Project Update #2. Cedar Springs Road Minor Reconstruction and Culvert Replacement (Britannia Road to Kilbride St)
|
|
- Simon McDowell
- 5 years ago
- Views:
Transcription
1 Project Update #2 Cedar Springs Road Minor Reconstruction and Culvert Replacement (Britannia Road to Kilbride St) Contract No. CW File The City of Burlington has awarded the above-mentioned project to Fermar Paving Limited. The construction includes: Cedar Springs Road Removal and replacement of existing asphalt roadway, with some minor reconstruction work in select areas. Installation of new guiderails. Removal of existing 1000mm diameter culvert structure and installation of new 1600mm diameter culvert structure. Widening of the existing roadway with 1.5m paved shoulders on both sides of Cedar Springs Road. Contacts Inquiry/Concern Contact Title Contact Number Day to Day Dave Hill Inspector City of construction inquiries Burlington All other construction questions Janine Yaromich Project Manager - City of Burlington x7421 All other construction questions Rob Stuart Contract Administration - City of Burlington x7519
2 Construction Schedule & Staging
3 Construction activity will commence the week of June 11, 2018 and proceed as detailed below. Please note that this construction schedule is tentative and subject to change. Stage Construction Tentative Timing 1 Installation of project signs Installation of tree protection and sediment erosion control measures Tree removals June 11 th to July 3 rd, 2018 ROAD FULLY OPEN mm culvert removal 1600mm culvert installation Guiderail replacements Removal of asphalt roadway Road widening excavations Road crossing culvert replacements July 3 rd to Aug. 31 st, 2018 ROAD FULLY CLOSED 3 Installation of new roadway asphalt Tree planting Site restoration Aug. 31 st to Oct. 1 st, 2018 ROAD FULLY OPEN Road Closures Stage 1 Cedar Springs Road - June 11 th to July 3 rd, 2018 Lane Restrictions: Localized lane restrictions, one lane of traffic will be maintained at all times, expect some minor delays during the day time. The road will be FULLY OPENED. Stage 2 Cedar Springs Road - July 3 rd to August 31 st, 2018 Lane Restrictions: Traffic will be restricted to local access only. Cedar Springs Road will have one lane of traffic maintained at all times outside of the road closure area south of Grand Blvd. Expect delays from construction activities. Road will be FULLY CLOSED at 6097 Cedar Springs road south of Grand Blvd.
4 Stage 3 Cedar Springs Road August 31 st to Oct. 1, 2018 Lane Restrictions: Cedar Springs Road will have one lane of traffic maintained at all times. Expect delays from asphalt paving activities. The road will be FULLY OPENED. Work to be done on Grand Blvd entrance As part of this project, Cedar Springs Road at the Grand Blvd entranceway is being reconstructed. This work is scheduled to commence after September 4 th, While the excavation is on going, the road will be in a gravel state and one lane of traffic will remain open at all times.
5 Access to Your Property Please note that during normal construction hours (Monday to Friday, 7:00 a.m. to 7:00 p.m.) vehicle access to and from your property may at times be difficult. In addition, driveways will be temporarily closed when work is being carried out in the immediate area. Commercial driveways will be staged to maintain access. You will be notified in advance, by either the Inspector or the Contractor of any access closures. Road Works It is expected that the roadways will be in a gravel state for an extended period of time at which point, the contractor will suppress any dust and/or nuisance caused by the granular with a dust-controlling agent. Culvert Construction In addition to the 1600mm culvert being installed south of Grand Blvd, four roadway crossing culverts have been identified for removal and replacement. The work in these areas is to be completed in stages so that one lane is open to traffic at all times. Lawn Irrigation System If you