1 SR-203 Sidewalks and Town-Wide Mobility Improvements Town Council Presentation September 7, 2016
2 SR-203 Sidewalks and Town- Wide Mobility Improvements SR-203 Sidewalks and Appurtenances Town-Wide Mobility Improvements Recently completed Ongoing Near Term Planned
3 Planning Background ~ SR 203 Mobility Element Accepted in 2011/2012, In Process of Update in 2015/2016 Main Street Plan Accepted on February 19, 2014 North Village Specific Plan Adopted in 2000, Amended in 2014 Master Pedestrian Plan Accepted March 15, 2014
4 Planning Background ~ SR 203 Trail System Master Plan Pedestrian Master Plan General Bicycle Master Plan Local Transportation Commission State Transportation Improvement Program Eastern Sierra Transit Authority
5 Planning: Mobility Element Mobility Element Accepted in 2011/2012, In Process of Update in 2015/2016 Emphasizes Feet-First Transportation - emphasizes and prioritizes nonmotorized travel first, public transportation second, and vehicle last. Goal M.1. Create a safe and efficient complete streets network that is based on feet-first principles, accommodates all modes of transportation, and serves all users. Policy M.1.1. Plan, design, and construct all new streets as complete streets and work to retrofit and/or accommodate complete streets infrastructure or strategies on existing streets in ways that respect and maintain neighborhood character Policy M.1.5. Reduce conflicts between vehicles and pedestrians through improved access, design, and management, including driveways, frontage roads, and turn lanes. Goal M.8. Support feet-first objectives by providing a linked year-round recreational and commuter pedestrian system that is safe and comprehensive. Action M Work with Caltrans to make State Route 203 within Town a complete street by providing improved pedestrian facilities and safety measures, including sidewalks and safe crossings. Goal M.10. Support feet-first objectives by providing a linked year-round recreational and commuter bicycle system that is safe and comprehensive. Action M Work with Caltrans to make State Route 203 within Town a complete street by providing improved bicycle facilities and improved safety, including the installation of bike lanes, pavement markings, signage, and crossings.
6 Planning ~ Main Street Plan Main Street Plan Accepted February 19, 2014 Study Area: 1.5-mile Corridor of Main Street Focus: Providing a Plan to offer Pedestrian Opportunities Divided Design into 4 Categories: Downtown Main Street, West Main Street Area A, West Main Street Area B, Resort Gateway Area
7 Planning: North Village Specific Plan North Village Specific Plan Adopted in 2000, Amended in 2014 Achieve the following pedestrian objectives: provide for safe and continuous pedestrian movements (including) pedestrian crossing(s) mid-block on Minaret, and pedestrian crossings at the Main Street, Lake Mary Road, and Forest Trail intersections. Public places on each side of Minaret are connected by sidewalks, and paths for continuous pedestrian circulation within the pedestrian core and throughout North Village. These walks and pathways, along with the bicycle lanes on Minaret and Lake Mary Roads, connect to the community-wide trail and bikeway systems. Identifies future sidewalk on the west side of Minaret Road
8 Planning: Pedestrian Master Plan Pedestrian Master Plan Accepted March 15, 2014 Identified all SR-203 sidewalks For implementation
9 Projects Identified in Planning Studies Objective: Construct sidewalk facilities adjacent to SR-203; Install bicycle lanes adjacent to SR-203; Improve current drainage facilities; Update lighting to meet Town Standards Current Projects Identified in Planning Studies: SR-203 (North Main Street) Sidewalk and Safety Project North side Main Street, from the Lake Mary Road/Minaret Road intersection to the Main Street/Sierra Boulevard intersection(route203,4.8/5.3) SR-203 (West Minaret Road) Sidewalk and Safety Project West side Minaret Road from Lake Mary Road/Minaret Road intersection to the 8050 Driveway 2016 CFD Project East side Minaret Road from Forest Trail to Burgers Lower Main Street Sidewalk Project South side Main Street, from Manzanita Road/South Frontage Road intersection to Laurel Mountain Road/South Frontage Road(Route203,5.3/5.6) North side Main Street, from 3330 Main Street to Main Street/Forest Trail intersection (Route 203, 5.4/5.6) Not currently programmed South side Main Street, from the Lake Mary Road/Minaret Boulevard intersection to Main Street/Mountain Boulevard intersection (Route203,4.8/5.3)
10 Phasing ~ SR CFD Project SR-203, Phase 1 (North Main St.) Sidewalk and Safety Project SR 203, Phase 3: Lower Main Street Project SR-203, Phase 2 (West Minaret Rd) Sidewalk and Safety Project Future MUP: To be determined Note: All blue line are existing sidewalks or multi-use paths.
