Metro Bike/Bus Interface Study
|
|
- Edwina Curtis
- 6 years ago
- Views:
Transcription
1 Metro Bike/Bus Interface Study
2 Agenda 1. Background & Process 2. Corridors & Metrics 3. General Findings 4. Training Recommendations 5. Design Guidelines 6. Questions
3 L.A. County Bus Service LA Metro 1,433 sq miles of service area 170 bus routes 2,248 buses in fleet 15,967 bus stops 22 Additional Municipal Operators
4 Bicycling is On The Rise 5% of patrons access Metro bus by bike 80% of LA residents live with 3 miles of high frequency bus or rail Between , bike commuting increased 81%
5 Bike Infrastructure is On the Rise
6 Bike/Bus Interactions
7 Existing Design Guidance
8 Study Steps Best Practices & Literature Review Before/After Analysis Training Guidance for Operators & People on Bicycles Bike/Bus Roadway Design Guidebook
9 Working Group Metro Bike Program & Systemwide Planning Long Beach Los Angeles/LADOT Pasadena Santa Monica West Hollywood Planning Staff Engineering Staff Caltrans Culver City LA County DPW LADOT Long Beach Metro Operations & Service Planning Big Blue Bus Culver City Bus Foothill Transit GTrans LADOT Long Beach Transit Pasadena Transit Transit Operators Bicycle Education & Outreach Bike SGV LACBC MCM Santa Monica Spoke
10 Peer Review SEPTA (Philadelphia) King County Metro / Seattle DOT San Francisco MTA
11 Outreach Municipal Staff Interviews Operator & Bicyclist Focus Groups Bicyclist Survey
12 Study Corridors Infrastructure Type Corridors Location InstallationDate Standard bike lanes 7th St Downtown Los Angeles 8/29/2011 Main St Santa Monica / Venice (Los Angeles) 1/28/2012 Pacific Av San Pedro (Los Angeles) 10/1/2015 San Pedro St South Los Angeles 6/8/2013 Van Nuys Blvd Arleta (Los Angeles) 4/6/2013 Buffered bike lanes Alamitos Ave Long Beach 4/16/2016 Colorado Blvd Eagle Rock (LA) 10/3/2013 Venice Blvd Central Los Angeles 2/28/2015 Separated bikeways Broadway Long Beach 4/23/2011 Los Angeles St Downtown Los Angeles 6/1/2016 Shared Bus/Bike Lanes (Bus Only Lanes) Reseda Blvd Reseda (Los Angeles) 4/2/2015 Rosemead Blvd Temple City 5/10/2014 Figueroa St Downtown Los Angeles 7/7/2016 Sunset Blvd Silver Lake (Los Angeles) Late Summer 2013 Wilshire Blvd Koreatown (Los Angeles) 6/1/2013
13 Study Metrics 1. Corridor volumes (ADT, bus frequency, bikes) 2. Ridership 3. Behavior Daily bus on/off Vehicle speeding Bicyclists riding the wrong way / sidewalk 4. Bus operations Change in bus speed Change in reliability 5. Bicycle Traffic Stress 6. Collisions by mode
14 General Findings 1. Bicycling increased on all study corridors 2. Addition of bike facilities improved safety and standardized riding behavior 3. No apparent correlation between bus frequency and bicycling activity 4. Bus performance largely unchanged on study corridors 5. All users prefer green skip-stripe markings 6. Buses and bicycles can share streets safely
15 Key Takeaways for Bus Operator Training 1. Critical elements for initial and ongoing training: Minimum passing distances Knowing the door zone Unpredictable riding behaviors 2. Understanding the bicycling perspective On-bicycle experience Bicycle safety training 3. Sharing information about new street conditions
16 Key Takeaways for Bicycle Safety Training 1. Critical elements for bicycle safety training: How to assess safe opportunity to pass a bus Ride consistently in view of a side mirror How riding behavior is perceived by others 2. Provide opportunities for training Informal educational opportunities Public awareness campaign Seek out riders with greatest need
17 Design Guidelines Eight recommendations Responsive to gaps in existing guidelines Data-centric Supported by outreach and stakeholder engagement
18 Bus Stop Zones: Provide Space for Bus to Clear Bikeway Provide enough space for bus to pull completely flush with curb Buses angled into stop may lead to people riding bikes into adjacent lane Improved visibility for bus operator re-entering traffic
