High Pressure Iron (HPI) Recertification Guidelines & Procedures
|
|
- Melvyn Floyd
- 6 years ago
- Views:
Transcription
1 Page 1 of 5 HPI Shop 6201 Andrews Hwy Odessa, Tx Ph: Fx: Howard Supply Company High Pressure Iron (HPI) Recertification Guidelines & Procedures
2 Page 2 of 5 Purpose The purpose of this document is to represent Howard Supply Company's (HSC) standard operating procedures (SOP) used in inspection, repair, testing, and recertifying high-pressure iron (flow control and stimulation equipment). This SOP is to ensure that all products serviced by HSC meet, or exceed Customer, OEM, and/or Industry Standards/Specifications. Scope - HPI Inspection & Recertification Processes performed by HSC (as a third party), are to ensure that a customer s HPI equipment is free of flaws, damages, defects, or excessive wear that would render the equipment out of conformance and unsafe for use under high pressures and/or it s intended application. Types of inspection performed by HSC, dependent upon Customer Specified Recertification Level: Visual, Ultrasonic Thickness (UT), Hydrostatic Pressure Test (PT) & Magnetic Particle (MPI). Responsibility Technician Qualifications Level 1 - HPI Technician Onsite and/or prior experience & training of processes, measurements (Non-NDE related) and procedures. Duties could include teardown, clean up, dimensional measuring/gauging, visual inspections, service/repairs, re-assembly, blasting, painting, and pressure testing. Level 2 HPI Technician All requirements of Level 1 HPI Technician plus Certificate of Training for Level 1 or 2 NDE (either MPI or UT) Level 3 HPI Technician All requirements of Level 1 HPI Technician plus Certificate of Training for Level 2 NDE (both MPI & UT) * Certificate of Training to be conducted and approved by ASNT Level 3 Certified Personnel
3 Page 3 of 5 Section 1 - Inspection Visual Inspection: (Required for Recertification) A thorough visual inspection will be performed on every piece of High-Pressure Iron (HPI). The visual inspection will include all visible surfaces (internal & external) and all components of the assembly to identify any flaws, damages, defects or excessive wear. Visual Inspections will be performed in all stages of the recertification process: Prior to beginning any work After contaminates (paint, rust, grease, etc.) are removed After disassembly (if applicable) During reassembly (if applicable) Prior to Hydrostatic Pressure Testing (PT) Prior to customer delivery Ultrasonic Thickness Inspection (UT): (Required for Recertification) Ultrasonic Thickness Inspections will be performed on every piece of High Pressure Iron (HPI). The UT process will verify that wall thicknesses meet acceptable minimum specifications, and that no material defects exist. UT readings will be taken at multiple locations, sufficient to ensure product is within compliance. Hydrostatic Pressure Test (PT): (Required for Recertification) Hydrostatic Pressure Testing will be conducted on every piece of High Pressure Iron (HPI), excluding flanges and swages (optional). HPI will be tested to its specified Cold Working Pressure (CWP) rating for a minimum of 3 continuous minutes, or longer if needed to meet customer specifications. Manifold Trailers will undergo PT at CWP for a minimum of five minutes. Magnetic Particle Inspection (MPI): (Optional Performed per Customer Request) Magnetic Particle Inspection is optional, and will only be performed per customer request. MPI is the best option for detecting cracks and other surface indications undetectable by the human eye during visual inspection. Due to the nature of the operation of Manifold Trailers, HSC recommends that MPI be performed on all components that make up the assembly. Inspection Rejections: All High-Pressure Iron (HPI) that fails any of the inspection processes will be documented, marked appropriately and disposed of per customer guidance. HSC can offer permanent deformation of failed HPI and disposal at no additional expense to customer. If failed HPI is to be returned to customer, all existing ID/Certification Bands will be removed (Cut-off) and returned separately to further ensure the iron doesn t mistakenly get returned to service.
4 Page 4 of 5 Section 2 High Pressure Iron Recertification Levels Level 1 HPI Recertification: Level 1 Recertification is a basic level of inspection/recertification, and does not include the complete disassembly of the item. Wing nuts and segments are removed to expose all inspection points (if applicable). Sub ends (male, female and threaded) are cleaned for thorough visual and NDE inspection. UT inspection is performed at various OEM and/or customer specified locations for minimum wall thickness. Nuts are ground to remove and repair irregularities of the wings. Seals and retainer rings are replaced, and properly lubricated. Equipment passing inspection is Hydrostatic Pressure Tested (PT) at Cold Working Pressure (CWP). Equipment is banded with HSC, the unique ID#, date tested, CWP and Customer Name. Equipment failing initial PT can be moved to Level 2 Recertification, per customer request, if the problem appears to be correctable by a complete rebuild. Inspection reports are prepared and provided to the customer in either hard copy or digital format. Level 2 HPI Recertification All the benefits of Level 1 Recertification, plus complete disassembly and rebuild, including all new rebuild kits. HSC recommends Level 2 Recertification whenever possible to ensure the most thorough inspection and preventative maintenance is performed. HSC Level 2 Inspection and Recertification not only ensures operational compliance, but also a higher level of safety assurance and extended life of the equipment. Recertification Service Level 1 Level 2 Remove Wing Nut / Segments X X Clean Sub Ends X X Visual Inspection X X Ultrasonic Testing (UT) X X Grinding Wing Nuts X X Magnetic Particle Inspection (MPI) Optional Optional Disassemble / Re-Kit / Rebuild Lev 2 Only X Hydrostatic Pressure Test Cold Working Pressure (CWP +5%/-0%) X X Banding (HSC, ID#, Date, CWP & Customer Name) X X Paint Optional Optional Inspection Reports X X HSC guarantees product conformity at the time of shipment/delivery to customer. Customer is responsible for supplying proper training in product use to ensure the integrity of product conformance is preserved through proper handling and use. All product(s) that have been modified or damaged through misuse, abuse, accident, neglect, or mishandling should be removed from service immediately and sent through the inspection & recertification process.
