MPO Staff Report MPO Technical Advisory Committee: December 13, 2017 MPO Executive Board: December 20, 2017

Size: px
Start display at page:

Download "MPO Staff Report MPO Technical Advisory Committee: December 13, 2017 MPO Executive Board: December 20, 2017"

Transcription

1 MPO Staff Report MPO Technical Advisory Committee: December 13, 2017 MPO Executive Board: December 20, 2017 RECOMMENDED ACTION: Consider HSIP Candidate Projects for the FY TIP as Being Consistent with the Long Range Transportation Plan and Give Priority Ranking Matter of HSIP Candidate Projects for TIP. Background: The MPO and NDDOT formally solicited candidate projects for the TIP/STIP. In order for the MPO to give both the local agencies as much time as possible yet still allow MPO staff to vet the candidate projects, the project submittal deadline to the MPO was December 6th. Two applications were submitted; both by the City of Grand Forks. The top priority application was to upgrade all the school crossing beacons in Grand Forks. The proposed project would upgrade all 22 beacons to allow more events to be programmed to adjust to the complicated school schedule. Additionally, the beacons would be upgraded to allow for pedestrians to activate rather than just relying on programmed events. The total cost estimate being in Year of Expenditure FY2022 is $730,000 with federal participation of $630,000. When reviewing the Local Road Safety Program (LRSP) document, these school beacons are not listed as a specific, prioritized project. However, not being explicitly listed does not prevent a project from being considered. In working with City Staff, the following prioritized strategies are identified as being consistent: LRSP under Table 3-9 Unsignalized Intersection Strategies (Infrastructure Strategies) both: A Reduce the frequency and severity of intersection conflicts through geometric design improvements. A4 Improve pedestrian and bicycle facilities to reduce conflicts between motorist and nonmotorists and C-Improve driver awareness of intersections as viewed from the intersection approach. C1- Improve visibility of intersections by providing enhanced signing, delineation or pavement markings/messages (stop bar, larger regulatory signs, LED stop signs, etc.) The second application is to implement some remaining recommendations from the 32 nd Ave S

2 Road Safety Review. This review created the award of the FY2019 HSIP project to modify left tern lanes along key intersections on 32 nd Ave S. This application address the intersection of S. 17 th St and 32 nd Ave S. The Review recommended to re-align left turn lanes and install pedestrian crosswalks if a signal is installed. The recommendations were not needed now and therefore were not included in the FY2019 project. The City is applying for HSIP funds to make these two improvements plus install the traffic signal. Upon further research and clarification from NDDOT, installing traffic signals are not eligible through HSIP funds. Due to the vast majority of the cost estimate is due to the traffic signals, the City staff did not desire to remove from the application the cost of the signals and just submit the two recommended items (which partially are dependent upon installation of traffic signal). Therefore the application is ineligible. These candidate projects are being processed with many unknown outcomes of FAST. It is very possible that significant changes may occur to these projects as more information and decisions are made through implementation of FAST. In short, any action of these projects is subject to change. A separate staff report was released for the ND TA Program. The Urban Roads Program, both the Regional Roads and Local Urban Roads, are yet to formally be solicited. In part, the proposed NDDOT Main Street Initiative may significantly impact the Program. A separate staff report was released to provide an update on this item. Findings and Analysis: The MPO must annually prepare a Transportation Improvement Program TIP eligible projects with the MPO Area must be submitted to the MPO for its consideration The projects submitted are being considered as being consistent with the Long Range Transportation Plan (via the LRSP) with the understanding that as FAST is implemented this determination is subject to change. One project should be given high priority ranking; the other project is ineligible. Support Materials: Pages from LRSP Applications

3 ND INFRASTRUCTURE & DRIVER BEHAVIOR PHASE 2 Grand Forks Grand Forks June 2014 North Dakota Local Road Safety Program TBG SEA

4 LOCAL ROAD SAFETY PROGRAM JUNE 2014 CHAPTER 3: GRAND FORKS REGION PRIORITY SAFETY STRATEGIES TABLE 3-9 Unsignalized Intersection Strategies (Infrastructure Strategies) Objectives Strategies Effectiveness A Reduce the frequency and severity of intersection conflicts through geometric design improvements B Improve sight distance at unsignalized intersections C Improve driver awareness of intersections as viewed from the intersection approach D Appropriate intersection traffic control to minimize crash frequency and severity A1 Provide left-turn lanes at intersections A2 Provide offset turn lanes at intersections A3 Realign intersection approaches to reduce or eliminate intersection skew A4 Improve pedestrian and bicycle facilities to reduce conflicts between motorists and nonmotorists A5 Use indirect left-turn treatments to minimize conflicts at divided highway intersections B1 Clear sight triangle on approaches and in medians by clearing grub, eliminating parking, etc Cost to Implement and Operate 1 Timeframe for Implementation 2 Tried Moderate Medium Proven Moderate Medium Tried Moderate to High Medium Proven High Medium Varies Moderate Medium Tried Moderate Medium C1 Improve visibility of intersections by providing enhanced signing, delineation or pavement markings/messages (stop bar, Tried Low Short larger regulatory signs, LED stop signs, etc) C2 Improve visibility of intersections by providing appropriate street lighting Tried Low Short C3 Install larger regulatory and warning signs at intersections, including the use of dynamic warning signs at appropriate intersections Proven Low to Moderate Medium C4 Call attention to the intersection by installing rumble strips or splitter islands on intersection approaches Tried Low Short D1 Construct roundabouts at appropriate locations Notes: 1 Cost: Low = <$50,000 per intersection; Moderate = $50,000 to $500,000 per intersection; High = >$500,000 per intersection 2 Implementation: Short = <1 year; Medium = 1 to 2 years; Long = >2 years Source: NCHRP Report 500 Series, 2003 Tried Low to Moderate Medium TBG MSP USC 409: NDDOT Reserves All Objections

5 LOCAL ROAD SAFETY PROGRAM JUNE 2014 CHAPTER 4: GRAND FORKS INFRASTRUCTURE SAFETY PROJECTS FIGURE 4-10 City of Grand Forks Projects Location Map Roadway Segments and Pedestrian and Bicycle Projects TBG MSP USC 409: NDDOT Reserves All Objections

6 LOCAL ROAD SAFETY PROGRAM JUNE 2014 CHAPTER 4: GRAND FORKS INFRASTRUCTURE SAFETY PROJECTS FIGURE 4-11 City of Grand Forks Projects Location Map Right Angle Intersection Projects TBG MSP USC 409: NDDOT Reserves All Objections

