NCDOT S EXPERIENCE USING HYDRAULIC SETTLEMENT GAUGES. David L. Teague,P.E. NCDOT GEOTECHNICAL ENGINEERING UNIT

Similar documents
Vented VW Settlement Cell

VW Liquid Settlement System VWLSS-200

Precision Liquid Settlement Array Manual

SOIL SETTLEMENT GAGE. Model SSG. Roctest Limited, All rights reserved.

SOIL SETTLEMENT GAGE Model SSG. Roctest Limited, 2005, All rights reserved.

Vibrating Wire Load Cell (3, 4, 5 And 6 Gauge Cells) User Manual

Vented VW Pressure Transducer

Item 404 Driving Piling

Instruction Manual Model 4615

SECTION PRESSURE TESTING OF PIPING

STRUCTURAL STABILITY ASSESSMENT

SafetyBuletin. Se ingoutriggerstopreventaccidents

_ pressure transducers. User Manual

Integral type Differential pressure flowmeter VNT Series

Step 1. PLANNING FOR THE INSTALLATION TOOLS REQUIRED

USER S MANUAL. Model TES-SM-30V

TA10A and TA10P Steam Tracing Temperature Control Valves Installation and Maintenance Instructions

Vibrating Wire Soil Extensometer. User Manual. Man /08/2016 P. Day Andy Small Chris Rasmussen

NEXT GENERATION FLEX FENCE

SSM0019 G. D Aerator SS6000 Liquid Settlement System Flushing Tool User s Manual

BTD52L Thermodynamic Steam Trap Installation and Maintenance Instructions

STEEL TRENCH SHIELDS DW MODELS

VACUUM TESTING PRECAST CONCRETE MANHOLES

GROUND IMPROVEMENT USING RAPID IMPACT COMPACTION

Tripod Setup Guide (M-TPx)

HOW TO DIG A TEST PIT

Figure 4.1 Schematic of Virginia Tech Calibration Chamber and Accessory Components

Flow Measurement. SITRANS F US Inline. Flowmeter SITRANS FUS880 (retrofit kit) 4/275. Overview

MODEL TES-GS-30V VIBRATING WIRE SETTLEMENT MEASUREMENT SYSTEM

IFTGS14 Ball Float Steam Trap ½" and ¾" with Integral Spiratec Sensor

Installation Instructions MODEL VSTI-A020 Tank Indicator Installation Model: VSTI-A020, Stainless Reverse Read System Versa Steel Inc. Guide Cables No

Instrumentation & Data Acquisition Systems

Level MEASUREMENT 1/2016

Preferred Instruments Danbury, CT USA

Electric and Natural Gas Safety Slide Show Presenter s Notes

-FRU FREEZE RESISTANT WATER VALVE COOLERS SYSTEM

INTERFELS RADIAL AND TANGENTIAL TOTAL PRESSURE CELLS

SPOOLER INSTRUCTIONS. STEP 12 If you are going to paint your posts, that should be done at this time.

TOTAL PRESSURE CELLS VWTPC-4000 I N S T R U C T I O N M A N U A L

SPEED SHORE MANUFACTURER S TABULATED DATA "MHS" MODELS. STEEL MANHOLE SHIELDS 4 Single Wall 4 Double Wall 4 Double Wall with Cut-Outs

DUAL-VORTEX SEPARATOR. Inspection and Maintenance Guide

Dry Hydrants. The installation of a non-pressurized pipe system into local water sources provides a ready means of supplying water to fire engines.

Pumping Systems for Landscaping Pumps, Controls and Accessories. Mark Snyder, PE

PTF4 Pivotrol Pump (patented) version Dual Mechanism - Pressure Powered Pump

Student Manual. Lesson 4- Nuclear Density Testing. Version 1.0-3/09 4-1

Spiratec ST14, ST16 and ST17 Sensor Chambers and sensors

FT16 Ball Float Steam Trap Installation and Maintenance Instructions

W A S T E W A T E R T R E A T M E N T S Y S T E M S

Buried Cable Installation Practices

TECHNICAL BENEFITS OF CJS / RAISE HSP. Technical Advantages

36E DSI and HSI Two-Stage Combination Gas Valve INSTALLATION INSTRUCTIONS

ACCURACY, PERFORMANCE, AND HANDLING OF OIL-FILLED DIGIQUARTZ PRESSURE INSTRUMENTATION

H-LEVEL _ H-LEVEL LIQUID LEVEL SYSTEM SETTLEMENT GAUGES

BARRIER OFFSET 0" A 6" 6" A 12" 12" A 26" A 26" 3A OR 4A L OR S * ** L OR S L OR S

Instrumentation & Data Acquisition Systems

VW Piezometers, VWP-3000 Series

Safe Excavation & Safety Watch Guidelines

APPENDIX A 'F' MANITOBA HYDRO REQUIREMENTS

Aluminum Sheeting Guide (ASG)

