Pipeline Integrity Valve Spacing Engineering Assessment (CDN) Grande Prairie Mainline Loop 2 (Progress Section) NPS 36

Size: px
Start display at page:

Download "Pipeline Integrity Valve Spacing Engineering Assessment (CDN) Grande Prairie Mainline Loop 2 (Progress Section) NPS 36"

Transcription

1 APPROVALS Library: EDMS General Page 1 of 10

2 TABLE OF CONTENTS APPROVALS 1 1. PURPOSE BACKGROUND VALVE SPACING ASSESSMENT APPROACH OPERATIONS AND MAINTENANCE CONSIDERATIONS... 6 a. The nature and amount of fluid released due to a blowdown or a failure... 6 b. The time to blowdown the isolated section... 7 c. The effects on the inhabitants of the area from gas release... 7 d. Continuity of service... 7 e. Operating and maintenance flexibility... 7 f. Future development within the valve spacing section... 7 g. Significant conditions that could adversely affect the operation and security of the pipeline... 8 Proposed Actions EFFECT ON THE PUBLIC SAFETY... 8 Proposed Actions CONCLUSIONS RESPONSE PLAN REFERENCES Regulations, Codes and Standards TransCanada Procedures and References Industry Papers and Publications Library: EDMS General Page 2 of 10

3 1. PURPOSE TransCanada PipeLines Limited (TransCanada) on behalf of NOVA Gas Transmission Ltd. (NGTL) provides the Engineering Assessment (EA) for the valve spacing on the Grande Prairie Mainline Loop 2 (Progress Section) NPS 36. A Class 2 site located between the two mainline block valves NW10-0-1SV2- GPM (NW10) and GPM143-2-BV (GPM143) requires the valve spacing to be a maximum of 25 km with an adjustment factor of 25%, as per Canadian Standards Association (CSA) Z Clause in absence of an EA. In accordance with CSA Z Clause 4.4.4, this EA demonstrates that the existing mainline block valve spacing, of approximately 31.7 km, is adequately safe with the recommendations made in this EA. 2. BACKGROUND A class location change site was identified on the Grande Prairie Mainline Loop 2 (Progress Section) NPS 36 between mainline block valves NW10 and GPM143, as outlined in Table 2.1, below. Due to the class location change, the requirement for valve spacing has also changed, according to CSA Z Clause and Table 4.7. The existing spacing between mainline block valves NW10 and GPM143 is approximately 31.7 km, while the required valve spacing for a Class 2 location is 25 km in absence of an EA. Figure 2.1 shows the valve section under consideration, with the mainline block, side, and crossover valves and the Class 2 location section of the pipeline labeled. The relevant crossover and side valves within the valve section are described along with the mainline block valves in Table 2.2 below. Figure 2.2 and Figure 2.3 shows a schematic of the side valve and crossover valve, respectively. Table 2.1: Pipeline Section with Change in Class Location Designation and Valve Section Details Line Name Grande Prairie Mainline Loop 2 (Progress Section) NPS 36 Outer Diameter (NPS) MOP (kpa) Valve Section NW10 to GPM143 Class Location Change Section 6734 m to 8170 m Class Location Change Section Length (m) 1436 Change in Class Location Designation Class 1 to Class 2 Existing Valve Spacing (km) 31.7 Table 2.2: Mainline block, Crossover, and Side Valves in the Valve Section Valve Name Valve Function Valve Type Valve Mechanism Emergency Shutdown Mechanism Available NW10 Mainline block Ball Automatic Yes GPM143 Mainline block Ball Automatic Yes POG10-0-1SV2-GPM (POG10) Side Ball Manual No GPM143-1-U2 Crossover Ball Automatic Yes Library: EDMS General Page 3 of 10

4 Figure 2.1: Location of Valves and the Class 2 Location Site on the Grande Prairie Mainline Loop 2 (Progress Section) NPS 36 Library: EDMS General Page 4 of 10

5 Figure 2.2: Schematic of the Side Valve POG10-0-1SV2-GPM Figure 2.3: Schematic of the Crossover Valve GPM143-1-U2 Library: EDMS General Page 5 of 10

6 3. VALVE SPACING ASSESSMENT APPROACH CSA Z Clause 4.4 describes the requirements for valve location and spacing. This valve spacing EA for the pipeline will be carried out in accordance with CSA Z Clause 4.4.4, which outlines the following factors to be considered to determine the proper valve spacing: a. The nature and amount of fluid released due to a blowdown or a failure; b. The time to blowdown the isolated section; c. The effects on the inhabitants of the area from gas release; d. Continuity of service; e. Operating and maintenance flexibility; f. Future development within the valve spacing section; g. Significant conditions that could adversely affect the operation and security of the pipeline. In addition to these operations and maintenance considerations, it is also necessary to consider the effect of increased valve spacing on public safety. The two risk measures used by TransCanada to evaluate public safety are Individual Risk (IR) and Societal Risk (SR). IR is the annual probability of a fatality to an individual located on top of the pipeline. It is a risk assessment performed for every pipeline. SR is the annual risk to a group of structures, or a settlement, due to its proximity to the pipeline. Combined, IR and SR will capture the acceptability of risk from a safety perspective for both sparsely and densely populated areas. Both of these risk measures are then compared to the industry accepted risk criteria to determine the acceptability of risk. In the following sections, the above-mentioned considerations will be addressed for the Grande Prairie Mainline Loop 2 (Progress Section) NPS 36 between mainline block valves NW10 and GPM OPERATIONS AND MAINTENANCE CONSIDERATIONS a. The nature and amount of fluid released due to a blowdown or a failure The service fluid in the pipeline is sweet natural gas. If a blowdown is required for planned maintenance activities, a transfer compressor will be utilized to draw the valve section down to 1000 kpa. The remaining gas would then be vented to the atmosphere. At this pressure, the volume of gas vented would be as follows for the existing valve spacing and the CSA Z required valve spacing: 31.7 km valve spacing: m km valve spacing: m 3 In the event of an emergency blowdown, such as an emergency repair, the volume of the gas released from the line would be dependent on the pressure in the line. At maximum operating pressure (MOP), the volume of gas vented for the two compared valve spacing distances, assuming that the mainline block valves have closed, would be: 31.7 km valve spacing: m km valve spacing: m 3 Library: EDMS General Page 6 of 10

