Central Avenue Corridor Study FPID Number:

Size: px
Start display at page:

Download "Central Avenue Corridor Study FPID Number:"

Transcription

1 Central Avenue Corridor Study FPID Number: City Commission Presentation 1 March 27, 2018

2 Meeting Agenda 1. Introductions 2. Project Overview 3. Opportunity for Economic Development 4. Healthy Community Design 5. Future Conditions Overview 6. Identified Issues 7. Improvements being Evaluated 8. Next Steps 2

3 Project Overview Study Area: Medical Arts District Primary Study Corridor: Central Ave 1.7 miles long Several Secondary Study Corridors 3

4 Project Schedule 16 month schedule ( living document ) 1 Define the Problem April 2017 June Define the Purpose and Need June 2017 December Define Alternatives September 2017 January Evaluate and Select We are Here December 2017 May 2018 Alternatives 5 Formulate Implementation Strategy April 2018 July

5 Public Involvement Three (3) Project Visioning Team meetings Two (2) Public Workshops Individual Stakeholder meetings Medical Arts District Osceola Regional Medical Center Florida Hospital Kissimmee Property Owner/Developer Project Website 5

6 Project Goals MPO and City of Kissimmee want to coordinate the development of a future vision for Central Avenue that establishes a multimodal approach to providing for future transportation needs. Community-based evaluation to determine how best to meet the needs of current and future users. Establish a long-term plan to guide evolution of the corridor that appropriately correlates the balance between land use and transportation planning. 6

7 An Opportunity for Economic Development Improvements to Roads, Trails, and the Public Realm result in Economic Development Opportunity to connect the Seven Mile Loop Opportunity to enhance SunRail Circulator use Case Study Gaines Street, City of Tallahassee An 2011 ECFRPC study estimated that trail users accounted for 25% of downtown Winter Garden sales ($5M/year) 7

8 Gaines Street, Tallahassee FL Four lane, 1.5-mile segment Primarily industrial and brownfield sites Lack of sidewalks and bike lanes Lack of pedestrian amenities 8

9 Gaines Street, Tallahassee FL Cost: $35 million (One-sent sales tax referendum, grants) Safety Improvements: Sidewalks, pedestrian refuges, crossings and signage Place: Public art installations, pedestrian-scale lighting, street furniture Private Investment: $242 million 9

10 Gaines Street, Tallahassee FL Stadium Centre (The Deck, The Block, and The Axis): Residential, student-oriented (2014) Cost: $115 million- $120 million Jobs: 854 (construction); 157 (permanent) Catalyst: Residential, student-oriented (2013) Cost: $25 million Jobs: 500 (construction) 10

11 Healthy Community Design Identifies physical improvements and policies that can result in better health outcomes for the communities served by Central Ave Collaboration with Department of Health, Florida Hospital Kissimmee, and Osceola Regional Medical Center 11

12 Health Trends Asthma 16.0% 14.0% 12.0% 10.0% 8.0% 6.0% 4.0% 2.0% 0.0% Source: Florida Hospital Kissimmee, 2016 Community Health Needs Assessment (CHNA)

13 Health Trends Diabetes 20.0% 18.0% 16.0% 14.0% 12.0% 10.0% 8.0% 6.0% 4.0% 2.0% 0.0% Source: Florida Hospital Kissimmee, 2016 Community Health Needs Assessment (CHNA)

14 Health Trends Obesity 45.0% 40.0% 35.0% 30.0% 25.0% 20.0% 15.0% 10.0% 5.0% 0.0% Source: Florida Hospital Kissimmee, 2016 Community Health Needs Assessment (CHNA)

15 Future Conditions Overview Assumed 3.0% annual growth rate N. Central Avenue Park Place Blvd to Hilda St AADT Regression Source Growth Rate Historical Traffic Volumes 4.80% Travel Demand Model 2.63% BEBR Population Projections 3.35% City of Kissimmee EAR Report 0.96% 15

16 Future Conditions Overview Increased volumes at Central Ave/W Donegan Ave will necessitate a new signal 2022 Baseline Conditions (Unsignalized) AM Peak Mid Day PM Peak v/c Delay LOS v/c Delay LOS v/c Delay LOS NBL F F F NBT/R D E E SBL/T/R C C C EBL A A A EBT/R Unopposed movement WBL A A A WBT/R Unopposed movement 16

17 Future Conditions Overview Roundabout at MLK/Neptune Rd will operate over capacity in 2040 Approach (NOT Direction) 2040 Baseline Conditions AM Peak PM Peak v/c Delay LOS v/c Delay LOS South A D East Lane 1 (Inner) F F East Lane 2 (Outer) B B North Lane 1 (Inner) B F North Lane 2 (Outer) A D West Lane 1 (Inner) B C West Lane 2 (Outer) A C Total C F 17

18 Study Sections Southern: South of US 192 Middle: US 192 to Columbia Ave Northern: North of Columbia Ave Northern Middle Southern 18

19 Southern Section Issues Bike/Ped Transit Roadway Other Southern Section: South of US 192 Lack of midblock crossings No bicycle facilities Limited shade Lack of amenities at stops Stop locations connecting to BRT line Roundabout operations Signal timings at Oak St/Central Ave Intersection safety 19

