INTERNAL LEAKAGE CHECK OF THE FLIGHT GMA

Similar documents
BLEED DOWN OF THE HIGH GMA PRESSURE

STANFORD UNIVERSITY W.W. HANSEN EXPERIMENTAL PHYSICS LABORATORY GRAVITY PROBE B, RELATIVITY GYROSCOPE EXPERIMENT STANFORD, CALIFORNIA

TEST OF GMA SPINUP ASSEMBLY PRESSURE SENSOR CALIBRATION

GMA SLEEP PROCEDURE AT VAFB

GDS OPERATING PROCEDURE

BLEED DOWN OF THE GMA HIGH PRESSURE AT VAFB

SCRUB LAUNCH RECOVERY PROCEDURE FOR THE GMA

CALIBRATING THE GMA PRESSURE SENSORS AND THE ECU ENGINEERING UNIT

GMA FUNCTIONAL TEST SETTING & TESTING OF SPIN UP PARAMETERS. P0586 REV -- 20, June 2000 GPB SCIENCE MISSION PROCEDURE

GMA TO SPACE VEHICLE PLUMBING HOOKUP

GMA VENT EXTENSION SERVICE PROCEDURE

GMA PREPARATION FOR E28 TESTING

STANFORD UNIVERSITY W.W. HANSEN EXPERIMENTAL PHYSICS LABORATORY GRAVITY PROBE B, RELATIVITY GYROSCOPE EXPERIMENT STANFORD, CALIFORNIA

DESIGN VERIFICATION AND QUALIFICATION OF NEW POPPET AND BUSHING ON GMA FLIGHT SOLENOID VALVES

GSE CAGING AND SPINUP BUFFER LINE INSTALLATION

Vibration/leak Test 2.5 and 6 Vatterfly Valves (3179 and 3223) spare units. GP-B Engineering Procedure P0761 Rev.-

GSE CAGING BALLAST SYSTEM INSTALLATION

(PTP) PROBE PRESSURE MEASUREMENT SYSTEM INSTALLATION AND LEAK CHECK PROCEDURE

LOW PRESSURE VOLTAGE BREAKDOWN TEST PROCEDURE FOR GSS FSU FLIGHT SPARE HVA BOARD October 28, P0938 Rev

PROCEDURE FOR THERMAL CYCLING IN LIQUID NITROGEN

CLEANLINESS TEST OF PROBE SPINUP EXHAUST LINES

CHECK READOUT LOOP CONTINUITY IN PROBE C

Proton Monitor Thermal Vacuum Test Procedure GP-B P0635

GUARD TANK PRESSURIZATION FOR TRANSPORT

PROBE-C CAGING VALVE INSTALLATION

(PTP) REMOVE PROBE SPINUP GAS/VAC. LINES (HORIZ.)

ASSEMBLY OF GAS FLOW HARDWARE INTO SM GMA

IEP SENSOR BRACKET CHECKOUT AND VERIFICATION. This is a non-hazardous test.

POROUS PLUG CHARACTERIZATION TEST

PROCEDURE TO MEASURE READOUT LOOP RESISTANCE

PREPARE FOR CRYO OPS FOLLOWING TRANSPORT TO B1610 To be performed at Vandenberg Air Force Base building 1610

Proto-qual Vibration Test Procedure 2.5 and 6 Vacuum Valves (3179 and 3223) Retest of Flight Spare Valves. GP-B P0735 Rev.-

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Spacecraft Battery Magnetic Field Survey

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Prepare Payload for Mass/CG Measurements and Condition Payload During Spin Balance Test

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR DISCONNECT MAIN TANK VENT LINE FROM GAS MODULE MAIN TANK SUBATMOSPHERIC

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Install Fill Line Burst Disk on SMD

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Install Fill Line Relief Assembly on SMD

Pressurize Well to One Atmosphere with Probe Installed

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR REGULATE GUARD TANK PRESSURE

DRAFT. Operating Procedures for the NPDGamma Liquid Hydrogen Target in TA-53, Building MPF-35

NPDGamma LH2 Target OJT Lesson Plan: Senior Operator for the NPDGamma LH2 Target Operators

