ABU - Port of Barrow Island Cyclone Procedure

Similar documents
Gorgon Pilotage Passage Plan - PBG to Gorgon Marine Terminal Primary Route

Gorgon - Pilotage - Passage Plan - Gorgon Marine Terminal to PBG Alternative Route

Gorgon - Pilotage - Passage Plan - PBG to Gorgon Marine Terminal - Alternative Route

Port of Barrow Island - Local Knowledge Certificate Examination

Gorgon - Pilotage - Passage Plan Materials Offloading Facility (MOF) to PBG

PORT OF DAMPIER - CYCLONE RESPONSE PLAN

Gorgon - Pilotage - Passage Plan PBG to Materials Offloading Facility (MOF)

Forth Ports Limited. Port of Dundee. Rig Move Guidelines

PILOTAGE DIRECTIONS REVIEWED DECEMBER 2016

properly applied assessment in the use.1 landmarks.1 approved in-service of ECDIS is not experience The primary method of fixing required for those

Severe Weather Planning Information. Maritime Stakeholders

Wheatstone Marine Operations - Pilotage - Passage Plan - Onslow Port Limit to WMT

APC Operating Procedures Oil Tankers

ANNEX 2 RESOLUTION MEPC.124(53) Adopted on 22 July 2005 GUIDELINES FOR BALLAST WATER EXCHANGE (G6) THE MARINE ENVIRONMENT PROTECTION COMMITTEE,

HELSINKI COMMISSION HELCOM SAFE NAV 4/2014 Group of Experts on Safety of Navigation Fourth Meeting Helsinki, Finland, 4 February 2014

Delaware River Vessel Reporting System Mariners Advisory Committee For

IMO RESOLUTION A.960(23) Adopted 5 December 2003 (Agenda item 17)

Understanding of Meteorology. for. Handling LNG at Ports

WORK-REST REQUIREMENTS FOR PILOTS

AK-APC-NTV Operating Procedures for Cargo and Passenger Non Tank Vessels Transiting and Operating in Alaska Waters December 26, 2015

Transport Infrastructure Act 1994 Gladstone Ports Corporation. Port Notice 04/17 LNG Vessel Operating Parameters

WAK-APC-T Operating Procedures for Oil Tankers Transiting or Operating in Western Alaska Waters

Marine Guide for Ship Masters Contents

Code Of Practice For Towage Operations In The Port of St Helier (Towage Guidelines)

Whitstable Harbour Pilotage Information


Cargo pumps shall not be operated in excess of their designed maximum working parameters.

Pilotage Directions 2017

Cyclone And Severe Weather Marina Plan

Port of Port Elizabeth Information

National Standard for Commercial Vessels

PILOTAGE INFORMATION

ADANI PORTS & SEZ LTD. ++ MUNDRA PORT ++ GENERAL INFORMATION

TOWAGE GUIDELINES FOR THE GLOUCESTER HARBOUR. August 2018

DUBLIN PORT COMPANY PILOTAGE BYE-LAWS. 1st July Dublin Port Company Pilotage Bye-Laws, 1 st July 2018 Page 1

THE SYLLABUS FOR WRITTEN EXAMINATION PILOT'S FOURTH CLASS LICENCE (TEES AND HARTLEPOOL) AND

References: Manual Chapt. 9 ISO 9001 par.7 ISO par. 4 ISM Code par. 7; 8

NOTIFICATION AND STANDARD EVENT PLANNING RISK ASSESSMENT GUIDANCE NOTE

ANNEX 5 RESOLUTION MEPC.127(53) Adopted on 22 July 2005 GUIDELINES FOR BALLAST WATER MANAGEMENT AND DEVELOPMENT OF BALLAST WATER MANAGEMENT PLANS (G4)

Harbourmaster s Office Tamaki River. Navigation Safety Operating Requirements 2014

GENERAL LIMITATIONS AND RESTRICTIONS. LNGC Temporary Exemption (Effective August 21, 2018)

GUIDELINES FOR NAVIGATION UNDER THE CONFEDERATION BRIDGE

SECTION II NM 26/10 NAVIGATION PUBLICATIONS ALMANACS CORRECTIONS

RESOLUTION MEPC.288(71) (adopted on 7 July 2017) 2017 GUIDELINES FOR BALLAST WATER EXCHANGE (G6)

Harbourmaster s Office Operation of Superyacht in the Auckland Region Navigation Safety Operating Requirements

COAST GUARD ADVISORY NOTICE (CGAN ) To: Distribution Date: September 1, 2017

Forth Ports Limited. Port of Dundee. Marine Guidelines and Port Information

MARINER S GUIDE TO THE FORTH

Appendix 8-A Safety Zone Entry Check Lists

CARGO OPERATIONS (TANKER) MANUAL CH.05 BALLAST HANDLING. Rev. No: 2. Page: 1 of PURPOSE

All comments received will be taken into consideration before the proposed amendments are implemented.