5 Page 5 of 5 Section 3 High Pressure Iron Documentation Equipment Quick Reference: (Requirements & Options) Equipment Level 1 Level 2 Visual UT MPI PT Ball Injector Required Optional Required Required Optional Required Bull Plug Required N/A Required Required Optional Required Check Valve Required Optional Required Required Optional Required Cross Required N/A Required Required Optional Required Crossover Required N/A Required Required Optional Required Ell Required N/A Required Required Optional Required Flange Required N/A Required Required Optional N/A Hose Loop Required Optional Required Required Optional Required Lateral Required N/A Required Required Optional Required Plug Manifold Required Optional Required Required Optional Required Plug Valve Required Optional Required Required Optional Required Pressure Relief Valve Required Optional Required Required Optional Required Pup Joint Required N/A Required Required Optional Required Swage Required N/A Required Required Optional N/A Swivel Joint Required Optional Required Required Optional Required Tee Required N/A Required Required Optional Required Wye Required N/A Required Required Optional Required Banding Process: If equipment arrives banded from prior certification, band will remain affixed until such time as the equipment has passed all stages of inspection and is ready to have new recertification band attached. HSC uses uncoated stainless steel bands as a normal practice, however coated-color stainless steel bands are available per customer request to meet customers color coding scheme. No equipment is deemed Safe and/or Approved for operation without a band. (If items physical shape doesn t allow for band to be affixed, Certification Criteria will be Stamped or Stenciled directly onto item). Reporting & Traceability: The following information will be recorded into HSC s online High Pressure Iron Management Database and will be accessible to our customer s: HSC Job# Job Date HSC Location Customer Customer Location Customer Unit# Inspection Results UT Results Inspection Level HSC ID# Item Description CWP Test Pressure *Affixed to each inspection report will be the Hydrostatic Pressure Test Results in Chart Form. Please make sure to initial and date each page and complete the below information. Customer Name: Customer Representative (Print): Customer Representative (Sign):
Product Bulletin No.: D99-RRV2015-PIB-001
Product Bulletin No.: D99-RRV2015-PIB-001 Titan BX Automatic Pressure Relief Valves Issue Date: April 22, 2016 Subject: Product: Affected Assemblies Objectives: Structural failure of a Titan Type BX pneumatically-operated
More informationTechnical Standard. API6D Ball & Plug Valve. Inspection & Test Procedure
Technical Standard API6D Ball & Plug Valve Inspection & Test Procedure 1 Scope This standard provides specific inspection items to be performed on all ball & plug valves. The valves shall be provided with
More informationBVM CORPORATION TYPE AAX TONG 55,000 FT/LBS. TORQUE Part number: Serial Number:
BVM CORPORTION TYPE X TONG 55,000 FT/LBS. TORQUE Part number: Serial Number: WRNING: Manual tongs which have experienced excessive wear or are found to have cracks should be replaced or repaired by BVM
More informationInstallation, Operation and Maintenance Manual for Back Pressure Regulator
Installation, Operation and Maintenance Manual for Back Pressure Regulator Model 8860 2009 Groth Corporation IOM-8860 Rev. B 12541 Ref. ID: 95565 Page 2 of 13 Table of Contents I. INTRODUCTION 3 II. DESIGN
More informationWHEATLEY Series 500 Swing Check Valve
Document Number: TC003001-13 Revision: 02 WHEATLEY Series 500 Swing Check Valve Installation, Operation, and Maintenance Manual TABLE OF CONTENTS BILL OF MATERIALS...3 SCOPE...5 INSTALLATION AND OPERATION
More informationP-04 Stainless Steel Corrugated Hoses and Metal Bellows Expansion Joints
Guideline No.P-04 (201510) P-04 Stainless Steel Corrugated Hoses and Metal Bellows Expansion Joints Issued date: 20 th October 2015 China Classification Society Foreword This Guideline is a part of CCS
More informationTHE PROCESS OF JOINT INTEGRITY
BOLTED JOINTS A.333 THE PROCESS OF JOINT INTEGRITY To assist in managing a process, ask yourself the following questions: why, what, who, and how? Why do we need a Flange Joint Integrity program? This
More informationTBV OPERATION AND MAINTENANCE MANUAL SERIES 2800: FLANGED BALL VALVE. For technical questions, please contact the following:
TBV OPERATION AND MAINTENANCE MANUAL SERIES 2800: FLANGED BALL VALVE For technical questions, please contact the following: Engineering Department 1537 Grafton Road Millbury, MA 01527 Phone: (508) 887-9400
More informationWHEATLEY WHEATLEY SERIES 500 SWING CHECK VALVE. Installation, Operation and Maintenance Manual
WHEATLEY SERIES 500 SWING CHECK VALVE STANDARD INTEGRAL SEAT & OPTIONAL REMOVABLE SEAT 2" FP - 6" FP 150# - 1500# 8" FP - 12" FP 150# - 900# API 6D and B16.34 2" FP - 4" FP 5000# DRILLING PRODUCTION VALVE
More informationDate of Issue: July 2016 Affected Publication: API Specification 16C, Choke and Kill Equipment, Second Edition, March 2015 ADDENDUM 1
Date of Issue: July 2016 Affected Publication: API Specification 16C, Choke and Kill Equipment, Second Edition, March 2015 ADDENDUM 1 Page 16, Section 4.6, delete the entire section and renumber all subsequent
More informationCLASS D - SENSITIVE LEAK TEST GAS AND BUBBLE METHOD. 1.1 To provide definitive requirements for PNEUMATIC pressure testing of piping systems.
