A CHANGING CITY By the year 2040, Edmonton will be home to more than 1 million people. To accommodate growth and support a healthy and compact city, we need a new approach to development/redevelopment
More informationItem Description: Presentation and Discussion: Berkeley Rapid Transit Locally Preferred Alternative
Office of the City Manager Meeting Date: April 29, 2010 Item Number: 1 Item Description: Presentation and Discussion: Berkeley Rapid Transit Locally Preferred Alternative Staff report, resolution, and
More informationMajor Bike Routes 102 Avenue Workshop April 21, 2015
Major Bike Routes 102 Avenue Workshop April 21, 2015 Our Purpose Today Provide context on how Major Bike Routes fit into Edmonton s future Share information on what we heard in our last phase, and how
More informationAPPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016
APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of
More informationEast Burke Transportation, Safety and Capacity Improvements
East Burke Transportation, Safety and Capacity Improvements The purpose of this project is to increase mobility and improve safety for pedestrians, cyclists, and motor vehicles along VT Route 114 in the
More informationCity of Wilsonville 5 th Street to Kinsman Road Extension Project
City of Wilsonville 5 th Street to Kinsman Road Walking Tour & Neighborhood Workshop Summary Report Public Outreach Overview On July 18 th, 2017, the City of Wilsonville hosted a neighborhood walking tour
More informationCity of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE
Welcome Welcome to the third community meeting for the Issaquah-Fall City Road Improvements Project. AGENDA 6:00 p.m. Welcome and sign-in 6:10 p.m. Presentation 6:50 p.m. Open house Learn about the roadway
More informationCity of Elizabeth City Neighborhood Traffic Calming Policy and Guidelines
City of Elizabeth City Neighborhood Traffic Calming Policy and Guidelines I. Purpose: The City of Elizabeth City is committed to ensure the overall safety and livability of residential neighborhoods. One
More informationByron Avenue. Public Meeting. Thursday June 16, Traffic Calming Design Sherbourne Road to Island Park Drive
Byron Avenue Traffic Calming Design Sherbourne Road to Island Park Drive Public Meeting Thursday June 16, 2016 Our Lady of Fatima Parish 153 Woodroffe Avenue 6 9pm 1 Project Summary Area Projects Background
More informationVictoria Park Master Plan
Victoria Park Master Plan Phase I Presented By: ARCHITECTURAL ALLIANCE & HUGHES HUGHES INC. History of Victoria Park Phase I Purpose Inventory of Existing Conditions Identification of Options by Type (for
More informationTRANSPORTATION & MOBILITY VISIONING MEETING. August 23 24, 2017
TRANSPORTATION & MOBILITY VISIONING MEETING August 23 24, 2017 Project Team 1999 South Lakefront Framework Plan In 1999, the Chicago Park District authorized framework plans for three historic parks: Jackson,
More information2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE
About the Project The City of Edmonton is planning a major bike route on the southside of Edmonton. The Strathcona Bike Route will connect the communities of Strathcona, Garneau and the University area,
More informationOCALA/MARION TPO CITY OF BELLEVIEW CORRIDOR PLAN STUDY PRESENTATION TO THE BELLEVIEW CITY COMMISSION JANUARY 25, :00 PM
OCALA/MARION TPO CITY OF BELLEVIEW CORRIDOR PLAN STUDY PRESENTATION TO THE BELLEVIEW CITY COMMISSION JANUARY 25, 2016 6:00 PM STUDY AREA Ocala/Marion TPO US-441 Corridor Study 2 Ocala/Marion TPO US-441
More informationPrinceton Avenue and Spruce Street Transportation and Site Access Enhancements Project
Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Mercer County Planning Division AECOM Transportation (formerly DMJM Harris) January 29, 2009 Agenda Project Status
More informationSafe Streets. City of Lake Forest Park. March 21, 2017
Safe Streets City of Lake Forest Park March 21, 2017 1 01 WELCOME 2 Agenda WELCOME WHAT IS THIS PROJECT? CONTEXT DRAFT CITYWIDE PROJECTS EXERCISE INTRODUCTION 3 02 WHAT IS THIS PROJECT? 4 WHAT IS THIS
More informationChapter 2: Standards for Access, Non-Motorized, and Transit
Standards for Access, Non-Motorized, and Transit Chapter 2: Standards for Access, Non-Motorized, and Transit The Washtenaw County Access Management Plan was developed based on the analysis of existing
More informationCITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY
RMA-2015-ATM-038 CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY DATE: April 22, 2015 SUBJECT Approval of Roadway Modifications Recommended through an Area Traffic Management Study
More informationNEWMARKET UPHAM S CORNER
SOUTH STATION Planning Initiative NEWMARKET UPHAM S CORNER COLUMBIA ROAD (P) FOUR CORNERS/GENEVA Working Advisory Group (WAG) Meeting #5 TALBOT AVENUE MORTON STREET BLUE HILL AVE/CUMMINS HWY (P) RIVER
More informationAbout the study. North Milwaukee Ave. Key goals of this study are to: Achieve Vision Zero* by. Harmonize the space and improve walkability
About the study Key goals of this study are to: North Milwaukee Avenue is a local and regional street for multiple modes of transportation. It is officially zoned and functions as a pedestrian street southeast
More informationPresentation Outline. Project/Study Purpose. Existing Conditions. Future Conditions. Understanding the Streetside. Similar Walkable Environments
Presentation Outline Project/Study Purpose Study Area Map Existing Conditions Future Conditions Understanding the Streetside Similar Walkable Environments Conceptual Alternatives Magnolia/NE 1st Ave Block
More informationAgenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN
PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations
More informationThe DC Pedestrian Master Plan
The DC Pedestrian Master Plan September 28, 2010 George Branyan Pedestrian Program Coordinator District Department of Transportation Presentation Agenda Scope of the Plan Methodology Recommendations Implementation
More informationCity of Vestavia Hills Traffic Calming Policy for Residential Streets
City of Vestavia Hills Traffic Calming Policy for Residential Streets PURPOSE: The purpose of the Traffic Calming Policy for Residential Streets is to address safety concerns related to vehicular traffic
More informationDRAFT. A fifth objective, other considerations, has been added to capture considerations not captured by the four primary objectives.
TECHNICAL MEMORANDUM Albany - Washington Avenue Traffic Calming Evaluation Matrix of Conceptual Alternatives Date: May 17, 2017 Project #: 17356 To: Aleida Andrino-Chavez From: Laurence Lewis, Sara Muse,
More information14 TH STREET TRANSPORTATION & STREETSCAPE DESIGN STUDY PLAN B PLAN B TRANSPORTATION & STREETSCAPE RECOMMENDATIONS
14 TH STREET TRANSPORTATION & STREETSCAPE DESIGN STUDY PLAN B PLAN B TRANSPORTATION & STREETSCAPE RECOMMENDATIONS 141 Symbols Recommendations - Southern End of 14th Street Study Area Streetscape Each icon
More informationTown of Ashland. Downtown Planning Initiative 2 nd Community Workshop. March 29, Presented by:
Town of Ashland Downtown Planning Initiative 2 nd Community Workshop Presented by: March 29, 2018 Agenda Tonight Review project & goals Recap 1st workshop (September 18, 2017) Present design alternatives
More information5. RUNNINGWAY GUIDELINES
5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved
More informationUNIVERSITY AVENUE CORRIDOR REDESIGN. January 8, 2017 PUBLIC OPEN HOUSE
January 8, 2017 PUBLIC OPEN HOUSE COLLABORATIVE COMMUNITY-BASED DESIGN IS THE FOUNDATION TO A SUCCESSFUL PROJECT AGENDA FOR TONIGHT 1 INTRODUCTIONS 2 WHY ARE WE HERE PROJECT NEED 3 SCHEDULE & GOALS 4 OPEN
More informationBroadway Complete Streets Project
Broadway Complete Streets Project Megan Johnson, P.E. Associate Civil Engineer James Pangburn, P.E. Consultant Project Manager After the construction of the highway system, Broadway was cut off
More informationLong Island Rail Road Expansion Project Floral Park to Hicksville
Long Island Rail Road Expansion Project Floral Park to Hicksville Final Environmental Impact Statement Appendix 1-D Complete Streets Policy Checklist April 2017 0902ML PIN: Project Location: 18A-4 Floral
More informationLee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses
Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses Introduction At the Lee s Summit Road Improvement Study Public Open House held Thursday, June 7, 2007
More informationBROOKLAND Multi-Modal Transportation & Streetscape Study* NE Washington, DC
BROOKLAND Multi-Modal Transportation & Streetscape Study* NE Washington, DC The study s goal is to create a multi-modal transportation and streetscape design plan to increase transportation efficiency,
More information