1 For release: Immediately Page: 1 of 5 Date: April 2, 2012 Ref #: Media contacts: Karon Trenaman, ICBC invests $738,000 to make Surrey, White Rock and Delta roads safer You ve likely driven by 168 th Street and 48 th Avenue in Surrey and noticed the improvements to Nicomekl Bridge including corridor and intersection improvements, road widening and alignment. This is one of the road improvements ICBC invested in last year to help make Surrey, White Rock and Delta safer for everyone. ICBC launched the road improvement program in 1989, and since then, has invested over $100 million in projects across B.C. In 2011, ICBC invested approximately $4 million in projects in the Lower Mainland and $6.5 million in 283 projects across the province. We care about people s wellbeing and are always looking for new ways to create safer roads, said Fiona Temple, ICBC s director of road safety. That s why we work with communities to identify high-crash areas and make improvements that benefit everyone drivers, cyclists and pedestrians. Simply put, safer drivers and roads mean fewer crashes, injuries and deaths. The most recent evaluation of the program found that two years following a project s implementation, there is on average, a 20 per cent reduction in severe crashes and a 12 per cent reduction in property damage crashes. The evaluation concluded that for every dollar invested in a project, ICBC and customers save $5.60 over two years and $12.80 over five years in reduced claims costs. Keeping drivers, pedestrians, cyclists and everyone else safe on our roads, is a priority of the province and of ICBC, said Dave Hayer, Surrey-Tynehead MLA. The recent investments in Surrey are just another example of the importance ICBC puts on road safety. Investing in road improvements, along with educating drivers through awareness campaigns and funding enhanced police enforcement, are all part of ICBC s commitment to help make B.C. roads safer. Over the last 22 years, ICBC s road improvement program has evolved significantly community investments and successful partnerships have led to award winning projects and the contributions have helped advance the knowledge of the road safety engineering industry in B.C. and across Canada. A look at the evolution of ICBC s road improvement program can be viewed here. All proposed road improvement projects are assessed based on their ability to make roads safer. ICBC works in partnership with municipalities and the provincial government on delivering road enhancements. ICBC also participates in engineering studies and assists communities with road safety issues in the planning of roadways and managing traffic. Road improvement projects completed in 2011 in Surrey: Location: 108 th Avenue and 162 nd Street o Project description: Pedestrian signal installation o ICBC contribution: $9,000
2 Page 2 Location: 168 th Street and 48 th Avenue (Nicomekl Bridge) o Project description: Corridor and intersection improvements, road widening, alignment, road widening, alignment o ICBC contribution: $37,000 Location: 152 nd Street (10300 Block to 104 th Avenue) o Project description: Corridor and intersection improvements, widening to add third Southbound lane o ICBC contribution: $25,000 Location: King George Boulevard and 88 th Avenue o Project description: Left-turn lane extension and improvements o ICBC contribution: $36,000 Location: 64 th Avenue and 134 th Street o Project description: Traffic signal installation o ICBC contribution: $84,500 Location: area-wide at 39 locations o Project description: Signal visibility upgrade Location: King George Boulevard (60 th Avenue to 84 th Avenue) o Project description: Signal timing coordination Location: Scott Road (64 th Avenue to 84 th Avenue) Location: Fraser Highway (184 th Avenue to 188 th Avenue)
3 Page 3 Location: 152 nd Street (91 st Street to 105 th Avenue) Location: 16 th Avenue (King George Boulevard to 148 th Street) o ICBC contribution: $12,000 Location: area wide at 110 locations o Project description: Countdown timers installed o ICBC contribution: $85,000 Location: 152 nd Street and 56A Avenue o Project description: Median installation o ICBC contribution: $36,000 Location: Highway 15 at 68A Avenue o Project description: Intersection improvements, advance warning flasher o ICBC contribution: $9,600 Location: Highway 15 at 88 th Avenue o Project description: Intersection improvements, Westbound protected left turn signal o ICBC contribution: $6,200 Location: Highway 15 at 16 th Avenue o Project description: Intersection improvements, Westbound permissive left turn o ICBC contribution: $11,200 Location: 60 th Avenue and 142 nd Street o Project description: Intersection improvements, crosswalk installation, overhead flashing beacon
