PRESTIGE OIL RECOVERY FROM THE SUNKEN PART OF THE WRECK Massimo Fontolan, Sonsub Ltd., Robin Galletti, SATE srl. Introduction

Similar documents
Fully Submersible Heavy Lift Vessel

LNG TANDEM OFFLOADING A KEY ENABLING TECHNOLOGY TO MAKE LNG PRODUCTION OFFSHORE HAPPEN

Field Development & Construction

Three Lines of Defence

BRINGING A NEW DIMENSION TO PIPELINE PIGGING. By: David Aitken, Aubin Group, UK

Saab Seaeye Cougar XT Compact

OIL IN NAVIGABLE WATERS REGULATIONS [L.N. 101 of 1968.] under sections 5 and 7. [22nd April, 1968] [Comrnencernent.]

Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico Field Development

Learn more at

Challenges in Ship Design to Maintain Thrusters inside Ship

GLS New Technology Rising to the Challenge of Subsea lifting. Subsea 2012 Paddy Collins

Geo-Vibro Corer

RIGID RISERS FOR TANKER FPSOs

Underwater Blanking Tools. Miko Plaster. Tanker Kit. Sea Chest Blanking. Pipe Plugs

RAMSTM. 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs

UNDERWATER SERVICES COMPANY PROFILE

A NEW APPROACH TO BUCKLING DETECTION IN OFFSHORE PIPELINE LAYING

1.0 PURPOSE AND NEED

NT09-21 Cruise Report SURUGA-BAY Cable Laying Experiment / VBCS Function Test

Underwater Blanking Tools

Chapter 2 Preparations for Tank Cleaning Work

Case studies from classes led by Dr. Ron Fulbright, University of South Carolina Upstate. IMPROVED BLOWOUT PREVENTER

TECHNICAL SPECIFICATION SCHILLING UHD III WORK CLASS ROV SYSTEM

CLIENT NAME: LOCATION: CALM BUOY INSPECTION:

NOBLE REV 02 FPSO MOORING SYSTEM INTEGRITY STUDY

Risers for Deepwater FPSO s

PLEM CONTROL SYSTEMS

PLEM CONTROL SYSTEMS

CONTACT US 24/7 T E THE NETHERLANDS / ROTTERDAM T SINGAPORE / SINGAPORE T

Centre of Excellence for Subsea Safety

Protection for Vessels Engaged in Servicing Submarine Cables

Multi-Purpose Workboats and Vessels. Marine Engineering and Construction. Salvage and Wreck Removal. Marine Consultancy Services

Unique Group employs over 450 people worldwide through its seven multi-site divisions: Survey Equipment. Marine & Subsea. Diving & Life Support

Polar Research Vessel Operational Requirements and Summary of Technical Studies

The SDS Skip. Subsea Deployment Systems Ltd.

Re-usable Riser and Flowline System for Deep Water Application. C. DIEUMEGARD SUBSEA ASIA - 11 th June 2008

THE NATURAL CHOICE. High end valves for the natural gas value chain. Inspired By Challenge

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland

GOVERNMENT GAZETTE REPUBLIC OF NAMIBIA

Fundamentals Of Petroleum Engineering PRODUCTION

Autonomous Shutdown Valve

Chapter 9: Sea operations

Dynamic Positioning: Method for Disaster Prevention and Risk Management

Point LaBarbe/McGulpin Point Response April 2 May 8, 2018 Regional Response Team 3 Meeting November, 2018

Design of Offshore Structures Prof. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras

DIFFERENT SOLUTIONS TO INSPECT PLATFORM RISERS. By R van Agthoven and H Quakkelsteijn, ApplusRTD, Rotterdam, The Netherlands

Isis Deployment. TMS and Live Boating. Inmartech08. Dave Turner Operations Co-ordinator.

ROV Development ROV Function. ROV Crew Navigation IRATECH SUB SYSTEMS 2010

BACKGROUND TO STUDY CASE

TP 11249E SHIP SAFETY STANDARD FOR IN-WATER SURVEYS

SIMOPRO Riser Replacement Novel method for replacement of pliant wave risers whilst continuing production on platform

DP Ice Model Test of Arctic Drillship

Product highlights Variable frequency and thrust

GUIDELINES FOR SURVEY OF OIL FLOATING STORAGE VESSELS FIXED AT ANCHORAGE

Development of a New Deep-Water Riser System. Daniel Karunakaran Subsea 7

A NEW DEEPWATER TANKER LOADING SYSTEM FOR WEST AFRICA

Allspeeds Ltd. Royal Works, Atlas St Clayton le Moors Accrington Lancashire England BB5 5LW. Tel +44 (0)

SLOP RECEPTION AND PROCESSING FACILITIES

INNOVATIVE MOORING SYSTEMS

S/Y MORSKI ZEKAN TECHNICAL INFORMATION

SBM Installer. Diving Support & Construction Vessel

0TMS Design and analysis of ITB ultra deep ROV

EMERGENCY CORE COOLING SYSTEM SIMPLIFICATION

An airbag was attached to the WCR tool and inflated to allow the WCR tool to rotate on the pipeline and free the diver.