7

8

9 PROJECT LOCATION MAP GRAND FORKS, NORTH DAKOTA Flashing Beacon Upgrade SCHOOL FLASHING BEACON LOCATIONS NO. 48th ST. 17th AVE. NO. INTERSTATE 29 NO. 42nd ST. 27th AVE. NO. NORTH COLUMBIA ROAD SCHOOL LOCATIONS NO. 69th ST. U. S. HIGHWAY NO. 2 12th AVE. NO. NO. 55th ST. 6th AVE. NO. UNIVERSITY AVE. GATEWAY DRIVE 25th ST. NO. U.S. HIGHWAY NO. 81 STATE MILL ROADNO. 3RD ST. 6th AVE. NO. UNIVERSITY AVE. NO. 4TH ST. NO. 5TH ST. DEMERS AVENUE DEMERS AVENUE 4th AVE. SO. SO. 48th ST. INTERSTATE 29 SO. 30th ST. 11th AVE. S 17th AVE. SO. 24th AVE. SO. SO. WASHINGTON ST. 10th AVE. SO. ROAD BELMONT SOUTH COLUMBIA ROAD 32nd AVENUE SOUTH 47th AVE. SO. 36th AVE. SO. 40th AVE. SO. COUNTY HIGHWAY NO. 81 BELMONT RD. 62nd AVE. SO. S:\ TIP-TAP-HSIP-SRF\HSIP\Flashing Pedestrian Crossing Signage\Pushbuttons and Controllers\PROJECT LOCATION MAP.dwg

10 2017 HSIP Application Controllers and Pushbuttons Updated 11/21/2017 Ben Franklin Discovery Century Kelly & Schroeder Middle s Viking Lewis & Clark SPEC CODE DESCRIPTION Quantity Total Unit Unit price Total TRAFFIC CONTROL LSUM $2, $ 26, INLET PROTECTION SPECIAL EA $ $ 28, IN DIAMERTER RIGID CONDUIT LF $7.00 $ 18, NO12 AWG 2 CONDUCTOR CABLE LF $2.00 $ 6, REVISE FLASHING BEACON SYSTEM EA $18, $ 396, Holy Family Subtotal $ 22, $ 22, $ 44, $ 42, $ 44, $ 22, $ 23, $ 43, $ 21, $ 22, $ 42, $ 41, $ 82, $ 476, $ 476, % Contingencies $ 4, $ 5, $ 9, $ 8, $ 9, $ 5, $ 5, $ 8, $ 5, $ 4, $ 9, $ 8, $ 17, $ 95, Total $ 27, $ 28, $ 54, $ 51, $ 54, $ 28, $ 28, $ 52, $ 27, $ 27, $ 52, $ 50, $ 100, $ 572, Phoenix Wilder Winship Valley Middle West Lake Agassiz Subtotal inflated to 2022 (4% compound) $ 26, $ 27, $ 53, $ 51, $ 54, $ 27, $ 27, $ 52, $ 26, $ 27, $ 52, $ 50, $ 100, $ 579, % Contingencies $ 6, $ 5, $ 11, $ 10, $ 10, $ 6, $ 6, $ 10, $ 5, $ 5, $ 10, $ 10, $ 21, $ 120, Total $ 33, $ 33, $ 65, $ 62, $ 65, $ 34, $ 34, $ 63, $ 32, $ 33, $ 63, $ 61, $ 122, $ 700, Federal Share $ 29, $ 29, $ 58, $ 55, $ 58, $ 30, $ 30, $ 56, $ 28, $ 29, $ 56, $ 54, $ 109, $ 630, City Share $ 3, $ 3, $ 6, $ 6, $ 6, $ 3, $ 3, $ 6, $ 3, $ 3, $ 6, $ 6, $ 12, $ 70,000.00

11

12 32nd Ave S CITY OF GRAND FORKS ENGINEERING DEPARTMENT 32nd Ave S (Bus US 81) & S 17th St Traffic Signal and Left Turn Lane Realignment S 17th St 187' Matching Existing Taper New Lane Striping New Lane Striping 32nd Ave S 250' New Sidewalks and Curb Ramps New Traffic Signal New Traffic Signal New Traffic Signal New Traffic Signal New Sidewalks and Curb Ramps Matching Existing Taper DATE 11/21/2017 SCALE NTS CITY PROJECT 7676 PAGE 1 of 1

13 Project: Traffic Signal & Left Turn Lane Realignment 32nd Ave S (Bus US 81) & S 17th St *Estimated unit prices taken from project SU-6-986(120)124 Washington & 44th St Traffic Signal bid on 10/13/ /16/2017 SPEC CODE Total UNIT ITEM NO. NO. ITEM DESCRIPTION UNIT Quantity PRICE TOTAL CONTRACT BOND L SUM 1 $ 5, $ 5, REMOVAL OF CONCRETE PAVEMENT SY 150 $ $ 2, REMOVAL OF CURB AND GUTTER LF 950 $ 9.00 $ 8, COMMON EXCAVATION-TYPE B CY 100 $ $ 1, SEEDING CLASS III AC 0.1 $ 23, $ 2, HYDRAULIC MULCH AC 0.1 $ 9, $ IN REINFR CONCRETE PAVEMENT CL AE SY 360 $ $ 34, MOBILIZATION L SUM 1 $ 49, $ 49, FLAGGING MHR 80 $ $ 3, TRAFFIC CONTROL SIGNS UNIT 1034 $ 1.40 $ 1, TYPE III BARRICADE EA 16 $ $ 1, SIDEWALK BARRICADE EA 4 $ $ PEDESTRIAN LONGITUDINAL BARRICADE LF 490 $ $ 12, DELINEATOR DRUMS EA 142 $ $ 3, SEQUENCING ARROW-TYPE C EA 2 $ $ OBLITERATION OF PVMT MK SF 64 $ $ 1, INLET PROTECTION-SPECIAL EA 8 $ $ 1, ADJUST MANHOLE EA 1 $ $ CURB & GUTTER TYPE I LF 533 $ $ 19, SIDEWALK CONCRETE -5IN SY 100 $ $ 6, CONCRETE MEDIAN NOSE PAVING SY 36 $ $ 3, DETECTABLE WARNING PANELS SF 60 $ $ 2, EPOXY PVMT MK MESSAGE SF 64 $ $ EPOXY PVMY MK 6IN LINE LF 464 $ 4.30 $ 1, EPOXY PVMT MK 8IN LINE LF 1800 $ 2.15 $ 3, EPOXY PVMY MK 24IN LINE LF 116 $ $ 3, EPOXY PVMT MK CURB TOP & FACE LF 32 $ $ REVISE LIGHTING SYSTEM EA 1 $ 21, $ 21, TRAFFIC SIGNAL SYSTEM EA 1 $ 318, $ 318, IT SYSTEM EA 1 $ 27, $ 27, Subtotal $ 539, subtotal Inflated to 4% $ 656, Notes: 20% Contingencies $ 131, Existing Section is 8" Concrete Pavement on 12" Lime Treated Subgrade Constructed Total $ 788, Under NDDOT Project F-6-081(10)940 City Project 2645 Rehab work done in 2012 under NDDOT project SU-6-081(078)940, City project 6634 Concrete Edge Milling & 2" Asphalt Overlay (3/4" leveling Course & 1-1/4" Wear Course FAA 45 mix) Previous experience has shown that lime treated base should not be replaced with aggregate Assumption that at existing turn lanes lime treated base extends underneath proposed turn lane widening