SEMASPEC Test Method for Determination of Cycle Life of Automatic Valves for Gas Distribution System Components

D R A F T. Operating Procedures for the NPDGamma Liquid Hydrogen Target at the BL 13. Version 1.00

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR STOP PUMPING ON SMD VACUUM SHELL / DISCONNECT VACUUM MODULE

AcornVac Vacuum Plumbing Systems - Trouble Shooting Guide

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR CONNECT VACUUM MODULE / PUMP ON SMD VACUUM SHELL

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR

CERTIFICATION OF THE TEMPERATURE MONITOR AND ALARM

Annual Inspection and Calibration Checklist VAF Oilcon MK-6(M) MEPC.108(49) Page 1 of 5

Reduce Liquid Level in Main Tank- Liquid at NBP To be performed at Vandenberg Air Force Base building 1610

HYDROSTATIC LEAK TEST PROCEDURE

STANDARD OPERATING PROCEDURES

R I T. Title: STS ASE Semiconductor & Microsystems Fabrication Laboratory Revision: Original Rev Date: 01/21/ SCOPE 2 REFERENCE DOCUMENTS

OPERATION OF LIQUID PARTICLE COUNTER. GP-B P0045 Rev -

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Configure SMD for Transport to SLC-2W To be performed at Vandenberg Air Force Base building 1610

E2.14 Control of Hazardous Energy. Effective Date: 03/01/2018

LAKOS Waterworks. PWC Series Sand Separators. Installation & Operation Manual LS-829 (10/12)

CO 2. (R744) Service Station Presentation. Contents. Goals Basic functions Specification Recovery R477 Vacuum Charge Safety Other features Prototype

OPERATING INSTRUCTIONS

Inert Air (N2) Systems Manual

Constant Pressure Inlet (CCN) Operator Manual

Piped Air SCBA Refilling System Standard

PUMP DOWN MAIN TANK TO SUBATMOSPHERIC CONDITION

The latest automotive systems require innovative leak test methods and fixturing.

Significant Change to Dairy Heat Treatment Equipment and Systems

INSTRUCTION MANUAL. FLOW CONTROL DRAWERS MANUAL / PLC CONTROL SERIES Model Version Perma Pure LLC Tel:

Early evap monitors. Photo courtesy Toyota Motor Sales, U.S.A., Inc.; diagram courtesy University of Toyota

Gas Cabinets and Valve Manifold Boxes: Applying CGA G13- Rev 2015 to Gas Delivery Equipment

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR

American Society of Sanitary Engineering PRODUCT (SEAL) LISTING PROGRAM

Hazards associated with the gas system and how to mitigate them

Compiled by: B Beard. Approved by: SH Carstens. Description of requirements and procedures for compact provers to be used as verification standards.

Ag Leader Technology Proportional Valve

The Discussion of this exercise covers the following points:

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR MAIN TANK SUBATMOSPHERIC FILL FROM NBP SUPPLY DEWAR GUARD TANK PRECOOL

Lockout/Tagout Training Overview. Safety Fest 2013

GRAVITY PROBE B PROCEDURE FOR SCIENCE MISSION DEWAR. Upright SMD (Rotate from Horizontal to Vertical Orientation)

HumiSys HF High Flow RH Generator

American Society of Sanitary Engineering PRODUCT (SEAL) LISTING PROGRAM

Exercise 5-2. Bubblers EXERCISE OBJECTIVE DISCUSSION OUTLINE. Bubblers DISCUSSION. Learn to measure the level in a vessel using a bubbler.