11 2016 CFD Project 2016 CFD Project Construction: Summer 2016 Status: Spiess Construction. Start date: August 31. Scope: Construction of sidewalk, curb and gutter, transit pull out and shelter, drainage improvements, and street lighting for Minaret Road and Forest Trail. Location: Forest Trail from Berner Street to Minaret Road and Minaret Road from Forest Trail to Burgers Cost (without contingencies): $928,692.50
12 SR-203, Phase 1 (North Main St) Sidewalk and Safety Project Construction: Summer 2016/2017 Current Status: Recommended for award September 7. Spiess Construction. May begin September 2016, majority of work summer Scope: Construction of sidewalk, curb and gutter, pedestrian ramp at northeast corner Main/Minaret, bus turnout and shelter, reconstruct retaining walls, drainage improvements, and street lighting. Location: Main Street from Mountain Boulevard to Minaret Road Cost (without contingencies): $2,537, Agreements: Cooperative Agreement with Caltrans/STIP Funds; Private Developer contribution SR-203, Phase 1 (North Main St.) Sidewalk and Safety Project
13 SR-203, Phase 2 (West Minaret Rd) Sidewalk and Safety Project Proposed Construction Date: Summer 2017 Current Status: Initial development of project plans, specifications and estimates. Initiating possible right of way process. Scope: Construction of a sidewalk, bus turnout, reconstruction of two retaining walls, drainage improvements, and street lighting Location: Minaret Road from Lake Mary Road to 8050 Driveway Estimated Cost (without contingencies): $850,000 Agreements: Cooperative Agreement with Caltrans, Private Developer contribution to be included SR-203, Phase 2 (West Minaret Rd) Sidewalk and Safety Project
14 SR 203, Phase 3 ~ Lower Main St Sidewalks Proposed Construction Date: Summer 2019 Current Status: Applied for ATP Grant, awaiting results. Requested STIP funding in 2018/2020 Fiscal Years for programming. Scope: Construction of sidewalk from Sierra Boulevard to Forest Trail (intermittent) and from Manzanita Road to Laurel Mountain Road, retaining wall from Mountain Blvd to Sierra Blvd, drainage improvements, and street lighting Location: Main Street from Mountain Boulevard to Laurel Mountain Road Estimated Cost (without contingencies): $4,000,000 Agreements: Cooperative Agreement with Caltrans SR 203, Phase 3: Lower Main Street Project
15 Bike Lanes Town initiated an Encroachment Permit in 2011 for needed bike signs and pavement markings from SR- 203/Minaret Road intersection to the Welcome Center Driveway
16 Multi-use Paths and Sidewalks Multi-Use Paths (MUP) versus Sidewalks Multi-Use Path: Signed as Trail Signage Sidewalks: Signed by Municipal Signage
17 Recently Completed Town- Wide Mobility Improvements Lakes Basin Path (2011) Meadow Lane Connector Path (2011) Sherwin Street Bridge (2011) Sierra Park Sidewalks(2011) Tavern Road Sidewalks(2012) Sierra Nevada Sidewalks(2013) College Connector Path (2013) Canyon Boulevard Sidewalks (2014) Meridian Boulevard Sidewalks (2014) Waterford Bridge and Multi-use Path (2014) Trails End Park Improvements (2015) Mammoth Elementary School Improvements (2015) North Village Ramp Improvements (2016)
18 Recently Completed Town- Wide Mobility Improvements
19 On-Going Mobility Improvements (2016) 2016 CFD Project Hillside Drive Parking Lot Lake Mary Road to Lake George Road Multi-use Path Meridian Multi-use Path Repair North Main Street Sidewalks Old Mammoth Road Concrete Improvements
20 On-going Mobility Improvements
21 Programmed Mobility Improvements SR-203 (West Minaret Road) Sidewalk and Safety Project (2017) Mammoth Creek Gap Closure Project (2018) Lower Main Street Sidewalk Project (2019)
22 Programmed Mobility Improvements
23 Town-Wide Mobility Improvements
MASTER BICYCLE AND PEDESTRIAN PLAN
VILLAGE OF NORTHBROOK MASTER BICYCLE AND PEDESTRIAN PLAN DRAFT PLAN OPEN HOUSE May 2, 2018 AGENDA 1. Community Engagement 2. Vision and Goals 3. General Structure of Plan 4. Recommendations Overview 5.