have a lawn irrigation system within the City s road allowance, please disconnect and remove any sprinkler heads within the City s road allowance. Please flag all other irrigation heads, so they are not damaged. The City is not responsible for damaged heads within the road allowance. Vibration You may at times experience some minor vibration as a result of construction equipment. Garbage Pick up Please continue to put your garbage and recycling out on the usual day. It is the contractor s responsibility to move your garbage to a location that can be accessed by the garbage truck and return your garbage containers. In order to help the contractor, we would ask that you indicate on your garbage cans and recycle bins your house numbers. c.c. Councillor Taylor, Ward 3 City of Burlington: Scott Hamilton, Trevor Clark Fermar Paving Limited
Street Improvements in the area of New Street and Drury Lane
Street Improvements in the area of New Street and Drury Lane Public Information Centre (PIC) Monday February 22, 2016 Central Recreation Centre - Auditorium Page 1 of 45 02/22/16 A G E N D A 1. Project
More informationINGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI
INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI 48854-0038 March 27, 2018 William M. Conklin, P.E. Managing Director FOR IMMEDIATE RELEASE:
More informationInspector MUST Sign and Date Each Inspection
Work Area: Applicant: Mercer County Department of Transportation - Highways Division Application and Permit for Road Work in Mercer County, New Jersey NO. East Windsor Ewing Hamilton Hopewell Lawrence
More informationROAD OCCUPANCY PERMIT APPLICATION # Damascus Township, 60 Conklin Hill Road, Damascus, PA Tel Fax
Instructions: For a driveway access permit, fill in sections 1, 2, 3 and 4, and the appropriate drawings and sign. For a Utility access, fill in sections 1, 2, 3 and 5, and figures 1 and 3. Prepare a detailed
More informationPERFORMANCE ACTIVITY 613 IMPACT ATTENUATOR WORK DESCRIPTION 3
PERFORMANCE ACTIVITY 613 IMPACT ATTENUATOR WORK DESCRIPTION 1 WORK DESCRIPTION 2 WORK DESCRIPTION 3 Install Remove Repair 613 IMPACT ATTENUATOR ACTIVITY DESCRIPTION Repair, install, remove and maintain
More informationHospital Link Project Project Update September 2017
Hospital Link Project Project Update September 2017 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction is well underway. Read on for important
More informationRoad Usage Permit Application Form
15/06/2012 Road Usage Permit Application Form City Yards 1495 Hardy Street Kelowna, BC V1Y 7W9 Tel: (250) 469-8600 Fax: (250) 862-3330 PERMITS WILL BE APPROVED OR DECLINED WITHIN 5 BUSINESS DAYS. WORK
More informationHospital Link Project Project Update November 2017
Hospital Link Project Project Update November 2017 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction is well underway. Read on for important
More informationLARIMER COUNTY: ENGINEERING DOUGLAS ROAD (CR 54)
LARIMER COUNTY: ENGINEERING DOUGLAS ROAD (CR 54) INTRODUCTIONS * Pipeline 1041 Application Coordinator Todd Blomstrom Public Works Director Mark Peterson County Engineer Terry Gilbert Community Development
More informationHighway 56 Traffic Study Rymal Road to Cemetery Road
January 31, 2018 6:00 pm 8:00 pm Highway 56 Traffic Study Rymal Road to Cemetery Road City of Hamilton Public Meeting 2 2 Purpose of Public Meeting To review and obtain public input and comments on the
More informationMILEGROUND - AIRPORT ROAD. Fall 2018/ Spring Fall 2020 TBD. US 119 Monongalia County HOW WILL TRAFFIC CONTROL BE HANDLED: KNOW BEFORE YOU GO
MILEGROUD - AIRPORT ROAD US 119 Monongalia County The Mileground - Airport Road project on US 119 involves upgrading the three-lane facility to a five-lane facility to help eliminate congestion and improve
More informationCTH M HIGHWAY PROJECT CTH Q to STH 113
CTH M HIGHWAY PROJECT CTH Q to STH 113 PUBLIC INFORMATIONAL MEETING #3 Wednesday, May 25, 2005 Town of Westport Administration Building 5387 Mary Lake Road 6:00 p.m. to 8:00 p.m. PUBLIC INFORMATIONAL MEETING