20 Southern Section Improvements Under Evaluation Off street trail US 192 trail bridge (longer term) Bus stop amenities Road diet/lane repurposing (however, not feasible) Reduce lane width Raised median with landscaping Roundabout improvements Signal retiming Mid-block pedestrian crossings Northern Middle Southern 20

21 OC7 Southern Section-North of MLK JR Blvd Existing Proposed 21

22 Southern Section-At Osceola Regional Medical Ctr Existing Proposed 22

23 Southern Section-At Osceola Regional Medical Ctr Before After 23

24 Southern Section-At Osceola Regional Medical Ctr 24

25 Middle Section Issues Bike/Ped Transit Roadway Other Middle Section: US 192 to Columbia Ave Narrow bike lanes Narrow sidewalks North south connectivity at US 192 Lack of amenities at stops Stop locations connecting to BRT line SB approach at US 192 intersection Intersection safety Drainage Lighting Courtesy of: Google Earth 25

26 Middle Section Potential Improvements Bus stops Amenities Relocation Shared-Use Path Raised median Reduce posted speed Right turn lane for SB approach at US 192/Central Ave intersection Lighting Northern Middle Southern 26

27 Middle Section-North of US 192 Existing Proposed (Assumes utilities buried underground) 27

28 Middle Section-North of US 192 Before After 28

29 Northern Section Issues Bike/Ped Transit Roadway Other Northern Section: Columbia Ave to Donegan Ave Lack of facilities Connectivity to school Lack of crossings No service Columbia Ave Intersection (SB Approach) Donegan Ave Intersection (Signal) Intersection safety Drainage Lighting 29

30 Northern Section Potential Improvements Reduce posted speed Institute school zone Convert to urban crosssection Reduce lane width Add bicycle (shared-use path) and pedestrian facilities Signalize Central Avenue at W Donegan Avenue Peanut roundabout at Park Place Boulevard intersection Lighting Underground utilities Turn lane at Columbia Ave Northern Middle Southern 30

31 OC8 Northern Section-North of Columbia Ave Existing Proposed (Assumes utilities buried underground) 31

32 Northern Section-South of Park Place Blvd Existing Proposed (Assumes utilities buried underground) 32

33 OC9 Northern Section-South of Hilda St Existing Proposed (Assumes utilities buried underground) 33

34 Northern Section- Peanut Roundabout 34

35 Northern Section-South of Hilda St Before After 35

36 Peanut Roundabout 36

37 Hilda Street / Highlands Elementary School 37

38 Next Steps Adjust Proposed Improvements as needed Develop Concept Plans for the Proposed Improvements Apply for LAP Funding for design and construction 38

39 Questions/Comments? Contact Us! Randy Schrader, AICP Senior Planner, Development Services City of Kissimmee Fabricio Ponce, PE Transportation Systems Manager VHB

Road Diets FDOT Process

Road Diets FDOT Process Florida Department of TRANSPORTATION Road Diets FDOT Process Humberto Castillero, PE, PTOE Roadway Design Office Purpose of Guide Develop a statewide lane elimination review process Balance state & local

More information

Southview Blvd & 3 rd Avenue Improvement Project. Public Open House December 4, to 7pm

Southview Blvd & 3 rd Avenue Improvement Project. Public Open House December 4, to 7pm Southview Blvd & 3 rd Avenue Improvement Project Public Open House December 4, 2014 5 to 7pm Southview Blvd & 3 rd Avenue Public Information Meeting Agenda Presentation 5:30 to 6:15 pm Purpose of Project

More information

Downtown Naples Mobility and Connectivity Study. Naples City Council Presentation January 2017

Downtown Naples Mobility and Connectivity Study. Naples City Council Presentation January 2017 Downtown Naples Mobility and Connectivity Study Naples City Council Presentation January 2017 Agenda 1. Introduction 2. Scope Review 3. Project Schedule 4. Existing Conditions 5. Public Charrette 6. Mobility

More information

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY A1 Roadway Resurfacing $23,846,000 TYPE: Preservation of existing system Roadway resurfacing A2 Signal Replacement $6,000,000 TYPE: Preservation of existing system Replace traffic signals. B1 W 6th St

More information

General Plan Circulation Element Update Scoping Meeting April 16, 2014 Santa Ana Senior Center, 424 W. 3rd Street, Santa Ana, CA 92701

General Plan Circulation Element Update Scoping Meeting April 16, 2014 Santa Ana Senior Center, 424 W. 3rd Street, Santa Ana, CA 92701 General Plan Circulation Element Update Scoping Meeting April 16, 2014 Santa Ana Senior Center, 424 W. 3rd Street, Santa Ana, CA 92701 Meeting Agenda 1. Purpose of Scoping Meeting 2. Project Overview 3.

More information

Planning Study SR 976. Project Advisory Team Meeting May 24, 2017

Planning Study SR 976. Project Advisory Team Meeting May 24, 2017 ` SR 976 BIRD ROAD/SW 40TH STREET FROM SR 821/HEFT TO SR 5/US-1 Miami-Dade County, Florida FPID No.: 434845-4-22-01 Planning Study Project Advisory Team Meeting May 24, 2017 1 Agenda Introductions Project

More information

In station areas, new pedestrian links can increase network connectivity and provide direct access to stations.

