1 STAFF REPORT TO THE PLANNING COMMISSION December 12,2016 PUD Concept and Development Stage Plan And Rezoning Applicant: Owner: Requested Action: Location: Zoning: Edward Farr Architects Brad Neuerburg 7710 Golden Triangle Drive Eden Prairie, MN Tiller Corporation Steven Sauer POBox 1480 Maple Grove, MN PUD Concept and Development Stage Plan and Rezoning for the purpose of developing property into a 26,000 s.f. 2 story corporate office and retail store. Outlot A, Tiller Shuler Addition R-A, Single-Family Agricultural Adjacent Land Use and Zoning: North: Medium Density Residential and RMU-Non-Retail Focus; R-A, Single-Family Agricultural East: RMU-Non-Retail Focus; R-A, Single-Family Agricultural South: Regional Mixed Use; PUD, Planned Unit Development West: RMU-Non-Retail Focus; PUD, Planned Unit Development Application Received: 60 Day Review Deadline: November 14,2016 January 13,2017 STAFF COMMENTS: The applicant seeks Planned Unit Development, Concept and Development Stage Plan approval for the purpose of platting and developing the site into a 2-story, 26,000 square foot corporate office and retail building. The site is immediately adjacent to the southeast corner of the Village at Arbor Lakes and will gain access from that development's internal street system. The 5.6 acre parcel is irregular in shape and has most of its eastern boundary in the existing pond, with the building located in the southwest corner of the same. G:\CASES\20 16\\Staff Reports\PC Reports\ PUD REZ docx
2 Staff Report to the Planning Commission PUD Concept/Dvlpt Stage Plan and Rezoning December 12, 2016 Page 2 This two-story building is clad primarily in an earth tone face brick with EIFS material, significant window space and cast stone base for accent to complement the darker brick. The key feature is the 49' tower that anchors the primary entrance into the retail portion of the building. Awnings and decorative lighting will enhance the overall appearance. The entrances for the retail portion of the building are on the southwest and west sides, while the corporate office entrance is on the east side of the building. To note, will be moving from their current location on Main Street to this location for better exposure. The landscaping plan provides for a variety of overstory and understory trees and perennial plants and flowers. Because the site is adjacent to a storm pond where a more natural transition from sod to low maintenance turf seed is fairly common, this proposed plan incorporates said turf seed. This is largely located beyond the immediate improvements. Due to the greater likelihood for maintenance of the proposed turf seed, the owner will be required to provide a maintenance agreement to ensure a healthy growing condition of the grass that will be free of weeds especially any noxious weeds. Due to the staggered nature of Arbor Committee meetings, the Committee will be providing comments to which adherence will be required by the owner. This is memorialized in an attached memorandum. The key issue regarding this request is a proposed second access to the site from Elm Creek Boulevard. This is illustrated on the attached plan sheets. The applicant desires the two points of access and seeks support. The preliminary submittal warranted immediate attention to and concern about this access, and serious concerns remain today. The City's engineering staff and Hennepin County have reviewed the revised designs from the applicant (Sheets C3.01, C3.02 and C3.03). Elm Creek Boulevard is a county road (County State Aid Highway 130). As such, any proposed access along a county roadway will require approval from Hennepin County. In order for any of the proposed partial accesses on Elm Creek Boulevard to meet Hennepin County's access spacing requirements, they would need to be located at least 660 feet from the adjacent Elm Creek Boulevard/Fountains Drive/Village Drive intersection (or approximately midway between Fountains Drive/Village Drive and Zachary Lane intersections along Elm Creek Boulevard). 1) Option #1 (Shown on Sheet C3.01) proposes a right-in only access on Elm Creek Boulevard. This option appears to keep the proposed Elm Creek Boulevard access in the same location as the original site plan (approximately 270 feet from Fountains/Village Drive); however, the access has been modified to provide a right-in access only. Even though the revised right-in only access would remove potential conflicts between rightout vehicles exiting the site and West-bound right-turning traffic along Elm Creek Boulevard, the proposed driveway is still within the influence area of the Elm Creek Boulevard/Fountain Drive/Village Drive intersection (which is defined as the area that G:\CASES\20 16\\Staff Reports\PC Reports\ PUD REZ docx
3 Staff Report to the Planning Commission pun Concept/Dvlpt Stage Plan and Rezoning December 12, 2016 Page 3 extends both upstream and downstream from the physical intersection area and includes any turn lanes, channelization, and distance for drivers to make decisions). An average driver requires 3 seconds to perceive and react to conditions in the roadway ahead of them that will require them to reduce their speed and/or change lanes. The posted speed limit on Elm Creek Boulevard in the vicinity of the proposed development is 50 mph. At 50 mph, vehicles will travel approximately 220 feet during the 3 second perception/reaction time. Since the WB right-turn lane on Elm Creek Boulevard at the Fountains Drive/Village Drive intersection is approximately 400 feet long, the influence area of the Elm Creek Boulevard/Fountains Drive/Village Drive intersection is 620 feet upstream of the intersection, or approximately equal to the County's 660 foot minimum spacing of a partial access along a minor arterial roadway. Therefore, the proposed rightin access shown in Option #1 is too close to the Fountains Drive/Village Drive intersection and may result in higher crash rates and increased congestion at the existing signalized intersection. 