More informationNon-Motorized Transportation 7-1
Non-Motorized Transportation 7-1 Transportation facilities no longer mean just accommodating a vehicle powered by a combustion engine. Pedestrian and non-motorized facilities are important modes of travel
More informationWest Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road
West Dimond Blvd Jodhpur St to Sand Lake CSS Transportation Project Summary Municipality of Anchorage Project # 05 005 Project Manager: John Smith, P.E. (MOA PM&E) Project Administrator: Julie Makela,
More informationCorpus Christi Metropolitan Transportation Plan Fiscal Year Introduction:
Introduction: The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) has continued the efforts started through the Intermodal Surface Transportation Efficiency
More informationEngineering - Bicycle and Pedestrian
Capital Improvement Plan Project Summary # Bikeways Program 781,000 860,000 900,000 933,000 933,000 933,000 # Cannonball Path 1,200,000-780,000 - - - # Capital City Trail - 70,000 - - 910,000 - # Goodman
More informationExhibit 1 PLANNING COMMISSION AGENDA ITEM
Exhibit 1 PLANNING COMMISSION AGENDA ITEM Project Name: Grand Junction Circulation Plan Grand Junction Complete Streets Policy Applicant: City of Grand Junction Representative: David Thornton Address:
More informationSolana Beach Comprehensive Active Transportation Strategy (CATS)
Solana Beach Comprehensive Active Transportation Strategy (CATS) 3.0 Goals & Policies The Solana Beach CATS goals and objectives outlined below were largely drawn from the Solana Beach Circulation Element
More informationMAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report
Page 1 MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report August 1, 2012 MAG Project #481 Page 2 Task 6 Executive Summary and Regional Significance Report Introduction
More informationCity of Madison: 2017 Capital Budget Capital Improvement Plan
Capital Improvement Plan Project Summary Bikeways Program 779,000 751,000 630,000 670,000 703,000 703,000 Cannonball Path 210,000 - - 730,000 - - Cap City Trail 1,140,000-360,000 - - 910,000 Ice Age Junction
More informationRESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY
RESOLUTION NO. 2018-?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY WHEREAS, safe, convenient, and accessible transportation for all users is a priority of the City of Neptune
More informationCITY OF PORTSMOUTH PLANNING DEPARTMENT
CITY OF PORTSMOUTH PLANNING DEPARTMENT MEMORANDUM TO: JOHN P. BOHENKO, CITY MANAGER FROM: JULIET T.H. WALKER, PLANNING DIRECTOR SUBJECT: BICYCLE / PEDESTRIAN PLAN PROGRESS UPDATE DATE: 3/13/2018 Background
More information5 CIRCULATION AND STREET DESIGN
5 CIRCULATION AND STREET DESIGN This chapter describes circulation and streetscape improvements proposed for the Northwest Chico Specific Plan Area. It includes detailed design specifications for existing
More informationDuwamish Way-finding and CTR Report
V. North Tukwila When the North Tukwila Manufacturing and Industrial Center was designated in 1992 as part of the region s land use and transportation plan, the plan called for the area to set a light-rail
More informationLiving Streets Policy
Living Streets Policy Introduction Living streets balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote safety and convenience, enhance community identity, create
More informationNM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County.