14 Road Safety Review Recommendations 23 USC 409 Documents NDDOT Reserves All Objections Timeframe Improvement Reason Long Separate Work Revise the access to be more restrictive. Transit Plan is looking at possible bus stop revisions: install NB/SB pedestrian crossing or move bus stop closer to signalized intersection. 32nd Ave S & 25th St Intended to be SB to WB right turn only, but people still make SB to EB left turns. Supportive Past Studies Help pedestrians safely cross 32nd Ave S. 32nd Ave S & 24th St (Walmart) Timeframe Improvement Reason Supportive Past Studies Short Install countdown pedestrian signal heads. Requested with HSIP D Short Replace the WB to SB 5 section left turn head with a 4 section FYA head. To comply with MUTCD and to provide corridor consistency. Timeframe Improvement Reason Long Re align E/W left turn lanes to have zero or positive offset. 32nd Ave S & 23rd St Re alignment not needed now due to no left turn crashes and only low volumes. Supportive Past Studies Timeframe Improvement Reason Short Re align E/W left turn lanes to have zero or positive offset. 32nd Ave S & 20th St Improve sight distance and reduce left turn crashes (predominant trend on 2014 Urban High Crash Location List). Supportive Past Studies Short Install countdown pedestrian signal heads. Requested with HSIP D B, D, G Likely Short Long Replace traffic signal cabinet. Replace poles/mast arms as needed. Install FYA heads and add missing right turn overlaps. Install EB to SB and WB to NB exclusive right turn lanes. Existing cabinet cannot handle FYA. FYA heads have been shown to be safer, more efficient, and more flexible. Right turn overlaps improve efficiency. Not needed now due to low number of EB/WB rear end crashes. G Timeframe Improvement Reason Long Long Re align E/W left turn lanes to have zero or positive offset. Install NB/SB pedestrian crosswalks if a signal is installed in the future. 32nd Ave S & 17th St Re alignment not needed now due to no left turn crashes and only low volumes. Undesirable to install unsignalized NB/SB ped crosswalks now due to high EB/WB vehicle volumes. Page 7 Supportive Past Studies

15

16

17

18

19

20

21

Toolbox of Countermeasures and Their Potential Effectiveness to Make Intersections Safer

Toolbox of Countermeasures and Their Potential Effectiveness to Make Intersections Safer 8 Toolbox of Countermeasures and Their to Make Intersections Safer Introduction Studies included in the NCHRP 17-18 (3), Guidance for Implementation of the AASHTO Strategic Highway Safety Plan, as well

More information

City of Grand Forks Staff Report

City of Grand Forks Staff Report City of Grand Forks Staff Report Committee of the Whole November 27, 2017 City Council December 4, 2017 Agenda Item: Federal Transportation Funding Request Highway Safety Improvement Program Submitted

More information

Safety at Unsignalized Intersections. Unsignalized Intersections

Safety at Unsignalized Intersections. Unsignalized Intersections Safety at FHWA Safety Focus Areas 2 National Statistics 3 National Statistics There were 41,059 highway fatalities in 2007. Where did they occur? Non-Intersections 79% About half of all crashes and half

More information

Active Transportation Facility Glossary

Active Transportation Facility Glossary Active Transportation Facility Glossary This document defines different active transportation facilities and suggests appropriate corridor types. Click on a facility type to jump to its definition. Bike

More information

Highway Safety Improvement

Highway Safety Improvement Highway Safety Improvement Tracy Turpin, PE. Highway Safety Improvement Program Manager Virginia Department of Transportation Presented at Chesapeake and Virginia Chapters of ATSSA Meeting October 13 th,2016

More information

Lessons Learned from the Minnesota County Road Safety Plans. Richard Storm CH2M HILL

Lessons Learned from the Minnesota County Road Safety Plans. Richard Storm CH2M HILL Lessons Learned from the Minnesota County Road Safety Plans Richard Storm CH2M HILL May 21, 2014 Overview of the MN CRSP: Why Prepare Safety Plans for Local Systems? MAP-21: Requires states to address

More information

4 GENERIC COST ESTIMATING TOOL

4 GENERIC COST ESTIMATING TOOL 4 GENERIC COST ESTIMATING TOOL Table 4-1 presents a generic cost estimating tools that can serve as a conceptual planning tool for local jurisdictions to estimate the costs of pedestrian improvements.

More information

ACTION TRANSMITTAL No

ACTION TRANSMITTAL No Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: January 5, 2017 TO: FROM: ACTION TRANSMITTAL No. 2017-04 Transportation Advisory Board TAC Funding & Programming Committee

More information

5. RUNNINGWAY GUIDELINES

5. RUNNINGWAY GUIDELINES 5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved

More information

MPO Staff Report Technical Advisory Committee: December 12, :30 pm MPO Executive Board: December 19, : 00 Noon

MPO Staff Report Technical Advisory Committee: December 12, :30 pm MPO Executive Board: December 19, : 00 Noon MPO Staff Report Technical Advisory Committee: December 2, 28 :3 pm MPO Executive Board: December 9, 28 2: Noon RECOMMENDED ACTION Recommends Technical Advisory Committee support application as projects

More information

Chapter 4: Funding and Implementation

Chapter 4: Funding and Implementation Chapter 4: Funding and Implementation 83 84 Cost Estimating Cost estimating is an iterative process. When a project is in the conceptual stage, preliminary cost estimates are also provided conceptually,

More information

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 7 DISTRICT WIDE BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT AND IMPROVEMENT PLAN

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 7 DISTRICT WIDE BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT AND IMPROVEMENT PLAN FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 7 DISTRICT WIDE BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT AND IMPROVEMENT PLAN TRANSIT SAFETY ASSESSMENT SR 55/US 19 AT 80 TH AVE N DRAFT JUNE

More information

Bridgewater Complete Streets Prioritization Plan and Pedestrian Safety Assessment

Bridgewater Complete Streets Prioritization Plan and Pedestrian Safety Assessment Bridgewater Complete Streets Prioritization Plan and Pedestrian Safety Assessment Presented by Luciano Rabito Manager of Complete Streets Presented to Bridgewater, MA Wednesday, April 26, 2017 6:30 P.M.