4 Page 4 Location: 16 th Avenue and 136 th Street o Project description: Signal installation Location: Highway 15 and 88 th Avenue o Project description: Protected left turn signal o ICBC contribution: $10,200 Location: Fraser Highway Corridor (Whalley Boulevard to 64 th Avenue) and uninterrupted power supply installation o ICBC contribution: $79,440 Location: 64 th Avenue Corridor (128 th Street to Fraser Highway) and uninterrupted power supply installation o ICBC contribution: $74,000 Road improvement projects completed in 2011 in White Rock: Location: Marine Drive and Magdalen Crescent o Project description: Pedestrian and intersection improvements, signage, realignment, channelized islands o ICBC contribution: $5,000 Location: North Bluff Road Johnston Road to Martin Street o Project description: Corridor improvements, remove bus bays o ICBC contribution: $24,000 Location: North Bluff Road (George Street to Stayte Road) o Project description: Corridor improvements, remove hydro poles o ICBC contribution: $20,000
5 Page 5 Road improvement projects completed in 2011 in Delta: Location: 116 th Street and 4 intersections o Project description: Signal head visibility upgrade o ICBC contribution: $11,000 Location: Ladner Trunk Road and 62 nd Street o Project description: signal installation, Northbound left-turn arrow o ICBC contribution: $11,000 Location: 112 th Street and 84 th Avenue o Project description: Uninterrupted power supply installation o ICBC contribution: $2,500 Location: 56 th Street and 1 st Avenue o Project description: Traffic signal installation o ICBC contribution: $9,000 Location: 64 th Avenue (Scott Road to Wade Road) o Project description: Traffic signal coordination o ICBC contribution: $6,000 Location: 72 nd Avenue (Scott Road to Nicholson Road) o Project description: Traffic signal coordination o ICBC contribution: $4,000 Location: 84 th Avenue and 110 th Street o Project description: Pedestrian safety improvements, upgrade crosswalk, signs, pavement markings o ICBC contribution: $2,000 Location: 92A Avenue and 112 th Street o Project description: Intersection safety improvements, pavement markings o ICBC contribution: $7,
ICBC invests $1.175 million to help make Surrey, Delta and White Rock s roads safer in 2013
Date: March 18, 2014 Page: 1 of 8 Media contacts: Michelle Hargrave, 250-979-4642 Lindsay Olsen, 604-982-4759 ICBC invests $1.175 million to help make Surrey, Delta and White Rock s roads safer in 2013
More informationDate: February 18, 2015 Page: 1 of 9. ICBC invests $1.195 million to improve Surrey, Delta & White Rock roads
News release Date: February 18, 2015 Page: 1 of 9 Media contacts: Lindsay Olsen, 604-982-4759 ICBC invests $1.195 million to improve Surrey, Delta & White Rock roads You may have noticed the new pedestrian
More informationDate: February 18, 2015 Page: 1 of 5. ICBC invests $391,000 to improve Tri-Cities roads
News release Date: February 18, 2015 Page: 1 of 5 Media contacts: Lindsay Olsen, 604-982-4759 ICBC invests $391,000 to improve Tri-Cities roads You may have noticed the new sidewalks, pedestrian signals
More informationDate: February 18, 2015 Page: 1 of 5. ICBC invests $714,000 to improve Greater Victoria roads
News release Date: February 18, 2015 Page: 1 of 5 Media contacts: Tamara McLean, 250-414-7883 ICBC invests $714,000 to improve Greater Victoria roads You may have noticed the new sidewalks, pedestrian
More information72 Avenue Four Laning (BNSF Overpass to 120 Street) WELCOME. Public Information Meeting
72 Avenue Four Laning (BNSF Overpass to 120 Street) WELCOME Public Information Meeting Project Goals About the Project The goal of this project is to address congestion along 72 Avenue and adjacent streets
More informationPattullo Bridge Replacement Project Community Connections Phase 2 Consultation. Appendix 3: Open House Display Boards
Replacement Project Community Connections Phase 2 Consultation Appendix 3: Open House Display Boards November 2016 Welcome! Welcome to the Replacement Project Public Open House We Want to Hear from You
More informationEMPHASIS AREA 1: PEDESTRIANS
EMPHASIS AREA 1: PEDESTRIANS A pedestrian is seriously injured or killed every 3 days on Toronto s roads. Pedestrian collisions involve any person that is not riding in a vehicle or on a bicycle. 26% OF
More informationFreeway ramp intersection study
Freeway ramp intersection study Supporting Vision Zero: Zero traffic deaths in San Francisco by 2024 Study Goals: Primary Improve Safety Improve Accessibility Secondary Provide Efficient Circulation Accommodate
More informationDEPARTMENT OF ENVIRONMENTAL SERVICES. North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis. Prepared for:
DEPARTMENT OF ENVIRONMENTAL SERVICES North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis Prepared for: Arlington County Department of Environmental Services 2100 Clarendon Boulevard,
More informationMandan Commission Meeting August 2, 2016 Mandan City Hall
Mandan-Bismarck Corridor Improvement Study Mandan Commission Meeting August 2, 2016 Mandan City Hall 2014 HDR, Inc., all rights reserved. Mandan Corridors Study Schedule 2015 2016 Study Kick Off August
More informationCARE AND VIGILANCE SAVE LIVES!
