Surfers Paradise Ocean Front

Similar documents
Corrosion problems in seawater pump caissons. Practical solutions.

Elcometer 123. Surface Profile Gauge. Operating Instructions

Retractable Pool Cover

Use equation for the cylindrical section and equation or for the ends.

AUSTRALIAN PROFESSIONAL GALVANIZING Capability Statement CAPABILITY STATEMENT. APG S01.04 Capability Statement_APG.docx 27/06/2015 Page 1 of 6

Elcometer 125. Surface Profile Comparator. Operating Instructions

Oxymax W COS51D. Technical Information. Digital sensor for measuring dissolved oxygen Membrane-covered amperometric sensor

MEASURING WATER CONTENT IN COMPRESSED BREATHING AIR IN COMPLIANCE WITH EN 12021:2014 ULTRA-PRECISE AND ULTRA-RELIABLE WITH POLYMER TECHNOLOGY

Materials Performance November Nitrogen generator inhibits corrosion within fire protection systems

Elcometer Viscosity Cup. Operating Instructions

TECHNICAL DATA CAUTION

Calibration Procedure. PosiTest DFT Combo

200A Series ELECTRONIC LEVEL TRANSMITTER

L 100. Bubble-Tube Level System. Installation, Operation and Maintenance Instructions

BYLAW NUMBER

CHANNEL & SUPPORT SYSTEMS

Elcometer ISO Groove Depth Checker. Operating Instructions

PROJECTS STREETS

Pulsed Eddy Current (PEC) Inspection through Insulation

Procedure for Setting a Mooring

We re good at what we do! Anywhere, TX SITE

SCENARIO 18 Leak on Intermodal Pressure Tank Container

PRO-50 Instrument Supply Regulator

TOWN OF AURORA. Pool Enclosure Permit Guide. PLANNING AND BUILDING SERVICES Building Division

INTRODUCTION Porosity, permeability, and pore size distribution are three closely related concepts important to filter design and filter performance.

SHOP WELDED TANKS STANDARD CONNECTIONS

THE CORPORATION OF THE TOWN OF GREATER NAPANEE BY-LAW NO

ASHRAE made significant changes in 2001 to the calculations. Fundamentals of Safety Relief Systems

SPECIFICATIONS PARTICLE SENSOR KS-19F Higashimotomachi, Kokubunji, Tokyo , Japan

Intertherm 3070 Application Guidelines

SPECIFICATIONS PARTICLE SENSOR KS-18F Higashimotomachi, Kokubunji, Tokyo , Japan

EASIDEW TRANSMITTER with Current Source Output

CITY OF TORONTO. BY-LAW No

TOWNSHIP OF DOURO-DUMMER BY-LAW NO

Model PDT Dewpoint Transmitter

LEGIONELLA MANAGEMENT PROCEDURE

TECHNICAL DATA OBSOLETE

Liquefied gas cargo tanks and process pressure vessels

January 2010 (Replaces November 2007) ENVIRONMENTAL CATEGORIES

Auriol LCD sports watch with altimeter and compass

Football Equipment. 5 9/16" Gooseneck Goalposts

Trial Anchors through Existing Gabions

Residential Fence Tubing

2017 LGA 191/192 & 195 Pipeline Safety Conference

Fences. General Considerations Approval is required for fences.

Mechanical Anchoring Systems HDA Undercut Anchor Product description. HDA-P Undercut Anchor Pre-Set Type

TECHNICAL DATA. TRIMPAC Model B-5 & B-5B

INDUSTRIAS IBAIONDO, HYDROPNEUMATIC TANKS

Gas Physics Pressure and Flow Topics Covered:

Before application, test the atmospheric conditions in the vicinity of the substrate for the dew formation according to ISO

VARIABLE ORIFICE BALANCING VALVE PN 25 TECHNICAL DATA SHEET. Approved by*: Main features:

Speed control assembly model A-1

Electropneumatic Transducer (I/P) Installation, Operation and

Standard Recommended Practice. Field Measurement of Surface Profile of Abrasive Blast-Cleaned Steel Surfaces Using a Replica Tape

Installation, Operation and Maintenance Instructions for Chemical Dosing Pots

Calibration Procedure

CORROSION AT THE AIR-WATER INTERFACE REMOVE THE GAS

94060 FRP Conservation Vent. Features. FRP Conservation Vent. One piece construction prevents product leakage

94060 FRP Conservation Vent. Features. FRP Conservation Vent. One piece construction prevents product leakage

IP2, IP2A and IP2D. Spirax-Monnier International Compressed Air Filter/ Regulators