In station areas, new pedestrian links can increase network connectivity and provide direct access to stations. The Last Mile Planning for Pedestrians Planning around stations will put pedestrians first. Making walking to stations safe and easy is important; walking will be a part of every rapid transit Accessible

More information

Executive Summary Route 30 Corridor Master Plan

Executive Summary Route 30 Corridor Master Plan Route Corridor Master Plan Project Overview The Route Corridor Master Plan is a coordinated multimodal transportation and land use plan for the entire stretch of Route through East Whiteland Township,

More information

US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue

US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue 41 US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue EXECUTIVE SUMMARY DRAFT FEBRUARY 2019 Project Overview The US 41 Complete Streets Corridor Planning Study,

More information

OCALA/MARION TPO CITY OF BELLEVIEW CORRIDOR PLAN STUDY PRESENTATION TO THE BELLEVIEW CITY COMMISSION JANUARY 25, :00 PM

OCALA/MARION TPO CITY OF BELLEVIEW CORRIDOR PLAN STUDY PRESENTATION TO THE BELLEVIEW CITY COMMISSION JANUARY 25, :00 PM OCALA/MARION TPO CITY OF BELLEVIEW CORRIDOR PLAN STUDY PRESENTATION TO THE BELLEVIEW CITY COMMISSION JANUARY 25, 2016 6:00 PM STUDY AREA Ocala/Marion TPO US-441 Corridor Study 2 Ocala/Marion TPO US-441

More information

MAYFIELD ROAD CORRIDOR MULTIMODAL TRANSPORTATION PLAN. Public Workshop

MAYFIELD ROAD CORRIDOR MULTIMODAL TRANSPORTATION PLAN. Public Workshop MAYFIELD ROAD CORRIDOR MULTIMODAL TRANSPORTATION PLAN Public Workshop 06.06.18 AGENDA Project Process & Schedule Document Review Summary Project Goals Initial Findings Concept Development Next Steps PROJECT

More information

Completing the Street: Denning Drive

Completing the Street: Denning Drive Completing the Street: Denning Drive Public Workshop and Walking Audit Winter Park Civic Center May 12, 2016 Completing the Street What Makes This a Complete Street? Completing the Street Complete Streets

More information

SR 693 (Pasadena Avenue) Corridor Study from Shore Drive South to 66 th Street

SR 693 (Pasadena Avenue) Corridor Study from Shore Drive South to 66 th Street Welcome and Introduction Sign-in and comment sheets Restrooms and exits Meeting agenda and timeline Meeting goals / expectations Provide input to guide study recommendations Actively participate throughout

More information

Appendix G: Future Conditions Traffic Analysis Memorandum

Appendix G: Future Conditions Traffic Analysis Memorandum ppendix G: Future Conditions Traffic nalysis Memorandum Prepared by: Bolton & Menk, Inc. Riverfront Drive Corridor Study ǀ T42.867 ppendix MEMORNDUM Date: pril, 27 To: Paul Vogel From: Ross B. Tillman,

More information

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Aaron Elias, Bill Cisco Abstract As part of evaluating the feasibility of a road diet on Orange Grove Boulevard in Pasadena,

More information

Atwood Avenue Fair Oaks Avenue Cottage Grove Road

Atwood Avenue Fair Oaks Avenue Cottage Grove Road Atwood Avenue Fair Oaks Avenue Cottage Grove Road Agenda Purpose Review project scope & goals Present design alternatives Gather feedback Answer Questions Format Open House Presentation Q&A Open House

More information

Safe Streets. City of Lake Forest Park. March 21, 2017

Safe Streets. City of Lake Forest Park. March 21, 2017 Safe Streets City of Lake Forest Park March 21, 2017 1 01 WELCOME 2 Agenda WELCOME WHAT IS THIS PROJECT? CONTEXT DRAFT CITYWIDE PROJECTS EXERCISE INTRODUCTION 3 02 WHAT IS THIS PROJECT? 4 WHAT IS THIS

More information

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn

More information

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto

More information

Montgomery County Life Sciences Center Loop Trail

Montgomery County Life Sciences Center Loop Trail Montgomery County Life Sciences Center Loop Trail Advisory Committee Meeting #1 February 10, 2015 Agenda 1. Project Background 2. Existing Conditions Analysis 3. Examples from Elsewhere 4. Discussion Project

More information

RETREAT AGENDA ITEM MIDTOWN AREA TRANSPORTATION PLAN UPDATE

RETREAT AGENDA ITEM MIDTOWN AREA TRANSPORTATION PLAN UPDATE October 17, 2017 RETREAT AGENDA ITEM MIDTOWN AREA TRANSPORTATION PLAN UPDATE STATEMENT OF ISSUE An update on the Midtown Area Transportation Plan will be provided including a discussion of preliminary

More information

NEWMARKET UPHAM S CORNER

NEWMARKET UPHAM S CORNER SOUTH STATION Planning Initiative NEWMARKET UPHAM S CORNER COLUMBIA ROAD (P) FOUR CORNERS/GENEVA Working Advisory Group (WAG) Meeting #5 TALBOT AVENUE MORTON STREET BLUE HILL AVE/CUMMINS HWY (P) RIVER

