1 Pine Hills Road Pedestrian/Bicycle Safety Study Community Meeting #1 June 8, 2017
2 Meeting Agenda Study Overview Community Survey Existing Conditions Access Management Potential Safety Countermeasures Potential Gateway Features Connection to Pine Hills Trail Proposed Street Typicals Public Outreach Questions & Answers Forum
3 STUDY OVERVIEW
4 Study Overview Walk-Ride-Thrive! Making streets safer for pedestrians and bicyclists Improving roadways to promote pedestrian and bicycle safety Providing educational outreach regarding the importance of safety while biking and walking Reinforcing proper road use and behavior by all 3 Pedestrian/Bicycle Safety Studies (UCF, Oak Ridge, Pine Hills)
5 Study Overview Kicked Off: January 2017 Anticipated Completion: January 2018 Corridor Length: Approximately 3.6 miles Goal: Identify opportunities for implementing safety improvements for people walking, bicycling, driving or taking the bus
6 Study Overview Key Focus Areas Access management/median modifications Lighting evaluation Intersection/mid-block crossing improvements Connectivity and integration with Pine Hills Trail (Segment I & Segment II) and LYNX Pine Hills SuperStop Pine Hills Road at Silver Star Road Gateway Travel lane widths Median landscaping (where possible) Enhanced signage and way-finding
7 Study Overview Key Stakeholders Community Members
8 Study Schedule Data Collection & Analysis Development of Safety Measures & Access Management Identification of Preferred Improvements Refinement of Improvements & Cost Benefit Analysis Agency Coordination Meeting Community Meeting Newsletter LPA/BCC Meetings
9 Public Involvement Study Newsletter Study Website Agency Coordination Meetings Community Meetings LPA/BCC Public Meetings Comments received tonight or postmarked by June 15, 2017 will become part of the first public meeting summary. All comments received throughout this Study will become part of public record and included in Final Study Report.
10 COMMUNITY SURVEY
11 Community Survey Conducted March 1 st to April 15 th Developed in English, Spanish and Haitian-Creole Available online Paper copies provided at 3 locations along corridor Total of 161 responses Majority of respondents: ages and over 65 years of age Majority live/work in 32308
12 Community Survey Results Biggest Challenges: Crossing at intersections Bad driver behaviors (drivers do not yield) Crossing behavior: 38% always cross at intersection or crosswalk 12% always do not cross at intersection or crosswalk 50% often do not cross at intersections or crosswalk 42% cross all lanes at gaps/ breaks in traffic Most preferred improvements: Better lighting Increased presence of law enforcement Wider sidewalks with greater separation from road Pedestrian warning signs/flashing beacons at crosswalks Special signal phasing and pedestrian signs
13 EXISTING CONDITIONS
14 Existing Conditions: Previous Studies Evaluation also considered: FDOT Improvements (Silver Star Road Intersection, Median Plantings, and Sidewalk/Crosswalk Improvements) OC pedestrian island study and construction Pine Hills Trail design and construction Sheriff's Office Operation RISE
15 Existing Conditions: Roadway Features Minor Arterial Urban Section with Curb and Gutter 5 Lanes with Two-Way Continuous Left Turn Lane Varying right-of-way (100 south of Silver Star/85 north of Silver Star) High number of single and multiple driveways 40 mph Speed Limit Pedestrian Crossings Across Pine Hills Road: 7 midblock crossings 8 signalized intersections Along Pine Hills Road: 9 unsignalized intersections
16 Existing Conditions: Pedestrian/Bicycle Facilities Pedestrian Facilities Continuous sidewalks (both sides) South of Belco Drive 5 North of Belco Drive 7 on east side, 5 on west side Curb ramps needed in several locations Ensure sidewalk repair/ maintenance Bicycle Facilities 6 bicycle lanes along both sides south of Figwood Lane No bicycle lane north of Silver Star Road Majority of respondents indicated they prefer to bike off street on wider sidewalk/multipurpose path
17 Existing Conditions: Traffic, Speed, and Transit AM, Afternoon, School and PM peak hours AADT: 25,060 to 34,733 S of Silver Star Rd 29,606 to 32,671 N of Silver Star Rd Truck volumes: < 8.2% 4 LYNX Routes/33 Bus Stops 15% with landing pads 58% with seating 52% with lighting Only 1 Stop (# 28) has pad, shelter, seating and lighting Heaviest Boarding/Alighting: NB Colonial Dr. & Belco Dr. SB Lupez Dr. & Alhambra Dr. Location Posted Speed vs. Actual Speed S of Indian Hill Rd North of Balboa Dr Crosswalk South of Balboa Dr Crosswalk 85 th Percentile Speed Most of traffic travels 7 to 8 miles per hour over the posted speed
18 Existing Conditions: Lighting Luminosity Evaluation 11pm 4am Signalized intersection crosswalks, midblock crosswalks and transit stops Findings Conventional High Pressure Sodium (HPS) street lighting present along both sides throughout Lighting at intersections and mid-block locations Needs improvements 22 (67%) transit stops needs improvements (non-industry standard) 15 (45%) transit stops located farther than 30 from overhead light source High Pressure Sodium LED