2) Option #2 (Shown on Sheet C3.02) also proposes a right-in only access on Elm Creek Boulevard. However, this option shifts to the proposed Elm Creek Boulevard access approximately 160 feet to the east, for a total distance between Fountains/Village Drive and the proposed right-in access driveway of approximately 430 feet. While Option #2 does push the proposed access outside of the physical right-turn lane, the driveway is still within the influence area of the intersection, and as a result may still result in higher crash rates and increased congestion at the existing signalized intersection. Therefore, the proposed right-in access shown in Option #2 is still too close to the Fountains Drive/Village Drive intersection. 3) Option #3 (Shown on Sheet C3.03) proposes a right-in/right-out access on Elm Creek Boulevard at the same location shown in Option #2 (approximately 430 feet from the Fountains/Village Drive intersection). Option #3 is not acceptable since it not only proposes an access within the influence area of the adjacent Elm Creek Boulevard/Fountains Drive/Village Drive signalized intersection, but it also adds additional conflicts into the influence area which could lead to even greater crash potential and congestion upstream of the existing traffic signal. In summary staff does not recommend the designs provided by the applicant, and the County cannot find reason to authorize the designs as depicted. All signage provided on the plan is considered independently of the application at hand and is G:\CASES\20I 6\\StaffReports\PC Reports\ PUD REZ docx
4 Staff Report to the Planning Commission PUD Concept/Dvlpt Stage Plan and Rezoning December 12, 2016 Page 4 reviewed typically in-house unless the applicant pursues a sign package. STAFF RECOMMENDATION: Motion to recommend that the City Council direct staff to draft an Ordinance rezoning property from R-A, Single-Family Agricultural to PUD, Planned Unit Development, subject to the filing of the Final Plat for this proposal and subject to the removal of the proposed access from Elm Creek Boulevard on all plan sheets. Motion to recommend that the City Council direct the City Attorney to draft a resolution approving the PUD Concept and Development Stage Plan for, including the Preliminary Plat of Tiller Schuler 2nd Addition, subject to the applicant addressing to the satisfaction of the City any remaining applicable comments contained in the memorandums from Arbor Committee Staff Liaison, Community Development Director, and Assistant City Engineer dated November 19, November 21 and November 22 (Revised December 7),2016 respectively. This motion as written will require the removal of the proposed access from Elm Creek Boulevard on all plan sheets. Please note that Park Dedication commentary will be made at the time a final plat for this proposal is submitted for consideration. Authored by: Dick Edwards G :\CASES\20 16\Schlller Shoes\Staff Reports\PC Reports' PUD REZ docx
5 Narrative and Overview PUD Application (Revised ) This two story building will feature a retail store on the main level, with the corporate office above on the 2nd floor. Building size is approx. 13,000 sf per floor. is moving from their current location on Main Street to this new location on Elm Creek Blvd which will give them greater exposure. The site design has essentially been laid out to fit with existing zoning parameters, even though it is required to be submitted as a PUD. The landscaping, curb cuts and grading are all designed to be functional and ~" \..1j;l SCHULER SHOES complement the surrounding context. Furthermore, the site layout and landscaping are designed to provide excellent flow for customers and a visual connection to Elm Creek Blvd with a very welcoming and approachable design that compliments the proposed building. The layout of the building consists of entrances for the retail store on the SW corner and West side. The corporate office entrance is on the East side of the building. The less attractive parts of the building such as the delivery area and trash enclosure are hidden behind the building and out of view from the streets. Parking wraps around the building to accommodate the fluctuating retail users, along with the more consistent office users. 116 Parking stalls are provided, which is right in line with the city guidelines. Primary access to the site will be from the entrance off of the newly constructed Village Drive, with additional limited access directly off Elm Creek Blvd via a Right-In. Two points of access is critical for this user so any support for the Elm Creek access point will be greatly appreciated. Overall we believe the use and layout of this proposed development fits nicely with the city's comprehensive plan and city goals and that this project will bring many great contributions to the City of Maple Gove. has a long history of success and customer satisfaction in Maple Grove and other communities for many years. Their mission of improving lives - one person, one pair, and one neighborhood at a time are well known to our community. They want this project to be representative of quality that they are known for. With that in mind, high quality materials such as Brick, Glass, Cast Stone and EIFS (2nd story) will convey a traditional feeling with an eye to the future. The 49' feature on the SE corner will provide a welcoming presence and identity. Additionally, the ample landscaping around the building and along the ROW will also help create a much needed transition between the retail uses West and South of this site, to the other non-retail uses to the East and North of it. Our entire team is extremely excited about the potential of this project and are confident that other community stakeholders will recognize the potential and benefits as well! ::::-:~_ ~~~'::"~~~;~?::"-;Y'- ~~5:;~~~:;!::;~:F~i-t$:._:.... _-,- ::..::::~-...._.. -~~.'.'~:;--: ", -:.