Transportation PRINCE WILLIAM COUNTY 2008 COMPREHENSIVE PLAN NON-MOTORIZED PLAN CONTENTS Goals, Policies, and Action Strategies Table 4 (Bike Facility Classifications and Descriptions) Table 5 (Bike Facility
More informationCITY OF BLOOMINGTON COMPLETE STREETS POLICY
CITY OF BLOOMINGTON COMPLETE STREETS POLICY POLICY OBJECTIVE: The City of Bloomington will enhance safety, mobility, accessibility and convenience for transportation network users of all ages and abilities,
More informationChapter 5 Future Transportation
Chapter 5 Future Transportation The Future Land Use Plan identifies the desired land use designations. The land uses desired for Crozet depend, in large part, on the success of the transportation system,
More informationWatertown Complete Streets Prioritization Plan. Public Meeting #1 December 14, 2017
Watertown Complete Streets Prioritization Plan Public Meeting #1 December 14, 2017 Goals for Public Meeting Overview of MassDOT Complete Streets Funding Program Educate the community on Complete Streets
More informationACTIVE TRANSPORTATION/NONMOTORIZED TRANSPORTATION
ACTIVE TRANSPORTATION/NONMOTORIZED TRANSPORTATION BACKGROUND Active transportation, also known as nonmotorized transportation, is increasingly recognized as an important consideration when planning and
More informationProposed. City of Grand Junction Complete Streets Policy. Exhibit 10
Proposed City of Grand Junction Complete Streets Policy Exhibit 10 1 City of Grand Junction Complete Streets Policy Vision: The Complete Streets Vision is to develop a safe, efficient, and reliable travel
More information3.16 TRANSPORTATION, CIRCULATION, AND PARKING Regulatory Setting Environmental Setting ROADWAY SYSTEM
3.16 TRANSPORTATION, CIRCULATION, AND PARKING This section assesses the potential for implementation of the Orchard Park Redevelopment component of the 2018 LRDP to result in impacts related to transportation,
More information10A. DATE: October 5, Pedestrian and Bicycle Advisory Committee. Kevin Colin, Deputy Planning Manager Curt Bates, City Engineer
10A DATE: October 5, 2016 TO: PREPARED BY: SUBJECT: Pedestrian and Bicycle Advisory Committee Kevin Colin, Deputy Planning Manager Curt Bates, City Engineer Discussion and Provide Comments, Associated
More informationArlington s Master Transportation Plan
Arlington s Master Transportation Plan The Master Transportation Plan (MTP) Adopted in eight parts Goals & Policies element and MTP Map adopted in 2007 Bicycle, Pedestrian and Demand and Systems Management
More informationCONNECTING PEOPLE TO PLACES
CONNECTING PEOPLE TO PLACES 82 EAST BENCH MASTER PLAN 07 Introduction The East Bench transportation system is a collection of slow moving, treelined residential streets and major arteries that are the
More informationAGENDA ITEM NO. 5b HCAOG TAC meeting of May 8, 2014
Humboldt County Association of Governments Eureka, CA, 95501 AGENDA ITEM NO. 5b HCAOG TAC meeting of May 8, 2014 DATE: May 1, 2014 TO: HCAOG Technical Advisory Committee (TAC) FROM:, SUBJECT: Letters of
More informationBasalt Creek Transportation Refinement Plan Recommendations
Basalt Creek Transportation Refinement Plan Recommendations Introduction The Basalt Creek transportation planning effort analyzed future transportation conditions and evaluated alternative strategies for
More informationComplete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER
Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets City Commission adopted a Complete Streets policy in 2012 Complete Streets are road networks that are designed for all users:
More informationCOASTAL RAIL TRAIL ROSE CREEK BIKEWAY PROJECT COMMUNITY WORKSHOP #2 AUGUST 15, 2013
COASTAL RAIL TRAIL ROSE CREEK BIKEWAY PROJECT COMMUNITY WORKSHOP #2 AUGUST 15, 2013 CHRIS CARTERETTE, AICP PROJECT MANAGER Chris.Carterette@sandag.org Direct: 619-699.7319 REGIONAL PLANNING BACKGROUND
More informationAppendix C 3. Bicycle / Pedestrian Planning
Appendix C 3. Bicycle / Pedestrian Planning BICYCLE/PEDESTRIAN PLANNING 2005 Master Plan GOAL: Provide for safe and convenient bicycle and pedestrian circulation throughout the City. Develop a city-wide
More informationGoal 3: Foster an environment of partnerships and collaboration to connect our communities and regions to one another.