More information

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of

More information

Town of Bethlehem. Planning Assessment. Bethlehem Town Board

Town of Bethlehem. Planning Assessment. Bethlehem Town Board Town of Bethlehem US 9W Corridor Transportation Planning Assessment Presented e to: Bethlehem Town Board June 2009 Overview Study Background Route 9W Corridor Conditions and Improvements Selkirk Bypass

More information

Public Workshop #2. September 14, 2016

Public Workshop #2. September 14, 2016 Public Workshop #2 September 14, 2016 Agenda Welcome Project Overview Where We Have Been Alternatives for State Street Land Use Street Design Next Steps 2 Project Overview Create a Vibrant State Street

More information

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN Section VIII Mobility Element Goals, Objectives, and Policies Adopted August 6, 2015 by Ordinance No. 1591 VIII MOBILITY ELEMENT Table of Contents Page Number

More information

Beach Cities Living Streets Design Manual and Aviation Boulevard Multimodal Corridor Plan

Beach Cities Living Streets Design Manual and Aviation Boulevard Multimodal Corridor Plan Beach Cities Living Streets Design Manual and Aviation Boulevard Multimodal Corridor Plan AGENDA 1 Introductions & Project Scope 2 Public Outreach Recap 3 Living Streets Design Manual 4 Aviation Boulevard

More information

2015 Florida Main Street Annual Conference. Complete Streets Equal Stronger Main Streets

2015 Florida Main Street Annual Conference. Complete Streets Equal Stronger Main Streets WHAT ARE COMPLETE STREETS? CASE STUDIES COMPLETING YOUR MAIN STREET 2015 Florida Main Street Annual Conference St. Petersburg, Florida August 19, 2015 WHAT ARE COMPLETE STREETS? CASE STUDIES COMPLETING

More information

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 What s Happening The City plans to mill and resurface Dr. M.L.

More information

Route 7 Corridor Study

Route 7 Corridor Study Route 7 Corridor Study Executive Summary Study Area The following report analyzes a segment of the Virginia State Route 7 corridor. The corridor study area, spanning over 5 miles in length, is a multi

More information

Walkability Audit Cities of Olympia, Tumwater and Lacey, Washington. Next Steps Memorandum September FINAL

Walkability Audit Cities of Olympia, Tumwater and Lacey, Washington. Next Steps Memorandum September FINAL Walkability Audit Cities of Olympia, Tumwater and Lacey, Washington Memorandum September 2012 - FINAL 1. INTRODUCTION The U.S. Environmental Protection Agency (EPA) selected the Thurston Regional Planning

More information

Linking Transportation and Health in Nashville & Middle Tennessee

Linking Transportation and Health in Nashville & Middle Tennessee Linking Transportation and Health in Nashville & Middle Tennessee Fit Nation New Orleans CPPW Mentoring Grant Built Environment Program May 14, 2011 Local Transportation Planning Framework Federal U.S.

More information

Implementing Complete Streets: The Road Diet. Ed McKinney, AICP Senior Associate, Glatting Jackson

Implementing Complete Streets: The Road Diet. Ed McKinney, AICP Senior Associate, Glatting Jackson Implementing Complete Streets: The Road Diet Ed McKinney, AICP Senior Associate, Glatting Jackson How do we implement complete streets on our existing roads? Many Roads Could Use a road diet Trying to

More information

Bellevue Transportation: Challenges, Opportunities and Priorities Bellevue Downtown Association September 20, 2018

Bellevue Transportation: Challenges, Opportunities and Priorities Bellevue Downtown Association September 20, 2018 Bellevue Transportation: Challenges, Opportunities and Priorities Bellevue Downtown Association September 20, 2018 Dave Berg Transportation Director City of Bellevue Traffic, traffic and more traffic!

More information

CRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN

CRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN CRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN Preferred Plan Community Presentation September 27, 2017 City of El Paso de Robles in partnership with: Local Government Commission, W-Trans,

More information

Pine Hills Road Pedestrian/Bicycle Safety Study Community Meeting #1

Pine Hills Road Pedestrian/Bicycle Safety Study Community Meeting #1 Pine Hills Road Pedestrian/Bicycle Safety Study Community Meeting #1 June 8, 2017 Meeting Agenda Study Overview Community Survey Existing Conditions Access Management Potential Safety Countermeasures Potential

More information

PEDESTRIAN ACTION PLAN

PEDESTRIAN ACTION PLAN ATTACHMENT 2 CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN This page intentionally left blank EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY Setting the Stage

More information

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them?

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them? Overview Illinois Bike Summit IDOT Complete Streets Policy Presentation Aren Kriks, P.E. District One Bicycle Coordinator and Bureau of Programming Project Engineer History of Complete Streets IDOT Policy

More information

HARRISON STREET/OAKLAND AVENUE COMMUNITY TRANSPORTATION PLAN

HARRISON STREET/OAKLAND AVENUE COMMUNITY TRANSPORTATION PLAN HARRISON STREET/OAKLAND AVENUE Community Workshop #4: Draft Plan Review December 3, 2009 D E S I G N, C O M M U N I T Y & E N V I R O N M E N T INTRODUCTIONS Key Project Staff: Alisa Shen, Project Manager,

More information

What Is a Complete Street?