6 77TH AVE PUD Concept/Dvlpt Stage Plan ~-- and Rezoning ~I--~------l ~ \~ r Z Z N NEIGHBORHOOD LOCATION MAP M~ple Grove o Feet I I I I I
Traffic Impact Memorandum. May 22, 2018
BISHOP PROFESSIONAL DEVELOPMENT BUILDING Proposed Land-use Change & Parking Modification 3601 SW 31st Street Topeka, Kansas 66614 CFS Project No. 185077 Traffic Impact Memorandum May 22, 2018 Prepared
More informationTENW Transportation Engineering NorthWest
TENW Transportation Engineering NorthWest MEMORANDUM DATE: May 16, 2018 PRELIMINARY DRAFT TO: FROM: SUBJECT: Angelie Stahlnecker City of Fircrest Jeff Schramm TENW Response to Comments from City of Tacoma
More informationBicycle and Pedestrian Advisory Committee (BPAC) November 21, 2013
Bicycle and Pedestrian Advisory Committee (BPAC) November 21, 2013 OVERALL LAND USE CONCEPT Overall Broadway Valdez District: 95.5 acres (35.1 acres right-of ways + 60.4 acres developable land) Plan Subareas:
More informationCHAPTER 7 ACCESS MANAGEMENT. Background. Principles of Access Management. Hennepin County Transportation Systems Plan (HC-TSP)
CHAPTER 7 ACCESS MANAGEMENT Background Principles of Access Management Hennepin County Transportation Systems Plan (HC-TSP) Chapter 7 Access Management 7.1 Background Access management has become an important
More informationTRAFFIC STUDY GUIDELINES Clarksville Street Department
TRAFFIC STUDY GUIDELINES Clarksville Street Department 9/1/2009 Introduction Traffic studies are used to help the city determine potential impacts to the operation of the surrounding roadway network. Two
More informationThe Woods at Rush Creek - PUD Concept & Dvlpt Stage Plan Review
.. - Cityof. Maple Grove Maple Grove Parks and Recreation MEMORANDUM TO: Peter Vickerman - City Planner FROM: Chuck Stifter - Director of Parks and Recreation ft ~ DATE: August: 12,2016 0 SUBJECT: The
More information1 st and 2 nd Street Couplet FAQ s
1 st and 2 nd Street Couplet FAQ s Q. Will the proposed roundabout at Flume/2nd/1 st Streets affect access to businesses nearby?... 2 Q. What if the project isn t received well by the community after construction?...
More informationAccess Location, Spacing, Turn Lanes, and Medians
Design Manual Chapter 5 - Roadway Design 5L - Access Management 5L-3 Access Location, Spacing, Turn Lanes, and Medians This section addresses access location, spacing, turn lane and median needs, including
More informationExhibit 1 PLANNING COMMISSION AGENDA ITEM
Exhibit 1 PLANNING COMMISSION AGENDA ITEM Project Name: Grand Junction Circulation Plan Grand Junction Complete Streets Policy Applicant: City of Grand Junction Representative: David Thornton Address:
More informationSixth Line Development - Transit Facilities Plan
Memorandum Date: November 13, 2012 To: From: c.c. Subject: Rob Freeman (Freeman Planning) Kevin Phillips Sixth Line Development - Transit Facilities Plan 33016631 This memo was prepared to review the transit
More informationAccess Management Regulations and Standards for Minor Arterials, Collectors, Local Streets
Access Management Regulations and Standards for Minor Arterials, Collectors, Local Streets September 2009 Paul Grasewicz Access Management Administrator Concept of Access Management The way to manage access
More informationMidway City Council 15 January 2019 Regular Meeting. Homestead Villas / Preliminary Approval
Midway City Council 15 January 2019 Regular Meeting Homestead Villas / Preliminary Approval CITY COUNCIL MEETING STAFF REPORT DATE OF MEETING: January 15, 2018 NAME OF PROJECT: NAME OF APPLICANT: AGENDA
More informationAPPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD
APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD INTERSECTION NEEDS AT SR 7 and OKEECHOBEE BOULEVARD SR 7 Extension Project Development and Environment (PD&E) Study From Okeechobee Boulevard (SR
More informationRoadway Classification Design Standards and Policies. Pueblo, Colorado November, 2004
Roadway Classification Design Standards and Policies Pueblo, Colorado November, 2004 Table of Contents Page Chapter 1. General Provisions 1.1 Jurisdiction 3 1.2 Purpose and Intent 3 1.3 Modification 3