Deep-water Pipelay Having the right tools

HYPERBARIC INTERVENTION IN SUBMARINE RESCUE SUT June 8 th Doug Austin Director, Asia Pacific

Fully Submersible Heavy Lift Vessel

ULMATEC LAUNCH AND RECOVERY SYSTEMS

Admiralty Inlet Pilot Tidal Project FERC No Appendix C. Derelict Gear Monitoring Plan

ACCESS the BLUE ECONOMY ALL OCEANS Engineering Ltd

Aquashield to Mitigate Water Ingress of Gas Pipes

Experience and Future Potential of the Oblique Icebreaker

Environmental Threats from Wrecks: The Point of View of the Environmental Authorities

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS

Charlottetown Marine Terminal Pipeline Decommissioning Project Description

Publishable Final Activity Report

REGULATION on life boats operated from land, No 123/1999 CHAPTER I. General provisions Article 1

We re Going Global. Vessel Loss Control. Technical Notes #36

The Baltic Diver ROV-Services

Risk Reduction in Offshore Decommissioning Chevron s Success in the Gulf of Mexico

Sustainable Installation & Maintenance Methods Keith McDermott Commercial Director for Tidal Energy Mike Wilson - Managing Director Mike Wilson

Aasta Hansteen. Operational Experiences. FFU Seminar 28 th January Tom-Erik Henriksen


Operating Procedure TITON SUBSEA BOLT TENSIONER

Pegasus Additional buoyancy for offshore helicopters

RESOLUTION MEPC.86(44) adopted on 13 March 2000 AMENDMENTS TO THE GUIDELINES FOR THE DEVELOPMENT OF SHIPBOARD OIL POLLUTION EMERGENCY PLANS

Internal riser inspections on FPSO storage & production facilities

VERTICAL BLADDER TANK

OFFSHORE SUPPORT VESSELS 2015

Site of yoke being supported by shore-side crane

From the Wellhead to the Tanker Offshore Production Systems. 28/03/2014 Instituto Superior Técnico

APPENDIX 4 STANDARD FORMAT FOR THE PROCEDURES AND ARRANGEMENTS MANUAL

BERMAD Fire Protection Hydraulic Control Valves

API Study on Detection and Recovery of Sunken Oil. API Study Objectives

Standard Operating Procedure

Section Decanting Response Tool

Yokosuka Cruise Report YK11-02

Captain Wellhead & Tree

Pilotage Directions 2017

XRAY GLIDER Underwater Video Cruise Plan May 21, 22, 23, 2007 R. G. Sproul

Transcription:

PRESTIGE OIL RECOVERY FROM THE SUNKEN PART OF THE WRECK Massimo Fontolan, Sonsub Ltd., Robin Galletti, SATE srl. Introduction This lecture deals with the equipment developed and the experience gained during the performance of operations carried out over a number of months during both the summer of 2003 and 2004 in water depths of nearly 4,000 meters, for the recovery of the fuel contained in the tanks of the Prestige tanker. Repsol YPF was appointed by the Spanish government to recover the fuel remaining in the wreck and subsequently selected Sonsub as the main contractor. The sinking In November 2002 the single-hull tanker Prestige sank at a distance of about 240 km (130 nautical miles) from the North West coast of Spain off Galicia, splitting in two halves 1.9 nautical miles apart. The bow came to rest in 3,830 metres water depth, while the stern came to rest in 3,565 metres water depth. The 1 st distress signal was sent on the 13 th November 2002, while the ship sank in two parts on 19 th November 2002 Initial activities Prior to the actual project for the recovery operations, a number of activities were performed. These included: During the month of December 2002 the Nautile mini submersible was engaged to perform preliminary survey and leak plugging of the wreck The Spanish Government appointed a Scientific Advisory Committee to advise as to the most suitable solutions to be adopted A large number of proposals, including one by Sonsub, were analysed by the Scientific Advisory Committee In 14 th February 2003 the Spanish Government entrusted Repsol YPF with the study of the technical viability, and following this with the management of the development of the necessary technology and the recovery operations. 3 Doability studies were assigned, two to Sonsub and one to Seal Engineering to develop the concepts considered the most interesting. These were to be completed in three months. Technical challenges The main technical challenges that were faced were: The 3,830 metres water depth. This was well beyond the state of the art for workclass ROVs, as well as all the required equipment. Previous wrecks that had required similar recovery (e.g. Erika) were in diver depths Viscosity of 5 million cst. This created a major challenge for the transfer of the oil both from the wreck to the surface, and for the transfer to shore The very tight schedule. During the 2003 operations, it was a requirement to design, construct and test the innovative solutions and equipment developed within September 2003. The contract for this was placed in May 2003 Selection of Sonsub Repsol YPF was appointed by the Spanish government and selected Sonsub as the main contractor, firstly for the doability studies, then for the innovative equipment development, then for the 2003 survey and verification operations, and finally for the 2004 full recovery. These contracts had the following schedule, which again illustrates the rapidity with which the activities had to be performed: March 2003, Sonsub selected to perform the doability studies on: o Shuttle recovery system o Coffin to confine the wreck April 2003, Sonsub selected to develop and construct: o Tapping tools o Extraction valves o Water injection system