More informationFDOT Treasure Coast Traffic Impact Report April 7 through April 14, 2017
April 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report April 7 through April 14, 2017 TREASURE COAST Construction and maintenance related
More informationIL Route 71 Construction Update
100 Parkers Mill Oswego, IL. 60543 (630) 554-3618 4.20.16 IL 71 TRAFFIC ADVISORY: Tentatively scheduled for April 21st A new traffic pattern from Paradise to Wolf Crossing on IL 71 will be in use. The
More informationFDOT Treasure Coast Traffic Impact Report
January 20, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report January 20 through January 27, 2017 TREASURE COAST Construction and maintenance
More informationWeymouth - Abington Route 18 Widening and Reconstruction Project File No
Weymouth - Abington Route 18 Widening and Reconstruction Project File No. 601630 PROJECT LOCATION Project Limit Previously Completed Signalized Intersections (Typical) Route 18 Widening Bridge No. W-32-013
More informationPERFORMANCE ACTIVITY 405 LIMB MANAGEMENT
PERFORMANCE ACTIVITY 405 LIMB MANAGEMENT 405 LIMB MANAGEMENT ACTIVITY DESCRIPTION Cut and/or remove and/or grind tree limbs from the right-of-way. TRAFFIC CONTROL Utilize intermittent mobile operations
More informationKalamazoo County Weekly Project Updates from the Cities of Portage, Kalamazoo and the Kalamazoo County Road Commission
FOR IMMEDIATE RELEASE Date: October 31, 2014 Kalamazoo County Weekly Project Updates from the Cities of Portage, Kalamazoo and the Kalamazoo County Road Commission Kalamazoo, MI- In a collaborative effort
More informationTOWN OF PALM BEACH FOR IMMEDIATE RELEASE. Patricia Strayer, P.E., Town Engineer Phone: ,
TOWN OF PALM BEACH DATE: November 9, 2018 FOR IMMEDIATE RELEASE MEDIA CONTACT: Patricia Strayer, P.E., Town Engineer Phone: 561-838-5440, Email: pstrayer@townofpalmbeach.com Construction & Traffic Highlights
More informationCity of Pleasant Hill
City of Pleasant Hill M E M O R A N D U M TO: FROM: Mayor and City Council June Catalano, Manager DATE: September 12, 2014 SUBJECT: WEEKLY UPDATE GENERAL UPDATE Goals Workshop The City Council will be
More informationMeeting Notes. PIM Meeting #1 CTH D Reconstruction Nenno Road to Canadian National Railroad Town of Wayne Washington County
Meeting Notes PIM Meeting #1 CTH D Reconstruction Nenno Road to Canadian National Railroad Town of Wayne Washington County Attendees: Date/Time: Location: See attached sign in sheet October 25, 2017; 6:00
More informationPERFORMANCE ACTIVITY 401 MOWING WORK DESCRIPTION 5
PERFORMANCE ACTIVITY 401 MOWING WORK DESCRIPTION 1 WORK DESCRIPTION 2 WORK DESCRIPTION 3 WORK DESCRIPTION 4 WORK DESCRIPTION 5 Brush Management Hand Trimming Outdoor Advertising Window Routine Safety 401
More informationMay 10, 2013 Meredith Cruz, (561) Palm Beach County Traffic Report May 10 through May 17, 2013
May 10, 2013 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 10 through May 17, 2013 Palm Beach County Palm Beach County traffic will be affected this week by ongoing
More informationCincinnati Dayton Rd Widening
Cincinnati Dayton Rd Widening Project Overview Widening of Cincinnati Dayton Rd to four lanes - providing a center turn lane and an additional northbound lane Realignment of Station Rd Widening of bridge
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax ROAD WATCH UPDATE
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE May 25 May 31, 2017 College Parkway: Lee County DOT will be trimming
More informationTaylor Road Resurfacing Project
Project General Information: Contractor: Perk Company, Inc. Awarded: July 28, 2011 Signed Contract: August 25, 2011 Project Bid Price: $3,600,000 Project Length: 1.5 miles 2 General Information: Project
More informationFDOT Treasure Coast Traffic Impact Report
February 10, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report February 10 through February 17, 2017 TREASURE COAST Construction and maintenance