19 Bus Stop Zones: Construct Bus Boarding Islands at Busy Stops Where bus, bicycle or both volumes are high Most effective for bike-bus safety at stops Successful in peer-review cities
20 Bus Stop Zones: Stripe Conflict Area at Stops Highlight where buses cross over path of bicycle riders to reach stop Guide people where to ride Apply consistently between jurisdictions
21 Intersections: Identify and Reduce Conflicts Promote separation for people on bicycles Use clear visual guidance for all users Guide riders both through and turning at intersections
22 Intersections: Identify and Reduce Conflicts
23 Intersections: Identify and Reduce Conflicts
24 Intersections: Provide Clear Sight Lines on Separated Bikeways Bus operators need to see people approaching conflict point Parking-separated or heavily-landscaped bikeways could obscure people riding bicycles Measure setback for visibility from initial conflict point
25 Intersections: Guide Riders Through Intersections All road users should know where to expect people on bicycles through an intersection
26 Corridors: Clearly Sign and Stripe Shared Bus-Bike Lanes Sharing bus lanes is more comfortable and safer for people on bicycles Identify clearly what users are permitted in the lane and when
27 Corridors: Use Left-Sided Bikeways on One-Way Streets Left-sided bikeways reduce conflicts with buses Attention to transition design is crucial Signalization and phase-separation for turns
28 Implementation Process Recommendations Recipe for Success 1. Collaborative process 2. Early engagement 3. Follow-up before after
29 Thank You Lia Yim, LA Metro Jeremiah LaRose, Fehr & Peers Mike Samuelson, Fehr & Peers
30 Sample Corridor: Reseda Boulevard
31
32
33
10/18/2017. Today s webinar agenda. Continuing Education. Designing Transit to Support Active Transportation, and Vice Versa
Today s webinar agenda 3:00 pm: Introduction 3:05 pm: Presentation 3:45 pm: Questions 4:00 pm: Webinar ends For technical assistance during the webinar: 1 800 263 6317 Choose these prompts: 1,1,1 Continuing
More informationLessons Learned from Cycle Tracks (Class IV Bikeways) Design Practice
Lessons Learned from Cycle Tracks (Class IV Bikeways) Design Practice By: Min Zhou, P.E., Principal/Vice President KOA Corporation 1 What is a Cycle Track (Class IV) TYPICAL BIKEWAY CLASSIFICATION CLASS
More informationA Survey of Planning, Design, and Education for Bikeways and Bus Routes on Urban Streets
A Survey of Planning, Design, and Education for Bikeways and Bus Routes on Urban Streets, Community & Economic Development Agency, Transportation Services Division (510) 238-3983 bikeped@oaklandnet.com
More informationVISIONZEROPHL.COM #VISIONZEROPHL
What is Vision Zero? What is Vision Zero? A policy that states clearly that traffic deaths are preventable and unacceptable. CORE PRINCIPLES: Human life takes priority over mobility; Human error is inevitable
More informationLos Angeles County Metropolitan Transportation Authority Metro Bicycle Roundtable
Los Angeles County Metropolitan Transportation Authority Metro Bicycle Roundtable Metro Headquarters Tuesday, November 5, 2013 5:30 7 pm Bicycle Program History & Future Countywide Planning/ Transportation,
More informationMetro Bike Program. Westside/Central Metro Service Council Meeting Wednesday, November 13, :00 7:00 pm
Los Angeles County Metropolitan Transportation Authority Metro Bike Program Westside/Central Metro Service Council Meeting Wednesday, November 13, 2013 5:00 7:00 pm Tony Jusay Transportation Planning Manager
More informationMASTER BICYCLE AND PEDESTRIAN PLAN
VILLAGE OF NORTHBROOK MASTER BICYCLE AND PEDESTRIAN PLAN DRAFT PLAN OPEN HOUSE May 2, 2018 AGENDA 1. Community Engagement 2. Vision and Goals 3. General Structure of Plan 4. Recommendations Overview 5.