What Is a Complete Street? Session 5 Charleen Zimmer, AICP, Zan Associates May 5-7, 2010 What Is a Complete Street? May 2010 5-1 Not a Complete Street More of a Complete Street May 2010 5-2 Benefits of Complete Streets Safety for

More information

PROJECT OBJECTIVES. Improve vehicle capacity for the intersection. Improve pedestrian and bicycle access

PROJECT OBJECTIVES. Improve vehicle capacity for the intersection. Improve pedestrian and bicycle access COMMUNITY MEETING Project Update March 15, 2010 Purcellville, Virginia OVERVIEW Project need / objectives Project recap Design elements Proposed improvements Summary of project benefits / next steps PROJECT

More information

Community Task Force July 25, 2017

Community Task Force July 25, 2017 Community Task Force July 25, 2017 Welcome and Introductions Project Partners Regional Transportation District (RTD) Colorado Department of Transportation (CDOT) Denver Regional Council of Governments

More information

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD INTERSECTION NEEDS AT SR 7 and OKEECHOBEE BOULEVARD SR 7 Extension Project Development and Environment (PD&E) Study From Okeechobee Boulevard (SR

More information

GIS Based Data Collection / Network Planning On a City Scale. Healthy Communities Active Transportation Workshop, Cleveland, Ohio May 10, 2011

GIS Based Data Collection / Network Planning On a City Scale. Healthy Communities Active Transportation Workshop, Cleveland, Ohio May 10, 2011 The Purpose of GIS Based Network Planning GIS Based Data Collection / Network Planning Healthy Communities Active Transportation Conference Tuesday, May 10, 2011 10:00 AM Norman Cox, LLA, ASLA. Ann Arbor,

More information

City of Wausau Wausau Center Urban Design and Transportation Master Plan. Design Workshop // October 18, 2018

City of Wausau Wausau Center Urban Design and Transportation Master Plan. Design Workshop // October 18, 2018 City of Wausau Wausau Center Urban Design and Transportation Master Plan Design Workshop // October 18, 2018 Design Workshops // October 15-18 Workshop Study Evaluate circulation and parking patterns around

More information

Austell Road Access Management Plan Public Meeting February 17, 2009

Austell Road Access Management Plan Public Meeting February 17, 2009 Austell Road Access Management Plan Public Meeting February 17, 2009 Laraine Vance: Dan Cohen: Cobb DOT Project Manager Pond & Company Planning Director 1 Access Management What is Access Management? The

More information

US 278 Corridor Concept Presentation. Avondale Estates Intersection Improvement/Roundabout and Road Diet Feasibility Study March 19, 2015

US 278 Corridor Concept Presentation. Avondale Estates Intersection Improvement/Roundabout and Road Diet Feasibility Study March 19, 2015 US 278 Corridor Concept Presentation Avondale Estates Intersection Improvement/Roundabout and Road Diet Feasibility Study March 19, 2015 Thanks to our Partners Atlanta Regional Commission Georgia Department

More information

Task Force Meeting #5, August 3, Prepared by DKS Associates

Task Force Meeting #5, August 3, Prepared by DKS Associates Task Force Meeting #5, August 3, 2018 Prepared by DKS Associates Agenda 1. Agenda Review and Meeting #4 Recap 2. Review Project Goal, Data, and Project Ideas 3. Recommendations and Reporting a) Recommended

More information

Colchester/Riverside/Barrett/ Mill Intersection Study. PAC Meeting #3 September 22, 2016

Colchester/Riverside/Barrett/ Mill Intersection Study. PAC Meeting #3 September 22, 2016 Colchester/Riverside/Barrett/ Mill Intersection Study PAC Meeting #3 September 22, 2016 Tonight s Agenda Review Project Purpose and Need Describe short term and long improvements and changes since public

More information

Complete Streets Training. Georgia Municipal Association June 27, 2016

Complete Streets Training. Georgia Municipal Association June 27, 2016 Complete Streets Training Georgia Municipal Association June 27, 2016 Overview What are CS? GDOT s Policy Case Study 2 What are Complete Streets? According to the National Complete Streets Coalition, complete

More information

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

Omaha s Complete Streets Policy

Omaha s Complete Streets Policy Omaha s Complete Streets Policy (Adopted August 2015) VISION To create great places and enhance our quality of life, the City of Omaha will provide safe, accessible streets for all users. Complete Streets

More information

WELCOME. to the meeting for the. Westside Avenue Action Plan Gateway to Revitalization

WELCOME. to the meeting for the. Westside Avenue Action Plan Gateway to Revitalization WELCOME to the meeting for the Columbia Road - Before and After Ridge Road - Before and After Before and After WAAP Bridge Sections Fountain Creek Before Retaining Wall for Roadway 30' Existing Fountain

More information

5 CIRCULATION AND STREET DESIGN

5 CIRCULATION AND STREET DESIGN 5 CIRCULATION AND STREET DESIGN This chapter describes circulation and streetscape improvements proposed for the Northwest Chico Specific Plan Area. It includes detailed design specifications for existing