MASS FLOW SYSTEMS MASS FLOW MEASURING, CONTROLLING AND BLENDING SYSTEMS

9408 Series Dissolved Oxygen Systems. Dissolved oxygen systems designed for reliable operation with minimal operating costs

Installation, Operation and Maintenance Instructions for Direct Hot Water Storage Vessels

Instruction Manual. CG16K Barometrically Compensated Capsule Dial Gauge. CG16K Capsule Dial Gauge, 0 to 25 mbar

ABB MEASUREMENT & ANALYTICS DATA SHEET series Dissolved oxygen systems

Vibrating Wire Load Cell (3, 4, 5 And 6 Gauge Cells) User Manual

RELIEF VALVES. General Description

SCREEN OPENINGS FOR STRAINERS

TECHNICAL DATA. Q = C v P S

Rate Charts: Gandy Spreaders 24, 36 & 42-inch Models

Designing an ICCP System for the Hull of an Arctic Ice-Breaking Vessel

Repair Stations. Securabike. Advantages

TECHNICAL DATA ACCELERATOR MODEL E-1

A hose layline contains important information for specifying the replacement assembly: manufacturer, hose trade name, working pressure and hose ID.

Interline 399 Application Guidelines

Product Numbers & Ordering Information

Example A: A 400-N force is applied to a tabletop over a square area with side-length L = 20-cm.

TECHNICAL DATA 3 MODEL G-3000 DRY VALVE RISER ASSEMBLY

INTERPLANT STANDARD - STEEL INDUSTRY CODE OF PRACTICE FOR SELECTION, Corresponding IS does not exist

CHICAGO, IL 6226 West 74th Street Chicago, IL Phone:

Calibration Procedure

TECHNICAL DATA. Q= Cv S

TECHNICAL DATA Q = C. v P S. 2 Model G-2000 Dry valve. Page 1 of 13

Introduction IP codes are used in electrical product catalogs, etc., to indicate waterproofness and so on.

ANTI-ENTRAPMENT PLAN

Cygnus Underwater. UT Meters & Spare Parts Sales. Searchwise Aberdeen Ltd Unit 6, Broomiesburn, Ellon Ind Estate, Ellon, Aberdeenshire, UK, AB41 9RD

ASPIRE for Integrity Management Support for Upstream Assets. Payam Jamshidi, TWI Ltd Sebastian Hartmann, Innospection Ltd

FLAMMABLE GAS SENSOR/TRANSMITTER

TECHNICAL DATA SINGLE INTERLOCKED PREACTION SYSTEM WITH PNEUMATIC RELEASE

Risk assessment (all vessel types)

The Experts in Vacuum Solutions

By E. Smith - BP Amoco Exploration, Sunbury, England, and J. McAleese - City University, London, England

SLSQ SURF SPORTS CALENDAR May 2014 to July 2015 (Version 2) NB: Any events listed are still very much tentative listings.

FLUORESCENCE DETERMINATION OF OXYGEN

FPG8601 Force Balanced Piston Gauge

CHAIN LINK FENCE GATE

HIGHVIEW COLLEGE RECREATIONAL WATER POLICY

Application notes for Die-Slide and Die-Slide Renovate

Dri-Line Mk3 Monnier Compressed Air Drain Trap

MAY 2015 EQUIPMENT LIST CONTENTS: 1. SWIMMING LANES 2. STARTING BLOCKS 3. STORAGE DRUMS FOR SWIMMING LANES 4. WATERPOLO GOALS AND FIELD LINES

Transcription:

Performance Report of Hot Dip Galvanized Coatings at Surfers Paradise Ocean Front 24 February 1999 CONDUCTED BY: SEAN McCORMICK INDUSTRIAL GALVANIZERS

