PROJECT BACKGROUND
STUDY CORRIDOR CASSELBERRY ELEMENTARY SCHOOL N SOUTH SEMINOLE MIDDLE SCHOOL CASSELBERRY GREENWAY TRAIL CANNON WAY TRAIL CROSSING Project Limits
STUDY CORRIDOR - SIGNALS CASSELBERRY ELEMENTARY SCHOOL N SOUTH SEMINOLE MIDDLE SCHOOL CASSELBERRY GREENWAY TRAIL CANNON WAY TRAIL CROSSING
STUDY CORRIDOR PEAK HOUR TRAFFIC VOLUMES SOUTH SEMINOLE MIDDLE SCHOOL CASSELBERRY ELEMENTARY SCHOOL N CASSELBERRY GREENWAY TRAIL CANNON WAY TRAIL CROSSING AM PM
STUDY CORRIDOR SIDEWALK GAPS CASSELBERRY ELEMENTARY SCHOOL N SOUTH SEMINOLE MIDDLE SCHOOL CASSELBERRY GREENWAY TRAIL Sidewalk Gaps (East Side) CANNON WAY TRAIL CROSSING
STUDY CORRIDOR AREAS OF FOCUS Midblock Crossing CASSELBERRY ELEMENTARY SCHOOL N SOUTH SEMINOLE MIDDLE SCHOOL Signalized Intersection Improvement Golf Cart Crossing Bike Lane Transition Signalized Intersection Improvement Improve Sidewalk, Bike Lane Addition Improve Trail Crossing CASSELBERRY GREENWAY TRAIL Signalized Intersection Improvement CANNON WAY TRAIL CROSSING
WALKING AUDIT FINDINGS
WALKING AUDIT Took place June 19 th, 2018 8:00 AM 8:30 AM Introduction o Safety Briefing o Logistics o Purpose 8:30 AM 11:30 AM Walk Corridor o North to Crystal Bowl Circle o South to Marigold Road o Cannon Way Crossing Time Permitting o Back to South Seminole Middle School 11:30 AM - 12:00 PM Debrief o Key Observations o Project Next Steps
ARC COLLECTOR MAPPING
Difficult to navigate OBSERVATIONS Cannon Way Trail Crossing
Missing Pedestrian Signals Missing Crosswalk OBSERVATIONS Winter Park Dr and Wilshire Dr (signal)
OBSERVATIONS Winter Park Dr from Wilshire Dr to Lilac Rd Missing East Side Sidewalk
Bike Lane West Side Only Flush Sidewalk West Side Only OBSERVATIONS Winter Park Dr from Marigold Rd to Queens Mirror Cir S
Possible Stormwater Project NB Sharrow to Bike Lane Left Turn Lane Golf Cart Crossing SB Bike Lane transition to curb OBSERVATIONS Winter Park Dr and Queens Mirror Cir S (Unsignalized)
OBSERVATIONS Queens Mirror Cir S (Unsignalized) to Queens Mirror Cir N (Spur) Overgrown Vegetation Crowding Sidewalk
QUEENS MIRROR CIR SPUR Crosswalk Improvement Approx. 90ft to cross
Extensive Utilities Natural Golf Cart Path Limited corner space OBSERVATIONS Winter Park and Queens Mirror (Signal)
Utilities Driveway Apron in Sidewalk Limited Parkway Area OBSERVATIONS Queens Mirror Cir N (Signal) to Crystal Bowl Cir S (Signal)
Yield and Signal Control Limited Refuge OBSERVATIONS Winter Park and Crystal Bowl (Signal) - 1
Sidewalk at Driveway Apron Irregular Pedestrian Activation Button OBSERVATIONS Winter Park and Crystal Bowl (Signal) - 2
PROPOSED IMPROVEMENT CONCEPTS
CANNON WAY TRAIL CROSSING Clarify Route using positive guidance Maximize use of existing crossing Enhance Crossing Visibility with the use of Rectangular Rapid Flash Beacons (RRFBs) Adjust guidewire to the west to accommodate widening
CANNON WAY TRAIL CROSSING Existing Crossing Proposed Concept
WILSHIRE DR INTERSECTION Recommended Upgrades Casselberry Styled Decorative Fluted Mast Arms One Arm per Pole ADA Accessible Pedestrian Actuation Push Buttons at each crosswalk. o Follow FDOT Design Standard 17784 Rehabilitate All Corners o Maintain Existing Curb and Drainage o Update Curb Ramps (ADAAG 4.7 Curb Ramps) https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-theada-standards/background/adaag#4.7 Consider Use of Leading Pedestrian Intervals
WILSHIRE DR INTERSECTION Existing Intersection Proposed Concept
WILSHIRE DR TO LILAC RD Sidewalk Connectivity Use available ROW on the east side of the roadway behind the utilities for an eight foot sidewalk New Curb Ramps o (ADAAG 4.7 Curb Ramps) https://www.access-board.gov/guidelines-and-standards/buildings-andsites/about-the-ada-standards/background/adaag#4.7
WILSHIRE DR TO LILAC RD Concept New 8ft Sidewalk
MARIGOLD ROAD TO QUEENS MIRROR CIR S Extending Greenway Trail North Use limited space in between the travelway and the utility poles to create a minimum 8ft wide shared path along the west side of the roadway Add curb to delineate the share use path Add open flumes to maintain existing drainage pattern Example Open Flume
MARIGOLD RD TO QUEENS MIRROR CIR S Existing Pathway New Curb and Gutter with Flumes New 8ft Sidewalk Proposed Concept
QUEENS MIRROR CIR S UNSIGNALIZED Golf Cart Crossings Manage convergence of sidewalk, bicycle lanes, and golf cars Improve visibility Introduce on-street bicycle facility
QUEENS MIRROR CIR S (UNSIGNALIZED) INTERSECTION Existing Intersection Proposed Concept
QUEENS MIRROR CIR SPUR Crosswalk Improvement Shorten Crosswalk by augmenting both curb lines Calm turning movements by redirecting the street to 90 degree angles No Southbound Right Turn Sign On Both Corners o Maintain Drainage o Update Curb Ramps (ADAAG 4.7 Curb Ramps) https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-theada-standards/background/adaag#4.7
QUEENS MIRROR CIR (SPUR) Existing Crosswalk Proposed Concept
QUEENS MIRROR CIR N SIGNALIZED Recommended Upgrades Casselberry Styled Decorative Fluted Mast Arms One Arm per Pole ADA Accessible Pedestrian Actuation Push Buttons at each crosswalk. o Follow FDOT Design Standard 17784 All Corners o Update Curb Ramps (ADAAG 4.7 Curb Ramps) https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-theada-standards/background/adaag#4.7 Continue Use of Exclusive Pedestrian Phase During School Hours
QUEENS MIRROR CIR N (SIGNAL) INTERSECTION Existing Intersection Proposed Concept
CRYSTAL BOWL CIR SIGNALIZED Recommended Upgrades Casselberry Styled Decorative Fluted Mast Arms One Arm per Pole ADA Accessible Pedestrian Actuation Push Buttons at each crosswalk. o Follow FDOT Design Standard 17784 All Corners o Update Curb Ramps (ADAAG 4.7 Curb Ramps) https://www.access-board.gov/guidelines-and-standards/buildings-and-sites/about-theada-standards/background/adaag#4.7 Continue Use Exclusive Pedestrian Phase
CRYSTAL BOWL CIR S (SIGNAL) INTERSECTION Existing Intersection Proposed Concept
ROLL PLOTS
WINTER PARK DRIVE South Section Concept
WINTER PARK DRIVE North Section Concept