Safe Work Procedure for installation of external cladding

Size: px
Start display at page:

Download "Safe Work Procedure for installation of external cladding"

Transcription

1 Safe Work Procedure for installation of external cladding This procedure has been formulated to cover safe systems of work for the installation of external cladding. This instruction will be used to reduce risks to workers health and the health and safety of others working on the site. This procedure encompasses systems of work involving access and egress, public protection, tools and equipment, removal of rubbish, storage of materials, personal protective equipment and working at heights. fasteners and explosive charges of electrical equipment 3. Hours of work 4. Training and information training in: 5. Site access and egress General site access and egress will be maintained in a manner that is safe and without endangering any employees or subcontractors working on site, being performed on the site. 6. Unauthorised entry entry and suitable signage is to be put in place to warn site workers of any dangers. 7. Safety of public/workers not involved minimise the risk of injury to the public, contractors and other personnel working on the site. 8. Removal of rubbish and excess materials performance shall be placed in the appropriate area ie. in the cage or waste bags provided. 9. Personal protective equipment (PPE) 10. Work method statement Tools and equipment ensure that the tools or equipment are accompanied by the relevant safety information with regard to the safe operation of the tools, latest servicing logbook the tools are to be rejected from site register where required. recorded in the register the care and use of these types of equipment excessive dust or dust making machinery set up for prolonged use. Material handling lifting equipment where necessary to carry, are to be manoeuvred by at least two people and where possible, lifting appliances will be used or site works.

2 Safe Work Procedure for installation of external cladding 10. Work method statement (continued) Ladders faults should be repaired or the ladder replaced e.g. driveways and doorways and appropriate fall protection equipment is used in conjunction with the ladder movements or footed by another person to prevent the ladder from slipping power lines or electrical equipment force which, if released, may cause the user to over balance or fall from the ladder. Safety harness possible to provide temporary platforms, safety harnesses will be used tonnes set up to prevent lanyards and inertia reel lines from being cut on sharp edges. Scaffold permitted. in use to ensure that no movement occurs from power lines responsible for reporting any faults in the erection and maintenance of the public is present, all work shall cease until the risk is controlled 11. Authorisation Working platforms (trestles) supervisor to be actioned immediately for housing construction supporting surface weight of tools, equipment and impact forces

3 Safe Work Procedure for THE USE OF ELEVATED WORK PLATFORM / SCISSOR LIFT, BOOM LIFT This procedure has been formulated to cover safe systems of work when using be used to reduce risks to workers health and the health and safety of others working on the site. 3. Training and information Use of EWP to the roof or other level of a building lift or stand on the handrails 7. Authorisation 4. Unauthorised entry entry and suitable signage is to be put in place to warn other site workers of any dangers. 5. Personal protective equipment (PPE) 6. Work safety method Work procedure operate these plant items known and not exceeded areas Pre use inspection

4 Safe work procedure for the manual handling of equipment and materials This procedure has been formulated to cover safe systems of work for the manual handling of equipment and materials. This instruction will be used to reduce risks to workers health and the health and safety of others working on the site. 3. Training and information or site works. awkward postures and movements including the possibility of slips, trips and falls trafficable areas, workers shall wear high visibility vests and have the hard hat area 7. Authorisation 4. Unauthorised entry entry and suitable signage is to be put in place to warn other site workers of any dangers. 5. Personal protective equipment (PPE) 6. Work safety method lifting equipment where necessary greasy surfaces to be manoeuvred by at least two people

5 Safe work procedure for RENDERING WORKS This procedure has been formulated to cover safe systems for rendering works. This instruction will be used to reduce risks to workers health and the health and safety of others working on the site. This procedure encompasses systems of work involving access and egress, public protection, tools and equipment, removal of rubbish, storage of materials, personal protective equipment and working at heights. fasteners and explosive charges of electrical equipment 3. Hours of work 4. Training and information training in: 5. Site access and egress General site access and egress will be maintained in a manner that is safe and without endangering any employees or subcontractors working on site, being performed on the site. 6. Unauthorised entry entry and suitable signage is to be put in place to warn site workers of any dangers. 7. Safety of public/workers not involved minimise the risk of injury to the public, contractors and other personnel working on the site. 8. Removal of rubbish and excess materials performance shall be placed in the appropriate area ie. in the cage or waste bags provided. 9. Personal protective equipment (PPE) 10. Work method statement Application condition until the contents have been completely removed and the Tools and equipment ensure that the tools or equipment are accompanied by the relevant safety information with regard to the safe operation of the tools, latest servicing logbook the tools are to be rejected from site register where required. recorded in the register the care and use of these types of equipment excessive dust or dust making machinery set up for prolonged use.