19 Existing Conditions: Crash History Analysis Period: Jan Dec Crash History (Total Crashes: 1,214) Crashes Involving Pedestrian/Bicycle 71 (6% of total crashes) Crashes with Injuries 59 (83%) Crashes with Fatalities 5 (7%) Pedestrian Crashes 50 (70%) Bicycle Crashes 21 (30%) Conditions During Crashes Evening/Night Approx. 39% Highest Crash Locations Silver Star Rd. & Colonial Dr. Mostly Dry Conditions Crashes by Age Groups Adult Non-Senior (18 64): 63% Minor (Under 18): 32% Summary of Crashes by User Driver Pedestrian Bicycle Other Highest Causes: Failure to Yield to Vehicle & Dart/Dash Across Road Jan 1 Feb 28, 2017: 80 crashes (5 involved pedestrian/bicycle; 2 pedestrian fatalities)
20 Existing Conditions: Observed Pedestrian/Bicycle Volumes Total Observed Pedestrian/Bike Volumes* Crossing Type Ped Bike Highest Frequency Locations Mid-block (At & Near) N of Fir Dr, Figwood Ln, Silver Star Rd Signalized Intersections (Including School Hours) 1, Silver Star Rd & Belco Dr Unsignalized Intersections 1, Between Spring Hill Dr and Champagne Cir Major Driveways Faith Christian Center Church Total Observed: 3, * Based on highest four hours per day (counts collected over a 3-day period)
21 ACCESS MANAGEMENT
22 Access Management Benefits of Medians Reduces crashes caused by traffic turning left, head-on and crossover traffic and headlight glare Provides refuge for pedestrians Helps traffic flow more efficiently Can improve appearance of a corridor and lessen stormwater runoff
23 Access Management South Section Access Management Based on: Turning Movement Counts Observed Pedestrian/Bicycle Counts Standard Spacing Requirements Maintaining Median Openings for Majority of Major Side Streets
24 Access Management North Section Access Management Based on: Turning Movement Counts Observed Pedestrian/Bicycle Counts Standard Spacing Requirements Maintaining Median Openings for Majority of Major Side Streets
25 POTENTIAL COUNTERMEASURES
26 Potential Safety Measures
27 POTENTIAL GATEWAY FEATURES
28 Potential Gateway Features Gateway Features at Pine Hills Road/Silver Star Road Wider Colored/Textured Crosswalks Larger Colored/Textured Pedestrian Landings Gateway and Enhanced Wayfinding Signage Towers and Low Walls with Pine Hills Branding Realignment of Pine Hills Trail Phase II Landscaping Intersection Modifications Reconstruct Curb Returns To Reduce Crossing Distances All Gateway Features and Intersection Modifications Subject to FDOT Approvals, Funding and Memorandum of Agreements for Maintenance Being in Place.
29 CONNECTION TO PINE HILLS TRAIL
30 Connection to Pine Hills Trail Realign Phase II along Belco Drive Connect Trail to East Side of Pine Hills Rd Phase II Proposed New Alignment New Signal Phase II Begin Point Pine Hills Trail Phase I (Est. Complete Jan. 2018)
31 PROPOSED TYPICALS
32 Proposed Typical South Section
33 Proposed Typical North Section
34 PUBLIC OUTREACH
35 Study Schedule Next Steps Data Collection & Analysis Development of Safety Measures & Access Management Identification of Preferred Improvements Refinement of Improvements & Cost Benefit Analysis Agency Coordination Meeting Community Meeting Newsletter LPA/BCC Meetings
36 Study Contacts Anoch Whitfield, AICP Orange County Project Manager 4200 South John Young Parkway Orlando, FL Phone: Spanish Contact Esther Fernández Cañizares Orange County Engineer II 4200 South John Young Parkway Orlando, FL Phone: Greg Smith, PE. Consultant Project Manager 301 E. Pine Street, Suite 1020 Orlando, FL Phone: Haitian-Creole Contact Celestin Pierre Orange County Assistant Project Manager 4200 South John Young Parkway Orlando, FL Phone:
37 Thank you!! QUESTIONS & ANSWERS FORUM
Pine Hills Road Pedestrian/Bicycle Safety Study Board of County Commissioners Work Session
Pine Hills Road Pedestrian/Bicycle Safety Study Board of County Commissioners Work Session February 20, 2018 Meeting Agenda Study Overview Existing Conditions Access Management Potential Gateway Features
More informationTransportation Planning Division
Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meetings Data Collected Focus Areas within Study Limits Design Principles Tool Box Recommended Concepts Schedule Moving
More informationTransportation Planning Division
Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meeting Stakeholder Interviews Data Collection Design Principles Tool Box Recommendations Schedule Moving Forward North
More informationPine Hills Road Pedestrian/Bicycle Safety Study Final Report
4.6.2 Pedestrian and Bicycle Traffic Volumes As presented in an earlier section, crosswalks are provided at mid-block crossings, signalized intersections, unsignalized intersections and at major driveways.