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE August 24 August 30, 2017 Hancock Bridge Parkway: Lee County DOT will
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE November 9 November 15, 2017 Update: 11/9/17 3:45 p.m. New Pass, Bridge
More informationThursday, May 18, p.m. Kortright Hills Public School Library, 23 Ptarmigan Drive, Guelph
Teal Drive to Niska Road Open house information package Thursday, May 18, 2017 5 8 p.m. Kortright Hills Public School Library, 23 Ptarmigan Drive, Guelph If you comments, please fill it out the comment
More informationReadington Road (C.R. 637) Construction
Public Information Meeting Thursday, August 2, 2012 Readington Road (C.R. 637) Construction from Dreahook Road to Harlan School Road Branchburg Township, Somerset County Readington Township, Hunterdon
More informationFDOT Treasure Coast Traffic Impact Report
September 29, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report September 29 through October 6, 2017 TREASURE COAST Construction and maintenance
More informationRue des Trappistes Culvert Replacement and Road Reconstruction PUBLIC ENGAGEMENT SUMMARY October 2017
Rue des Trappistes Culvert Replacement and Road Reconstruction PUBLIC ENGAGEMENT SUMMARY October 2017 Background The culvert at Rue des Trappistes and Westendorf Coulee needs to be replaced as it is at
More informationDOUG s CORNER CONTRACTOR S WEEKLY UPDATE NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE
CONTRACTOR S WEEKLY UPDATE -19TH AVENUE-BETHANY HOME TO DUNLAP December 29, 2014 Volume 2, Issue 102 DOUG s CORNER COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE Doug s Corner.1 3 Traffic/Active Work 4-6
More informationFINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By:
FINAL REPORT Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County Submitted By: Del Norte County Community Development Department Yonkers Creek Migration Barrier Removal Project
More informationENGINEERING AND PUBLIC WORKS. Transportation Improvements: Santa s Village Road (MR15) Public Meeting
ENGINEERING AND PUBLIC WORKS Transportation Improvements: Santa s Village Road (MR15) Public Meeting March 22, 2018 Agenda Welcome and Introductions Fred Jahn: Commissioner of Engineering and Public Works
More informationDOUG s CORNER CONTRACTOR S WEEKLY UPDATE NORTHWEST EXTENSION-19TH AVENUE-BETHANY HOME TO DUNLAP COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE
CONTRACTOR S WEEKLY UPDATE -19TH AVENUE-BETHANY HOME TO DUNLAP January 19, 2015 Volume 2, Issue 105 DOUG s CORNER COURTEOUS RESPONSIVE DEPENDABLE IN THIS ISSUE Doug s Corner.1 3 Traffic/Active Work 4-6
More informationCITY OF ROHNERT PARK CITY COUNCIL AGENDA REPORT
Meeting Date: May 10, 2016 Department: Submitted By: Prepared By: Agenda Title: Mission Statement We Care for Our Residents by Working Together to Build a Better Community for Today and Tomorrow. CITY
More informationProgress Report on the Design and Planning of an Infrastructure Improvement Project for the Sunnyside TIF District (Phase II)
Presentation to the CNRC Board of Directors Regular Meeting March 11, 2015 1 Agenda Preferred Alternate Refinement for University Avenue, 3rd Street, and Beverly Avenue Intersection Improvements validate
More informationJourney to Excellence. Building Markham s Future Together MARCH 24, 2015 HIGHWAY 407 TO HIGHWAY 7 MAIN STREET MARKHAM
MAIN STREET MARKHAM HIGHWAY 407 TO HIGHWAY 7 1 MARCH 24, 2015 2 DISCUSSION Update Committee on Project Schedule Reversible Lanes Recommendations Next Steps 3 COMPLETED WORK 4 PROJECT UPDATE Enbridge is
More informationPERFORMANCE ACTIVITY 306 DRAINAGE PIPE WORK DESCRIPTION 4
PERFORMANCE ACTIVITY 306 DRAINAGE PIPE WORK DESCRIPTION 1 WORK DESCRIPTION 2 WORK DESCRIPTION 3 WORK DESCRIPTION 4 Repair Install Remove Clean 306 DRAINAGE PIPE ACTIVITY DESCRIPTION Install, repair, clean,
More informationAccess Management Standards