More information

Updated There is no park access points beyond the limit of the phase I work. roadway to be constructed Viewport has been along full limits of the park

Updated There is no park access points beyond the limit of the phase I work. roadway to be constructed Viewport has been along full limits of the park The signs will be installed as Temporary signs the color (Orange/White) have been added to the plans. Need to specify color to be used for stripes. Closures that may be in place for extended periods need

More information

Pavement Markings (1 of 3)

Pavement Markings (1 of 3) Pavement Markings (1 of 3) DESCRIPTION AND DEFINITION Disadvantages Relatively high cost (over typical Crash reduction as yet unknown painted edge line) No tactile effect The STOP AHEAD pavement marking

More information

East Downtown Tax Increment Reinvestment Zone (TIRZ) No. 15 Infrastructure Assessment Study

East Downtown Tax Increment Reinvestment Zone (TIRZ) No. 15 Infrastructure Assessment Study East Downtown Tax Increment Reinvestment Zone (TIRZ) No. 15 Infrastructure Assessment Study Houston, TX Technical Memorandum April 15 th, 2009 Prepare by: 2950 North Loop West, Ste. 900 Houston, TX 77092

More information

IMPLEMENTATION WORKBOOK

IMPLEMENTATION WORKBOOK Lawrence Township Bicycle and Pedestrian Planning Assistance Study IMPLEMENTATION WORKBOOK Final Action Plan - Part 2 April 2009 Prepared For: The Township of Lawrence and the New Jersey Department of

More information

NDDOT TRAFFIC OPERATIONS MANUAL

NDDOT TRAFFIC OPERATIONS MANUAL Prepared By: North Dakota Department of Transportation Programming Division Traffic Operations Section June 05 Table of Contents TRAFFIC OPERATIONS OVERVIEW... 3 TRAFFIC OPERATIONS STUDIES RURAL SEGMENTS

More information

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn

More information

WYDOT DESIGN GUIDES. Guide for. Non-NHS State Highways

WYDOT DESIGN GUIDES. Guide for. Non-NHS State Highways WYDOT DESIGN GUIDES Guide for Non-NHS State Highways 2014 GUIDE FOR Non-NATIONAL HIGHWAY SYSTEM (Non-NHS) STATE HIGHWAYS PRESERVATION REHABILITATION RECONSTRUCTION INTRODUCTION This Guide is directed to

More information

North Avenue Corridor Study

North Avenue Corridor Study North Avenue Corridor Study Advisory Committee Meeting #6 July 1, 2014 Agenda Concept Revisions based on Advisory Committee feedback Review of New Concept Scoring & Costs Concept Discussion/Questions Voting:

More information

CITY OF KASSON TRANSPORTATION ALTERNATIVES KASSON SAFE ROUTES TO SCHOOL

CITY OF KASSON TRANSPORTATION ALTERNATIVES KASSON SAFE ROUTES TO SCHOOL ve ha 8t G B A Mantorville Ave N 240th Ave 16th St NE 11th Ave NE K-M HIGH SCHOOL SUNRISE TRAIL TO MANTORVILLE MNTH 57 SUNSET TRAIL TO MANTORVILLE NE PARK 16TH ST NE TRAIL K-M ELEMENTARY SCHOOL K-M MIDDLE

More information

MEMORANDUM. Date: 9/13/2016. Citywide Crosswalk Policy

MEMORANDUM. Date: 9/13/2016. Citywide Crosswalk Policy MEMORANDUM Date: 9/13/2016 Re: Citywide Crosswalk Policy Foreword Through the s Circulation Element and Complete Streets Policy, it is the City s goal to promote walking trips and provide safe facilities

More information

Pine Hills Road Pedestrian/Bicycle Safety Study Board of County Commissioners Work Session

Pine Hills Road Pedestrian/Bicycle Safety Study Board of County Commissioners Work Session Pine Hills Road Pedestrian/Bicycle Safety Study Board of County Commissioners Work Session February 20, 2018 Meeting Agenda Study Overview Existing Conditions Access Management Potential Gateway Features

More information

Lynchburg District Update

Lynchburg District Update Lynchburg District Update Virginia Statewide Bicycle and Pedestrian Advisory Committee Spring Meeting May 16 th, 2017 David Cook Transportation Planner, VDOT Lynchburg District Table of Contents Active

More information

Closing Plenary Session

Closing Plenary Session TRAFFIC SAFETY CONFERENCE Closing Plenary Session June 9, 2017 Las Colinas, TX Order of Report Out June 9, 2017 Las Colinas, TX Distracted Driving Prioritized Countermeasures Countermeasure 4a Systemically

More information

Broad Street Bicycle Boulevard Design Guidelines

Broad Street Bicycle Boulevard Design Guidelines Broad Street Bicycle Boulevard Design Guidelines Building from the strategies introduced in the 2013 Bicycle Transportation Plan and community input received thus far, City Transportation Staff have identified

More information

Updated There is no park access roadway to be constructed points beyond the limit of along full limits of the park's the phase I work. Phase 1. Revise

Updated There is no park access roadway to be constructed points beyond the limit of along full limits of the park's the phase I work. Phase 1. Revise The signs will be installed as Temporary signs the color (Orange/White) have been added to the plans. Need to specify color to be used for stripes. Closures that may be in place for extended periods need

More information

Chapter 2: Standards for Access, Non-Motorized, and Transit

Chapter 2: Standards for Access, Non-Motorized, and Transit Standards for Access, Non-Motorized, and Transit Chapter 2: Standards for Access, Non-Motorized, and Transit The Washtenaw County Access Management Plan was developed based on the analysis of existing

More information

Road Safety Audit Course Participant Guidebook. August 22 & 23, Cleveland Avenue Columbus, Ohio

Road Safety Audit Course Participant Guidebook. August 22 & 23, Cleveland Avenue Columbus, Ohio Road Safety Audit Course Participant Guidebook August 22 & 23, 2017 Cleveland Avenue Columbus, Ohio 1 2 Table of Contents Executive Summary... 5 Cleveland Avenue City of Columbus... 6 Road Location Details...