Non-Motorized Transportation Plan (NMTP) Draft Vision, Goal and,, Tri-County Regional Planning Commission (TCRPC) Purpose The purpose of the Tri-County Regional Planning Commission (TCRPC) Non-Motorized
More informationTABLE OF CONTENTS. Executive Summary
Executive Summary Background... ES-1 Pedestrian Network... ES-2 Bikeway Network... ES-2 Collision History... ES-2 Public Input... ES-4 Conclusions and Recommendations... ES-4 1. Introduction and Setting
More informationRoosevelt Estates Neighborhood Improvements
Roosevelt Estates Neighborhood Improvements Transportation Alternatives Application May 5 th, 2016 Qualifying Activities Construction of on-road and off-road trail facilities for pedestrians, bicyclists,
More informationCastro Valley Municipal Advisory Council March 19, 2018
Castro Valley Municipal Advisory Council March 19, 2018 1 Background 2 Draft Bicycle Vision and Pedestrian Networks 3 Next Steps 4 Updates Agenda 2 PROJECT AREA: Unincorporated Areas of Alameda County
More informationCITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies
CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN Section VIII Mobility Element Goals, Objectives, and Policies Adopted August 6, 2015 by Ordinance No. 1591 VIII MOBILITY ELEMENT Table of Contents Page Number
More informationAgenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN
PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations
More informationAPPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016
APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of
More informationCITY OF LANCASTER PROPOSED NEW PROJECTS
CITY OF LANCASTER 2013-2014 PROPOSED NEW PROJECTS Project Code 11 Facilities and Fixtures Project Title 1 11BS018 Main. Yard Storage Bldg, Phase 2 2 11GS007 Parks Improvements 3 11GS008 Dog Park AHP 4
More informationBicycle-Pedestrian Master Plan: Chapters 3 and 4 Distribution
Bicycle-Pedestrian Master Plan: Chapters 3 and 4 Distribution Finksburg Planning and Citizens Council March 22, 2018 Overview Progress Citizen Outreach Vision Chapter 3 - Existing Conditions Chapter 4
More informationAmericans with Disabilities Act Transition Plan for Public Right-of-Way Improvements
Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements Prepared by: Public Works Department Engineering Division October 2015 Table of Contents Section I Introduction.. 3
More informationTransportation Corridor Studies: Summary of Recommendations
Transportation Corridor Studies: Summary of Recommendations Route 4 Corridor Study: Route 10 Corridor Study: Route 44 Corridor Study: Route 175 Corridor Study: Route 5/15 Corridor Study: Rentschler Field
More informationA Matter of Fairness: ROCOG s Environmental Justice Protocol. What is Mobility Limitation?
No Person Left Behind What is Mobility Limitation? What is the Access Limitation? Environmental Justice population should be provided adequate mobility & access to meet their needs; Identify acceptable
More informationCity of Gainesville Transportation/Roadway Needs PROJECT SUMMARY
A1 Roadway Resurfacing $23,846,000 TYPE: Preservation of existing system Roadway resurfacing A2 Signal Replacement $6,000,000 TYPE: Preservation of existing system Replace traffic signals. B1 W 6th St
More informationPRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN
PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations
More informationComplete Streets Funding Program Project Prioritization Plan
Funding Program Project Prioritization Plan Location and Type Needs South Street Crosswalk Installation Stripe a new formalized crosswalk across South Street at the Anne T. Dunphy School pedestrian path
More informationClackamas County Comprehensive Plan
ROADWAYS The County s road system permits the movement of goods and people between communities and regions, using any of a variety of modes of travel. Roads provide access to virtually all property. They
More information2018 Pedestrian and Bicycle and Safe Routes to School Application for Funding Page 1 of 31
2018 Pedestrian and Bicycle and Safe Routes to School Application for Funding Page 1 of 31 2018 Pedestrian and Bicycle and Safe Routes to School Application for Funding Part 1: General Information Funding
More informationPrince George s County plans, policies, and projects
Prince George s County plans, policies, and projects Over 250 projects for trails, bikeways, designated bike lanes and sidewalk construction Trail projects that improve access to Metro Sidewalk and trail
More informationOmaha s Complete Streets Policy
Omaha s Complete Streets Policy (Adopted August 2015) VISION To create great places and enhance our quality of life, the City of Omaha will provide safe, accessible streets for all users. Complete Streets
More informationBicycle and Pedestrian Plans and Improvements
Bicycle and Pedestrian Plans and Improvements Presented to the City Council By Randle Harwood, Planning and Development, and Richard Zavala, Parks and Community Services September 24, 2013 Purpose Review