More informationARLINGTON COUNTY, VIRGINIA
ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of October 15, 2016 DATE: October 7, 2016 SUBJECT: Adoption of amendments to the Master Transportation Plan (MTP) to create a new Pedestrian
More informationCounty of Greenville South Carolina. Traffic Calming Program Neighborhood Traffic Education Program and Speed Hump Program
County of Greenville South Carolina Traffic Calming Program Neighborhood Traffic Education Program and Speed Hump Program (rev) August 2008 I. PURPOSE The potential negative impacts from vehicular traffic
More informationTRANSPORTATION STANDARDS
INTRODUCTION LOCAL STREETS ON-STREET PARKING SIDEWALKS STREET LIGHTING STREET FURNISHINGS TRAFFIC CALMING STREET TREES MEDIAN PLANTING BOULEVARD LOCATIONS VILLAGE CENTER STREET LOCATIONS RESIDENTIAL STREET
More information3.0 Future Conditions
3.0 Future Conditions In order to be able to recommend appropriate improvements to the transportation system of the Town, it is important to first understand the nature and volume of traffic that is expected
More informationLIVERPOOL TRANSPORTATION MODELING TECHNICAL MEMO MAY 2009
LIVERPOOL TRANSPORTATION MODELING TECHNICAL MEMO MAY 2009 Syracuse Metropolitan Transportation Council 100 Clinton Square 126 N. Salina Street, Suite 100 Syracuse, NY 13202 Telephone (315) 422-5716; Fax
More informationMEMORANDUM. David Mohlenbrok, Environmental Services Manager
MEMORANDUM DATE: August 10, 2017 TO: FROM: RE: Planning Commission Members David Mohlenbrok, Environmental Services Manager Blue Memo # 1 for Rocklin Station Project Comments Received on Initial Study/Mitigated
More informationAccess Management in the Vicinity of Intersections
Access Management in the Vicinity of Intersections FHWA-SA-10-002 Technical Summary Photo: Ralph Bentley (used with permission) 0 Access Management is: The design, implementation and management of entry
More informationPOLICY: TRAFFIC CALMING
2006 MAY REFERENCE: COUNCIL APPROVED BY COUNCIL MAY 23, 2006 CITY OPERATIONS - NO. 608 POLICY: TRAFFIC CALMING A. All requests for traffic calming within the City shall be considered in accordance with
More informationTraffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC
Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC 1. TABLE OF CONTENTS INTRODUCTION...1 1.1. Site Location and Study Area...1 1.2. Proposed Land Use and Site Access...2 1.3.
More informationCity of Wayzata Comprehensive Plan 2030 Transportation Chapter: Appendix A
A1. Functional Classification Table A-1 illustrates the Metropolitan Council s detailed criteria established for the functional classification of roadways within the Twin Cities Metropolitan Area. Table
More informationVision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods
N D. Focus Area II Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods Transit Road Focus Area II is located in the Hamlet
More informationOverview. Existing Conditions. Corridor Description. Assessment
Overview A study of the 23 rd Street corridor was undertaken to document the existing conditions, analyze traffic operations, and recommend remedies for deficient situations Although 23 rd Street is frequently
More informationTRAFFIC IMPACT STUDY CRITERIA
Chapter 6 - TRAFFIC IMPACT STUDY CRITERIA 6.1 GENERAL PROVISIONS 6.1.1. Purpose: The purpose of this document is to outline a standard format for preparing a traffic impact study in the City of Steamboat
More information/ ARLINGTON COUNTY, VIRGINIA
/ ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of September 24, 2016 DATE: August 11, 2016 SUBJECT: Amendment of the Master Transportation Plan (MTP) Streets Element to include new local
More information5858 N COLLEGE, LLC N College Avenue Traffic Impact Study
5858 N COLLEGE, LLC nue Traffic Impact Study August 22, 2016 Contents Traffic Impact Study Page Preparer Qualifications... 1 Introduction... 2 Existing Roadway Conditions... 5 Existing Traffic Conditions...