More information

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of

More information

THE FUTURE OF THE TxDOT ROADWAY DESIGN MANUAL

THE FUTURE OF THE TxDOT ROADWAY DESIGN MANUAL THE FUTURE OF THE TXDOT ROADWAY DESIGN MANUAL Kenneth Mora, P.E. (Design Division) 10/10/2017 Table of contents 1 2 Reduction in FHWA design controlling criteria Innovative Intersection Guidance 3-7 8-42

More information

Project Name Project Description Authorized Amount

Project Name Project Description Authorized Amount 1, 13 Branchville-Lewisburg Road (CR 628) Lewisburg-Creamery Road (CR 565) 2,3 Asbury-Bloomsbury Road/Asbury- Anderson Road (CR 632) Skid-resistant surface treatment, enhanced signage, pavement markings

More information

Chapter 4 Traffic Analysis

Chapter 4 Traffic Analysis Chapter 4 Traffic Analysis PURPOSE The traffic analysis component of the K-68 Corridor Management Plan incorporates information on the existing transportation network, such as traffic volumes and intersection

More information

Access Management in the Vicinity of Intersections

Access Management in the Vicinity of Intersections Access Management in the Vicinity of Intersections FHWA-SA-10-002 Technical Summary Photo: Ralph Bentley (used with permission) 0 Access Management is: The design, implementation and management of entry

More information

Freeway ramp intersection study

Freeway ramp intersection study Freeway ramp intersection study Supporting Vision Zero: Zero traffic deaths in San Francisco by 2024 Study Goals: Primary Improve Safety Improve Accessibility Secondary Provide Efficient Circulation Accommodate

More information

WYDOT DESIGN GUIDES. Guide for. NHS Arterial (Non-Interstate)

WYDOT DESIGN GUIDES. Guide for. NHS Arterial (Non-Interstate) WYDOT DESIGN GUIDES Guide for NHS Arterial (Non-Interstate) 2014 GUIDE FOR NATIONAL HIGHWAY SYSTEM (NHS) HIGHWAYS (NHS ARTERIALS, Non-Interstate) PRESERVATION REHABILITATION RECONSTRUCTION INTRODUCTION

More information

Washington St. Corridor Study

Washington St. Corridor Study FIGURE 7.17 Bridge Alternatives - Cross Sections 86 Discarded Alternative: Short-Term Bridge Repair Short-term repairs and west bridge span replacement were considered during analysis. Short-term repairs

More information

Engineering Countermeasures for Transportation Safety. Adam Larsen Safety Engineer Federal Highway Administration

Engineering Countermeasures for Transportation Safety. Adam Larsen Safety Engineer Federal Highway Administration Engineering Countermeasures for Transportation Safety Adam Larsen Safety Engineer Federal Highway Administration 360-619-7751 Adam.Larsen@DOT.GOV Countermeasure Selection Resources Manual for Selecting

More information

MUTCD Part 6: Temporary Traffic Control

MUTCD Part 6: Temporary Traffic Control MUTCD Part 6: Temporary Traffic Control OMUTCD English units are preferred. OHIO MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES TABLE OF CONTENTS PREFACE INTRODUCTION TABLE OF CONTENTS PART 1. GENERAL Chapter

More information

BUDGET FOR RESEDA BOULEVARD, STREET RECONSTRUCTION / VISION ZERO PROGRAM, REPORT BACK, COUNCIL FILE

BUDGET FOR RESEDA BOULEVARD, STREET RECONSTRUCTION / VISION ZERO PROGRAM, REPORT BACK, COUNCIL FILE FORM GEN. 160 (Rev. 11-02) CITY OF LOS ANGELES INTERDEPARTMENTAL CORRESPONDENCE Date: To: Honorable City Council From: Gary Lee Moore, City Engineer Bureau of Engineering 7%mt /Electronically signed by

More information

AGENDA ITEM 6 D THOMASVILLE ROAD (HERMITAGE BOULEVARD TO LIVE OAK PLANTATION ROAD) ROADWAY SAFETY AUDIT

AGENDA ITEM 6 D THOMASVILLE ROAD (HERMITAGE BOULEVARD TO LIVE OAK PLANTATION ROAD) ROADWAY SAFETY AUDIT May 15, 2018 AGENDA ITEM 6 D THOMASVILLE ROAD (HERMITAGE BOULEVARD TO LIVE OAK PLANTATION ROAD) ROADWAY SAFETY AUDIT TYPE OF ITEM: Discussion STATEMENT OF ISSUE The Florida Department of Transportation

More information

Acknowledgements. Mr. David Nicol 3/23/2012. Daniel Camacho, P.E. Highway Engineer Federal Highway Administration Puerto Rico Division

Acknowledgements. Mr. David Nicol 3/23/2012. Daniel Camacho, P.E. Highway Engineer Federal Highway Administration Puerto Rico Division Daniel Camacho, P.E. Highway Engineer Federal Highway Administration Puerto Rico Division Acknowledgements Mr. David Nicol Director, FHWA Office of Safety FHWA Office of Safety http://safety.fhwa.dot.gov/provencountermeasures/

More information

Recent U.S. Research on Safety Evaluation of Low-Cost Road Engineering Safety Countermeasures Lessons for Canada

Recent U.S. Research on Safety Evaluation of Low-Cost Road Engineering Safety Countermeasures Lessons for Canada Recent U.S. Research on Safety Evaluation of Low-Cost Road Engineering Safety Countermeasures Lessons for Canada Bhagwant Persaud Department of Civil Engineering, Ryerson University 350 Victoria Street,

More information

Toward Zero Deaths. Regional SHSP Road Show Meeting. Virginia Strategic Highway Safety Plan. presented by

Toward Zero Deaths. Regional SHSP Road Show Meeting. Virginia Strategic Highway Safety Plan. presented by Toward Zero Deaths Regional SHSP Road Show Meeting presented by Virginia Strategic Highway Safety Plan December 1, 2016 1 Welcome & Introductions Purpose of the Meeting Objectives & Key Outcomes Agenda»

More information

ICBC invests $1.175 million to help make Surrey, Delta and White Rock s roads safer in 2013

ICBC invests $1.175 million to help make Surrey, Delta and White Rock s roads safer in 2013 Date: March 18, 2014 Page: 1 of 8 Media contacts: Michelle Hargrave, 250-979-4642 Lindsay Olsen, 604-982-4759 ICBC invests $1.175 million to help make Surrey, Delta and White Rock s roads safer in 2013

More information

Fundamentals of Traffic Control Devices

Fundamentals of Traffic Control Devices Fundamentals of Traffic Control Devices Traffic Engineering & Operations October 8, 2014 Raj Ponnaluri, Angela Wilhelm, and Christopher Lewis Agenda Agenda Signs Pavement Markings Signals Traffic Operations