6 Safe work procedure for RENDERING WORKS 10. Work method statement (continued) Material handling lifting equipment where necessary are to be manoeuvred by at least two people and where possible, lifting appliances will be used or site works. Ladders faults should be repaired or the ladder replaced e.g. driveways and doorways and appropriate fall protection equipment is used in conjunction with the ladder movements or footed by another person to prevent the ladder from slipping power lines or electrical equipment force which, if released, may cause the user to over balance or fall from the ladder. Safety harness possible to provide temporary platforms, safety harnesses will be used and set up to prevent lanyards and inertia reel lines from being cut on sharp edges. supporting surface weight of tools, equipment and impact forces Scaffold permitted. in use to ensure that no movement occurs from power lines. responsible for reporting any faults in the erection and maintenance of the public is present, all work shall cease until the risk is controlled. 11. Authorisation Working platforms (trestles) supervisor to be actioned immediately for housing construction

S31 Opening Statement Working at Height

S31 Opening Statement Working at Height S31 Opening Statement Working at Height Falls from height are by far the most common cause of workplace deaths and one of the main causes of major injury in the workplace. Latest figures reveal that 46

More information

Working at Height - MEWPS & Ladders. Your company details Address Tel: Fax: Mobile:

Working at Height - MEWPS & Ladders. Your company details Address Tel: Fax: Mobile: Project/Contract Contractor Site Address Project Start Date Expected Duration Projected Completion Date Your company details Address Tel: Fax: Mobile: Document Author Authorised by Name Title Signature

More information

Safe Work Method Statement

Safe Work Method Statement TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Working at eight SWMS No. 16 Authorized and email Signed by the (Managing

More information

Safety Risk Assessment Roofing Works / Surveying / Inspections

Safety Risk Assessment Roofing Works / Surveying / Inspections One Direct aintenance td Persons at (Groups) Assessor Appointment Tel. No. Description of Task or Activity A One Direct employees ark Bloxidge H&S anager 0208 821 5197 One Direct Operatives accessing roof

More information

Method Statement Author

Method Statement Author Plan Bee Limited 3.3 Etna Industrial estate Clamp Road Motherwell Scotland ML2 7XQ Tel: 01698580572 Method Statement Method Statement Details Method Statement Number 7 Method Statement Date Monday 3rd

More information

Permit-To-Work Guidance and Templates

Permit-To-Work Guidance and Templates Managing Contractors Policy - Appendix E Permit-To-Work Guidance and Templates This document has been constructed to provide guidance in how to use a permit to work correctly. The first part explains the

More information

Safe Work Method Statement (SWMS)

Safe Work Method Statement (SWMS) Safe Work Method Statement (SWMS) Organisation Details : Organisation Name Northern Plumbing Contact ABN 17 15 41 4 Position Director Address 47 Thomas Street Edgeworth 85 Phone Number 0411 10 4 Project

More information

FATAL AND SEVERE RISK PROGRAM

FATAL AND SEVERE RISK PROGRAM FATAL AND SEVERE RISK PROGRAM LEADER SESSION FALL FROM HEIGHTS Only do the task if it can be done safely FALL FROM HEIGHTS OUR COMMITMENT LIFE SAVING BEHAVIOUR: I WILL ALWAYS USE ADEQUATE PROTECTION WHERE

More information

LADDERS FIXED AND PORTABLE

LADDERS FIXED AND PORTABLE CONTRACTOR WHS HAZARD STANDARD LADDERS FIXED AND PORTABLE EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition

More information

SYDNEY TRAMWAY MUSEUM WORKING ON ELEVATED PLATFORMS PROCEDURE

SYDNEY TRAMWAY MUSEUM WORKING ON ELEVATED PLATFORMS PROCEDURE WORKING ON ELEVATED PLATFORMS PROCEDURE DECEMBER 2008JANUARY 2014 1. Document Details: SYDNEY TRAMWAY MUSEUM Document Control Record Name: Working On Elevated Platforms Procedure Number STM 6161 Version

More information

SWMS No 012 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6

SWMS No 012 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6 Samark North Qld Pty Ltd SWMS SWMS No 0 Samark North Qld Pty Ltd ABN : 99 08 98 87 Electrical Contractors License C37 Page of 6 Safe Work Method Statement Title: SWMS:0 INSTALLING LIGHT POLES Work Method

More information

CONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA

CONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA RECOMMENDED ADDITIONAL CONTROLS TASK / ACTIVITY/ EQUIPMENT/ FACILITY HAZARDS UNWANTED EVENT MINIMUM CONTROLS REQUIRED RISK NO. LIKELI-HOOD CONSE-QUENCE RISK VALUE Project Risk Assessment Page 1 of 16 All

More information

Working at Height. Policy and Procedures. Author: Beth Webster Assistant Safety Advisor. On behalf of School Safety Committee.