CARE AND VIGILANCE SAVE LIVES! PEDESTRIAN, Be Safety Conscious! Each day, approximately ten pedestrians are involved in traffic accidents throughout Québec. If you use the province s road network on foot,
More informationCaptain Cook Elementary. Action Details Start Complete Notes
City of Vancouver Complete School Travel Plan Report Crosswalk improvements on E 55 th Avenue Track progress and collect all relevant ATP information into a School Travel Plan submitted to Captain Cook,
More informationMeeting Schedule 7:00-7:15 Open House 7:15-7:45 Existing Conditions/Short-Term Improvements Study Presentation 7:45-8:00 Q&A Session 8:00-8:10
Meeting Schedule 7:00-7:15 Open House 7:15-7:45 Existing Conditions/Short-Term Improvements Study Presentation 7:45-8:00 Q&A Session 8:00-8:10 Long-Term Study Presentation 8:10-8:40 Table Discussions 8:40-9:00
More informationFrom Mile Zero to Target Zero the Dawson Creek Case Study
From Mile Zero to Target Zero the Dawson Creek Case Study Raheem Dilgir, President, TranSafe Consulting Ltd. and Kevin Henderson, Manager of Planning and Development, City of Dawson Creek Paper prepared
More informationChicago Safe Routes to School Safe Routes to High School (SRTS/SRTHS)
Chicago Safe Routes to School Safe Routes to High School (SRTS/SRTHS) Marshall Community High School and Faraday Elementary School Recommended Improvements Agenda Goals Related Programs Project Location/Area
More informationCommittee of the Whole Report For the Meeting of October 6, 2016
CITY OF VICTORIA For the Meeting of October 6, 2016 To: Committee of the Whole Date: September 29,2016 From: Subject: Fraser Work, Director of Engineering and Public Works RECOMMENDATION That Council direct
More informationDr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018
Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 What s Happening The City plans to mill and resurface Dr. M.L.
More informationTransportation Planning Division
Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meetings Data Collected Focus Areas within Study Limits Design Principles Tool Box Recommended Concepts Schedule Moving
More informationDraft North Industrial Area-Wide Traffic Plan
Summary of North Industrial and Hudson Bay Industrial Recommended Improvements Table 1. Summary of s Item Location 1 2 3 4 5 6 7 8 9 10 11 12 Millar Ave north of 51st St Super 8 Motel back lane 400 Block
More informationEl Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018
El Camino Real Specific Plan TAC/CAC Meeting #2 Aug 1, 2018 Land Use Alternatives Goals and Tradeoffs Parks & open space Housing Retail & services Civic spaces Parking Community gathering spaces 3 Alternatives
More informationCity of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE
Welcome Welcome to the third community meeting for the Issaquah-Fall City Road Improvements Project. AGENDA 6:00 p.m. Welcome and sign-in 6:10 p.m. Presentation 6:50 p.m. Open house Learn about the roadway
More information1 To provide direction to Administration when determining the appropriate Pedestrian Crossing Control Device for a particular location.
