1 Meeting Notes Date: December 20, 2018 Project #: To: David Agacinski FDOT District One Bicycle & Pedestrian Coordinator Daniels Parkway Ft. Myers, Florida From: Project: Subject: Patty Hurd, Jennifer Musselman US 41 Complete Streets/Multimodal Corridor Study Steering Committee Meeting #3 (December 11, :00pm-3:00pm) Attendees: Jesten Abraham, FDOT David Agacinski, FDOT Bessie Reina, FDOT Ryan Brown, Sarasota/Manatee MPO Alvimarie Corales, Sarasota/Manatee MPO Alan Burr, New College of Florida Susan Dodd, City of Sarasota Colleen McGue, City of Sarasota Jennifer Price, FSU/Ringling Museum Stephen High, FSU/Ringling Museum John P. Carvalho, Florida Highway Patrol Kent Bontrager, Sarasota Manatee Airport Authority Nelson Galeano, Manatee County Norm Luppino, Resident David Potenza, Resident Patty Hurd, Jennifer Musselman, FILENAME: H:\20\ FDOT D1 COMPLETE STREETS\US 41\MEETINGS\STEERING COMMITTEE #3\STEERING COMMITTEE #3 NOTES_V2.DOCX

2 December 20, 2018 Page 2 Topics: 1. Project Background The Study Team provided an overview of work efforts to date. Key issues and opportunities include: College connections New College and University of South Florida Sarasota-Manatee (USFSM) are sharing more resources, including classes and campus police. New College students in particular rely on non-auto modes to get around as many do not have a car on campus. USFSM access The campus entrance is unsignalized and not likely to meet signal warrants in the near future. The campus requested a roundabout, which partly influenced the need for this study. Speeding Speed is an issue along the corridor, particularly in the northbound direction along the airport. University Parkway Intersection the intersection is currently failing during the PM peak period and is expected to get worse in the future. It also has a high crash rate when compared to similar intersections. The goals of the Study are to: Improve safety and comfort; Improve access to destinations along the Corridor; Maintain vehicular mobility; and Beautify the Corridor. 2. Intersection Concepts The Study Team reviewed potential improvements to the US 41 and University Parkway intersection. A full ICE evaluation was done at the intersection because a roundabout review was requested. The roundabout did not move forward. Additional westbound turn lanes can provide LOS E in 2040 and could be done with within the existing right-of-way with a B/C ratio of 132. This could be done in conjunction with additional pedestrian improvements at the intersection. An exclusive northbound right would further reduce delay but would require right-ofway. The B/C for the westbound and northbound turn lanes is 119. The right-of-way in the southeast corner is owned by Florida State University, through a state trust. Stephen High offered to coordinate with FSU to explore right-ofdonation if FDOT provides the information. The Ringling Museum requested adding a through arrow on one the eastbound lanes to help with traffic exiting the museum.

3 December 20, 2018 Page 3 The Study Team reviewed potential improvements to the US 41 and Tallevast Road intersection. The Study Team tested many interactions of turns lanes, some suggested by the traffic consultant (VHB) and some requested by the Steering Committee members. The preferred alternative is to add a westbound right-turn lane and southbound leftturn lane and remove a southbound through lane. o This alternative would require additional right-of-way, currently owned by the airport. The airport has a strong desire to close Ponce de Leon Avenue to preserve their runway zone. The Federal Aviation Administration (FAA) prohibits roads and parking in the runway protection zone. Because Ponce de Leon is existing, it does not need to be removed, but if there s an opportunity to, the FAA would encourage it. They may be amendable to donating the needed right-of-way in exchange for the closing of Ponce de Leon Avenue, a Manatee County road. This land cannot be built on either way. A resident commented that is usually easy to make a left-turn onto Tallevast and adding dual left-turn lanes with protected only phasing would make it more difficult. There is a concern this would lead to more traffic on neighborhood streets. 3. Corridor Improvements The Study Team reviewed the travel time analysis for a four-lane cross-section and a six-lane cross-section. With the intersection improvements at Tallevast and University, a four-lane section would operate better than the no-build alternative in If roundabouts are added to USFSM entrance and Braden Avenue, the end to end travel time would be slightly longer, but still less than the no-build alternative in The Study Team reviewed the alternative typical sections, provided in the attached slides. Three of the four alternatives south of Edwards Drive would require additional rightof-way, owned by New College and the Ringling Museum. The College and Museum may be willing to donate. These three alternatives would likely require a retaining