More information

City of Scotts Valley CITY COUNCIL STAFF REPORT

City of Scotts Valley CITY COUNCIL STAFF REPORT DATE: April 19, 2017 City of Scotts Valley CITY COUNCIL STAFF REPORT AGENDA ITEM 2 DATE: 4-19-2017 TO: FROM: APPROVED: SUBJECT: Honorable Mayor and City Council Scott Hamby, Public Works Director Jenny

More information

SRTS IMPLEMENTATION COSTS

SRTS IMPLEMENTATION COSTS SRTS IMPLEMENTATION COSTS What Is a Estimate? A cost estimate establishes the anticipated budget required to implement the actions (the improvement projects and programs) identified in your School Travel

More information

Figure 3B-1. Examples of Two-Lane, Two-Way Marking Applications

Figure 3B-1. Examples of Two-Lane, Two-Way Marking Applications Figure 3B-1. Examples of Two-Lane, Two-Way Marking Applications A - Typical two-lane, two-way marking with passing permitted in both directions B - Typical two-lane, two-way marking with no-passing zones

More information

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns Public Informational Meeting University Avenue (Allen Boulevard Segoe Road) March 23, 2011 City of Madison City of Middleton Village of Shorewood Hills Dane County Existing Roadway Conditions Poor pavement

More information

City of Albert Lea Policy and Procedure Manual 4.10 ALBERT LEA CROSSWALK POLICY

City of Albert Lea Policy and Procedure Manual 4.10 ALBERT LEA CROSSWALK POLICY 4.10 ALBERT LEA CROSSWALK POLICY PURPOSE: Pedestrian crosswalks are an integral part of our transportation infrastructure. To be effective and promote safety, marked crosswalks must be installed after

More information

CHAPTER 16 PEDESTRIAN FACILITIES DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS

CHAPTER 16 PEDESTRIAN FACILITIES DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS CHAPTER 16 PEDESTRIAN FACILITIES DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS Section Title Page 16.1 General... 16-1 16.1.1 AASHTO Reference... 16-1 16.1.2 ADA Requirements... 16-1 16.2 Sidewalks...

More information

Pedestrian Safety Guide for Transit Agencies

Pedestrian Safety Guide for Transit Agencies Pedestrian Safety Guide for Transit Agencies FDOT/FTPA/CUTR Professional Development Workshop June 15, 2010 1 Purpose Presentation Overview Bus Stop Location and Design Process/Partnership 2 Purpose Every

More information

CHAPTER 2G. PREFERENTIAL AND MANAGED LANE SIGNS

CHAPTER 2G. PREFERENTIAL AND MANAGED LANE SIGNS 2011 Edition - Revision 2 Page 275 Section 2G.01 Scope CHAPTER 2G. PREFERENTIAL AND MANAGED LANE SIGNS 01 Preferential lanes are lanes designated for special traffic uses such as high-occupancy vehicles

More information

Document 2 - City of Ottawa Pedestrian Crossover (PXO) Program

Document 2 - City of Ottawa Pedestrian Crossover (PXO) Program 40 Document 2 - City of Ottawa Pedestrian Crossover (PXO) Program OVERVIEW The City of Ottawa Pedestrian Crossover (PXO) Program provides the basis for PXO implementation in Ottawa. The program s processes

More information

Access Location, Spacing, Turn Lanes, and Medians

Access Location, Spacing, Turn Lanes, and Medians Design Manual Chapter 5 - Roadway Design 5L - Access Management 5L-3 Access Location, Spacing, Turn Lanes, and Medians This section addresses access location, spacing, turn lane and median needs, including

More information

Pinellas County Safety Initiatives

Pinellas County Safety Initiatives Florida Department of TRANSPORTATION Pinellas County Safety Initiatives Whit Blanton, FAICP Pinellas County MPO A Distinctive County A unique geography Multi-jurisdictional Key demographics seniors and

More information

Route 7 Corridor Study

Route 7 Corridor Study Route 7 Corridor Study Executive Summary Study Area The following report analyzes a segment of the Virginia State Route 7 corridor. The corridor study area, spanning over 5 miles in length, is a multi

More information

Pedestrians and Bicyclists. Bruce Friedman and Scott Wainwright FHWA MUTCD Team

Pedestrians and Bicyclists. Bruce Friedman and Scott Wainwright FHWA MUTCD Team Impact of the New MUTCD on Pedestrians and Bicyclists Bruce Friedman and Scott Wainwright FHWA MUTCD Team Development of the 2009 MUTCD NPA published in the Federal Register on January 2, 2008 Received

More information

Proven Safety Countermeasures. FHWA Office of Safety January 12, :00 p.m. to 2:00 p.m. Eastern Time

Proven Safety Countermeasures. FHWA Office of Safety January 12, :00 p.m. to 2:00 p.m. Eastern Time Proven Safety Countermeasures FHWA Office of Safety January 12, 2012 1:00 p.m. to 2:00 p.m. Eastern Time Introduction and Background While States should still be considering the application of all of the

More information

PEDESTRIAN CROSSING TREATMENTS

PEDESTRIAN CROSSING TREATMENTS PEDESTRIAN CROSSING TREATMENTS BEST PRACTICES Presented by: Doug Enderson, P.E., PTOE Cody Salo, P.E. 1 PRESENTER INTRODUCTIONS Doug Enderson, P.E., PTOE Ped Crossing Experience: ADA Design-Build ADA Inventory

More information

PEDESTRIAN SAFETY STUDY

PEDESTRIAN SAFETY STUDY PEDESTRIAN SAFETY STUDY SR 699 (BLIND PASS RD/GULF BLVD) FROM 93 RD AVENUE TO PINELLAS BAYWAY PINELLAS COUNTY SECTION NO.: 15100 MILEPOST: 0.111 3.569 STUDY LIMITS Prepared For: Florida Department of Transportation

More information

ROAD SAFETY AUDIT. Granite Avenue at Interstate 93 Ramps. Town of Milton. May 22, Prepared for: MassDOT

ROAD SAFETY AUDIT. Granite Avenue at Interstate 93 Ramps. Town of Milton. May 22, Prepared for: MassDOT ROAD SAFETY AUDIT Granite Avenue at Interstate 93 Ramps Town of Milton May 22, 2017 Prepared for: MassDOT Prepared by: Toole Design Group 2 Oliver Street, Suite 305 Boston, MA 02109 Table of Contents Background...

More information

Road Safety Assessments. Lt. Bob McCurdy Williamson County Sheriff s s Office Marion, IL.