GENERAL LIMITATIONS AND RESTRICTIONS. Draft Restrictions

Port Sections Guide Section 01

Uncontrolled document if printed.

IBF LIST of designated risk areas, with applicable benefits (as of 1 March 2018):

LOCAL NOTICE TO MARINERS

PORT INFO GENERAL BERTH INFO

Shell Australia. LPGC Cargo Operations - Guidance to LPGC Master/Ship Owners/Operators. Shell Australia. Marine OPS_PRE_ Report. Approved.

Chittagong, Bangladesh (Asia Region)

Minimum standard of competence for Master (STCW Reg II/2)

BMA INFORMATION BULLETIN No. 96

Marine Safety Information Bulletin COAST GUARD GUIDANCE FOR DEAD SHIP MOVEMENT IN SECTOR HONOLULU CAPTAIN OF THE PORT ZONE.

Dive Operations Plan for Personal Submersibles. Revision

NIGERIAN NOTICES TO MARINERS November 2017 EDITION PUBLISHED BY THE HYDROGRAPHIC OFFICE LAGOS. Notice 01 November 2017 Supplied Gratis

ABP South Wales Towage Guidelines. Date of issue: January ABP South Wales and River Usk Towage Guidelines

MARINE NOTICE MARINE NOTICE. Marine Notice 7/2012. Guidance on ECDIS for ships calling at Australian ports 7/2012

The Maritime Law Association of Australia and New Zealand

Introduction. Captain Michael Barnett Regional Harbour Master Cairns. Patrick Quirk General Manager Maritime Safety Queensland

Movement and traffic procedures

ABP South Wales and River Usk Towage Guidelines

Scientific Journal of Silesian University of Technology. Series Transport Zeszyty Naukowe Politechniki Śląskiej. Seria Transport

IBF LIST of warlike and high risk designations, with main applicable benefits (as of 16 th December 2015):

MARINE SAFETY REGULATION 2016 EXEMPTION ORDER. Clause 140(1)

Good Morning everyone, I will be talking this morning about the review and restructure of Cruise Whitsundays Safety Management Systems.

ANY OTHER BUSINESS. Guidelines for passenger ship tender operator. Submitted by Cruise Lines International Association (CLIA) SUMMARY

14 NOISE AND VIBRATION

EMERGENCY RESPONSE PROCEDURE - OPERATIONAL PORT OF PORT HEDLAND

COOPERATIVE VESSEL TRAFFIC SERVICE (CVTS) TAMPA BAY, FLORIDA

POS 02 VTS Guidelines

SOLAS requirements for nonpassenger ships 300 or above but less than 500 gross tonnage

ADMINISTRATIVE INSTRUCTION No. STCW-14 QUALIFICATION / CERTIFICATION REQUIRED FOR OPERATION OF A DOMESTIC VESSESL

NAVIGATION AND SEAMANSHIP Secure vessel at mooring, anchor, and berth

Preventing Damage to Harbour Facilities and. Ship Handling in Harbours PART 2 INDEX

1.0 PURPOSE 2.0 REFERENCES

ASSOCIATED BRITISH PORTS - LOWESTOFT

Local Notice to Mariners 02/2018

THE INEVITABLE RIPPLE 2ND OF APRIL TSUNAMI

Harbor Safety Committee HEAVY WEATHER (WX)

Tees & Hartlepool Pilotage Co. Ltd. Effective from 1 st January Pilotage Charges. Tees and Hartlepool Pilotage District

BWS ONLINE FORECASTING BERTH OPERATING SAFETY. Matthew R. O Halloran, Daphne Choong

ANCHORING. Small Craft Advisories (sustained winds 21 to 33 knots

TIDE TABLES FOR WARRENPOINT PORT (CARLINGFORD LOUGH) All times in GREENWICH MEANTIME HEIGHTS REFER TO CHART DATUM Chart Datum is mts.