More informationCity of Los Angeles CALIFORNIA
DEPARTMENT OF CITY PLANNING 00 N. SPRING STREET, ROOM 55 LOS ANGELES, CA 9001-4801 AND 66 VAN NUYS BLVD., SUITE 351 VAN NUYS, CA 91401 C CITY PLANNING COMMISSION WILLIAM ROSCHEN PRESIDENT REGINA M. FREER
More informationBoard-Approved Funding Awards for Cycle 4 Active Transportation Grant Program Projects (in Order of Project Rankings) Approved on
CAPITAL Large Category Projects Board-Approved Funding Awards for Cycle 4 Active Transportation Grant Program Projects (in Order of Project Rankings) Approved on 07-27-18 1 La Mesa University Ave Pedestrian
More informationMOBILITY WORKSHOP. Joint City Council and Transportation Commission May 5, 2014
MOBILITY WORKSHOP Joint City Council and Transportation Commission May 5, 2014 Review of General Plan M-1 Develop world-class transit system M-3 Maintain/enhance pedestrian-oriented City M-4 Create comprehensive
More informationFHWA Resources for Pedestrian and Bicycle Professionals
FHWA Resources for Pedestrian and Bicycle Professionals Charlie Zegeer, UNC Highway Safety Research Center/PBIC Libby Thomas, UNC Highway Safety Research Center Dan Nabors, Vanasse Hangen Brustlin (VHB)
More informationMoving Ahead. (Community Engagement) Chapter Three
3 Community Chapter Three Moving Ahead (Community Engagement) engagement provided an exciting opportunity to engage Redwood City residents, workers, and business owners people who walk, bike, take transit,
More informationBicycle Facilities Planning
Bicycle Facilities Planning Overview Types of Cyclists Purpose for Riding Types of Facilities Bike Lanes Bicycle Boulevards Cycle Tracks Intersections Signals Signing and Marking Discussion Types of Bicyclists
More informationCity of Charlottesville Bicycle and Pedestrian Master Plan Update
City of Charlottesville Bicycle and Pedestrian Master Plan Update September 17, 2014 I. Welcome and meeting overview II. Project status update III. Network overview IV. Break-out groups Pedestrian Network
More informationSanta Clara I-280 CORRIDOR STUDY
Santa Clara I-280 CORRIDOR STUDY OCTOBER 2017 PREPARED BY: 1.1 Background The I-280 Corridor Study within Santa Clara County is a high-level highway planning study led by the Santa Clara VTA, in partnership
More informationPlanning Guidance in the 2012 AASHTO Bike Guide
Planning Guidance in the 2012 AASHTO Bike Guide Presentation by: RJ Eldridge Peter Lagerwey August 22, 2012 WEBINAR 2: PLANNING GUIDANCE IN THE 2012 AASHTO BIKE GUIDE Today s Webinar Significant Updates
More informationDear Mr. Tweed: Sincerely, Min Zhou, P.E. Vice President
December 17, 2012 Mr. Steve Tweed City of Long Beach, Department of Public Works Traffic & Transportation Bureau, 10 th Floor City Hall 333 West Ocean Boulevard Long Beach, CA 90802 Subject: Broadway and
More informationCITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM
CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM Date: April 1, 219 To: Honorable City Council c/o City Clerk, Room 395, City Hall Attention: Honorable Mike Bonin, Chair, Transportation Committee From:
More informationCity of Richmond Bicycle Master Plan
City of Richmond Bicycle Master Plan October 2011 Prepared by Fehr & Peers In association with Eisen Letunic City of Richmond Bicycle Master Plan October 2011 Prepared by Fehr & Peers In association with
More informationEL CAMINO REAL BUS RAPID TRANSIT (BRT) PROJECT
Agenda Item #4.2 EL CAMINO REAL BUS RAPID TRANSIT (BRT) PROJECT VTA BOARD WORKSHOP MAY 1, 2015 ABOUT THIS PRESENTATION CONTEXT Existing conditions and planning for growth WHAT IS THE PROJECT? Project alternatives
More informationSANTA MONICA BOULEVARD CORRIDOR
CIRCULATION ELEMENT WHITE PAPER NO. 3 SANTA MONICA BOULEVARD CORRIDOR INTRODUCTION From the 1930s to the beginning of Los Angeles freeway era, Santa Monica Boulevard, (previously Route 66, the Beverly
More informationCommunity and Business Outreach November 2015 Goal #1: Improve safety in the corridor Goal #2: Make a more livable corridor Goal #3: Improve mobility for all Data Collection Alternatives Recommendations
More informationWestside Transportation Access Needs Assessment - Short and Long Term Improvements
ABSTRACT The Los Angeles County Metropolitan Transportation Authority (MTA) adopted the 2001 Long Range Transportation Plan (LRTP), which sets out the County s transportation investments for the next 20-25
More informationPolk Streetscape Project
What is this project? The Polk Streetscape Project is an effort to improve safety for everyone traveling on Polk Street between Union and McAllister streets. Also included in this project are paving, sewer
More informationBroadway Complete Streets Project
