MIRABAY PILOT PROJECT REPORT

Similar documents
Item 404 Driving Piling

PUSH PIER SYSTEMS STABILITY. SECURITY. INTEGRITY. Push Pier Systems PN #MBPPT

ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL

Civil Application Solutions

Perched Box Caisson Overview. January 2014

1) INTRODUCTION 2) THE UNFAIR ADVANTAGE

LoneStar Fiberglass Pools. Do-It-Yourself. Installation Manual

TYPES OF FOUNDATION. Superstructure. Substructure. Foundation

FLAGLER BEACH PIER POST INCIDENT SAFETY INSPECTION HURRICANE IRMA SEPTEMBER 15-17, 2017

3. Types of foundation

Construction Dewatering

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 7 OVER THE SNAKE RIVER DISTRICT 1 - PINE COUNTY

UNIT-I SOIL EXPLORATION

Risk Assessment and Mitigating Measures Regarding Pile Installation at EBS Biohub Jetty

TRENCH AND EXCAVATION COLLAPSE

Project Incorporation of Sea Level Rise City of Newport Beach Approach for Balboa Islands, City of Newport Beach, California

BENEFITS OF TIGHTER ANCHORING SYSTEMS

THE USE OF SPIN FIN PILES IN MASSACHUSETTS

Fig 2.17: Topographic model: snow-free area (Snow boundary = red) Contour interval of 1 m.

Keller Williams Realty Marco Island

Anchor Posts. *Patent Nos: Europe USA 12/372,965 2 ANCHOR SYSTEMS ANCHOR POSTS

Field Instruction. This instruction applies to Horizon Power employees and contractors involved in Horizon Power s underground projects.

Eilat 's artificial lagoons project on the Red Sea - Israel R. Raviv Ir. R. Raviv, Coastal Engineering Ltd., P.O. Box 7322, z/b 37072,

UNDERWATER BRIDGE INSPECTION REPORT METRO DISTRICT - ANOKA COUNTY

Field Instruction. This instruction applies to Horizon Power employees and contractors involved in Horizon Power s underground projects.

CENGRS GEOTECHNICA PVT. LTD. Job No Sheet No. 1

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 9 OVER THE BLUE EARTH RIVER DISTRICT 7 - BLUE EARTH COUNTY

We re good at what we do! Anywhere, TX SITE

STEEL TRENCH SHIELDS DW MODELS

SPEED SHORE MANUFACTURER S TABULATED DATA "MHS" MODELS. STEEL MANHOLE SHIELDS 4 Single Wall 4 Double Wall 4 Double Wall with Cut-Outs

PRO-ROD TM COILED ROD. Reduce Maintenance Increase Production Enhance Profit

GROUND IMPROVEMENT USING RAPID IMPACT COMPACTION

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 1 PINE COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO OVER THE STRAIGHT RIVER DISTRICT 6 - RICE COUNTY

PACIFIC SHORING, LLC ALUMINUM SHORING PRODUCTS HEAVY DUTY HYDRAULIC WALER RAIL SYSTEM. TABULATED DATA Effective August 25, 2015

PACIFIC SHORING, LLC ALUMINUM SHORING PRODUCTS PSH HEAVY DUTY HYDRAULIC WALER RAIL SYSTEM. TABULATED DATA Effective December 10, 2013

Composite Pilings. For A Lasting Foundation

DR.ING. CARLO AVANZINI PROFESSIONAL ENGINEER GRIP TEST REPORT NOVA SIRIA, ROLETTO, Premise

SPECIFICATION FOR CAISSON CONSTRUCTION

SPEED SHORE MANUFACTURER S TABULATED DATA MANGUARDS. October 31, 2005

OUTDOOR BACKSTOP WITH 5'-0" EXTENSION

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 101 OVER THE MINNESOTA RIVER DISTRICT 8 - REDWOOD COUNTY

Why Choose A Polymer Wall Swimming Pool?

STRUCTURAL STABILITY ASSESSMENT

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 4 - OTTER TAIL COUNTY

European Handball Federation TM EHF Beach Handball Commission

H8 Signs, Supports and Poles

STEEL TRENCH SHIELDS TUFF-LITE MODELS

Highbond anchor FHB II-A S

"STEEL FRAMED" ALUMINUM PANEL SHIELDS

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 4 - OTTER TAIL COUNTY

FLEXIBLE AND RELIABLE ANCHORING

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO B WABASHA STREET SOUTH BOUND (MASA 235 SB)

Student Manual. Lesson 4- Nuclear Density Testing. Version 1.0-3/09 4-1

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO MSAS 123 (2 ND AVE. SW) OVER THE CANNON RIVER CITY OF FARIBAULT, RICE COUNTY

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-7 SUB-STATION SY NO-225, NEAR RAYACHERLU VILLAGE

FITNESS, SAFETY & MEDICAL SUPPLIES

Single slide rail system Linear shoring

I would like to welcome Parish President VJ St. Pierre, Councilwoman Carolyn Schexnaydre and Councilman Terry Authement who are here.

