FERC Project 184 ECOLOGICAL RESOURCES COMMITTEE

Similar documents
FINAL Caples Lake Fisheries Management Plan. Version 4.0

Project 184 Preferred Canal Drainage Structure and Release Point Plan

M EMORANDUM O CTOBER 6, 201 6

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda

Project Award Presentation

Colusa Basin Drain Watershed Fish Stranding Tour Concept Paper Mike Hendrick and Brycen Swart NMFS

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda

Suitable Applications Check dams may be appropriate in the following situations: To promote sedimentation behind the dam.

Rugraw, LLC is the Applicant for FERC Project No Lassen Lodge Hydroelectric Project (LLHP).

Klickitat County Shoreline Master Program Update. Open House March 15, 2017

Washington State Fish Passage Barrier Removal Projects. Casey Kramer, PE WSDOT State Hydraulics Engineer

The California Department of Fish & Game (D.F.G.) files indicate Big. Sulphur Creek has historically been a problem area as far as fish are

Presented to Idaho Washington Aquifer Collaborative February 11, Spokane River Project License

Hydraulic Modeling to Aid TDG Abatement at Boundary and Cabinet Gorge Dams

Final Bull Trout Redd Monitoring Report for the Wallowa Falls Hydroelectric Project

107 FERC 61,282 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Big Spring Creek Habitat Enhancement and Fishery Management Plans

PROJECT OVERVIEW PROJECT AREA. FAHCE Fish Habitat Restoration Plan EIR

THREATENED, ENDANGERED, AND SENSITIVE SPECIES 2010 ANNUAL REPORT

Lewis River Hydroelectric Projects Settlement Agreement Aquatic Coordination Committee (ACC) Meeting Agenda

WFC 10 Wildlife Ecology & Conservation Nov. 29, Restoration Ecology: Rivers & Streams. Lisa Thompson. UC Cooperative Extension

Annual Report for Fiscal Year and Future Plans for the Tillamook Bay Watershed Council

TABLE OF CONTENTS 1.0 INTRODUCTION PLAN CERTIFICATION (B)(4) 1

Project Report for Marsh Creek and Albion River Instream Fish Barrier Removal Flynn Creek Road, CR 135, M.P. 8.1 and 8.3

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE SPORT FISHERIES MANAGEMENT

Youngs Creek Hydroelectric Project (FERC No. P 10359)

USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY. Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1

Interim Guidance Fish Presence Absence

Final Fish Salvage & Temporary Tailrace Barrier Report for the Wallowa Falls Hydroelectric Project Tailrace. (FERC No. P-308) December 18, 2017

LAKE TANEYCOMO 2011 ANNUAL LAKE REPORT

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT

Packwood Lake Intake Screen Velocity Test Report for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT

LAKE TANEYCOMO 2012 ANNUAL LAKE REPORT. Shane Bush Fisheries Management Biologist Missouri Department of Conservation Southwest Region

Mogollon Rim and White Mountains Angler Report

FERC Division of Dam Safety & Inspections

Environmental Review and Permitting for Wild Trout

Decommissioning Regulatory Process

Successful downstream passage of juvenile salmonids at a run-of-river hydro project in the Pacific Northwest

Conserving the Forests, Lakes and Streams of Northeast Michigan

Don Pedro Project Relicensing

145 FERC 62,070 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Sunset Beach Annexation LOCAL AGENCY FORMATION COMMISSION MEETING OCTOBER 11, 2017

Water in the Deschutes Who needs it?

BASS LAKE PLANNING UNIT Willow Creek Watershed

P U B L I C U T I L I T Y D I S T R I C T N O.

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By:

GRAND RAPIDS RESTORATION GRAND RAPIDS REVITALIZATION

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT

I would like to welcome Parish President VJ St. Pierre, Councilwoman Carolyn Schexnaydre and Councilman Terry Authement who are here.

CONNECTICUT RIVER WATERSHED COUNCIL The River Connects Us

STAFF REPORT. Meeting Date: March 1, 2017 Agenda Item 5B

Aliso Canyon Gas-Electric Coordination Phase 3 Draft Final Proposal

FCX Department of Occupational Health and Safety. Flagging and Barricading Guideline

[RR , XXXR0680R1, RR.R0336A1R.7WRMP0032] Notice of Availability of a Draft Environmental Impact Statement and Notice of

Notice of Proposed Rulemaking. Title 58. Recreation Part II. Fish and Boat Commission Chapter 65 Special Fishing Regulations.

