SCHOOL ROUTE PLAN. For HUNTER S CREEK ELEMENTARY SCHOOL LOCATION 14 ORANGE COUNTY. Prepared for:
|
|
- Silas Austin
- 6 years ago
- Views:
Transcription
1 SCHOOL ROUTE PLAN For HUNTER S CREEK ELEMENTARY SCHOOL LOCATION 14 ORANGE COUNTY Prepared for: ORANGE COUNTY SCHOOL ASSESSMENT PROGRAM ORANGE COUNTY PUBLIC WORKS Traffic Engineering Division 42 South John Young Parkway Orlando, Florida Contract No.: Y4-93B HNTB No Prepared by: Lake Mary, Florida June 12, 26 Professional Engineer: Douglas J. Petty P.E. No. 5873
2 School Route Plan-Hunter s Creek Elementary School TABLE OF CONTENTS EXECUTIVE SUMMARY INTRODUCTION EXISTING CONDITIONS QUALITATIVE ASSESSMENT RECOMMENDATIONS APPENDIX FIGURES, EXHIBITS, and TABLES FIGURES Figure 1-Project Location Map... 3 Figure 2-School Boundary Map... 9 Figure 3A-School Route Plan Map... 1 Figure 3B-School Route Plan Map Figure 4-Condition Diagram: at Lord Barclay Drive Figure 5-Condition Diagram: at Brookmura Drive Figure 6-Condition Diagram: at Town Loop Boulevard Figure 7-Conceptual Improvement Diagram Figure 8-Conceptual Improvement Diagram at Lord Barclay Drive 23 Figure 9-Conceptual Improvement Diagram at Brookmura Drive Figure 1-Conceptual Improvement Diagram at Town Loop Boulevard EXHIBITS Exhibit 1-West Driveway Exhibit 2- at Lord Barclay Drive/West Driveway Exhibit 3- at Town Loop Boulevard... 2 TABLES Table 1-Field Inventory... 4 Table 2-Summary of Vehicular Volumes... 5 Table 3-Summary of Pedestrian & Bicycle Volumes... 6
3 School Route Plan-Hunter s Creek Elementary School 1 EXECUTIVE SUMMARY HNTB Corporation conducted a School Route Plan Study for Hunter s Creek Elementary School located at 465, Orange County, Florida. This study is being performed as a part of the County s School Assessment Program to identify safe routes for children to walk and bicycle to school. Based on the results of the analysis, field observations, and engineering judgment, the following recommendations and conclusions were developed: 1. Overall, pedestrian and bicycle access to the school is generally safe and efficient. 2. The signing for the school crossing at and Hunter s Creek Boulevard should be updated to comply with the MUTCD. 3. The signing for the crosswalk across the East Driveway should be updated for uniformity and to comply with the MUTCD. 4. The signing at the school crossing of and Lord Barclay Drive/West Driveway should be updated to ensure uniformity, compliance with the MUTCD, and that the correct signing is provided for each approach that is designated as a school crossing. 5. The pedestrian detectors should be updated at the intersection of and Town Loop Boulevard. 6. At the intersection of and Town Loop Boulevard, the pedestrian signing should be updated to comply with the MUTCD. 7. The tree on the south approach of Town Loop Boulevard should be trimmed to allow for proper sign visibility.
4 School Route Plan-Hunter s Creek Elementary School 2 1. INTRODUCTION HNTB Corporation conducted a School Route Plan Study for Hunter s Creek Elementary School located at 465, Orange County, Florida. The purpose of this study is to identify safe routes for children to walk and bicycle to school. The analysis methods used in conducting this study are consistent with those set forth in the Manual on Uniform Traffic Control Devices (MUTCD 23), the Manual on Uniform Traffic Studies (MUTS), and Orange County guidelines and procedures.
5 School Route Plan-Hunter s Creek Elementary School 3 Figure 1-Project Location Map
6 School Route Plan-Hunter s Creek Elementary School 4 2. EXISTING CONDITIONS Hunters Creek Elementary School is located in southwestern Orange County just south of SR 417 and west of US 17/92. Significant features for the study location are summarized below: Feature Table 1-Field Inventory Description School Name Hunter s Creek Elementary School Address 465 Orlando, FL School Hours 8:45 AM to 3: PM (2: PM Wednesday) Student Enrollment 77 Primary Roadway Access Four lane divided with a grass median Posted speed limit: 4 mph Sidewalks: Both sides of the road Bike Lanes: None provided Street lighting: Both sides of the road Pedestrian and Bicycle Access to Sidewalk on the east side of East Driveway and sidewalk on the west School side of West Driveway. Carpool Access to School West driveway to front of school Bus Access East driveway to separate bus loop Guarded School Crossings at Hunter s Creek Boulevard Un-signalized crossing for north, south, and west approaches School crossing warning signs for north and south approaches Crossing guard provided during school times at Lord Barclay Drive/West Driveway Un-signalized crossing for north, south, and west approaches School crossing warning signs for north and west approaches Crossing guards provided during school times for each crossing at Town Loop Boulevard Signalized crossing for north, south, and west approaches School crossing warning signs for each approach Crossing guards provided during school times for each crossing at John Young Parkway Signalized crossing for each approach at the intersection School crossing warning signs for each approach Crossing guards provided during school times for each crossing Other Facilities Sidewalks are provided throughout a majority of the adjacent neighborhoods within the walk zone. Reduced Speed School Zones A 2 mph reduced speed zone is provided on within the vicinity of the school. Overhead span wire mounted speed school zone signs with flashing beacons east and west of Lord Barclay Drive are provided.