SAILING INSTRUCTIONS BILLY RUN. Saturday 28 April The organising authority (OA) is the South of Perth Yacht Club

Outcome of the discussion with other HSSC WG on contribution to the MSP MSP development work

Vessel Code of Practice

EMERGENCY RESPONSE PLAN - PORT OF PORT HEDLAND

PORT OF PORT HEDLAND PORT USER GUIDELINES AND PROCEDURES

RESOLUTION MEPC.86(44) adopted on 13 March 2000 AMENDMENTS TO THE GUIDELINES FOR THE DEVELOPMENT OF SHIPBOARD OIL POLLUTION EMERGENCY PLANS

Two phases have been established for the classification of incidents to help in determining the appropriate course of action;

Commandant United States Coast Guard NAVIGATION AND VESSEL INSPECTION CIRCULAR NO. 2-97, CHANGE 1

Transcription:

ABU - Port of Barrow Island Cyclone Procedure Revision ID: 5.0 Revision Date: 17 February 2017 Next Revision Due: 17 February 2020 Information Sensitivity: Public

CONTROLLED DOCUMENT Document Information Document Number ABU-COP-0017 Revision 5.0 Document Author Brendon Findlater Department Owner Marine Operations Revision History Rev No. Description Date Prepared By Approved By 1.0 Approved for Use 07/09/12 Brendon Findlater David Acomb 2.0 Approved for Use - updated 17/09/13 Brendon Findlater Hamish Murray 3.0 Approved for Use ready for Operations 20/02/15 Brendon Findlater Brad Ryman 4.0 Annual review Approved for use 07/11/16 Chris Butler Dave Acomb 5.0 Minor changes Approved for use 17/02/17 Brendon Findlater Dave Acomb Approvals Author: Checked: Approved: Name Signature Date Brendon Findlater John Meade Dave Acomb bgji, Brendon Findlater lvnx, John Meade dacz, David Acomb Digitally signed by bgji, Brendon Findlater DN: ou=chevron PKI, cn=bgji, cn=brendon Findlater, email=brendon.findlater@chevron.com Date: 2017.02.19 15:00:23 +08'00' Digitally signed by lvnx, John Meade DN: ou=chevron PKI, cn=lvnx, cn=john Meade, email=lvnx@chevron.com Date: 2017.02.17 16:30:56 +08'00' Digitally signed by dacz, David Acomb DN: ou=chevron PKI, cn=dacz, cn=david Acomb, email=dave.acomb@chevron.com Date: 2017.02.23 10:01:47 +08'00' 2017 by Chevron Australia Pty Ltd This document contains proprietary information of Chevron Australia Pty Ltd. Any use of this document without express, prior, written permission from Chevron Australia Pty Ltd and/or its affiliates is prohibited. Revision ID: 5.0 Revision Date: 17 February 2017 Page ii

Contents 1.0 Introduction... 5 1.1 Purpose... 5 1.2 Scope... 5 1.3 Objectives... 5 1.4 Target Audience... 5 1.5 Acronyms and Abbreviations... 6 2.0 Procedure Overview... 7 2.1 Cyclone Threat Monitoring... 7 2.2 The Barrow Island Cyclone Coordination Group (CCG)... 7 2.3 Cyclone Threat Assessment... 7 2.4 Cyclone Contingency Plans... 8 2.5 Cyclone Season... 8 3.0 Cyclone Response... 9 3.1 Stage 1 Monitor... 9 3.2 Stage 2 Prepare... 10 3.2.1 Condensate Tanker... 10 3.2.2 Moss LNG Carrier... 10 3.2.3 Membrane LNG Carrier... 11 3.2.4 Oil Tanker WA Oil CBM... 11 3.3 Stage 3 Clear Port... 11 3.3.1 LNG Carriers and Tankers... 12 3.4 Stage 4 Port Closed... 12 3.5 Stage 5 Open Port... 12 3.6 Resumption of Normal Port Operations... 13 4.0 Roles, Responsibilities and Competencies... 14 5.0 Continual Improvement... 15 6.0 Acronyms and Abbreviations... 16 7.0 References... 17 Tables Table 1-1: Acronyms and Abbreviations... 6 Table 3-1: Port of Barrow Island Cyclone Response Stages... 9 Table 4-1: Roles, Responsibilities and Competencies... 14 Table 6-1: Acronyms and Abbreviations... 16 Table 7-1: References... 17 Appendices Appendix A Checklist Table for Vessels in Port... 18 Revision ID: 5.0 Revision Date: 17 February 2017 Page iii