Working at Height. Policy and Procedures. Author: Beth Webster Assistant Safety Advisor. On behalf of School Safety Committee. Working at Height Policy and Procedures Author: Beth Webster Assistant Safety Advisor Authorised by: Issued by: John Stephenson Safety Office On behalf of School Safety Committee Review Date: NO LATER

More information

Prevention of Falls and Working at Heights

Prevention of Falls and Working at Heights Workplace Safety Schools Cleaning Prevention of Falls and Working at Heights It is the policy of the Company to avoid working at heights above 2 metres wherever practical. When avoidance is not an option,

More information

SASOL LIFE SAVING RULES (LSRs)

SASOL LIFE SAVING RULES (LSRs) SASOL LIFE SAVING RULES (LSRs) Zero harm by following Life Saving Rules Adhere to fall protection requirements at all times when WORKING AT HEIGHTS Obey all traffic rules while driving and walking for

More information

Safe Work Method Statement

Safe Work Method Statement TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Dogging of Crane General Loading and Unloading SWMS No. 20 Authorized

More information

Confined Spaces. This procedure applies to all workers of the Diocese of Maitland Newcastle (DoMN).

Confined Spaces. This procedure applies to all workers of the Diocese of Maitland Newcastle (DoMN). Purpose To provide guidance in controlling the risks associated with confined spaces including identifying confined spaces, working in a confined space and issuing confined space entry permits. Scope This

More information

You must NOT touch any equipment unless you are authorised to work on or with that equipment and you have followed correct safety procedures.

You must NOT touch any equipment unless you are authorised to work on or with that equipment and you have followed correct safety procedures. SYDNEY TOWN HALL 1 HIRER & CONTRACTOR SAFETY FACT SHEET Issue 2 September 2013 www.sydneytownhall.com.au City of Sydney - Venue Management will provide and maintain a safe working environment for the health,

More information

8. Fall Protection Procedures WAC

8. Fall Protection Procedures WAC 1.0 Fall Protection Introduction 8. Fall Protection Procedures WAC 296-155-245 If an employee is exposed to a fall hazard of ten (10) feet or more in height, the employee must use a fall restraint, fall

More information

Conducting An Effective. Welcome!

Conducting An Effective. Welcome! Conducting An Effective An introduction to the Five Step Process of Job Hazard Analysis JHA-JSA-SWMS-AHA Introductions Welcome! What do you know about Job Hazard Analysis (JHA s)? Does OSHA require JHA

More information

Safety Risk Assessment Working at Height: Mobile Tower Scaffold

Safety Risk Assessment Working at Height: Mobile Tower Scaffold Persons at (Groups) Assessor Appointment Tel. No. Description of Task or Activity A One Direct employees Mark Bloxidge H&S Manager 0208 821 5197 Working at height from Mobile Tower B Contractors/Sub contractors

More information

FALL PROTECTION (SAF-SPI-06)

FALL PROTECTION (SAF-SPI-06) 1. PURPOSE To describe the Ontario Operations standard methods for preventing serious injury resulting from fall from heights and to provide a Standard for Fall Protection to safeguard employees who work

More information

Safety Checklist for Events Held at Hillbrook

Safety Checklist for Events Held at Hillbrook Safety Checklist for Events Held at Hillbrook Hazards/ Issues or Tasks 1. EVENT ACCESS AND EGRESS Entry / Exit areas are kept clear and accessible. For an evening event, that you have appropriate Lighting.

More information

WORKING AT HEIGHTS CS-PTW-HAZ-02

WORKING AT HEIGHTS CS-PTW-HAZ-02 CS ENERGY PROCEDURE FOR WORKING AT HEIGHTS CS-PTW-HAZ-02 Responsible Officer: Corporate PTW Administrator Responsible Executive: Chief Executive Officer (CEO) DOCUMENT HISTORY Key Changes Prepared By Checked

More information

QUEENSLAND UNIVERSITY OF TECHNOLOGY

QUEENSLAND UNIVERSITY OF TECHNOLOGY QUEENSLAND UNIVERSITY OF TECHNOLOGY SITE SPECIFIC SAFETY MANAGEMENT PLAN FOR SAMFORD HOUSE SAMFORD ECOLOGICAL RESEARCH FACILITY SAMFORD VALLEY 2007 Dylan Randall SN: 06305466 dylan.randall@student.qut.edu.au

More information

Safe Work Method Statement

Safe Work Method Statement TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Use of a Mobile Elevated Work Platform (MEWP) Boom SWMS No. 19 Authorized

More information

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS Project: (insert Client) Replacement/ Repair of high level light units/ high

More information

RISK INFORMATION SCHOOLS SCHOOL GROUNDS MAINTENANCE

RISK INFORMATION SCHOOLS SCHOOL GROUNDS MAINTENANCE The Risk Information contained in this paper is intended to assist schools in establishing safe procedures for maintaining school grounds. Schools owe a duty of care to employees and students to keep them

More information

Job Safety and Environmental Analysis (JSEA)/Safe Work Method Statement (SWMS)

Job Safety and Environmental Analysis (JSEA)/Safe Work Method Statement (SWMS) Job Safety and Environmental Analysis (JSEA)/Safe Work Method Statement (SWMS) Part 1: Project and Task Identification Process: Initiators of JSEAs are responsible for consulting the Project Supervisor,

More information

Safe Work Method Statement (SWMS)