7 School Route Plan-Hunter s Creek Elementary School 5 Vehicular, Pedestrian, and Bicycle Volumes Two-hour turning movement counts were conducted at and Lord Barclay Drive/West Driveway and at and Town Loop Boulevard. The counts were conducted from 8:15 to 9:15 AM and 2:3 to 3:3 PM to coincide with the morning arrival time and afternoon departure time of students at the school. Pedestrian, bicycle, automobile, and bus traffic were recorded separately for this count. The following tables summarize the results of these counts: Table 2-Summary of Vehicular Volumes Approaches Lord Barclay Drive at Lord Barclay Drive/West Driveway Direction Northbound Southbound Eastbound Westbound Movement L T R TOT L T R TOT L T R TOT L T R TOT Morning Arrival: 815 to 915 Vehicles Busses Total Afternoon Departure: 143 to 153 Vehicles Busses Total Approaches Town Loop Boulevard at Town Loop Boulevard Direction Northbound Southbound Eastbound Westbound Movement L T R TOT L T R TOT L T R TOT L T R TOT Morning Arrival: 83 to 93 Vehicles Busses Total Afternoon Departure: 1445 to 1545 Vehicles Busses Total
8 School Route Plan-Hunter s Creek Elementary School 6 Table 3-Summary of Pedestrian & Bicycle Volumes at Lord Barclay Drive/West Driveway Total 8:15 8:3 8:45 9: Total 2:3 2:45 3: 3:15 AM PM AM 2 Lord Barclay Drive AM Total Total PM 18 Total AM 2 8: :15 8: :3 2 8: :45 9: 1 9: AM PM Total Total AM PM 2:3 6 2:3 2: :45 3: : 3:15 3 3:15 Total PM 25 Total PM West Driveway Total 8:15 8:3 8:45 9: Total 2:3 2:45 3: 3:15 AM 4 4 PM Total 12 AM PM 9 at Town Loop Boulevard Total 8:15 8:3 8:45 9: Total 2:3 2:45 3: 3:15 AM PM AM 2 Town Loop Boulevard AM Total Total 9 29 PM 38 Total AM 8: :15 8: :3 8: :45 9: 9 3 9: AM PM Total Total AM PM 2:3 2:3 1 2: :45 1 3: : 3:15 1 3:15 Total PM 4 Total PM 2 Town Loop Boulevard Total 8:15 8:3 8:45 9: Total 2:3 2:45 3: 3:15 AM 5 5 PM Total AM 3 2 PM 5
9 School Route Plan-Hunter s Creek Elementary School 7 3. QUALITATIVE ASSESSMENT Hunter s Creek Elementary School is located on approximately one half mile west of John Young Parkway. The school serves children who live in adjacent neighborhoods on the east side of John Young Parkway from South Town Loop Boulevard to North Town Loop Boulevard and on the west side of John Young Parkway from the Orange- Osceola County line to south of the SR 417. All of the neighborhoods in the school zone boundary are within the two mile walk zone. Orange County currently provides bus service for children who live south of Town Center Boulevard for neighborhoods on the east side of John Young Parkway and on the west side in proximity to John Young Parkway. Figure 2 illustrates the school zone boundaries, two-mile walk radius, and existing bus stops for Hunter s Creek Elementary School. Figure 3 is a School Route Plan map of the area within the two-mile walk limit and the school zone boundary where school bus service is not provided. This area is the focus of the qualitative assessment. The school route plan area was reviewed by a registered professional engineer to evaluate vehicle, pedestrian, and bicycle flow patterns to determine what improvements are necessary, if any, to improve the safety and efficiency of the children traveling to and from school. A majority of the children that walk or bicycle to the school live in the Glenhurst subdivision located to the north of Hunter s Creek Elementary School. Sidewalks are provided throughout this neighborhood. The main access to from these homes is provided via Lord Barclay Drive (eastern entrance) and Glenhurst Way. Guarded un-signalized school crossings are provided at both of these access points. Sidewalk is also provided for connecting the cul-de-sacs at the following locations to the sidewalk on Town Center Boulevard: Lord Barclay Drive (western end of subdivision), Hearthside Drive, Roxshire Drive, and Maymont Court. Access from this neighborhood to the school is provided via the sidewalk on the north side of and the guarded school crossing at Lord Barclay Drive/West Driveway. Some children were observed to walk to school from the Carrington (north side of Town Center Boulevard) and Chelsea Landing (north side of, east of the school) subdivisions. Sidewalks are provided on both sides of the roads within these neighborhoods. Access from these neighborhoods to the school is provided via the sidewalk on the north side of and the guarded school crossing at Lord Barclay Drive/West Driveway. School children walking from the gated Villanova subdivision located north of Town Center Boulevard, east of Town Loop Boulevard can use the guarded signalized crossing at Town Loop Boulevard. They can then utilize the sidewalk on the north side of Town Center Boulevard and the guarded school crossing at Lord Barclay Drive/West Driveway to access the school. There are several subdivisions located north and south of Hunter s Creek Boulevard. These include Calabay Cove, Orista Bay, Hunter s Isle, Montana, Ashton, Ocita, Cypress Pointe, and Timucua. Colonial Grand at Hunter s Creek Apartments is also located on the north side of Hunter s Creek Boulevard near John Young Parkway. Bus stops are located close to Timucua and the apartments, so it is not likely that children would be walking to school from these two locations.
10 School Route Plan-Hunter s Creek Elementary School 8 Sidewalk exists on both sides of Hunter s Creek Boulevard. School children who walk from the other subdivisions, with the exception of the east entrance of Calabay Cove and Cypress Pointe, would walk along Hunter s Creek Boulevard to access the guarded un-signalized crossing at, then use the sidewalk on the south side of Town Center Boulevard to access the school. Some of the north and south approach signing for the guarded un-signalized school crossing at and Hunter s Creek Boulevard does not comply with the MUTCD. In addition, a school crossing exists across the west approach on, yet no school signing is provided. The signing for the school crossing at Town Center Boulevard and Hunter s Creek Boulevard should be updated to comply with the MUTCD. As for the east entrance of Calabay Cove and Cypress Pointe, a sidewalk exists behind these two subdivisions that leads to the school. The shortest path for children in these locations would be to use this sidewalk to the school. There are two cul-de-sacs in Cypress Pointe and one cul-de-sac in Calabay Cove that have a paved connection to this sidewalk that children can use to access this sidewalk. Few children walk or bicycle from the neighborhoods located east of John Young Parkway within the two-mile walk limit. These neighborhoods within the school boundary include The Cottages subdivision and the Parks Apartments. Children can use the guarded signalized school crossings provided at John Young Parkway and (all approaches) and at Town Loop Boulevard and (three approaches) to arrive at the school safely. There are two ways for these children to access the school, depending on which side of they are using. From the sidewalk on the north side, children can use the guarded un-signalized crossing at Lord Barclay Drive/West Driveway to access the school. From the sidewalk on the south side, children can use the sidewalk provided on the east side of the school then cross the East Driveway at the unguarded marked school crossing to access the school. The unguarded school crossing on the East Driveway is signed as a Children Crosswalk for the northbound direction and a Student Crossing for the southbound direction. The signing for the crosswalk across the East Driveway should be updated for uniformity and to comply with the MUTCD.
11 9 N Hunter s Creek Elementary School 2 Mile Walk Zone Legend School Zone Boundary School School Bus Stop Traffic Signal Figure 2 School Boundary Map
12 Chelsea Landing 1 G N Carrington G Glenhurst G The Fairways Hunter s Creek Calabay Cove Orista Bay Montana Calabay Cove Cypress Pointe Colonial Grand at Hunter s Creek Apts. Fox Haven Hunter s Isle Ashton Timucua Eagle Landing Ocita Hunter s Creek Elementary School Legend G Crossing Guard Pedestrian Route Bike Lane Crosswalk School Crossing Signalized Intersection Stop Sign Yield Sign Figure 3A School Route Plan Map
13 11 N The Parks Apartments The Cottages Villanova G SEE FIGURE 3A Hunter s Creek Elementary School Legend G Crossing Guard Pedestrian Route Bike Lane Crosswalk School Crossing Signalized Intersection Stop Sign Yield Sign Figure 3B School Route Plan Map
14 School Route Plan-Hunter s Creek Elementary School 12 Hunter s Creek Elementary School was observed during the morning and afternoon hours to assess the operations of children entering and leaving the school. The following observations were made: A guarded un-signalized school crossing exists across the north, south, and west approaches at Lord Barclay Drive/West Driveway. The guards are stationed at the intersection from 8: to 9:45 AM and 2:35 to 4:35 PM (with the exception of Wednesday early release when they are there one hour earlier). One of the school crossing guards present on the day of the observation did not have any comments regarding any safety concerns. This school crossing also includes a reduced speed school zone from 4 mph to 2 mph on which is activated during the hours the school crossing guards are present. This school zone consists of overhead School Zone and End School Zone signs for the east and west approaches. In addition, variable Your Speed signs are provide on the east and west approaches to encourage motorists on Town Center Boulevard to obey the reduced school zone speed limit. These motorists appeared to be traveling at or below the reduced school zone speed. The signing for the school crossing at Lord Barclay Drive/West Driveway is not uniform, as some of the signs are old, and some of the signs are missing. The signing at the school crossing of and Lord Barclay Drive/West Driveway should be updated to ensure uniformity, compliance with the MUTCD, and that the correct signing is provided for each approach that is designated as a school crossing. Pedestrians and bicyclists were observed to utilize the sidewalks on the east and west sides of the school. Curb ramps, school crossing signs, and a crosswalk are provided to cross from the sidewalk on the east side of the school across the East Driveway bus loop to access the school. Some pedestrians and bicyclists may also use the sidewalk that runs behind the subdivisions on the north side of Hunter s Creek Boulevard that leads to the back of the school; however, this was not observed. A majority of the pedestrians and bicyclists were observed to be accompanied by parents either to the school if using the sidewalk on the south side of or to the school crossing at Lord Barclay Drive/West Driveway if using the sidewalk on the north side of. Overall pedestrian and bicycle access to the school is generally safe and efficient. Carpool vehicles enter the school parking lot via the West Driveway then circulate to the drop off and pick up locations at the front of the school. Proper circulation is provided within the school via pavement markings and cones as shown in the adjacent photographs. Drop off and pickup locations are in a line near the front of the school, and a passing lane is provided for motorists to maneuver around parked vehicles waiting for drop off and pick up. Carpool drivers then complete the circulation and exit through the West Driveway.