Page 1 of 7 CLASS D - SENSITIVE LEAK TEST GAS AND BUBBLE METHOD 1. SCOPE 1.1 To provide definitive requirements for PNEUMATIC pressure testing of piping systems. 1.2 The piping system as used herein is
More informationApollo Standard Port, Full Port & One Piece Flanged Ball Valves Installation, Operation, & Maintenance Manual
I854000.D Apollo Standard Port, Full Port & One Piece Flanged Ball Valves Installation, Operation, & Maintenance Manual Introduction This manual presents guidelines for the Installation, Operation and
More informationSpilt body Flange ball valve. TC-205MFF-PN1640 User Manual English Version. Document No: TC-205MFF-PN1640.Ur-manual. Date: 2007/04/2617. Version: 1.
Spilt body Flange ball valve TC-205MFF-PN1640 Series PED Category I,II TC-205MFF-PN1640 User Manual English Version Use for company in Europe who will place the product on the market, please amend which
More informationPRESSURE RETEST. 49 CFR, (g) Co#: Vin#: DOT Spec: MAWP:
PRESSURE RETEST 49 CFR, 180.407(g) Co#: Vin#: Spec: MAWP: Retest Date: Location: *External Inspection Performed: *Internal Inspection Performed: Test Pressure: psig Held for: min. (Must be at least 10
More informationTelefon (+45) Telefax (+45)
Uni-Valve A /S VENTILER & INSTRUMENTER Telefon (+45) 43 43 82 00 Telefax (+45) 43 43 74 75 mail@uni-valve.com www.uni-valve.com UNI-S83 / S84 3/4-way ball valve Installation and Operating manual 3/4-WAY
More informationWHEATLEY Series 822/820 Swing Check Valve
Document Number: TC003001-12 Revision: 02 WHEATLEY Series 822/820 Swing Check Valve Installation, Operation, and Maintenance Manual TABLE OF CONTENTS BILL OF MATERIALS...3 SCOPE...4 INSTALLATION AND OPERATION
More informationKMB 18/28 (BANDMASK) OVERHAUL, MAINTENANCE, AND INSPECTION CHECKLIST APPENDIX A
KMB 18/28 (BANDMASK) OVERHAUL, MAINTENANCE, AND INSPECTION CHECKLIST APPENDIX A2.1 01-31-17 THIS INSPECTION AND MAINTENANCE SHOULD BE PERFORMED AT LEAST ANNUALLY AND AS DICTATED BY CONDITION REVEALED DURING
More information3-PIECE BALL VALVE, 3600 PSI/ PN 248, WITH ISO DIRECT MOUNTING PAD 306M SERIES/ PED Category II
3-PIECE BALL VALVE, 3600 PSI/ PN 248, WITH ISO DIRECT MOUNTING PAD 306M SERIES/ PED Category II 306M User Manual English Version Use for company in Europe who will place the product on the market, please
More informationRS(H)10,15 USER MANUAL. Read the complete manual before installing and using the regulator.
RS(H)10,15 USER MANUAL Read the complete manual before installing and using the regulator. WARNING INCORRECT OR IMPROPER USE OF THIS PRODUCT CAN CAUSE SERIOUS PERSONAL INJURY AND PROPERTY DAMAGE. Due to
More informationAmerican Society of Sanitary Engineering PRODUCT (SEAL) LISTING PROGRAM
American Society of Sanitary Engineering PRODUCT (SEAL) LISTING PROGRAM ASSE STANDARD #1003 - REVISED: 2009 Water Pressure Reducing Valves for Domestic Water Distribution Systems MANUFACTURER: CONTACT
More informationSECTION BUTTERFLY VALVES
SECTION 15112 BUTTERFLY VALVES PART 1 GENERAL 1.01 SUMMARY A. All butterfly valves shall be of the tight closing, rubber seated type and fully comply with the latest revision of AWWA Standard C504, Class
More informationSAPAG. Safety valves, type 5700 Storage, Use, Operation and Maintenance Instructions. IMPORTANT NOTICE
SAPAG IMPORTANT NOTICE Contents Important notice 1 0 Valve identification 2 1 Storage 2 2 Installation 2 3 Operation 2 4 Maintenance 3 4.1 Dismantling 3 4.2 Inspection 3 4.3 Repair 3 4.4 Assembly 4 4.5
More informationMANUAL: Jumbo Siamese and Jumbo Wye
TASK FORCE TIPS FIRE FIGHTING EQUIPMENT MANUAL: Jumbo Siamese and Jumbo Wye INSTRUCTIONS FOR SAFE OPERATION AND MAINTENANCE Read instruction manual before use. Operation of this device without understanding
More informationRegulated Oil and Gas Companies under National Energy Board Jurisdiction
File 185-A000-41 8 August 2003 Regulated Oil and Gas Companies under National Energy Board Jurisdiction Dear Sir / Madam: Guidance Notes for Pressure Equipment under National Energy Board Jurisdiction
More informationOMG Southeast & Southwest RIGGING SAFETY PROGRAM (29 CFR Part , , , , , & ANSI B30.5, ANSI B30.