Session C9: Priest Rapids Fish Bypass: A Case Study from Start to Finish

D.B. Wilson Station CCR Landfill

OPPORTUNITIES & CONSTRAINTS

Interlake Tunnel WRA Board Workshop. August 25, 2014

TEMPORARY TRAFFIC CONTROL GUIDELINES FOR HIGHWAY-RAIL GRADE CROSSINGS

Climate Change Adaptation and Stream Restoration. Jack Williams;

5B. Management of invasive species in the Cosumnes and Mokelumne River Basins

FINAL Fish Salvage Plan for the Wallowa Falls Hydroelectric Project Tailrace. (FERC No. P-308) April 19, 2017

Lockout Tagout Policy

APPENDIX D WINNETKA PARK DISTRICT EXHIBITS

Blue River Restoration Project William D. Linfield, P.E.

Valve Replacement: Using Non-Intrusive Isolation Technology to Minimize Production Downtime

Eastern Brook Trout. Roadmap to

TECHNICAL MEMORANDUM 002 EMORANNO. 001

I-105 ExpressLanes Project

Rhode Island Department of Environmental Management Division of Fish and Wildlife American Shad Habitat Plan for the Pawcatuck River

HEC 26 Aquatic Organism Passage Design Manual Evolution & Application

City of Birmingham AD HOC RAIL DISTRICT COMMITTEE Thursday, July 20, 2016 Meeting. City Commission Room 151 Martin St., Birmingham, Michigan

Blue River Restoration Project

JAP Additional Information Sheet

Additional Exercises 7.7 Form I Applications Using Rational Equations and Proportions

RECORD OF MEETING OF THE INTERNATIONAL KOOTENAY LAKE BOARD OF CONTROL ANNUAL MEETING AT BONNERS FERRY, IDAHO

Abundance of Steelhead and Coho Salmon in the Lagunitas Creek Drainage, Marin County, California

Climate change and the California golden trout

FISH PASSAGE IMPROVEMENT in California s Watersheds. Assessments & Recommendations by the Fish Passage Forum

Eastern Brook Trout Joint Venture Annual Report The Nature Conservancy 2013

Installation Manual. Model # SF-3W 9/16/03 REV 1. Arch Chemicals, Inc Lower River Road. P.O. Box 800 Charleston, TN PULSAR

P.O. Box 65 Hancock, Michigan USA fax

2016 Annual Work Plan

NEVADA DEPARTMENT OF WILDLIFE STATEWIDE FISHERIES MANAGEMENT

Scope of Work for Traffic Signal and Interconnect Design Services for Santa Rosa Road

Community Development and Recreation Committee. General Manager, Parks, Forestry and Recreation. P:\2015\Cluster A\PFR\CD AFS#22685

Klamath Lake Bull Trout

STRUCTURE S-65 PURPOSE SPILLWAY OPERATION

TO: FROM: SUBJECT: RECOMMENDATION REPORT SUMMARY BOARD AUTHORITY

Questions & Answers About the Operate within Operate within IROLs Standard

Historical Disturbances

Applying Engineering Solutions to the Science of Protection and Enhancement of Aquatic Environments. Bill Holman, P.E. Stanley Consultants

The Role of River Advisory Councils

FISH PASSAGE ON THE BRONX RIVER: A VISION OF THE BRONX RIVER ECOLOGICAL AND RESTORATION MANAGEMENT PLAN

PROTECTING LAND & RESTORING RIVERS FOR SALMON & STEELHEAD

Minnesota Department of Natural Resources Division of Fish and Wildlife Section of Fisheries. Stream Survey Report. Cold Spring Creek.