More informationCirculation in Elk Grove includes: Motor vehicles, including cars and trucks
Circulation, as it is used in this General Plan, refers to the many ways people and goods move from place to place in Elk Grove and the region. Circulation in Elk Grove includes: Motor vehicles, including
More informationEnvironment and Public Works Committee Presentation
Mixed Use Centers Complete Streets Guidelines Project Environment and Public Works Committee Presentation December 10, 2008 Project Objectives: Conduct an inter-departmental and agency process to study
More informationComplete Streets Successes, Opportunities, and Challenges
Complete Streets Successes, Opportunities, and Challenges Juliet Walker, Transportation Planner, City of Portsmouth Rob Houseman, Director of Planning and Development, Town of Wolfeboro Chris Parker, Director
More informationHILLSDALE/US101 BICYCLE/PEDESTRIAN BRIDGE PROJECT
HILLSDALE/US101 BICYCLE/PEDESTRIAN BRIDGE PROJECT PUBLIC WORKSHOP AUGUST 19, 2014 DEPARTMENT OF PUBLIC WORKS STEWARDS OF THE INFRASTRUCTURE AND ENVIRONMENT PROJECT TEAM Aaron Lam, Associate Engineer Tracy
More informationBoard-Approved Funding Awards for Cycle 4 Active Transportation Grant Program Projects (in Order of Project Rankings) Approved on
CAPITAL Large Category Projects Board-Approved Funding Awards for Cycle 4 Active Transportation Grant Program Projects (in Order of Project Rankings) Approved on 07-27-18 1 La Mesa University Ave Pedestrian
More informationHennepin County Bicycle and Pedestrian Planning
Hennepin County Bicycle and Pedestrian Planning 1 Value of bicycle and sidewalk systems Safety Livability Mobility Health Personal Finances Economic Sustainability Clean Air Recreation Parking and congestion
More informationChapter 7. Transportation. Transportation Road Network Plan Transit Cyclists Pedestrians Multi-Use and Equestrian Trails
Chapter 7 Transportation Transportation Road Network Plan Transit Cyclists Pedestrians Multi-Use and Equestrian Trails 7.1 TRANSPORTATION BACKGROUND The District of Maple Ridge faces a number of unique
More informationCyclists and Bikeways: What s your match? A guide to bikeway options for a variety of cyclists
Cyclists and Bikeways: What s your match? guide to bikeway options for a variety of cyclists The workshop and this resource were made possible by funding from the Province of Ontario via the Ministry of
More informationPeterborough Council on Aging
Peterborough Council on Aging Discussion paper series #4, 2015 Transportation Transportation, including accessible and affordable public transport is a key factor influencing active aging. in particular,
More informationCity of Saline. Complete Streets Ordinance
City of Saline Complete Streets Ordinance September 13 and 20, 2010 CARLISLE/WORTMAN ASSOCIATES What Are Complete Streets? Complete streets are designed to serve everyonemotorists as well as pedestrians
More informationProposed Bridge Street East Bicycle Lanes Public Open House Thursday, April 27, 2017
WELCOME Proposed Bridge Street East Bicycle Lanes Public Open House Thursday, April 27, 2017 Purpose of the Open House The purpose of this Open House is to gain public input on the bicycle lanes proposed
More informationCITY OF SEATTLE RESOLUTION. WHEREAS, the Washington State Department of Transportation (WSDOT) led the Seattle
SDOT SR0 Design Refinements RES August, 0 Version #D 0 CITY OF SEATTLE RESOLUTION..title A RESOLUTION relating to the State Route 0, Interstate to Medina Bridge Replacement and High Occupancy Vehicle Project;
More informationNJDOT Complete Streets Checklist
Background The New Jersey Department of Transportation s Complete Streets Policy promotes a comprehensive, integrated, connected multi-modal network by providing connections to bicycling and walking trip
More informationChapter 3 DESIGN SPECIFICATIONS
Brampton PathWays Planning and Design Guidelines 27 Chapter 3 DESIGN SPECIFICATIONS 3.1 CLASS 1 MULTI-USE PATH Off-road multi-use trails are the backbone of the Brampton PathWays Network. They are typically
More informationMichael Parmer, Management Aide, City Manager's Office
P139 STAFF REPORT f CITY NL- NAGER' S OFFICE RANCHO Date: C;UCAMONGA To: From: Subject: Mayor and Members of the City Council John R. Gillison, City Manager Michael Parmer, Management Aide, City Manager's
More informationFM 1092/Murphy Road Access Management Study Pulic Meeting #1. Wednesday, August 31, :00 p.m. 8:00 p.m.
FM 1092/Murphy Road Access Management Study Pulic Meeting #1 Wednesday, August 31, 2011 6:00 p.m. 8:00 p.m. Introductions Agency Partners H-GAC Missouri City TxDOT Introductions Consulting Team In Association
More informationOcean Park Boulevard Green Street Project Alternatives & Trade Offs
Planning Commission March 4, 2009 Ocean Park Boulevard Green Street Project Alternatives & Trade Offs Purpose of Tonight s Meeting Review concept plans and options Provide input on alternatives and trade-offs
More informationChapter VISION, MISSION, AND GOALS AND OBJECTIVES. Vision. Mission. Goals and Objectives CONNECTING COMMUNITIES ACROSS THE ST.