Safe Work Method Statement (SWMS) Safe Work Method Statement (SWMS) Work Activity/Description: Site Name: Date: Site Address: Name Position Signature Document No: Prepared By: OHS Manager Revision: Reviewed By: National Program Manager

More information

Potential risk of injury to staff

Potential risk of injury to staff Register Fire, Earthquake - other Emergencies Manual Handling and Repetitive Work Repetitive, Forceful Work Poor Housekeeping Not Wearing PPE (Personal Protective Equipment) Potential risk of injury to

More information

B S Glass Ltd Safety procedures- outsourced Workplaces

B S Glass Ltd Safety procedures- outsourced Workplaces B S Glass Ltd Jan 17 B S Glass Ltd Safety procedures- outsourced Workplaces Index - - - - - - - - Page No On Site safety - - - - - - - - - - - - - - - - - - - Content 3. 1.00 Health and Safety Mission

More information

1 AIM 2 4 REASONS FOR INCLUSION 3 6 PLANT AND EQUIPMENT REQUIREMENTS 4 7 SYSTEM AND PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6

1 AIM 2 4 REASONS FOR INCLUSION 3 6 PLANT AND EQUIPMENT REQUIREMENTS 4 7 SYSTEM AND PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6 CONTENTS PAGE 1 AIM 2 2 APPLICATION 2 3 DEFINITIONS 2 4 REASONS FOR INCLUSION 3 5 REQUIREMENTS 3 6 PLANT AND EQUIPMENT REQUIREMENTS 4 7 SYSTEM AND PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6 APPENDIX

More information

Contractor Hazard Identification and Control Guide

Contractor Hazard Identification and Control Guide Exposure to Asbestos Containing Materials (ACM) Accidental disturbance or removal of ACM. Asbestos Containing Materials are to be removed outside school hours. No DET employees, students or visitors are

More information

The purpose of this training is to give field technicians awareness training and guidelines on potential hazards they may encounter in the field.

The purpose of this training is to give field technicians awareness training and guidelines on potential hazards they may encounter in the field. Purpose The purpose of this training is to give field technicians awareness training and guidelines on potential hazards they may encounter in the field. Fall Protection and Prevention JELD-WEN Field Employees

More information

SAFE WORK METHOD STATEMENT 0003 (Perimeter and Balcony Fallguard) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities)

SAFE WORK METHOD STATEMENT 0003 (Perimeter and Balcony Fallguard) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities) Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0003 (Perimeter and Balcony Fallguard) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities) Additional Information

More information

EXHIBITION Guide. Roles and Responsibilities OS11. A handbook for exhibitors and contractors

EXHIBITION Guide. Roles and Responsibilities OS11. A handbook for exhibitors and contractors Appendix 1 Health & Safety Declaration, Roles and Responsibilities Each exhibitor and Informa appointed contractor must complete the Health and Safety Declaration form provided below to confirm they have

More information

CHAPTER 10 FALL PROTECTION

CHAPTER 10 FALL PROTECTION CHAPTER 10 FALL PROTECTION A. INTRODUCTION... 1 B. CHAPTER-SPECIFIC ROLES and RESPONSIBILITIES... 2 C. HAZARD IDENTIFICATION... 3 1. Job Hazard Analysis (Jha).... 3 2. Fall Hazards... 3 D. HAZARD CONTROL...

More information

Temporary load-bearing support for structural alterations or repairs

Temporary load-bearing support for structural alterations or repairs CRITICAL NOTE This document only becomes a Safe Work Method Statement where the High Risk Construction Work section of this document is completed Company: ABN: Contact Person: Ph: Project/Site: Principal

More information

DREW UNIVERSITY FALL PROTECTION PROCEDURE (DRAFT 12/11)

DREW UNIVERSITY FALL PROTECTION PROCEDURE (DRAFT 12/11) PURPOSE The objective of this policy & guideline is to eliminate the potential for injuries and fatalities to employees and contractors resulting from falls from elevated work areas at Drew University

More information

BASIC HEALTH AND SAFETY MEASURES TO BE TAKEN INTO CONSIDERATION FOR STAND CONSTRUCTION AT MOBILE WORLD CONGRESS rev01

BASIC HEALTH AND SAFETY MEASURES TO BE TAKEN INTO CONSIDERATION FOR STAND CONSTRUCTION AT MOBILE WORLD CONGRESS rev01 BASIC HEALTH AND SAFETY MEASURES TO BE TAKEN INTO CONSIDERATION FOR STAND CONSTRUCTION AT MOBILE WORLD CONGRESS 2017 IMPORTANT! DURING BUILD-UP AND DISMANTLING ACCESS TO THE VENUE WILL ONLY BE GRANTED

More information

University College Dublin Machinery/Equipment Risk Assessment Template

University College Dublin Machinery/Equipment Risk Assessment Template 1. General Information Name of Person(s) carrying out assessment and their position Principal Investigator / Supervisor / Head of School or Unit (Person responsible for ensuring safety) Date of assessment

More information

EHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010)

EHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010) (Ref. SOP QMS-080; EHS-010) Form-445 Inspected by: Date of inspection Date of Report Report # Pages Area Manager: Area Inspected: General This EHS Workplace Inspection was conducted by: Scope of the Inspection:

More information

[Sample] Corporation. Fleet Management Fall Prevention Program

[Sample] Corporation. Fleet Management Fall Prevention Program February 6, 2014 Background: Purpose: [Sample] Corporation Fleet Management Fall Prevention Program Unit Positioning Worker Restraint System Personal Fall Arrest System (PFAS) Fleet Auto/Hydraulic Technicians

More information

Work Activity (e.g. Road Work): Work Location:.