OMG Southeast & Southwest RIGGING SAFETY PROGRAM (29 CFR Part 1926.251, 1926.550, 1910.180, 1910.184, 1910.330, & ANSI B30.5, ANSI B30.8) Nearly every project is required to perform some type of rigging
More informationTactAir PCP Fill Kit/Adapter. Operation Manual
TactAir PCP Fill Kit/Adapter Operation Manual INTRODUCTION Thank you for choosing a TactAir PCP fill accessory! Always exercise caution when operating this item. It will allow you to fill your PCP airguns
More informationSterile Visual Flow Indicator
Sterile Visual Flow Indicator Sanitary Process Connection Installation / Operation / Maintenance Manual P.O. Box 1116 Twinsburg, OH 44087 Phone: 330/405-3040 Fax: 330/405-3070 E-mail: view@ljstar.com Web
More informationINSPECTORATE FOR DIVING EQUIPMENT SERVICING & TESTING CODE OF PRACTICE CP11:2011
D003 INSPECTORATE FOR DIVING EQUIPMENT SERVICING & TESTING CODE OF PRACTICE CP11:2011 For INSPECTING and TESTING Transportable Pressure Receptacles (Cylinders) for Breathing Gases manufactured from Steel
More informationINSPECTION OF RECOVERY BOILERS
INSPECTION OF RECOVERY BOILERS W. B. A. (Sandy) Sharp SharpConsultant, Columbia, Maryland, U.S.A. TAPPI Kraft Recovery Short Course St. Petersburg, Florida, January 7-10, 2008 OUTLINE Purpose of inspections
More informationSTANDARD SPECIFICATION FOR SPLIT TEES (HOT TAP MATERIAL)
STANDARD SPECIFICATION FOR SPLIT TEES (HOT TAP MATERIAL) TEE (HOT TAPPING MATERIAL) S-04-02-040 Page 1 of 7 1.0 SCOPE This specification covers the basic requirements for the design, manufacture and supply
More informationHYDROSTATIC LEAK TEST PROCEDURE
This information is proprietary and shall not be disclosed outside your organization, nor shall it be duplicated, used or disclosed for purposes other than as permitted under the agreement with Kinetics
More informationSPECIFICATIONS - DETAILED PROVISIONS Section Butterfly Valves C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 15103 - Butterfly Valves C O N T E N T S PART 1 - GENERAL... 1 1.01 REQUIREMENT... 1 1.02 VALVE MANUFACTURER... 1 1.03 GUARANTEE... 1 PART 2 - PRODUCT... 1
More informationExternal-Style Pressure Relief Valve A Series. Installation, Operation & Maintenance (IOM) Manual. P/N: A-19075, Rev. 2.2
P/N: Issue Date: September 26, 2018 Supersedes: A-19075, Rev. 2.1 External-Style Pressure Relief Valve A-19075 Series Installation, Operation & Maintenance (IOM) Manual Manual content is subject to change.
More informationGuide for Evaluating Your Hose Assembly Supplier
Guide for Evaluating Your Hose Assembly Supplier Supplier Evaluation Checklist, and How to Clearly Define Application Requirements Safe, reliable hose assemblies require appropriate specification work
More informationInstallation and Service Manual
An Actuant Company Installation and Service Manual Heavy Duty Hydraulic Stabilization Legs CONTENTS Part # 3010003129 REV 0D Section Page 1.0 Receiving Instructions 2 2.0 Safety Issues 2 3.0 Hydraulic
More informationPressure Equipment Directive PED 2014/68/EU Commission's Working Group "Pressure"
F. INTERPRETATION OF THE ESSENTIAL SAFETY REQUIREMENTS ON MANUFACTURING Guideline F-01 Guideline related to: Annex 1 Section 3.1.2 According to section 3.1.2 (permanent joining) of Annex I, the third party
More informationAmerican Society of Sanitary Engineering PRODUCT (SEAL) LISTING PROGRAM
American Society of Sanitary Engineering PRODUCT (SEAL) LISTING PROGRAM ASSE STANDARD #1048 - REVISED: 2009 Double Check Detector Fire Protection Backflow Prevention Assemblies Separate, complete laboratory
More informationWKM Model 320F Floating Ball Valve
Date: 4 WKM Model 320F Floating Ball Valve Installation, Operation, and Maintenance Manual 1 Date: 4 All the information contained in this manual is the exclusive property of Cameron. Any reproduction
More information// ADapters GUIDelines
// ADapters GUIDelines ADAPTER SELECTION Selection of an appropriate ALFAGOMMA adapter for a given application depends on the fluid system operating parameters listed below and the tube material and wall
More informationAluminum 13 cu tank Includes regulator Fill pressure: 3,000 psi (200 bar) Output: 1,100 psi +/- 10% (75bar)
Aluminum 13 cu tank Includes regulator Patent numbers: 6,851,447 7,059,343 7,051,751 Fill pressure: 3,000 psi (200 bar) Output: 1,100 psi +/- 10% (75bar) Contents Safety system... 3 Fill your tank... 4
More informationPIP PNE00012 Piping Examination and Leak Test Guide
October 2017 Piping PIP PNE00012 Piping Examination and Leak Test Guide PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process industry facilities, this Practice has
More informationFluid Sealing Association
Fluid Sealing Association STANDARD FSA-PSJ-701-06 PIPING SYSTEMS NON-METALLIC EXPANSION JOINT HYDROTESTING AND VACUUM TESTING 994 Old Eagle School Road, Suite 1019 Wayne, Pennsylvania 19087-1866 Phone:
More informationproduct use, care, & inspection Document Released: January, 10, 2012 Approved By: Bryce Merrick
product use, care, & inspection Document Released: January, 10, 01 Approved By: Bryce Merrick product use, care, & inspection Contents product use 03 product warning 03 tuff bucket ANATomy 04 how to properly
More informationBeverage Systems. Component Inspection and Service TSB-Y Date: Subject: Products Affected: Description: July Inspection of CO 2
Component Inspection and Service Beverage Systems Technical Service Bulletin TSB-Y10-007 Date: July 2006 Subject: Inspection of CO 2 Pressure Control Circuits Products Affected: All Chart Beverage Systems
More informationSALCO PRODUCTS, INC. PRESSURE RELIEF VALVE STORAGE, INSTALLATION, OPERATING, MAINTENANCE/TESTING, AND INSPECTION INSTRUCTIONS
STORAGE INSTRUCTIONS Until it is time to install a new or reconditioned valve on the car, the valve must be kept in its original packaging in order to protect it from dirt and damage. INSTALLATION INSTRUCTIONS
More informationSummary of Accumulators These operating instructions apply to the accumulators listed in the table shown below.
Page 1 of 15 Summary of Accumulators These operating instructions apply to the accumulators listed in the table shown below. Model Number A25-XXXX-3.6K Series A40-XXXX-3K Series A40X-XXXX-3.6K Series A60-XXXX-3K
More informationSTANDARD METHOD OF IMPACT TEST AND PERFORMANCE REQUIREMENTS FOR FOOTBALL FACEGUARDS. NOCSAE DOC ND087-17m17c
STANDARD METHOD OF IMPACT TEST AND PERFORMANCE REQUIREMENTS FOR FOOTBALL FACEGUARDS NOCSAE DOC ND087-17m17c Prepared by NATIONAL OPERATING COMMITTEE ON STANDARDS FOR ATHLETIC EQUIPMENT Revised: January
More informationGeneral Performance Data Hose Ref Minimum Bend. Safety Pressure at 20 C (BAR) Working Pressure at. Flow Rate at 3 bar (lit/min) Working Pressure
The Classic range provides a safe and taint free conveyance of potable water supplies for Domestic and Commercial plumbing applications. The range is designed to achieve robust and flexible solutions with
More informationDRAFT 12/17/03 KMB 18/28 (BANDMASK) OVERHAUL, MAINTENANCE, AND INSPECTION CHECKLIST APPENDIX A
KMB 18/28 (BANDMASK) OVERHAUL, MAINTENANCE, AND INSPECTION CHECKLIST APPENDIX A2.1 12-17-03 THIS INSPECTION AND MAINTENANCE MUST BE PERFORMED AT LEAST ANNUALLY AND AS DICTATED BY CONDITION REVEALED DURING
More informationInstallation, Operation, and Maintenance Manual. Welker Constant Pressure Cylinder With Solid Indicator (Non-mixer) Model CP-30SI
Installation, Operation, and Maintenance Manual Welker Constant Pressure Cylinder With Solid Indicator (Non-mixer) Model The information in this manual has been carefully checked for accuracy and is intended
More informationSpeed control assembly model A-1
Pressure Regulation 533a 1. DESCRIPTION The Viking Speed Control Assembly provides adjustment of the opening speed of Viking Deluge Valves, and adjustment of both the opening and closing speed of Viking
More informationEASTERN ENERGY SERVICES PTE LTD. 60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG Singapore Telephone: Fax:
2 Table Of Contents 1. Introduction 3 2. About this Manual 3 3. Contacting YZ Systems 3 4. Vessel Components 4 5. Specifications 5 6. Application 6 7. Theory of Operation 7 8. DuraSite Installation & Use
More informationRE: PROPANE SYSTEM & REGULATOR TESTING/INSPECTION PROCEDURE
March 22, 2013 RE: PROPANE SYSTEM & REGULATOR TESTING/INSPECTION PROCEDURE Regulators: Symptom: Pressure Drop Cause: External leaks detected at pigtail hose MPT fitting connection(s) to regulator body
More informationMUELLER. Mega-Lite Drilling Machine. Reliable Connections. table of contents PAGE. Equipment 2. Operating Instructions 3-4. Parts Information 5
operating Instructions manual MUELLER Mega-Lite Drilling Machine table of contents PAGE Equipment 2 Operating Instructions 3-4 Parts Information 5 Travel Charts 6-11! WARNING: 1. Read and follow instructions
More informationRG3100 and RG3100Ice Regulator System
RG3100 and RG3100Ice Regulator System User Guide www.diverite.com Date of purchase: www.diverite.com RG1208-5 & RG1208-5Ice www.diverite.com First Stage Regulator Product Description The RG1208-5 and RG1208-5Ice
More informationINSTALLATION, OPERATION & MAINTENANCE MANUAL
INSTALLATION, OPERATION & MAINTENANCE MANUAL AWWA C500 SOLID WEDGE GATE VALVE 2 72 NRS and OS&Y Series 100 and Series 105 TABLE OF CONTENTS SECTION PAGE # Equipment List 2 General 3 Receipt and Inspection
More informationINSTALLATION COMMISSIONING, OPERATION & MAINTENANCE MANUAL
WedgeRock RW Series Worm Gear Actuators INSTALLATION COMMISSIONING, OPERATION & MAINTENANCE MANUAL Revision 01 Date 4/3/17 Page 1 Table of Contents 1.0 INTRODUCTION... 4 1.1 PURPOSE... 4 1.2 AUDIENCE...
