I-290 Phase I Study Area OAK PARK AVE AUSTIN BLVD. Reconstruction Area (9 miles) Oak Park RIDGELAND AVE CENTRAL AVE HARLEM AVE. Cicero.
|
|
- Maria McKinney
- 5 years ago
- Views:
Transcription
1 RIDGELAND AVE OAK PARK AVE AUSTIN BLVD UP-RR BRC-RR ASHLAND AVE Study Area Map I-290 Phase I Study Area 294 UP RR Metra UP-W Illinois Prairie Path 38 Berkeley WOLF RD Hillside MANNHEIM RD Bellwood 290 Westchester CERMAK RD 25TH AVE 17TH AVE 5TH AVE Maywood Broadview 1ST AVE River Forest Forest Park HARLEM AVE Oak Park Berwyn Reconstruction Area (9 miles) CENTRAL AVE LARAMIE AVE Cicero CICERO AVE NORTH AVE PULASKI RD Chicago CSX-RR Metra MD-N 290 Cook OGDEN AVE WESTERN AVE Re-striping Area (4 miles) ROOSEVELT RD RACINE AVE Metra UP-N Jane Byrne Interchange Study Area Legend N Interstate Existing CTA Rail/Station Access Railroad River Metra Line/Station IL Prairie Path Multi-Use Trail County Boundary
2 Study Process & Timeline MULTI-MODAL COORDINATION CTA VISION STUDY STAKEHOLDER INVOLVEMENT & AGENCY INPUT Data Collection (Needs Analysis) Purpose & Need Alternatives Development & Evaluation Preferred Alternative Mainline I-290 (Maywood Access Ongoing) Study Completion Fall 2009 Summer 2017 We Are Here CTA VISION STUDY INITIAL ALTERNATIVES IDENTIFY AND DEVELOP INITIAL ALTERNATIVES ALTERNATIVES CARRIED FORWARD ROUND 1 ROUND 2 ROUND 3 Single Mode Remaining Single Mode Alternatives Combination Alternatives Draft Environmental Impact Statement (DEIS) Alternatives Over 600 Stakeholder Individual Highway Combinations of Highway Four Combination Highway/ Ideas Reviewed & Screened & Transportation & Transportation Transit Alternatives to Smaller List Improvements Evaluated Improvements Evaluated Evaluated in Further Detail
3 I-290 Purpose and Need Purpose To provide an IMPROVED transportation facility along the I-290 Eisenhower Expressway multi-modal corridor. FIVE SPECIFIC NEED POINTS TO BE ADDRESSED: > IMPROVE modal connections and opportunities > IMPROVE regional and local travel > IMPROVE access to employment > IMPROVE safety for all users > IMPROVE facility deficiencies
4 Benefits Multi-Modal: Improved design for motorists, bicyclists, and pedestrians Wider sidewalks, new east-west AESTHETICS opportunities and multi-use path Transit Trips Increase of 4,300 east-west daily transit trips Travel time SAVINGS 56% in managed lanes 25% in general purpose Productivity: $2.7 billion travel time savings 62% overall Safety Improvements ACCESS to jobs increased by 398,000 within 60 Minutes
5 How are noise impacts determined? Traffic noise studied at exterior locations of frequent human use Receptors \ Traffic Noise Impacts Future Build Condition Only Noise Abatement Criteria > By land use type noise sensitive uses > 67 db(a) residential, park, school > 72 db(a) restaurant, office Substantial Noise Increase from Existing Condition > Does not occur for I-290 project
6 What is viewpoint solicitation? > Vote FOR or AGAINST the proposed noise wall > Voting ballots and noise wall information mailed to anyone benefitted by a noise wall This summer, noise wall locations will be > Noise wall benefit is a perceptible noise reduction from a proposed wall re-evaluated between 1st Avenue and 25th Avenue based on revised ramps. > Each wall is voted for separately > Two rounds of Balloting: Round 1 Goal: 33% response rate for each wall Round 2 ballots resent for walls that did not receive 33% response in Round 1 At the end of Round 2, if greater than 50% of the ballots received are in favor of a wall, that noise wall will be recommended for implementation \
7 Preliminary Preferred Alternative High Occupancy Toll 3+ & Supporting Transit Existing Conditions HOT 3+ 25% 56% 56% 25% Travel Time Improvements SUPPORTING TRANSIT: > Bus feeder service > Blue Line extension to Mannheim > Initial service option - bus in managed lane > I-290 corridor improvements will enable/leverage transit improvements
8 Blue Line Vision Study: Preliminary Findings CTA focus on modernization of existing facility Not planning for an extension at this time Third Express Track Not Needed > Potential express service - limited time savings > Insufficient ROW to add third track and 24 wide platforms in trench Forest Park Terminal Modernization > Evaluating site for new terminal/yard/shop > Improved access to terminal bus/auto/pedestrians Recommendations to Improve Stations > Wider platforms > ADA accessibility > Improved weather and noise protection
9 I-290 Study Schedule May June July August September October November December January 2017 Stakeholder Coordination Publish DEIS Study Completion (FEIS/ROD) SUMMER 2017 Public Hearing Phase II (Design and Land Acquisition) NOT FUNDED Phase III (Construction) NOT FUNDED