Work Activity (e.g. Road Work): Work Location:. Working with Cranes Work Activity (e.g. Road Work): Work Location:. GENERAL INFORMATION Hinchinbrook Shire Council Lannercost Street Ingham Qld, 4850 ABN 46 291 971 168 Ph: 47764610 All personnel conducting

More information

IMMANUEL CHURCH, CHICHESTER HEALTH AND SAFETY POLICY

IMMANUEL CHURCH, CHICHESTER HEALTH AND SAFETY POLICY IMMANUEL CHURCH, CHICHESTER HEALTH AND SAFETY POLICY Approved by the Trustees: November 2016 Health and Safety Policy Introduction The main piece of health and safety legislation is the Health and Safety

More information

Risk Assessment Form (Qualitative)

Risk Assessment Form (Qualitative) Assessment Form (Qualitative) Project / ocation:..d.a.s WATERS Contract No: RA & Issue No: 008 Prepared by:.r.smit Date: 10/10/16 Signature: ACTIVITY DESCRIPTION: Person (s) at risk: General Ground works

More information

SCOUTS AUSTRALIA NSW

SCOUTS AUSTRALIA NSW SCOUTS AUSTRALIA NSW Contractor Health and Safety Handbook 2 Scouts Australia NSW Contractor Safety Handbook v 5.0 Frebruary 2018 Contents... 2 Contractor Health and Safety Handbook... 2 Revisions... 2

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT LOADING AND UNLOADING VEHICLES Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES

More information

Working at Height. A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use.

Working at Height. A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use. A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use. Title: Number: WORKING AT HEIGHT CSBP-GM-11-031-02 Version Number: 24.0.0 Date Revised: 10 September

More information

Safe Work Method Statement

Safe Work Method Statement Title Skid Steer Operation (Bobcat) SWMS No. 14 Authorized and email Signed by the (Managing Director / CEO / Partner / Proprietor) on Date 01/08 /2016 Safe Work Procedure for the Work:- Yes No Employees

More information

SWMS No 007 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6

SWMS No 007 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6 Samark North Qld Pty Ltd SWMS Manual SWMS No 007 Samark North Qld Pty Ltd ABN : 99 082 958 487 Electrical Contractors License C37121 Page 2 of 6 Safe Work Method Statement Title: SWMS:007 WORKING ON ENERGISED

More information

Safety at Work. Rules for Staying Alive

Safety at Work. Rules for Staying Alive Safety at Work Rules for Staying Alive Safety at Work Rules for Staying Alive Introduction The purpose of Dana Gas Rules For Staying Alive is to address the key causes of deaths in our industry. These

More information

PRO Working at Height

PRO Working at Height MS&L Procedure PRO-4.5-0001-1-05 Working at Height Version: 3 Authorised by: Tom Angliss & Owen Quake Authorisation Date: 21/11/2017 This document has been approved for release and changed as per the associated

More information

UNCONTROLLED IF PRINTED. Issued with the authority of the Chief Commissioner and General Manager of Scouts Australia NSW

UNCONTROLLED IF PRINTED. Issued with the authority of the Chief Commissioner and General Manager of Scouts Australia NSW PROCEDURE Plant and equipment safety Issued with the authority of the Chief Commissioner and General Manager of Chief Commissioner signature Chief Executive Officer signature Sponsor Head of Risk Document

More information

ACCREDITED SAFETY TRAINING FOR EQUIPMENT OPERATORS

ACCREDITED SAFETY TRAINING FOR EQUIPMENT OPERATORS JOB HAZARD ANALYSIS ELEVATING WORK PLATFORM Note: This is just a guideline. A Assessment must be designed for each specific EWP and each specific work area and task. A JHA is a never ending document. There

More information

CONSTRUCTSAFE TIER 1 HEALTH AND SAFETY COMPETENCY TEST FRAMEWORK

CONSTRUCTSAFE TIER 1 HEALTH AND SAFETY COMPETENCY TEST FRAMEWORK CONSTRUCTSAFE TIER 1 HEALTH AND SAFETY COMPETENCY TEST FRAMEWORK ConstructSafe Project Team March 2018 Version 1.3 1 Table of Contents 1. Introduction... 3 2. Candidate minimum required knowledge... 3