May 2003, Sonsub selected to perform: o Survey of the wreck o Plugging of leaks o Verification testing of shuttle concept February 2004, Sonsub selected for complete recovery of a target 11,100 tonnes of oil Equipment developed The following main new items of equipment had to be developed, tested and employed for the recovery operations: Heavy work class ROVs for 4000 m water depth Measurement systems to define residual oil Beam sensors for positioning Tapping tools for 700 mm openings in tanks Anchored valve systems over openings Shuttles of 350 m 3 volume Transferral of oil from shuttles with core flow technology The ROV for up to 4000 metres Prior to this project, the INNOVATOR had a proven track record of performance and reliability operating on Deep-water Projects up to 3,000 m. The Prestige Project presented a ground breaking challenge which involved a modification program to upgrade all aspects of the Innovator ROV system to operate continuously in 4,000m of water. This was achieved using the existing 3000 m umbilical to the Tether Management System, and the 1200 m tether already developed for touch down monitoring of pipelines. The configuration was changed in that the tether was deployed vertically rather than horizontally. Due to the inherent capabilities that the INNOVATOR already had as well as its track record, the actual items of equipment that had to be modified to achieve the 4000 m water depth target were limited to the following principal systems: Buoyancy Manipulators Cameras and lights The testing of the ROVs was carried out as the first activity of the 2003 campaign, and was essetial to the feasibility of performing any of the operations on the wreck. Plugging of leaks Following the successful tests on the INNOVATOR ROVs, operations commenced on the survey of the wreck, following which the plugging of the leaks still present from the various tanks was carried out, using a number of different methods and tools. Remaining fuel on the wreck The oil measurement analyses performed during the 2003 campaign indicated that the remaining fuel oil could be estimated at: 13 000 Tm in the bow, located in port and starbord tanks, while the central tanks were effectively empty, and 700 Tm in the stern Polar Prince and FPSO ODIN on site The Polar Prince, a multi purpose DP2 class vessel operated by Sonsub, was adopted for both the 2003 and the 2004 operations. This vessel was able to deploy up to 3 INNOVATOR ROVs to full depth simultaneously, as well as all the necessary tapping tools, extraction valves and water injection systems. The MST/FSO Odin was the designated oil recovery vessel. She is a Multi-purpose Shuttle Tanker vessel with DP 3 dynamic positioning capabilities used as a Floating Storage and Offloading unit. She stocked the Prestige oil cargo once recovered to the surface and discharged from the shuttle tanks.