Broadway Complete Streets Project Megan Johnson, P.E. Associate Civil Engineer James Pangburn, P.E. Consultant Project Manager After the construction of the highway system, Broadway was cut off
More informationBeach Cities Living Streets Design Manual and Aviation Boulevard Multimodal Corridor Plan
Beach Cities Living Streets Design Manual and Aviation Boulevard Multimodal Corridor Plan AGENDA 1 Introductions & Project Scope 2 Public Outreach Recap 3 Living Streets Design Manual 4 Aviation Boulevard
More informationEXECUTIVE SUMMARY. Vision
Vision Walking and bicycling in Salt Lake City will be safe, convenient, comfortable, and viable transportation options that connect people to places, foster recreational and economic development opportunities,
More informationBetter Market Street. Engineering, Maintenance & Safety Committee (EMSC) February 28, 2018
Better Market Street Engineering, Maintenance & Safety Committee (EMSC) February 28, 2018 1 Market Street Market Street - San Francisco by rulenumberone2 2 Market Street is the... City s busiest pedestrian
More informationActive Transportation Access to Transit
Active Transportation Access to Transit Introduction COMO Connect customers access transit service in many ways, including walking, bicycling, riding in a car and being dropped off, and directly boarding
More informationWALKNBIKE DRAFT PLAN NASHVILLE, TENNESSEE EXECUTIVE SUMMARY NASHVILLE, TENNESSEE
NASHVILLE, TENNESSEE EXECUTIVE SUMMARY Executive Summary A world-class multi-modal transportation system is essential to a vibrant city and better quality of life. -Mayor Barry The WalknBike plan aims
More informationBikeway action plan. Bicycle Friendly Community Workshop March 5, 2007 Rochester, MN
Bikeway action plan Summary The was held on March 5, 2007 at the Rochester Mayo Civic Center. The workshop was hosted by Rochester-Olmsted County Planning Department in collaboration with the League of
More informationMajor Bike Routes 102 Avenue Workshop April 21, 2015
Major Bike Routes 102 Avenue Workshop April 21, 2015 Our Purpose Today Provide context on how Major Bike Routes fit into Edmonton s future Share information on what we heard in our last phase, and how
More informationTABLE OF CONTENTS. Executive Summary
Executive Summary Background... ES-1 Pedestrian Network... ES-2 Bikeway Network... ES-2 Collision History... ES-2 Public Input... ES-4 Conclusions and Recommendations... ES-4 1. Introduction and Setting
More informationResults from the 2009 City of Los Angeles Bicycle and Pedestrian Count
Results from the 2009 City of Los Angeles Bicycle and Pedestrian Count Table of Contents Executive Summary 2 About the Los Angeles County Bicycle Coalition 3 2009 Bicycle and Pedestrian Count Objectives
More informationCyclists and Bikeways: What s your match? A guide to bikeway options for a variety of cyclists
Cyclists and Bikeways: What s your match? guide to bikeway options for a variety of cyclists The workshop and this resource were made possible by funding from the Province of Ontario via the Ministry of
More information1.0 INTRODUCTION 1.1 PURPOSE OF THIS REPORT
1.0 INTRODUCTION This chapter provides an overview of the purpose, authorization and focus of this Recirculated Draft Environmental Impact Report (EIR), an identification of the Lead Agency, an outline
More informationCOASTAL RAIL TRAIL ROSE CREEK BIKEWAY PROJECT COMMUNITY WORKSHOP #2 AUGUST 15, 2013
COASTAL RAIL TRAIL ROSE CREEK BIKEWAY PROJECT COMMUNITY WORKSHOP #2 AUGUST 15, 2013 CHRIS CARTERETTE, AICP PROJECT MANAGER Chris.Carterette@sandag.org Direct: 619-699.7319 REGIONAL PLANNING BACKGROUND
More informationCITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE
CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE Date: May 9, 2017 To: Honorable City Council c/o City Clerk, Room 395, City Hall Attention: Honorable Mike Bonin, Chair, Transportation Committee From:
More information9/25/2018. Multi-Modal Level of Service (MMLOS) Bianca Popescu, Transportation Planner
Multi-Modal Level of Service (MMLOS) Bianca Popescu, Transportation Planner 1 What is MMLOS? Is this a nice place to walk? Is this a nice place to bike? Is transit convenient? Bottom line - Are there options
More informationSan Mateo County Bicycle and Pedestrian Advisory Committee
San Mateo County Bicycle and Pedestrian Advisory Committee January 19, 2017 Emma Shlaes, Policy Manager About SVBC Mission Our purpose is to create a healthy community, environment, and economy through
More informationMARKET/JFK VISION ZERO PILOT PROJECT FEBRUARY 2019 EVALUATION REPORT
MARKET/JFK VISION ZERO PILOT PROJECT FEBRUARY 2019 EVALUATION REPORT WHY IS THIS PROJECT IMPORTANT? Market Street and JFK Boulevard in Center City are key east-west corridors in the core business district.