4 December 20, 2018 Page 4 wall, since the land adjacent to the roadway is higher than the road. There is also a pinch point at the pedestrian bridge. The following questions and discussion took place: o Does FDOT allows trees in the buffer space? Yes, as long as it is four feet from the travel lane. o Businesses along this corridor have removed trees in the past that block their businesses. FDOT may want to consider investing in landscaping in the median instead of the outside buffer. o Will a four-lane section create more traffic? The four-lane section is expected to handle all the traffic the Tallevast and University Parkway signals are able to process. If those two intersections are improved in conjunction with the lane elimination, the travel time will be faster compared to the no-build alternative o What are the minimum sidewalk widths per FDOT and ADA standards? The FDOT minimum is 6. The ADA minimum is 5 and allows for occasional pinch points down to 4. The proposed cross sections meet both standards. For shared use paths, FDOT prefers 12 and will go to 10 if needed. 4. Public Involvement The Study Team shared key highlights from the survey: 772 responses from across the two-county area The survey ran from September through December 3 rd 94% of respondents drive alone on US 41 and 22% ride their bikes on US 41 o A resident noted there are two recreational bicycling groups that use the corridor 5 times a week to get from the Ballentine neighborhood up to the museum district and Indian Beach/Sapphire Shores neighborhood Respondents rated safety, speeding, and quality of bicycle facilities as top concerns Respondents rated improved bicycle facilities, medians, design to lower speed, landscaping, intersection capacity, and wider sidewalks as top improvements. 61% of respondents support the lane reduction if done in conjunction with intersection improvements The alternatives with dedicated bike facilities were generally favored over wide sidewalk/multi-use path alternatives 5. Implementation and Next Steps

5 December 20, 2018 Page 5 A resurfacing project is programmed in 2023 for the Manatee County section of the Study. There is time to scope additional elements, but there is not currently money available. A PD&E Study is funded in 2021/22. This study would need to be moved up, or the resurfacing moved out, to incorporate recommendations into resurfacing. The MPO may have additional funding in 2020/21 or 2022/23 to advance the PD&E o The Steering Committee was supportive of advancing the PD&E to an earlier year The MPO could also use these funds to construct the University Pkwy changes, since they do not require PD&E. o The Steering Committee was supportive of advancing the improvements at the University Parkway intersection as a standalone project. They requested FDOT coordinate with FSU to see if the needed ROW could be donated. The Committee would still support the project if only the westbound lanes can be added. The Study Team requested letters of support from local governments and will provide briefing materials.

US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue

US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue 41 US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue EXECUTIVE SUMMARY DRAFT FEBRUARY 2019 Project Overview The US 41 Complete Streets Corridor Planning Study,

More information

RM 620 FEASIBILITY STUDY

RM 620 FEASIBILITY STUDY RM 620 FEASIBILITY STUDY Sections 5 & 6 December 7, 2015 STUDY PROCESS Study Purpose and Goals The RM 620 Feasibility Study was launched by the Texas Department of Transportation (TxDOT) to analyze transportation

More information

HENDERSON DEVELOPMENT 213, 217, 221, 221 ½, 223 HENDERSON AVENUE and 65 TEMPLETON STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW.

HENDERSON DEVELOPMENT 213, 217, 221, 221 ½, 223 HENDERSON AVENUE and 65 TEMPLETON STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. HENDERSON DEVELOPMENT 213, 217, 221, 221 ½, 223 HENDERSON AVENUE and 65 TEMPLETON STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW Prepared for: 2294170 Ontario Inc. February 2, 2017 117-652 Report_1.doc

More information

US 41 (Tamiami Trail) Corridor Study. Roadway Safety Audit

US 41 (Tamiami Trail) Corridor Study. Roadway Safety Audit US 41 (Tamiami Trail) Corridor Study Roadway Safety Audit US 41 RSA June 14/15, 2017 Agenda Project Overview Schedule RSA Process Overview RSA Responsibilities Historical Crash Review 2 PROJECT OVERVIEW

More information

Reference number /VP. Lafayette Downtown Congestion Study - Additional Traffic Analysis

Reference number /VP. Lafayette Downtown Congestion Study - Additional Traffic Analysis To James Hinkamp and Tony Coe, City of Lafayette Date January 19, 2017 Copies Reference number 243381/VP From Michael Iswalt and Vanessa Peers File reference 4-05 Subject Lafayette Downtown Congestion

More information

PAT Meeting #2 Future Alternatives Meeting Agenda

PAT Meeting #2 Future Alternatives Meeting Agenda PAT Meeting #2 Future Alternatives Meeting Agenda Future Build Alternatives Discussion August 18, 2017 Viera Gov't Center, Atlantic Room, Building C, 3rd Floor 9:00 AM 11:00 AM 1. Schedule Update 2. Issues/Opportunities

More information

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Aaron Elias, Bill Cisco Abstract As part of evaluating the feasibility of a road diet on Orange Grove Boulevard in Pasadena,

More information

Bay to Bay Boulevard Complete Streets Project

Bay to Bay Boulevard Complete Streets Project Bay to Bay Boulevard Complete Streets Project Dale Mabry Highway to Bayshore Boulevard February 08, 2018 Photo Source: Tampa Bay Times Alessandra Da Pra Meeting Format Introduction Resurfacing Information

More information

Thank you for attending

Thank you for attending Improving mobility safety comfort WELCOME Thank you for attending The purpose of this meeting is to: Learn about the project Prioritize potential walking and biking improvements on Snelling Ave Gather