Appendix Figures Appendix Figure A-1: Checklist Table for Vessels in Port... 18 Revision ID: 5.0 Revision Date: 17 February 2017 Page iv

1.0 Introduction The Port of Barrow Island is a declared State-owned Port under the Shipping and Pilotage Act 1967. The Western Australia Department of Transport Harbour Master for the Port of Barrow Island manages the Port remotely through his Port Operating Requirements and recognising the role of the on-site Port Captain. Chevron Australia Pty Ltd is the company currently undertaking activities at the Port of Barrow Island under an arrangement with the State of Western Australia and is the operator of the Port. The Port of Barrow Island Cyclone Procedure is intended to provide additional detail to supplement and interpret the Port Operating Requirements issued by the Harbour Master, and enable timely preparation of the Port in readiness for a tropical low or cyclone threatening to impact the Port of Barrow Island and mitigate any associated risks to personnel, the environment, Port infrastructure and assets (property). 1.1 Purpose The purpose of this Port of Barrow Island Cyclone Procedure is to ensure that: All vessels planning to put to sea and/or transit to the mainland have adequate time to clear the Port and adjacent coast, in order to avoid the impact of any approaching system. Smaller vessels working in the Port have sufficient time to take the necessary steps to enact their cyclone plans before the onset of adverse weather and sea conditions make this activity more hazardous than normal. The Port is clear of all trading vessels and the Port support vessels are secured in their cyclone rated pens prior to the impact or potential impact of a tropical low or cyclone. The Port Captain and Port Superintendent can provide clear guidance on the decision process about which marine operations can continue once a cyclone alert threat has been activated. 1.2 Scope The scope of this document includes: Cyclone contingency plan requirements for Port of Barrow Island users; Port of Barrow Island cyclone response stages; Resumptions of operations following a cyclone response. 1.3 Objectives The objectives of this document are to: Provide clarity on the triggers for cyclone response planning for the Port; Advise Port users of what actions will be taken at each stage of cyclone response; Detail what actions are required by the Port, post experiencing a cyclone event and prior to recommencing operations. 1.4 Target Audience This document is intended for use by: The Port Captain The Harbour Master Revision ID: 5.0 Revision Date: 17 February 2017 Page 5

Barrow Island Marine Operations Team Barrow Island Emergency/Cyclone Management personnel; Chevron Australia Emergency/Cyclone management personnel; Lifters and Lifting Co-ordinators; Barrow Island Gas Plant Ownership and Operating Agreement (BGPA) Operators; LNG, Condensate and Oil tanker operators; LNG, Condensate and Oil tanker personnel; Supply Chain Management and Shore Base Co-ordinators; Vessel Masters and management for vessels based at, visiting or trading to the Port of Barrow Island. 1.5 Acronyms and Abbreviations Table 1-1: Acronyms and Abbreviations Acronym/Abbreviation ABU BoM BWI CBM CCP CCG GMT Harbour Master nm Marine Operations Team Port Captain Port PIC SCM SSU Chevron Australia Business Unit Bureau of Meteorology The Port of Barrow Island Meaning Conventional Buoy Mooring operated by WA Oil Cyclone Contingency Plans Cyclone Coordination Group Gorgon Marine Terminal comprising of the LNG/Condensate Jetties East and West The Western Australia Department of Transport Harbour Master for the Port of Barrow Island Nautical miles The BWI Marine team headed by the Port Superintendent and including the Port Captain, Marine Pilots and Marine Communications Operators (MCO s) Means the individual or his/her delegate, recognised by the Western Australia Department of Transport as responsible for ensuring that the Port adheres to Commonwealth & State maritime legislation and the WA DoT Harbour master s representative for the Port of Barrow Island The Port of Barrow Island Person In Charge of the Barrow Island Gorgon Facility Supply Chain Management BoM Special Services Unit Revision ID: 5.0 Revision Date: 17 February 2017 Page 6