15 School Route Plan-Hunter s Creek Elementary School 13 The West Driveway also serves the staff parking area. The West Driveway exit is signed as a right turn only. No motorists were observed to violate the turn prohibition during the morning or afternoon school periods. Busses enter and exit the school via the East Driveway bus loop and drop the children off at the front of the school. This operation was observed to be safe and efficient and with no observed conflicts between busses, vehicles, or pedestrians. Westbound left turning carpool motorists were observed to complete their movement when eastbound vehicles on were stopped for school children crossing the west approach. No conflicts were observed due to this, and adequate gaps are provided for these motorists to complete their movement without significant queuing or delay. The signalized intersection of and Town Loop Boulevard was observed during the morning and afternoon school hours. The following observations were made: A guarded school crossing exists at this intersection across the north, south, and west approaches. The guards are stationed at the intersection from 8: to 9:45 AM and 2:35 to 4:35 PM (with the exception of Wednesday early release). One of the school crossing guards present on the day of the observation did not have any comments regarding any safety concerns. Countdown pedestrian signals are provided for each crossing, but the detectors for each of these signals are old as shown in the photograph to the right. The School crossing signing and pavement markings appear to be in good condition with two exceptions. The pedestrian sign for eastbound vehicles located adjacent to the crosswalk across the west approach is old. Also, there is no pedestrian sign located
16 School Route Plan-Hunter s Creek Elementary School 14 adjacent to the crosswalk for southbound drivers. The pedestrian signing at this intersection should be updated to comply with the MUTCD. The advanced pedestrian crosswalk sign located on the south approach is blocked by a tree as shown in the photograph to the right. The tree on the south approach of Town Loop Boulevard should be trimmed to allow for proper sign visibility. Photographs of the school crossing at Lord Barclay Drive/West Driveway, the overhead school zone, the East and West Driveways, and the intersection of at Town Loop Boulevard are included in Exhibits 1 to 3. In addition, the school driveway intersections and the intersection of at Town Loop Boulevard are illustrated on Figures 4 through 6, respectively.
17 Lord Barclay Drive N 15 West Driveway YOUR SPEED 12' 422' 484' 12' YOUR SPEED RIGHT TURN ONLY at Lord Barclay Drive Figure 4 Condition Diagram
18 N at Brookmura Drive CHILDREN CROSSWALK 16 Huntwick Drive Figure 5 Condition Diagram Brookmura Drive 12' 12' STUDENT CROSSING BUS & REGISTERED CAR POOL ONLY BUSES ONLY East Driveway
19 N at Town Loop Boulevard Figure 6 Condition Diagram ' 12' 326'12' Town Loop Blvd. 12' 12' 315' 366' Town Loop Blvd. 12' 12' 12' 12' 12' BLANK OUT SIGN BLANK OUT SIGN
20 School Route Plan-Hunter s Creek Elementary School 18 Exhibit 1-West Driveway Carpool Access to the School Carpool Exit from the School
21 School Route Plan-Hunter s Creek Elementary School 19 Exhibit 2- at Lord Barclay Drive/West Driveway Looking east along at Lord Barclay Drive/West Driveway Looking west along at Lord Barclay Drive/West Driveway
22 School Route Plan-Hunter s Creek Elementary School 2 Exhibit 3- at Town Loop Boulevard Looking east along at Town Loop Boulevard Looking west along at Town Loop Boulevard
23 School Route Plan-Hunter s Creek Elementary School RECOMMENDATIONS Based on the results of the analysis, the field observations and engineering judgment, the following improvements are proposed: 1. The signing for the school crossing at and Hunter s Creek Boulevard should be updated to comply with the MUTCD. 2. The signing for the crosswalk across the East Driveway should be updated for uniformity and to comply with the MUTCD. 3. The signing at the school crossing of and Lord Barclay Drive/West Driveway should be updated to ensure uniformity, compliance with the MUTCD, and that the correct signing is provided for each approach that is designated as a school crossing. 4. The pedestrian detectors should be updated at the intersection of and Town Loop Boulevard. 5. At the intersection of and Town Loop Boulevard, the pedestrian signing should be updated to comply with the MUTCD. 6. The tree on the south approach of Town Loop Boulevard should be trimmed to allow for proper sign visibility. Figures 7, 8, 9, and 1 have been included on the following pages to illustrate these recommendations.
24 Update signing to conform with MUTCD Chelsea Landing G 22 N Existing sign to remain Carrington Remove existing sign G Update pedestrian detectors Install school crosswalk signs with down placards Glenhurst G Calabay Cove Install advanced school sign with school placard Update signing to conform with MUTCD The Fairways Remove existing sign Hunter s Creek Orista Bay Montana Install school crosswalk sign with down placard Calabay Cove Cypress Pointe Colonial Grand at Hunter s Creek Apts. Fox Haven Existing sign to remain Hunter s Isle Ashton Timucua Eagle Landing Ocita Hunter s Creek Elementary School Legend G Crossing Guard Pedestrian Route Bike Lane Crosswalk School Crossing Signalized Intersection Stop Sign Yield Sign Figure 7 Conceptual Improvement Diagram
25 Install school crosswalk signs with down placards Lord Barclay Drive Existing sign to remain N Existing sign to remain 23 Remove existing sign 12' 422' 484' 12' Existing sign to remain Install school placard Install school crosswalk signs with down placards Remove existing sign West Driveway at Lord Barclay Drive Figure 8 Conceptual Improvement Diagram
26 24 Brookmura Drive N Huntwick Drive 12' 12' Remove existing sign East Driveway Install school crosswalk signs with down placards Remove existing sign CROSSING CHILDREN CROSSWALK STUDENT at Brookmura Drive Figure 9 Conceptual Improvement Diagram
27 Existing signs to remain Town Loop Blvd. Install school crosswalk sign with down placard Upgrade pedestrian detectors N ' 12' 12' 12' 12' Relocate school crosswalk sign to southeast quadrant Existing sign to remain 12' 182' 326'12' Install school crosswalk sign with down placard 12' 12' 12' School crosswalk sign relocated from northeast quadrant Existing sign to remain Remove existing sign Town Loop Blvd. 315' Trim tree to allow for proper advance school sign visibility Existing sign to remain at Town Loop Boulevard Figure 1 Conceptual Improvement Diagram
28 School Route Plan-Hunter s Creek Elementary School APPENDIX
29 HNTB CORPORATION 3 PRIMERA BOULEVARD SUITE #2 LAKE MARY, FLORIDA File Name : FOUREIGH Site Code : Start Date : 3/27/26 Page No : 1 FOURTH STREET AT EIGHTH AVENUE TDC-8 DT EIGHTH AVENUE Southbound Groups Printed- 1 - Autos Trucks FOURTH STREET Westbound EIGHTH AVENUE Northbound FOURTH STREET Eastbound Start Time Right Thru Uturn Right Thru Uturn Right Thru Uturn Right Thru Uturn Int. Total 8: : : Total : **BREAK** Total **BREAK** 14: : Total : : Grand Total Apprch % Total % EIGHTH AVENUE Southbound FOURTH STREET Westbound EIGHTH AVENUE Northbound FOURTH STREET Eastbound Start Time Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Int. ht u n Total Total Hour From 8:15 to 11:45-1 of 1 Intersectio n 8:15 Volume Percent Volume Volume High Int. 8:15 8:45 8:3 8:3 Volume Hour From 8:15 to 11:45-1 of 1 By Approach 8:15 8:15 8:15 8:15 Volume Percent High Int. 8:15 8:45 8:3 8:3 Volume