Recommendations for Marking Power Facilities

Recommendations for Marking Communication Facilities

SAFETY HANDBOOK. Working around. natural gas pipelines. works for your safety. Reprinted with permission from ATCO Gas.

CP10 Sensor Installation and Maintenance Instructions

ATS430 turbidity sensor Retractable insertion assembly

Practice Test FOR GAS POSITIONS APTITUDE BATTERY

EUROFLO CULVERT PIPE. Fittings / Pipes

"STEEL FRAMED" ALUMINUM PANEL SHIELDS

Recommendations for Marking Gas Facilities Using 3M EMS Electronic Markers

TEK-SUB 4800B. Submersible Level Transmitter. Flow Level Temperature Pressure Valves Analyzers Accessories TekValSys LEVEL

Bollard Light Installation Guidelines

Instant Garage 20' x 12' 3" x 8' 3"

36E DSI, HSI & Proven Pilot Two-Stage Combination Gas Valve INSTALLATION INSTRUCTIONS

Next Generation Quartz Pressure Gauges

ADVANTAGES DESCRIPTION MECHANICAL FITTINGS AND DIMENSIONS

Excavations and Trenches

WIND AND SNOW FENCES

POOL AND HOT TUB/SPA REGULATIONS A BUILDING PERMIT IS REQUIRED BEFORE THE INSTALLATION OF A POOL.

City of Crystal Lake Community Development Department

TOWER INSTALLATION MANUAL For A.R.E. Guyed Pipe Towers Short Towers 43, 64 and 85 feet tall

NEW VERSAFLOW CORIOLIS

then the work done is, if the force and the displacement are in opposite directions, then the work done is.

SITE TESTING STANDARDS FOR METHANE

This loop is filled with an antifreeze solution such

TD45 Thermodynamic Steam Trap Installation and Maintenance Instructions

AVS32 Stainless Steel Air Vent for Steam Systems Installation and Maintenance Instructions

Guide for Evaluating Your Hose Assembly Supplier

Pressure Measurement

Recirculating Coolers

Models 106-RF / 206-RF Rate of Flow Control Valve

Comments on Homework. Class 4 - Pressure. Atmospheric Pressure. Gauge vs. Absolute Pressure. 2. Gauge vs. Absolute Pressure. 1.

Technical Test Theory Crawler - Tractor/Dozer A34

SINGER MODEL 106/206-RPS-L&H

PERMANENT POOLS. Location

Total s Golden rules

INSTALLATION AND OPERATING INSTRUCTIONS

Construction Dewatering

! CAUTION! ! WARNING! General Information

TEST FOR STABILOMETER VALUE OF BITUMINOUS MIXTURES

OP CHECKLIST FOR 1D CONSOLIDATION LABORATORY TEST

T EK-COR 1100A Coriolis Mass Flowmeter

Transcription:

NCDOT S EXPERIENCE USING HYDRAULIC SETTLEMENT GAUGES David L. Teague,P.E. NCDOT GEOTECHNICAL ENGINEERING UNIT

OUTLINE Introduction Benefits of Hydraulic Settlement Gauges (HSG) over traditional settlement plates Installation procedures Calibration for temperature Case Study MSE Wall in Wayne County, NC (Currently under construction) Results compared to traditional settlement plates (for completed project)

INTRODUCTION What are Hydraulic Settlement Gauges?

Traditional Settlement Plate

BENEFITS OF HSG Once installed, HSG are completely buried, therefore they are not subject to being damaged or destroyed during fill placement and compaction efforts. Traditional settlement plates may be subject to surveyor error. Readings can be taken anytime by in-house personnel. A surveyor is not required. Readings can be taken during construction as well as anytime after construction. Traditional settlement plates must be removed before paving.