10 1 st Ave. to 25 th Ave. Improvements Alternatives Evaluation Spring Initial expressway access alternatives have been identified for evaluation to determine how to provide the best overall benefits for the Village of Maywood EXISTING 24 th Ave VanBuren St. 3 s 3 s Wedgewood Dr. 25 th Ave 23 rd Ave 17 th Ave Bataan Dr. 9 th Ave 5 th Ave 1 st Ave Lexington St. VanBuren St. Alternative 24 th Ave 1 Wedgewood Dr. 25 th Ave 23 rd Ave 17 th Ave Bataan Dr. 9 th Ave 5 th Ave 1 st Ave Lexington St. ALL RAMPS INCLUDED Updated interchanges at 25 th Avenue & 1 st Avenue VanBuren St. Alternative 24 th Ave 2 Wedgewood Dr. 25 th Ave 23 rd Ave 17 th Ave Bataan Dr. 9 th Ave 5 th Ave 1 st Ave s Consolidated Lexington St. Without ramps at 9 th Avenue 2 s at 17 th Avenue Updated interchanges at 25 th Avenue & 1 st Avenue Benefits Comparison to Existing Local Travel Times 5% reduction Local Traffic Volumes 5% reduction 1 st Ave. Traffic Flow 26% improvement 1st Ave. Traffic Queues 60% improvement I-290 Safety 15% improvement I-290 Speeds 113% improvement
11 1 st Ave. to 25 th Ave. Improvements Alternatives Evaluation Spring Initial expressway access alternatives have been identified for evaluation to determine how to provide the best overall benefits for the Village of Maywood EXISTING 24 th Ave VanBuren St. 3 s 3 s Wedgewood Dr. 25 th Ave 23 rd Ave 17 th Ave Bataan Dr. 9 th Ave 5 th Ave 1 st Ave Lexington St. VanBuren St. Alternative 24 th Ave 3 Wedgewood Dr. 25 th Ave 23 rd Ave 17 th Ave Bataan Dr. 9 th Ave 5 th Ave 1 st Ave Lexington St. s Consolidated No ramps at 9 th Avenue Updated interchanges at 25 th Avenue & 1 st Avenue VanBuren St. Alternative 24 th Ave 4 Wedgewood Dr. 25 th Ave 23 rd Ave 17 th Ave Bataan Dr. 9 th Ave 5 th Ave 1 st Ave Lexington St. s Consolidated Without ramps at 9 th Avenue 2 s at 17 th Avenue Without frontage road connections at 1 st Avenue Updated interchanges at 25 th Avenue & 1 st Avenue
12 1 st Ave. to 25 th Ave. Improvements Alternatives Evaluation Spring Initial expressway access alternatives have been identified for evaluation to determine how to provide the best overall benefits for the Village of Maywood EXISTING 24 th Ave VanBuren St. 3 s 3 s Wedgewood Dr. 25 th Ave 23 rd Ave 17 th Ave Bataan Dr. 9 th Ave 5 th Ave 1 st Ave Lexington St. VanBuren St. Alternative 24 th Ave 5 Wedgewood Dr. 25 th Ave 23 rd Ave 17 th Ave Bataan Dr. 9 th Ave 5 th Ave 1 st Ave Lexington St. s Consolidated Without ramps at 9 th Avenue 2 s at 17 th Avenue Connect frontage roads to 25 th Avenue Updated interchanges at 25 th Avenue & 1 st Avenue VanBuren St. Alternative 24 th Ave 6 Wedgewood Dr. 25 th Ave 23 rd Ave 17 th Ave Bataan Dr. 9 th Ave 5 th Ave 1 st Ave ALL RAMPS INCLUDED Lexington St. Without frontage road connections at 1 st Avenue Updated interchanges at 25 th Avenue & 1 st Avenue Benefits Comparison to Existing Local Travel Times 24% reduction Local Traffic Volumes 5% reduction 1 st Ave. Traffic Flow 74% improvement 1st Ave. Traffic Queues 77% improvement I-290 Safety 9% improvement I-290 Speeds 133% improvement
13 1 st Ave. to 25 th Ave. Improvements Summary of Results Alternatives Evaluation Spring 2016 Safety, traffic, & travel related factors evaluated Local & I-290 factors Alternatives 1 & 4 have similar overall performance Alternatives 1 & 6 address community context Alternatives 1 & 6 recommended for further study
14 1 st Ave. to 25 th Ave. Improvements Alternative Recommendation Alternative 6 is recommended Alternatives Evaluation Summer 2016 Both Alternatives keep all ramps open along I-290 Alternative 6 provides 10% better travel flow on I-290 Alternative 6 provides 31% better travel flow on 1 st Ave. Alternative 6 provides 26% less vehicle stacking on 1 st Ave. Alternative 6 accommodates the predominant travel patterns to & from commercial areas in Maywood Alternative 6 has fewer pedestrian crossing points Vehicle Stacking at 1 st Avenue Average of AM & PM peak period traffic stacking Alt 1 Alt 6 Number of pedestrian crossing points Alternative 1 has six pedestrian crossing points Alternative 1 has four pedestrian crossing points Crossings will likely take more than 1 traffic signal for either alternative