30 HNTB CORPORATION 3 PRIMERA BOULEVARD SUITE #2 LAKE MARY, FLORIDA File Name : FOUREIGH Site Code : Start Date : 3/27/26 Page No : 2 EIGHTH AVENUE Southbound FOURTH STREET Westbound EIGHTH AVENUE Northbound FOURTH STREET Eastbound Start Time Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Int. ht u n Total Total Hour From 12: to 15:15-1 of 1 Intersectio n 14:3 Volume Percent Volume Volume High Int. 15: 15: 15: 14:3 Volume Hour From 12: to 15:15-1 of 1 By Approach 14:15 14:3 14:3 14:3 Volume Percent High Int. 15: 15: 15: 14:3 Volume
31 HNTB CORPORATION 3 PRIMERA BOULEVARD SUITE #2 LAKE MARY, FLORIDA File Name : FOUREIGH Site Code : Start Date : 3/27/26 Page No : 1 FOURTH STREET AT EIGHTH AVENUE TDC-8 DT EIGHTH AVENUE Southbound FOURTH STREET Westbound Groups Printed- 2 - Trucks EIGHTH AVENUE Northbound FOURTH STREET Eastbound Start Time Right Thru Uturn Right Thru Uturn Right Thru Uturn Right Thru Uturn Int. Total 8: **BREAK** 8: Total : 1 1 **BREAK** Total 1 1 **BREAK** 14: : Total : **BREAK** Grand Total Apprch % Total % EIGHTH AVENUE Southbound FOURTH STREET Westbound EIGHTH AVENUE Northbound FOURTH STREET Eastbound Start Time Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Int. ht u n Total Total Hour From 8:15 to 11:45-1 of 1 Intersectio n 8:15 Volume Percent Volume Volume High Int. 8:: AM 8:15 8:45 9: Volume Hour From 8:15 to 11:45-1 of 1 By Approach 8:15 8:15 8:15 8:15 Volume Percent High Int. - 8:15 8:45 9: Volume
32 HNTB CORPORATION 3 PRIMERA BOULEVARD SUITE #2 LAKE MARY, FLORIDA File Name : FOUREIGH Site Code : Start Date : 3/27/26 Page No : 2 EIGHTH AVENUE Southbound FOURTH STREET Westbound EIGHTH AVENUE Northbound FOURTH STREET Eastbound Start Time Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Int. ht u n Total Total Hour From 12: to 15:15-1 of 1 Intersectio n 14:15 Volume Percent Volume Volume High Int. 15: 14:3 Volume Hour From 12: to 15:15-1 of 1 By Approach 12: 14:15 12: 14:15 Volume Percent High Int. - 15: - 14:3 Volume
33 HNTB CORPORATION 3 PRIMERA BOULEVARD SUITE #2 LAKE MARY, FLORIDA File Name : SIXELEVEN Site Code : Start Date : 3/28/26 Page No : 1 SIXTH STREET AT ELEVENTH AVENUE TDC-8 DT ELEVENTH AVENUE Southbound SCHOOL Westbound Groups Printed- Trucks ELEVENTH AVENUE Northbound SIXTH STREET Eastbound Start Time Right Thru Uturn Right Thru Uturn Right Thru Uturn Right Thru Uturn Int. Total 8: : **BREAK** Total : 1 1 **BREAK** Total 1 1 **BREAK** 14: : Total : 1 1 **BREAK** Grand Total Apprch % Total % ELEVENTH AVENUE Southbound SCHOOL Westbound ELEVENTH AVENUE Northbound SIXTH STREET Eastbound Start Time Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Int. ht u n Total Total Hour From 8:15 to 11:45-1 of 1 Intersectio n 8:15 Volume Percent Volume Volume High Int. 8:: AM 8:: AM 8:3 8:3 Volume Hour From 8:15 to 11:45-1 of 1 By Approach 8:15 8:15 8:15 8:15 Volume Percent High Int :3 8:3 Volume
34 HNTB CORPORATION 3 PRIMERA BOULEVARD SUITE #2 LAKE MARY, FLORIDA File Name : SIXELEVEN Site Code : Start Date : 3/28/26 Page No : 2 ELEVENTH AVENUE Southbound SCHOOL Westbound ELEVENTH AVENUE Northbound SIXTH STREET Eastbound Start Time Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Int. ht u n Total Total Hour From 12: to 15:15-1 of 1 Intersectio n 14:15 Volume Percent Volume Volume High Int. 14:3 14:45 14:3 Volume Hour From 12: to 15:15-1 of 1 By Approach 14: 12: 14: 14:15 Volume Percent High Int. 14:3-14:45 14:3 Volume
35 HNTB CORPORATION 3 PRIMERA BOULEVARD SUITE #2 LAKE MARY, FLORIDA File Name : SIXELEVEN Site Code : Start Date : 3/28/26 Page No : 1 SIXTH STREET AT ELEVENTH AVENUE TDC-8 DT ELEVENTH AVENUE Southbound Groups Printed- Autos - Trucks SCHOOL Westbound ELEVENTH AVENUE Northbound SIXTH STREET Eastbound Start Time Right Thru Uturn Right Thru Uturn Right Thru Uturn Right Thru Uturn Int. Total 8: : : Total : **BREAK** Total **BREAK** 14: : Total : : Grand Total Apprch % Total % ELEVENTH AVENUE Southbound SCHOOL Westbound ELEVENTH AVENUE Northbound SIXTH STREET Eastbound Start Time Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Int. ht u n Total Total Hour From 8:15 to 11:45-1 of 1 Intersectio n 8:15 Volume Percent Volume Volume High Int. 8:3 8:45 8:3 8:15 Volume Hour From 8:15 to 11:45-1 of 1 By Approach 8:15 8:15 8:15 8:15 Volume Percent High Int. 8:3 8:45 8:3 8:15 Volume
36 HNTB CORPORATION 3 PRIMERA BOULEVARD SUITE #2 LAKE MARY, FLORIDA File Name : SIXELEVEN Site Code : Start Date : 3/28/26 Page No : 2 ELEVENTH AVENUE Southbound SCHOOL Westbound ELEVENTH AVENUE Northbound SIXTH STREET Eastbound Start Time Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Rig Thr Utur App. Int. ht u n Total Total Hour From 12: to 15:15-1 of 1 Intersectio n 14:3 Volume Percent Volume Volume High Int. 14:45 15: 15: 15: Volume Hour From 12: to 15:15-1 of 1 By Approach 14:3 14:3 14:3 14:3 Volume Percent High Int. 14:45 15: 15: 15: Volume
Hidden Oaks Elementary School
Hidden Oaks Elementary School SCHOOL ROUTE PLAN For HIDDEN OAKS ELEMENTARY SCHOOL LOCATION 13 ORANGE COUNTY Prepared for: ORANGE COUNTY SCHOOL ASSESSMENT PROGRAM ORANGE COUNTY PUBLIC WORKS Traffic Engineering
More informationMeadow Woods Elementary School
Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete this text box) Meadow Woods Elementary School Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete
More informationOrange Center Elementary School
Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete this text box) Orange Center Elementary School Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete
More informationDurrance Elementary School
Durrance Elementary School SCHOOL ROUTE PLAN For DURRANCE ELEMENTARY SCHOOL LOCATION 9 ORANGE COUNTY Prepared for: ORANGE COUNTY SCHOOL ASSESSMENT PROGRAM ORANGE COUNTY PUBLIC WORKS Traffic Engineering
More informationWindy Ridge Elementary School
Windy Ridge Elementary School SCHOOL ROUTE PLAN For WINDY RIDGE ELEMENTARY SCHOOL LOCATION 54 ORANGE COUNTY Prepared for: ORANGE COUNTY SCHOOL ASSESSMENT PROGRAM ORANGE COUNTY PUBLIC WORKS Traffic Engineering
More informationDrag and drop pic and stretch/crop to the limits of the blue rectangle (delete this text box) Maxey Elementary School
Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete this text box) Maxey Elementary School SCHOOL ROUTE PLAN For MAXEY ELEMENTARY SCHOOL LOCATION 33 ORANGE COUNTY Prepared for:
More informationLake Whitney Elementary School
Lake Whitney Elementary School SCHOOL ROUTE PLAN For LAKE WHITNEY ELEMENTARY SCHOOL LOCATION 18 ORANGE COUNTY Prepared for: ORANGE COUNTY SCHOOL ASSESSMENT PROGRAM ORANGE COUNTY PUBLIC WORKS Traffic Engineering
More informationSAFE ROUTES TO SCHOOL
SAFE ROUTES TO SCHOOL Forest Ridge Elementary School Existing Conditions and ACTION PLAN > Oak Creek - Franklin Joint School District Table of Contents CONTEXT Enrollment Boundaries
More informationTable 1 Traffic and Pedestrian Counts on Lafayette Street