More information

Giles Run Connector Road

Giles Run Connector Road Giles Run Connector Road Laurel Hill Adaptive Reuse Area to Laurel Crest Drive South County Federation Meeting June 14, 2016 History Connector road included in the Laurel Hill Comprehensive Plan amendment

More information

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE About the Project 2014/2015 BIKE ROUTE PLAN The City of Edmonton is planning a major bike route on the south side of Edmonton. This bike route is one part of a plan to provide citizens with transportation

More information

WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING. March 28, 2017

WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING. March 28, 2017 WISCONSIN AVENUE EXTENSION SECOND PUBLIC INFORMATION MEETING March 28, 2017 STUDY AREA N MEETING AGENDA Introductions Study Background Alternatives Studied Recommended Alternative Discussion STUDY BACKGROUND

More information

How to Develop a Pedestrian Safety Action Plan

How to Develop a Pedestrian Safety Action Plan How to Develop a Pedestrian Safety Action Plan Course Introduction Presented by: Peter Eun FHWA RC Safety Engineer Ryan Snyder President, Ryan Snyder Associates, LLC Paul Zykofsky Director, Land Use and

More information

Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements Advertisement for Construction - Progress Report

Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements Advertisement for Construction - Progress Report Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements Advertisement for Construction - Progress Report UPC Design 70762 / CN 109813 Locally Administered PE Phase VDOT Administered

More information

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE About the Project The City of Edmonton is planning a major bike route on the southside of Edmonton. The Strathcona Bike Route will connect the communities of Strathcona, Garneau and the University area,

More information

Board of Supervisors February 27, 2017

Board of Supervisors February 27, 2017 : Traffic Analysis Results & Draft Conceptual Plan Board of Supervisors February 27, 2017 Transportation Solutions Building Better Communities Presentation Overview Background Summary of Traffic Analysis

More information

AGENDA ITEM 6 D THOMASVILLE ROAD (HERMITAGE BOULEVARD TO LIVE OAK PLANTATION ROAD) ROADWAY SAFETY AUDIT

AGENDA ITEM 6 D THOMASVILLE ROAD (HERMITAGE BOULEVARD TO LIVE OAK PLANTATION ROAD) ROADWAY SAFETY AUDIT May 15, 2018 AGENDA ITEM 6 D THOMASVILLE ROAD (HERMITAGE BOULEVARD TO LIVE OAK PLANTATION ROAD) ROADWAY SAFETY AUDIT TYPE OF ITEM: Discussion STATEMENT OF ISSUE The Florida Department of Transportation

More information

Bellevue Downtown Association Downtown Bike Series

Bellevue Downtown Association Downtown Bike Series Bellevue Downtown Association Downtown Bike Series Meeting 2 Franz Loewenherz Andreas Piller Kyle Potuzak Chris Long October 26, 2017 Today s Agenda: 1) Meeting Purpose 2) 9/28 Meeting Recap 3) Candidate

More information

Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements 100% Engineering Design - Progress Report

Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements 100% Engineering Design - Progress Report Capital Projects Update: N. Lynn Street Esplanade and Custis Trail Improvements 100% Engineering Design - Progress Report UPC 70762 Locally Administered PE Phase VDOT Administered CN Phase 4/6/17 1 Project

More information

Balancing Operation & Safety for Motorized and Non-Motorized Traffic

Balancing Operation & Safety for Motorized and Non-Motorized Traffic Balancing Operation & Safety for Motorized and Non-Motorized Traffic Brian Willham, PE, PTOE Iowa Director - MOVITE June 30, 2014 Learning Objectives: When & Why should we measure the performance of complete

More information

REPORT CONCURRENCE. City Manager. The General Manager concurs with the recommendation of this report.

REPORT CONCURRENCE. City Manager. The General Manager concurs with the recommendation of this report. COUNCIL REPORT Report No. ENG 08-018 Executive Committee Date: May 0, 018 File No: 5400-1 To: From: Subject: Mayor and Council Purvez Irani, Senior Transportation Engineer Bluejay Street Road Improvements

More information

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Mercer County Planning Division AECOM Transportation (formerly DMJM Harris) January 29, 2009 Agenda Project Status

More information

Boston Post Road Design Feasibility Study

Boston Post Road Design Feasibility Study Boston Post Road Design Feasibility Study Prepared for the City of Rye Final Report July 18, 2007 Prepared by: Buckhurst Fish & Jacquemart (BFJ) 115 Fifth Avenue New York, NY 10003 www.bfjplanning.com

More information

Trip Generation Impact Analysis Reporting Form

Trip Generation Impact Analysis Reporting Form CITY OF DESTIN CONCURRENCY EVALUATION CERTIFICATION MULTI-MODAL TRANSPORTATION DISTRICT OLD DESTIN SUB-AREA (TIER 1) The following certificate, in conjunction with a trip generation and distribution analysis,

More information

AGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive

AGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive AGENDA REPORT To: From: By: Honorable Mayor and City Council Members Warren Hutmacher, City Manager Tom Black, Public Works Director Date: March 23, 2016 Agenda: March 28, 2016 WORK SESSION AGENDA: Barnwell