Purpose: 1 To provide direction to Administration when determining the appropriate Pedestrian Crossing Control Device for a particular location. Policy Statement(s): 2 The City installs Pedestrian Crossing
More informationCAPITOL DRIVE & FOND DU LAC AVENUE INTERSECTION ANALYSIS. Urban Planning 772 SARAH BREGANT, RYAN PETERSON, & MATT WERDERITCH
CAPITOL DRIVE & FOND DU LAC AVENUE INTERSECTION ANALYSIS Urban Planning 772 SARAH BREGANT, RYAN PETERSON, & MATT WERDERITCH OVERVIEW N 51 ST BOULEVARD N 51 ST BOULEVARD 12,100 44,700 W CAPITOL DRIVE 52,600
More informationSaskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening
Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening We are here today to present the draft plan for the Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening project
More informationPEDESTRIAN ACTION PLAN
ATTACHMENT 2 CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN This page intentionally left blank EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY Setting the Stage
More informationCincinnati Dayton Rd Widening
Cincinnati Dayton Rd Widening Project Overview Widening of Cincinnati Dayton Rd to four lanes - providing a center turn lane and an additional northbound lane Realignment of Station Rd Widening of bridge
More informationCOMMUNITY MEETING AGENDA
COMMUNITY MEETING AGENDA Welcome and Introductions SAFE Presentation Project Presentation Priorities Feedback Next Steps Q&A Santa Cruz Avenue Corridor Study 1 Santa Cruz Avenue Corridor Study Community
More informationTraffic Safety Advisory Committee - Proposed 2015 Initiatives
City of Richmond Report to Committee To: Public Works and Transportation Committee Date: December 23,2014 From: Victor Wei, P. Eng. File: 01-0100-30-TSAD1- Director, Transportation 01/2014-Vo101 Re: Traffic
More informationNorth Shore Transportation Improvement Strategy
North Shore Transportation Improvement Strategy Preliminary, Near-term Recommendation 2016 April Transportation Improvement Strategy (TIS) Comprehensive and Analytical A multi-modal transportation strategy
More informationCITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY
RMA-2015-ATM-038 CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY DATE: April 22, 2015 SUBJECT Approval of Roadway Modifications Recommended through an Area Traffic Management Study
More informationFrequently Asked Questions
Frequently Asked Questions Business US 190 in Copperas Cove From Avenue D to Constitution Drive What is access management? A. Access Management is a growing effort by government agencies to improve how
More informationF L E T C H E R A V E N U E
Jan. 29, 2014 Introduction F L E T C H E R A V E N U E FDOT Local Agency Program (LAP) Project FPN: 428214-1-58-01 CIP 63090 Hillsborough County, Traffic Engineering, PWD Stake holders and partners are
More informationSan Francisco s Capital Plan & the Mayor s Transportation Task Force 2030: Funding the next steps for transportation
San Francisco s Capital Plan & the Mayor s Transportation Task Force 2030: Funding the next steps for transportation San Francisco Capital Needs In 2006, the Mayor and Board of Supervisors approved San
More informationRiver Road - Proposed Road Safety Enhancement Measures
City of Richmond Report to Committee To: From: Re: Public Works and Transportation Committee Victor Wei, P. Eng. Director, Transportation Date: June 6, 2017 River Road - Proposed Road Safety Enhancement
More informationTraffic Control Inspection Checklist Segment:
Traffic Control Inspection Checklist Segment: Simon Contractors Simon Contractors Originator: Description Reviewed by: Initials Date Distribution: Traffic Quality Manager, Site Assistant Traffic Manager
More informationPedestrian Road Safety Audit
Pedestrian Road Safety Audit Middlebrook Road From Father Hurley Boulevard to Waring Station Road December 2017 Montgomery County Department of Transportation Table of Contents 1. Introduction... 1 1.1
More informationWelcome to the Quebec Alternatives Analysis Public Meeting
Welcome to the Public Meeting Please sign in. Public Comment Please fill out a comment card and tell us what you think. Check back or comment any time at: www.quebecalternatives.com Project Area Technical
More informationCRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN
CRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN Preferred Plan Community Presentation September 27, 2017 City of El Paso de Robles in partnership with: Local Government Commission, W-Trans,
More informationPOLICY: TRAFFIC CALMING
2006 MAY REFERENCE: COUNCIL APPROVED BY COUNCIL MAY 23, 2006 CITY OPERATIONS - NO. 608 POLICY: TRAFFIC CALMING A. All requests for traffic calming within the City shall be considered in accordance with
More informationTraffic Safety Plan Second Avenue
Traffic Safety Plan Second Avenue April 2017 City of Greater Sudbury Roads & Transportation Services Division Overview Overview... 2 1.0 Project Overview... 4 2.0 Pedestrian Safety... 4 2.1 Current Infrastructure...