More informationLARGE R/W GATE VALVES
The original, and the definitive standard. LARGE R/W GATE VALVES 24 THROUGH 54 STYLE 7000 AWWA C515 250 PSI NSF 61 Certified Fusion Bond Epoxy Coated 10 Year Limited Warranty M&H Valve is a division of
More informationSECTION FACILITY FALL PROTECTION PART I - GENERAL
SECTION 11 24 29 - FACILITY FALL PROTECTION PART I - GENERAL 1.1 The Illinois Department of Labor (IDOL) regulates fall protection for general industry and construction in the public sector under the Illinois
More informationRubber Dock Hose care, Use & Maintenance
Rubber Dock Hose care, Use & Maintenance Prepared by: Thomas J. Wise VP Corporate Development Contents Revised - July. 2014 1. Novaflex Rubber Dock Hose Testing & Inspection Program 1.1 Introduction -
More informationReliance Industries, LLC Operating instructions for the / Bolt-on D-Ring Anchorage. Model # 3071
Reliance Industries, LLC Operating instructions for the 3071-1 / 3071-2 Bolt-on D-Ring Anchorage Model # 3071 Reliance Industries, LLC PO Box 140008 Denver, CO 80214 Ph. (800) 488-5751 Ph. (303) 424-8650
More informationLab Cock. Contents. User s Manual (1) Be sure to read the following warranty clauses of our product 1. (2) General operating instructions 2
Serial No. H-V005-E-6 Lab Cock Contents User s Manual (1) Be sure to read the following warranty clauses of our product 1 (2) General operating instructions 2 (3) General instructions for transportation,
More informationOperation and Maintenance Instructions
Hydratight Limited Bentley Road South Darlaston West Midlands WS10 8LQ United Kingdom Tel: +44 121 50 50 600 Fax: +44 121 50 50 800 E-mail: enquiry@hydratight.com Website: www.hydratight.com TOP COLLAR
More informationHomestead Series 820 AWWA Butterfly Valves
Homestead Series 820 AWWA Butterfly Valves Dependable Valves for Water & Wastewater Service BODY: The ductile iron body meets or exceeds the design strength requirements of the AWWA C504 standards. Flange
More informationINSTALLATION MANUAL Matheson Tri-Gas Cabinet Enclosures
INSTALLATION MANUAL Matheson Tri-Gas Cabinet Enclosures MINT-0289-XX TABLE OF CONTENTS Limited Warranty... 3 User Responsibility... 3-4 General Service... 4 Safety Precautions.... 5 Physical Dimensions..
More information1700ESL Kamvalok Coupler
PART #H32138PA November 2008 1700ESL Kamvalok Coupler OPW Transport Series Dry Disconnect Couplings are considered the standard of the industry. For use on multi-compartment petroleum, solvent and chemical
More informationA REFERENCE GUIDE FOR REQUALIFICATION OF GAS CYLINDERS
A REFERENCE GUIDE FOR REQUALIFICATION OF GAS CYLINDERS AIGA 090/14 Asia Industrial Gases Association 3 HarbourFront Place, #09-04 HarbourFront Tower 2, Singapore 099254 Tel : +65 6276 0160 Fax : +65 6274
More informationAtmospheric relief valve type 1100 Installation and maintenance instructions
SAPAG 1. Description Sapag atmospheric relief valves type 1100 have been selected for installation because of their performance features, reliability and ease of maintenance. They are designed to protect
More informationGemini Owner s Manual
Gemini Owner s Manual WARNING - Improper use of the Gemini Breathable Inflator may result in serious injury or death. Do not attempt to use this product unless you have received certified scuba instruction
More informationTITAN FLOW CONTROL, INC.
