Connecting to the Dutch high-voltage grid. How TenneT can help you

Similar documents
Connecting wind energy THE OFFSHORE GRID IN THE NETHERLANDS

Offshore grid NL. Hollandse Kust (noord) & Hollandse Kust (west Alpha) General project introduction. 14 september 2018

Dutch offshore wind energy developments:

All TSOs of the Nordic Capacity Calculation Region Proposal for fallback procedures in accordance with Article 44 of Commission Regulation (EU)

Dutch tender system and future perspectives. Ir. F.C.W. (Frank) van Erp. Roadmap towards 4,500 MW offshore wind power in the Netherlands

Chapter 2.7 Bylaw sport governance and management

AB AMBER GRID RULES FOR NATURAL GAS TRANSMISSION SYSTEM BALANCING I. GENERAL PROVISIONS

AB AMBER GRID RULES FOR NATURAL GAS TRANSMISSION SYSTEM BALANCING I. GENERAL PROVISIONS

TOWARDS A BIKE-FRIENDLY CANADA A National Cycling Strategy Overview

Fact Sheet part of eex group

THE HORNS REV WIND FARM AND THE OPERATIONAL EXPERIENCE WITH THE WIND FARM MAIN CONTROLLER

Amendments to the International Convention on Maritime Search and Rescue of 27 April 1979

Please read this document of Terms and conditions carefully so that you fully understand our responsibilities and your commitments.

DOCKYARD PORT OF PLYMOUTH HARBOUR SAFETY PLAN. Issue 2 Jun 13

SERTP - 1 st Quarter Meeting

DEPARTMENT OF TRANSPORT

Tennis Victoria Club Guide Coach Relationship

Planning for tennis in your Local Government Area. A resource from Tennis Australia

District Cooling System at Kai Tak Development Content

Offshore wind in COWI

Changes to the Gas. (Safety and Measurement) Regulations. effective 1 July 2013

WINDSPEED project: Assessing future offshore grid infrastructure

London Organising Committee of the Olympic Games and Paralympic Games. 14 June 2010

Scoping analysis of the potential yield of the Hollandse Kust (noord) wind farm and the influence on the existing wind farms in the proximity

NS Fiets BV Management of bicycle parking at Dutch railway stations

Wind farm zone Borssele Project and Site Description 15 th December 2014

Review of Considerations and Requirements for Automated Enforcement

Attachment Pro Forma Pro Forma Regulatory Statements Revised proposed access arrangement information

Fishery Improvement Projects

Membership criteria for applicant impairment organisations (IOSDs)

Membership Guidelines

POLICY GUIDE. DataCore Cloud Service Provider Program (DCSPP) DCSPP OVERVIEW POLICY GUIDE INTRODUCTION PROGRAM MEMBERSHIP DCSPP AGGREGATORS

MSW Objective 1.1: Level of Service Standards To maintain the IMSWMS MSW collection system to meet or exceed established LOS standards.

EUROPEAN YOUTH OLYMPIC GAMES QUALIFICATION EVENT BID DOCUMENT 2014

Future of Collective Bargaining in Germany and the Importance of the recently introduced Minimum Wage Regulations

Dockless Cycle Share

Juni 2013 DI Bernhard Engleder,

MEMO CC: Summary. ESMWT16419: _MEM_RVO_HKZ floating LiDAR uncertainty_v3.docx 1/8

SPM 9541 November 2010 Aad Correljé

Information sheet swimming pools Page 1 of 8. Introduction INFORMATION SHEET LVD ADCO PUMPS AND OTHER ELECTRICAL APPLIANCES FOR MOBILE SWIMMING POOLS

ESB Ocean Energy Projects

Entry Level Requirements and Basic Introductory Course Outline for New Remotely Operated Vehicle (ROV) Personnel

A. PURPOSE B. BACKGROUND

Rig move Code of Practice (COP) and Scope of Work (SOW)

FACTSHEET on Bike sharing and public bicycle system

APPOINTMENT OF AUDIT SERVICES PROVIDER INVITATION TO TENDER

Economic Transformation and Recovery in Hong Kong and Singapore

MARKET RESEARCH OF EARTH GAS IN SLOVAKIA

Pressure Equipment Directive PED 2014/68/EU Commission's Working Group "Pressure"

Scoping analysis of the potential yield of the Hollandse Kust (zuid) wind farm sites and the influence on the existing wind farms in the proximity

Preliminary Survey Notification and Information for Fisheries Interests.