7 b. The time to blowdown the isolated section For both the existing valve spacing of approximately 31.7 km and the required Class 2 location valve spacing of 25 km, the blowdown times would be less than 8 hours. It should be noted that this applies to both blowdowns with and without silencers. The implication of the blowdown time being less than 8 hours is that the blowdown could be performed during the normal working hours. c. The effects on the inhabitants of the area from gas release According to the TransCanada Operating Procedure (TOP) Pipeline Operations (Gas Handling), local landowners and relevant government agencies will be advised at least 48 hours prior to any planned blowdown operation. A silencer would be installed (if planned maintenance is to occur) at NW10 or GPM143 if there were residents within 750 m of either valve site. There are no residents located within 750 m of either NW10 or GPM143. d. Continuity of service In the case of either planned or unplanned maintenance activities between NW10 and GPM143, the valve section would need to be taken out of service temporarily. Since this pipeline has parallel pipelines, flow is able to be diverted around the valve section and service would not be interrupted for the temporary period. Furthermore, any changes to the valve spacing would not have any impact on the continuity of service for this pipeline. e. Operating and maintenance flexibility Current system design has two receipt meter stations tied to the Grande Prairie Mainline Loop 2 (Progress Section) NPS 36. However, both receipt meter stations have tie-ins to other pipelines. Therefore, the existing valve spacing has no impact on the operating or maintenance flexibility of this pipeline. f. Future development within the valve spacing section The existing valve spacing of approximately 31.7 km for the Grande Prairie Mainline Loop 2 (Progress Section) NPS 36 is not in accordance with CSA Z Clause and Table 4.7. This EA was performed to evaluate the safety impact of the existing valve spacing, as per CSA Z Clause The Class 2 location site driver is the presence of a hazardous industrial installation. It is not anticipated that any section of pipe in this valve section will undergo further class location upgrades, as there is no anticipated residential development of over 46 dwelling units in the area. It is not anticipated that further development in the area will have additional impacts on this valve section. Library: EDMS General Page 7 of 10

8 g. Significant conditions that could adversely affect the operation and security of the pipeline Conditions that may affect pipeline operation are addressed above in sections d. and e. In addition, the valves operating incorrectly would pose another significant condition that could adversely affect the operation of the pipeline for this valve section. It is thus proposed to ensure that all valves within the valve section are winterized annually according to TransCanada s valve stem winterizing procedure before the winter season each year. Proposed Actions Starting in 2017, ensure that the mainline block valves, NW10 and GPM143, the side valve POG10, and the crossover valve, GPM143-1-U2, are winterized annually according to TransCanada s valve stem winterizing procedure before the winter season each year. The proposed action is to ensure the reliability of the valves and to maintain good working condition of the existing valves. 5. EFFECT ON PUBLIC SAFETY The effects of changing the valve spacing on public safety are minimal if the valve spacing is more than 10 km, as shown in the Pipeline Research Council International (PRCI) report Valve Spacing Basis for Gas Transmission Pipelines. This is because the greatest consequence of a pipeline rupture occurs within the first 30 seconds after the failure and the subsequent ignition. This initial stage following the failure will be independent of the valve spacing, therefore making the effects on the population independent of valve spacing. The following three arguments are made by the PRCI report as to why the impact of valve spacing is minimal on the population: 1. The primary consequence of a natural gas pipeline failure is related to the effects of thermal radiation exposure of the fire ball following ignition. The hazard zone is largest immediately following ignition. Reduction of valve spacing does not diminish the size of the hazard zone immediately following ignition. 2. The jet fire that follows the initial release phase after ignition has a smaller hazard zone. This jet fire could hinder emergency personnel from entering the site so it is important to reduce the duration of a fire. A key factor in reducing jet fire duration is cutting off fuel supply by quickly closing proximate valves. Automatic shutoff valves (ASVs) and remotely controlled valves close more quickly than manual valves. The mainline block valves, NW10 and GPM143, and the crossover valve, GPM U2, are ASVs. The side valve, POG10, is a manual valve. Thus, it is recommended to install an ASV at POG10 by the end of 2017 to ensure quicker valve closure in the event of an emergency. 3. According to the PRCI study: as the valve closure time increases beyond 7.5 minutes (10 minutes is the practical minimum valve closure time), the risk level is independent of valve spacing and thus valve spacing does not affect the risk to the public. Changing the valve spacing, therefore, will not affect the risk in this case. In the IR and SR calculation, the consequence of pipeline failure is determined based on the hazard zone, which is independent of valve spacing as demonstrated above. Therefore, the reduction of valve spacing will not have any impact on IR and SR. Library: EDMS General Page 8 of 10

9 Proposed Actions An ASV should be installed at side valve POG10 by the end of 2017 to ensure quicker valve closure in the event of an emergency. Since there is no risk reduction with a decrease in valve spacing, it is proposed that the mainline block valve spacing is maintained at the existing spacing of approximately 31.7 km. 6. CONCLUSIONS A valve spacing EA was performed for the section of pipeline between mainline block valves NW10 and GPM143 of the Grande Prairie Mainline Loop 2 (Progress Section). A section of pipe within this valve section has changed from a Class 1 location to a Class 2 location, requiring a valve spacing of 25 km with an adjustment factor of 25%, as per CSA Z Clause and Table 4.7. However, CSA Z Clause allows for the completion of an EA to demonstrate that the existing valve spacing of approximately 31.7 km is safe for the surrounding population and to ensure it will not adversely affect the operation and maintenance activities on this pipeline. This EA demonstrated that: There is no increase of risk to the population due to the existing valve spacing; The reduction of valve spacing will not have any impact on IR and SR; There is no adverse impact to operation and maintenance activities on the pipeline with regard to the existing valve spacing. Recommendations to increase reliability of valves and reduction in valve closure times are recommended to enable emergency response 7. RESPONSE PLAN TransCanada has determined the appropriate approach to maintain safety for the valve section. The following actions will be implemented for the site to achieve adequate levels of safety and reliability: 1. Starting in 2017, ensure the mainline block valves, NW10 and GPM143, the side valve POG10, and the crossover valve, GPM143-1-U2, are winterized annually according to TransCanada s valve stem winterizing procedure before the winter season each year; 2. An automatic shutoff valve will be installed at POG10 by the end of 2017; 3. The valve spacing will remain at approximately 31.7 km. Library: EDMS General Page 9 of 10