15 st 1 Ave. to th 25 Ave. Improvements PROPOSED COMMON FEATURES Spring 2016 The following improvements will be included as part of a consensus plan for I-290 reconstruction. A consensus plan must address a combination of factors, including community concerns, engineering, and the environment. Bataan Dr. & Reconstruction Bataan Drive and Harrison Street will be completely reconstructed between 1st th Avenue and 25 Avenue Additional greenspace will be provided between the expressway and frontage roads in some areas Additional Green Space Bataan Dr. & fully reconstructed th 17 Ave, Cross Road Bridge Improvements: th 9 Ave, th 5 Ave Existing local bridges over I-290 will be replaced and include wider sidewalks Proposed Bridges (12 sidewalks) Maintain Existing Roadway Width Existing Bridges 5 wide sidewalks Sidewalk Widths 12 wide sidewalk 9 walk + 3 planter (optional) Safer Prairie Path No existing Avenue Prairie Path Protected crosswalk Prairie Path Modernized signals with pedestrian countdown timers Completes connection to the DesPlaines River bridge crossing to CTA Blue Line Terminal Sidewalk Widths 12 wide sidewalk 9 walk + 3 planter (optional) Planters are local cost st 1 Avenue st 1 Connection east to DesPlaines River Trail Crossing and CTA Blue Line Terminal Modern traffic signal with pedestrian crossing countdown timers High visibility crosswalks ADA Compliant sidewalks and curb ramps Drainage Improvements (see accompanying boards) Improved lighting
16 1 st Ave. to 25 th Ave. Improvements Existing Drainage Conditions Spring 2016 Village Combined Sewer System The Village of Maywood has a combined sewer Local Village Street system. Both storm water & waste water are collected in the same pipe. The Village sewers are limited in their conveyance capacity. During heavier Local street combined sewer intensity storm events, the runoff can flood the local Village streets and affect basements. Additionally, it also can add to the flooding that occurs to I-290. Combined Village storm & waste water flows to the Metropolitan Water Reclamation District s (MWRD) sewer system. Village Storm Water Overflow Area When the Maywood system is overwhelmed, water overflows to the Eisenhower Expressway, which is at a lower elevation than the Village. Expressway Pump Station The Expressway drainage system is also undersized and floods, causing expressway closures during heavy rain storms When closed due to flooding, expressway traffic reroutes through the communities
17 1 st Ave. to 25 th Ave. Improvements PROPOSED DRAINAGE IMPROVEMENTS Spring 2016 The following improvements will be included as part of a consensus plan for I-290 reconstruction. A consensus plan must address a combination of factors, including community concerns, engineering, and the environment. Improved Expressway Drainage As part of the reconstruction of I-290, the capacity of the highway drainage system will be increased, which will greatly reduce the occurrences of expressway flooding & expressway closures. Overflow from Maywood would continue to flow into the I-290 system. Additional expressway storm sewer pipe Frontage Road & Local Drainage IDOT and MWRD have collaborated to develop a drainage system plan that will improve the expressway & frontage road drainage system, while also providing a benefit to the Village of Maywood. This will be a joint effort between IDOT, MWRD and the Village of Maywood Large storm sewer pipes will be constructed under & Bataan Dr. to let stormwater flow directly to the Des Plaines River & bypass the combination sewer system. Frontage Road Future Village storm sewer connections I-290 Trunk Sewer New Frontage Road Sewer The Village will be able to extend storm sewers on the intersecting side streets, allowing for reduction of runoff within the combined sewer system. The diversion of these flows will mitigate the occurrence of street and basement flooding in the area. This will greatly reduce flooding over 141 acres of local property & reduce the amount of storm water in the combination sewer system by 17% to 26% for an additional 643 acres, which increases its level of service. New frontage road sewers drain to DesPlaines River
18 1st Ave. to 25th Ave. Improvements ALTERNATIVES EVALUATION Vehicle Stacking at 1st Avenue Alternative Recommendation Average of AM & PM peak period traffic stacking Alternative 6 is recommended BENEFITS COMPARISON Both Alternatives keep all ramps open along I Alternative 6 provides 26% less vehicle stacking 4 Alternative 6 provides 10% better travel flow on I-290 Number of pedestrian crossing points 4 Alternative 6 provides 31% better travel flow on 1st Ave. 4 Alternative 6 provides 26% less vehicle stacking on 1st Ave. 4 Alternative 6 accommodates the Alternative 1 has six pedestrian crossing points 4 Alternative 6 has four pedestrian crossing points predominant travel patterns to & from commercial areas in Maywood 4 Alternative 6 has fewer pedestrian crossing points
Maywood Town Hall Meeting. May 4, 2016
Maywood Town Hall Meeting May 4, 2016 1 AGENDA Overall I-290 Study Background Maywood Advisory Working Group (AWG) findings to date Noise Wall Update Next Steps 2 Questions? Study team members also available
More informationI-290 Phase I Study Village of Forest Park November 9, of 25
I-290 Phase I Study Village of Forest Park November 9, 2015 1 of 25 I-290 Study Area Reconstruction Section (9 miles) Re-striping Section (4 miles) 13 miles West of Mannheim Road to Racine Avenue Connects