More informationShort-Term Enhancements Improvements to keep Austin moving. MetroRapid
Short-Term Enhancements Improvements to keep Austin moving Long-Term Investments Projects to support our future Mobility Hubs MetroRapid MetroRail MetroExpress Commuters Connectors Circulators Project
More informationNorthbound San Jose Avenue & I-280 Off-Ramp Road Diet Pilot Project
Project Overview Fed by a two-lane Interstate-280 (I-280) off-ramp, high vehicular volumes and speeds are longstanding issues along San Jose Avenue. Residents in the surrounding neighborhoods have expressed
More informationWELCOME! Please complete a comment sheet as we value your feedback. 4 pm to 8 pm. September 15, Hosted by: AECOM on behalf of City of Calgary
WELCOME! Thank you for attending our open house. There will be no formal presentation today so please take the time to read the boards. If you have any questions, please do not hesitate to approach one
More informationZlatko Krstulich, P.Eng. City of O9awa
Zlatko Krstulich, P.Eng. City of O9awa 1. Introduction to the Ontario Traffic Manual Series 2. What is OTM Book 18: Bicycle Facilities? 3. Study / Committee Team Members 4. Brief overview of the content
More informationDevelopment of Arlington County s Marked Crosswalk Guidelines. Jon Lawler, P.E. Design Engineer Arlington County, VA
Development of Arlington County s Marked Crosswalk Guidelines Jon Lawler, P.E. Design Engineer Arlington County, VA April 13, 2015 Transportation System Users Residents Estimated 215,000 in 2014 Lowest
More informationABOUT THIS STUDY The Tenderloin-Little Saigon Community-Based Transportation Plan
ABOUT THIS STUDY The Tenderloin-Little Saigon Community-Based Transportation Plan The Greater Tenderloin Community Study Milestones October Community based organizations (Tenderloin Housing Clinic and
More informationUPTOWN REGIONAL BIKE CORRIDORS PROJECT SAN DIEGO ASSOCIATION OF GOVERNMENTS
UPTOWN REGIONAL BIKE CORRIDORS PROJECT SAN DIEGO ASSOCIATION OF GOVERNMENTS SUMMARY REPORT: COMMUNITY UPDATE MEETING February 6, 2014 6 8:30 p.m. Roosevelt Middle School Library 3366 Park Blvd, San Diego
More informationAGENDA ITEM G-2 Public Works
AGENDA ITEM G-2 Public Works STAFF REPORT City Council Meeting Date: 12/6/2016 Staff Report Number: 16-214-CC Regular Business: Approve the Oak Grove University Crane Bike Improvement Concept Plan, authorize
More information5. RUNNINGWAY GUIDELINES
5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved
More informationWatertown Complete Streets Prioritization Plan. Public Meeting #1 December 14, 2017
Watertown Complete Streets Prioritization Plan Public Meeting #1 December 14, 2017 Goals for Public Meeting Overview of MassDOT Complete Streets Funding Program Educate the community on Complete Streets
More informationActive Transportation Facility Glossary
Active Transportation Facility Glossary This document defines different active transportation facilities and suggests appropriate corridor types. Click on a facility type to jump to its definition. Bike
More informationThe Big Picture. FY Bicycling Highlights
FY 2007 2009 Bicycling Highlights Bikeway Improvements are identified as a Major City Goal in the 2007-2009 Financial Plan. Objectives of the goal are to continue to work towards the completion of the
More informationSR-203 Sidewalks and Town-Wide Mobility Improvements. Town Council Presentation September 7, 2016
SR-203 Sidewalks and Town-Wide Mobility Improvements Town Council Presentation September 7, 2016 SR-203 Sidewalks and Town- Wide Mobility Improvements SR-203 Sidewalks and Appurtenances Town-Wide Mobility
More informationMEMORANDUM - CITY OF PASADENA Department Of Transportation DATE: OCTOBER 21, 2008 TO: ENVIRONMENTAL ADVISORY COMMISSION FROM: ~ FRED C. DOCK, DIRECTOR OF TRANSPORTATION SUBJECT: UPDATE ON DEPT. OF TRANSPORTATION
More informationOutreach Approach RENEW SF served as the primary liaison with the North Beach community; the Chinatown. Executive Summary
Executive Summary Executive Summary The Columbus Avenue Neighborhood Transportation Study s objective is to identify changes to transportation infrastructure and policies that could enhance the livability