1.0 INTRODUCTION The purpose of this brief report is to establish the corrosion rate of hot dip galvanized products along the oceanfront at Surfer Paradise. From this information it will be possible to establish an approximate life span for internal steelwork (galvanized) used in the refurbishment of the building at number 2 Wharf Street. It is important to note that all references made about galvanizing in this report are based on the steelwork being completely exposed (external) or completely enclosed (internal). Galvanized steelwork that is partially exposed or subject to areas where it will pool water will generally corrode at a much higher rate. 2.0 RESULTS 2.1.0 Areas Tested There was three (3) areas tested at Surfers Paradise. The age of the galvanized steelwork tested ranged from two and a half (2.5) to twelve (12) years. All tests were conducted on the ocean side of the steelwork. The results of the tests performed are presented in the following format: Site No. Steel section description. Original coating mass minimum requirement (AS1650-1989). Coating thickness readings (microns) as at 24/02/99 All of the tests performed are shown in micrometres, however some readings have been converted to grams/m 2 by multiplying the result by 7.15 as per AS1650-1989 Appendix H 5.2. All coating thickness readings were taken using a calibrated Elcometer 345 electronic digital coating thickness gauge. Both the light pole and pole nails current average coating thickness still remains higher than the original minimum average coating thickness required by AS1650-1989 Section 5. This is not uncommon and is largely a result of the steel metallurgy and thickness. Case Study: Surfers Paradise Oceanfront 1999 Page: 2

2.2.1 Site One: 75NB (3mm) Pipe Geoffery Cornish Walkway This particular pole is at the very northern end of the walkway and is approximately 100 metres south of Wharf Road. The pole was galvanized and erected approximately six seven years ago. Original coating thickness requirement was 63µm or 450 grams/m 2. Readings taken: 53, 56, 52, 54, 58, 58, 49, 51, 43, 49 Ave: 52.3µm Case Study: Surfers Paradise Oceanfront 1999 Page: 3

2.2.2 Site Two: Pole Nails (10mm FMS) Cnr Broadbeach Blvd & Second Ave This pole nail is located approximately 150 metres south of Wharf Road. The pole nail was installed approximately 2.5 years ago in 1996. Original coating thickness requirement was 84µm or 600 grams/m 2. Readings taken: 116,108, 120, 104, 152, 104, 112, 103, 110, 118 Ave: 114.7µm Case Study: Surfers Paradise Oceanfront 1999 Page: 4

2.2.3 Site Three: Light Pole (5mm) Broadbeach Surf Life Saving Club The readings on this light pole still remain well above the minimum requirements of AS1650, which is 84µm or 600 grams/m 2. The pole is situated in front of the Broadbeach Surf Life Saving Club and was installed approximately 12 years ago. Readings taken: 124, 124, 129, 138, 123, 127, 112, 136, 126, 148 Ave: 128.7µm Case Study: Surfers Paradise Oceanfront 1999 Page: 5

Case Study: Surfers Paradise Oceanfront 1999 Page: 6

3.0 EXPECTED LIFE Without knowing the actual thickness of the coating when the steel was initially galvanized it is not possible to calculate the exact corrosion rate at Surfers Paradise. However by using past experiences it is possible to predict the expected life of the hot dip galvanized products. The formula used in all calculations is as follows: ((initial coating thickness current coating thickness)/life in service) The 75NB pipe has an average reading today of 52.3µm. Because of the way this pipe is galvanized it would be highly unlikely that its initial coating thickness would have been much greater than what the standard called for (63µm). However if you were to be extremely conservative and you said 100µm was the initial coating thickness, than you would achieve a corrosion rate of 8µm/year ((100-52)/6). Average readings on pole nails galvanized in our yard on the 24/02/99 averaged 130µm. Therefore if we use 130µm as the original coating thickness on the pole nail tested at Surfers Paradise, you obtain a corrosion rate of 6µm/year ((130-115)/2.5). The average reading on the light pole tested at Surfers Paradise is well in excess of average readings on similar sections today. There are various reasons as to why the readings are so high, but if once again we err on the side of conservatism and say the initial coating thickness was 200µm, we obtain a corrosion rate of approximately 6µm/year ((200-128.7)/12). Therefore it is possible to conservatively state that the corrosion rate on completely exposed hot dip galvanized steelwork on the oceanfront at Surfers Paradise is approximately 6-8µm/year. Corrosion rates of internal galvanized steel at a similar location will obviously be different. A recent report completed by Industrial Galvanizers (conducted over five years) found that corrosion rates inside are in the vicinity of ten (10) times less than corrosion rates experienced outside. It can therefore be strongly supported that, providing atmospheric conditions remain relatively similar to those currently being experienced at Surfers Paradise, it would not be unreasonable to expect the galvanized coating (internal) to have a maintenance free life of at least thirty (30) years. Case Study: Surfers Paradise Oceanfront 1999 Page: 7