More information

Shockoe Bottom Preliminary Traffic and Parking Analysis

Shockoe Bottom Preliminary Traffic and Parking Analysis Shockoe Bottom Preliminary Traffic and Parking Analysis Richmond, Virginia August 14, 2013 Prepared For City of Richmond Department of Public Works Prepared By 1001 Boulders Pkwy Suite 300, Richmond, VA

More information

THE ALAMEDA CONCEPT DESIGN COMMUNITY MEETING 3. A Plan for The Beautiful Way JANUARY 28, 2010

THE ALAMEDA CONCEPT DESIGN COMMUNITY MEETING 3. A Plan for The Beautiful Way JANUARY 28, 2010 CONCEPT DESIGN COMMUNITY MEETING 3 JANUARY 28, 2010 AGENDA INTRODUCTION COMMUNITY INPUT ROADWAY STUDIES STREETSCAPE DESIGN STATIONS DISCUSSION SUMMARY AND DISCUSSION NEXT STEPS CLOSE INTRODUCTION SCHEDULE

More information

Downtown Naples Mobility and Connectivity Study. Naples City Council Presentation January 2017

Downtown Naples Mobility and Connectivity Study. Naples City Council Presentation January 2017 Downtown Naples Mobility and Connectivity Study Naples City Council Presentation January 2017 Agenda 1. Introduction 2. Scope Review 3. Project Schedule 4. Existing Conditions 5. Public Charrette 6. Mobility

More information

FAIRFIELD INN & SUITES HOTEL 135 THAD JOHNSON PRIVATE OTTAWA TRANSPORTATION BRIEF. Prepared for:

FAIRFIELD INN & SUITES HOTEL 135 THAD JOHNSON PRIVATE OTTAWA TRANSPORTATION BRIEF. Prepared for: FAIRFIELD INN & SUITES HOTEL 135 THAD JOHNSON PRIVATE OTTAWA TRANSPORTATION BRIEF Prepared for: Bona Building & Management Co. Ltd. Place Vanier, 333 North River Road Vanier, Ontario K1L 8B9 August 12,

More information

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of

More information

CAPITOL DRIVE & FOND DU LAC AVENUE INTERSECTION ANALYSIS. Urban Planning 772 SARAH BREGANT, RYAN PETERSON, & MATT WERDERITCH

CAPITOL DRIVE & FOND DU LAC AVENUE INTERSECTION ANALYSIS. Urban Planning 772 SARAH BREGANT, RYAN PETERSON, & MATT WERDERITCH CAPITOL DRIVE & FOND DU LAC AVENUE INTERSECTION ANALYSIS Urban Planning 772 SARAH BREGANT, RYAN PETERSON, & MATT WERDERITCH OVERVIEW N 51 ST BOULEVARD N 51 ST BOULEVARD 12,100 44,700 W CAPITOL DRIVE 52,600

More information

West Circle Drive (CSAH 22) Traffic Operations Study

West Circle Drive (CSAH 22) Traffic Operations Study West Circle Drive (CSAH 22) Traffic Operations Study May 24, 2016 Open House Harriet Bishop Elementary School 6:45 8:00 p.m. Presentation at 7:00 p.m. Purpose of Tonight s Meeting Introductions Explain

More information

Fleur Drive Reconstruction

Fleur Drive Reconstruction Fleur Drive Reconstruction October 29, 2018 1 Agenda: Fleur Drive Reconstruction Project Scope & Cost Overview Fleur Drive Cross Section Elements - Travel Lane Widths - Sidewalk Widths - Parkway Widths

More information

Existing Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer

Existing Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Date: April 16 th, 2015 To: From: Re: Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Darian Nagle-Gamm, Traffic Engineering Planner Highway 6 (2 nd Street) /

More information

OFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Canada Inc.

OFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Canada Inc. OFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: 9402209 Canada Inc. December 15, 2015 115-625 Report_2.doc D. J. Halpenny & Associates Ltd. Consulting Transportation

More information

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 What s Happening The City plans to mill and resurface Dr. M.L.

More information

Beach Cities Living Streets Design Manual and Aviation Boulevard Multimodal Corridor Plan

Beach Cities Living Streets Design Manual and Aviation Boulevard Multimodal Corridor Plan Beach Cities Living Streets Design Manual and Aviation Boulevard Multimodal Corridor Plan AGENDA 1 Introductions & Project Scope 2 Public Outreach Recap 3 Living Streets Design Manual 4 Aviation Boulevard

More information

ALLEY 24 TRAFFIC STUDY

ALLEY 24 TRAFFIC STUDY ALLEY 24 TRAFFIC STUDY in City of Frostburg, Maryland January 2013 3566 Teays Valley Road Hurricane, WV Office: (304) 397-5508 www.denniscorporation.com Alley 24 Traffic Study January 2013 Frostburg, Maryland

More information

Comments EXECUTIVE SUMMARY

Comments EXECUTIVE SUMMARY Comments 1. Under any Alternatives, MCDOT should provide better at-grade pedestrian crossing of Georgia Avenue and Forest Glen Road, including improved crosswalks with wider medians and adequate signal