More informationHennepin County Bicycle and Pedestrian Planning
Hennepin County Bicycle and Pedestrian Planning 1 Value of bicycle and sidewalk systems Safety Livability Mobility Health Personal Finances Economic Sustainability Clean Air Recreation Parking and congestion
More informationPEDALING FORWARD. A Glance at the SFMTA s Bike Program for SFMTA.COM
PEDALING FORWARD A Glance at the SFMTA s Bike Program for 2017-2021 SFMTA.COM INTRODUCTION About This Booklet More people from all walks of life see their bicycle as a more convenient way to get where
More informationBUDGET FOR RESEDA BOULEVARD, STREET RECONSTRUCTION / VISION ZERO PROGRAM, REPORT BACK, COUNCIL FILE
FORM GEN. 160 (Rev. 11-02) CITY OF LOS ANGELES INTERDEPARTMENTAL CORRESPONDENCE Date: To: Honorable City Council From: Gary Lee Moore, City Engineer Bureau of Engineering 7%mt /Electronically signed by
More information4 MOBILITY PLAN. Mobility Plan Objectives. Mobility Context. 1. Integrate with Local and Regional Transit Improvements
Harbor Mixed Use CHAPTER Transit Corridor 4: Mobility Plan 4 MOBILITY PLAN Mobility Plan Objectives The Harbor Corridor Plan seeks to expand and improve the ways that people move along and through the
More informationFederal Highway Administration Pedestrian Safety Guidance for Transit
Federal Highway Administration Pedestrian Safety Guidance for Transit Dan Nabors Vanasse Hangen Brustlin, Inc. September 23, 2009 Pedestrian Safety Tools & Techniques Pedestrian Safety Guidebooks Transit
More informationSOLANA BEACH BICYCLE TRANSPORTATION PLAN SECOND ADDENDUM
SOLANA BEACH BICYCLE TRANSPORTATION PLAN SECOND ADDENDUM Prepared by the City of Solana Beach January 2005 Introduction In June of 1993, the Solana Beach City Council adopted a Bikeway Master Plan as directed
More informationABOUT THIS OPEN HOUSE
ABOUT THIS OPEN HOUSE Welcome, and thanks for joining us today for the Folsom-Howard Near-Term Project! The purpose of today s open house is to: Understand how the near-term project ties into the larger
More informationComplete Streets Workshop Follow-up. April 27, 2011 Rockledge City Hall
Complete Streets Workshop Follow-up April 27, 2011 Rockledge City Hall Agenda Complete Streets draft briefing presentation and sample policy language Share your Complete Streets projects and post workshop
More informationCity of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE
Welcome Welcome to the third community meeting for the Issaquah-Fall City Road Improvements Project. AGENDA 6:00 p.m. Welcome and sign-in 6:10 p.m. Presentation 6:50 p.m. Open house Learn about the roadway
More informationComplete Streets Policies in Charlotte
Complete Streets Policies in Charlotte Complete Streets Peer Exchange Baton Rouge, LA January 19, 2016 Norm Steinman, AICP Charlotte DOT Changing what we do to change what will happen 1. Inventory of Conditions
More informationG AT E WAY PLAN. Community BRIEFING KIT GATEWAY BIKE
G AT E WAY PLAN GATEWAY BIKE Community BRIEFING KIT PLAN August 2016 TABLE OF CONTENTS INTRODUCTION... 1 THE BENEFITS OF A BIKEABLE COMMUNITY... 2 ECONOMY...2 SAFETY...3 HEALTH...3 HOUSEHOLD SPENDING...3
More informationComplete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA
Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Aaron Elias, Bill Cisco Abstract As part of evaluating the feasibility of a road diet on Orange Grove Boulevard in Pasadena,
More informationBellevue Downtown Association Downtown Bike Series
Bellevue Downtown Association Downtown Bike Series Meeting 2 Franz Loewenherz Andreas Piller Kyle Potuzak Chris Long October 26, 2017 Today s Agenda: 1) Meeting Purpose 2) 9/28 Meeting Recap 3) Candidate
More informationGuidance. ATTACHMENT F: Draft Additional Pages for Bicycle Facility Design Toolkit Separated Bike Lanes: Two-Way to One-Way Transitions
ATTACHMENT F: Draft Additional Pages for Bicycle Facility Design Toolkit Separated Bike Lanes: Two-Way to One-Way Transitions This treatment provides a transition from two-way separated bike lanes to one-way
More informationM14A/D Select Bus Service