More informationTraffic Signal Phasing Study Summary & Staff Recommendations
Traffic Signal Phasing Study Summary & Staff Recommendations Consultant Study by Skipper Consulting, Inc. Staff Committee Recommendations by Randy Pewitt, Executive Director of Emergency Mgt. and Safety
More informationStakeholder Consultation Survey Proposed Cycle Options on Napa Valley Avenue
Stakeholder Consultation Survey Proposed Cycle Options on Napa Valley Avenue 1. Are you a resident of Vaughan? Information about the way you travel 2. Do you live or work in the Napa Valley Avenue area
More informationRoad Improvement Demonstration Program. Robert G. Lariviere, P.E. AAA Michigan Traffic Engineer
Road Improvement Demonstration Program Robert G. Lariviere, P.E. AAA Michigan Traffic Engineer What is the AAA Road Improvement Demonstration Program? A public/private partnership designed to enhance traffic
More informationDOT Policy and Procedure Integrity Excellence Respect
DOT Policy and Procedure 05.05.020 Integrity Excellence Respect Alaska s Speed Limit Policy Contained in DOT Policy and Procedure (P&P) 05.05.020, Establishment of Speed Limits and Zones Incorporates pertinent
More informationFEDERAL HIGHWAY ADMINISTRATION APPLICATION
FEDERAL HIGHWAY ADMINISTRATION APPLICATION REQUEST FOR PERMISSION TO EXPERIMENT WITH A BICYCLE BOX INTERSECTION TREATMENT Submitted by: City of Columbus Department of Public Service Date: June 26, 2009
More informationHighway 1 Kamloops to Alberta Four-Laning Program
Highway 1 Kamloops to Alberta Four-Laning Program COMMUNITY ENGAGEMENT DISCUSSION GUIDE AND FEEDBACK FORM February 7 March 1, 2013 www.bchwy1.ca 1 FEEDBACK FORM INSIDE HOW INPUT WILL BE CONSIDERED FAST
More information2011 Capital Projects University Area - Community Council Priority List Municipality of Anchorage
2011 Capital Projects University Area - Community Council Priority List Municipality of Anchorage 2 Project Management and Engineering Projects on 40th Ave Extension - Lake Otis Pkwy to Dale St $18,103,000
More informationCorporate. Report COUNCIL DATE: June 26, 2006 NO: C012 COUNCIL-IN-COMMITTEE. TO: Mayor & Council DATE: June 22, 2006
Corporate NO: C012 Report COUNCIL DATE: June 26, 2006 COUNCIL-IN-COMMITTEE TO: Mayor & Council DATE: June 22, 2006 FROM: General Manager, Engineering FILE: 0410-20(MoT/Gate) SUBJECT: Surrey Response on
More informationCTDOT Pedestrian and Bicycle Safety Initiatives
CTDOT Pedestrian and Bicycle Safety Initiatives 2017 Northeast Transportation Safety Conference Mark F. Carlino, P.E. Traffic Engineering Division Chief Bureau of Engineering and Construction Connecticut
More information133 rd Street and 132 nd /Hemlock Street 132 nd Street and Foster Street MINI ROUNDABOUTS. Overland Park, Kansas
133 rd Street and 132 nd /Hemlock Street 132 nd Street and Foster Street MINI ROUNDABOUTS Overland Park, Kansas September 1, 2017 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. LITERATURE REVIEW... 1 3. CONCEPT
More informationREDUCING COLLISIONS AT HIGH CRASH LOCATIONS
REDUCING COLLISIONS AT HIGH CRASH LOCATIONS Presented by Nazir Lalani P.E. Traffex Engineers Inc. N_lalani@hotmail.com ACCIDENTS AND SAFETY Why is safety important? Safety components Who is responsible?