More information

6.4 RECOMMENDED IMPROVEMENTS

6.4 RECOMMENDED IMPROVEMENTS 6.4 RECOMMENDED IMPROVEMENTS 6.4.1 Williston Road Recommendations While all alternatives would be an improvement over existing conditions, Alternative 3B is recommended over the others because it provides

More information

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009 Summary: Several recent studies have assessed potential development and redevelopment opportunities in the Mercer Crossing area of Trenton, Ewing, and Lawrence. This Princeton Avenue and Spruce Street

More information

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study

More information

Sarasota/Manatee MPO Project Priorities 2016 Adopted April 25, 2016

Sarasota/Manatee MPO Project Priorities 2016 Adopted April 25, 2016 All projects on the following priority lists should be implemented in the priority sequence listed, as consistent with the fiscal constraints identified in the MPO s adopted Long Range Transportation Plan

More information

WELCOME Public Information Centre

WELCOME Public Information Centre WELCOME Public Information Centre Fernforest Drive Brampton Soccer Centre Community Room #2 Tuesday January 19, 2016 6:30 p.m.to 9:00 p.m. Please sign in Neighbourhood Traffic Calming Guide Background

More information

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto

More information

This page intentionally left blank.

This page intentionally left blank. This page intentionally left blank. COMMUNITY Glenpool Community Overview Glenpool Glenpool is a city of nearly 12,000 residents located in Tulsa County southwest of Tulsa and Jenks. The city is growing

More information

Road Diets FDOT Process

Road Diets FDOT Process Florida Department of TRANSPORTATION Road Diets FDOT Process Humberto Castillero, PE, PTOE Roadway Design Office Purpose of Guide Develop a statewide lane elimination review process Balance state & local

More information

Project Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015

Project Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015 Meadows Place, TX October 9, 2015 Contents 1 Introduction... 1 2 Data Collection... 1 3 Existing Roadway Network... 2 4 Traffic Volume Development... 2 5 Warrant Analysis... 3 6 Traffic Control Alternative

More information

BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY

BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY 7B BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY PLACEMENT: REQUESTS AND PRESENTATIONS PRESET: TITLE: FLORIDA DEPARTMENT OF TRANSPORTATION (FDOT) PRESENTATION RECONSTRUCTION OF SR-76 (SW KANNER HIGHWAY)

More information

Planning Study SR 976. Project Advisory Team Meeting May 24, 2017

Planning Study SR 976. Project Advisory Team Meeting May 24, 2017 ` SR 976 BIRD ROAD/SW 40TH STREET FROM SR 821/HEFT TO SR 5/US-1 Miami-Dade County, Florida FPID No.: 434845-4-22-01 Planning Study Project Advisory Team Meeting May 24, 2017 1 Agenda Introductions Project

More information

HILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF. Prepared for:

HILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF. Prepared for: HILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF Prepared for: Bona Building & Management Co. Ltd. Place Vanier, 333 North River Road Vanier, Ontario K1L 8B9 October

More information

Joshua Jester, E.I., Florida Department of Transportation, District One

Joshua Jester, E.I., Florida Department of Transportation, District One MEMORANDUM To: From: Joshua Jester, E.I., Florida Department of Transportation, District One Michael Garau, P.E., Kimley-Horn and Associates, Inc. Date: October 5, 2018 Subject: at Gulfstream Avenue Intersection

More information

TRAFFIC IMPACT ANALYSIS

TRAFFIC IMPACT ANALYSIS TRAFFIC IMPACT ANALYSIS FOR THE CHAMPAIGN UNIT#4 SCHOOL DISTRICT PROPOSED HIGH SCHOOL (SPALDING PARK SITE) IN THE CITY OF CHAMPAIGN Final Report Champaign Urbana Urbanized Area Transportation Study 6/24/2014

More information

City of Seattle Edward B. Murray, Mayor

City of Seattle Edward B. Murray, Mayor City of Seattle Edward B. Murray, Mayor Department of Transportation Scott Kubly, Director Eastlake Community Council 117 E Louisa St. #1 Seattle, WA 98102-3278 January 28, 2016 RE: Roosevelt to Downtown

More information

Maywood Town Hall Meeting. May 4, 2016

Maywood Town Hall Meeting. May 4, 2016 Maywood Town Hall Meeting May 4, 2016 1 AGENDA Overall I-290 Study Background Maywood Advisory Working Group (AWG) findings to date Noise Wall Update Next Steps 2 Questions? Study team members also available

More information

Brian McHugh, Buckhead Community Improvement District. SUBJECT: Wieuca Road at Phipps Boulevard Intersection Improvements Project

Brian McHugh, Buckhead Community Improvement District. SUBJECT: Wieuca Road at Phipps Boulevard Intersection Improvements Project MEMO TO: FROM: Brian McHugh, Buckhead Community Improvement District Jagan Kaja, AICP, WSP Parsons Brinckerhoff SUBJECT: Wieuca Road at Phipps Boulevard Intersection Improvements Project DATE: October