More informationBroad Street Bicycle Boulevard Design Guidelines
Broad Street Bicycle Boulevard Design Guidelines Building from the strategies introduced in the 2013 Bicycle Transportation Plan and community input received thus far, City Transportation Staff have identified
More informationBETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY
DRAFT PLAN City Council Meeting August 14, 2017 STUDY AREA Sedgwick Corridor State Route 160, principal arterial with Class 3 access management designation, commuter and freight route, connection to SR
More informationPine Hills Road Pedestrian/Bicycle Safety Study Final Report APPENDIX C TECHNICAL MEMORANDUM 3: EXISTING CONDITIONS REPORT
Final Report APPENDIX C TECHNICAL MEMORANDUM 3: EXISTING CONDITIONS REPORT Draft March 2017 On behalf of Orange County Mayor Teresa Jacobs, District 2 Commissioner Bryan Nelson and District 6 Commissioner
More information5. RUNNINGWAY GUIDELINES
5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved
More informationTransportation Planning Division
Transportation Planning Division Study Area & Maintenance Responsibility Brief Overview of Public Outreach 3 Core Group Meetings (October 2014, February/August 2015) 6 Stakeholder Interviews (November,
More informationCOMMUNITY MEETING #1 Summary
COMMUNITY MEETING #1 Summary October 26, 2016 LOCATION: TIME: ATTENDEES: Dr. Phillips High School Cafeteria 6500 Turkey Lake Road, Orlando, FL 32819 6:00 pm to 8:00 pm 79 citizens Commissioner Scott Boyd,
More informationOrange County s Transportation Planning and Multimodal Corridor Plan
Orange County Transportation Planning Division Orange County s Transportation Planning and Multimodal Corridor Plan Presentation to UCF LIFE November 11, 2014 Alissa Barber Torres, Ph.D., AICP, PLS Presentation
More informationAgenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN
PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations
More informationF L E T C H E R A V E N U E
Jan. 29, 2014 Introduction F L E T C H E R A V E N U E FDOT Local Agency Program (LAP) Project FPN: 428214-1-58-01 CIP 63090 Hillsborough County, Traffic Engineering, PWD Stake holders and partners are
More informationCITY OF CASSELBERRY WINTER PARK DRIVE IMPROVEMENT STUDY
CITY OF CASSELBERRY WINTER PARK DRIVE IMPROVEMENT STUDY Preliminary Recommendations October 2018 2014 HDR, Inc., all rights reserved. PROJECT BACKGROUND WALKING AUDIT FINDINGS PROPOSED IMPROVEMENT CONCEPTS
More informationPublic Information Meeting. Orange Camp Road. Dr. Martin Luther King Jr. Beltway to I-4. Presented by: Volusia County August 2, 2018
Public Information Meeting Orange Camp Road Dr. Martin Luther King Jr. Beltway to I-4 Presented by: Volusia County August 2, 2018 1 Project Goals To improve the operations and safety for Orange Camp Road
More informationCity of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE
Welcome Welcome to the third community meeting for the Issaquah-Fall City Road Improvements Project. AGENDA 6:00 p.m. Welcome and sign-in 6:10 p.m. Presentation 6:50 p.m. Open house Learn about the roadway
More informationAtwood Avenue Fair Oaks Avenue Cottage Grove Road
Atwood Avenue Fair Oaks Avenue Cottage Grove Road Agenda Purpose Review project scope & goals Present design alternatives Gather feedback Answer Questions Format Open House Presentation Q&A Open House
More informationComplete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER
Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets City Commission adopted a Complete Streets policy in 2012 Complete Streets are road networks that are designed for all users:
More informationDr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018
Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 What s Happening The City plans to mill and resurface Dr. M.L.