More informationCorridor Advisory Group Meeting #21. October 15, 2015
Corridor Advisory Group Meeting #21 October 15, 2015 Agenda CAG #20 Recap Study Timeline Round 3 Wrap-Up/Results Air Quality Noise Analysis Environmental Justice Preliminary Preferred Alternative Recommendation
More informationCorridor Advisory Group and Task Force Meeting #10. July 27, 2011
Corridor Advisory Group and Task Force Meeting #10 July 27, 2011 1 Agenda Recap CAG/TF #9 Public Meeting #2 Summary Single Mode Alternatives Evaluation Results Next Steps 2 3 CAG/TF #9 Recap CAG /TF #9
More informationManaged Lanes. Steve Schilke, P.E. Major Projects Unit Head District 1. Illinois Traffic Engineering and Safety Conference October 2016
Managed Lanes Steve Schilke, P.E. Major Projects Unit Head District 1 Illinois Traffic Engineering and Safety Conference October 2016 Agenda Managed Lanes Projects I-55 (Stevenson Expressway) Express Toll
More informationComprehensive Collection of Stakeholder Alternatives by Mode
2011 Illinois Department of Transportation Comprehensive Collection of Stakeholder Alternatives by Mode October 2009 January 2011 www.dot.il.gov www.eisenhowerexpressway.com FILEY RD FILEY RD IHB RR 2
More informationInitial Alternatives Identification and Evaluation Report. November 2011 APPENDIX B. Summary of Stakeholder Single Mode Suggestions
Initial Alternatives Identification and Evaluation Report ovember 2011 APPEDIX B Summary of Stakeholder Single Mode Suggestions 2011 Illinois Department of Transportation Summary of Stakeholder Alternatives
More informationPublic Meeting #2 May 18, 2011 Comment Summary by Category
Multi-modal Options The mode of transportation which should be used is an increased option of mass transit. Light rail should be added. Express rail with Park N Rides will provide a short, safe means of
More informationTRANSPORTATION & MOBILITY VISIONING MEETING. August 23 24, 2017
TRANSPORTATION & MOBILITY VISIONING MEETING August 23 24, 2017 Project Team 1999 South Lakefront Framework Plan In 1999, the Chicago Park District authorized framework plans for three historic parks: Jackson,
More informationLawrence Avenue Streetscape Concepts August 30, 2011
Lawrence Avenue Streetscape Concepts August 30, 2011 Neighborhood Context Phase II: River to Western Ave. Phase I: Western Ave. to Clark St. Key Map Lawrence Ave. Existing Streetscape Conditions East of
More information5. RUNNINGWAY GUIDELINES
5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved
More informationOverview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them?
Overview Illinois Bike Summit IDOT Complete Streets Policy Presentation Aren Kriks, P.E. District One Bicycle Coordinator and Bureau of Programming Project Engineer History of Complete Streets IDOT Policy
More informationWELCOME. Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018
WELCOME Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018 MEETING AGENDA 1. Welcome and Introductions 2. Study Progress Update 3. Problem Statement 4. Technical Analysis
More informationClackamas County Comprehensive Plan
ROADWAYS The County s road system permits the movement of goods and people between communities and regions, using any of a variety of modes of travel. Roads provide access to virtually all property. They
More informationAPPENDIX 2 LAKESHORE ROAD TRANSPORTATION REVIEW STUDY EXECUTIVE SUMMARY
APPENDIX 2 LAKESHORE ROAD TRANSPORTATION REVIEW STUDY EXECUTIVE SUMMARY Appendix 2 City of Mississauga Lakeshore Road FINAL REPORT Transportation Review Study December 2010 EXECUTIVE SUMMARY Study Purpose
More informationOmaha s Complete Streets Policy
Omaha s Complete Streets Policy (Adopted August 2015) VISION To create great places and enhance our quality of life, the City of Omaha will provide safe, accessible streets for all users. Complete Streets
More informationBrooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017
Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn
More informationCentral Harlem Avenue Corridor Study
Attendees Central Harlem Avenue Corridor Study Steering Committee Meeting #2 Corridor Tour February 27, 2018 First Name Last Name Organization Jacob Connor CTA Nicole Campbell City of Berwyn Tomohiko Music
More informationComplete Streets Chicago: Data Driven Design. Luann Hamilton Deputy Commissioner
Complete Streets Chicago: Data Driven Design Luann Hamilton Deputy Commissioner AGENDA Chicago s goals Complete Streets & Sustainable Infrastructure Guides Data-Driven Planning Setting goals Scoping/research
More information122 Avenue: 107 Street to Fort Road
: 107 Street to Fort Road November 24, 2015 4:30 8:00 p.m. Meeting Purpose Summarize project work completed to date Share results of public input from Phase 1 Share the draft concept plan and proposed
More informationAPPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016
APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of
More informationMayor s Bicycle Advisory Council. Wednesday, December 13 th, 2017
Mayor s Bicycle Advisory Council Wednesday, December 13 th, 2017 Bicyclist Fatalities, Year to Date (January 1 November 30, 2017) - MBAC Briefing Bicyclist Fatality Statistics Year to date total, 2017
More informationSTATION #3 INITIAL ALTERNATIVES
www.dot.il.gov www.eisenhowerexpressway.com STATIO #3 IHB RR Heavy Rail Transit (HRT) High capacity transit mode serving urban areas:» Steel wheeled, high performance electric powered rail vehicles» Right-of-way
More information95 th Street Corridor Transportation Plan. Steering Committee Meeting
95 th Street Corridor Transportation Plan Steering Committee Meeting August 11, 2014 PROJECT OBJECTIVES Develop a Transportation and Economic Plan for the 95 th Street Corridor Improve public transit efficiency
More informationTerwillegar Drive Expressway Draft Concept Plan
Terwillegar Drive Expressway Draft Concept Plan Anthony Henday Drive to Whitemud Drive November 28 5:00-8:00 p.m. December 1 10:00 a.m. - 3:00 p.m. Let s Talk Today you can: Learn about the new direction
More informationTransportation Improvement Plan SECTION2
The transportation improvement plan, in combination with the land use concept plan, provides the framework for development in Romeoville s East Side TOD Area. Components included in this plan address:
More informationU.S. Route 45 (IL 132 to IL 173 and Millburn Bypass) Frequently Asked Questions
U.S. Route 45 (IL 132 to IL 173 and Millburn Bypass) Frequently Asked Questions This document provides responses to the frequently asked questions pertaining to the U.S. Route 45; IL Route 132 to IL Route
More informationNJDOT Complete Streets Checklist
Background The New Jersey Department of Transportation s Complete Streets Policy promotes a comprehensive, integrated, connected multi-modal network by providing connections to bicycling and walking trip
More informationWest Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road
West Dimond Blvd Jodhpur St to Sand Lake CSS Transportation Project Summary Municipality of Anchorage Project # 05 005 Project Manager: John Smith, P.E. (MOA PM&E) Project Administrator: Julie Makela,
More informationProposed. City of Grand Junction Complete Streets Policy. Exhibit 10
Proposed City of Grand Junction Complete Streets Policy Exhibit 10 1 City of Grand Junction Complete Streets Policy Vision: The Complete Streets Vision is to develop a safe, efficient, and reliable travel
More informationHARRISON STREET/OAKLAND AVENUE COMMUNITY TRANSPORTATION PLAN
HARRISON STREET/OAKLAND AVENUE Community Workshop #4: Draft Plan Review December 3, 2009 D E S I G N, C O M M U N I T Y & E N V I R O N M E N T INTRODUCTIONS Key Project Staff: Alisa Shen, Project Manager,
More informationWELCOME! OPEN HOUSE SHAW ROAD IMPROVEMENT PROJECT JUNE 30, 2015
WELCOME! OPEN HOUSE SHAW ROAD IMPROVEMENT PROJECT JUNE 30, 2015 Traffic Improvements Project Goals Widen roadway to construction two-way left turn lanes-greatly decreases congestion Ease access to & from
More informationComplete Streets implementation in Chicagoland
Complete Streets implementation in Chicagoland presented by Active Transportation Alliance Chicago Metropolitan Agency for Planning National Complete Streets Coalition 1 Speakers: Paul Lippens, AICP Senior
More informationPoor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns
Public Informational Meeting University Avenue (Allen Boulevard Segoe Road) March 23, 2011 City of Madison City of Middleton Village of Shorewood Hills Dane County Existing Roadway Conditions Poor pavement
More informationRESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY
RESOLUTION NO. 2018-?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY WHEREAS, safe, convenient, and accessible transportation for all users is a priority of the City of Neptune
More informationCity of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County
City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, November 10, 2016 5:30 to 7 P.M. Festival Foods 810 E. Washington
More informationTRANSPORTATION COMMISSION Agenda Staff Report
TRANSPORTATION COMMISSION Agenda Staff Report Agenda Item No. 5.a DATE: JULY 31, 2014 TO: FROM: SUBJECT: TRANSPORTATION COMMISSION COMMUNITY DEVELOPMENT DEPARTMENT - PLANNING DRAFT OLYMPIC CORRIDOR PREFERRED
More informationMASTER BICYCLE AND PEDESTRIAN PLAN
WELCOME! PLEASE FEEL FREE TO REVIEW THE EXHIBITS THE PRESENTATION WILL BEGIN AT 6:00 PM VILLAGE OF NORTHBROOK MASTER BICYCLE AND PEDESTRIAN PLAN DRAFT EXISTING CONDITIONS REPORT AND PUBLIC MEETING WELCOME!