Distribution of fishing intensity of pulseand beam trawling in the North Sea. Marcel Machiels. IMARES rapport C146A/15

July 2016 JD No 6 Post No 6 JOB DESCRIPTION

International Scrum Master Certified (SMC TM )

Overview of market trends through 2005 Forecasts for 2006 and 2007

CYCLING SCOTLAND SCOTTISH CHARITY NO.SCO29760 CYCLE FRIENDLY EMPLOYER AWARD HANDBOOK

THE PEP Partnership on Cycling

Offshore Energy Årsmøde Offshore Wind Energy in Europe

Questions & Answers About the Operate within Operate within IROLs Standard

Thames Water Utilities Limited (TWUL) Wholesale Data logger installation for revenue meters - terms, conditions and guidance

BiboBlock. Fall arrest system for flat roofs

ITALIAN PV MARKET WORKSHOP ON PV INCENTIVE PROGRAMS

ASSESSMENT REPORT OF DIRECTIVE 2004/67/EC ON SECURITY OF GAS SUPPLY

EUSMUNC06 (SQA Unit Code - FG2W 04) Locate and avoid supply apparatus for Utilities Network Construction

The primary purpose of the TFF is to help promote a healthy farm tenanted sector in Scotland. It aims to fulfil this purpose by:

Pre Feasibility Study Report Citiwater Cleveland Bay Purification Plant

Efficiency Indicators of Railways in France

1 Licence Fees. National Paralympic Committee Presidents / Secretary General Via . Bonn, 30 October 2017 RM/IPC

BBL Reverse Flow project and implications for IP Bacton. Presentation to the UNC Transmission Workgroup 7 th June 2018

Representation Contract

RACING VICTORIA S EQUINE WELFARE STRATEGY

22 November 2016 OFFSHORE WIND EUROPE. Offshore wind smashes $100/MWh. Tom Harries

9. Parking Supporting Statement

Amendments to the International Convention on maritime search and rescue of 27 April Concluded London, 18 May 1998.

Products for Cryogenic Applications

Gas Interruptions. customer guide

Preliminary 2012 EAI Integrated Resource Plan (IRP) Action Plan

Urban Pathways. FACTSHEET on Bike sharing and public bicycle system 2017

Energy Outlook Global and Domestic Trends and Challenges. Dr. John Caldwell Director of Economics, EEI 1

CAVING REGISTRATION LEVELS AND ASSESSMENT REQUIREMENTS

EUROPEAN TRIATHLON UNION TRIATHLON CLUB EUROPEAN CHAMPIONSHIPS BID DOCUMENT BID DOCUMENTS ETU TRIATHLON CLUB EUROPEAN CHAMPIONSHIPS

The European Athletic Association (hereinafter European Athletics) shall promote a European Cross Country Championships every year.

The future of UK Gas Security. Findings of a survey of major energy users conducted on behalf of:

Report to COUNCIL for decision

Local Government Road Safety Summit - 9 April 2018

REPORT DECISION. The scour protection shall be designed to avoid progressive collapse of scour protection edges.

Customer Service and Operations Committee. Board Information Item III-A. March 12, 2015

Hollandse Kust (zuid) Wind resource assessment. 17 January 2017 Anthony Crockford

THE SCOTS COLLEGE Role Description Oval Greenkeeper

THE PLANNING AND. Transport and the law Integrated transport planning Strategies Responsibilities of local government and road controlling authorities

APPENDIX 2 PROPOSAL FOR REPLACEMENT FOR POOLE (DOLPHIN) LEISURE CENTRE FINAL SPECIFICATION

Section 2 Strategic Alignment. Contents

Alstom Ocean Energy Path towards Industrailsation. Ken Street 18 th April 2013

SEMINAR PRECRIMBET - GERMANY

Chief Operating Officer Approved by. Responsible Officer. Vice-Chancellor Approved and commenced 25 September, 2017 Review by September, 2020

Safety Monitor Requirements Revised. February 2018

Marine Renewables Industry Association. Marine Renewables Industry: Requirements for Oceanographic Measurements, Data Processing and Modelling

Qualification Purpose Statement: 1st4sport Level 3 Certificate in Coaching Judo (QCF)

Public data underlying the figures of Annual Report on the Results of Monitoring the Internal Electricity and Natural Gas Markets in 2016

HIPPO ENGLISH WITHOUT BORDERS

Transcription:

Connecting to the Dutch high-voltage grid How TenneT can help you 1

Introduction The energy transition is driving new dynamics in the energy sector Europe-wide. This has prompted numerous organisations to consider entering the Dutch energy market. This document outlines how TenneT can help you. As a regulated organisation, TenneT has been assigned clearly defined statutory duties and responsibilities. Against this backdrop, we are committed to serving you to the best of our ability. 2

COBRAcable (Denemarken) NorNed (Noorwegen) Contents 1. TenneT in a nutshell - About the TenneT grid - Statutory frameworks and legal status 2. Connecting to the TenneT grid - Which grid is best for your connection? - Location of your connection - Costs of a grid connection - Procedure and lead time 3. Obligations for connected parties - Requesting your own BRP or MRP recognition - Balance Responsible Parties (BRPs) - Metering Responsible Parties (MRPs) - About e-programmes and imbalance settlements 4. Doing business with TenneT - Digital portal MyTenneT - Contact details 4 4 4 5 5 6 6 7 Hollandse Kust (noord) Alpha Hollandse Kust (zuid) Alpha Hollandse Kust (zuid) Beta Westerlee BritNed (Groot-Brittannië) 9 Maasvlakte 9 9 Borssele Beta Borssele Alpha Borssele Bleiswijk Zandvliet (België) Beverwijk Diemen 6 Ens Geertruidenberg Arnhem Dodewaard Van Eyck (België) Maasbracht Zwolle Eemshaven Meeden 4 5 Hengelo G (D 7 Wesel (Duitsla 9 Rommerskirchen (Du Siersdorf (Duitsland) 3

1. TenneT in a nutshell Power plants Large industries Renewables In-feed (Extra) High-voltage grid Transmission/ distribution Consumers/ prosumers TenneT manages the high-voltage grid in the Netherlands and large parts of Germany. From the places where electricity is generated, we transmit it to end-users over more than 22,500 kilometres of high voltage lines and other electricity infrastructure. Our onshore and offshore cross-border connections form an indispensable link between electricity producers and consumers in the Netherlands and a large part of Germany. 99.99% availability The Dutch government has entrusted TenneT with the task of ensuring a reliable and safe electricity supply, now and in the years ahead. With availability already at 99.99%, the TenneT high- Import voltage grid is among the world s most reliable and safest. In part this is thanks to our good technical infrastructure, which we constantly maintain and expand. The near-continuous availability of our grid is also the result of careful balancing, i.e. keeping the demand for and supply of electricity in balance. Export Statutory frameworks and legal status Both in the Netherlands and in Germany, TenneT almost exclusively performs regulated tasks arising from our designation by law as a grid operator. These tasks are to: provide connection and transmission services provide system services facilitate the energy market In performing these tasks, we are bound by statutory frameworks, such as the Electricity Act 199 (Dutch only) and the Electricity Grid Code (Dutch only). In the Netherlands, our compliance with legislation is overseen by the Authority for Consumers & Markets (ACM); in Germany, the same is done by the Bundesnetzagentur (BNetzA), the Federal Network Agency. TenneT is wholly-owned by the State of the Netherlands. 4