10 8. REFERENCES Regulations, Codes and Standards The jurisdictional regulations and legal requirements that apply to this record are: Canadian Standards Association (CSA) Z Oil and Gas Pipeline System, Clause 4.4 TransCanada Procedures and References The TransCanada procedures, guidelines, reports and documents that apply to this report are: CDN-GAS-IMP Canadian Gas Pipeline Integrity Management Program (CDN) (EDMS No ) TED-MECH-VS-GAS Gas Valve Spacing Directive (CDN US MEX) (EDMS No ) TER-RISK-CON Thermal Radiation Consequence Models for Natural Gas Pipelines (CDN US MEX) (EDMS No ) TOP Pipeline Operations (Gas Handling) (CDN US MEX) (EDMS No ) Industry Papers and Publications The papers and publications that apply to this report are: Eiber, R. et al (2000), Valve Spacing Basis for Gas Transmission Pipelines, Pipeline Research Council International, Report no. L51817 Health and Safety Executive (HSE), Reducing Risks, Protecting People, 2001 British Standards Institute (BSI) BSI , Code of practice for pipelines Part 3: Steel pipelines on land Guide to the application of pipeline risk assessment to proposed developments in the vicinity of major accident hazard pipelines containing flammables Supplement to PD , 2009 Library: EDMS General Page 10 of 10

Item ID: Rev.: 00 Status: Final Effective Date: 29-Feb-2015 EXECUTIVE SUMMARY

Item ID: Rev.: 00 Status: Final Effective Date: 29-Feb-2015 EXECUTIVE SUMMARY EXECUTIVE SUMMARY The objective of this report is to demonstrate that sections of pipeline between MLV 401 and MLV 402 on the Canadian Mainline Line 400-2 meet the applicable requirements in CSA Z662-15

More information

Application of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines

Application of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines Communication 1737 Application of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen

More information

Responding to Natural Gas Pipeline Emergencies

Responding to Natural Gas Pipeline Emergencies Responding to Natural Gas Pipeline Emergencies Who is Florida Gas Transmission? Florida Gas Transmission operates nearly 5,000-miles of interstate natural gas transmission pipelines, a system that extends

More information

NORMAL OPERATING PROCEDURES Operating Parameter Information

NORMAL OPERATING PROCEDURES Operating Parameter Information Operating Parameter Information Each operator performing the normal operating procedures (routine checks) of the facility should be familiar with the current normal operating parameters of all systems

More information

BSR GPTC Z TR GM References and Reporting Page 1 of 8

BSR GPTC Z TR GM References and Reporting Page 1 of 8 Page 1 of 8 PRIMARY: 192.605 SECONDARY: 191.23 PURPOSE: Review guide material added by TR 2009-17 to 5.1(e) and consider restructuring the guide material under 192.605 as discussed further below. ORIGIN/RATIONALE

More information

ERCBH2S Frequently Asked Questions.

ERCBH2S Frequently Asked Questions. ERCBHS Frequently Asked Questions. Issue: Sweet pipeline tie-in to a sour gathering system A company is tying a sweet pipeline into one containing HS. Since the model assumes flow from either end of the

More information

IGEM/TD/1. Background, Development, Changes J V Haswell

IGEM/TD/1. Background, Development, Changes J V Haswell IGEM/TD/1 Background, Development, Changes J V Haswell TD/1 Background Development, Changes Technical and Safety Philosophy History of Development Key Code Requirements:- Rou?ng, BPDs Design parameters

More information

OPERATING PROCEDURES

OPERATING PROCEDURES OPERATING PROCEDURES 1.0 Purpose This element identifies Petsec s Operating Procedures for its Safety and Environmental Management System (SEMS) Program; it applies to all Petsec operations. Petsec is

More information

Risks Associated with Caissons on Ageing Offshore Facilities

Risks Associated with Caissons on Ageing Offshore Facilities Risks Associated with Caissons on Ageing Offshore Facilities D. Michael Johnson, DNV GL, Peter Joyce, BG Group, Sumeet Pabby, BG Group, Innes Lawtie, BG Group. Neil Arthur, BG Group, Paul Murray, DNV GL.

More information

IGEM/TD/2 Edition 2 with amendments July 2015 Communication 1779 Assessing the risks from high pressure Natural Gas pipelines

IGEM/TD/2 Edition 2 with amendments July 2015 Communication 1779 Assessing the risks from high pressure Natural Gas pipelines Communication 1779 Assessing the risks from high pressure Natural Gas pipelines Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen Communication 1779 Assessing the risks from high pressure Natural

More information

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011 AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF SEMS HAZARD ANALYSIS TRAINING September 29, 2011 Purpose The purpose of this meeting is to provide guidelines for determination of hazard

More information

Identification and Screening of Scenarios for LOPA. Ken First Dow Chemical Company Midland, MI

Identification and Screening of Scenarios for LOPA. Ken First Dow Chemical Company Midland, MI Identification and Screening of Scenarios for LOPA Ken First Dow Chemical Company Midland, MI 1 Layers of Protection Analysis (LOPA) LOPA is a semi-quantitative tool for analyzing and assessing risk. The

More information

REDUCING EMISSIONS WHEN TAKING COMPRESSORS OFF-LINE

REDUCING EMISSIONS WHEN TAKING COMPRESSORS OFF-LINE Lessons Learned From Natural Gas STAR Partners REDUCING EMISSIONS WHEN TAKING COMPRESSORS OFF-LINE Executive Summary Compressors are used throughout the natural gas system to move natural gas from production

More information

PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES

PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES NB16 0603 NR Task Group 1 9 16 1. One update by NR task group page 3: 7/17/19 2. Two updates to S6.1 and S6.3 on page 1: 7/19/17 SUPPLEMENT 6 PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES

More information

UTAS EH&S INSTRUCTION No. 036 June 2012 Revision No. 3. Purging of Flammable Gas Equipment and/or Piping (Explosion Hazard)

UTAS EH&S INSTRUCTION No. 036 June 2012 Revision No. 3. Purging of Flammable Gas Equipment and/or Piping (Explosion Hazard) Purging of Flammable Gas Equipment and/or Piping (Explosion Hazard) APPLICABILITY: This EH&S Instruction applies to UTAS sites worldwide, including contractors working at UTAS facilities. The document

More information

John Gurden, J P Kenny Ltd Onshore Pipeline and the Landfall Valve Installation (LVI) Design. Knowledge of the Corrib Onshore Pipeline Project