More informationExecutive Summary Route 30 Corridor Master Plan
Route Corridor Master Plan Project Overview The Route Corridor Master Plan is a coordinated multimodal transportation and land use plan for the entire stretch of Route through East Whiteland Township,
More informationAccess Management Guidelines February 2013 THE CITY OF
Access Management Guidelines February 2013 THE CITY OF Table of Contents Introduction 2 Review and Approval Process 5 Technical Guidelines 9... 10... 12 3. Separation Distance: Non-Signalized All-Turns
More informationChapter 3: Multi-Modal Circulation and Streetscapes
CHAPTER 3: MULTI-MODAL CIRCULATION AND STREETSCAPES Chapter 3: Multi-Modal Circulation and Streetscapes Overview Streetscape improvements have already been completed for Depot Street between Main Avenue
More informationVillages of Pasadena Hills Financial Plan UPDATED Spring 2012 DRAFT
36 37 38 39 40 41 42 43 44 45 46 Appendix B (Unchanged from January 2009 Adoption) 47 Projects Approved Prior to VOPH Comprehensive Plan Amendment Ashley Groves Chapel Creek Chapel Hill Farmington Hills
More informationAccess Management Regulations and Standards
Access Management Regulations and Standards Efficient highway operation Reasonable property access Concept of Access Management The way to manage access to land development while simultaneously preserving
More informationMUNICIPALITY OF ANCHORAGE Traffic Department MEMORANDUM
MUNICIPALITY OF ANCHORAGE DATE: MEMORANDUM TO: FROM: SUBJECT: Anchorage Contractors, Builders, Designers, and Land Owners Robert E. Kniefel, P.E., Municipal Traffic Engineer Municipal Driveway Standards
More informationAccess requests to County streets and roadways are processed through one of the following methods:
13.1 GENERAL APPLICATION PROCESS Access requests to County streets and roadways are processed through one of the following methods: A. Planned Developments may set general locations for access points.
More informationWHEREAS delivery trucks also pass through the Narrows, into the northern parking lot, to loading docks in the back of the building.
CEDAR-ISLES-DEAN NEIGHBORHOOD ASSOCIATION ( CIDNA ) RESOLUTION OPPOSING A DRUG STORE DRIVE THRU, AND COMMENDING DORAN COMPANIES FOR PROPOSING MITIGATING AMENITIES INCLUDING NEW LANDSCAPING AND A DEDICATED
More information5 CIRCULATION AND STREET DESIGN
5 CIRCULATION AND STREET DESIGN This chapter describes circulation and streetscape improvements proposed for the Northwest Chico Specific Plan Area. It includes detailed design specifications for existing
More informationCity of Davis East Covell Corridor Plan
Community Open House #2 January 22, 2014 6:00 8:00 p.m. Veterans Memorial Center, Club Room City of Davis Introduction The (ECCP) is a taking a comprehensive look at the existing transportation systems
More informationTraffic Impact Analysis Chatham County Grocery Chatham County, NC
Chatham County Grocery Chatham County, NC TABLE OF CONTENTS 1. INTRODUCTION... 1 1.1. Location and Study Area... 1 1.2. Proposed Land Use and Access... 2 1.3. Adjacent Land Uses... 2 1.4. Existing ways...
More informationProject Goal and Description. Why Broadway? Broadway SFMTA.COM/BROADWAY. The goal of the Broadway Safety Improvement
PROJECT OVERVIEW Project Goal and Description The goal of the Broadway Safety Improvement d St Van Ness Ave Project is to improve safety and comfort for all who Franklin St Hyde St Octavia St Gough St
More informationAccess Management Regulations and Standards
Access Management Regulations and Standards January 2014 Efficient highway operation Reasonable property access Concept of Access Management The way to manage access to land development while preserving
More informationStation Plan: Penn & 43rd Avenue
Station Plan: Penn & 43rd Avenue This station will serve the northern portion of the Penn Avenue corridor, including the commercial node at 44th Avenue. Ridership and roadway geometry support station siting
More informationINTRODUCTION THOROUGHFARE SYSTEM CLASSIFICATIONS
INTRODUCTION The thoroughfare plan will assist public officials in the development of a specialized system for efficient and safe movement of vehicular traffic while minimizing potential conflicts with
More informationRECOMMENDED MOTION: I MOVE TO PASS SECOND READING AND ADOPT ORDINANCE 556, TO REMOVE NE 173RD STREET FROM THE DESIGNATED PEDESTRIAN-ORIENTED STREETS.