2.0 Procedure Overview 2.1 Cyclone Threat Monitoring The Port of Barrow Island receives daily weather forecasts from the Bureau of Meteorology - Special Services Unit (SSU). The forecasts will be distributed via electronic mail to vessel s masters and personnel engaged with operations within the Port of Barrow Island. During the cyclone season, cyclone and tropical low development forecasts are received on a daily basis. When there is potential for a system to develop, forecasts are broadcast at six hourly intervals. The forecast frequency is increased to three hourly updates following the named development of a tropical low or cyclonic system. 2.2 The Barrow Island Cyclone Coordination Group (CCG) When a forecast indicates that there is potential for a system to develop, the Cyclone Coordination Group (CCG) will convene to resolve any potential factors that may be required in the cyclone threat assessment. The group includes the Barrow Island PIC, Port of Barrow Island representative(s) (Port Captain and/or Port Superintendent) and Emergency Management, along with key operational personnel. A number of factors will influence the demobilisation of vessels including tug availability, pilot availability, vessel operational requirements, plant operational requirements, localised weather conditions and pilotage limitations (e.g. weather, tide, UKC). To assist in the decision making process at this meeting and prioritisation of vessel demobilisation, the Port of Barrow Island representative will source additional information from the following personnel: Pilot/Loadmaster and export vessel Master; Lifting Coordinator; Production Operations Superintendent; ABU Marine Supply Chain Management and Logistics; Tug and Pilot vessel operator. Information required from the above personnel will include: Details of their vessels that are operating in the Port; Vessel Masters intentions for demobilisation; Any limitations for sailing, e.g. loading status; stability & stress condition; machinery or propulsion limitations and any other considerations or limiting factors; Operational constraints on the Jetty and Production systems; Recommended demobilisation priority. 2.3 Cyclone Threat Assessment Key to the decision making process in declaring a cyclone alert are the time frames required to activate the resources and plans necessary to continue Port operations where possible, prepare vessels for departure, ensure the safety of personnel and ensure the safe-haven for BWI based marine assets. The decision to declare a cyclone alert state will be based on worst-case scenarios and, in most cases, will ensure adequate margins of safety are applied for all personnel and vessels operating at BWI. Revision ID: 5.0 Revision Date: 17 February 2017 Page 7

To that end, the decision to clear the Port may be made ahead of any of action directed by regulators or by other operators from this same region. 2.4 Cyclone Contingency Plans In accordance with the Port Information Guide and Barrow Island Terminal Regulations (approved by the Harbour Master s operating requirements), vessel operators shall ensure that each vessel operating in the Port has an appropriate cyclone contingency plan or procedure in place that is approved by the Port Captain, and that vessel Masters are familiar with the plan. Such plans or procedures should ensure that vessels have an adequate response time to proceed to sea or proceed to the adjacent coast in order to avoid the impact of any approaching cyclonic event. Prior to the commencement of cyclone season, marine contractors operating in the Port shall confirm to the Port Captain that they have reviewed their Cyclone Contingency Plans and provide a copy of any updated or revised procedures. 2.5 Cyclone Season Cyclone season in the northwest region of Australia is during the months between 1 November and 30 April. There are no safe havens or cyclone rated moorings located within the Port other than the tug pens, which are for exclusive use of the Gorgon Marine Terminal (GMT) tugs and pilot boat. Revision ID: 5.0 Revision Date: 17 February 2017 Page 8

3.0 Cyclone Response The Port of Barrow Island will employ a staged response to a cyclone threat; each vessel operator will comply with their own CCP, however where their staged response lags behind the BWI cyclone response, these procedures take precedence and will form the primary guidance for all vessels within the Port. Table 3-1: Port of Barrow Island Cyclone Response Stages Stage Key Action Description Monitor Prepare Clear Port Close Port Open Port Tropical cyclone or tropical low (System) has formed within 800nm (1500km). System approaches or develops within 400nm (750km) and is tracking towards Port, with potential for impact. System approaches or develops within 300nm (550km) and/or gale force winds are forecast to affect the Port within 24 hours. System approaches or develops within 200nm (370km) and/or gale force winds expected to affect the Port within 12 hours. Cyclone or threat of cyclone has passed damage assessment and recovery. In the event that vessels are required to proceed to sea for cyclone avoidance, the Gorgon Marine Terminal sequence for sailing Trading vessels will generally be, but not restricted to the following order: 1. Membrane LNG Carriers; 2. MOSS LNG Carriers; 3. Condensate/Crude Tankers. This sequence may vary depending on the vessel s loaded condition, weather conditions and the priorities determined by the BWI Marine Operations team in consultation with the Cyclone Coordination Group. IMPORTANT NOTICE: Consultation between the Port Captain and the Harbour Master will ensure appropriate staging is announced at the appropriate times and disseminated accordingly to vessels within or scheduled to call at the Port. The Master of a vessel within the Port retains responsibility for ensuring the safety of his/her personnel and of the vessel. Notwithstanding the vessel operator s own CCP, where a vessel operators staged response lags behind the BWI cyclone response, these procedures will take precedence and will form the primary guidance for all vessel Masters within the Port. 3.1 Stage 1 Monitor SSU Warnings indicate that a tropical cyclone or low has formed or moved within 800nm (1,500kms) of the Port of Barrow Island or that there is potential for a system to develop. The Port of Barrow Island cyclone response procedure will be implemented. The Port Captain will monitor the development of the system. Revision ID: 5.0 Revision Date: 17 February 2017 Page 9