John Gurden, J P Kenny Ltd Onshore Pipeline and the Landfall Valve Installation (LVI) Design. Knowledge of the Corrib Onshore Pipeline Project STATEMENT OF EVIDENCE ABP Ref. No: PL16.GA0004 John Gurden, J P Kenny Ltd Onshore Pipeline and the Landfall Valve Installation (LVI) Design Qualifications and Experience 1. My name is John Gurden and I

More information

Lockout Tagout Policy

Lockout Tagout Policy Office of Environmental Health & Safety www.moreheadstate.edu/ehs 606-783-2584 Lockout Tagout Policy PURPOSE To establish procedures for the de-energization and isolation of energy sources or the lockout

More information

Manual Actuated Boiler Blowdown Valves

Manual Actuated Boiler Blowdown Valves Manual Actuated Boiler Blowdown Valves Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Operation 5. Maintenance 6. Spare parts p.1 1. Safety

More information

Using Consequence Modeling to Help Make Emergency Decisions

Using Consequence Modeling to Help Make Emergency Decisions Using Consequence Modeling to Help Make Emergency Decisions Della Wong / Nova Chemicals & Robert B. Gerow / SAFER-ERMC CSChE 2002 Conference October 20-23, 23, 2002 Vancouver B.C. If auto safety was like

More information

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS Annex 3, page 2 ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS The text of existing chapter 15 is replaced by the following: "1 Application This

More information

CHE Well Testing Package/Service:

CHE Well Testing Package/Service: CHE Well Testing Package/Service: CHE delivers well testing package And services, trailer mounted well testing package and offshore/onshore well testing services with over 10 years experience. Our testing

More information

Every things under control High-Integrity Pressure Protection System (HIPPS)

Every things under control High-Integrity Pressure Protection System (HIPPS) Every things under control www.adico.co info@adico.co Table Of Contents 1. Introduction... 2 2. Standards... 3 3. HIPPS vs Emergency Shut Down... 4 4. Safety Requirement Specification... 4 5. Device Integrity

More information

Gulfstream Natural Gas System

Gulfstream Natural Gas System Website: www.gulfstreamgas.com Gulfstream has prepared this fact sheet as a guide for emergency response officials who may be asked to respond to an incident involving a Gulfstream natural gas pipeline

More information

INOGATE Technical Secretariat UK Experience European Standards Implementation Key Expert Phil Winnard Session 2 Georgia, October 2015

INOGATE Technical Secretariat UK Experience European Standards Implementation Key Expert Phil Winnard Session 2 Georgia, October 2015 INOGATE Technical Secretariat UK Experience European Standards Implementation Key Expert Phil Winnard Session 2 Georgia, October 2015 BUILDING PARTNERSHIPS FOR ENERGY SECURITY www.inogate.org EN 12186

More information

Success Paths: A Risk Informed Approach to Oil & Gas Well Control

Success Paths: A Risk Informed Approach to Oil & Gas Well Control API Winter E&P Standards Conference, Austin January 18, 2017 Success Paths: A Risk Informed Approach to Oil & Gas Well Control Dr. Dan Fraser Director, Strategic Alliances for Global Energy Solutions,

More information

O&M MANUAL HIGHLIGHTS

O&M MANUAL HIGHLIGHTS O&M MANUAL HIGHLIGHTS GENERAL PROVISIONS Each pipeline must be operated according to this SUBPART 192.603(a) RECORDS 192.603(b) Keep records necessary to administer the procedures of 192.605 RECORDS Life

More information

2 Sentry MCL Installation, Operation & Maintenance

2 Sentry MCL Installation, Operation & Maintenance Gas Liquid & Slurry Solid & Powder Steam & Water Installation, Operation & Maintenance Manual Original Instructions Liquid Sampling Manual Low-Emission Samplers S-GA-IOM-00249-7 11-17 Sentry MCL 966 Blue

More information

CITY OF WEST KELOWNA COUNCIL POLICY MANUAL

CITY OF WEST KELOWNA COUNCIL POLICY MANUAL CITY OF WEST KELOWNA COUNCIL POLICY MANUAL Page 1 of 7 DEPARTMENT: Engineering Services SUBJECT: Traffic Calming Policy (Revised June 6, 2017) Policy Statement: The provision of traffic calming measures

More information

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland Abstract Flooding, cleaning, gauging, dewatering and venting of offshore oil and gas pipelines

More information

Flammable Environments Guideline

Flammable Environments Guideline GUIDE Flammable Environments Guideline 2014-0004 The Canadian Association of Petroleum Producers (CAPP) represents companies, large and small, that explore for, develop and produce natural gas and crude

More information

Journal of Applied Fluid Transients, Vol 1-1, April 2014 (3-1)

Journal of Applied Fluid Transients, Vol 1-1, April 2014 (3-1) Modeling and Field Verification Study of Air Slam Conditions on kalanit Pipeline System By Yiftach Brunner & Sathish Kumar ir valves are integral part of long water transmission mains and are essential

More information

Our Approach to Managing Level Crossing Safety Our Policy

Our Approach to Managing Level Crossing Safety Our Policy Our Approach to Managing Level Crossing Safety Our Policy Our policy towards managing level crossing risk is: that we are committed to reducing the risk at level crossings where reasonably practicable

More information

Gas Cabinets and Valve Manifold Boxes: Applying CGA G13- Rev 2015 to Gas Delivery Equipment

Gas Cabinets and Valve Manifold Boxes: Applying CGA G13- Rev 2015 to Gas Delivery Equipment Gas Cabinets and Valve Manifold Boxes: Applying CGA G13- Rev 2015 to Gas Delivery Equipment The Standard Governing the Storage & Use of Silane: Compressed Gas Association s Publication CGA G-13 2015: Storage

More information

Be our partner in safe, reliable natural gas delivery

Be our partner in safe, reliable natural gas delivery Wide Web at. pipeline operators. The industry has a proven record of safety. Por favor visite para Main, House Main Wide Web at. pipeline operators. The industry has a proven record of safety. Por favor

More information

T e l N o : F a x N o : E m a i l : a i s h c m c - m e. c o m w w w. c m c - m e.