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-1 SUB-STATION SY NO-44, NEAR KYATAGANACHERLU VILLAGE

TECHNICAL MEMORANDUM 002 EMORANNO. 001

Installaon Instrucons Supplement-High Ground Water Condions P-1

STATUS REPORT FOR THE SUBMERGED REEF BALL TM ARTIFICIAL REEF SUBMERGED BREAKWATER BEACH STABILIZATION PROJECT FOR THE GRAND CAYMAN MARRIOTT HOTEL

NCDOT S EXPERIENCE USING HYDRAULIC SETTLEMENT GAUGES. David L. Teague,P.E. NCDOT GEOTECHNICAL ENGINEERING UNIT

FIU Digital Commons. Florida International University. Henry O. Briceño Florida International University,

Safety Barrier System Acceptance Conditions SMART Steel Crash Cushion

computed using Equation 3-18 by setting the 2nd term equal to 0 and K A equal to K o and using the pressure distribution as shown in Figure 3-23.

Array Solutions 350 Gloria Rd Sunnyvale, TX Phone FAX

MODULAR ALUMINUM PANEL SHIELDS MAPS

BALL STOP INSTALLTION GUIDE

DIRECTIONAL DRILLING

ANNUAL INSPECTION BY A QUALIFIED PROFESSIONAL ENGINEER ALL CCR IMPOUNDMENTS CCR Rule Section (b)

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 4 OVER THE BEAVER RIVER ST. LOUIS COUNTY

AUTOMATIC DREDGING PROFILE AND CONTOUR CONTROL

Successful slope stabilization under severe conditions

HydroCourt Owner-Users Manual

Glass Steel, Inc. Fiberglass Composite Troughs

Annual CCR Landfill Inspection OML Existing Landfill OML Expansion Phase 1

Appendix J: Q1-Highway 35 Route Construction Plan

SOIL ANCHORS ETSAB/UPC J.Llorens - ETSAB/UPC PASSIVE ANCHORS - ANTECEDENTS

IN-PLACE DENSITY OF BITUMINOUS MIXES USING THE NUCLEAR MOISTURE-DENSITY GAUGE FOP FOR WAQTC TM 8

ENCYCLOPEDIA OF ANCHORING

BRUCE HAMMER SUCCESS STORY, BRIDGE PILING Model SGH-4719 Pile Hammer (Max. Energy 89.3 ton.m)

The New Anchor Post Product

TO RECEIVE the most benefit from a

indoor / outdoor INSTALLATION GUIDE

Green CCR Surface Impoundment

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 133 OVER A DITCH ST. LOUIS COUNTY

BARRIER OFFSET 0" A 6" 6" A 12" 12" A 26" A 26" 3A OR 4A L OR S * ** L OR S L OR S

Fehmarnbelt Fixed Link. Geotechnical Large Scale Testing

CONDITION ASSESSMENT REPORT

CASE STUDY OXLEY HIGHWAY SLIP STABILISATION

GATE INSTALLATION INSTRUCTIONS

USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY. Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1

INSTITUTE OF AERONAUTICAL ENGINEERING (Autonomous) Dundigal, Hyderabad

Components of a Barrage

R.GRANDORI- SELI spa 1

Reef Ball Designed Reefs Beaches, Turks and Caicos Final Report

Kennedy Bridge - Summary of Pier 6 Movement Records

TOWN of CHEEKTOWAGA Permit Application for Swimming Pools, Hot Tubs, or Personal Spas

Transcription:

MIRABAY PILOT PROJECT REPORT 9/25/2014 By: Ingenium, Inc./Carl A. Hazenberg, P.E. Seawalls along the MiraBay canal system started experiencing problems shortly after construction. Following the issues, litigation took place from 2007-2013. As a result of the litigation, recommendations for rock rip rap solutions to stabilize the existing seawalls issues were offered. The goal of pilot project was to examine other possible seawall stabilization solutions for the MiraBay Community. Three solutions were designed, constructed, loaded, and measured for movement on two vacant properties, 5607 Seagrass Pl and 5701 Tybee Island Dr.