CITY OF WOODINVILLE, WA REPORT TO THE CITY COUNCIL 17301 133rd Avenue NE, Woodinville, WA 98072 wvvw.ci.woodinville.wa.us To: Honorable City Council Date: 02/05/2013 From: Richard A. Leahy, City Manager
More information122 Avenue: 107 Street to Fort Road
: 107 Street to Fort Road November 24, 2015 4:30 8:00 p.m. Meeting Purpose Summarize project work completed to date Share results of public input from Phase 1 Share the draft concept plan and proposed
More informationDriveway Design Criteria
Design Manual Chapter 5 - Roadway Design 5L - Access Management 5L-4 Driveway Design Criteria A. General For efficient and safe operations, access drives and minor public street intersections can be improved
More informationSTEERING COMMITTEE MEETING June 17, Streetscape Overview Burlington Comprehensive Master Plan
STEERING COMMITTEE MEETING June 17, 2015 Streetscape Overview Burlington Comprehensive Master Plan 1 Introduction Slide This slide show was presented to the Burlington Steering Committee on June 17, 2015
More informationJONESBORO HIGHWAY 63 HIGHWAY 18 CONNECTOR STUDY
JONESBORO HIGHWAY 63 HIGHWAY 18 CONNECTOR STUDY Craighead County May 2007 JONESBORO HIGHWAY 63 HIGHWAY 18 CONNECTOR STUDY Craighead County May 2007 Prepared by Planning and Research Division Arkansas State
More informationChapter 2: Standards for Access, Non-Motorized, and Transit
Standards for Access, Non-Motorized, and Transit Chapter 2: Standards for Access, Non-Motorized, and Transit The Washtenaw County Access Management Plan was developed based on the analysis of existing
More informationLee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses
Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses Introduction At the Lee s Summit Road Improvement Study Public Open House held Thursday, June 7, 2007
More informationAGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive
AGENDA REPORT To: From: By: Honorable Mayor and City Council Members Warren Hutmacher, City Manager Tom Black, Public Works Director Date: March 23, 2016 Agenda: March 28, 2016 WORK SESSION AGENDA: Barnwell
More informationWest Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road
West Dimond Blvd Jodhpur St to Sand Lake CSS Transportation Project Summary Municipality of Anchorage Project # 05 005 Project Manager: John Smith, P.E. (MOA PM&E) Project Administrator: Julie Makela,
More information#!! "$% ##! &! # '#! % $ #!
Executive Summary US Highway 16 (US 16) is the primary corridor connecting Rapid City to the Black Hills region. It serves a growing population of commercial and residential traffic, as well as seasonal
More informationKing Soopers #116 Thornton, Colorado
Traffic Impact Study King Soopers #116 Thornton, Colorado Prepared for: Galloway & Company, Inc. 1.0 EXECUTIVE SUMMARY King Soopers #116, a grocery marketplace anchored commercial development, is proposed
More informationReport. Typical Sections. City of Middleton, WI
Report Typical Sections City of Middleton, WI December 2006 Report for City of Middleton, Wisconsin Typical Sections repared by: Traffic Associates LLC and STRAND ASSOCIATES, INC. 910 West Wingra Drive
More informationTENW Transportation Engineering NorthWest
DRAFT FOR CLIENT REVIEW ONLY TENW Transportation Engineering NorthWest MEMORANDUM DATE: August 22, 2017 TO: FROM: SUBJECT: Patrick Yamashita City of Mercer Island Chris Forster, P.E. TENW Trip Generation
More informationInformation on display. Inside this handout. Triangle Area revisions. Project need displays. Preferred alternative on aerial maps
Public information meeting #4 4 to 7 p.m., September 30, 2009 Hales Corners Welcome Thank you for attending this public information meeting for the WIS 100 Corridor Study. Your interest and comments are
More informationThis page intentionally left blank.
This page intentionally left blank. COMMUNITY Coweta Community Overview Coweta Coweta, a residential community located in Wagoner County, is a suburb of Tulsa situated southeast of the metropolitan area
More informationROUNDABOUTS/TRAFFIC CIRCLES
GENERAL 1. Description This standard identifies minimum requirements that shall be met for Roundabouts and Neighborhood Traffic Circles in the design and construction of elements for Arlington County Horizontal
More informationNEIGHBORHOOD TRAFFIC CALMING POLICY
NEIGHBORHOOD TRAFFIC CALMING POLICY I. PURPOSE The City of Kent continually strives to strengthen and protect its neighborhoods by improving the quality of life in residential areas. Traffic conditions
More informationA plan for improved motor vehicle access on Railroad Avenue in Provincetown
A plan for improved motor vehicle access on Railroad Avenue in Provincetown February 2011 A plan for improved motor vehicle access on Railroad Avenue in Provincetown INTRODUCTION AND PROBLEM IDENTIFICATION
More informationTRAFFIC ACTION PLAN. Laurie Meadows Neighborhood CITY OF SAN MATEO
TRAFFIC ACTION PLAN Laurie Meadows Neighborhood CITY OF SAN MATEO Draft January 2017 Table of Contents Introduction... 2 The Traffic Forum Process... 5 Neighborhood Traffic Issues... 7 Neighborhood Recommendations
More informationPEDESTRIAN CIRCULATION & STREETSCAPE DESIGN
CHAPTER 4 Chapter 4 Pedestrian Circulation & Trails PEDESTRIAN CIRCULATION & STREETSCAPE DESIGN In recent years, the City has constructed new sidewalks and enhanced existing ones in the downtown with brick
More informationTOWN OF CHAPEL HILL POLICY AND PROCEDURES FOR TRAFFIC CALMING MEASURES
TOWN OF CHAPEL HILL POLICY AND PROCEDURES FOR TRAFFIC CALMING MEASURES (Adopted by the Town Council on June 30, 2004) (Revised December 6, 2010) (Revised February 8, 2016) POLICY AND PROCEDURES FOR TRAFFIC