More informationRoad Diets FDOT Process
Florida Department of TRANSPORTATION Road Diets FDOT Process Humberto Castillero, PE, PTOE Roadway Design Office Purpose of Guide Develop a statewide lane elimination review process Balance state & local
More informationDesigning Complete Streets: What you need to know
Designing Complete Streets: What you need to know Getting from this to this. Continuous sidewalk Buffer w/trees Bicycle lane Raised median Buildings close to the street Flexibility in design Design and
More informationMeeting Schedule 7:00-7:15 Open House 7:15-7:45 Existing Conditions/Short-Term Improvements Study Presentation 7:45-8:00 Q&A Session 8:00-8:10
Meeting Schedule 7:00-7:15 Open House 7:15-7:45 Existing Conditions/Short-Term Improvements Study Presentation 7:45-8:00 Q&A Session 8:00-8:10 Long-Term Study Presentation 8:10-8:40 Table Discussions 8:40-9:00
More informationFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 7 DISTRICT WIDE BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT AND IMPROVEMENT PLAN
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 7 DISTRICT WIDE BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT AND IMPROVEMENT PLAN TRANSIT SAFETY ASSESSMENT SR 55/US 19 AT 80 TH AVE N DRAFT JUNE
More informationSR 693 (Pasadena Avenue) Corridor Study from Shore Drive South to 66 th Street
Welcome and Introduction Sign-in and comment sheets Restrooms and exits Meeting agenda and timeline Meeting goals / expectations Provide input to guide study recommendations Actively participate throughout
More information122 Avenue: 107 Street to Fort Road
: 107 Street to Fort Road November 24, 2015 4:30 8:00 p.m. Meeting Purpose Summarize project work completed to date Share results of public input from Phase 1 Share the draft concept plan and proposed
More informationSTATUS OF 2009 PEDESTRIAN MASTER PLAN (AS OF DECEMBER 2013)
Appendix P.1 STATUS OF 2009 PEDESTRIAN MASTER PLAN (AS OF DECEMBER 2013) The 2009 Pedestrian Master Plan establishes 21 core recommendations in three goal areas to improve pedestrian transportation in
More informationCity of Wilsonville 5 th Street to Kinsman Road Extension Project
City of Wilsonville 5 th Street to Kinsman Road Walking Tour & Neighborhood Workshop Summary Report Public Outreach Overview On July 18 th, 2017, the City of Wilsonville hosted a neighborhood walking tour
More informationORANGE COUNTY PUBLIC WORKS TRAFFIC INVESTIGATIONS
ORANGE COUNTY PUBLIC WORKS TRAFFIC INVESTIGATIONS STAFF REPORT OF: January 6, 2019 SUPERVISORIAL DISTRICT: 5 SUBJECT: LOCATION: INVESTIGATOR: O Neill Drive at Roanoke Drive; Ladera Ranch; TB 922-E6 Clever
More informationMalabar Road (SR 514) PD&E. Town of Malabar Briefing (July 17, 2017)
Malabar Road (SR 514) PD&E Town of Malabar Briefing (July 17, 2017) 1 Agenda Project limits and briefing focus PD&E process and project status Public and agency project comments Review Recommended Alternatives:
More informationAPPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016
APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of
More informationUS 41 (Tamiami Trail) Corridor Study. Roadway Safety Audit
US 41 (Tamiami Trail) Corridor Study Roadway Safety Audit US 41 RSA June 14/15, 2017 Agenda Project Overview Schedule RSA Process Overview RSA Responsibilities Historical Crash Review 2 PROJECT OVERVIEW
More informationUS 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue
41 US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue EXECUTIVE SUMMARY DRAFT FEBRUARY 2019 Project Overview The US 41 Complete Streets Corridor Planning Study,
More informationSouthview Blvd & 3 rd Avenue Improvement Project. Public Open House December 4, to 7pm
Southview Blvd & 3 rd Avenue Improvement Project Public Open House December 4, 2014 5 to 7pm Southview Blvd & 3 rd Avenue Public Information Meeting Agenda Presentation 5:30 to 6:15 pm Purpose of Project
More informationPedestrian Safety Guide for Transit Agencies
Pedestrian Safety Guide for Transit Agencies FDOT/FTPA/CUTR Professional Development Workshop June 15, 2010 1 Purpose Presentation Overview Bus Stop Location and Design Process/Partnership 2 Purpose Every
More informationLANE ELIMINATION PROJECTS