Transcription:

Kirkwood Meadows Public Utility District Community Services Building 33540 Loop Road Kirkwood, CA 95646 WELCOME AND INTRODUCTIONS July 10, 2008, Meeting Notes Doug Barber (FS), Peg Campbell (EID), Dan Corcoran (EID), Tom Cumpston, (EID), Brian Deason (EID), Dan Downey (EID), Jake Eymann (EID), Tom Henie (KMPUD), Alice Howard (ERC Member), Robert Hughes (DFG), Cheri Jaggers (EID), Kathy Jimenez (EID), Mitchell Katzel (Entrix), Susy Keirn (EID), Steve Lindstrom (EID), Bill Moler (URS), Jim Murphy (EID), Duane Nelson (FS), George Osborne (EID), Brad Pearson (League to Save Sierra Lakes (LSSL)), Mike Richter (Kirkwood Mountain Resort), Norm Rupp (LSSL), Steve Setoodeh (EID), Chris Shutes (ERC Member), Evelyn Spirou (Amador Co.), John Voss (Caples Lake Resort), Dick Wentzel (East Silver Lake Homeowner s Association), Conference phone attendees: Kim Morales (FS), Beth Paulson (FS), Jann Williams (FS) The Ecological Resources Committee (ERC) meeting convened at approximately 10:10 a.m. ADDITIONS TO AGENDA Henie asked to have two items added to the July 10, 2008, Agenda: (1) Fish Planting, and (2) Electricity. He presented these two items at the end of the meeting. APPROVAL OF MINUTES The notes of May 8, 2008, ERC meeting were approved after the following changes: Page 1, Paragraph 3, first sentence: Robert Hughes reported that his staff was changed to Robert Hughes reported that DFG staff. Page 3, paragraph 2, second sentence: It was noted that the FS has not formally approved, but the technical person did approve via email. was replaced with An email from a Forest Service Biologist was received and read to the group. The only changes to the May 20, 2008, conference call notes were grammatical in nature. WATER UPDATE Downey from EID handed out the El Dorado Irrigation District Project 184 SCADA Daily Reading Sheet giving an update on Lake Aloha, Echo Lake, Caples Lake, and Silver Lake storage. ERC Meeting Notes Page 1 of 5 July 10, 2008

The flows from Lake Aloha will be increased on July 11 to meet fish flow requirements. Lake Aloha did not spill this year, coming within 0.25 inch of the manual gate. Echo Lake is full and the water will not be used until after Labor Day. Caples Lake did not fill this year. The lake is at 19,000 acre feet. The flow will probably be cut back during the week of July 14 and flow increased from Lake Aloha to make up for Caples cut back. The lake level target for Caples at the end of July is 18,646 acre feet. Every effort will be made to keep the lake at that level or above. There will be outflow during August to bring Caples to the target of 14,376 acre feet at the end of August. Silver Lake water will not be used until September 15 th. The powerhouse has been shut down until August. DAM SAFETY ACTIVITIES A: Follow-up on Caples and Silver outlet works inspection Deason gave a PowerPoint presentation on the stream surveys of Caples Creek during the Caples Main Dam outlet works inspection on June 10 th and 11 th. The surveys were conducted to monitor for potential fish stranding or isolation during the ramp down. Two teams of four people monitored the upstream and downstream reach each day of the inspection. The results of this monitoring were that no stranding was observed anywhere in the 1.5 mile reach. Four isolation pools were observed in the low gradient reach, and from them, a total of five brook trout, ranging in size from 3-6 inches and ten trout fry (total length ~ 1 inch) were moved from isolation pools to the main channel. B: Review of Special Board Meeting Eymann gave a similar PowerPoint presentation to the ERC that he gave to the EID Board of Directors (Board) at the Special Board Meeting held July 1, 2008. The presentation described the background of the operational problems at Caples main dam, preliminary results of the inspections at Caples main dam and Silver Lake outlet works, and requested the Board to declare an emergency for purposes of exemption from competitive bidding requirements and CEQA review for the Caples Lake Dam outlet works and Silver Lake Dam outlet works. The presentation and an audio file of the July 1, 2008 Special Board Meeting is available on the Project 184 website at: http://www.project184.org/doc_lib/doc_lib.html Wentzel asked why the Silver Lake Dam was inspected without the ERC being notified beforehand. Eymann explained that EID was using best management practices. EID inspected Silver Lake Dam because they had the divers on hand with time to perform the task. There was no deviation from license requirements to facilitate the Silver Lake inspection, and therefore, there was no authorization required from the ERC. ERC Meeting Notes Page 2 of 5 July 10, 2008