More information

HIGHBURY AVENUE/HAMILTON ROAD INTERSECTION IMPROVEMENTS PUBLIC INFORMATION CENTRE 1 MAY 14, 2015

HIGHBURY AVENUE/HAMILTON ROAD INTERSECTION IMPROVEMENTS PUBLIC INFORMATION CENTRE 1 MAY 14, 2015 HIGHBURY AVENUE/HAMILTON ROAD INTERSECTION IMPROVEMENTS Municipal Class Environmental Assessment PUBLIC INFORMATION CENTRE 1 MAY 14, 2015 ACCESSIBILITY Under the Accessibility Standards 2015 for Customer

More information

Plant City Walk-Bike Plan

Plant City Walk-Bike Plan Plant City Walk-Bike Plan Plant City Commute Mode Share 2.2% 1.4% 2.9% Drove alone 10.2% Carpooled Public transportation (0.1%) Walked Used a Bike (0.4%) 82.9% Taxicab, motorcycle, or other means Worked

More information

Albany Shaker Road Corridor Study Public Meeting # 2

Albany Shaker Road Corridor Study Public Meeting # 2 Albany Shaker Road Corridor Study Public Meeting # 2 Scope / Meeting Purpose This project is a CDTC Linkage Study. The Linkage Program is designed to implement the adopted planning and investment principles

More information

North Avenue Corridor Study

North Avenue Corridor Study North Avenue Corridor Study Advisory Committee Meeting #6 July 1, 2014 Agenda Concept Revisions based on Advisory Committee feedback Review of New Concept Scoring & Costs Concept Discussion/Questions Voting:

More information

Lawrence Avenue Streetscape Concepts August 30, 2011

Lawrence Avenue Streetscape Concepts August 30, 2011 Lawrence Avenue Streetscape Concepts August 30, 2011 Neighborhood Context Phase II: River to Western Ave. Phase I: Western Ave. to Clark St. Key Map Lawrence Ave. Existing Streetscape Conditions East of

More information

Public Information Centre

Public Information Centre WELCOME Public Information Centre Father Tobin Road Lougheed Middle School - Library Wednesday November 7, 2012 7:00 p.m.to 9:00 p.m. Please sign in Neighbourhood Traffic Calming Guide Background The City

More information

Gateway Transportation Study

Gateway Transportation Study Gateway Transportation Study Amherst, Massachusetts SUBMITTED TO University of Massachusetts Amherst Town of Amherst SUBMITTED BY Vanasse Hangen Brustlin, Inc. Watertown, Massachusetts March 213 Back of

More information

Fairfax County Parkway Widening Fairfax County

Fairfax County Parkway Widening Fairfax County Get Involved VDOT representatives will review and evaluate information received as a result of this meeting. Please fill out the comment sheet provided in this brochure if you have any comments or questions.

More information

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them?

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them? Overview Illinois Bike Summit IDOT Complete Streets Policy Presentation Aren Kriks, P.E. District One Bicycle Coordinator and Bureau of Programming Project Engineer History of Complete Streets IDOT Policy

More information

Designing for Pedestrian Safety

Designing for Pedestrian Safety Designing for Pedestrian Safety Introduction to Pedestrian Safety Design and Planning Principles Presented by: Craig Allred FHWA Resource Center Technical Specialist and Michael Ronkin Owner, Designing

More information

Northbound San Jose Avenue & I-280 Off-Ramp Road Diet Pilot Project

Northbound San Jose Avenue & I-280 Off-Ramp Road Diet Pilot Project Project Overview Fed by a two-lane Interstate-280 (I-280) off-ramp, high vehicular volumes and speeds are longstanding issues along San Jose Avenue. Residents in the surrounding neighborhoods have expressed

More information

THIS PAGE LEFT BLANK INTENTIONALLY

THIS PAGE LEFT BLANK INTENTIONALLY GA SR 25 Spur at Canal Road Transportation Impact Analysis PREPARED FOR GLYNN COUNTY, GEORGIA 1725 Reynolds Street, Suite 300 Brunswick, Georgia 31520 PREPARED BY 217 Arrowhead Boulevard Suite 26 Jonesboro,

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.3 DIVISION: Sustainable Streets Division BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Approving traffic and parking modifications to install

More information

CSAH 101 Preliminary Design

CSAH 101 Preliminary Design CSAH 101 Preliminary Design Public Open House No. 2 January 29, 2013 CSAH 62 to Hutchins Drive Welcome / Introductions Hennepin County Craig Twinem, Transportation Maury Hooper, Transportation Nick Peterson,

More information

Offset Single Point Interchange I-25 at Rio Bravo Boulevard Albuquerque, New Mexico

Offset Single Point Interchange I-25 at Rio Bravo Boulevard Albuquerque, New Mexico Offset Single Point Interchange I-25 at Rio Bravo Boulevard Albuquerque, New Mexico INSTITUTE OF TRANSPORTATION ENGINEERS 2016 WESTERN DISTRICT MEETING JULY 11, 2016 7/11/2016 1 Project Vicinity Map 7/11/2016