More informationEMPHASIS AREA 2: SCHOOL CHILDREN
EMPHASIS AREA 2: SCHOOL CHILDREN A child is seriously injured or killed every 17 weeks on their way to or from school on Toronto s roads. School children are pedestrians and cyclists between the ages of
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 10.2 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Approving various parking and traffic modifications on Herbst Road
More informationHuntington Station Metro Zone / North Kings Highway Concept Plan
Summary Narrative of Huntington Station Metro Zone / North Kings Highway Concept Plan Located in Fairfax County, Virginia prepared for A.J. Dwoskin & Associates, Inc.. 9302 Lee Highway, Suite 300 Fairfax,
More informationToolbox of Countermeasures and Their Potential Effectiveness to Make Intersections Safer
8 Toolbox of Countermeasures and Their to Make Intersections Safer Introduction Studies included in the NCHRP 17-18 (3), Guidance for Implementation of the AASHTO Strategic Highway Safety Plan, as well
More informationExisting Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer
Date: April 16 th, 2015 To: From: Re: Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Darian Nagle-Gamm, Traffic Engineering Planner Highway 6 (2 nd Street) /
More informationHennepin County Transportation Department
Hennepin County Transportation Department Complete Streets Design and Implementation Prepared for the Complete Streets Task Force Craig Twinem, P.E. Design Division Manager Tom Johnson, P.E. Transportation
More informationTonight is for you. Learn everything you can. Share all your ideas.
Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.
More information» Draft Recommendations» Discussion» Next Steps. Plan for Walking and Biking
SAC Meeting Plan #3 for September Walking and 12, Biking 2018 » Draft Recommendations» Discussion» Next Steps Plan for Walking and Biking » Stakeholder and Public Outreach» Background data collection and
More informationImproving Cyclist Safety at the Dundas Street West and Sterling Road Intersection
STAFF REPORT ACTION REQUIRED Improving Cyclist Safety at the Dundas Street West and Sterling Road Intersection Date: August 17, 2012 To: From: Wards: Reference Number: Public Works and Infrastructure Committee
More informationMOBILITY WORKSHOP. Joint City Council and Transportation Commission May 5, 2014
MOBILITY WORKSHOP Joint City Council and Transportation Commission May 5, 2014 Review of General Plan M-1 Develop world-class transit system M-3 Maintain/enhance pedestrian-oriented City M-4 Create comprehensive
More information2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE
About the Project 2014/2015 BIKE ROUTE PLAN The City of Edmonton is planning a major bike route on the south side of Edmonton. This bike route is one part of a plan to provide citizens with transportation
More informationMayor s Bicycle Advisory Council. Wednesday, December 13 th, 2017
Mayor s Bicycle Advisory Council Wednesday, December 13 th, 2017 Bicyclist Fatalities, Year to Date (January 1 November 30, 2017) - MBAC Briefing Bicyclist Fatality Statistics Year to date total, 2017
More informationDOWNTOWN MIAMI PEDESTRIAN PRIORITY ZONE
DOWNTOWN MIAMI PEDESTRIAN PRIORITY ZONE AUGUST 6, 2013 DOWNTOWN MIAMI BY THE NUMBERS more than 200,000 people live, work, and play here every day is home to more than 1,000 events each year hosts more
More informationAddendum to SDDCTEA Pamphlet 55 17: Better Military Traffic Engineering Revision 1 Effective: 24 Aug Crosswalk Guidelines
Addendum to SDDCTEA Pamphlet 55 17: Better Military Traffic Engineering Revision 1 Effective: 24 Aug 2017 Crosswalk Guidelines Warrants for Uncontrolled Crosswalk Locations Crosswalks at Midblock Locations
More information01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS
01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS Existing Bus Stop Existing US101 On-ramp Existing POC Old Redwood Highway Rich Street City ROW Environmental Study Limit Industrial Way NO DESIGNATED
More informationFDOT Treasure Coast Traffic Impact Report April 7 through April 14, 2017
April 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report April 7 through April 14, 2017 TREASURE COAST Construction and maintenance related