C: Next Steps Since the July 1, 2008, Special Board Meeting, EID has hired an engineering consultant and a contractor to develop a plan to fix the problems at the two dams. EID indicated the best estimate at this time is that the repairs will take place in September 2009. Pearson noted that if the tower-works in Silver Lake are considered unstable and unsafe, then EID should block passage onto the tower. It was noted that the Caples Lake boat launch project is another major consideration and construction should coincide with the emergency repairs. CAPLES LAKE BOAT LAUNCH UPDATE Status: Barber (FS) said this project was now out to bid and all permits have been acquired except one. The one remaining is the encroachment permit from CalTrans. EID is working with FS to address CalTrans requirements. Litigation Update: EID is handling the litigation on the Caples Lake Boat Launch in-house. California Environmental Quality Act (CEQA) requires the parties have an early settlement conference, which occurred by telephone about 10 days ago. They have six issues about the project: 1) size of the project, 2) on-site presence (they would like 24/7), 3) location of the gate, 4) hours of operation (they want defined hours rather than dusk to dawn), 5) landscape plan, 6) lake tender s house to be retained. EID evaluated retention of the lake tender s house and determined it was not feasible due to its degraded condition and cost to repair. The only scheduled court date at the moment is a scheduling and status conference in September. CAPLES LAKE FEASIBILITY STUDY A report was given by consultants, Moler, geologist with URS, and Katzel with ENTRIX, who are working with EID to develop a feasibility study. Deason stated that the objective for today is to develop a preliminary plan of action with alternatives, and to get input from the ERC. This feasibility study is required by the license and is meant to evaluate whether the facilities can be modified to provide pulse flows up to 600 cfs to the Caples Creek natural channel. The ERC suggested including integration of the spillway channel restoration and stabilization into the screening criteria. In addition, the ERC suggested several alternatives to evaluate including: armoring spillway channel to accommodate additional ERC Meeting Notes Page 3 of 5 July 10, 2008

flow, slip-lining the outlet works, changing port size for existing slide gates, and adding slide gate control at upper sealed port. The ERC suggested that the feasibility study should not proceed until a number of milestones were achieved. First, the gates need to be repaired. Second, the discharge capacity needs to be confirmed. Third, data from the geomorphology monitoring, which is scheduled to begin in 2009, needs to be collected and evaluated in order to know what pulse flow discharge is actually required. Deason will write an extension request letter to the ERC and bring to the August 7, 2008, ERC meeting for review and approval. The letter will outline the current status of the Caples Feasibility Study, why EID has reached a point where it can not go further, outline milestones that need to happen in order for the study to move forward, and request an extension of time. OVERVIEW OF CAPLES LAKE ACTIVITIES 2008 2009 UPDATE Deason reviewed the updated Caples Lake Activities Overview chart that he reviewed at the May 8, 2008, ERC meeting. This chart lists the steps in each project relating to Caples Lake separately, and then how they are all interconnected. OTHER ITEMS, DISCUSSIONS Corcoran discussed two plans that are due by October: Oyster Creek Stabilization Caples Spillway Stabilization Each of these plans depends upon information obtained by implementation of the geomorphology monitoring scheduled to occur in 2009. Therefore, these two plans will require extensions. Jaggers explained that the Alternative Forecasting Tool is anticipated to be reviewed by the ERC in August and approved in September but that will not allow enough time for agency approval, so an extension letter will be needed. Henie reported on the Fish Enhancement Fund stocking program at Caples Lake and Silver Lake over the last 5 years. The first two years 40% trophy and 60% catchables were planted. In years three and four, the percentage of trophy fish went down to 34% and catchables increased; year five the trophies were decreased to 30%. Henie also discussed the concept of delivering electricity to the Kirkwood region and the KMPUD s role in possibly enhancing EID s electricity capabilities in the area. The area being considered is 2.5 by 4.5 miles and covers three counties. Generators are currently used for making electricity. Bringing in electricity from Sierra Pacific or PG&E is being explored. The plan is to go underground. Permitting is ready to start this year or next ERC Meeting Notes Page 4 of 5 July 10, 2008

year and construction the following year. The estimated project cost is approximately 30 to 45 million dollars. Regarding the ongoing water quality monitoring, Brian mentioned that a couple of the sampling dates were missed due to smoke/air quality, especially in some of the remote sites that require extensive hiking to access. ACTION ITEM Deason will write an extension request letter to ERC and bring to the August 7, 2008, ERC meeting for approval. The letter will outline the current status of the Caples Feasibility Study, why EID has reached a point where it can not go further, outline milestones that need to happen in order for the study to move forward, and request an extension from FERC. ADJOURNMENT Meeting was adjourned at 2:45 p.m. ERC Meeting Notes Page 5 of 5 July 10, 2008