VISION, MISSION, AND GOALS AND OBJECTIVES Chapter 3 The Plan s vision, mission, and goals and objectives were developed through a series of interactive exercises with the Citizens Advisory Committee (CAC)
More informationTRANSPORTATION TRAINING TOPICS. April 6, 2010
TRANSPORTATION TRAINING TOPICS April 6, 2010 Roles of Transportation Providers Context and Policy Makers Division of Transportation and Traffic Other City Operations Other Transportation Operators CMA
More information5. RUNNINGWAY GUIDELINES
5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved
More informationDRAFT - CITY OF MEDFORD TRANSPORTATION SYSTEM PLAN Roadway Cross-Sections
Roadway Cross-Sections Medford s roadway cross-section standards apply to new and reconstructed roads. The crosssections take into consideration roadway function and operational characteristics, including
More informationHouma-Thibodaux Metropolitan Planning Organization STP<200K Funding Application APPLICATION
APPLICATION HOUMA-THIBODAUX METROPOLITAN PLANNING ORGANIZATION (HTMPO) FOR SURFACE TRANSPORTATION PROGRAM (STP
More informationBicycle Pedestrian Master Plan Pre Bid Meeting Portsmouth, NH August 15, 2013
Bicycle Pedestrian Master Plan Pre Bid Meeting Portsmouth, NH August 15, 2013 2005 Master Plan GOAL: Provide for safe and convenient bicycle and pedestrian circulation throughout the City. Develop a city
More informationCottonwood Heights HAWK Pedestrian Crossing on Fort Union Blvd. Project Type Capital Improvement
Cottonwood Heights HAWK Pedestrian Crossing on Fort Union Blvd. At West Side of Mountview Park Entrance (Approx. 1600 East) $ 206,800 $ 192,800 Install a HAWK Pedestrian Crossing System on Fort Union Boulevard,
More informationArlington Public Schools Thomas Jefferson Site Evaluation Transportation Networks. Thomas Jefferson Working Group Meeting #6 November 10, 2014
Arlington Public Schools Thomas Jefferson Site Evaluation Transportation Networks Thomas Jefferson Working Group Meeting #6 November 10, 2014 2 3 INTRODUCTION 4 Goal of our work: Identify and assess multi-modal
More informationGiles Run Connector Road
Giles Run Connector Road Laurel Hill Adaptive Reuse Area to Laurel Crest Drive South County Federation Meeting June 14, 2016 History Connector road included in the Laurel Hill Comprehensive Plan amendment
More informationIn station areas, new pedestrian links can increase network connectivity and provide direct access to stations.
The Last Mile Planning for Pedestrians Planning around stations will put pedestrians first. Making walking to stations safe and easy is important; walking will be a part of every rapid transit Accessible
More informationSacramento Grid 2.0. The Downtown Transportation Study
Sacramento Grid 2.0 The Downtown Transportation Study April 20, 2016 The Grid 4.25 square miles Street grid defined at birth of City Lettered and numbered streets spaced every 400 ft East-west alleys halfway
More informationUniversity of Victoria Campus Cycling Plan Terms of Reference. 1.0 Project Description
University of Victoria Campus Cycling Plan Terms of Reference 1.0 Project Description The Campus Cycling Plan, a first for the University, will provide a comprehensive and coordinated approach to support
More informationTRANSPORTATION & MOBILITY
TRANSPORTATION & MOBILITY ROADWAY SYSTEM There are approximately 40 miles of roadways in Manitou Springs. For planning purposes, roadways are typically assigned a functional classification which defines
More informationEast Burke Transportation, Safety and Capacity Improvements
East Burke Transportation, Safety and Capacity Improvements The purpose of this project is to increase mobility and improve safety for pedestrians, cyclists, and motor vehicles along VT Route 114 in the
More informationBicycle Facilities Planning
Bicycle Facilities Planning Overview Types of Cyclists Purpose for Riding Types of Facilities Bike Lanes Bicycle Boulevards Cycle Tracks Intersections Signals Signing and Marking Discussion Types of Bicyclists
More informationITEM 3 ATTACHMENT A RESOLUTION NO
ITEM 3 ATTACHMENT A RESOLUTION NO. 2018-1575 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CALABASAS, CALIFORNIA, ADOPTING THE FISCAL YEAR 2017-18 LIST OF PROJECTS FUNDED BY SB 1: THE ROAD REPAIR AND
More informationThis chapter describes the proposed circulation system and transportation alternatives associated with
5.0 Circulation 5.1 OVERVIEW This chapter describes the proposed circulation system and transportation alternatives associated with West Landing, and summarize the information contained in the Existing