ASSE International Product (Seal) Listing Program. ASSE Performance Requirements for Air Valve and Vent Inflow Preventer

Drift-Chamber Gas System Controls Development for the CEBAF Large Acceptance Spectrometer

(PTP) Un-vented Rate of Temperature Rise Using Guard Tank

PERFORMANCE SPECIFICATION PROPELLANT, HYDROGEN

Vacuum Pumpdown and Venting Procedure, CRaTER Thermal Vacuum System. Dwg. No

NGP-250/500 Nitrogen Generator Quick Start Guide

OPERATION MANUAL BFX-2

FE Petro vs. New Red Jacket Competitive Comparison

IMPROVED XENON LOADING EQUIPMENT WITH LOADING CAPACITY UP TO 1200 KG FOR ALPHABUS

Every things under control High-Integrity Pressure Protection System (HIPPS)

MASSACHUSETTS STATE POLICE CRIME LABORATORY. Certificate of Calibration Procedure for the Alcotest 9510

Proper Pump Installation Practices

STANDARD OPERATING PROCEDURES

Canadian Light Source Inc. Vacuum Component Leak Test Technical Procedure

Energy Control Procedures Lockout/Tagout 29 CFR

LESER Deutschland Standard Functional Tightness Test (Cryo) Content

Instructions for Assembly, Installation, and Operation of the Gas Addition Kit Accessory with the CEM Discover Systems

API MPMS Chapter 17.6 Guidelines for Determining the Fullness of Pipelines between Vessels and Shore Tanks

1020 Industrial Drive, Orlinda, TN fax

NO SMOKING WHEN OXYGEN IS IN USE.

Transcription:

SU/GP-B P0931 Rev A STANFORD UNIVERSITY W.W. HANSEN EXPERIMENTAL PHYSICS LABORATORY GRAVITY PROBE B, RELATIVITY GYROSCOPE EXPERIMENT STANFORD, CALIFORNIA 94305-4085 INTERNAL LEAKAGE CHECK OF THE FLIGHT GMA GP-B ENGINEERING PROCEDURE P0931 Rev A 13 September, 2002 PREPARED R. Stephenson, GMA Engineer Date APPROVED C. Gray, GMA REE Date APPROVED D. Ross, Quality Assurance Date APPROVED R. Brumley, Hardware Manager Date

REVISION RECORD REVISION ECO PAGES DATE A 1384 Added Table and pressure sensor check after 9/13/02 step 3.5 Made provisions for the GMA being connected to the GAF, Space vehicle, or free standing. Changed order of some steps to match the "wait" steps in the CSTOL script. Moved GDS connection. This means that the GDS is only connected if necessary. Removed "Put valves into flight configuration" from end of procedure. TABLE OF CONTENTS A SCOPE 4 B SAFETY 4 C QUALITY ASSURANCE 4 C.1 QA Notification 4 C.2 Red-line Authority 4 C.3 Discrepancies 4 D TEST PERSONNEL 4 E REQUIREMENTS 4 E.1. Electrostatic Discharge Requirements 4 E.2. Lifting Operation Requirements 4 E.3. Hardware/Software Requirements 5 E.4. Instrument Pretest Requirements 5 E.5. Configuration Requirements 5 E.6. Optional Non-flight Configurations 5 E.7. Verification/ Success Criteria 5 E.8. Constraints and Restrictions 5 F REFERENCE DOCUMENTS 5 F.1. Drawings 5 F.2. Supporting documentation 5 F.3. Additional Procedures 6 G OPERATIONS 6 G.1. Verify Appropriate QA Notification 6 G.2. Verify Configuration Requirements 6 G.3 Setting Up the GMA 6 G.4 GMA Internal Leakage Test. 8 G.5 GMA Final Configuration 12 G.6 Tables 14 G.7 Diagrams 15 G.8 PRE-TEST CHECKLIST 19 G.9 POST-TEST CHECKLIST 20 Page 2 of 21