The Port Captain will promulgate warnings and advice to Port users via electronic mail or by VHF or telephone where this is not possible. The Port Captain will plan for a possible Port closure. There are no restrictions on vessel movements. 3.2 Stage 2 Prepare A tropical cyclone or low is tracking towards the Port, is within 400nm (750kms) and has the potential to affect the Port of Barrow Island. After consultation with the Harbour Master, the Port Captain will promulgate warnings and advice to Port users via electronic mail or by VHF or telephone where this is not possible. Warning shall include estimated time for trigger of stage 3 and will be calculated within the Appendix A of this document. The Port of Barrow Island will commence preparations for a cyclone impact. The Port Captain will instruct Port users to commence implementing their cyclone plan or procedure, if they have not already done so. Timelines for Port departure need to be developed to ensure that preparations, which may require significant lead-time, are commenced at an appropriate point to ensure their completion before cyclonic conditions affect the Port of Barrow Island. The timelines should consider the following Time required for cargo / ballasting operations to be completed to the required safe stage where for the vessel is able to sail; Time required for GMT Marine Loading Arm (MLA) draining, purging and disconnection; Time required by vessels to reach safe waters ahead of approaching cyclones (by consultation with vessel Master). There are no restrictions on general vessel movements. Specific GMT/CBM vessel considerations are detailed in sub paragraphs below. During cargo loading, a minimum of one tug is to be on standby at the tug pen. Off duty tugs are to remain on call for an early departure scenario. Vessel movements or loadings are subject to the forecast weather conditions, localised weather, tide and tidal streams. 3.2.1 Condensate Tanker Decisions to berth Condensate Tankers will be made by the Port Captain and Port Superintendent in consultation with the CCG and based on the localised weather/tidal conditions and the forecasted potential for a system to impact the Port. There are no restrictions for Condensate Tankers loading at the GMT. Masters are to be kept informed of the situation and are to make early calculations to establish proposed timelines should the system continue to close in on the Port. 3.2.2 Moss LNG Carrier Decisions to berth Moss LNG Carriers will be made by the Port Captain and Port Superintendent in consultation with the CCG and based on the localised weather/tidal conditions and the forecasted potential for a system to impact the Port. Revision ID: 5.0 Revision Date: 17 February 2017 Page 10

LNG Carriers may continue loading provided the localised weather forecasts indicate a vessel can safely proceed to sea prior to the onset of Stage 4 and with the consultation and approval of the BWI Marine Operations Team. 3.2.3 Membrane LNG Carrier Decisions to berth Membrane Carriers will be made by the Port Captain and Port Superintendent in consultancy with the CCG and based on the localised weather/tidal conditions and the forecasted potential for a system to impact the Port. A Membrane carrier alongside at the declaration of Stage 2 will not proceed to load past the lower sloshing limit (in each tank) unless it can load or transfer sufficient cargo to safely achieve the upper sloshing limit before the forecast time for the declaration of Stage 3. A Membrane LNG carrier alongside that is loaded between lower and upper sloshing levels at the declaration of Stage 2 must carefully plan and understand timings to achieve safe sloshing limits in the event of early departure and before the declaration of Stage 3. Approval to load or continue loading must be in consultation with the BWI Marine Operations Team and will be granted by the Port Captain. 3.2.4 Oil Tanker WA Oil CBM Decisions to berth oil tankers at the WA Oil CBM will be made by the Port Captain in consultation with the CCG and WA Oil, based on the localised weather/tidal conditions and the forecasted potential for a system to impact the Port. There are no restrictions to movements or loadings. Masters are to be kept informed of the situation and developments. 3.3 Stage 3 Clear Port A tropical cyclone or low continues tracking towards the Port of Barrow Island, is within 300nm (550kms) and has the potential to impact the Port. Gale force winds are expected to affect the Port of Barrow Island within 24 hours. After consultation with the Harbour Master, the Port Captain will continue to promulgate warnings and advice to Port users via electronic mail or by VHF or telephone where this is not possible. The Port Captain will ensure that preparations are underway to ensure that the Port of Barrow Island and its anchorages will be cleared of all vessels at short notice. All trading vessels must ensure that they will be able to depart and be clear of the Port of Barrow Island Port limits at least 12 hours prior to the forecast onset of gale force winds. This timeframe is to ensure that all vessels have an adequate margin of safety to clear the coast and navigate open waters with a margin of safety and prior to the onset of cyclonic conditions. Sufficient tugs will remain on standby as required to assist a vessel to sail at short notice. Port users shall advise the Port Captain once they have completed their cyclone preparations and are ready to sail via electronic mail or by VHF or telephone where this is not possible. Trading vessels will not be permitted to arrive at the Port facilities unless prior permission is granted by the Port Captain. Permission for trading vessels to arrive will only be considered for extenuating circumstances i.e. emergencies, medical evacuation etc. Revision ID: 5.0 Revision Date: 17 February 2017 Page 11