Access Management Standards Section 1: Application of Access Standards This chapter describes the Department's access management standards for access connections on the county roadway system. The standards
More informationITEMIZED LIST FOR TRAFFIC CONTROL TOTAL UNITS S
STATE OF SOUTH DAKOTA PROJECT SHEET TOTAL SHEETS ( ) 029S-288 10 2 7 MAINTENANCE OF TRAFFIC Removing, relocating, covering, salvaging and resetting of permanent traffic control devices, including delineation,
More informationBuilding Great Neighbourhoods STRATHEARN
Building Great Neighbourhoods STRATHEARN Public Involvement Community League Meeting #1: October 5, 2015 Public Meeting #2: March 15, 2016 Public Meeting #3: January 17, 2017 Building Great Neighbourhoods
More informationSTANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF MANITOWOC, WISCONSIN SECTION 900 TRAFFIC CONTROL
SECTION 900 TRAFFIC CONTROL STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF MANITOWOC, WISCONSIN SECTION 900 TRAFFIC CONTROL Section Number Title 901 GENERAL 902 MATERIALS, EQUIPMENT, AND
More informationShoulders. Chapter 4: chapter contents
Chapter 4: Shoulders chapter contents Characteristics of Well-Maintained Shoulders 73 Optimal Timing/Conditions for Maintenance 73 Shoulder Maintenance Issues 74 Shoulder Maintenance Activities 75 Repairing
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE October 12 October 18, 2017 Gunnery Road and 8th Street SW Intersection
More informationTraffic Control Signals Cosburn Avenue and Todmorden Lane/ Private Access
REPORT FOR ACTION Traffic Control Signals Cosburn Avenue and Todmorden Lane/ Private Access Date: May 25, 2017 To: Toronto and East York Community Council From: Acting Director, Transportation Services,
More informationAPPENDIX L. Design Criteria
APPENDIX L Design Criteria DRAFT PRELIMINARY DESIGN CRITERIA Page 1 of 18 APPROVALS MANAGER, ENGINEERING CITY OF HAMILTON MANAGER, ENGINEERING REGION OF HALTON DATE This Design Criteria for the New East-West
More informationTRAFFIC FIELD OPERATIONS (1 of 7) - ADMINISTRATION
TRAFFIC FIELD OPERATIONS (1 of 7) - ADMINISTRATION Field Operations Director 003513 Sr. Community Educator 003542 Asst. Field Operations Director 001046 Stormwater Operations Analyst 003833 Special Projects
More informationCulpeper District. Albemarle County Monthly Report September, 2011
Culpeper District Albemarle County Monthly Report Special Issues FY Revenue Sharing Program - If you wish to participate in the Revenue Sharing Program for the fiscal year starting July 1, 2012, applications
More informationFifth & Kirkham Traffic-Calming Project. 5 th Avenue and Kirkham Street Presented at the UCSF Quarterly Parnassus Community Meeting May 3, 2018
Fifth & Kirkham Traffic-Calming Project 5 th Avenue and Kirkham Street Presented at the UCSF Quarterly Parnassus Community Meeting May 3, 2018 1 Agenda Welcome and introductions Project history, goals,
More informationCONSTRUCTION ENCROACHMENT PERMIT APPLICATION AND PROCESSING INSTRUCTIONS
'HYHORSPHQW (QJLQHHULQJ 5LFKDUGV %OYG UG )ORRU 6DFUDPHQWR &$ Phone: 916-808-8300 Fax: 916-808-1984 (QJLQHHULQJ 6HUYLFHV 'LYLVLRQ CONSTRUCTION ENCROACHMENT PERMIT APPLICATION AND PROCESSING INSTRUCTIONS
More informationODOT construction cost is $51,000,000. State assumes and bears 100 percent of the cost of improvement.
1. I 271 WIDENING & RESURFACING - PID 89458 Project consists of major reconstruction, widening and bridge deck replacement. Project will accomplish widening from 4 to 6 lanes, including redecking and widening
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax ROAD WATCH UPDATE
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE May5 th through May 11 th, 2016 Road Maintenance This Week Striping Maintenance:
More informationEl Paso County 2040 Major Transportation Corridors Plan
El Paso County 2040 Major Transportation Corridors Plan Connect-our-County Online Transportation User Survey Preliminary Results June 24, 2010 Years of Residence 2. How many years have you LIVED HERE?