PRESENTATION OUTLINE Lane Elimination Considerations Districts 4 & 7 Draft Lane Elimination Processes FDOT Lane Elimination Guidelines Example Projects D4 Case Study: SR A1A (Ft. Lauderdale) D7 Case Study:
More informationRIVERSIDE, Newton MA BH NORMANDY RIVERSIDE LLC. Riverside Station. A green, transit-oriented community
Riverside Station A green, transit-oriented community October 6, 2011 TONIGHT S AGENDA: 1. Project Update (5 min.) 2. Master Plan Update (10 min.) 3.Traffic Plan Update (10 min.) Questions & Answers MASTER
More informationLong Island Rail Road Expansion Project Floral Park to Hicksville
Long Island Rail Road Expansion Project Floral Park to Hicksville Final Environmental Impact Statement Appendix 1-D Complete Streets Policy Checklist April 2017 0902ML PIN: Project Location: 18A-4 Floral
More informationRiverside Drive Complete Streets Project 3 rd Community Meeting. March 26, 2015
Riverside Drive Complete Streets Project 3 rd Community Meeting March 26, 2015 Providing Feedback Sign-In with contact information for future updates Complete questionnaire provided tonight Complete comment
More informationMEMORANDUM. Charlotte Fleetwood, Transportation Planner
MEMORANDUM Date: Updated August 22, 2017 To: Organization: Charlotte Fleetwood, Transportation Planner Boston Transportation Department From: Jason DeGray, P.E., PTOE, Regional Director of Engineering
More informationBay to Bay Boulevard Complete Streets Project
Bay to Bay Boulevard Complete Streets Project Dale Mabry Highway to Bayshore Boulevard February 08, 2018 Photo Source: Tampa Bay Times Alessandra Da Pra Meeting Format Introduction Resurfacing Information
More informationFinancial Project ID No(s).: and ETDM No(s).: and 14181
Palm Beach Metropolitan Planning Organization (MPO) Presentation I-95 at Boynton Beach Boulevard Interchange and I-95 at Gateway Boulevard Interchange Project Development and Environment Study Palm Beach
More informationMultimodal Analysis in the 2010 Highway Capacity Manual
Multimodal Analysis in the 2010 Highway Capacity Manual It s not just cars anymore! Jamie Parks, AICP HCAT Conference May 9-10, 2011 Multimodal LOS in the 2010 HCM History and background Overview of methods
More informationLee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses
Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses Introduction At the Lee s Summit Road Improvement Study Public Open House held Thursday, June 7, 2007
More informationWaterford Lakes Small Area Study
Waterford Lakes Small Area Study Existing Traffic Conditions PREPARED FOR: ORANGE COUNTY PUBLIC WORKS DEPARTMENT TRAFFIC ENGINEERING DIVISION ORLANDO, FLORIDA PREPARED WITH: INWOOD CONSULTING ENGINEERS
More informationBrooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017
Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn
More informationPEDESTRIAN SAFETY IMPROVEMENT EVALUATION GUIDELINE FOR UNCONTROLLED CROSSINGS
PEDESTRIAN SAFETY IMPROVEMENT EVALUATION GUIDELINE FOR UNCONTROLLED CROSSINGS Traffic Safety Engineering Division Updated: April 2018 EXECUTIVE SUMMARY NDOT Traffic Safety Engineering Division developed
More informationBridgewater Complete Streets Prioritization Plan and Pedestrian Safety Assessment
Bridgewater Complete Streets Prioritization Plan and Pedestrian Safety Assessment Presented by Luciano Rabito Manager of Complete Streets Presented to Bridgewater, MA Wednesday, April 26, 2017 6:30 P.M.
More informationRoad Diets and Roundabouts
Road Diets and Roundabouts Paul Zykofsky, AICP Local Government Commission Sacramento, CA Classic Road Diet 4 to 3 lanes San Antonio TX On-street parking Median Bike Lanes Center Turn-Lane Seattle WA Road
More informationBicycle and Pedestrian Chapter TPP Update Overview. TAB September 20, 2017
Bicycle and Pedestrian Chapter TPP Update Overview TAB September 20, 2017 Bicycling & Walking in the Twin Cities Where are we now? The Bike-Pedestrian system Current trends New developments Where are we
More informationPRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN
PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations
More informationNorth Avenue Corridor Study
North Avenue Corridor Study City Council October 6, 2014 Presentation Outline Project Initiation & Process Corridor Conditions & Issues Vision & Goals Concept Development - Development/Evaluation Implementation
More informationSAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY
THIS PRINT COVERS CALENDAR ITEM NO. : 11 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Approving traffic modifications on Twin Peaks Boulevard between Christmas
More informationThe DC Pedestrian Master Plan
The DC Pedestrian Master Plan September 28, 2010 George Branyan Pedestrian Program Coordinator District Department of Transportation Presentation Agenda Scope of the Plan Methodology Recommendations Implementation
More informationArlington Public Schools New Elementary School at Thomas Jefferson Site Off-Site Transportation. Thomas Jefferson BLPC / PFRC Meeting July 27, 2016
Arlington Public Schools New Elementary School at Thomas Jefferson Site Off-Site Transportation Thomas Jefferson BLPC / PFRC Meeting July 27, 2016 1.Review of Analysis 2.Key Transportation Issues 3.Recommendations
More informationHillsborough Pedestrian Safety Action Plan 2015 Update. Hillsborough MPO BPAC May 2015
Hillsborough Pedestrian Safety Action Plan 2015 Update Hillsborough MPO BPAC May 2015 Presentation Overview Pedestrian Safety Action Plan (PSAP) Review Pedestrian Crash Trends Stakeholder Activities Engineering
More informationFDOT Bicycle/Pedestrian Focused Initiative & Complete Streets
Florida Department of TRANSPORTATION FDOT Bicycle/Pedestrian Focused Initiative & Complete Streets Billy L. Hattaway, PE District One Secretary Secretary s Pedestrian Safety Initiative Dangerous by Design
More informationIntersection Improvement: Sturgeon Road, Silver Avenue and Murray Park Road Roundabout. Welcome. Public Information Session
Intersection Improvement: 1 Welcome WHY IS AN INTERSECTION IMPROVEMENT NEEDED? 2 Traffic volumes for Sturgeon Road, Silver Avenue and Murray Park Road exceed the capacity of the existing 4-way stop controlled
More informationWELCOME Mission-Geneva Transportation Study
WELCOME Mission-Geneva Transportation Study Study Process and Schedule 2005 2006 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct Task 2 Develop Outreach Plan Task 3 Document Existing Conditions/ Prioritize
More informationWhat Is a Complete Street?
Session 5 Charleen Zimmer, AICP, Zan Associates May 5-7, 2010 What Is a Complete Street? May 2010 5-1 Not a Complete Street More of a Complete Street May 2010 5-2 Benefits of Complete Streets Safety for
More informationIMPROVING PEDESTRIAN SAFETY AT UNCONTROLLED CROSSINGS. Guidelines for Marked Crosswalks
IMPROVING PEDESTRIAN SAFETY AT UNCONTROLLED CROSSINGS Presented by Nazir Lalani P.E. Traffex Engineers Inc. N_lalani@hotmail.com Guidelines for Marked Crosswalks Source: FHWA, Safety Effects of Marked
More informationCity of Gainesville Transportation/Roadway Needs PROJECT SUMMARY
A1 Roadway Resurfacing $23,846,000 TYPE: Preservation of existing system Roadway resurfacing A2 Signal Replacement $6,000,000 TYPE: Preservation of existing system Replace traffic signals. B1 W 6th St
More informationWaterford Lakes Small Area Study Report
Waterford Lakes Small Area Study Report Orange County District 4 Prepared for: Orange County Public Works Department Traffic Engineering Division 4200 S. John Young Parkway Orlando, FL 32839-9205 Prepared
More informationColumbia Pike Implementation Team (CPIT) Meeting
Columbia Pike Implementation Team (CPIT) Meeting November 30, 2010 Agenda Introductions / Purpose of Meeting Review of project goals Multimodal project: 10% street design between the curbs Discussion Multimodal
More informationBicycle Facilities Planning
Bicycle Facilities Planning Overview Types of Cyclists Purpose for Riding Types of Facilities Bike Lanes Bicycle Boulevards Cycle Tracks Intersections Signals Signing and Marking Discussion Types of Bicyclists
More informationComplete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA
Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Aaron Elias, Bill Cisco Abstract As part of evaluating the feasibility of a road diet on Orange Grove Boulevard in Pasadena,
More informationUCF/ALAFAYA TRAIL PEDESTRIAN SAFETY STUDY
February 2017 PREPARED FOR: ORLANDO, FLORIDA PREPARED BY: TABLE OF CONTENTS TABLE OF CONTENTS... 1-0 TABLE OF FIGURES... 1-2 Chapter 1 Study Purpose and Scope... 1-1 Purpose... 1-1 Scope and Study Limits...