M14A/D Select Bus Service Manhattan Community Board 6: April 1, 2019 New York City Transit 2 Background M14 Select Bus Service M14 was identified as a critical future SBS corridor in past BRT studies as
More informationTunnel Reconstruction Brooklyn CB 1 August 14, 2018
Tunnel Reconstruction Brooklyn CB 1 August 14, 2018 Reconstructing the Tunnel 2 Service During Tunnel Reconstruction April 2019 through July 2020 3 Projected Cross River Travel Paths of Customers The Service
More informationWELCOME. Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018
WELCOME Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018 MEETING AGENDA 1. Welcome and Introductions 2. Study Progress Update 3. Problem Statement 4. Technical Analysis
More informationVision Zero Task Force June 28, 2017 COUNTERMEASURE PAIRING
Vision Zero Task Force June 28, 2017 COUNTERMEASURE PAIRING PROCESS 1 SET GOALS AND POLICY 4 COLLISION PROFILES 2 DATA COLLECTION 5 COUNTER- MEASURES 3 DATA ANALYSIS 6 ACTION PLAN ENGINEERING COUNTERMEASURES
More informationTransportation Planning Division
Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meeting Stakeholder Interviews Data Collection Design Principles Tool Box Recommendations Schedule Moving Forward North
More informationFeasibility Study. Expo-Downtown Bicycle Connector
Feasibility Study Expo-Downtown Bicycle Connector May 2017 Table of Contents Introduction... 2 Project Goals... 2 Study Scope... 2 Community Engagement... 3 Project Description... 6 Considerations... 6
More informationAgenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN
PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations
More informationEliminate on-street parking where it will allow for a dedicated bus only lane %
Traffic Dashboard Priorities Survey Responses Introduction 1) Are you familiar with bus rapid transit (BRT)? a. No, BRT is new to me. 597 23.5% b. I ve heard of BRT, but I don t know much about it. 1,136
More informationCity of Los Angeles CALIFORNIA
DEPARTMENT OF CITY PLANNING 200 N. SPRING STREET, ROOM 2 LOS ANGELES, CA 90012-4801 AND 6262 VAN NUYS BLVD., SUITE 31 VAN NUYS, CA 91401 - CITY PLANNING COMMISSION WILLIAM ROSCHEN PRESIDENT REGINA M. FREER
More informationPlanning Suburban Bike Networks
Planning Suburban Bike Networks Stacey Meekins, AICP 28 October, 2015 Bikeway design guidance Different Cyclists Have Different Needs No interest 33% Strong and Fearless 1% Enthused and Confident 7% Interested,
More information6.0 PEDESTRIAN AND BICYCLE FACILITIES 6.1 INTRODUCTION 6.2 BICYCLE DEMAND AND SUITABILITY Bicycle Demand
6.0 PEDESTRIAN AND BICYCLE FACILITIES 6.1 INTRODUCTION Bicycle and pedestrian travel along and in the vicinity of the corridor is part of the vision of Somerset and Hunterdon counties and the integrated
More informationCity of Seattle Edward B. Murray, Mayor
City of Seattle Edward B. Murray, Mayor Department of Transportation Scott Kubly, Director Eastlake Community Council 117 E Louisa St. #1 Seattle, WA 98102-3278 January 28, 2016 RE: Roosevelt to Downtown
More informationHARRISON STREET/OAKLAND AVENUE COMMUNITY TRANSPORTATION PLAN
HARRISON STREET/OAKLAND AVENUE Community Workshop #4: Draft Plan Review December 3, 2009 D E S I G N, C O M M U N I T Y & E N V I R O N M E N T INTRODUCTIONS Key Project Staff: Alisa Shen, Project Manager,
More informationWELCOME Mission-Geneva Transportation Study
WELCOME Mission-Geneva Transportation Study Study Process and Schedule 2005 2006 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sept Oct Task 2 Develop Outreach Plan Task 3 Document Existing Conditions/ Prioritize
More informationINTRODUCTION/BACKGROUND
TECHNICAL MEMORANDUM TO: Tim Rood, CD+A Date: FROM: Iteris, Inc. Job No: 17J1417C9 SUBJECT: Lincoln Boulevard Peak Period Bus Only Lane Feasibility Analysis INTRODUCTION/BACKGROUND Peak period, peak directional
More informationLANCASTER CITY BICYCLE NETWORK
LANCASTER CITY BICYCLE NETWORK Downtown Merchants Meeting Wednesday, July 19, 2017 http://www.lancasteratp. DOWNTOWN WALKABILITY ANALYSIS What changes can be made, in the least amount of time, and for