More informationROAD MAINTENANCE. Back to Basics. Duane A. Blanck, P.E MAT Spring Short Course
ROAD MAINTENANCE Back to Basics Duane A. Blanck, P.E. 2018 MAT Spring Short Course Understanding the Basics of Road Maintenance Road Maintenance = biggest expenditure of a Township in terms of both time
More informationENERGY SECTOR COORDINATION
ENERGY SECTOR COORDINATION Darin Kosmak, Deputy Director TxDOT Rail Division November 4, 2013 Energy Sector Considerations Existing FM roads not built to handle truck traffic resulting from: Oil & natural
More informationGWINNETT COUNTY DEPARTMENT OF TRANSPORTATION
GWINNETT COUNTY DEPARTMENT OF TRANSPORTATION 1 of 7 June 20, 2007 GENERAL: The following guidelines shall be used in the determination of the requirement for left turn lanes for development projects and
More informationEl Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018
El Camino Real Specific Plan TAC/CAC Meeting #2 Aug 1, 2018 Land Use Alternatives Goals and Tradeoffs Parks & open space Housing Retail & services Civic spaces Parking Community gathering spaces 3 Alternatives
More informationOLIVE AVENUE CLASS 2 BIKE LANES HSIP, CIP PROJECT NO CONSTRUCTION CONTRACT AWARD
STAFF REPORT MEETING DATE: June 7, 2016 TO: FROM: City Council Russ Thompson, Public Works Director Gosia Woodfin, Assistant Engineer 922 Machin Avenue Novato, CA 94945 415/ 899-8900 FAX 415/ 899-8213
More informationUPDATES 11/14/2018: 10/25/2018: CLOSED 10/22/2018: 10/12/2018: 10/05/2018: 09/27/2018:
Veterans Boulevard (formerly Boundary Road) This two-year construction project will widen and pave all of Veterans Boulevard. In 2017, the first portion of the road from Highway 16A to 44 Avenue was completed.
More informationFleur Drive Reconstruction
Fleur Drive Reconstruction October 29, 2018 1 Agenda: Fleur Drive Reconstruction Project Scope & Cost Overview Fleur Drive Cross Section Elements - Travel Lane Widths - Sidewalk Widths - Parkway Widths
More informationRiver Road - Proposed Road Safety Enhancement Measures
City of Richmond Report to Committee To: From: Re: Public Works and Transportation Committee Victor Wei, P. Eng. Director, Transportation Date: June 6, 2017 River Road - Proposed Road Safety Enhancement
More informationDowntown Redevelopment Project Update
Downtown Redevelopment Project Update The redevelopment project will begin the week of September 4, 2017. It is anticipated that construction will be approximately 565 days, depending on weather. 8-1-18
More information20 minute presentation on proposed project. Comments and Questions following presentation. City of Madison
20 minute presentation on proposed project Comments and Questions following presentation 2016 2017 Replace concrete pavement & base Replace curb and sidewalk as needed Proposed contra-flow bike lane Replace
More informationReference: Laguna Canyon Road Traffic Conditions Data Collection Summary
Stantec Consulting Services Inc. 38 Technology Drive Suite 100, Irvine CA 92618-5312 September 8, 2017 File: 2073014320 Attention: Mark Trestik, Assistant City Engineer City of Beach Department of Public
More informationLee County Department of Transportation
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE New Updates & Revisions September 3 rd, through September 9 th, 2015
More informationWELCOME! OPEN HOUSE SHAW ROAD IMPROVEMENT PROJECT JUNE 30, 2015
WELCOME! OPEN HOUSE SHAW ROAD IMPROVEMENT PROJECT JUNE 30, 2015 Traffic Improvements Project Goals Widen roadway to construction two-way left turn lanes-greatly decreases congestion Ease access to & from
More informationState Route 28 Shared Use Path & Safety/Stormwater Enhancements Public Information Meeting
State Route 28 Shared Use Path & Safety/Stormwater Enhancements Public Information Meeting Thursday, March 30, 2017 4-7 p.m. Presentation at 5:30 p.m. The Chateau at Incline Village 955 Fairway Blvd. Incline
More informationGENERAL CODE PROVISIONS TABLE OF CONTENTS
GENERAL CODE PROVISIONS CHAPTER 1 CODE OF ORDINANCES... 1 CHAPTER 2 CHARTER... 9 CHAPTER 3 BOUNDARIES... 11 CHAPTER 4 MUNICIPAL INFRACTIONS... 17 CHAPTER 5 OPERATING PROCEDURES... 25 CHAPTER 6 CITY ELECTIONS...
More informationReplacement of N. Carlin Springs Road Bridge over George Mason Dr.
Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance of Travel (MOT) plans February 2017 Project Elements Removal of existing bridge
More informationThe District Municipality of Muskoka 70 Pine Street Bracebridge ON P1L 1N3
Public Information Centre Summary Report Muskoka Road 15 (Santa s Village Road) Transportation Improvements from the Beaver Creek Bridge to the Entrance of Santa s Village The District Municipality of
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE August 17 August 23, 2017 Traffic Maintenance: Signal Maintenance Bonita
More informationINTERSECTION WITH RIGHT TURN TAPER
(TYP.) TAPER 4" BROKEN INTERSECTION WITH RIGHT TURN TAPER 4" SOLID WHITE 4" BROKEN ARROW & LEGEND MARKINGS (SEE NOTE 2) INTERSECTION WITH RIGHT TURN LANE Notes: 1. Paint intersection tapers greater than
More informationProgrammatic Categorical Exclusion Update Question & Answers
Office of Environmental Stewardship 395 John Ireland Blvd St. Paul, MN 55155 Programmatic Categorical Exclusion Update Question & Answers Date: October 2017 OPTIONAL District/Division Nam This FAQ document
More informationCity of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE
Welcome Welcome to the third community meeting for the Issaquah-Fall City Road Improvements Project. AGENDA 6:00 p.m. Welcome and sign-in 6:10 p.m. Presentation 6:50 p.m. Open house Learn about the roadway
More informationPRESENTATION OUTLINE
November 8, 2017 PRESENTATION OUTLINE Regional Express Lanes Network Purpose/Benefits of Express Lanes 95 Express Phase 3C Project Video and Overview 95 Express Phase 3C Schedule 2 SOUTH FLORIDA REGIONAL
More informationTownship of Springwater
Township of Springwater Approved: November 2008 Effective: Date of Passing Next Review: TBD Department: Public Works Subject: Sidewalks Policy Number: A09 SI A. Authority This policy shall be approved
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax ROAD WATCH UPDATE
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE November 10 th, through November 16 th, 2016 Alico & Gator Road Intersection
More informationSECTION 14: LANDSCAPING AND BEAUTIFICATION
SECTION 14: LANDSCAPING AND BEAUTIFICATION RULE 14.1 GENERAL PROVISIONS 14.1.1 The rules and guidelines contained in this section have been established to provide proper guidelines for the beautification
More informationCITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES
CITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES PROJECT LOCATION MAP (1) DEYOUNG PARK IMPROVEMENTS Project Description - DeYoung Park Improvements include treehouse deck, play area, new
More informationAgenda. NTTA Network of Roadways. Emergency Procurement Caught on Video: Real Life Emergency Response Presented to: APWA
Emergency Procurement Caught on Video: Real Life Emergency Response Presented to: APWA J.C. Wood, P.E. Director of Maintenance North Texas Tollway Authority September 19, 2011 Agenda Setting the Stage
More informationWelcome to the Public Meeting. Red Hill Business Park South Transportation Master Plan Addendum. December 4, :00 p.m. to 8:00 p.m.
Welcome Welcome to the Transportation Master Plan Addendum December 4, 2012 6:00 p.m. to 8:00 p.m. Please sign-in Background PIC#1 Public Information Centre #1 (PIC#1) was held on June 25, 2012. Feedback
More informationPavement Rehabilitation & Buffered Bike Lane
Pembina Highway from Grant Avenue to Osborne Street Pavement Rehabilitation & Buffered Bike Lane Welcome April 21, 2016 Please complete and submit a comment sheet prior to leaving or complete it online
More informationSan Tomas Expressway
Implementation Plan San Tomas Expressway Roads and Airports Department August 19, 2003 Implementation Plan San Tomas Expressway County of Santa Clara Roads and Airports Department 101 Skyport Drive San
More information4 DISRUPTION MANAGEMENT PLAN HIGHWAY 7 RAPIDWAY CONSTRUCTION BETWEEN BAYVIEW AVENUE AND WARDEN AVENUE TOWNS OF MARKHAM AND RICHMOND HILL