T e l N o : F a x N o : E m a i l : a i s h c m c - m e. c o m w w w. c m c - m e. MU047: Practical Valve Technology: Selection, Installation, Upgrading, Inspection & Troubleshooting MU047 Rev.002 CMCT COURSE OUTLINE Page 1 of 7 Training Description: This five-day intensive course covers

More information

Abstract. 1 Introduction

Abstract. 1 Introduction Risk assessment study of the mutual interactive influence of working procedures on terminals handling dangerous goods in port of Koper (Slovenia) L. Battelino Water Management Institute, Maritime Engineering

More information

DF1 and DF2 Diffusers

DF1 and DF2 Diffusers 1550650/4 IM-P155-07 ST Issue 4 and Diffusers Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Commissioning 5. Operation 6. Maintenance

More information

Flare Gas Measurement in B.C., Alberta, and Saskatchewan Using GE Ultrasonic Metering Technology

Flare Gas Measurement in B.C., Alberta, and Saskatchewan Using GE Ultrasonic Metering Technology November 2017 Flare Gas Measurement in B.C., Alberta, and Saskatchewan Blaine Barnes Tundra Process Solutions www.tundrasolutions.ca 1 MEASUREMENT REGULATIONS With the creation of Directive PNG017 by the

More information

HOT OILING OPERATIONS ALL HSE PRC 172. Approved By: Manager, HSE Performance Assurance. Table of Contents

HOT OILING OPERATIONS ALL HSE PRC 172. Approved By: Manager, HSE Performance Assurance. Table of Contents Owner: HSE Performance Assurance ALL HSE PRC 172 Approved By: Manager, HSE Performance Assurance Retention Code: CG01 CA Revised: March 2015 Review Frequency: Five years or less Table of Contents 1.0 Purpose...

More information

Water Pressure Reducing Valves

Water Pressure Reducing Valves Water Pressure Reducing Valves Controlling Water Pressure in Residential, Commercial, and OEM Applications Watts.com The One-stop Shop for Pressure Regulators Watts is the manufacturer of choice for Water

More information

Lockout / Tag out Program

Lockout / Tag out Program Lockout / Tag out Program Presented by DOSHTI www.doshti.com You will learn Purpose of Lockout- Tag out Requirements for LOTO Types of Hazardous Energy Procedures for LOTO The OSHA Standard for the Control

More information

Delayed Coker Automation & Interlocks

Delayed Coker Automation & Interlocks Delayed Coker Automation & Interlocks a Presented by Mitch Moloney of ExxonMobil @ coking.com April-2005 MJ Moloney - ExxonMobil April-2005 coking.com 0 Automation & Interlocks @ ExxonMobil - Background

More information

INSTALLATION & OPERATION MANUAL FOR Stockpot Range

INSTALLATION & OPERATION MANUAL FOR Stockpot Range INSTALLATION & OPERATION MANUAL FOR Stockpot Range MODELS MLS VSP100 ML-052822 VSP200 ML-052823 VSP200F ML-769292 www.vulcanhart.com MODELS MLS WSPR1 ML-760600 WSPR2 ML-760601 WSPR2F ML-769292 www.wolfrange.com

More information

General Duty Clause. Section 112(r)(1) of CAA. Chris Rascher, EPA Region 1

General Duty Clause. Section 112(r)(1) of CAA. Chris Rascher, EPA Region 1 General Duty Clause Section 112(r)(1) of CAA Chris Rascher, EPA Region 1 Background on the General Duty Clause General Duty Clause 112(r)(1) of CAA Prevention of Accidental Releases Purpose and General

More information

Preventive Maintenance

Preventive Maintenance A Health and Safety Guideline for Your Workplace Why? Preventive maintenance is predetermined work performed to a schedule with the aim of preventing the wear and tear or sudden failure of equipment components.

More information

BRITISH STANDARD BS 341-4: Transportable gas container valves. Part 4: Pressure relief devices ICS

BRITISH STANDARD BS 341-4: Transportable gas container valves. Part 4: Pressure relief devices ICS BRITISH STANDARD BS 341-4:2004 Transportable gas container valves Part 4: Pressure relief devices ICS 23.060.40 This British Standard, having been prepared under the direction of the Standards Policy and

More information

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell:

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell: Energy Control Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: 905.577.0303 cell: 905.977.0210 consultant@staffaid.ca www.staffaid.com Safety, Energy Control, Power Lockout & Function Test Procedures

More information

NATURAL GAS MAINTENANCE. Part 192 Subpart "M"

NATURAL GAS MAINTENANCE. Part 192 Subpart M NATURAL GAS MAINTENANCE Part 192 Subpart "M" CONTACT INFORMATION Pamela West Pipeline Safety Specialist U.S. Department of Transportation PHMSA Inspector Training and Qualifications Main: (405) 686-2310

More information

FAQs: Confined Spaces in Residential Construction

FAQs: Confined Spaces in Residential Construction Provided by Marshall & Sterling, Inc. FAQs: Confined Spaces in Residential Construction A new standard for construction work in confined spaces became effective Aug. 3, 3015. The new standard (Subpart

More information

PIPELINE SAFETY. Darin Burk, Manager Pipeline Safety. January 28, 2014

PIPELINE SAFETY. Darin Burk, Manager Pipeline Safety. January 28, 2014 PIPELINE SAFETY Darin Burk, Manager Pipeline Safety January 28, 2014 Congressional Delegation of Authority Pipeline Safety Act of 1968 Congress Delegated Inspection and Enforcement Authority to the Secretary

More information

Thank You for Attending Today s Webinar. Today s Featured Speaker

Thank You for Attending Today s Webinar. Today s Featured Speaker Thank You for Attending Today s Webinar Your Host Mike DeLacluyse President Lesman Instrument Company miked@lesman.com Today s Featured Speaker A.J. Piskor Combustion & Controls Specialist Lesman Instrument

More information

Striking an underground pipeline or underground electric line can lead to serious injury or death. If you hit either, call (800) , even if

Striking an underground pipeline or underground electric line can lead to serious injury or death. If you hit either, call (800) , even if 1 Striking an underground pipeline or underground electric line can lead to serious injury or death. If you hit either, call (800) 477-5050, even if there is no apparent damage. Call 911 if gas is blowing

More information

PIG MOTION AND DYNAMICS IN COMPLEX GAS NETWORKS. Dr Aidan O Donoghue, Pipeline Research Limited, Glasgow

PIG MOTION AND DYNAMICS IN COMPLEX GAS NETWORKS. Dr Aidan O Donoghue, Pipeline Research Limited, Glasgow PIG MOTION AND DYNAMICS IN COMPLEX GAS NETWORKS Dr Aidan O Donoghue, Pipeline Research Limited, Glasgow A model to examine pigging and inspection of gas networks with multiple pipelines, connections and