More information

UNIVERSITY AVENUE CORRIDOR REDESIGN. January 8, 2017 PUBLIC OPEN HOUSE

UNIVERSITY AVENUE CORRIDOR REDESIGN. January 8, 2017 PUBLIC OPEN HOUSE January 8, 2017 PUBLIC OPEN HOUSE COLLABORATIVE COMMUNITY-BASED DESIGN IS THE FOUNDATION TO A SUCCESSFUL PROJECT AGENDA FOR TONIGHT 1 INTRODUCTIONS 2 WHY ARE WE HERE PROJECT NEED 3 SCHEDULE & GOALS 4 OPEN

More information

AMENDING MOTION: Mobility Plan - Pedestrians and Disadvantaged Communities

AMENDING MOTION: Mobility Plan - Pedestrians and Disadvantaged Communities I MOVE that the Council: AMENDING MOTION: Mobility Plan - Pedestrians and Disadvantaged Communities 1. INSTRUCT the Department of City Planning to amend the proposed Mobility Plan to include the following;

More information

Advancing Transportation Choices in Des Moines. MPO Environmental Roundtable January 9, 2018

Advancing Transportation Choices in Des Moines. MPO Environmental Roundtable January 9, 2018 Advancing Transportation Choices in Des Moines MPO Environmental Roundtable January 9, 2018 Presented by Jennifer McCoy, PE, PTOE City Traffic Engineer Agenda Des Moines Area Transportation Planning Connect

More information

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

Prince George s County plans, policies, and projects

Prince George s County plans, policies, and projects Prince George s County plans, policies, and projects Over 250 projects for trails, bikeways, designated bike lanes and sidewalk construction Trail projects that improve access to Metro Sidewalk and trail

More information

TRANSPORTATION FACILITY PLANNING Waugh Chapel Road Maytime Drive to New Market Lane

TRANSPORTATION FACILITY PLANNING Waugh Chapel Road Maytime Drive to New Market Lane July 24, 2018 TRANSPORTATION FACILITY PLANNING Waugh Chapel Road Maytime Drive to New Market Lane DPWandYOU.com Making a difference, together Meeting Agenda Purpose of the project Overview of work conducted

More information

Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue

Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue T A N Y A B R O O K S A S S I S T A N T D I R E C T O R M O B I L I T Y P L A N N I N G M O B I L I T Y A N D S

More information

COMMUNITY MEETING AGENDA

COMMUNITY MEETING AGENDA COMMUNITY MEETING AGENDA Welcome and Introductions SAFE Presentation Project Presentation Priorities Feedback Next Steps Q&A Santa Cruz Avenue Corridor Study 1 Santa Cruz Avenue Corridor Study Community

More information

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 7 DISTRICT WIDE BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT AND IMPROVEMENT PLAN

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 7 DISTRICT WIDE BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT AND IMPROVEMENT PLAN FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 7 DISTRICT WIDE BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT AND IMPROVEMENT PLAN TRANSIT SAFETY ASSESSMENT SR 55/US 19 AT 80 TH AVE N DRAFT JUNE

More information

KEARNY MESA COMMUNITY PLAN UPDATE

KEARNY MESA COMMUNITY PLAN UPDATE KEARNY MESA COMMUNITY PLAN UPDATE January 18, 2018 SUBCOMMITTEE MEETING Mobility Concepts and Urban Design Presentation Outline Mobility Concepts: Multimodal Planning Toolbox Presentation and Activities

More information

TRANSPORTATION STANDARDS

TRANSPORTATION STANDARDS INTRODUCTION LOCAL STREETS ON-STREET PARKING SIDEWALKS STREET LIGHTING STREET FURNISHINGS TRAFFIC CALMING STREET TREES MEDIAN PLANTING BOULEVARD LOCATIONS VILLAGE CENTER STREET LOCATIONS RESIDENTIAL STREET

More information

Route 79/Davol Street Corridor Study

Route 79/Davol Street Corridor Study Route 79/Davol Street Corridor Study Fall River, MA Public Information Meeting #2 November 21, 2013 Fall River Heritage State Park Fall River, MA Agenda Welcome and Introductions Overview of Study Process

More information

Reference number /VP. Lafayette Downtown Congestion Study - Additional Traffic Analysis

Reference number /VP. Lafayette Downtown Congestion Study - Additional Traffic Analysis To James Hinkamp and Tony Coe, City of Lafayette Date January 19, 2017 Copies Reference number 243381/VP From Michael Iswalt and Vanessa Peers File reference 4-05 Subject Lafayette Downtown Congestion

More information

Ocean Park Boulevard Green Street Project Alternatives & Trade Offs

Ocean Park Boulevard Green Street Project Alternatives & Trade Offs Planning Commission March 4, 2009 Ocean Park Boulevard Green Street Project Alternatives & Trade Offs Purpose of Tonight s Meeting Review concept plans and options Provide input on alternatives and trade-offs

More information

Tonight is for you. Learn everything you can. Share all your ideas.

Tonight is for you. Learn everything you can. Share all your ideas. Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.