Road Safety Assessments. Lt. Bob McCurdy Williamson County Sheriff s s Office Marion, IL. Road Safety Assessments Lt. Bob McCurdy Williamson County Sheriff s s Office Marion, IL. Why Are We Here? 2005 US Traffic Fatalities = 43,443 1429 4329 1361 1616 1534 3504 1729 3543 Illinois Annual Fatallities

More information

Bluffdale/ UDOT South High-T Intersection Project Type Operations

Bluffdale/ UDOT South High-T Intersection Project Type Operations Bluffdale/ UDOT 14600 South High-T Intersection Project Type Operations 14600 South and Redwood Road $ 600,000 $ 550,000 This project is to install a new High-T intersection at Redwood Road and 14600 South

More information

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

TRAFFIC IMPACT ANALYSIS

TRAFFIC IMPACT ANALYSIS TRAFFIC IMPACT ANALYSIS FOR THE CHAMPAIGN UNIT#4 SCHOOL DISTRICT PROPOSED HIGH SCHOOL (SPALDING PARK SITE) IN THE CITY OF CHAMPAIGN Final Report Champaign Urbana Urbanized Area Transportation Study 6/24/2014

More information

Toronto and East York Community Council. Director, Transportation Services, Toronto and East York District

Toronto and East York Community Council. Director, Transportation Services, Toronto and East York District No Turn on Red Regulations STAFF REPORT ACTION REQUIRED Date: June 1, 2010 To: From: Toronto and East York Community Council Director, Transportation Services, Toronto and East York District Wards: Trinity

More information

SBCAG STAFF REPORT Federal Transportation Improvement Program. MEETING DATE: January 19, 2017 AGENDA ITEM: 5E

SBCAG STAFF REPORT Federal Transportation Improvement Program. MEETING DATE: January 19, 2017 AGENDA ITEM: 5E SBCAG STAFF REPORT SUBJECT: 2017 Federal Transportation Improvement Program MEETING DATE: January 19, 2017 AGENDA ITEM: 5E STAFF CONTACT: Anne Jensen RECOMMENDATION: Adopt Resolution 17-01 approving Amendment

More information

What Engineering Can Do for You! Low Cost Countermeasures for Transportation Safety

What Engineering Can Do for You! Low Cost Countermeasures for Transportation Safety What Engineering Can Do for You! Low Cost Countermeasures for Transportation Safety Adam Larsen Safety Engineer Federal Highway Administration 360-619-7751 Adam.Larsen@DOT.GOV Adam Larsen TTP Safety Engineer

More information

PEDESTRIAN SAFETY IMPROVEMENT EVALUATION GUIDELINE FOR UNCONTROLLED CROSSINGS

PEDESTRIAN SAFETY IMPROVEMENT EVALUATION GUIDELINE FOR UNCONTROLLED CROSSINGS PEDESTRIAN SAFETY IMPROVEMENT EVALUATION GUIDELINE FOR UNCONTROLLED CROSSINGS Traffic Safety Engineering Division Updated: April 2018 EXECUTIVE SUMMARY NDOT Traffic Safety Engineering Division developed

More information

Meeting Schedule 7:00-7:15 Open House 7:15-7:45 Existing Conditions/Short-Term Improvements Study Presentation 7:45-8:00 Q&A Session 8:00-8:10

Meeting Schedule 7:00-7:15 Open House 7:15-7:45 Existing Conditions/Short-Term Improvements Study Presentation 7:45-8:00 Q&A Session 8:00-8:10 Meeting Schedule 7:00-7:15 Open House 7:15-7:45 Existing Conditions/Short-Term Improvements Study Presentation 7:45-8:00 Q&A Session 8:00-8:10 Long-Term Study Presentation 8:10-8:40 Table Discussions 8:40-9:00

More information

Abstract. Background. protected/permissive operation. Source: Google Streetview, Fairview/Orchard intersection

Abstract. Background. protected/permissive operation. Source: Google Streetview, Fairview/Orchard intersection ITE 2015 Western District Annual Meeting Ada County Highway District s Flashing Yellow Arrow Initiative Primary Author: Tim Curns, PE Ada County Highway District Traffic Engineer Author: Andrew Cibor,

More information

SR 44 from US 441 / SR 500 to SR 44 / Orange Ave.

SR 44 from US 441 / SR 500 to SR 44 / Orange Ave. SR 44 from US 441 / SR 500 to SR 44 / Orange Ave. Financial Project ID: 409870-1-52-01 LAKE COUNTY DESIGN ALTERNATIVE STUDY FOR MULTI-USE PATH Prepared for: FLORIDA DEPARTMENT OF TRANSPORTATION District

More information

Typical Cross Section: DOWNTOWN (Observer Highway - 8th Street)

Typical Cross Section: DOWNTOWN (Observer Highway - 8th Street) Typical Cross Section: DOWNTOWN (Observer Highway - 8th Street) DRAFT SEPTEMBER 23, 14 1 Washington Street Typical Block Downtown Typical Block: DOWNTOWN (Observer Highway - 8th Street) New crosswalks

More information

ACTION TRANSMITTAL No

ACTION TRANSMITTAL No Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: August 25, 2016 TO: FROM: ACTION TRANSMITTAL No. 2016-47 Technical Advisory Committee TAC Funding and Programming Committee

More information

North Avenue Corridor Study

North Avenue Corridor Study North Avenue Corridor Study City Council October 6, 2014 Presentation Outline Project Initiation & Process Corridor Conditions & Issues Vision & Goals Concept Development - Development/Evaluation Implementation

More information

San Pablo High Treatment applied incrementally at each N + ++

San Pablo High Treatment applied incrementally at each N + ++ Transit Improvements T1 Further study options for creation or designation of segregated transit lanes along San Pablo, including options for restrictions during a limited number of peak travel hours and

More information

SR 53 Corridor Study. Final Report Presentation. Friday, October 3, :00 AM to noon

SR 53 Corridor Study. Final Report Presentation. Friday, October 3, :00 AM to noon SR 53 Corridor Study Final Report Presentation Friday, October 3, 2014 10:00 AM to noon SR 53 Corridor Study Final Report Presentation Study Purpose: Investigate safety improvements along the SR 53 corridor

More information

San Francisco s Capital Plan & the Mayor s Transportation Task Force 2030: Funding the next steps for transportation

San Francisco s Capital Plan & the Mayor s Transportation Task Force 2030: Funding the next steps for transportation San Francisco s Capital Plan & the Mayor s Transportation Task Force 2030: Funding the next steps for transportation San Francisco Capital Needs In 2006, the Mayor and Board of Supervisors approved San

More information

Citywide Sidewalk and Crosswalk Programs

Citywide Sidewalk and Crosswalk Programs Citywide Sidewalk and Crosswalk Programs Council Meeting October 20, 2015 Presented by Rita Hu and Jamal Mahmoud Program Goals Implement the City s comprehensive plan. Provide pedestrian with safe walking