More information

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD INTERSECTION NEEDS AT SR 7 and OKEECHOBEE BOULEVARD SR 7 Extension Project Development and Environment (PD&E) Study From Okeechobee Boulevard (SR

More information

WELCOME. Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018

WELCOME. Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018 WELCOME Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018 MEETING AGENDA 1. Welcome and Introductions 2. Study Progress Update 3. Problem Statement 4. Technical Analysis

More information

Improving Cyclist Safety at the Dundas Street West and Sterling Road Intersection

Improving Cyclist Safety at the Dundas Street West and Sterling Road Intersection STAFF REPORT ACTION REQUIRED Improving Cyclist Safety at the Dundas Street West and Sterling Road Intersection Date: August 17, 2012 To: From: Wards: Reference Number: Public Works and Infrastructure Committee

More information

State Road 54/56 Tampa Bay s Northern Loop. The Managed Lane Solution Linking I-75 to the Suncoast Parkway

State Road 54/56 Tampa Bay s Northern Loop. The Managed Lane Solution Linking I-75 to the Suncoast Parkway State Road 54/56 Tampa Bay s Northern Loop The Managed Lane Solution Linking I-75 to the Suncoast Parkway SUNCOAST PARKWAY Both I 75 and the Suncoast Parkway are planning, or in the process of constructing,

More information

Traffic Study North Shore School District 112

Traffic Study North Shore School District 112 Traffic Study North Shore School District 112 Proposed Expansion of Northwood Junior High School Prepared By: May 1, 2015 1. Introduction Kenig, Lindgren, O Hara, Aboona, Inc. (KLOA, Inc.) has been retained

More information

Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation

Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation City of Hillsdale, Hillsdale County, Michigan June 16, 2016 Final Report Prepared for City of Hillsdale 97 North Broad

More information

This page intentionally left blank.

This page intentionally left blank. This page intentionally left blank. COMMUNITY Coweta Community Overview Coweta Coweta, a residential community located in Wagoner County, is a suburb of Tulsa situated southeast of the metropolitan area

More information

Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation

Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation APRIL 2016 A collaborative study between: For Additional Information or to Comment If you would like additional

More information

Washington St. Corridor Study

Washington St. Corridor Study FIGURE 7.17 Bridge Alternatives - Cross Sections 86 Discarded Alternative: Short-Term Bridge Repair Short-term repairs and west bridge span replacement were considered during analysis. Short-term repairs

More information

Foothill Expressway Improvements Between El Monte and San Antonio

Foothill Expressway Improvements Between El Monte and San Antonio Foothill Expressway Improvements Between El Monte and San Antonio June 29, 2017 - Los Altos Community Meeting Introduction Project Background Agenda Visit Stations: Provide Input and Ask Questions Reconvene:

More information

Date: April 4, Project #: Re: A Street/Binford Street Traffic/Intersection Assessment

Date: April 4, Project #: Re: A Street/Binford Street Traffic/Intersection Assessment To: Peter Cavanaugh General Electric From: David Bohn, PE Ryan White, PE Date: April 4, 217 Project #: 13421. Re: / Traffic/Intersection Assessment Consistent with the Cooperation Agreement between the

More information

INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED. Prepared for: Canada Inc.

INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED. Prepared for: Canada Inc. INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED Prepared for: 7849648 Canada Inc. Octiober 1, 2015 114-598 Overview_2.doc D. J. Halpenny & Associates Ltd. Consulting

More information

Newport City Thoroughfare Plan

Newport City Thoroughfare Plan Newport City Thoroughfare Plan Summary This plan is intended to review and make recommendations for Newport City s thoroughfare network, in consideration of the full range of uses of the city s streets.

More information

FY 2017 FY 2021 PRIORITY PROJECT LIST ADOPTION. June 26, 2015

FY 2017 FY 2021 PRIORITY PROJECT LIST ADOPTION. June 26, 2015 FY 2017 FY 2021 PRIORITY PROJECT LIST ADOPTION June 26, 2015 s (PPLs) RMP Roadways PPL RMP Bicycle and Pedestrian PPL RMP Strategic Intermodal System (SIS) PPL Transportation Systems Management (TSM) PPL

More information

2. NORTEL CARLING CAMPUS EXPANSION - PROPOSED MODIFICATIONS TO MOODIE DRIVE (REGIONAL ROAD 59) AND HIGHWAY 417 INTERCHANGE

2. NORTEL CARLING CAMPUS EXPANSION - PROPOSED MODIFICATIONS TO MOODIE DRIVE (REGIONAL ROAD 59) AND HIGHWAY 417 INTERCHANGE 2. NORTEL CARLING CAMPUS EXPANSION - PROPOSED MODIFICATIONS TO MOODIE DRIVE (REGIONAL ROAD 59) AND HIGHWAY 417 INTERCHANGE COMMITTEE RECOMMENDATIONS AS AMENDED That Council approve: 1. The endorsement