More information

Welcome. If you have any questions or comments on the project, please contact:

Welcome. If you have any questions or comments on the project, please contact: Welcome This drop-in public open house is intended to provide information about the Bay Street bike lanes project. This project proposes a dedicated cycling facility along Bay Street between Aberdeen Avenue

More information

Roads and Vehicular Traffic Design Principles. Roads and Vehicular Traffic Recommendations

Roads and Vehicular Traffic Design Principles. Roads and Vehicular Traffic Recommendations CIRCULATION AND PARKING roads and vehicular traffic The Campus Master Plan updates the campus transportation network through a multi-modal approach that encourages walking and biking while improving vehicular

More information

TPA Committee Meetings May 2018

TPA Committee Meetings May 2018 TPA Committee Meetings May 2018 Purpose Develop a comprehensive plan to identify multimodal improvements for all users of the roadway and evaluate the potential for a premium express bus service Overview

More information

Virginia Street Bus RAPID Transit Extension Project. Environmental Assessment (EA) Presentation Public Hearing June 22, 2017

Virginia Street Bus RAPID Transit Extension Project. Environmental Assessment (EA) Presentation Public Hearing June 22, 2017 Virginia Street Bus RAPID Transit Extension Project Environmental Assessment (EA) Presentation Public Hearing June 22, 2017 Presentation to RTC July 17, 2015 Presentation Overview Project Timeline Environmental

More information

Chapter 3 BUS IMPROVEMENT CONCEPTS

Chapter 3 BUS IMPROVEMENT CONCEPTS Chapter 3 BUS IMPROVEMENT CONCEPTS The purpose of this chapter is to describe potential bus improvement strategies and potential impacts or implications associated with BRT implementation within the existing

More information

A CHANGING CITY. of Edmonton, it is essential that it reflects the long-term vision of the City.

A CHANGING CITY. of Edmonton, it is essential that it reflects the long-term vision of the City. A CHANGING CITY By the year 2040, Edmonton will be home to more than 1 million people. To accommodate growth and support a healthy and compact city, we need a new approach to development/redevelopment

More information

WELCOME! Please complete a comment sheet as we value your feedback. 4 pm to 8 pm. September 15, Hosted by: AECOM on behalf of City of Calgary

WELCOME! Please complete a comment sheet as we value your feedback. 4 pm to 8 pm. September 15, Hosted by: AECOM on behalf of City of Calgary WELCOME! Thank you for attending our open house. There will be no formal presentation today so please take the time to read the boards. If you have any questions, please do not hesitate to approach one

More information

Carmel, Indiana Illinois Street and 126th Street Westfield Boulevard and 96th Street Arts and Design District RAB

Carmel, Indiana Illinois Street and 126th Street Westfield Boulevard and 96th Street Arts and Design District RAB Sustainability Benefits Of Network Wide Roundabout Use Case Study of Carmel, Indiana Presented By: Michael McBride PE Carmel City Engineer Carmel, Indiana Carmel, Indiana 1996 Carmel, Indiana Population

More information

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach CONNECTIVITY PLAN Adopted December 5, 2017 City of Virginia Beach CONTENTS 1.0 Background & Purpose... 2 2.0 Existing Inventory & Analysis... 3 ViBe District Existing Walking Conditions... 4 3.0 ViBe District

More information

INNER LOOP EAST. AIA Rochester Annual Meeting November 13, 2013 TRANSFORMATION PROJECT. Bret Garwood, NBD Erik Frisch, DES

INNER LOOP EAST. AIA Rochester Annual Meeting November 13, 2013 TRANSFORMATION PROJECT. Bret Garwood, NBD Erik Frisch, DES INNER LOOP EAST TRANSFORMATION PROJECT AIA Rochester Annual Meeting November 13, 2013 Bret Garwood, NBD Erik Frisch, DES Why? We are building a city that encourages walking, biking and enjoying the outdoor

More information

PUBLIC REALM MASTER PLAN

PUBLIC REALM MASTER PLAN WESTSHORE BUSINESS DISTRICT PUBLIC REALM MASTER PLAN MASTER PLAN COMMITTEE MEETING MARCH 20, 2013 WESTSHORE BUSINESS DISTRCT PUBLIC REALM MASTER PLAN MACRO-SCALE CONCEPT: A PUBLIC REALM FRAMEWORK DEFINED

More information

LANE ELIMINATION PROJECTS

LANE ELIMINATION PROJECTS PRESENTATION OUTLINE Lane Elimination Considerations Districts 4 & 7 Draft Lane Elimination Processes FDOT Lane Elimination Guidelines Example Projects D4 Case Study: SR A1A (Ft. Lauderdale) D7 Case Study:

More information

PEDESTRIAN ACTION PLAN

PEDESTRIAN ACTION PLAN CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN DRAFT OCTOBER 2015 Safe Streets Santa Monica, December 3, 2015 Beth Rolandson, AICP Principal Transportation Planner Strategic + Transportation Planning, Planning

More information

City of Waterloo Complete Streets Policy

City of Waterloo Complete Streets Policy City of Waterloo Complete Streets Policy Chris Hodgson P. Eng City of Waterloo Complete Streets Forum 2011 April 28-29 Toronto Waterloo context: Current population Major employers Universities and student

More information

Transportation Planning Division

Transportation Planning Division Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meeting Stakeholder Interviews Data Collection Design Principles Tool Box Recommendations Schedule Moving Forward North

More information

Environmental Assessment Findings & Recommendations. Public Hearing November 13, 2014