3.3.1 LNG Carriers and Tankers At the declaration of Stage 3, tanker loading at the CBM or LNG carriers / Tankers alongside the GMT are to make all necessary preparations to be able to depart within 1-hours notice. Readiness to sail must take into consideration tidal heights, localised weather and current/tide as well as the time required to disconnect any loading arms in a safe and controlled manner. LNG Carriers or Tankers may also need time to prepare with respect to transferring cargo or ballast and ensure adequate stability criteria are met. Where one or more vessels remains alongside the GMT, the GMT assist tugs will remain on permanent standby in the tug pen to assist with the departure of vessels from the GMT at short notice. The Port Captain will require all LNG Carriers and Tankers to depart the Port prior to declaring Stage 4 of this Cyclone Procedure. 3.4 Stage 4 Port Closed A tropical cyclone or low continues tracking towards the Port of Barrow Island, is within 200nm (370kms) and is likely to impact the Port of Barrow Island. Gale force winds are expected to affect the Port of Barrow Island within 12 hours. Where possible, the Port Captain, in consultation with the Harbour Master will continue to promulgate warnings and advice to Port users via electronic mail or by VHF or telephone where this is not possible. The Port of Barrow Island will be closed to all vessels except those wishing to transit the Port of Barrow Island en-route to safer waters. The Port of Barrow Island will be closed to all commercial operations, including activities not associated with Chevron. 3.5 Stage 5 Open Port Resume Normal Operations with Caution Once the cyclone or threat of cyclone has passed and conditions permit, the Port of Barrow Island will be re-opened. This may be a phased process, dependent on wind and sea conditions, damage assessment and recovery. Note: If safe to do so, this stage can be initiated at any time through this process. The Port Captain, in consultation with the Harbour Master will notify users via electronic mail or by VHF or telephone where this is not possible, when the Port of Barrow Island has reopened Typically, the actual and forecast winds are to be less than gale force (approx 55km/h 30kts) with commensurate sea conditions before the Port of Barrow Island will be re-opened. In some circumstances, the resumption of normal operations may include restrictions. Examples could include the closure of berths or areas of caution/restriction for vessels to operate in. Any restrictions will be advised through the Open Port notification process. If there are no cautions/restrictions advised in the Open Port notification, operators can assume that all normal operations can be conducted. If there are any conditions warranting cautions/restrictions over an extended period of time (e.g. damage to Navigational Aids), the Port Captain will issue a relevant Marine Notice for the Port of Barrow Island. Operators and Masters will need to make their own assessment as to the suitability of prevailing conditions for the safety of their particular operation. Some restrictions on vessel berthing and movements may still be in force. Revision ID: 5.0 Revision Date: 17 February 2017 Page 12

3.6 Resumption of Normal Port Operations In order to ensure that facilities within the Port of Barrow Island are safe, prior to the resumption of operations, operators shall confirm to the Port Captain, in consultation with the Port Superintendent, that berths and any associated navigation aids and channels are serviceable and safe for operations. Of particular concern are: The ability to provide a safe berth; Fendering and mooring arrangements; Ship shore interface equipment; Charted depths alongside or in a berth are confirmed; Navigation aids location verified and lit; Channel charted dimensions (depth and width) confirmed. Any damage to berth facilities, channels or navigation aids shall be reported to the Port Captain as soon as possible, and where appropriate, warnings will be issued by the Port Captain via Marine Notice(s). Revision ID: 5.0 Revision Date: 17 February 2017 Page 13