More information5. RUNNINGWAY GUIDELINES
5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved
More informationPolk Streetscape Project
What is this project? The Polk Streetscape Project is an effort to improve safety for everyone traveling on Polk Street between Union and McAllister streets. Also included in this project are paving, sewer
More informationMARKHOUSE ROAD IMPROVEMENTS
MARKHOUSE ROAD IMPROVEMENTS www.enjoywalthamforest.co.uk Waltham Forest is changing and we want you to be part of it. Thanks to a funding pot of 27million from Transport for London, we re delivering the
More informationTransportation Planning Division
Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meeting Stakeholder Interviews Data Collection Design Principles Tool Box Recommendations Schedule Moving Forward North
More information2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE
About the Project The City of Edmonton is planning a major bike route on the southside of Edmonton. The Strathcona Bike Route will connect the communities of Strathcona, Garneau and the University area,
More informationEveryone is a Pedestrian
Everyone is a Pedestrian Improving Pedestrian Safety in Texas Transportation and Trinity River Project Committee 26 May 2015 Everyone is a Pedestrian Federal Highway Administration [ FHWA ] Programs to
More informationSPEED MANAGEMENT FOR VISION ZERO
SPEED MANAGEMENT FOR VISION ZERO LUANN HAMILTON, DEPUTY COMMISSIONER FOR PROJECT DEVELOPMENT CHICAGO DEPARTMENT OF TRANSPORTATION NACTO DESIGNING CITIES 2017 Vision Zero Action Plan Speed management and
More informationCity of Scotts Valley CITY COUNCIL STAFF REPORT
DATE: April 19, 2017 City of Scotts Valley CITY COUNCIL STAFF REPORT AGENDA ITEM 2 DATE: 4-19-2017 TO: FROM: APPROVED: SUBJECT: Honorable Mayor and City Council Scott Hamby, Public Works Director Jenny
More informationPotential Bicycle Facility on Bayou Street Mobile, Alabama
Potential Bicycle Facility on Bayou Street Mobile, Alabama By Richard A. Hall, P.E. Prepared For Mobile Downtown Alliance Hall Planning & Engineering, Inc. March 28, 2018 Introduction Review of the February
More informationCity Avenue Projects
City Avenue Projects City Avenue Special Services District Conceived in the early 1990 s Lita Cohen, Jim Ettelson, Joe Manko, and Michael Nutter Saint Joseph s provided key start-up support. True Public/Private
More informationRank #1 Highest Priority Intersection
Rank #1 Highest Priority Intersection Attachment 3: Proposed Interventions Pedestrian Safety City of Toronto s 10 Priority Intersections Sheppard Avenue East and Ambrose Road/Provost Drive Located in the
More informationAPPENDIX E Evaluation of Improvement Alternatives
APPENDIX E Evaluation of Improvement Alternatives Table E-1 Preliminary Comparison of Design Alternatives, Concord Table E-2 Preliminary Comparison of Route 2 Improvement Packages, Acton and Concord TABLE
More informationBay to Bay Boulevard Complete Streets Project
Bay to Bay Boulevard Complete Streets Project Dale Mabry Highway to Bayshore Boulevard February 08, 2018 Photo Source: Tampa Bay Times Alessandra Da Pra Meeting Format Introduction Resurfacing Information
More informationCITY OF SASKATOON COUNCIL POLICY
ORIGIN/AUTHORITY Clause 1, Report No. 1-1980 and Clause 4, Report No. 22-1990 of the Works and Utilities Committee; Clause 6, Report No. 17-2004 of the Planning and Operations Committee; and Clause D5,
More informationSan Francisco 2009 Collisions Report April 21, 2011
San Francisco 29 Collisions Report April 21, 211 City and County of San Francisco San Francisco Municipal Transportation Agency 1 South Van Ness Avenue, 7 th Floor San Francisco CA 9413 CONTENTS About
More informationParisi TRANSPORTATION CONSUtllHG
Attachment 1 To: Jonathan Goldman, P.E., QSD, CFM From: Cc: David Parisi, P.E., Curt Harrington, E.l.T. Andrew Davidson, P.E. Date: June 6, 2016 Subject: Bridgeway - Uncontrolled Crosswalk Tool and Location
More informationNortheast 65 th Street Vision Zero Project Proposals From A Roosevelt High School Student Joe Mangan
Northeast 65 th Street Vision Zero Project Proposals From A Roosevelt High School Student Joe Mangan PROPOSALS: 1. Extend raised cycle tracks down 65 th Street Northeast. Please do not consider any other