PREFACE: This manual contains information concerning the installation, operation, and maintenance of Titan Flow Control (Titan FCI) Simplex Basket Strainers. To ensure efficient and safe operation of Titan
More informationQUALITY ASSURANCE SPECIFICATION NONDESTRUCTIVE EXAMINATION PAGE 1 OF 7
QUALITY ASSURANCE SPECIFICATION REVISION: 0 DATE: 08/29/14 NONDESTRUCTIVE EXAMINATION PAGE 1 OF 7 1.0 Purpose The purpose of this specification is to establish the minimum quality assurance requirements
More informationHealth & Safety Policy and Procedures Manual SECTION 25 RIGGING AND HOISTING EQUIPMENT
SECTION 25 RIGGING AND HOISTING EQUIPMENT 1. RIGGING AND HOISTING: These rules apply to all Maul Electric, Inc. employees and subcontractors. Note: Maul Electric, Inc. employees will utilize mechanical
More informationInstruction Manual Updated 7/26/2011 Ver. 2.2
4-Unit Model MB HTHP Filter Press #171-50-4: 115-Volt #171-51-4: 230-Volt Instruction Manual Updated 7/26/2011 Ver. 2.2 OFI Testing Equipment, Inc. 11302 Steeplecrest Dr. Houston, Texas 77065 U.S.A. Tele:
More informationCS150 CAP STAPLER OWNER S MANUAL
Operation Revised 6/2013 www.stingerworld.com CS150 CAP STAPLER OWNER S MANUAL! Maintenance Safety Warranty PLEASE READ! This manual contains important information about product safety. WELCOME TO STINGER
More informationCOSASCO 6000 PSI SINGLE ISOLATION SERVICE VALVE (FR) MAINTENANCE
COSASCO 6000 PSI SINGLE ISOLATION SERVICE VALVE (FR) MAINTENANCE 11841 Smith Avenue Santa Fe Springs, CA 90670 Tel: (562) 949-0123 (800) 635-6898 Fax: (562) 949-3065 www.cosasco.com Page: 2 of 26 Revision
More informationSERVICE MANUAL MODEL BA600AMST-S1 BREATHING AIR PANEL
SERVICE MANUAL MODEL BA600AMST-S1 BREATHING AIR PANEL WARNING: Do not attempt to operate this equipment without first reading and understanding the service manual enclosed with this device. 2/05 GENERAL
More informationLRS(H)4 USER MANUAL. Read the complete manual before installing and using the regulator.
LRS(H)4 USER MANUAL Read the complete manual before installing and using the regulator. WARNING INCORRECT OR IMPROPER USE OF THIS PRODUCT CAN CAUSE SERIOUS PERSONAL INJURY AND PROPERTY DAMAGE. Due to the
More informationOperating Instructions Model and Hydrostatic Test Pump
Operating Instructions Model 29200 and 2920 Hydrostatic Test Pump Dimension Weight Pump Pressure for 29200 Pump Pressure for 2920 Gauge for 29200 Gauge for 2920 Inlet Connection Outlet Connection Hose
More informationNB/NBR NITROGEN BOOSTER FOR AVIATION SERVICE
NB/NBR NITROGEN BOOSTER FOR AVIATION SERVICE INSTALLATION, OPERATION & MAINTENANCE MANUAL INTERFACE DEVICES, INC. 230 Depot Road, Milford, CT 06460 Ph: (203) 878-4648, Fx: (203) 882-0885, E-mail: info@interfacedevices.com
More informationNAVSEA STANDARD ITEM. 2.2 T9074-AS-GIB-010/271, Requirements for Nondestructive Testing Methods
NAVSEA STANDARD ITEM ITEM NO: 009-53 DATE: 29 JUL 2011 CATEGORY: II 1. SCOPE: 1.1 Title: Bolted Bonnet Steam Valve; repair (shop) 2. REFERENCES: 2.1 S9086-CJ-STM-010/CH-075, Fasteners 2.2 T9074-AS-GIB-010/271,
More informationBinks SG-2 Plus TM Rotary 2 QT. PRESSURE CUP
Binks SG-2 Plus TM Rotary 2 QT. PRESSURE CUP Model No. 80-651 Rotary Agitator INTRODUCTION Binks SG-2 TM Plus Rotary 2 Qt. Pressure Cup is ideal for component spraying and industrial applications where
More information1.3 LIMITATIONS: The following application limitations must be recognized and considered before using this product:
3965 Pepin Avenue Red Wing, MN 55066-1837 Toll Free: (800) 328-6146 Phone: (651) 388-8282 Fax: (651) 388-5065 www.protecta.com User Instruction Manual AJ720A Concrete Anchor This manual is intended to
More informationCommon Discrepancies Uncovered on ADCI Diving Contractor & Training Program Audits
Common Discrepancies Uncovered on ADCI Diving Contractor & Training Program Audits Ways to Set Your Company or School Up For Success on ADCI Audits and Reduce Costs In most instances, all discrepancies
More informationLARGE DRY CHEMICAL, TWIN-AGENT, AFFF, HALON 1211, AND AQUASONIC (NITROGEN-OPERATED SYSTEMS) Pressure Regulator Test Manual
LARGE DRY CHEMICAL, TWIN-AGENT, AFFF, HALON 1211, AND AQUASONIC (NITROGEN-OPERATED SYSTEMS) Pressure Regulator Test Manual 002694 IntroductIon 8-1-11 Page 1 ForEWord This manual is intended for use with
More informationULTRA HIGH PRESSURE PAINT GRATE CLEANER FCT-JS OPERATION AND MAINTENANCE MANUAL