More informationAccess Management Regulations and Standards for Minor Arterials, Collectors, Local Streets
Access Management Regulations and Standards for Minor Arterials, Collectors, Local Streets September 2009 Paul Grasewicz Access Management Administrator Concept of Access Management The way to manage access
More informationPROJECT OBJECTIVES. Improve vehicle capacity for the intersection. Improve pedestrian and bicycle access
COMMUNITY MEETING Project Update March 15, 2010 Purcellville, Virginia OVERVIEW Project need / objectives Project recap Design elements Proposed improvements Summary of project benefits / next steps PROJECT
More informationCity Avenue Projects
City Avenue Projects City Avenue Special Services District Conceived in the early 1990 s Lita Cohen, Jim Ettelson, Joe Manko, and Michael Nutter Saint Joseph s provided key start-up support. True Public/Private
More informationLANE ELIMINATION PROJECTS
PRESENTATION OUTLINE Lane Elimination Considerations Districts 4 & 7 Draft Lane Elimination Processes FDOT Lane Elimination Guidelines Example Projects D4 Case Study: SR A1A (Ft. Lauderdale) D7 Case Study:
More informationFrequently Asked Questions
Frequently Asked Questions Business US 190 in Copperas Cove From Avenue D to Constitution Drive What is access management? A. Access Management is a growing effort by government agencies to improve how
More informationExhibit 1 PLANNING COMMISSION AGENDA ITEM
Exhibit 1 PLANNING COMMISSION AGENDA ITEM Project Name: Grand Junction Circulation Plan Grand Junction Complete Streets Policy Applicant: City of Grand Junction Representative: David Thornton Address:
More informationVIII. Project Prioritization & Implementation
Transportation Plan 2030 July 2006 VIII. Project Prioritization & Implementation Public Transit Service Investigation into the development of a demand responsive service route system through a process
More informationGARLAND ROAD/GASTON AVENUE/ GRAND AVENUE INTERSECTION IMPROVEMENT STUDY
MEETING OF AFFECTED PROPERTY OWNERS AND STAKEHOLDERS GARLAND ROAD/GASTON AVENUE/ GRAND AVENUE INTERSECTION IMPROVEMENT STUDY CSJ 0009-02-067 Meeting Agenda 1 2 3 4 5 6 7 8 9 10 Opening Remarks State Representative
More informationINTRODUCTION. The focus of this study is to reduce congestion and improve mobility for all modes of transportation. Figure ES-1 Study Corridor Map
INTRODUCTION The I-280 Corridor Study is a highway planning study led by Santa Clara VTA, in partnership with the City of Cupertino and in coordination with other stakeholders in the study area. The study
More informationNEPA/404 Materials and Correspondence I-290 Eisenhower Expressway Cook County, Illinois
Appendix NEPA/404 Materials and Correspondence I-290 Eisenhower Expressway Cook County, Illinois Prepared For: Illinois Department of Transportation Prepared By: WSP Parsons Brinckerhoff December 2015
More informationPaoli Road Improvement Feasibility Study
Paoli Road Improvement Feasibility Study & Public Participation Project March 24, 2015 Prepared for: Tredyffrin Township Prepared by: McMahon Associates, Inc. with Town Planning Partnership, LLC Glackin
More informationFM 1092/Murphy Road Access Management Study Pulic Meeting #1. Wednesday, August 31, :00 p.m. 8:00 p.m.
FM 1092/Murphy Road Access Management Study Pulic Meeting #1 Wednesday, August 31, 2011 6:00 p.m. 8:00 p.m. Introductions Agency Partners H-GAC Missouri City TxDOT Introductions Consulting Team In Association
More informationEvaluation of Alternatives and Options For the City of Windsor Sam Schwartz Engineering PLLC January 2005
Evaluation of Alternatives and Options For the City of Windsor Sam Schwartz Engineering PLLC January 2005 Image courtesy of Canadian Transit Company Overview of Presentation Background Evaluation of River
More informationNon-Motorized Transportation 7-1
Non-Motorized Transportation 7-1 Transportation facilities no longer mean just accommodating a vehicle powered by a combustion engine. Pedestrian and non-motorized facilities are important modes of travel
More informationCity of Moorhead Committee of the Whole Meeting
City of Moorhead Committee of the Whole Meeting Corridor Study Limits Center Avenue (Red River to 8th Street) TH 10 (Red River to TH 336) TH 75 (20th Ave S to Main Avenue) 2 Study Need: Project Overview
More information3.9 Recreational Trails and Natural Areas
3.9 Recreational Trails and Natural Areas 3.9.1 Introduction Parks and other recreational facilities such as trails, bicycle routes, and open space are important community resources. This section discusses
More informationMunicipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018
Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Background Agenda Traffic Study Update Class EA Alternatives Bridge
More informationFEASIBILITY STUDY MACARTHUR BOULEVARD
FEASIBILITY STUDY MACARTHUR BOULEVARD Wabash Avenue to South Grand Avenue Springfield, IL SANGAMON COUNTY TABLE OF CONTENTS 1.0 DESCRIPTION & PURPOSE AND NEED OF STUDY... 1 2.0 EXISTING CONDITIONS... 2
More informationLong Island Rail Road Expansion Project Floral Park to Hicksville
Long Island Rail Road Expansion Project Floral Park to Hicksville Final Environmental Impact Statement Appendix 1-D Complete Streets Policy Checklist April 2017 0902ML PIN: Project Location: 18A-4 Floral
More informationEnvironmental Assessment Findings & Recommendations. Public Hearing November 13, 2014
Environmental Assessment Findings & Recommendations Public Hearing November 13, 2014 Welcome! Welcome and Introductions Project and Environmental Assessment Overview Public Comments Adjourn Purpose of
More informationMission-Geneva Transportation Study Community Workshop 2 July 8, 2006
Community Workshop 2 July 8, 2006 Small Group Workbook 1 Basic Improvements on Mission Street Streetscape. Pedestrian-scale lighting; landscaping; community art on utility boxes; more (possibly unique)
More informationDr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018
Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 What s Happening The City plans to mill and resurface Dr. M.L.
More informationPRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN
PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations
More informationNEWMARKET UPHAM S CORNER
SOUTH STATION Planning Initiative NEWMARKET UPHAM S CORNER COLUMBIA ROAD (P) FOUR CORNERS/GENEVA Working Advisory Group (WAG) Meeting #5 TALBOT AVENUE MORTON STREET BLUE HILL AVE/CUMMINS HWY (P) RIVER
More informationUS 20 Feasibility Study. Village Board Meeting. Shales Parkway to IL Route 390 IL Route 390 Extension (North Ave to US 20)
US 20 Feasibility Study Shales Parkway to IL Route 390 IL Route 390 Extension (North Ave to US 20) Village Board Meeting Bartlett Village Hall February 16, 2016 1 Background 1991 IDOT Study Recommendations
More informationNorth Avenue Corridor Study
North Avenue Corridor Study City Council October 6, 2014 Presentation Outline Project Initiation & Process Corridor Conditions & Issues Vision & Goals Concept Development - Development/Evaluation Implementation
More informationAbout the study. North Milwaukee Ave. Key goals of this study are to: Achieve Vision Zero* by. Harmonize the space and improve walkability
About the study Key goals of this study are to: North Milwaukee Avenue is a local and regional street for multiple modes of transportation. It is officially zoned and functions as a pedestrian street southeast
More informationCommerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue
Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue T A N Y A B R O O K S A S S I S T A N T D I R E C T O R M O B I L I T Y P L A N N I N G M O B I L I T Y A N D S
More informationADA TRANSITION PLAN 2013
ADA TRANSITION PLAN 2013 TABLE OF CONTENTS Contents Introduction 1 Purpose 2 Identified Obstacles to the Public Right of Way 3 Criteria for Determining Impediments at Village Facilities 4 Removing Barriers
More informationTOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY
TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY I. VISION, GOALS & PRINCIPLES VISION To improve the streets of Portland making them safer and more accessible for all users including pedestrians,
More informationFulton Market Streetscape
Fulton Market Streetscape Ogden Avenue to Halsted Street Public Meeting Recommended Improvements December 10th, 2014 Meeting Purpose and Goals Present Existing Conditions Community Input and Charrette
More informationPine Hills Road Pedestrian/Bicycle Safety Study Board of County Commissioners Work Session
Pine Hills Road Pedestrian/Bicycle Safety Study Board of County Commissioners Work Session February 20, 2018 Meeting Agenda Study Overview Existing Conditions Access Management Potential Gateway Features
More informationFM #: ETDM #: 11241
SR 826/Palmetto Expressway PD&E Study From SR 93/I 75 to the Golden Glades Interchange FM #: 418423 1 22 01 ETDM #: 11241 Agency/ Kick Off Meeting October 27, 2011 2 Location Map From SR 93/I 75 to Golden
More informationCentral Harlem Avenue Corridor Study
Central Harlem Avenue Corridor Study Steering Committee Meeting #1 January 18, 2018 Berwyn Public Library First Name Last Name Organization Cindy Cambray CMAP Tony Manno CMAP Jacob Connor CTA Nicole Campbell
More informationSession 1 23 CFR 772: Type I Project Definitions
Session 1 23 CFR 772: Type I Project Definitions Facilitator: Carole Newvine, Oregon DOT Participants: Carole Newvine, Oregon DOT Mariano Berrios, Florida DOT Tom Hanf, Michigan DOT Greg Smith, North Carolina
More informationAccess Management Regulations and Standards
Access Management Regulations and Standards Efficient highway operation Reasonable property access Concept of Access Management The way to manage access to land development while simultaneously preserving
More informationVDOT I-66 Inside the Beltway Eastbound Widening Environmental Assessment. Staff Recommendations
VDOT I-66 Inside the Beltway Eastbound Widening Environmental Assessment Staff Recommendations Department of Environmental Services Transportation January 28, 2017 Timeline of Transform66 June 2012: I-66
More informationAccess Management Regulations and Standards
Access Management Regulations and Standards January 2014 Efficient highway operation Reasonable property access Concept of Access Management The way to manage access to land development while preserving
More informationAgenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN
PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations
More informationState Road 54/56 Tampa Bay s Northern Loop. The Managed Lane Solution Linking I-75 to the Suncoast Parkway
State Road 54/56 Tampa Bay s Northern Loop The Managed Lane Solution Linking I-75 to the Suncoast Parkway SUNCOAST PARKWAY Both I 75 and the Suncoast Parkway are planning, or in the process of constructing,
More informationWatertown Complete Streets Prioritization Plan. Public Meeting #1 December 14, 2017
Watertown Complete Streets Prioritization Plan Public Meeting #1 December 14, 2017 Goals for Public Meeting Overview of MassDOT Complete Streets Funding Program Educate the community on Complete Streets
More informationCity of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE
Welcome Welcome to the third community meeting for the Issaquah-Fall City Road Improvements Project. AGENDA 6:00 p.m. Welcome and sign-in 6:10 p.m. Presentation 6:50 p.m. Open house Learn about the roadway
More informationCity of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County