More information

Lockout/Tagout Training Overview. Safety Fest 2013

Lockout/Tagout Training Overview. Safety Fest 2013 Lockout/Tagout Training Overview Safety Fest 2013 Purpose of Lockout/Tagout The standard covers the servicing and maintenance of machine and equipment in which the unexpected energization or start up of

More information

Irrigation System Winterization and Pressurization Procedures

Irrigation System Winterization and Pressurization Procedures Irrigation System Winterization and Pressurization Procedures Introduction Any time that an irrigation system is filled and pressurized, or when the system is drained and water flushed from the system,

More information

1.0 PURPOSE 2.0 SCOPE 3.0 DEFINITIONS. ANSI: American National Standards Institute. CCC: Chemical Control Centre

1.0 PURPOSE 2.0 SCOPE 3.0 DEFINITIONS. ANSI: American National Standards Institute. CCC: Chemical Control Centre Revision Date: 5/17/2016 Page: 1 of 13 Health & Safety has developed the emergency eyewash & safety shower equipment procedure which will be implemented in 3 phases over the next four years. Phase 1 will

More information

STAGE 1 FINAL HAZARD ANALYSIS FOR BETHUNGRA LINE VALVE TO BOMEN

STAGE 1 FINAL HAZARD ANALYSIS FOR BETHUNGRA LINE VALVE TO BOMEN STAGE 1 FINAL HAZARD ANALYSIS FOR THE YOUNG TO BOMEN PIPELINE - FROM 8 KILOMETRES NORTH OF BETHUNGRA LINE VALVE TO BOMEN Prepared for: APA Group Document Number: APAGRO\11-243 Revision B Prepared by: Karin

More information

Training Fees 4,000 US$ per participant for Public Training includes Materials/Handouts, tea/coffee breaks, refreshments & Buffet Lunch.

Training Fees 4,000 US$ per participant for Public Training includes Materials/Handouts, tea/coffee breaks, refreshments & Buffet Lunch. Training Title CONTROL & SAFETY RELIEF VALVES Training Duration 5 days Training Venue and Dates Control & Safety Relief Valves 5 06-10 May, 2018 $4,000 Dubai, UAE Trainings will be conducted in any of

More information

INSTALLATION & OPERATION MANUAL FOR Teppan-Yaki Griddles

INSTALLATION & OPERATION MANUAL FOR Teppan-Yaki Griddles INSTALLATION & OPERATION MANUAL FOR Teppan-Yaki Griddles MODELS MLS TYG48C ML-769368-Z1 TYG60C ML-766505-Z www.wolfrange.com TYG48C ITW Food Equipment Group, LLC An Illinois Tool Works Company 3600 North

More information

RESOLUTION A.567(14) adopted on 20 November 1985 REGULATION FOR INERT GAS SYSTEMS ON CHEMICAL TANKERS

RESOLUTION A.567(14) adopted on 20 November 1985 REGULATION FOR INERT GAS SYSTEMS ON CHEMICAL TANKERS INTERNATIONAL MARITIME ORGANIZATION A 14/Res.567 16 January 1986 Original: ENGLISH ASSEMBLY - 14th session Agenda item lo(b) IMO RESOLUTION A.567(14) adopted on 20 November 1985 THE ASSEMBLY, RECALLING

More information

ONSHORE GAS GATHERING FAQS

ONSHORE GAS GATHERING FAQS ONSHORE GAS GATHERING FAQS These Frequently Asked Questions (FAQs) are intended to clarify, explain, and promote better understanding of the gas gathering line rules. These FAQs are not substantive rules

More information

Project Specific Information Package Simonette Expansion Pipeline Project

Project Specific Information Package Simonette Expansion Pipeline Project Date of Handout: 3800, 525 8th Avenue S.W. Calgary, Alberta T2P 1G1 File #: Project Specific Information Package Simonette Expansion Pipeline Project Pembina Pipeline Corporation ( Pembina ) plans to make

More information

Digester Processes. 1. Raw Sludge Pumping System

Digester Processes. 1. Raw Sludge Pumping System Digester Processes 1. Raw Sludge Pumping System Removes accumulated sludge from the primary clarifiers, pumped through 1 of 2 pipes either 150 or 200mm in diameter (Fig. 1.1). Fig 1.1 Pipes feeding Digesters

More information

Fire Performance Safety Standard

Fire Performance Safety Standard Fire Performance Safety Standard February 2008 Fire Safety Standards for Fire Performers Working Before an Audience The fire safety standards and implementation guidelines contained within this document

More information

STCP 08-2 Issue 004: Circuit Live Trip & DAR Tests

STCP 08-2 Issue 004: Circuit Live Trip & DAR Tests STCP 08-2 Issue 004: Circuit Live Trip & DAR Tests STC Procedure Document Authorisation Party Name of Party Representative Signature Date National Grid Electricity Transmission SP Transmission Ltd Scottish

More information

COUNTY ROAD 22 HORSESHOE VALLEY ROAD. Municipal Class Environmental Assessment. simcoe.ca

COUNTY ROAD 22 HORSESHOE VALLEY ROAD. Municipal Class Environmental Assessment. simcoe.ca OCTOBER 2014 Municipal Class Environmental Assessment COUNTY ROAD 22 HORSESHOE VALLEY ROAD Project A Truck Climbing Lanes Project B Intersection Improvements simcoe.ca CORPORATE COMMUNICATIONS DEPARTMENT

More information

By Roger T. Hill, BTech CEng FIMechE, Director, Arthur D. Little Limited, Cambridge CB4 4DW, England

By Roger T. Hill, BTech CEng FIMechE, Director, Arthur D. Little Limited, Cambridge CB4 4DW, England Pipeline Risk Analysis By Roger T. Hill, BTech CEng FIMechE, Director, Arthur D. Little Limited, Cambridge CB4 4DW, England For almost a century, pipelines have been used to transport oil, gas and petroleum

More information

Relief Systems. 11/6/ Fall

Relief Systems. 11/6/ Fall Relief Systems 1 Relief Scenarios o A single relief event requires a particulate vent area and valve size o Relief scenarios are determined based on a PHA o For each scenario, a vent area is calculated

More information

Appendix B Transportation Report

Appendix B Transportation Report Project File Report Appendix B Transportation Report Town of Whitby HMM Project No. 327878 Final Report October 2014 Revision and Version Tracking CP Rail Crossing at New Coronation Road Class EA Study

More information

TN-20/2007. Special Precautions for Fusing Saddle Fittings to Live PE Fuel Gas Mains Pressurized on the Basis of a 0.