More informationM-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016
M-58 HIGHWAY ACCESS MANAGEMENT STUDY Prepared for CITY OF BELTON By May 2016 Introduction Missouri State Highway 58 (M-58 Highway) is a major commercial corridor in the City of Belton. As development has
More informationHidden Oaks Elementary School
Hidden Oaks Elementary School SCHOOL ROUTE PLAN For HIDDEN OAKS ELEMENTARY SCHOOL LOCATION 13 ORANGE COUNTY Prepared for: ORANGE COUNTY SCHOOL ASSESSMENT PROGRAM ORANGE COUNTY PUBLIC WORKS Traffic Engineering
More informationOverland Traffic Consultants, Inc. October 15, Mr. Bruce McBride Project Delivery Analysts, LLC Shawnee Street Moorpark, CA 93021
Overland Traffic Consultants 952 Manhattan Beach Boulevard, Suite #100 Manhattan Beach, CA 90266 Phone (661) 799-8423 E-mail: otc@overlandtraffic.com October 15, 2015 Mr. Bruce McBride Project Delivery
More informationSummary: Mercer County Princeton Avenue & Spruce Street Study January 2009
Summary: Several recent studies have assessed potential development and redevelopment opportunities in the Mercer Crossing area of Trenton, Ewing, and Lawrence. This Princeton Avenue and Spruce Street
More informationCaltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns
Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns Revised: May 10, 2016 The California Department of Transportation (Caltrans) is planning various
More informationVDOT I-66 Inside the Beltway Eastbound Widening Environmental Assessment. Staff Recommendations
VDOT I-66 Inside the Beltway Eastbound Widening Environmental Assessment Staff Recommendations Department of Environmental Services Transportation January 28, 2017 Timeline of Transform66 June 2012: I-66
More information6.4 RECOMMENDED IMPROVEMENTS
6.4 RECOMMENDED IMPROVEMENTS 6.4.1 Williston Road Recommendations While all alternatives would be an improvement over existing conditions, Alternative 3B is recommended over the others because it provides
More informationCounty of Spartanburg South Carolina
County of Spartanburg South Carolina Traffic Calming Program June 2012 (Revised/Program on Hold) PURPOSE The potential negative impacts from vehicular traffic on residential roads have been a longstanding
More informationCompliance with Section 18-52(4) City of Thornton Development Code
May 25, 2016 Jay Ruchti City of Thornton City Development Department 9500 Civic Center Drive Thornton, CO 80229 RE: Golf Safety Netting TOPGOLF Entertainment Complex (Southeast Corner of East 136 th Avenue
More informationPlanning & Zoning Commission
Preliminary Plat Westwood, Section 3 Planning & Zoning Commission Planning & Development Department March 21, 2016 Request Subdivide approximately 38.1 acres of previously unplatted property to create
More informationRESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY
RESOLUTION NO. 2018-?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY WHEREAS, safe, convenient, and accessible transportation for all users is a priority of the City of Neptune
More informationTraffic Impact Study for Rolling Ridge Redevelopment
Traffic Impact Study for Rolling Ridge Redevelopment Webster Groves, Missouri October 19, 2018 Prepared For: Gershman Commercial Real Estate 150 North Meramec Avenue Suite 500 St. Louis, Missouri 63105
More informationTonight is for you. Learn everything you can. Share all your ideas.
Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.
More informationThird Street Bridge & Corridor Project
Third Street Bridge & Corridor Project Preparation for the FY2018 budget to commence October 1, 2017, includes funding to address a project that has been considered since 1994. The Third Street bridge
More information12/4/2016 VIA . RE: Grocery Outlet Del Paso (DR16-328)
12/4/2016 VIA EMAIL Ethan Meltzer, Assistant Planner City of Sacramento Community Development Department 300 Richards Blvd, 3 rd Floor Sacramento, CA 95811 RE: Grocery Outlet Del Paso (DR16-328) Dear Mr.
More information3.1 TRAFFIC CALMING PROCESS SUMMARY
SECTION 3 3.0 TRAFFIC CALMING 3.1 TRAFFIC CALMING PROCESS SUMMARY Traffic calming is a means in which to reduce speeds and minimize vehicular traffic on local neighborhood streets. Citizen involvement
More informationWELCOME. City of Eden Prairie West 70 th Street
WELCOME City of Eden Prairie West 70 th Street Project Schedule Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug >>> May WEST SEGMENT Concept Plan Fall 2014 Plan Development Winter 2014 Summer 2015 Construction
More informationTo: Planning Commission Date: September 19, 2012 From: By: Subject:
To: Planning Commission Date: September 19, 2012 From: By: Subject: City of Woodinville, WA Report to the planning commission 17301 133 rd Avenue NE, Woodinville, WA 98072 www.ci.woodinville.wa.us Richard
More informationDRAFT. Malibu Bluffs Park Skate Park Facility Site Assessment. Prepared For: The City of Malibu Parks and Recreation Department
Malibu Bluffs Park Skate Park Facility Site Assessment Prepared For: The City of Malibu Parks and Recreation Department Prepared on February 28, 2013 By: 1 INTRODUCTION AND PROJECT BACKGROUND For more
More informationCity of Elizabeth City Neighborhood Traffic Calming Policy and Guidelines
City of Elizabeth City Neighborhood Traffic Calming Policy and Guidelines I. Purpose: The City of Elizabeth City is committed to ensure the overall safety and livability of residential neighborhoods. One
More informationo n - m o t o r i z e d transportation is an overlooked element that can greatly enhance the overall quality of life for the community s residents.