City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, April 28, 2016 6 to 8 P.M. Lapham Elementary School 1045 E. Dayton
More informationPlanning Study SR 976. Project Advisory Team Meeting May 24, 2017
` SR 976 BIRD ROAD/SW 40TH STREET FROM SR 821/HEFT TO SR 5/US-1 Miami-Dade County, Florida FPID No.: 434845-4-22-01 Planning Study Project Advisory Team Meeting May 24, 2017 1 Agenda Introductions Project
More informationCity of Seattle Edward B. Murray, Mayor
City of Seattle Edward B. Murray, Mayor Department of Transportation Scott Kubly, Director Eastlake Community Council 117 E Louisa St. #1 Seattle, WA 98102-3278 January 28, 2016 RE: Roosevelt to Downtown
More informationElmhurst Metra Station. Public Hearing Wednesday - November 30, 2016
Elmhurst Metra Station Public Hearing Wednesday - November 30, 2016 Agenda Introduction to Hearing Format - Presentation (20 Minutes) - Exhibits/Workstations - Record (Comment Cards, Court Reporter)
More informationSafe Routes to School Action Plan Aberdeen, Idaho
Background Aberdeen, Idaho is a largely agricultural community of nearly 2,000 people and is located in the southeast portion of the state on the western edge of American Falls Reservoir. The community
More informationAmericans with Disabilities Act Transition Plan for Public Right-of-Way Improvements
Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements Prepared by: Public Works Department Engineering Division October 2015 Table of Contents Section I Introduction.. 3
More informationMeeting Summary Public Information Meeting #1 Warren County Pathway Corridor Project September 27, 2018
Meeting Summary Public Information Meeting #1 Warren County Pathway Corridor Project September 27, 2018 The first public information meeting for the Warren County Pathway Corridor Project was held on Thursday,
More informationBlue Ribbon Commission Report Recommendations on Pedestrian and Bicycle Infrastructure Improvements
Recommendations on Pedestrian and Bicycle Infrastructure Improvements July 2017 Plan Development: Our committee consisted of seven individuals appointed by the Mayor and Village Board. Those members included:
More informationCapital Metro Downtown Multimodal Station
Capital Metro Downtown Multimodal Station Open House December 11, 2015 Project Goals & Objectives 1 2 3 4 Address near- and long- term MetroRail operational needs Address existing safety issues and modal
More informationSR 693 (Pasadena Avenue) Corridor Study from Shore Drive South to 66 th Street
Welcome and Introduction Sign-in and comment sheets Restrooms and exits Meeting agenda and timeline Meeting goals / expectations Provide input to guide study recommendations Actively participate throughout
More informationTRANSPORTATION NEEDS ASSESSMENT
TRANSPORTATION NEEDS ASSESSMENT A travel demand analysis was carried out to determine the operational issues and the potential benefit that adding traffic capacity would have on the road network. All the
More informationFreeway System Considerations
Session 11 Jack Broz, PE, HR Green May 5-7, 2010 Freeway System Considerations Mainline Transit: Shoulder Operations, BRT, Stations HOV, HOT, UPA Interchanges Exit Ramps Entrance Ramps Bridges Local Crossings
More informationSection 7 Complete Green Street Guidelines DRAFT
Section 7 Complete Green Street Guidelines DRAFT 1 Section: 7.0 COMPLETE GREEN STREET GUIDELINES These guidelines serve as options to mitigate the environmental impact of a project as well as guide the
More informationI-10 AT SCENIC LOOP RD. Open House
I-10 AT SCENIC LOOP RD Open House General Information I-10 At Scenic Loop Rd KENDALL COUNTY OPEN HOUSE June 30, 2015 Currey Creek Baptist Church 35 Cascade Cavern 5:00 7:00 Boerne, TX 78015 2 Public Meeting
More informationS T A T I O N A R E A P L A N
The Circulation and Access Plan describes vehicle, pedestrian, and transit improvements recommended within the Concept Plan. In order to create and sustain a vibrant business district that provides pedestrian-friendly
More informationHennepin County Pedestrian Plan Public Comment Report
Hennepin County Pedestrian Plan Public Comment Report On May 31, 2013, the draft Hennepin County Pedestrian Plan was released for a 45-day public comment period ending July 15, 2013. The county received
More informationPublic Information Meeting. Warren County Pathway Corridor Project September 27, 2018
Public Information Meeting Warren County Pathway Corridor Project September 27, 2018 Why are we here? Introduce Study Hear concerns and Ideas Obtain input on preliminary Alternatives Previous Study (2008)
More informationPREFERRED ALTERNATIVE IMPLEMENTATION PLAN. Prepared for. Ohio Department of Transportation, District South SR 741 Lebanon, Ohio 45036
HAM-32F-0.00 PID 86461 PREFERRED ALTERNATIVE IMPLEMENTATION PLAN Prepared for Ohio Department of Transportation, District 8 505 South SR 741 Lebanon, Ohio 45036 Prepared by URS Corporation 564 White Pond
More informationLos Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation
Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto
More informationBETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY
DRAFT PLAN City Council Meeting August 14, 2017 STUDY AREA Sedgwick Corridor State Route 160, principal arterial with Class 3 access management designation, commuter and freight route, connection to SR
More information