More informationMilitary Road Safety Improvements
Military Road Safety Improvements 26 th Road North to 31 st Street North SUMMARY OF DATA REVIEW AND PRELIMINARY RECOMMENDATIONS Prepared for: Department of Environmental Services Traffic Engineering and
More informationStudy Area and Location District PSA Ward ANC Phase Description B Existing 2500 Block Naylor Road Southeast Northbound
Speed Limit and Safety Nexus Studies for Automated Enforcement Locations in the District of Columbia 25 Block Naylor Road SE Study Area and Location District PSA Ward ANC Phase Description 7 71 7 7B Existing
More informationActive Transportation Facility Glossary
Active Transportation Facility Glossary This document defines different active transportation facilities and suggests appropriate corridor types. Click on a facility type to jump to its definition. Bike
More informationDewey Area Traffic Calming Project
SFMTA Municipal Transportation Agency Image: Crosswalk of California Street and Grant Avenue Dewey Area Traffic Calming Project 10 08 2013 SAN FRANCISCO, CALIFORNIA Tonight s Agenda Introductions Project
More informationNeighborhood Pedestrian Safety and Traffic Calming Study
Neighborhood Pedestrian Safety and Traffic Calming Study for the area bounded by Foster Avenue, Bedford Avenue, Farragut Road and Ocean Avenue Flatbush, Brooklyn, New York prepared by Michael King, miking@trafficcalmer.com
More informationPedestrian Road Safety Audit
Pedestrian Road Safety Audit Middlebrook Road From Father Hurley Boulevard to Waring Station Road December 2017 Montgomery County Department of Transportation Table of Contents 1. Introduction... 1 1.1
More informationSouthcote Road Improvements Class Environmental Assessment Study
1 Southcote Road Improvements Class Environmental Assessment Study Public Information Centre #1 May 24, 2018 Study Area 2 3 Welcome The Ancaster Transportation Master Plan (2011) outlined a long range
More informationThank you for attending
Improving mobility safety comfort WELCOME Thank you for attending The purpose of this meeting is to: Learn about the project Prioritize potential walking and biking improvements on Snelling Ave Gather
More informationMemo. Introduction. Memphis STP Pedestrian Sidewalk Project
Memo Memphis STP Pedestrian Sidewalk Project To: Kyle Wagenshutz, City of Memphis From: Matthew Berkow, Collin Chesston, and Anne Eshleman, Alta Planning + Design Date: June 2014 Re: Photo Inventory Introduction
More informationSouthbend to Prima Vista. October 30, Floresta Corridor Master Plan
Application of a Complete Street initiative and how it might function operationally 8 8 Southbend to Prima Vista October 30, 2017 Presentation Agenda 2 Perspective and History Traffic projections, Levels
More informationPedestrian, Bicycle and Traffic Calming Strategic Implementation Plan. January 18, 2011
Pedestrian, Bicycle and Traffic Calming Strategic Implementation Plan January 18, 2011 Tonight s Agenda Receive update on project Provide feedback on two policy issues Complete Streets Policy Project Prioritization
More informationCentral Avenue Corridor Study FPID Number:
Central Avenue Corridor Study FPID Number: 437932-1-18-01 City Commission Presentation 1 March 27, 2018 Meeting Agenda 1. Introductions 2. Project Overview 3. Opportunity for Economic Development 4. Healthy
More informationNEWMARKET UPHAM S CORNER
SOUTH STATION Planning Initiative NEWMARKET UPHAM S CORNER COLUMBIA ROAD (P) FOUR CORNERS/GENEVA Working Advisory Group (WAG) Meeting #5 TALBOT AVENUE MORTON STREET BLUE HILL AVE/CUMMINS HWY (P) RIVER
More informationDowntown Naples Mobility and Connectivity Study. Naples City Council Presentation January 2017
Downtown Naples Mobility and Connectivity Study Naples City Council Presentation January 2017 Agenda 1. Introduction 2. Scope Review 3. Project Schedule 4. Existing Conditions 5. Public Charrette 6. Mobility
More information95 th Street Corridor Transportation Plan. Steering Committee Meeting #2
95 th Street Corridor Transportation Plan Steering Committee Meeting #2 February 18, 2015 PURPOSE OF THE MEETING Update Steering Committee Present Community/Stakeholder Survey Results Present Transportation
More informationSpeed. Scale/design geometrics
20 30 40 50 60 70 10 80 0 90 Speed Scale/design geometrics Source: New Jersey DOT 15 MPH can mean the difference between crash avoidance and almost certain death Speed Complete Streets Scale/design
More informationHARRISON STREET/OAKLAND AVENUE COMMUNITY TRANSPORTATION PLAN
HARRISON STREET/OAKLAND AVENUE Community Workshop #4: Draft Plan Review December 3, 2009 D E S I G N, C O M M U N I T Y & E N V I R O N M E N T INTRODUCTIONS Key Project Staff: Alisa Shen, Project Manager,
More informationState Street and Pierce Park Lane Intersection Concept Report