TN-20/2007. Special Precautions for Fusing Saddle Fittings to Live PE Fuel Gas Mains Pressurized on the Basis of a 0. TN-20/2007 Special Precautions for Fusing Saddle Fittings to Live PE Fuel Gas Mains Pressurized on the Basis of a 0.40 Design Factor Special Precautions for Fusing Saddle Fittings to Live PE Fuel Gas Mains

More information

New Hampshire Public Utilities Commission CFR 49 Part 192 Regulations. MINIMUM Pipeline Safety Regulations

New Hampshire Public Utilities Commission CFR 49 Part 192 Regulations. MINIMUM Pipeline Safety Regulations New Hampshire Public Utilities Commission CFR 49 Part 192 Regulations MINIMUM Pipeline Safety Regulations Application for Jurisdictional LPG Operators 1 Pipeline Safety Regulations 49 CFR Part 192 (NOTE:

More information

Installation Operating Instructions for Duplex Manual Manifolds PX-TMD Series

Installation Operating Instructions for Duplex Manual Manifolds PX-TMD Series Introduction Powerex manifolds are cleaned, tested and prepared for the indicated gas service and are built in accordance with the Compressed Gas Association guidelines. The manifold consists of a regulator

More information

CIRCULAR NO. O-13. Recommended Practices for Manual Protection of Highway/Railway Grade Crossings

CIRCULAR NO. O-13. Recommended Practices for Manual Protection of Highway/Railway Grade Crossings CIRCULAR NO. O-13 Recommended Practices for Manual Protection of Highway/Railway Grade Crossings Effective: October 1, 2004 CONTENTS 1. SCOPE 2. GENERAL PRINCIPLES 3. DEFINITIONS 4. PROTECTION REQUIRED

More information

GAS FUEL VALVE FORM AGV5 OM 8-03

GAS FUEL VALVE FORM AGV5 OM 8-03 ALTRONIC AGV5 OPERATING MANUAL GAS FUEL VALVE FORM AGV5 OM 8-03 WARNING: DEVIATION FROM THESE INSTALLATION INSTRUCTIONS MAY LEAD TO IMPROPER ENGINE OPERATION WHICH COULD CAUSE PERSONAL INJURY TO OPERATORS

More information

Risk Analysis using Corrosion Rate Parameter on Gas Transmission Pipeline

Risk Analysis using Corrosion Rate Parameter on Gas Transmission Pipeline IOP Conference Series: Materials Science and Engineering PAPER OPEN ACCESS Risk Analysis using Corrosion Rate Parameter on Gas Transmission Pipeline To cite this article: B Sasikirono et al 2017 IOP Conf.

More information

Proposed Abstract for the 2011 Texas A&M Instrumentation Symposium for the Process Industries

Proposed Abstract for the 2011 Texas A&M Instrumentation Symposium for the Process Industries Proposed Abstract for the 2011 Texas A&M Instrumentation Symposium for the Process Industries Focus Area: Automation HMI Title: Author: Shared Field Instruments in SIS: Incidents Caused by Poor Design

More information

High-Pressure Boiler Inspection Procedures: A Complete Checklist

High-Pressure Boiler Inspection Procedures: A Complete Checklist High-Pressure Boiler Inspection Procedures: A Complete Checklist Inspecting high-pressure boilers is a complex process requiring preparation, planning, and a multitude of safety precautions. Regular inspections

More information

FIRE SPRINKLER PRODUCTS PRODUCT CATALOG

FIRE SPRINKLER PRODUCTS PRODUCT CATALOG AGF Manufacturing Inc. FIRE SPRINKLER PRODUCTS PRODUCT CATALOG CAT-AGF_2018 3/18 Reliability, Versatility, Code Compatibility All orders MUST be received by AGF Manufacturing, Inc. in a written format

More information

Safe Work Practices and Permit-to-Work System

Safe Work Practices and Permit-to-Work System CHAPTER 24 Safe Work Practices and Permit-to-Work System 24.1 INTRODUCTION OSHA s Process Safety Management (PSM) Standard (OSHA, 1992) requires employers to develop and implement safe work practices (SWPs)

More information

DESIGN DATA A WET PIPE BLADDER TANK FOAM/WATER SYSTEM WITH HYDRAULICALLY ACTUATED DELUGE CONCENTRATE CONTROL VALVE

DESIGN DATA A WET PIPE BLADDER TANK FOAM/WATER SYSTEM WITH HYDRAULICALLY ACTUATED DELUGE CONCENTRATE CONTROL VALVE February 9, 1998 Foam 101a A BLADDER TANK WITH 1. DESCRIPTION A Wet Pipe Bladder Tank Foam/Water System is a standard wet pipe automatic sprinkler system capable of discharging a foam/water solution automatically

More information

This objective implies that all population groups should find walking appealing, and that it is made easier for them to walk more on a daily basis.

This objective implies that all population groups should find walking appealing, and that it is made easier for them to walk more on a daily basis. Walking for life The Norwegian Walking Strategy Guro Berge Norwegian public Roads Administration "Walking for life" is the slogan for the National Walking Strategy that is now being formulated in Norway.