More information

Work At Height Health & Safety Management Standard Issue 3 (April 2011)

Work At Height Health & Safety Management Standard Issue 3 (April 2011) Work At Height Health & Safety Management Standard Issue 3 (April 2011) Introduction This document contains corporate standards and guidance on the management of risks arising from work at height. It is

More information

PRO Working at Height

PRO Working at Height MS&L Procedure PRO-4.5-0001-1-05 Working at Height Document Owner: Bill Kruesi HSSE Manager - Asset Mgmt. Approved By: Prepared By: Document Status: Version Number: 4 Owen Quake Bill Kruesi Adrian Connolly

More information

Ormiston Academies Trust. Ormiston Horizon Academy. Working at Height Policy October 2016

Ormiston Academies Trust. Ormiston Horizon Academy. Working at Height Policy October 2016 Ormiston Academies Trust Ormiston Horizon Academy Working at Height Policy Project/job number: Author: Sharlene Smith/Handsam Date: 25/10/16 Contributors: Sharlene Smith Version number: 1.1 Reviewed by:

More information

CONSTRUCTION SAFETY PROGRAM FOR. Golder Acoustics Inc.

CONSTRUCTION SAFETY PROGRAM FOR. Golder Acoustics Inc. CONSTRUCTION SAFETY PROGRAM FOR Golder Acoustics Inc. TABLE OF CONTENTS Topic... Page Safety and Health Policy... 2 Safety and Health Objectives... 3 Job Site Inspections... 4 Contractor Safety Administrator...

More information

Leicester City Council Health & Safety Risk Assessment Form Ref:

Leicester City Council Health & Safety Risk Assessment Form Ref: Division/Section: Bridges Team Work Activity: Structural Repairs Activity Location: 8 Minehead Street, Leicester Persons Affected: Manager: Date of Assessment: Property Occupiers and Site Operatives Abul

More information

PRO Lifting Operations

PRO Lifting Operations MS&L Procedure PRO-4.5-0001-1-06 Lifting Operations Document Owner: Bill Kruesi HSSE Manager - Asset Mgmt. Owen Quake ANZ Engineering Authority Approved By: Bill Kruesi HSSE Manager - Asset Mgmt. Control

More information

FALL PREVENTION PROCEDURE

FALL PREVENTION PROCEDURE TABLE OF CONTENTS 1. OBJECTIVE... 3 2. SCOPE... 3 3. DEFINITIONS... 3 4. RESPONSIBILITIES... 4 5. HAZARD AND RISK ASSESSMENT... 4 5.1 WORKING AT HEIGHT PERMIT... 4 5.1.1 Permit Currency... 5 5.1.2 Working

More information

COMPANY HEALTH & SAFETY POLICY

COMPANY HEALTH & SAFETY POLICY COMPANY HEALTH & SAFETY POLICY 1 STATEMENT OF GENERAL POLICY The Organisation accepts the obligations placed upon it by the various Acts of Parliament covering health, safety and welfare including: Deposit

More information

Fall Protection at the Top of the Quarry Face

Fall Protection at the Top of the Quarry Face Fall Protection at the Top of the Quarry Face November 2017 Regulation 9 of the Safety, Health and Welfare at Work (Quarries) Regulations 2008 requires the Operator to ensure, as regards that quarry, that

More information

Wheeler Cranes 6 McIntyre Rd Tomago NSW 2324

Wheeler Cranes 6 McIntyre Rd Tomago NSW 2324 Wheeler Cranes 6 McIntyre Rd Tomago NSW 2324 ABN: 34 088 229 190 This SWMS has been developed and authorised by: Name Albie Wheeler Position Managing Director Date 1/7/12 Signature Phone 0249649991 Mobile

More information

1. Objective of the initiative To ensure that all employees and subcontractors are aware of the risks associated with working at height.

1. Objective of the initiative To ensure that all employees and subcontractors are aware of the risks associated with working at height. Safety Initiative 02 Working at Height May 2011 CONTENTS 1. Objective of the initiative 2. Overview. 3. Implementation 4. Duties 5. Hierarchy of Controls 6. Workplace Inspections 7. Fragile Surfaces 8.

More information

Field Instruction. The purpose of this instruction is to inform all Horizon Power workers of the safety requirements when working from a EWP.

Field Instruction. The purpose of this instruction is to inform all Horizon Power workers of the safety requirements when working from a EWP. 2.7 Safety Requirements When Working from an EWP Purpose The purpose of this instruction is to inform all Horizon Power workers of the safety requirements when working from a EWP. Scope The scope of this

More information

Critical Risk Control Protocol

Critical Risk Control Protocol Critical Risk Control Protocol Contents Foreword 3 Introduction 4 Critical Controls 4 Exemption Process 4 UGL s Critical Risks 5 Working at Height 6 Operation of Mobile Plant 7 Working in Confined Spaces

More information

Pre-control risk estimate. Likelihood Risk

Pre-control risk estimate. Likelihood Risk Activity Consequence s mitigation measures Site Access & Egress Slips, trips & falls al injury by falling. Sprains & broken bones. Site operatives 3 4 12 Ensure access to site is kept clear of plant &