4 DISRUPTION MANAGEMENT PLAN HIGHWAY 7 RAPIDWAY CONSTRUCTION BETWEEN BAYVIEW AVENUE AND WARDEN AVENUE TOWNS OF MARKHAM AND RICHMOND HILL The Transportation Services Committee recommends the adoption of
More informationE 86 th Street Safety & Streetscape Improvements/ Madison Avenue School Safety Neckdowns. Project ID: HWMM008
E 86 th Street Safety & Streetscape Improvements/ Madison Avenue School Safety Neckdowns Project ID: HWMM008 Community Board 8 Transportation Committee Meeting July 06, 2016 6:30PM Project Data Project
More informationEl Dorado County / Tahoe Roadwork Schedule
Today s Date: Friday, August 3, 2012, #12-220 District: District 3 - Marysville, http://www.dot.ca.gov/dist3 Jody Jones, District Director Contact: Deanna Shoopman deanna_shoopman@dot.ca.gov 530. 741.4566
More informationU.S. HIGHWAY 50 IMPROVEMENT PROJECT
U.S. HIGHWAY 50 IMPROVEMENT PROJECT in the City of South Lake Tahoe Project Purpose and Need Planned Improvements Project Cost and Delivery Schedule Proposed Construction Staging Project Partners: HIGHWAY
More informationDriveway Design Criteria
Design Manual Chapter 5 - Roadway Design 5L - Access Management 5L-4 Driveway Design Criteria A. General For efficient and safe operations, access drives and minor public street intersections can be improved
More informationREQUIREMENTS FOR TRAFFIC CONTROL PLAN SUBMISSION
REQUIREMENTS FOR TRAFFIC CONTROL PLAN SUBMISSION A draft traffic control plan, consistent with the following applicable conditions, must be included in every permit application submitted to the City of
More informationChapter 3 DESIGN SPECIFICATIONS
Brampton PathWays Planning and Design Guidelines 27 Chapter 3 DESIGN SPECIFICATIONS 3.1 CLASS 1 MULTI-USE PATH Off-road multi-use trails are the backbone of the Brampton PathWays Network. They are typically
More informationConcrete Pavements ACCELERATED CONSTRUCTION OF URBAN INTERSECTIONS WITH PORTLAND CEMENT CONCRETE PAVEMENT (PCCP)
Concrete Pavements ACCELERATED CONSTRUCTION OF URBAN INTERSECTIONS WITH PORTLAND CEMENT CONCRETE PAVEMENT (PCCP) Pavements Asphalt pavement has long been a popular road construction material. In areas
More informationARLINGTON COUNTY, VIRGINIA
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of October 15, 2016 DATE: October 7, 2016 SUBJECT: Adoption of amendments to the Master Transportation Plan (MTP) to create a new Pedestrian
More informationControlled. Semi-Controlled PAGE 01 CHAPTER 12 INTERSECTIONS
PAGE 01 CHAPTER 12 INTERSECTIONS You will cross many intersections while driving. Intersections are especially dangerous because vehicles are crossing each other s driving path. Many crashes happen at
More informationODOT DISTRICT CONSTRUCTION PROGRAM SERVING BUTLER, CLERMONT, CLINTON, GREENE, HAMILTON, PREBLE AND WARREN COUNTIES.
ODOT DISTRICT 8 2018 CONSTRUCTION PROGRAM Preble Greene SERVING BUTLER, CLERMONT, CLINTON, GREENE, HAMILTON, PREBLE AND WARREN COUNTIES. Butler Hamilton Warren Clinton Lebanon Clermont John R. Kasich,
More informationDuwamish Way-finding and CTR Report
V. North Tukwila When the North Tukwila Manufacturing and Industrial Center was designated in 1992 as part of the region s land use and transportation plan, the plan called for the area to set a light-rail
More informationAdvanced Construction Techniques. Concrete Pavements ACCELERATED CONSTRUCTION OF URBAN INTERSECTIONS WITH PORTLAND CEMENT CONCRETE PAVEMENT (PCCP)
CM 510 Concrete Pavements ACCELERATED CONSTRUCTION OF URBAN INTERSECTIONS WITH PORTLAND CEMENT CONCRETE PAVEMENT (PCCP) Pavements Asphalt pavement has long been a popular road construction material. In
More informationPROJECT FACT SHEET May 25, 2018
SITE CHALLENGES & PROJECT BACKGROUND In 2014, the City of Aspen identified the Castle Creek Bridge and Hallam Street corridor as a deficient link in Aspen s bicycle and pedestrian network. Safe and efficient
More information