Downtown Salem Transportation Study 2 July 8, 2005 On-street parking is allowed on both sides of Lafayette Street. Cars were parked at the island that separates a pull-out area in front of the school entrance
More informationMulti-Modal Traffic Analysis. Parisi and Associates
Mill Valley to Corte Madera Bicycle and Pedestrian Corridor Study Appendix D: Multi-Modal Traffic Analysis Prepared by Parisi and Associates August 2009 Appendix D - Multi-Modal Traffic Analysis Table
More informationPEDESTRIAN SAFETY STUDY
PEDESTRIAN SAFETY STUDY SR 699 (BLIND PASS RD/GULF BLVD) FROM 93 RD AVENUE TO PINELLAS BAYWAY PINELLAS COUNTY SECTION NO.: 15100 MILEPOST: 0.111 3.569 STUDY LIMITS Prepared For: Florida Department of Transportation
More informationSebastopol Charter School Traffic Management Plan
Sebastopol Charter School The serves as the working document in support of these essential goals: to ensure the safety and efficiency of student arrival to and departure from school to ensure the safety
More informationTRAFFIC MANAGEMENT PLAN
292 84 140440 TRAFFIC MANAGEMENT PLAN The purpose of the Traffic Management Plan (TMP) is to have established procedures for traffic flow and circulation around the elementary school related to student
More informationATTACHMENT NO. 11. RRLRT No. 2. Railroad / Light Rail Transit Technical Committee TECHNICAL COMMITTEE: Busway Grade Crossings STATUS/DATE OF ACTION
ATTACHMENT NO. 11 RRLRT No. 2 TECHNICAL COMMITTEE: TOPIC: Railroad / Light Rail Transit Technical Committee Busway Grade Crossings STATUS/DATE OF ACTION RRLRT TC Draft: 06/23/2011 RRLRT TC Approval: 06/27/2014
More informationCity of Albert Lea Policy and Procedure Manual 4.10 ALBERT LEA CROSSWALK POLICY
4.10 ALBERT LEA CROSSWALK POLICY PURPOSE: Pedestrian crosswalks are an integral part of our transportation infrastructure. To be effective and promote safety, marked crosswalks must be installed after
More informationC/CAG. Sunnybrae Elementary School Walking and Bicycling Audit. San Mateo-Foster City School District JUNE 2013
Sunnybrae Elementary School Walking and Bicycling Audit JUNE 2013 San Mateo-Foster City School District C/CAG City/County Association of Governments of San Mateo County SUNNYBRAE ELEMENTARY SCHOOL WALKING
More informationAPPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016
APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of
More informationWalkabout Summary Report
Walkabout Summary Report Introduction On September 3, 2014, stakeholders at Bessie Weller Elementary School (Bessie Weller ES) in Staunton, Virginia met to examine the walking and bicycling network around
More informationAGENDA ITEM 6 D THOMASVILLE ROAD (HERMITAGE BOULEVARD TO LIVE OAK PLANTATION ROAD) ROADWAY SAFETY AUDIT
May 15, 2018 AGENDA ITEM 6 D THOMASVILLE ROAD (HERMITAGE BOULEVARD TO LIVE OAK PLANTATION ROAD) ROADWAY SAFETY AUDIT TYPE OF ITEM: Discussion STATEMENT OF ISSUE The Florida Department of Transportation
More informationFinal Sidewalk Feasibility Study
Garfield Drive From Anastasia Drive to Elizabeth Place City of South Daytona July 23, 2009 Final Sidewalk Feasibility Study Prepared for: Prepared by: Final Sidewalk Feasibility Study Garfield Drive 2
More informationArlington Public Schools Thomas Jefferson Site Evaluation Transportation Networks. Thomas Jefferson Working Group Meeting #6 November 10, 2014
Arlington Public Schools Thomas Jefferson Site Evaluation Transportation Networks Thomas Jefferson Working Group Meeting #6 November 10, 2014 2 3 INTRODUCTION 4 Goal of our work: Identify and assess multi-modal
More informationDRAFT Davidson Elementary School Expansion Transportation Impact Analysis
DRAFT Davidson Elementary School Expansion Transportation Impact Analysis Prepared for: Town of Davidson 216 S. Main Street Davidson, NC 28036 Prepared by: Stantec Consulting Services Inc. 2127 Ayrsley
More informationCaltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns
Caltrans Sloat Boulevard Pedestrian Safety Project Response to Community Questions, Comments & Concerns Revised: May 10, 2016 The California Department of Transportation (Caltrans) is planning various
More informationWaterford Lakes Small Area Study
Waterford Lakes Small Area Study Existing Traffic Conditions PREPARED FOR: ORANGE COUNTY PUBLIC WORKS DEPARTMENT TRAFFIC ENGINEERING DIVISION ORLANDO, FLORIDA PREPARED WITH: INWOOD CONSULTING ENGINEERS
More informationTRAFFIC IMPACT ANALYSIS
TRAFFIC IMPACT ANALYSIS FOR THE CHAMPAIGN UNIT#4 SCHOOL DISTRICT PROPOSED HIGH SCHOOL (SPALDING PARK SITE) IN THE CITY OF CHAMPAIGN Final Report Champaign Urbana Urbanized Area Transportation Study 6/24/2014
More informationTRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT
TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT DEERFIELD TOWNSHIP, WARREN COUNTY, OHIO Nantucket Circle and Montgomery Road () Prepared for: ODLE
More informationDESIGN CRITERIA DIVISION 4900 TRAFFIC SIGNALS
DESIGN CRITERIA DIVISION 4900 TRAFFIC SIGNALS 4901 GENERAL: These criteria shall be adhered to for the design of all publiclyfinanced or privately-financed traffic signal systems to be installed in the
More informationMEMORANDUM. Discussion of the planned crosswalk improvement on Mount Vernon Road near Stratham Drive
MEMORANDUM To: From: Mayor and City Council Michael Smith, Public Works Director Date: August 24, 2015 Subject: Discussion of the Mount Vernon Road Crosswalk Improvement ITEM DESCRIPTION Discussion of
More informationJuly 5, Arthur R. Ware, Jr. Elementary School 2017 Safe Routes to School Walkabout Report
July 5, 2017 Arthur R. Ware, Jr. Elementary School 2017 Safe Routes to School Walkabout Report 1 Walkabout Report Introduction On April 28, 2017, City, School, and SAWMPO staff met to conduct a Safe Routes
More informationMEMORANDUM. Charlotte Fleetwood, Transportation Planner
MEMORANDUM Date: Updated August 22, 2017 To: Organization: Charlotte Fleetwood, Transportation Planner Boston Transportation Department From: Jason DeGray, P.E., PTOE, Regional Director of Engineering
More informationTraffic Circulation & Pedestrian Safety Study
Lyons Township High School North Campus La Grange, Illinois Parking Lot Vaughan Building N Main Building Prepared for: Prepared by: July 23, 2015 Contents List of Figures, iii 1. Introduction...1 2. Existing
More informationChapter 4.3 Enterprise Elementary. Volusia County MPO. March Page 7.0
Chapter 4.3 Enterprise Elementary Enterprise, FL Volusia County MPO March 2008 Page 7.0 Volusia County MPO Bicycle and Pedestrian School Safety Review Study Introduction Enterprise Elementary School is
More informationMilitary Road Safety Improvements
Military Road Safety Improvements 26 th Road North to 31 st Street North SUMMARY OF DATA REVIEW AND PRELIMINARY RECOMMENDATIONS Prepared for: Department of Environmental Services Traffic Engineering and
More informationPART 7. TRAFFIC CONTROLS FOR SCHOOL AREAS CHAPTER 7A. GENERAL
2012 Edition Page 825 Section 7A.01 Need for Standards January 13, 2012 PART 7. TRAFFIC CONTROLS FOR SCHOOL AREAS CHAPTER 7A. GENERAL 01 Regardless of the school location, the best way to achieve effective
More informationWHEREAS delivery trucks also pass through the Narrows, into the northern parking lot, to loading docks in the back of the building.