N o n - m o t o r i z e d transportation is an overlooked element that can greatly enhance the overall quality of life for the community s residents. 84 Transportation CHAPTER 11 INTRODUCTION Transportation
More informationBicycle and Pedestrian Facilities Toolbox (Excerpt from Figure 3.1)
Appendix B Neighborhood Connections Summaries This Appendix is a supplement to the information presented in Chapter 3 Connect People. The Appendix includes a summary or profile for each of the proposed
More informationKDOT Access Management Policy (AMP)
KDOT Access Management Policy (AMP) (January 2013 Edition) Errata KDOT intends to correct these errors during the next revision to the Policy. Corrections are denoted in red text with a solid line through
More informationOrange Center Elementary School
Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete this text box) Orange Center Elementary School Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete
More informationAPPENDIX E GRADE CROSSING LOCATIONS
APPENDIX E GRADE CROSSING LOCATIONS 1 2 3 Citrus Avenue Riverside County and City Palmyrita Avenue Columbia Avenue MP 0.57 002X-0.6 027301Y MP 1.00 002X-1.0 027302F MP 1.24 002X-1.3 027303M 1. Existing
More informationDRAFT. A fifth objective, other considerations, has been added to capture considerations not captured by the four primary objectives.
TECHNICAL MEMORANDUM Albany - Washington Avenue Traffic Calming Evaluation Matrix of Conceptual Alternatives Date: May 17, 2017 Project #: 17356 To: Aleida Andrino-Chavez From: Laurence Lewis, Sara Muse,
More informationFLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 7 DISTRICT WIDE BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT AND IMPROVEMENT PLAN
FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 7 DISTRICT WIDE BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT AND IMPROVEMENT PLAN TRANSIT SAFETY ASSESSMENT SR 55/US 19 AT 80 TH AVE N DRAFT JUNE
More informationStreet Paving and Sidewalk Policy
City Commission Policy 600 Street Paving and Sidewalk Policy DEPARTMENT: Public Works DATE ADOPTED: June 7, 1995 DATE OF LAST REVISION: December 10, 2014 Policy No. 600.01 AUTHORITY: PASS City of Tallahassee-Leon
More informationChapter 4 TOOLBOX AND SAMPLE BIKE BOULEVARD LAYOUT
Chapter 4 TOOLBOX AND SAMPLE BIKE BOULEVARD LAYOUT OVERVIEW This chapter describes a cohesive set of strategies to create a bicycle boulevard, namely to make streets safer and more efficient for bicycle
More informationHow to Develop a Pedestrian Safety Action Plan
How to Develop a Pedestrian Safety Action Plan Course Introduction Presented by: Peter Eun FHWA RC Safety Engineer Ryan Snyder President, Ryan Snyder Associates, LLC Paul Zykofsky Director, Land Use and
More informationTransportation Impact Study for Abington Terrace
Transportation Impact Study for Abington Terrace Abington Township, Montgomery County, PA Sandy A. Koza, P.E., PTOE PA PE License Number PE059911 Prepared by McMahon Associates, Inc. 425 Commerce Drive,
More informationApplication of a Complete Street
Application of a Complete Street Southbend to Prima Vista Update May 14, 2018 Meeting Agenda Perspective and History Public input received Typical sections being considered Presentation of the 2-lane master
More information5/7/2013 VIA . RE: University Village Safeway Expansion (P13-019)
5/7/2013 VIA EMAIL David Hung, Associate Planner Community Development Department, Current Planning Division City of Sacramento 300 Richards Boulevard, 3 rd Floor Sacramento, CA 95811 RE: University Village
More informationTRAFFIC CALMING POLICY NEWTOWN TOWNSHIP DELAWARE COUNTY, PA
TRAFFIC CALMING POLICY NEWTOWN TOWNSHIP DELAWARE COUNTY, PA September 2014 1 TABLE OF CONTENTS INTRODUCTION... 3 PURPOSE AND GOALS... 3 DEFINITIONS... 4 APPLICABILITY... 5 ELIGIBLE STREETS... 5 LOCATION
More informationComments EXECUTIVE SUMMARY
Comments 1. Under any Alternatives, MCDOT should provide better at-grade pedestrian crossing of Georgia Avenue and Forest Glen Road, including improved crosswalks with wider medians and adequate signal