More information

GAS SAFETY Information Bulletin

GAS SAFETY Information Bulletin GAS SAFETY Information Bulletin June 2016 G-03-11-ABSA [Rev2] Page 1 of 7 Fuel Gas Pressure Piping in Plants This bulletin has been jointly developed by Safety Services, the Pressure Equipment Sub- Council,

More information

PULSATION DAMPENER / SUPPRESSOR SERIES PDS PROVIDES MULTIPLE SYSTEM SAFEGUARDS

PULSATION DAMPENER / SUPPRESSOR SERIES PDS PROVIDES MULTIPLE SYSTEM SAFEGUARDS PULSATION / SUPPRESSOR SERIES PDS PROVIDES MULTIPLE SYSTEM SAFEGUARDS FUNCTIONS: 1. Pulsation Dampener smooths pump flow 2. Surge Suppressor absorbs shocks and vibrations 3. Water Hammer Arrestor eliminates

More information

Dynamic Analysis of a Multi-Stage Compressor Train. Augusto Garcia-Hernandez, Jeffrey A. Bennett, and Dr. Klaus Brun

Dynamic Analysis of a Multi-Stage Compressor Train. Augusto Garcia-Hernandez, Jeffrey A. Bennett, and Dr. Klaus Brun Dynamic Analysis of a Multi-Stage Compressor Train Augusto Garcia-Hernandez, Jeffrey A. Bennett, and Dr. Klaus Brun Slide 2: Presenter/Author Bios Augusto Garcia-Hernandez Group Leader, Pipeline Simulation,

More information

DISTRIBUTION, OPERATION and MAINTENANCE STRATEGY ASSET MANAGEMENT WORK INSTRUCTION ISOLATION OF A WATER NETWORK

DISTRIBUTION, OPERATION and MAINTENANCE STRATEGY ASSET MANAGEMENT WORK INSTRUCTION ISOLATION OF A WATER NETWORK Document Title: Work Instruction Isolation of a Water Network Document Reference: DOM-WN-WIN-00000302 Approved By: Asset Management Title: General Manager Record of Changes and Amendments Amendment No.

More information

PNEUMATIC STOPPERS OPERATING MANUAL. Type F G H - FOG

PNEUMATIC STOPPERS OPERATING MANUAL. Type F G H - FOG OPERATING MANUAL PNEUMATIC STOPPERS Type F G H - FOG This document is property of SO.CA.P. s.r.l. LISSONE - ITALY - ANY DUPLICATION IS FORBIDDEN Rev 07 del 01/11/2016 info@socapsrl.com - www.socapsrl.com

More information

Frequently Asked Questions Directive 056 Facilities Technical

Frequently Asked Questions Directive 056 Facilities Technical Frequently Asked Questions Directive 056 Facilities Technical October 2017 This document clarifies and supports some of the technical requirements related to Directive 056: Energy Development Applications

More information

Standard: NFPA 86 Process Ovens and Furnaces. NFPA 85 Boiler and Combustion Systems Hazards Code

Standard: NFPA 86 Process Ovens and Furnaces. NFPA 85 Boiler and Combustion Systems Hazards Code 11699 Brookpark Road Cleveland, OH 44130 USA P: 216-749-2992 F: 216-398-8403 www.combustionsafety.com Why Test? Main and pilot safety shutoff valves keep fuel out of the firebox when equipment is shut

More information

The Risk of LOPA and SIL Classification in the process industry

The Risk of LOPA and SIL Classification in the process industry The Risk of LOPA and SIL Classification in the process industry Mary Kay O Connor Process Safety Center International Symposium Beyond Regulatory Compliance, Making Safety Second Nature October 28-29,

More information

Your safety and the safety of others are very important.

Your safety and the safety of others are very important. NATURAL GAS TO PROPANE CONVERSION KIT ALPKT57- INSTALLATION INSTRUCTIONS PROPANE CONVERSION KIT SAFETY... INSTALLATION REQUIREMENTS... Tools and Parts... LP Gas Requirements... Table of Contents INSTALLATION

More information

553 Series.

553 Series. 38467.03 www.caleffi.com Pre-adjustable filling units Copyright 01 Caleffi 3 Series Function The automatic filling valve is a device consisting of a pressure reducing valve with compensating seat, visual

More information

EDUCATION DEPARTMENT ACCU-TEST

EDUCATION DEPARTMENT ACCU-TEST ABN 17 100 208 964 EDUCATION DEPARTMENT ACCU-TEST GAS SAFETY SHUT OFF SYSTEM Operating & Installation Manual Head Office (Melbourne) Sydney Brisbane (Distributor) 1/5 Samantha Court 2/14 Welder Road 17

More information

ASSE International Product (Seal) Listing Program

ASSE International Product (Seal) Listing Program ASSE International Product (Seal) Listing Program ASSE 1070-2015 / ASME A112.1070-2015 / CSA B125.70-15 Performance Requirements for Water Temperature Limiting Devices Manufacturer: Contact Person: E-mail:

More information

2017 Temporary traffic control guidelines for pedestrians. v.2

2017 Temporary traffic control guidelines for pedestrians. v.2 2017 Temporary traffic control guidelines for pedestrians v.2 Temporary Traffic Control Guidelines for Pedestrians (2017) The safety and mobility of pedestrians, cyclists and motorists must be considered

More information

TECHNICAL DATA. than the water inlet pressure to the concentrate

TECHNICAL DATA. than the water inlet pressure to the concentrate Foam102a 1. DESCRIPTION The Viking Low Flow Foam/Water proportioning system, is a UL Listed and FM Approved system, for use with 3M foam concentrates. This system consists of a standard wet pipe sprinkler

More information

Dri-Line Mk3 Monnier Compressed Air Drain Trap

Dri-Line Mk3 Monnier Compressed Air Drain Trap 5044050/2 IM-P504-24 CH Issue 2 Dri-Line Mk3 Monnier Compressed Air Drain Trap Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation and Operation

More information

Tri-Tech Medical Inc.

Tri-Tech Medical Inc. Introduction Tri-Tech Medical manifolds are cleaned, tested and prepared for the indicated gas service and are built in accordance with the Compressed Gas Association guidelines. The manifold consists

More information

Engineering Safety into the Design

Engineering Safety into the Design Engineering safety into the design Peter Scantlebury P.Eng Technical Safety Manager Amec Foster Wheeler, Oil & Gas Canada Abstract Safety by design is Amec Foster Wheeler s systematic approach to engineering

More information

CPX EMERGENCY STANDBY MANIFOLD INSTALLATION, OPERATIONS & MAINTENANCE MANUAL

CPX EMERGENCY STANDBY MANIFOLD INSTALLATION, OPERATIONS & MAINTENANCE MANUAL CPX EMERGENCY STANDBY MANIFOLD INSTALLATION, OPERATIONS & MAINTENANCE MANUAL Company Registered Office: Crown House, Stockport, Cheshire, SK13RB No. 850 0700 67 Registered in England and Wales No. 05058855

More information

Network Regulator Maintenance Operatives LS (Non-Accredited)

Network Regulator Maintenance Operatives LS (Non-Accredited) Background Network Regulator Maintenance Operatives LS (Non-Accredited) Network Maintenance Operative (NMO) would be trained to perform work on pressure reducing equipment upstream of the ECV on pressures

More information