More information

WHS CONTRACTOR INFORMATION PACKAGE

WHS CONTRACTOR INFORMATION PACKAGE WHS CONTRACTOR INFORMATION PACKAGE Introduction This information package provides Informa exhibitors and contractors with important information that will be required to plan and manage work on all stages

More information

SWMS documented by: Feb Bo Ceprnja Date Feb Feb Feb 2018

SWMS documented by: Feb Bo Ceprnja Date Feb Feb Feb 2018 Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0002 (Void Platform Stairs) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities & SWMS 0002 Void Platform) Additional

More information

1. What is the top priority when working on Canadian Pacific (CP) property? 2. When working on CP property what must all Contractors comply with?

1. What is the top priority when working on Canadian Pacific (CP) property? 2. When working on CP property what must all Contractors comply with? 1. What is the top priority when working on Canadian Pacific (CP) property? A. Production B. Safety C. Quality D. Project deadline 2. When working on CP property what must all Contractors comply with?

More information

Health & Safety Policy HSP 13 Working at Height Version Status Date Title of Reviewer Purpose/Outcome

Health & Safety Policy HSP 13 Working at Height Version Status Date Title of Reviewer Purpose/Outcome Health & Safety Policy HSP 13 Working at Height Version Status Date Title of Reviewer Purpose/Outcome 1.0 Draft 07.03.2016 David Maine 1 st Draft for consultation/review 1.1 Approved 10.01.2017 David Maine

More information

Company Health & Safety Policy

Company Health & Safety Policy Westoaks Builders Ltd Reviewed 12th Jan 2015 HS27: Company Health & Safety Policy 1 Company Health & Safety Policy Statement of General Policy The Organisation accepts the obligations placed upon it by

More information

Overview. Identify fall hazardous areas Describing potential fall hazards How appropriate portable and extension ladders are used

Overview. Identify fall hazardous areas Describing potential fall hazards How appropriate portable and extension ladders are used FALL PROTECTION Overview Identify fall hazardous areas Describing potential fall hazards How appropriate portable and extension ladders are used Fall Protection All situations that expose personnel to

More information

SUMBSE01 - SQA Code HC85 04 Apply health and safety and environmental legislation in the building services engineering sector

SUMBSE01 - SQA Code HC85 04 Apply health and safety and environmental legislation in the building services engineering sector Overview This standard is about establishing and maintaining working practices and procedures across a specified range of installation and/or maintenance activities that give consideration to health and

More information

Working at Heights PROCEDURE

Working at Heights PROCEDURE Working at Heights PROCEDURE Contents 1.0 Purpose 2.0 Objective 3.0 Scope and limitation 4.0 References and sources of information 5.0 Responsibilities 5.1 University Managers 5.2 University Staff Overseeing

More information

Fall Protection Program

Fall Protection Program Fall Protection Program 1.0 Purpose To provide guidance for the establishment of a Fall Protection Program for the Washington State Department of Transportation (WSDOT) operations and facilities as required

More information

Health & Safety Contractor rules

Health & Safety Contractor rules Health & Safety Contractor rules Contents 1. Introduction... 1 2. The legal bit explaining our terminology... 1 2.1 Legal requirements... 1 3. Our health and safety requirements... 1 3.1 Access to BT premises...

More information

Fall Prevention Program

Fall Prevention Program Fall Prevention Program [SAMPLE] CORPORATION FLEET AUTO HYDRAULIC MECHANICS/TECHNICIANS O C TO B E R 2 1, 2 0 1 4 Golden Rule The golden rule of [corporation s] fall prevention program is unit positioning

More information

SITE SAFETY PLAN AND NEW EMPLOYEE SAFETY ORIENTATION LOCATION: BROWN-MINNEAPOLIS TANK-SOUTHWEST (ALBUQUERQUE FABRICATION PLANT) REVISED:

SITE SAFETY PLAN AND NEW EMPLOYEE SAFETY ORIENTATION LOCATION: BROWN-MINNEAPOLIS TANK-SOUTHWEST (ALBUQUERQUE FABRICATION PLANT) REVISED: SITE SAFETY PLAN AND NEW EMPLOYEE SAFETY ORIENTATION LOCATION: BROWN-MINNEAPOLIS TANK-SOUTHWEST (ALBUQUERQUE FABRICATION PLANT) REVISED: 09-11-2009 The following summarizes the orientation requirements

More information

Work At Heights Toolkit. for Supervisors

Work At Heights Toolkit. for Supervisors Work At Heights Toolkit for Supervisors For Supervisors How to use this toolkit? The toolkit aims to provide information for supervisor to communicate one topic a day to workers. Pictures are for illustration

More information

OSHA s new walking working surfaces standards

OSHA s new walking working surfaces standards OSHA s new walking working surfaces standards changes and new requirements Inspection of walking working surfaces 1910.22(d) Regularly and as needed and correct, repair, or guard against hazardous conditions;

More information

Fall Protection: How to Protect Your Workers. Sponsored by

Fall Protection: How to Protect Your Workers. Sponsored by Fall Protection: How to Protect Your Workers Sponsored by Failure to plan is planning to fall. A Little Background Who is? Why do they exist? How do they come up with the standards? Are the standards enforceable?