MiraBay Pilot Project Report A S S E S S M E N T O F C O N S T R U C T E D O P T I O N S Option #1 Involved the use of a pair of rectangular fiberglass wale beams to support the lower part of the existing vinyl sheet pile. These wale beams were anchored back with a helical screw anchors, which were driven to a distance sufficient to develop the required holding capacity. Anchor installation torques and pulling capacities varied significantly due to the varying soil conditions. Rock rip rap was piled up at the base of the seawall to provide additional stabilization. Maximum slope of the rip rap is 2 horizontal to 1 vertical and has a horizontal impact of approximately 8 feet in front of the existing seawall. Typical Section of Option #1 Page 1

Photo of Option #1 from Front Option #2 Identical to Option #1, with the exception of a vinyl sheet pile knee wall. This was installed to intersect the toe of the rip rap and reduce the horizontal impact waterside of the wall. Sheets were driven 1 to 1.5 short of design depth due to refusal from hard soils. Despite this installation struggle, sufficient stability was still achieved. Horizontal impact for this option is approximately 4.5 feet and would cause less conflict with water craft than Option #1. Page 2

Typical Section of Option #2 Photo of Option #2 (front) Option #3 This involved driving of new FRP sheet pile directly in front of existing vinyl sheet pile seawall. New concrete cap was poured at the top to tie the new sheets in with the existing concrete cap and existing deadman system. New sheet piles were driven approximately 0.5 short of design penetration due to conflict of vibratory hammer with existing concrete cap. In spite of this conflict and slightly shorter sheet, sufficient stability was provided by the dense soils. Typical Section of Option #3 Page 3

Photo of Option #3 Option #4 A fourth option represents the proposed solution that resulted from past litigation. This option utilizes rock rip rap placed in front of the existing vinyl sheet pile seawall. The option does not incorporate an earth anchor, resulting in a larger rip rap footprint. Rock would be piled up at a greater elevation on the wall, and encroach waterside approximately 12 feet. Typical Section Option #4 Page 4

Observations during Construction Variability of site soils and the presence of compacted shell, presented unpredictability when driving of helical earth anchors. Contractor overtorqued and broke several anchor shafts while attempting to drive through lenses of compacted shell. At Seagrass site, contractor excavated to confirm the presence of shell layer where anchors were breaking. At the Tybee location one of the anchors had to be driven longer than the design length due to very loose soil. Installation of the anchor system proved to be the most difficult aspect of the project. Future design and construction should require anchor flexibility to account for these varying site conditions. Photo of Helical Earth Anchor Installation Furthermore, it is worth noting that existing tie-rods showed signs of corrosion beyond three feet behind the cap. This is unusual since most tie rods tend to corrode immediately behind the cap due to greater presence of oxygen at the ground surface. This may indicate that soils present are chemically aggressive for typical steel. However, no measurements were taken for section loss to determine whether significant structural loss will occur over the life of the structure. Anchors, rods, and hardware installed on the pilot project for options #1 and #2 were treated by a thermal diffusion galvanization for superior corrosion protection. Photo of corrosion on existing tie-rod Loading of Seawall Timber walls were constructed approximately 5 behind the existing seawall. The intent was to simulate segmental block retaining walls present throughout the community. These timber walls were filled with compacted sand and built 6 tall. This is 25% higher than the 4.75 high segmental block walls, and corresponds to a 25% greater surcharge being applied to the seawall than typically present. Next, water was pumped immediately within the backfill areas of both the retaining and seawalls to induce a full saturated hydraulic load. While impossible to know Page 5

the exact hydraulic loading of the existing seawall throughout the community during heavy rain events, I estimate the loading applied for the pilot project is 100% to 250% greater than the current seawall normally experiences. Also, due to lack of compaction of backfill and presence of voids, much of the water flowed parallel to the seawall and flowed out at drainage(weep) holes of the seawall on the adjacent property. Instrumentation Inclinometers and surveying were performed along the two properties to measure movement along the seawall. Initial baseline readings were taken prior to construction of the timber retaining wall. Subsequent measurements for movement were taken after each hydraulic loading. In summary, all of the options constructed for the pilot project showed little to no movement. The little movement noted in a few inclinometers, were likely due to voids present in the backfill soils. Survey information along the concrete cap and front of the sheet pile, showed no appreciable movement of the seawall and coincided with the results obtained from the inclinometers. Page 6

Conclusion Photo of inclinometer installation Photo of inclinometers in place (blue) The pilot project attempted to replicate the primary loading conditions of the existing seawall throughout the community. However, due to size and variation present within the community, it is impossible to account for all possible variables that impact the seawall. Therefore, it is vital that as sections of the seawall are stabilized throughout the community as part of the master seawall stabilization project, that each of these potential variables are recognized and considered for the implemented design. Nevertheless, construction of a taller timber retaining wall (6 feet) applied a significant greater load than the segmental block wall of 4.75 feet. Also, saturation of water behind the seawall and timber retaining wall applies loads far greater than of likely hydraulic loads present on site. All three options constructed and measured in the field appear to be acceptable in terms of sufficiency concerning structural capacity and movement. Page 7