COBRAcable (Denmark) NorNed (Norway) 2. Connecting to the TenneT grid Eemshaven Oudeschip Eemshaven Oost Robbenplaat Eemshaven Converterstation Eemshaven Weiwerd Bergum Vierverlaten Meeden Diele (Germany) Louwsmeer Zeyerveen Oudehaske Ens Hessenweg Which grid is best for your connection? The electricity grid in the Netherlands consists of the national high-voltage grid and several regional grids. TenneT manages the national high-voltage grid, which transmits electricity at 110, 150, 220 or 30 kv. The regional electricity grids, with voltages of 10, 20 and 50 kv, are managed by seven regional grid operators. For connection to the Dutch electricity grid, there is a similar distribution of tasks as the one that exists for managing the grids. TenneT provides connections with power greater than (approximately) 100 MW. Connections with power less than (approximately) 100 MW are usually provided by the relevant regional grid operator (refer to the overview of their coverage areas). TenneT and the regional grid operators cooperate with each other and will jointly assist you in finding the optimum solution for you in terms of grid engineering. Connection < 100 MW Contact the relevant regional grid operator (see overview) Connection > 100 MW TenneT, read this brochure for the conditions Borssele Beta Borssele Alpha Hollandse Kust (noord) Alpha Lelystad Zwolle Beverwijk Oostzaan Hengelo Vijfhuizen Diemen Hollandse Kust (zuid) Alpha Hollandse Kust (zuid) Beta Ede Arnhem Doetinchem Wateringen Bleiswijk Westerlee Waddinxveen Dodewaa rd BritNed (Great-Britain) Krimpen a /d IJssel Maasvlakte Wesel (Germany) Crayestein Simonshaven Geertruidenberg Boxmeer Eindhoven Borssele Weert 30 kv-verbinding/station/transformator op steel Van Eyck (Belgium) 30 kv-verbinding/station Maasbracht project Zandvliet (Belgium) 30 kv-interconnector Rommerskirchen (Germany) 30 kv-interconnector Sproject iersdorf (Germany) 30 kv-verbinding/station/transformator op steel 30 kv-verbinding/station project 30 kv-interconnector 30 kv-interconnector project 220 kv-verbinding/station/transformator op steel 220 kv interconnectoren 150 kv-verbinding/station/transformator op steel 110 kv-verbinding/station/transformator op steel 110 kv-verbinding project Onshore DC-verbinding project Zee interconnector Zee interconnector project Offshore verbinding Meeden 220 kv-verbinding/station/transformator op steel 220 kv interconnectoren 150 kv-verbinding/station/transformator op steel 110 kv-verbinding/station/transformator op steel 110 kv-verbinding project Onshore DC-verbinding project Zee interconnector Zee interconnector project Offshore verbinding Offshore verbinding project Offshore converterstation/station TenneT hoofdkantoor TenneT kantoor Productie eenheid Naam station 5 Aan deze kaart kunnen geen rechten worden ontleend. 30 juni 2017 Gronau (Germany)

Location of your connection TenneT can advise you on the engineering feasibility (or unfeasibility) of a connection at a certain place and will provide you with a rough planning and cost estimate. The connection will generally be to the nearest high-voltage substation where capacity is available or can be created. Together with you, TenneT can examine the possibilities. Decisions about locations of wind and solar farms are the responsibility of the Ministry of Economic Affairs and Climate Policy and the regional or local authorities (i.e. the provincial or municipal authority concerned). TenneT plays no role in these decisions. Costs of a grid connection Costs are obviously payable for a new grid connection. ACM issues guidelines for our pricing in the Electricity Tariff code (Dutch only). For installing a new connection, TenneT charges: the connection tariff (or initial investment costs). These costs vary, because every connection has to be customised. By way of indication, here is an approximate overview of the costs (201 price levels) of bays in an outdoor configuration, for the most frequently occurring connections: - 110 kv and 150 kv: approx. 1.5 million - 220 kv and 30 kv: approx. 3 million Once the connection is ready, you pay TenneT each month: the periodical connection charge. This annual charge covers the costs of preventive maintenance and, if necessary, complete or partial replacement of the connection; the transmission tariff, which covers TenneT s transmission of electricity. These costs consist of a fixed amount for costs unrelated to transmission (e.g. for invoicing, administrative work and similar) and a variable amount for transmission-related costs, charged as an amount per kilowatt. ACM sets the tariffs from year to year on the recommendation of TenneT. The transmission tariffs of TenneT are downloadable from the ACM website. If you wish to stop using your connection, TenneT will charge: a non-recurring contribution towards removing the connection. Again, these costs vary according to the type of connection. TenneT will charge you these costs in the event of the breaking or expiring of your connection and transmission agreement. 6

Procedure and lead time In the case of a new connection, TenneT will discuss the possibilities with you, and together we will explore, if necessary with the regional grid operator, what the best connection option is for your particular situation. We will then produce a technical plan for this, accompanied by an offer. After the order has been placed, TenneT will create the connection. As soon as the connection is delivered, it will be put into service. On average it takes 12 to 1 months to create a new connection to the high-voltage grid (in a situation where expansion of the grid is unnecessary). Soon the TenneT website contains more information about the steps in the connection process. The connection process 1: Information phase 2: Basic design phase 3: Construction phase This phase is used to hold talks with the customer. Based on the outcome, TenneT will make a quick scan so as to identify the substation to which the customer can be connected, provide a rough timeline for doing this and estimate the total costs. On request TenneT will also submit an offer for a basic design. The basic design will work out the request for a connection in greater detail, including a project description, planning aspects, licences and the technical properties of the connection. Subject to approval, this phase will end with signature of the construction agreement, in which the planning and the costs will be agreed. This phase formally starts at the time of signature of the construction agreement. In many cases, the call for tenders for installation of the connection will already have started, so as to enable the contract to be awarded as soon as the construction agreement has been signed. Throughout the entire construction phase, TenneT will hold regular talks with the customer, for example to close an Connection and Transport agreement. 7