More information

Contractors' Code of Safe Practice

Contractors' Code of Safe Practice Contractors' Code of Safe Practice Introduction As the controller of premises, The University of Hong Kong has a duty to ensure, so far as is reasonably practicable, the health and safety of all its employees,

More information

Telco Antennas SWMS Working At Height Above 2m

Telco Antennas SWMS Working At Height Above 2m Telco Antennas SWMS Working At Height Above 2m A SWMS shall be developed for a task where the risk has been assessed as Medium or Higher Division: Date: SWMS No: (e.g. Installation, Engineering Workshop)

More information

LEVEL 2 CERTIFICATE OF COMPETENCE IN THE SAFE USE AND OPERATION OF MOBILE ELEVATED WORK PLATFORMS

LEVEL 2 CERTIFICATE OF COMPETENCE IN THE SAFE USE AND OPERATION OF MOBILE ELEVATED WORK PLATFORMS NPTC Registered Charity No. 1096429 NATIONAL AGRICULTURAL CENTRE STONELEIGH PARK, WARWICKSHIRE CV8 2LG Tel: 024 7669 6553 Fax: 024 7669 6128 Email: information@nptc.org.uk LEVEL 2 CERTIFICATE OF COMPETENCE

More information

Appendix 4C - Sample SWMS Trenching

Appendix 4C - Sample SWMS Trenching Appendix 4C - Sample SWMS Trenching SAFE WORK METHOD STATEMENT SWMS Reference : Insert document number : Version A Date : Workplace / Project : Company Address: Work Activity / Job / Task or Process :

More information

Once the job has been planned and the site has been inspected according to WHS and site requirements it is important to follow work procedure and

Once the job has been planned and the site has been inspected according to WHS and site requirements it is important to follow work procedure and Once the job has been planned and the site has been inspected according to WHS and site requirements it is important to follow work procedure and instructions in the implementation of safe work at heights.

More information

Bogo Operations Pollution Incident Response Management Plan

Bogo Operations Pollution Incident Response Management Plan Bogo Operations Pollution Incident Response Management Plan Rhyolite Hard Rock Aggregate Quarry 134 Paynes Road BOOKHAM NSW 2582 PO Box 426 COWRA NSW 2794 p: 02 6227 7260 p: 02 6345 4253 e: info@bogoquarry.com.au

More information

TENDERER OCCUPATIONAL HEALTH AND SAFETY (OHS) MANAGEMENT SYSTEM QUESTIONNAIRE

TENDERER OCCUPATIONAL HEALTH AND SAFETY (OHS) MANAGEMENT SYSTEM QUESTIONNAIRE TENDERER OCCUPATIONAL HEALTH AND SAFETY (OHS) MANAGEMENT SYSTEM QUESTIONNAIRE This questionnaire forms part of the SANBI tender evaluation process and is to be completed by tenderers and submitted with

More information

WHS-12 Working at Heights Procedure

WHS-12 Working at Heights Procedure Table of Contents Table of Contents... 1 1 Purpose... 3 2 Scope... 3 3 References... 3 4 Roles and Responsibilities... 4 5 Definitions... 4 6 Records... 6 7 Attachments... 7 8 General Requirements... 7

More information

At the end of this presentation you should know the difference between fall prevention, fall restraint, and fall arrest.

At the end of this presentation you should know the difference between fall prevention, fall restraint, and fall arrest. 0 At the end of this presentation you should know the difference between fall prevention, fall restraint, and fall arrest. We will review the hazards associated with fall protection and how to mitigate

More information

THICKNESSER RISK ASSESSMENT (U003ra)

THICKNESSER RISK ASSESSMENT (U003ra) Task Being Carried Out: Area: Persons at Risk: Operation of T500 Thicknesser Brindle Mill Operatives, Maintenance engineers Description of Equipment: Wadkin T500 Thicknesser Serial No.: T500 82240 (Machine

More information

CONTRACTOR WHS HAZARD STANDARD CONFINED SPACE EXTERNAL USE ONLY

CONTRACTOR WHS HAZARD STANDARD CONFINED SPACE EXTERNAL USE ONLY CONTRACTOR WHS HAZARD STANDARD CONFINED SPACE EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition WHS

More information

MSA Fall Protection Kits

MSA Fall Protection Kits MSA Fall Protection Kits Scaffolding application Falls from height continue to be the largest single cause of fatal and life changing injuries for workers across industry. Scaffolders, when erecting, altering

More information

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS Project: Insert Client Repair/ Replacement of low level light units/ low level

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT EXCAVATION OR TRENCHING Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES

More information