4.0 Roles, Responsibilities and Competencies The following table outlines the roles, responsibilities and competencies associated with this document. Table 4-1: Roles, Responsibilities and Competencies Role Responsibilities Port Captain Vessel Masters/Operators The BWI Port Captain (PC) is responsible to the BWI Person In Charge (PIC) for the implementation of the Port Cyclone Procedure. The PC will consult with Port operators to ensure timely execution of these procedures to ensure that the Port is prepared for the onset of cyclonic conditions. The PC is to review these procedures annually, prior to commencement of cyclone season. The PC is also to ensure any changes to these procedures are communicated to the relevant stakeholders (e.g. Port Regulator and BWI Emergency Management Coordinator). After a cyclone event, the Port Captain and Port Superintendent will coordinate efforts to re-establish operations and confirm the Port is ready to be re-opened for normal operations. Consult with the Harbour Master and adjacent Ports (e.g. Dampier Port) of intentions to close/open Port The Master of a vessel within the Port retains responsibility for ensuring the safety of the vessel and those onboard. Notwithstanding the vessel operator s own cyclone procedures, the Master of a vessel operating within the Port shall be guided by these cyclone procedures. Revision ID: 5.0 Revision Date: 17 February 2017 Page 14

5.0 Continual Improvement This document is to be reviewed annually, prior to commencement of cyclone season. Revision ID: 5.0 Revision Date: 17 February 2017 Page 15

6.0 Acronyms and Abbreviations The below table defines the acronyms and abbreviations used in this document. Table 6-1: Acronyms and Abbreviations Acronym/Abbreviation ABU BoM BWI CBM CCP CCG GMT Harbour Master nm Marine Operations Team Port Captain Port PIC SCM SSU Chevron Australia Business Unit Bureau of Meteorology The Port of Barrow Island Definition Conventional Buoy Mooring operated by WA Oil Cyclone Contingency Plans Cyclone Coordination Group Gorgon Marine Terminal comprising of the LNG/Condensate Jetties East and West The Western Australia Department of Transport Harbour Master for the Port of Barrow Island Nautical miles The BWI Marine team headed by the Port Superintendent and including the Port Captain, Marine Pilots and Marine Communications Operators (MCO s) Means the individual or his/her delegate, recognised by the Western Australia Department of Transport as responsible for ensuring that the Port adheres to Commonwealth & State maritime legislation and the WA DoT Harbour master s representative for the Port of Barrow Island The Port of Barrow Island Person In Charge of the Barrow Island Gorgon Facility Supply Chain Management BoM Special Services Unit Revision ID: 5.0 Revision Date: 17 February 2017 Page 16

7.0 References The following documentation is either directly referenced in this document or is a recommended source of background information. Table 7-1: References Ref. No. Description Chevron ABU Marine Oil Pollution Plan Port Information Guide Barrow Island ABU - Cyclone Response Plan ABU Emergency Contact Directory HR Wallingford Tidal Stream Predictions Gorgon - Barrow Island Terminal Regulations Manual Document ID OE-11.01.101 ABU110700304 OE-11.01.112 OE-11.01.142 GOR-COP-0174 Revision ID: 5.0 Revision Date: 17 February 2017 Page 17

Appendix A Checklist Table for Vessels in Port Event Time Required Latest time for event Anticipated time for close Port N/A Vessel Type: LNG Carrier (Moss/Membrane) Time needed for to be in clear water from Port limits Time needed from berth to Port limits Vessel latest ETD Time required to complete loading, disconnect and prepare for sea Current time Earliest time vessel ready to sail Vessel Type: Tanker Time needed for to be in clear water from Port limits Time needed from berth to Port limits Vessel latest ETD Time required to complete loading, disconnect and prepare for sea Current time Earliest time vessel ready to sail Vessel Type: Logistics Time needed for to be in clear water from Port limits Time needed from berth to Port limits Vessel latest ETD Time required to complete loading, disconnect and prepare for sea Current time Earliest time vessel ready to sail Vessel Type: Other Time needed for to be in clear water from Port limits Time needed from berth to Port limits Vessel latest ETD Time required to complete loading, disconnect and prepare for sea Current time Earliest time vessel ready to sail Appendix Figure A-1: Checklist Table for Vessels in Port Revision ID: 5.0 Revision Date: 17 February 2017 Page 18