State Street and Pierce Park Lane Intersection Prepared for September 2017 Prepared by CITATION Parametrix. 2017. State Street & Pierce Park Lane Intersection. Prepared by Parametrix, Boise, ID. September
More informationAppendix A: Crosswalk Policy
Appendix A: Crosswalk Policy Appendix A: Crosswalk Policy Introduction This citywide Crosswalk Policy is aimed at improving pedestrian safety and enhancing pedestrian mobility by providing a framework
More informationOakland Pedestrian Master Plan Oakland Pedestrian Plan Draft Recommendations Chapter Outline
EISEN LETUNIC T R A N S P O R T A T I O N, ENVIRO N M E N TA L A N D URBAN PLANNIN G MEMORANDUM To Oakland Pedestrian Plan Technical Advisory Committee & Pedestrian Advisory Group From Victoria Eisen Date
More informationHennepin Avenue Reconstruction Washington Avenue to 12 th Street
CITY OF MINNEAPOLIS Hennepin Avenue Reconstruction Washington Avenue to 12 th Street April 2016 1 Upcoming Opportunities Public Meeting #2 April 25, 2016 Minneapolis Central Library Doty Board Room Repeat
More informationSR/CR A1A PEDESTRIAN SAFETY & MOBILITY STUDY
SR/CR AA PEDESTRIAN SAFETY & MOBILITY STUDY PEDESTRIAN / BICYCLE SAFETY REVIEW Focus Area H / 9th Street S to 3th Street N Prepared for: River to Sea Transportation Planning Organization 2570 West International
More informationLincoln Way Multimodal Safety and Operations Study. City and University Summary Presentation
Lincoln Way Multimodal Safety and Operations Study City and University Summary Presentation February 27, 2018 Agenda Introductions Study Overview: Phase 1 - Discovery Phase 2 Improvement Recommendations
More informationFreeway ramp intersection study
Freeway ramp intersection study Supporting Vision Zero: Zero traffic deaths in San Francisco by 2024 Study Goals: Primary Improve Safety Improve Accessibility Secondary Provide Efficient Circulation Accommodate
More informationColchester/Riverside/Barrett/ Mill Intersection Study. PAC Meeting #3 September 22, 2016
Colchester/Riverside/Barrett/ Mill Intersection Study PAC Meeting #3 September 22, 2016 Tonight s Agenda Review Project Purpose and Need Describe short term and long improvements and changes since public
More informationToolbox of Countermeasures and Their Potential Effectiveness to Make Intersections Safer
8 Toolbox of Countermeasures and Their to Make Intersections Safer Introduction Studies included in the NCHRP 17-18 (3), Guidance for Implementation of the AASHTO Strategic Highway Safety Plan, as well
More informationPlanning Study SR 976. Project Advisory Team Meeting May 24, 2017
` SR 976 BIRD ROAD/SW 40TH STREET FROM SR 821/HEFT TO SR 5/US-1 Miami-Dade County, Florida FPID No.: 434845-4-22-01 Planning Study Project Advisory Team Meeting May 24, 2017 1 Agenda Introductions Project
More informationBike Planning: A New Day
Bike Planning: A New Day Josh Sikich, AICP, LEED AP Chicago Office Director Alta Planning + Design 312-265-0628 joshuasikich@altaplanning.com cities of all sizes are changing Illinois Bike Summit October
More informationMASTER BICYCLE AND PEDESTRIAN PLAN
VILLAGE OF NORTHBROOK MASTER BICYCLE AND PEDESTRIAN PLAN DRAFT PLAN OPEN HOUSE May 2, 2018 AGENDA 1. Community Engagement 2. Vision and Goals 3. General Structure of Plan 4. Recommendations Overview 5.
More informationBicycle and Pedestrian Plans and Improvements
Bicycle and Pedestrian Plans and Improvements Presented to the City Council By Randle Harwood, Planning and Development, and Richard Zavala, Parks and Community Services September 24, 2013 Purpose Review
More informationClosing Plenary Session
TRAFFIC SAFETY CONFERENCE Closing Plenary Session June 9, 2017 Las Colinas, TX Order of Report Out June 9, 2017 Las Colinas, TX Distracted Driving Prioritized Countermeasures Countermeasure 4a Systemically
More informationTHE ALAMEDA CONCEPT DESIGN COMMUNITY MEETING 3. A Plan for The Beautiful Way JANUARY 28, 2010
CONCEPT DESIGN COMMUNITY MEETING 3 JANUARY 28, 2010 AGENDA INTRODUCTION COMMUNITY INPUT ROADWAY STUDIES STREETSCAPE DESIGN STATIONS DISCUSSION SUMMARY AND DISCUSSION NEXT STEPS CLOSE INTRODUCTION SCHEDULE
More informationPedestrian & Bicycle Safety Innovations & Applications
Pedestrian & Bicycle Safety Innovations & Applications County Engineers Association of Maryland Spring, 2017 Conference May 25, 2017 George Branyan Pedestrian Program Coordinator District Department of
More information2018 Pedestrian and Bicycle and Safe Routes to School Application for Funding Page 1 of 31
2018 Pedestrian and Bicycle and Safe Routes to School Application for Funding Page 1 of 31 2018 Pedestrian and Bicycle and Safe Routes to School Application for Funding Part 1: General Information Funding
More information