More information

Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999

Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999 Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999,1'(; A ACCELERATION Data on acceleration from stop D-29 Effects of grade D-35 Intersections D-97, D-99 Lanes D-97, F-5, F-7, F-15, F-21,

More information

Welcome! Urban Work Zone Design. Training Course 0-1

Welcome! Urban Work Zone Design. Training Course 0-1 Welcome! Urban Work Zone Design Training Course 0-1 Instructor Instructor s Name Here 0-2 About This Course This material is based upon work supported by the Federal Highway Administration (FHWA) under

More information

Olmsted County Highway Safety Plan

Olmsted County Highway Safety Plan TB072009008MKE Olmsted County Highway Safety Plan September 2009 Submitted to: Table of Contents 1. Introduction...1-1 2. Comprehensive Crash Analysis...2-1 3. Safety Emphasis Areas...3-1 4. Safety Strategies...4-1

More information

Pedestrian Road Safety Audit

Pedestrian Road Safety Audit Pedestrian Road Safety Audit Middlebrook Road From Father Hurley Boulevard to Waring Station Road December 2017 Montgomery County Department of Transportation Table of Contents 1. Introduction... 1 1.1

More information

Date: February 18, 2015 Page: 1 of 9. ICBC invests $1.195 million to improve Surrey, Delta & White Rock roads

Date: February 18, 2015 Page: 1 of 9. ICBC invests $1.195 million to improve Surrey, Delta & White Rock roads News release Date: February 18, 2015 Page: 1 of 9 Media contacts: Lindsay Olsen, 604-982-4759 ICBC invests $1.195 million to improve Surrey, Delta & White Rock roads You may have noticed the new pedestrian

More information

INTERSECTIONS AT GRADE INTERSECTIONS

INTERSECTIONS AT GRADE INTERSECTIONS INTERSECTIONS 1 AT GRADE INTERSECTIONS INTERSECTIONS INTERSECTIONS = INTERRUPTED FACILITIES Definitions and key elements An intersection is defined as an area where two or more roadways join or cross.

More information

SHSP Action Plan Development. Intersection EA Team

SHSP Action Plan Development. Intersection EA Team SHSP Action Plan Development Intersection EA Team March 7, 2018 Agenda Welcome and Introductions Review Completed Action Plans Developed by Working Groups Next Steps STRATEGIES: INTERSECTION SAFETY EMPHASIS

More information

Final Report for the Minnesota County Roadway Safety Plans. Prepared for

Final Report for the Minnesota County Roadway Safety Plans. Prepared for Final Report for the Minnesota County Roadway Safety Plans Prepared for January 2014 Contents Acronyms... ii Introduction / Overview... 1-1 Crash Data Analysis and Safety Emphasis Areas... 2-1 Safety Strategies...

More information

Ohio Department of Transportation Edition of the OMUTCD It s Here!

Ohio Department of Transportation Edition of the OMUTCD It s Here! Ohio Department of Transportation John R. Kasich, Governor Jerry Wray, Director 2012 Edition of the OMUTCD It s Here! June 6, 2012 Here are reasons why we have a Manual of Uniform Traffic Control Devices

More information

PEDESTRIAN ACCOMMODATIONS DPS 201 AT INTERCHANGES

PEDESTRIAN ACCOMMODATIONS DPS 201 AT INTERCHANGES PEDESTRIAN ACCOMMODATIONS DPS 201 AT INTERCHANGES UNDERSTANDING THE ISSUES Intersections of freeway ramp terminals at crossroads are the most critical components of an interchange Challenge: balance mobility

More information

MEMORANDUM. DATE March 1, 2012 TO Town of Milton Mark Abbott, Seth Asante, and Efi Pagitsas Boston Region MPO Staff

MEMORANDUM. DATE March 1, 2012 TO Town of Milton Mark Abbott, Seth Asante, and Efi Pagitsas Boston Region MPO Staff MEMORANDUM DATE March 1, 212 TO Town of Milton FROM RE Mark Abbott, Seth Asante, and Efi Pagitsas Boston Region MPO Staff FFY 211 Safety and Operations Analyses at Selected Boston Region MPO Intersections:

More information

COWETA HIGH SCHOOL AND EAST HIGHWAY 51

COWETA HIGH SCHOOL AND EAST HIGHWAY 51 COWETA HIGH SCHOOL AND EAST HIGHWAY 51 Lack of sidewalks along Ben Lumpkin Rd. Lack of crosswalks and ramps at intersection. Hwy 51 is wide to cross as a pedestrian. No ADA compliance or connection to

More information

Hennepin County Pedestrian Plan Public Comment Report

Hennepin County Pedestrian Plan Public Comment Report Hennepin County Pedestrian Plan Public Comment Report On May 31, 2013, the draft Hennepin County Pedestrian Plan was released for a 45-day public comment period ending July 15, 2013. The county received

More information

MINERAL AVENUE CORRIDOR ASSESSMENT STUDY IMPLEMENTATION STRATEGY

MINERAL AVENUE CORRIDOR ASSESSMENT STUDY IMPLEMENTATION STRATEGY MINERAL AVENUE CORRIDOR ASSESSMENT STUDY IMPLEMENTATION STRATEGY INTRODUCTION City Personnel Sign-in Sheet Comment Forms Please Write Down Any Feedback INTRODUCTION List of Topics for Presentation Study

More information

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES November 16, 2011 Deb Humphreys North Central Texas Council of Governments Bicycle and Pedestrian Advisory Committee Snapshot of the Guide 1. Introduction

More information

Legislative Update Williamsburg Residency

Legislative Update Williamsburg Residency Hampton Roads District Legislative Update Williamsburg Residency Jim Brewer, Resident Administrator 757-253-5140 Projects Under Way Warwick Boulevard Project http://www.warwickboulevard.org/ Contractors:

More information

Who is Toole Design Group?

Who is Toole Design Group? 2018 AASHTO Bike Guide Status Update NCHRP 15 60 Amalia Leighton Cody, PE, AICP & Kenneth Loen, PE Washington APWA October 4, 2018 Who is Toole Design Group? TDG is a full service engineering, planning

More information

Roundabout Evaluations in Virginia: US 15/US 50 Gilberts Corner, VA SR 106/SR 634 Prince George County, VA

Roundabout Evaluations in Virginia: US 15/US 50 Gilberts Corner, VA SR 106/SR 634 Prince George County, VA Roundabout Evaluations in Virginia: US 15/US 50 Gilberts Corner, VA SR 106/SR 634 Prince George County, VA VDOT & FHWA Roundabout Workshop September 17, 2013 Chris Tiesler, PE Presentation Outline US 15/US

More information