ROV performs beam sensor operations A deck structural ultra sonic beam detection and plate thickness system was used to map the location where the extraction valves were to be installed. Marking of hot tapping locations The locations for the installation of the tapping tool were then marked. Positioning of tapping tool Hop-tapping and extraction valves installations were performed on each of the four cargo tanks within the wreck bow section. Tapping tool The tool, which carries the extraction valve, is provided with an anchor bolt unit (6-off per system) to lock the valve to the deck before starting the trepanning operations. The centre of the tool carries the trepan tool for cutting 700mm holes. The system is operated by ROV through a dedicated IHPU Extraction valve The design of the extraction valves were particularly focused on safe recovery operations and each valve included failsafe shut -down systems as necessary to ensure that oil spills were avoided during the extraction process. Each valve includes a double gate system on top and bottom. The bottom gate is operated by ROV torque tool while the top one is either operated by ROV or can close automatically through a fuse-bolt system broken by the force exerted when the shuttle tank is completely filled with oil. Water injection system During the flow of oil from the cargo tanks to the shuttle tanks, it was necessary to ensure the free entry of water into the lower part of the tanks to replace the escaping oil. For this purpose, a dedicated water injection system was developed composing of water injection casings being installed via the Prestige deck hatches. Shuttle during construction Each shuttle tank is composed as follows: A main aluminium body with a diameter of approx 5.3m and an overall length of approx 23m, suitable to take up to a maximum of 350 m3 of oil; A bottom interface provided with an ROV operable door to allow flowing of the oil from the oil extraction valve into the shuttle tank; A top interface with two ROV operated gate valves system and a mechanical interface to the riser termination unit; A pull down winch located on the top section of the shuttle tank to allow connection and controlled final approach/release from the oil extraction valve; Suitable buoyancy installed externally to the shuttle tank to have it buoyant and allow controlled transportation through the water column by using the dedicated shuttle handling equipment. Shuttle towing Following completion of extraction valves installation, the shuttle tanks were towed offshore and prepared for installation. Shuttle deployment The shuttle tanks were designed to be continuously buoyant with the descent and recovery operation regulated and controlled by means of ballast chains. They are deployed to the Prestige wreck in approximately 4 hours time, connected to the extraction valve assembly with a secondary connection to a safety anchor dead weight.

Shuttle winch system Once deployed and connected to the pre-installed extraction valves, final positioning of the shuttle to enable safe oil extraction is achieved via the operation of an ROV operated mechanical winch which is an integral part of the shuttle. Oil filling The shuttle lower door assembly can then be opened again via ROV int ervention in preparation for the gravity entry of oil from the extraction valve. Oil flow through valve and Shuttle being filled During the extraction process the flow oil is controlled by ROV operation of the double gate extraction valve, with again failsafe systems to ensure overfilling is avoided. Shuttle recovery When the shuttle was approximately 60m WD, a riser assembly is lowered from the Odin and connected to the shuttle. Shuttle top interface to riser The top interface connects to the riser termination unit and has two ROV operated gate valves to permit the oil to be pumped into the riser Riser termination unit The riser/pump assembly system is made up of a number of different components. These are: An handling winch; A 6 flexible hose (riser); A riser termination unit provided with a pump and a mechanical interface allowing to dock and lock onto the shuttle tank top interface: A service hydraulic bundle to allow operation of the riser termination unit from the surface. Oil transfer to FPSO via Core Flow One problem faced during the engineering phase was the fuel discharging operation. This was a point of great concern because, given the very high oil viscosity, it initially seemed very difficult to pump the fuel out of the shuttle for a route of about 60m length from the shuttle riser connection to the Odin tank. The adopted innovative Core Flow solution proved highly successfully and a significant contribution to the overall success of the project. In effect water is pumped into the riser during the discharging in such a fashion as to form an outer sheath around the oil, giving birth to a so called core flow where the oil flows inside the water film. This latter functions as a lubricant, i.e. it reduces the friction losses between the highly viscous oil and the riser walls. With this method, by using a standard pump mounted at the bottom end of the riser it is possible to pump the oil up to the Odin tank. Bacteria injection The final phase of the project consisted of bioremediation nutrients injection. The rate at which micro organisms naturally present in the water and in the oil actively consume fuel-derived toxic compounds can be greatly increased by the addition of nutrients. This solution has been adopted for all tanks on the Prestige where some oil still remains after the operations. Prestige key dates The following dates summarise the project development: March to May 2003 Concept developed May to July 2003 equipment for operations in 3830 m designed, constructed and tested October 2003, first cargo of 100 tonnes recovered with shuttle concept December 2003 to April 2004, procedures and equipment for industrial recovery completed June to October 2004 complete remaining cargo of 13,400 tonnes of oil recovered

Sonsub Capabilities Sonsub has established itself as having: Unique deepwater intervention capability up to 4000 m water depth Marine spread resources, operating 8 vessels State of the art ROVs, with a total of 58 vehicles operated Underwater operations experience Innovative, project specific, equipment development Experience from the Prestige project Access to a worldwide group with such as Saipem that can support all its activities Conclusion The recovery of the fuel from the Prestige wreck, although considered by salvage experts as impossible at such a depth, was completed: within schedule within budget without any environmental pollution within any incidents or accidents