More informationPurpose: Financial Implications and Impact Statement: It is estimated that the cost to implement:
Various Modifications Lower Jarvis Street and Lake Shore Boulevard East; Lower Jarvis Street, east side, between Lake Shore Boulevard East and The Esplanade - 45-77 Lower Jarvis Street; and Lower Jarvis
More informationECONOMY PEOPLE ENVIRONMENT
Report Back on Local Transit Improvements May 29, 2013 ECONOMY PEOPLE ENVIRONMENT Intro Council Requested Report Back Topics Progress on Planning for Broadway Subway False Creek Bridges Local Transit Improvements
More information8 PROPOSED ROUNDABOUT DUFFERIN STREET AND KING VAUGHAN ROAD INTERSECTION CITY OF VAUGHAN
8 PROPOSED ROUNDABOUT DUFFERIN STREET AND KING VAUGHAN ROAD INTERSECTION CITY OF VAUGHAN The Transportation Services Committee recommends the adoption of the recommendation contained in the following report
More informationSummary: Mercer County Princeton Avenue & Spruce Street Study January 2009
Summary: Several recent studies have assessed potential development and redevelopment opportunities in the Mercer Crossing area of Trenton, Ewing, and Lawrence. This Princeton Avenue and Spruce Street
More informationRoad Safety Assessments. Lt. Bob McCurdy Williamson County Sheriff s s Office Marion, IL.
Road Safety Assessments Lt. Bob McCurdy Williamson County Sheriff s s Office Marion, IL. Why Are We Here? 2005 US Traffic Fatalities = 43,443 1429 4329 1361 1616 1534 3504 1729 3543 Illinois Annual Fatallities
More informationHillsborough Pedestrian Safety Action Plan 2015 Update. Hillsborough MPO BPAC May 2015
Hillsborough Pedestrian Safety Action Plan 2015 Update Hillsborough MPO BPAC May 2015 Presentation Overview Pedestrian Safety Action Plan (PSAP) Review Pedestrian Crash Trends Stakeholder Activities Engineering
More informationTraffic Safety Advisory Committee - Proposed 2016 Initiatives
City of Richmond Report to Committee To: Public Works and Transportation Committee Date: December 21, 2015 From: VictorWei, P. Eng. File: 01-0100-30-TSAD1- Director, Transportation 01/2015-Vol 01 Re: Traffic
More informationMPO Staff Report MPO Technical Advisory Committee: December 13, 2017 MPO Executive Board: December 20, 2017
MPO Staff Report MPO Technical Advisory Committee: December 13, 2017 MPO Executive Board: December 20, 2017 RECOMMENDED ACTION: Consider HSIP Candidate Projects for the FY2019-2022 TIP as Being Consistent
More information41st Avenue B-Line Kerrisdale Village Street Improvements
1. WELCOME! 41st Avenue B-Line Kerrisdale Village Improvements Public Open House Please sign in so we can provide updates and information on construction The City of Vancouver is working with TransLink
More informationCaltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns
Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns Revised: May 10, 2016 The California Department of Transportation (Caltrans) is planning various
More informationWELCOME. The following materials and resources are available to you:
WELCOME Welcome! Thank you for attending today s Southwest Rapid Transitway Stage 2 information session. The following materials and resources are available to you: A large-scale overview map, which offers
More informationINNOVATIVE INTERSECTION DESIGN
INNOVATIVE INTERSECTION DESIGN J. Eddie Valtier, P.E. ELP TP&D Director Introduction Why Do We Need To Start Looking For Innovative Intersection Designs? Congestion is worsening and traffic volumes and
More informationRoute 29 Solutions Projects
Route 29 Solutions Route 29 Solutions Projects www.route29solutions.org October 10, 2014 Route 29 Widening to Six Lanes Albemarle County This project will widen a 1.8-mile segment of Route 29 from four
More informationWelcome to the McKenzie Interchange Project Open House!
Welcome to the McKenzie Interchange Project Open House! Purpose of Open House To provide you with information regarding the project and for you to have the opportunity to share your input on design concepts.
More informationWHANGAREI IMPROVEMENTS
WHANGAREI IMPROVEMENTS PROJECT OVERVIEW The NZ Transport Agency (NZTA) is working with Whangarei District Council (WDC) to improve the state highway through Whangarei. In addition to the recently completed