More information

PROJECT OVERVIEW. 20th Avenue Project Limits (Lincoln Way to Wawona St)

PROJECT OVERVIEW. 20th Avenue Project Limits (Lincoln Way to Wawona St) PROJECT OVERVIEW In 2014, San Francisco adopted Vision Zero as City policy, with a commitment to eliminate all traffic deaths in the City by 2024. nue Project Limits (Lincoln Way to St) Collision data

More information

Everyone is a Pedestrian

Everyone is a Pedestrian Everyone is a Pedestrian Improving Pedestrian Safety in Texas Transportation and Trinity River Project Committee 26 May 2015 Everyone is a Pedestrian Federal Highway Administration [ FHWA ] Programs to

More information

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY A1 Roadway Resurfacing $23,846,000 TYPE: Preservation of existing system Roadway resurfacing A2 Signal Replacement $6,000,000 TYPE: Preservation of existing system Replace traffic signals. B1 W 6th St

More information

CITY OF SLO SEEKS INPUT ON PREFERRED ALTERNATIVE FOR BROAD STREET BICYCLE BOULEVARD PROJECT

CITY OF SLO SEEKS INPUT ON PREFERRED ALTERNATIVE FOR BROAD STREET BICYCLE BOULEVARD PROJECT City of San Luis Obispo, News Release DATE: August 1, 2017 RELEASE: Immediate CONTACT: Luke Schwartz (805) 781-7190 Transportation Planner-Engineer, Public Works CITY OF SLO SEEKS INPUT ON PREFERRED ALTERNATIVE

More information

Transportation Planning Division

Transportation Planning Division Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meetings Data Collected Focus Areas within Study Limits Design Principles Tool Box Recommended Concepts Schedule Moving

More information

Commercial-Vista Corridor Plan Project Management Team. Judith Johnduff, AICP, Associate Transportation Planner Public Works Department

Commercial-Vista Corridor Plan Project Management Team. Judith Johnduff, AICP, Associate Transportation Planner Public Works Department MEMO TO: Commercial-Vista Corridor Plan Project Management Team FROM: DATE: June 1, 2015 Judith Johnduff, AICP, Associate Transportation Planner Public Works Department SUBJECT: Public Events #2 - Summary

More information

AGENDA REQUEST. Unfinished Business BY Neighborhood and Development Services. November 1, 2010 SUBJECT:

AGENDA REQUEST. Unfinished Business BY Neighborhood and Development Services. November 1, 2010 SUBJECT: AGENDA REQUEST AGENDA HEADING: Unfinished Business BY Neighborhood and Development Services Originating Department COMMISSION MEETING DATE: November 1, 2010 Timothy Litchet Department Head AGENDA ITEM

More information

Colchester/Riverside/Barrett/ Mill Intersection Study. PAC Meeting #3 September 22, 2016

Colchester/Riverside/Barrett/ Mill Intersection Study. PAC Meeting #3 September 22, 2016 Colchester/Riverside/Barrett/ Mill Intersection Study PAC Meeting #3 September 22, 2016 Tonight s Agenda Review Project Purpose and Need Describe short term and long improvements and changes since public

More information

Monterey Road Complete Streets

Monterey Road Complete Streets Monterey Road Complete Streets Complete Street Objectives Improve livability and economic vitality Enhance pedestrian environment Accommodate bicyclists safely Reduce noise and air pollution Create attractive,

More information

CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY

CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY RMA-2015-ATM-038 CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY DATE: April 22, 2015 SUBJECT Approval of Roadway Modifications Recommended through an Area Traffic Management Study

More information

INTERSECTION CONTROL NOVEMBER 2018

INTERSECTION CONTROL NOVEMBER 2018 INTERSECTION CONTROL NOVEMBER 2018 ICE OVERVIEW AGENDA Why ICE? When ICE is Required? Applicability and Process 2 AVAILABLE RESOURCES http://www.fdot.gov/traffic/trafficservices/intersection_operations.shtm

More information

MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. Prepared for:

MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. Prepared for: MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW Prepared for: 2434984 Ontario Inc. 13-5510 Canotek Road Ottawa, Ontario K1J 9J5 June 4, 2015 115-613 Report_2.doc D. J.

More information

Lake Whitney Elementary School

Lake Whitney Elementary School Lake Whitney Elementary School SCHOOL ROUTE PLAN For LAKE WHITNEY ELEMENTARY SCHOOL LOCATION 18 ORANGE COUNTY Prepared for: ORANGE COUNTY SCHOOL ASSESSMENT PROGRAM ORANGE COUNTY PUBLIC WORKS Traffic Engineering

More information

Eliminate on-street parking where it will allow for a dedicated bus only lane %

Eliminate on-street parking where it will allow for a dedicated bus only lane % Traffic Dashboard Priorities Survey Responses Introduction 1) Are you familiar with bus rapid transit (BRT)? a. No, BRT is new to me. 597 23.5% b. I ve heard of BRT, but I don t know much about it. 1,136