3. Obligations for connected parties Connected parties are obliged by law to inform TenneT daily about their planned and their actual electricity production, consumption and transmission needs. This is necessary to maintain the balance in the high voltage grid: TenneT keeps electricity supply and demand in equilibrium, 24 hours a day, 365 days of the year. Connected parties may contractually assign these obligations to recognised parties if they wish. Requesting your own BRP or MRP recognation To keep supply and demand in balance in the Dutch grid, it is essential for TenneT to be in possession of reliable forecasts of the planned electricity production, consumption and transmission needs, and also reliable metering data of the actual production, consumption and transmission. These data are so important to the electricity grid s functioning that, under Dutch law, they may be issued only by organisations approved for that purpose ( recognised parties ). These organisations are called Balance Responsible Parties (BRPs) and Metering Responsible Parties (MRPs). If there is no such approval, the grid operator may stop managing or disable the connection concerned. As a connected party, you can ask TenneT for your own recognition as a BRP or MRP, or engage a recognised external party. The external parties are standalone, independent organisations: as the organisation that issues recognitions, TenneT has no financial and/or organisational ties with those parties. About e-programmes and imbalance settlements If the actual production and consumption of electricity do not properly correspond with the forecast, TenneT must intervene in order to maintain the balance in the grid, for example by deploying reserve or even emergency capacity. Therefore, there are financial consequences for a Balance Responsible Party (BRP) if its e-programme (i.e. the sum of the traded energy of all customers of a single BRP) fails to match the metered quantity. This is called the imbalance settlement. For the Netherlands as a whole, TenneT handles the financial resolution of imbalance settlements, via the recognised Balance Responsible Parties. Balance Responsible Parties (BRPs) Balance Responsible Parties must satisfy the requirements contained in documents including the System Code laid down by regulator ACM. As an organisation that issues recognitions, TenneT will check compliance with the admission requirements. On the TenneT website you will find a register of recognised parties with balance responsibility. If you want to apply for your own BRP recognition, you should contact the TenneT Customer Care Center at tennetccc@tennet.eu. We will assist you in completing the steps necessary to satisfy the BRP recognition criteria. Metering Responsible Parties (MRPs) Metering Responsible Parties must satisfy conditions including requirements contained in the Metering Code (Dutch only) laid down by the Authority for Consumers and Markets (ACM). As an organisation that issues recognitions, TenneT will check compliance with the requirements. On the TenneT website you will find a register of recognised parties with metering responsibility. If you want to apply for your own MRP recognition, you should contact the TenneT Customer Care Center at tennetccc@tennet.eu.

4. Doing business with TenneT As a TenneT client, you can maintain contact with us in different ways: face-to-face and digital. Face-to-face contacts will be with one of our customer relations managers. Each of these managers is responsible for a specific region of the country or area of attention. You can also contact us at any time via the TenneT Customer Care Center. Digital portal MyTenneT TenneT also operates an online portal called My TenneT to enable you to take care of TenneT matters quickly and conveniently. The digital dashboard consists of various elements for connected parties and for Balance Responsible Parties and Metering Responsible Parties. It is accessible in Dutch and English versions via the TenneT website. Using MyTenneT, you can perform 24 hours a day, 7 days a week such activities as: view your invoices view the details and status of your connection project(s) view the details of your connection(s) find the details of your BRP or MRP recognition view your financial guarantee manage your contact information find the details of your TenneT contact persons My TenneT is user-friendly. It s simply a question of click & go. A particularly useful feature is your ability to set which employees in your organisation are allowed certain privileges. As the My TenneT data are privacy-sensitive, this website has the highest level of security. More information TenneT helpt u graag uw plannen voor de Nederlandse energiemarkt te realiseren. Want to know more about possibilities for getting a connection to the TenneT grid? Contact one of our customer relations managers or the TenneT Customer Care Center at tennetccc@tennet.eu Want more information about recognition as a Balance Responsible Party or Metering Responsible Party? Contact the TenneT Customer Care Center at tennetccc@tennet.eu 9

TenneT TSO B.V. Postbus 71 600 AS Arnhem Nederland +31 (0)26 373 11 11 tennetccc@tennet.eu 10