CEDAR-ISLES-DEAN NEIGHBORHOOD ASSOCIATION ( CIDNA ) RESOLUTION OPPOSING A DRUG STORE DRIVE THRU, AND COMMENDING DORAN COMPANIES FOR PROPOSING MITIGATING AMENITIES INCLUDING NEW LANDSCAPING AND A DEDICATED
More informationALLEY 24 TRAFFIC STUDY
ALLEY 24 TRAFFIC STUDY in City of Frostburg, Maryland January 2013 3566 Teays Valley Road Hurricane, WV Office: (304) 397-5508 www.denniscorporation.com Alley 24 Traffic Study January 2013 Frostburg, Maryland
More informationIntroduction Additional Safe Routes to School Resources Main Street Elementary School Survey Results Field Audit...
Contents Introduction... 2 Additional Safe Routes to School Resources... 2... 3 Survey Results... 4 Field Audit... 6 Proposed Safe Routes to School Elements... 9 Typical Safe Routes to School Summary...
More informationTransportation Impact Study for Abington Terrace
Transportation Impact Study for Abington Terrace Abington Township, Montgomery County, PA Sandy A. Koza, P.E., PTOE PA PE License Number PE059911 Prepared by McMahon Associates, Inc. 425 Commerce Drive,
More informationChapter 3.9 Timbercrest Elementary School. Volusia County MPO. November 2008
Chapter 3.9 Timbercrest Elementary School Deltona, FL Volusia County MPO November 2008 Volusia County MPO School Bicycle and Pedestrian Review Study, Phase 3B School Summary Timbercrest Elementary School
More informationMission Bay Loop (MBL) Public Meeting
Mission Bay Loop (MBL) Public Meeting La Scuola Internazionale di San Francisco, November 18, 2014 Frequently Asked Questions 1. When would construction have to start before the SFMTA loses TIGER funds?
More informationORANGE COUNTY PUBLIC WORKS TRAFFIC INVESTIGATIONS
ORANGE COUNTY PUBLIC WORKS TRAFFIC INVESTIGATIONS STAFF REPORT OF: January 6, 2019 SUPERVISORIAL DISTRICT: 5 SUBJECT: LOCATION: INVESTIGATOR: O Neill Drive at Roanoke Drive; Ladera Ranch; TB 922-E6 Clever
More informationCorporate. Report COUNCIL DATE: May 25, 1998 NO: R1500 REGULAR COUNCIL. TO: Mayor & Council DATE: April 27, 1998
R1500 : Traffic Safety at 25 Avenue and 128 Street Intersection Corporate NO: R1500 Report COUNCIL DATE: May 25, 1998 REGULAR COUNCIL TO: Mayor & Council DATE: April 27, 1998 FROM: General Manager, Engineering
More informationDEPARTMENT OF ENVIRONMENTAL SERVICES. North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis. Prepared for:
DEPARTMENT OF ENVIRONMENTAL SERVICES North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis Prepared for: Arlington County Department of Environmental Services 2100 Clarendon Boulevard,
More informationCITY OF OAK CREEK SAFE ROUTES TO SCHOOL ACTION PLAN. East Middle School
CITY OF OAK CREEK SAFE ROUTES TO SCHOOL ACTION PLAN East Middle School CITY OF OAK CREEK SAFE ROUTES TO SCHOOL ACTION PLAN East Middle School Why Safe Routes to School? Safe Routes to School ( SRTS ) is
More informationCo-ordinator Transportation Committee. Director, Mobility Services and Corporate Fleet Services Environment and Transportation Department
28 REGIONAL MUNICIPALITY OF OTTAWA-CARLETON MUNICIPALITÉ RÉGIONALE D OTTAWA-CARLETON REPORT RAPPORT Our File/N/Réf. Your File/V/Réf. 25 23-97-R016 DATE 15 April 1997 TO/DEST. FROM/EXP. SUBJECT/OBJET Co-ordinator
More informationFRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY
FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Prepared for: City of Thornton And Colorado Department of Transportation Prepared by: 11 Blake Street, Suite 2 Denver, Colorado 822 Contact: Brian Bern, PE, PTOE
More informationDecember 4, Merrimac Zoning Board of Appeals 2-8 School Street Merrimac, MA Attn: Kathy Marshall. Dear Board Members:
December 4, 28 Merrimac Zoning Board of Appeals 2-8 School Street Merrimac, MA 86 Attn: Kathy Marshall RE: RAMSHEAD MERRIMAC, MA Dear Board Members: Bayside Engineering, Inc. has received the MDM Transportation
More informationPeer Review of Highlands Neighborhood Traffic and Pedestrian Safety Plan
FINAL REPORT March 14, 2017 Prepared for: Ada County Highway District Prepared by: SIX MILE ENGINEERING, PA Executive Summary The (Highlands Safety Plan) developed by the Ada County Highway District (ACHD)
More informationComplete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA
Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Aaron Elias, Bill Cisco Abstract As part of evaluating the feasibility of a road diet on Orange Grove Boulevard in Pasadena,
More informationChapter 3.3 Horizon Elementary School. Volusia County MPO. June 2009
Chapter 3.3 Horizon Elementary School Port Orange, FL Volusia County MPO June 2009 Volusia County MPO School Bicycle and Pedestrian Review Study, Phase 3C School Summary Horizon Elementary School is located
More informationSAFE ROUTES TO SCHOOL
SAFE ROUTES TO SCHOOL Edgewood Elementary School Existing Conditions and ACTION PLAN > Oak Creek - Franklin Joint School District Table of Contents CONTEXT Enrollment Boundaries Enrollment
More informationThis Chapter sets forth the minimum design, technical criteria and specifications to be used in the preparation of all roadway plans.