ULTRA HIGH PRESSURE PAINT GRATE CLEANER FCT-JS OPERATION AND MAINTENANCE MANUAL 466 S. Skylane Drive DURANGO, COLORADO 81303 970-259-2869 PHONE 970-259-2868 FAX www.stoneagetools.com sales@stoneagetools
More informationUser Information Sheet 013
User Information Sheet 013 Formerly LPGA Technical Memorandum NO.81 Issue 2 September 2007 ACME threaded couplings 1 INTRODUCTION ACME threaded couplings/end fittings are widely used for LPG transfer operations
More informationAnnex G (normative) Requirements for Nondestructive Examination
Purchase API Spec online at http://www.techstreet.com/api Annex G (normative) G.1 General Requirements for Nondestructive Examination This annex specifies the requirements for NDE that shall be performed
More informationGUIDELINES. Systems. Pressure. Guidelines for Competent Person In-service examination of pressure systems pipework
GUIDELINES Pressure Systems Guidelines for Competent Person In-service examination of pressure systems pipework Document Reference: PSG 05 Issue 01.3 Dated 10/04/19 The Safety Assessment Federation Ltd
More information1 Exam Prep. Tabs and Highlights
1 Exam Prep NFPA 14: Standard for the Installation of Standpipe and Hose Systems Tabs and s These 1 Exam Prep tabs are based on the NFPA 14: Standard for the Installation of Standpipe and Hose Systems,
More informationMODEL UM UNIVERSAL MANIFOLD ASSEMBLY (With or Without Control Valve) 1¼", 1½", 2", 2½", 76.1mm, 3", 4", 6",165.1mm, 8"
4077 Airpark Dr. Standish, MI 48658 989-846-4583 www.globesprinkler.com Technical Support 989-414-2600 techservice@globesprinkler.com MODEL UM UNIVERSAL MANIFOLD ASSEMBLY (With or Without Control Valve)
More informationDifferential Pressure Regulator Type Type 45-6 (0.1 to 1 bar, DN 15) Mounting and Operating Instructions EB 3226 EN
Differential Pressure Regulator Type 45-6 Type 45-6 (0.1 to 1 bar, DN 15) Mounting and Operating Instructions EB 3226 EN Edition March 2008 Contents Contents Page 1 Design and principle of operation...................
More informationInstallation, Operation, and Maintenance Manual. Welker Constant Pressure Cylinder With Welker Magnetic Indicator (With Gravity Mixer) Model CP2GM-HP
Installation, Operation, and Maintenance Manual Welker Constant Pressure Cylinder With Welker Magnetic Indicator (With Gravity Mixer) Model The information in this manual has been carefully checked for
More information5k Slickline Lightweight Pressure Control Equipment 4 ID
5k Slickline Lightweight Pressure Control Equipment 4 ID Table of Contents 5k Slickline Lightweight Pressure Control Equipment 4 ID... 1 Hydraulic Slickline Stuffing Box... 3 Wireline Lubricators... 4
More informationINSTALLATION, OPERATION & MAINTENANCE GUIDE
INSTALLATION, OPERATION & MAINTENANCE GUIDE INTERNATIONAL BRAZIL SOUTHERN USA HEADQUARTERS REPAIR & SERVICE 1 Jackson Street Rua Javaés, 441/443 1719 South Sonny Avenue Essex Junction, VT 05452 Bom Retiro,
More informationFIREFIGHTING EQUIPMENT
FIREFIGHTING EQUIPMENT User Manual "BIPOK" 2way gated wyes DOC 2052 EN Rev.A 20/0/204 Identification Type of Product Product Product Referenced FIELD Documentation Number 2052 Language 2way gated wyes
More informationInstallation Instructions and valve Maintenance Rev. 0 of 21/09/15
ASSEMBLING PROCEDURE AND VALVE MAINTENANCE 1.0.... Safety Information 2.0.. INTRODUCTION 3.0 VARIATIONS 4.0..ASSEMBLING PROCEDURE FOR THE STEM 5.0 ASSEMBLING PROCEDURE FOR OUTLET CONNECTIONS 6.0 PROCEDURE
More informationROPV R40 E Series User Manual
HARBIN ROPV INDUSTRY DEVELOPMENT CENTER ROPV R40 E Series User Manual For Use with the Following ROPV Pressure Vessel Models: R40 300E R40 450E Headquarters Tel:(+86)451-82267301 Fax:(+86)451-82267303
More informationHydraulic Punch Drivers
SERVICE MANUAL 7804SB / 7806SB Quick Draw 7704SB / 7706SB Quick Draw Flex Quick Draw Hydraulic Punch Drivers Serial Codes AHJ and YZ Read and understand all of the instructions and safety information in
More informationPP-1, PP-1W, PP-2, & PP-3
Welker Pitot Probe Model PP-1, PP-1W, PP-2, & PP-3 The information in this manual has been carefully checked for accuracy and is intended to be used as a guide for the installation, operation, and maintenance
More informationINSTALLATION / OPERATION / MAINTENANCE INSTRUCTION
ARCHON Industries, Inc. Armored Gauge Valves Model series 700 & 900 INSTALLATION / OPERATION / MAINTENANCE INSTRUCTION Instruction # 1011 Rev. B Issued: July 22, 2003 Approved: K. Mayer, Engineering Manager
More information