More informationMeadow Woods Elementary School
Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete this text box) Meadow Woods Elementary School Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete
More informationHarbord Street and Hoskin Avenue Bicycle Lane Upgrades
STAFF REPORT ACTION REQUIRED and Bicycle Lane Upgrades Date: April 22, 2014 To: From: Wards: Reference Number: Public Works and Infrastructure Committee General Manager, Transportation Services 19 and
More informationShore Drive Safety Task Force. Report to the SDAC
Shore Drive Safety Task Force Report to the SDAC April 20, 2006 Table of Contents Introduction... 3 Section I Safety Recommendations... 5 Section II Communication/Public Involvement Plan... 14 Section
More informationSafe Streets. City of Lake Forest Park. March 21, 2017
Safe Streets City of Lake Forest Park March 21, 2017 1 01 WELCOME 2 Agenda WELCOME WHAT IS THIS PROJECT? CONTEXT DRAFT CITYWIDE PROJECTS EXERCISE INTRODUCTION 3 02 WHAT IS THIS PROJECT? 4 WHAT IS THIS
More informationRZC Appendix 8A Marymoor Subarea Street Requirements
RZC Appendix 8A Marymoor Subarea Street Requirements For additional design details for Marymoor Subarea infrastructure, refer to the 2017 Marymoor Subarea Infrastructure Planning Report. STREET REQUIREMENTS
More informationBicycle and Pedestrian Advisory Committee (BPAC) November 21, 2013
Bicycle and Pedestrian Advisory Committee (BPAC) November 21, 2013 OVERALL LAND USE CONCEPT Overall Broadway Valdez District: 95.5 acres (35.1 acres right-of ways + 60.4 acres developable land) Plan Subareas:
More informationAppendix 3 Roadway and Bike/Ped Design Standards
Appendix 3 Roadway and Bike/Ped Design Standards OTO Transportation Plan 2040 4/20/2017 Page A3-1 Adopted Standards The adopted OTO Design Standards and Major Thoroughfare Plan are contained herein.
More informationTOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY
TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY I. VISION, GOALS & PRINCIPLES VISION To improve the streets of Portland making them safer and more accessible for all users including pedestrians,
More informationBuilding Great Neighbourhoods BELLEVUE AND VIRGINIA PARK
Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK This is Meeting 2 Unfortunately, some residents in Bellevue and Virginia Park received the wrong information for this public open house (Meeting
More informationBuilding Great Neighbourhoods BONNIE DOON
Building Great Neighbourhoods BONNIE DOON We Are Here Today To Explain the Neighbourhood Renewal Process Show you the Westwood Preliminary Design Ask for local knowledge Highlight the Local Improvement
More informationCITY OF ELKO BICYCLE AND PATHWAY PLAN
CITY OF ELKO BICYCLE AND PATHWAY PLAN INTRODUCTION: The City of Elko is intended to provide the basic framework for the development of a functional bicycle and pathway system for the community with connections
More informationAGENDA ITEM G-2 Public Works
AGENDA ITEM G-2 Public Works STAFF REPORT City Council Meeting Date: 12/6/2016 Staff Report Number: 16-214-CC Regular Business: Approve the Oak Grove University Crane Bike Improvement Concept Plan, authorize
More informationThe Bike Buzz in Richland. November 2017 Carl Berkowitz
The Bike Buzz in Richland November 2017 Carl Berkowitz Richland has been growing by leaps and bounds with lots of new homes and roads throughout the community. Recognizing all the growth in the Queensgate
More informationCity of Davis East Covell Corridor Plan
Community Open House #2 January 22, 2014 6:00 8:00 p.m. Veterans Memorial Center, Club Room City of Davis Introduction The (ECCP) is a taking a comprehensive look at the existing transportation systems
More informationCity of Waterloo Complete Streets Policy
City of Waterloo Complete Streets Policy Chris Hodgson P. Eng City of Waterloo Complete Streets Forum 2011 April 28-29 Toronto Waterloo context: Current population Major employers Universities and student
More informationPlant City Walk-Bike Plan
Plant City Walk-Bike Plan Plant City Commute Mode Share 2.2% 1.4% 2.9% Drove alone 10.2% Carpooled Public transportation (0.1%) Walked Used a Bike (0.4%) 82.9% Taxicab, motorcycle, or other means Worked
More informationADA TRANSITION PLAN 2013
ADA TRANSITION PLAN 2013 TABLE OF CONTENTS Contents Introduction 1 Purpose 2 Identified Obstacles to the Public Right of Way 3 Criteria for Determining Impediments at Village Facilities 4 Removing Barriers