4.1 GENERAL This Chapter sets forth the minimum design, technical criteria and specifications to be used in the preparation of all roadway plans. These Roadway Standards are for new construction and modification
More informationAppendix T CCMP TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD
Appendix T CCMP 3.3.4 TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD 3.3.4 Trail Traffic and Transportation Design Multi-use trails have certain design standards, which vary depending on the agency that
More informationNJDOT Complete Streets Checklist
Background The New Jersey Department of Transportation s Complete Streets Policy promotes a comprehensive, integrated, connected multi-modal network by providing connections to bicycling and walking trip
More informationTRAFFIC ACTION PLAN. Laurie Meadows Neighborhood CITY OF SAN MATEO
TRAFFIC ACTION PLAN Laurie Meadows Neighborhood CITY OF SAN MATEO Draft January 2017 Table of Contents Introduction... 2 The Traffic Forum Process... 5 Neighborhood Traffic Issues... 7 Neighborhood Recommendations
More informationTRAFFIC ASSESSMENT River Edge Colorado
TRAFFIC ASSESSMENT River Edge Colorado Submitted by: Fehr & Peers 621 17th Street, Ste. 231 Denver, CO 8293 (33) 296-43 December, 21 App. M-2 Traffic Assessment River Edge Colorado December 21 TABLE OF
More informationWEST AVENUE AND NEW ROAD TRAFFIC STUDY PART III WEST AVENUE CLOSURE ALTERNATIVES ANALYSIS
WEST AVENUE AND NEW ROAD TRAFFIC STUDY PART III WEST AVENUE CLOSURE ALTERNATIVES ANALYSIS CITY OF LINWOOD ATLANTIC COUNTY, NEW JERSEY March 30, 2006 PREPARED FOR: City of Linwood 400 Poplar Avenue Linwood,
More information2007 TRAFFIC SIGNAL PRIORITY LIST SUMMARY OF STAFF RECOMMENDATIONS TO PEDESTRIAN/BICYCLE/MOTOR VEHICLE COMMISSION.
Traffic Engineering and Parking Divisions David C. Dryer, City Traffic Engineer and Parking Manager 215 Martin Luther King, Jr. Boulevard P.O. Box 2986 Madison, Wisconsin 53701-2986 Phone 608 266 4761
More informationFigure 1: Vicinity Map of the Study Area
ARIZONA TEXAS NEW MEXICO OKLAHOMA May 5, 2016 Mr. Anthony Beach, P.E. BSP Engineers 4800 Lakewood Drive, Suite 4 Waco, Texas 76710 Re: Intersection and Access Analysis along Business 190 in Copperas Cove
More informationTable of Contents FIGURES TABLES APPENDICES. Traffic Impact Study Hudson Street Parking Garage MC Project No.: A Table of Contents
Traffic Impact Study Hudson Street Parking Garage MC Project No.: 151714A Table of Contents Table of Contents I. INTRODUCTION... 2 II. EXISTING CONDITIONS... 5 III. 215 EXISTING TRAFFIC CONDITIONS... 6
More informationFINAL DESIGN TRAFFIC TECHNICAL MEMORANDUM
FINAL DESIGN TRAFFIC TECHNICAL MEMORANDUM July 2014 FINAL (SR 43) Project Development and Environment Study From State Road 60 (Adamo Drive) to I-4 (SR 400) Hillsborough County, Florida Work Program Item
More informationINTERSECTION SAFETY AUDIT: STH 16/67 AND CTH Z
WISCONSIN DEPARTMENT OF TRANSPORTATION INTERSECTION SAFETY AUDIT: STH 16/67 AND CTH Z OCONOMOWOC, WI WISCONSIN DEPARTMENT OF TRANSPORTATION INTERSECTION SAFETY AUDIT: STH 16/67 AND CTH Z OCONOMOWOC, WI
More informationFDOT Treasure Coast Traffic Impact Report
January 20, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report January 20 through January 27, 2017 TREASURE COAST Construction and maintenance
More informationQUICKIE C STORE AND GAS BAR 1780 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:
QUICKIE C STORE AND GAS BAR 1780 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: Quickie Convenience Stores Larny Holdings Ltd. c/o PBC Group April 15, 2015 115-615 Report_1.doc D. J. Halpenny
More informationTo: ACHD Commissioners and Director 3/14/2017. Peer Review of Highlands Neighborhood Traffic and Pedestrian Safety Plan Information Briefing
Paul Woods, President Rebecca W. Arnold, Vice President Kent Goldthorpe, Commissioner Sara M. Baker, Commissioner Jim D. Hansen, Commissioner MEMORANDUM Engineering To: ACHD Commissioners and Director
More informationTraffic Study North Shore School District 112
Traffic Study North Shore School District 112 Proposed Expansion of Northwood Junior High School Prepared By: May 1, 2015 1. Introduction Kenig, Lindgren, O Hara, Aboona, Inc. (KLOA, Inc.) has been retained
More informationTraffic Impact Study. Westlake Elementary School Westlake, Ohio. TMS Engineers, Inc. June 5, 2017
TMS Engineers, Inc. Traffic Impact Study Westlake Elementary School Westlake, Ohio June 5, 2017 Prepared for: Westlake City Schools - Board of Education 27200 Hilliard Boulevard Westlake, OH 44145 TRAFFIC
More informationFDOT Treasure Coast Traffic Impact Report
February 10, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report February 10 through February 17, 2017 TREASURE COAST Construction and maintenance
More informationFDOT Treasure Coast Traffic Impact Report April 7 through April 14, 2017
April 7, 2017 Chuck McGinness, 954 777 4302 chuck.mcginness@dot.state.fl.us FDOT Treasure Coast Traffic Impact Report April 7 through April 14, 2017 TREASURE COAST Construction and maintenance related
More informationTRAFFIC ACTION PLAN. Central Neighborhood CITY OF SAN MATEO
TRAFFIC ACTION PLAN Central Neighborhood CITY OF SAN MATEO Draft January 2017 Table of Contents Introduction... 1 The Traffic Forum Process... 4 Neighborhood Traffic Issues... 7 Neighborhood Recommendations
More informationINDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for:
INDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW Prepared for: Simluc Contractors Limited 2550 Blackwell Street, Ottawa K1B 5R1 October 18, 2013 113-584 Overview_1.doc D. J.
More informationAppendix A. Knoxville TPO Greenway Signage Guidelines. Appendix A: Knoxville TPO Greenway Signage Guidelines Knox to Oak Ridge Greenway Master Plan
Appendix A Knoxville TPO Greenway Signage Guidelines 75 Overview: Adequate signing and marking are essential on shared-use paths, especially to alert bicyclists to potential conflicts and to convey regulatory
More informationOwnership Lots 17 & 18 (Part of Lot 14), Montgomery Auto Sales Park
Traffic Impact Analysis Ownership Lots 17 & 18 (Part of Lot 14), Montgomery Auto Sales Park Silver Spring, MD Lot 17: Site Plan No. 821413 Lot 18: Site Plan No. 821414 Filing Number: 13-TS-1198527A Prepared
More informationClybourn Ave. Protected Bike Lane Study Halsted St. to Division St.