BENEFITS OF HSG (continued) Possible to remove HSG and re-use on another project (Save $$$) Roughly the same cost as Traditional Settlement plates. Traditional = $700-$800 each HSG = $900-$1000 each

INSTALLATION PROCEDURES Dig trench from cell location to reservoir. Ten feet of initial head is ideal. Minimum 2-3 ft. Length of cables can be up to 300 ft. Helpful if contractor is available with excavator to dig trench. Trench needs to be 18 inches deep.

INSTALLATION PROCEDURES Dig hole for settlement cell. Hole should be approximately 2 ft. square and 18 inches deep. Attach settlement cell to plate by either bolting vertically or attaching horizontally. Hand tamp the bottom of the hole so it is flat. Do not want any wobbling of the plate once it is placed in hole Place plate with attached cell into hole

INSTALLATION PROCEDURES Lay tubes flat and straight with minimum hills and valleys. Some, but not a lot of slack in tubes.

INSTALLATION PROCEDURES Backfill trench and cover cell with 2-3 ft. of soil Coil excess tubing and bury it. Connect tubes to reservoir. Must insulate tubes coming from out of ground to readout box from temperature. Can use pipe insulators with slotted PVC Pipe. Add fluid to top of reservoir. If any air is in the system it will affect results.

TAKING READINGS Readings are taken using a Vibrating Wire (VW) Data Recorder. VW Data Recorder records Temperature and Frequency. Temperature is used in the formula to convert frequency to pressure, then converted to elevation.

TAKING READINGS Check Dessicant chamber for saturation Fill Reservoir until fluid is up to overflow hole. Wait 10 minutes (if fluid is added). This allows any air bubbles to come to surface. Read Temperature Take Readings of VW Data every 30 seconds for 5 minutes. Frequency should be stable. If reservoir has the potential to settle, survey readings are needed. It is best to position reservoir on a post or other stationary position that is not subject to movement.

EXAMPLE CALIBRATION RECORD OF SETTLEMENT CELL

CONVERTING FREQUENCY TO PRESSURE To convert frequency reading to pressure in PSI, use the following formula: P = (A x F^2) + (B x F) + C Where P = pressure in PSI F = Frequency in hertz A, B, and C are determined by manufacturer at time of calibration

CONVERTING FREQUENCY TO PRESSURE To correct readings for temperature, use the following formula: Pt = P + ((Tcal Tnow) x m) Where Pt = corrected pressure Tcal = Temperature at calibration Tnow = Current temperature of cell (VW Data recorder). Not ambient temperature. m = sensitivity from manufacturers calibration

AIR TEMPERATURE CORRECTION We have noticed that on hot days the sensors seem to read about ¼ inch too low and on cold days the sensors read about ¼ inch too high. This is not satisfactory for our purposes. Therefore we started using an air temperature correction which works like this:

AIR TEMPERATURE CORRECTION Corrected temperature = ((Tu x St) + (Ta x AT)) / Tu +TA) Where Tu = Length of tubing underground St = Temperature measured at sensor (from data recorder) Ta = Length of tubing above ground AT = Air temperature at time of reading

AIR TEMPERATURE CORRECTION The idea is we want to find the average temperature of the tube, which is the weighted average of the buried tube and the exposed tube. So if the tube is 150 ft. long and 5 ft. is exposed, the ground temperature is 15 C and the air temperature is 30 C the corrected Temperature would be: ((145 x 15) + (5 x 30)) / (145 + 5) = 15.5 C

AIR TEMPERATURE CORRECTION The corrected temperature is then used in place of the sensor temperature when calculating settlement. So far, when using the air temperature correction, all the anomalies have disappeared.

CASE STUDY R-2554A Wayne County, NC Project consists of a 45 ft. high MSE Wall adjacent to a bridge. Subsurface conditions indicated that significant settlement would be possible. Traditional settlement plates were installed as part of the project contract. HSG were installed by NCDOT in-house forces as a pilot project to compare results.

PREDICTED SETTLEMENT UNDER WALL Maximum predicted settlement = 381 mm = 15 in.

Results from completed project Jacksonville Bypass, Onslow County, NC

Another benefit of HSG is that it is possible to retrieve the cells after settlement is complete. The cells can be reused on another project, saving money. Cells are placed inside outer PVC pipe. A cable is attached to the cell and run out to the end of the embankment or outside the wall footprint. When settlement is complete, the cell is pulled through the pipe and retrieved.

INSTALLATION COMPLETE

HSG Retrieval on Sunset Beach project

THE END Questions? Questions?