Environmental Assessment Findings & Recommendations. Public Hearing November 13, 2014 Environmental Assessment Findings & Recommendations Public Hearing November 13, 2014 Welcome! Welcome and Introductions Project and Environmental Assessment Overview Public Comments Adjourn Purpose of

More information

DISTRICT BICYCLE PROGRAM

DISTRICT BICYCLE PROGRAM DISTRICT BICYCLE PROGRAM TxDOT Fort Worth District Public Hearing Bicycle Use on the State Highway System Public Hearing Agenda 1 2 3 4 5 6 Introduction Susan Howard TxDOT Public Involvement Specialist

More information

2012 PRIORITY TRANSPORTATION PROJECTS

2012 PRIORITY TRANSPORTATION PROJECTS 0 PRIORITY TRANSPORTATION PROJECTS The 0 Priority Transportation Projects include candidate road, congestion management, multi-use trail, transit, transportation regional incentive program (TRIP), county

More information

WELCOME. Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018

WELCOME. Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018 WELCOME Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018 MEETING AGENDA 1. Welcome and Introductions 2. Study Progress Update 3. Problem Statement 4. Technical Analysis

More information

7 Complete Streets & Roadway Aesthetics

7 Complete Streets & Roadway Aesthetics 7 Complete Streets & Roadway Aesthetics 7.1 OVERVIEW Our streets lay the foundation for how we interface with travel needs, physical exercise, social exchanges and access to goods and services. They are

More information

US 301 Resurfacing, Restoration, and Rehabilitation

US 301 Resurfacing, Restoration, and Rehabilitation US 301 Resurfacing, Restoration, and Rehabilitation From Pond Ave to North of Pioneer Museum Rd/Long Ave Pasco County, FL Work Program Item No. 429075-2 Project Overview Project Location: POND AVE WHITEHOUSE

More information

Community Transportation Plan Acknowledgements

Community Transportation Plan Acknowledgements Community Transportation Plan Acknowledgements The Decatur CTP was developed with participation and guidance from City of Decatur staff, its Resident Boards and Commissions, and numerous residents, business

More information

Project Advisory Group (PAG) Meeting #2 January 31, SR 693 (Pasadena Avenue) Corridor Study from Shore Drive South to 66 th Street

Project Advisory Group (PAG) Meeting #2 January 31, SR 693 (Pasadena Avenue) Corridor Study from Shore Drive South to 66 th Street Project Advisory Group (PAG) Meeting #2 January 31, 2018 Welcome & Introductions AGENDA 1. Where are we at? 2. Project Survey / Virtual Comment Tool / PAG Meeting #1 / Visioning Workshop Corridor Map Exercise

More information

Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary January 19 LPT ATTACHMENT 2.

Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary January 19 LPT ATTACHMENT 2. Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary 2011 January 19 1 of 19 Introduction This executive summary presents the results of the Southwest Bus Rapid Transit (SW

More information

MAKE YOUR PLACE IN CHANNELSIDE

MAKE YOUR PLACE IN CHANNELSIDE MAKE YOUR PLACE IN CHANNELSIDE INTRODUCTION PROJECT LIMITS Channelside Drive from Cumberland Ave to Kennedy Boulevard EXISTING CONDITIONS EXISTING CONDITIONS CHANNELSIDE DRIVE FROM E. CUMBERLAND AVENUE

More information

City of Moorhead Committee of the Whole Meeting

City of Moorhead Committee of the Whole Meeting City of Moorhead Committee of the Whole Meeting Corridor Study Limits Center Avenue (Red River to 8th Street) TH 10 (Red River to TH 336) TH 75 (20th Ave S to Main Avenue) 2 Study Need: Project Overview

More information

TRANSPORTATION COMMISSION Agenda Staff Report

TRANSPORTATION COMMISSION Agenda Staff Report TRANSPORTATION COMMISSION Agenda Staff Report Agenda Item No. 5.a DATE: JULY 31, 2014 TO: FROM: SUBJECT: TRANSPORTATION COMMISSION COMMUNITY DEVELOPMENT DEPARTMENT - PLANNING DRAFT OLYMPIC CORRIDOR PREFERRED

More information

Access BART: TOD and Improved Connections. October 29, 2008

Access BART: TOD and Improved Connections. October 29, 2008 Access BART: TOD and Improved Connections October 29, 2008 1 Access BART Study Goals Evaluate at the system-level land use and access scenarios to optimize ridership Identify station clusters that provide

More information

THIRD&GRAND. Public Workshop #1. Transportation Hub Area Plan. June 12, 2013

THIRD&GRAND. Public Workshop #1. Transportation Hub Area Plan. June 12, 2013 Transportation Hub Area Plan Public Workshop #1 June 12, 2013 Agenda Study Background Who is Involved Process and Schedule Planning Area and Project Site The Opportunity Site Analysis Land Use/Zoning Transportation

More information

Orange County s Transportation Planning and Multimodal Corridor Plan

Orange County s Transportation Planning and Multimodal Corridor Plan Orange County Transportation Planning Division Orange County s Transportation Planning and Multimodal Corridor Plan Presentation to UCF LIFE November 11, 2014 Alissa Barber Torres, Ph.D., AICP, PLS Presentation

More information

Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs

Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs City Council Study Session January 27, 2009 Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs Scope of Work Purpose of Tonight s Meeting Review work to date and direct staff

More information