More informationI-105 Corridor Sustainability Study (CSS)
I-105 Corridor Sustainability Study (CSS) Metro Streets and Freeways Subcommittee March 21, 2019 Gary Hamrick Cambridge Systematics, Inc. I-105 CSS Project History & Background Funded by Caltrans Sustainable
More informationMultimodal Through Corridors and Placemaking Corridors
68 Multimodal Through Corridors and Placemaking Corridors Corridors have different functions in a region. Some corridors are used to get smoothly and rapidly through a region or to get quickly to major
More information» Draft Recommendations» Discussion» Next Steps. Plan for Walking and Biking
SAC Meeting Plan #3 for September Walking and 12, Biking 2018 » Draft Recommendations» Discussion» Next Steps Plan for Walking and Biking » Stakeholder and Public Outreach» Background data collection and
More informationBus Rapid Transit ALTERNATIVES ANALYSIS. Open House
Bus Rapid Transit ALTERNATIVES ANALYSIS Open House June 23, 2015 Open House Meeting Agenda Agenda Introductions What is BRT? Project Goals Study Tasks Next steps Discussion PVTA Bus Rapid Transit Study
More informationUSDOT Bicycle and Pedestrian Safety Initiative: Safer People and Safer Streets. Barbara McCann, USDOT Office of Policy
{ USDOT Bicycle and Pedestrian Safety Initiative: Safer People and Safer Streets Barbara McCann, USDOT Office of Policy 4 Steps from policy to practice Creating multi-modal streets means: 1. Change Decision-Making
More informationFINAL PLAN APPENDIX D CITY OF BERKELEY BIKE PLAN D-1
CITY OF BERKELEY BIKE PLAN D-1 . Proposed Programs D.1. EDUCATION This appendix presents the recommended bicycle-related programs for the City of Berkeley. The recommendations are organized in four E s:
More informationChapter 14 PARLIER RELATIONSHIP TO CITY PLANS AND POLICIES. Recommendations to Improve Pedestrian Safety in the City of Parlier (2014)
Chapter 14 PARLIER This chapter describes the current status and future plans for biking and walking in the City of Parlier. RELATIONSHIP TO CITY PLANS AND POLICIES The Parlier General Plan is the primary
More informationMayor s Bicycle Advisory Council. Wednesday, December 13 th, 2017
Mayor s Bicycle Advisory Council Wednesday, December 13 th, 2017 Bicyclist Fatalities, Year to Date (January 1 November 30, 2017) - MBAC Briefing Bicyclist Fatality Statistics Year to date total, 2017
More informationBeyond First First Last Last Mile Strategies. APA National Conference April 3, 2016 Chelsea Richer, AICP Fehr & Peers
Beyond First First Last Last Mile Strategies APA National Conference April 3, 2016 Chelsea Richer, AICP Fehr & Peers 1 Beyond First Last Mile Strategies APA National Conference Jeremy Klop, AICP, Fehr
More information2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE
About the Project The City of Edmonton is planning a major bike route on the southside of Edmonton. The Strathcona Bike Route will connect the communities of Strathcona, Garneau and the University area,
More informationWelcome. If you have any questions or comments on the project, please contact:
Welcome This drop-in public open house is intended to provide information about the Bay Street bike lanes project. This project proposes a dedicated cycling facility along Bay Street between Aberdeen Avenue
More informationBicycle/Bus Conflict Area Study
Bicycle/Bus Conflict Area Study Gregory R. Krykewycz, PP, AICP Sr. Transportation Planner Office of Transit, Bicycle, & Pedestrian Planning DVRPC and the regional context Philadelphia s MPO, created in
More informationSouthwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary January 19 LPT ATTACHMENT 2.
Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary 2011 January 19 1 of 19 Introduction This executive summary presents the results of the Southwest Bus Rapid Transit (SW
More informationPROJECT OVERVIEW. 20th Avenue Project Limits (Lincoln Way to Wawona St)
PROJECT OVERVIEW In 2014, San Francisco adopted Vision Zero as City policy, with a commitment to eliminate all traffic deaths in the City by 2024. nue Project Limits (Lincoln Way to St) Collision data
More information