Clybourn Ave. Protected Bike Lane Study Halsted St. to Division St. Nathan Roseberry, Senior Engineer Pam Broviak, Project Manager July 24, 2014 Agenda Project Goals Existing Roadway Conditions Traffic
More informationTraffic Impact Study WestBranch Residential Development Davidson, NC March 2016
Traffic Impact Study WestBranch Residential Development Davidson, NC March 216 TRAFFIC IMPACT STUDY FOR THE WestBranch Residential Development LOCATED IN DAVIDSON, NC Prepared For: Lennar Carolinas, LLC
More informationPEDESTRIAN / BICYCLE SAFETY REVIEW
PEDESTRIAN / BICYCLE SAFETY REVIEW SR 50 / Clearlake Road from Dixon Boulevard to Michigan Avenue Prepared for: Space Coast Transportation Planning Organization 2725 Judge Fran Jamieson Way Bldg. B / Room
More informationComments EXECUTIVE SUMMARY
Comments 1. Under any Alternatives, MCDOT should provide better at-grade pedestrian crossing of Georgia Avenue and Forest Glen Road, including improved crosswalks with wider medians and adequate signal
More informationReference number /VP. Lafayette Downtown Congestion Study - Additional Traffic Analysis
To James Hinkamp and Tony Coe, City of Lafayette Date January 19, 2017 Copies Reference number 243381/VP From Michael Iswalt and Vanessa Peers File reference 4-05 Subject Lafayette Downtown Congestion
More informationC. Brian Shamburger, P.E., PTOE Kimley-Horn and Associates, Inc. State of Texas Registered Firm #928
TECHNICAL MEMORANDUM To: From: Mr. Douglas G. Williams Director Transportation Services Texas A&M University C. Brian Shamburger, P.E., PTOE Kimley-Horn and Associates, Inc. State of Texas Registered Firm
More informationBay to Bay Boulevard Complete Streets Project
Bay to Bay Boulevard Complete Streets Project Dale Mabry Highway to Bayshore Boulevard February 08, 2018 Photo Source: Tampa Bay Times Alessandra Da Pra Meeting Format Introduction Resurfacing Information
More informationTHIS PAGE LEFT BLANK INTENTIONALLY
GA SR 25 Spur at Canal Road Transportation Impact Analysis PREPARED FOR GLYNN COUNTY, GEORGIA 1725 Reynolds Street, Suite 300 Brunswick, Georgia 31520 PREPARED BY 217 Arrowhead Boulevard Suite 26 Jonesboro,
More informationMandan Commission Meeting August 2, 2016 Mandan City Hall
Mandan-Bismarck Corridor Improvement Study Mandan Commission Meeting August 2, 2016 Mandan City Hall 2014 HDR, Inc., all rights reserved. Mandan Corridors Study Schedule 2015 2016 Study Kick Off August
More informationAppendix B. Environmental Resource Technical Memorandum. Assessment on Travel Pattern and Access Impacts
Appendix B Environmental Resource Technical Memorandum Assessment on Travel Pattern and Access Impacts TECHNICAL MEMORANDUM ENVIRONMENTAL RE-EVALUATION FOR UNION STATION TO OAK CLIFF DALLAS STREETCAR To:
More informationTRANSPORTATION STANDARDS
INTRODUCTION LOCAL STREETS ON-STREET PARKING SIDEWALKS STREET LIGHTING STREET FURNISHINGS TRAFFIC CALMING STREET TREES MEDIAN PLANTING BOULEVARD LOCATIONS VILLAGE CENTER STREET LOCATIONS RESIDENTIAL STREET
More information5. MODIFICATIONS AT JEANNE D ARC BOULEVARD/REGIONAL ROAD 174 INTERCHANGE INTERSECTION - PUBLIC HEARING COMMITTEE RECOMMENDATION
5. MODIFICATIONS AT JEANNE D ARC BOULEVARD/REGIONAL ROAD 174 INTERCHANGE INTERSECTION - PUBLIC HEARING COMMITTEE RECOMMENDATION Having held a public hearing, that Council approve the preliminary designs
More informationSECTION 1 - TRAFFIC PLANNING
SECTION 1 - TRAFFIC PLANNING 1.1 TRAFFIC OPERATIONS 1.1.1 Roadway Functional Classification The Multnomah County Comprehensive Framework Plan s Policy 34: Trafficways and the Functional Classification
More informationBroad Street Bicycle Boulevard Design Guidelines
Broad Street Bicycle Boulevard Design Guidelines Building from the strategies introduced in the 2013 Bicycle Transportation Plan and community input received thus far, City Transportation Staff have identified
More informationTraffic Impact Memorandum. May 22, 2018
BISHOP PROFESSIONAL DEVELOPMENT BUILDING Proposed Land-use Change & Parking Modification 3601 SW 31st Street Topeka, Kansas 66614 CFS Project No. 185077 Traffic Impact Memorandum May 22, 2018 Prepared
More informationStreet / Bob Billings Parkway Lawrence, Kansas CFS Project No
Drive Improvements 6 th Street to 15 th Street / Bob Billings Parkway Lawrence, Kansas 6644 CFS Project No. 15-56 Traffic Impact Study July 15, 15 Prepared for: City of Lawrence Public Works Department
More informationIC Chapter 3. Traffic Control Signals
IC 9-21-3 Chapter 3. Traffic Control Signals IC 9-21-3-0.5 "Pedestrian hybrid beacon" Sec. 0.5. As used in this chapter, "pedestrian hybrid beacon" means a traffic control signal used to warn and control
More informationFrequently Asked Questions
Frequently Asked Questions Business US 190 in Copperas Cove From Avenue D to Constitution Drive What is access management? A. Access Management is a growing effort by government agencies to improve how
More informationF L E T C H E R A V E N U E
Jan. 29, 2014 Introduction F L E T C H E R A V E N U E FDOT Local Agency Program (LAP) Project FPN: 428214-1-58-01 CIP 63090 Hillsborough County, Traffic Engineering, PWD Stake holders and partners are
More informationWaterford Lakes Small Area Study Report
Waterford Lakes Small Area Study Report Orange County District 4 Prepared for: Orange County Public Works Department Traffic Engineering Division 4200 S. John Young Parkway Orlando, FL 32839-9205 Prepared
More informationSCHOOL CROSSING PROTECTION CRITERIA
CITY OF MADISON TRAFFIC ENGINEERING SCHOOL CROSSING PROTECTION CRITERIA January 2016 Adopted as Policy on August 31, 1976, by Common Council by Amended Resolution #29,540 Amended on September 14, 1976,
More informationCOWETA HIGH SCHOOL AND EAST HIGHWAY 51
COWETA HIGH SCHOOL AND EAST HIGHWAY 51 Lack of sidewalks along Ben Lumpkin Rd. Lack of crosswalks and ramps at intersection. Hwy 51 is wide to cross as a pedestrian. No ADA compliance or connection to
More informationHENDERSON DEVELOPMENT 213, 217, 221, 221 ½, 223 HENDERSON AVENUE and 65 TEMPLETON STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW.
HENDERSON DEVELOPMENT 213, 217, 221, 221 ½, 223 HENDERSON AVENUE and 65 TEMPLETON STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW Prepared for: 2294170 Ontario Inc. February 2, 2017 117-652 Report_1.doc
More informationGene Dillon Elementary School Traffic Study Division Street Site
To: From: Dr. James Hess, Superintendent Jordan Schwarze, PE, Senior Engineer Matt Pacyna, PE, Senior Associate Date: March 30, 2016 Subject: Gene Dillon Elementary School Traffic Study reet Site Memorandum
More informationOttawa Beach Road Study
Ottawa Beach Road Study Prepared For: Park Township September 30, 2014 Project No. G140303 OTTAWA BEACH ROAD STUDY PREPARED FOR: PARK TOWNSHIP SEPTEMBER 30, 2014 PROJECT NO. G140303 TABLE OF CONTENTS 1.0
More informationGuidance. ATTACHMENT F: Draft Additional Pages for Bicycle Facility Design Toolkit Separated Bike Lanes: Two-Way to One-Way Transitions
ATTACHMENT F: Draft Additional Pages for Bicycle Facility Design Toolkit Separated Bike Lanes: Two-Way to One-Way Transitions This treatment provides a transition from two-way separated bike lanes to one-way
More informationPedestrian Road Safety Audit
Pedestrian Road Safety Audit Middlebrook Road From Father Hurley Boulevard to Waring Station Road December 2017 Montgomery County Department of Transportation Table of Contents 1. Introduction... 1 1.1
More information