H PROCEDURE SIGN OFF 21 Page 3 of 21

A SCOPE This procedure checks the internal through leak rate of the solenoid valves on the flight Gas Management Assembly. A leak detector is connected downstream, and the solenoids are pressurized to a 20 psi differential and the steady state leak rate measured. This mimics exactly the leak test performed by Moog. B SAFETY The GMA is a gas pressure vessel. Under normal operations, the GMA requires no safety measures or equipment beyond those required for the use of a supply gas cylinder. When any of the systems are pressurized and connected to a vacuum system, be cautious not to vent high pressure through the pumping portions of the system. Only allow high pressure to vent through approved ports and make sure that these are open at time of venting. Note that the GMA is an extremely high value piece of space flight equipment. The GMA tanks are also fracture critical items, so care must be taken not to damage them in any way. C QUALITY ASSURANCE C.1 QA Notification This test will be conducted on a formal basis to approved and released procedures. The QA program office and ONR representative shall be notified 24 hours prior to the start of this procedure. A Quality Assurance Representative, designated by D. Ross shall be present during the procedure and shall review any discrepancies noted and approve their disposition. Upon completion of this procedure, the QA Program Engineer, D. Ross or her designate, will certify her concurrence that the effort was performed and accomplished in accordance with the prescribed instructions by signing and dating in the designated place(s) in this document. C.2 Red-line Authority Authority to redline (make minor changes during execution) this procedure is given solely to the Test Engineer or his designate and shall be approved by the QA Representative. C.3 Discrepancies Discrepancies will be recorded in a D-log or as a DR per Quality Plan P0108. D TEST PERSONNEL The Test Director shall be Chris Gray or an alternate that he shall designate. The Engineer has overall responsibility for the implementation of this procedure and shall sign off the completed procedure and relevant sections within it. E REQUIREMENTS E.1. N/A E.2. N/A Electrostatic Discharge Requirements Lifting Operation Requirements Page 4 of 21

E.3. Hardware/Software Requirements ECU Flight Equivalent Unit (FEU) P0931 Rev A Appropriate software for controlling GMA on the spacecraft, this includes a null script which enables command-line control of the GMA. Flight Gas Management Assembly (GMA) Gas Delivery System (GDS) GMA Fill Manifold GMA Spin up Outlet Manifold. Vacuum leak detector Alcatel pump cart (or equivalent dry pumping system) Clean manual valve Plumbing lines, cleaned consistently with Class 100 practices VCR gender changers, elbows, etc. as required, cleaned consistently with Class 100 practices Class 100 down flow hood, if required Hand held particle counter, if required E.4. Instrument Pretest Requirements All test equipment used in taking data shall be in calibration at time of test. E.5. Configuration Requirements GMA work will be performed under Class 100 flow hood or in clean room. E.6. N/A E.7. Optional Non-flight Configurations Verification/ Success Criteria Procedure must measure a leak rate for every GMA solenoid valve (ie. Table 2 is completely filled out). E.8. Constraints and Restrictions Normal clean room practices apply under down flow hood and in clean room. F REFERENCE DOCUMENTS F.1. Drawings GMA Schematic, Dwg. Number 26273 F.2. Supporting documentation S0699 GMA Leakage Test CSTOL S0681 CSTOL Scripts for GMA Testing Page 5 of 21

F.3. Additional Procedures P0886 GDS Operations P0923 Connecting and Disconnecting the GMA and the GAF P0942 Bleed Down of the GMA High Pressure G OPERATIONS G.1. Verify Appropriate QA Notification QA Notified G.2. Verify Configuration Requirements ONR Notified Verify GMA is situated in a Class 1000 or better clean room or under a Class 100 or better flow hood. If GMA is under flow hood, verify the environment with a hand held particle counter. Counts under the hood must average better than 5 per 0.1 liter measured of size 0.5 micron or greater. G.3 Setting Up the GMA Started on: Note: Mark off each step of procedure as it is completed. Quality WARNING HELIUM USED IN THE GRAVITY PROBE-B PROGRAM REPRESENTS A HAZARDOUS MATERIAL FOR THE PERSONNEL INVOLVED IN TESTING AND CRYOGENIC SYSTEM OPERATIONS. EXTREME CARE SHOULD BE USED WHEN WORKING AROUND OR WITH HELIUM. 3.1 Connect the ECU FEU to the GMA and start up the ECU and appropriate software. Record script used here: Note: Do not cycle any GMA solenoid valves at this time. 3.2 Use the ECU to read GMA pressure sensors GP1, GP2, GP3, GP4, GP5, and GP6. 3.3 Record their values here: Table 1, GMA pressures, PSIA: Expected >20 Pressure GP1 GP2 GP3 GP4 GP5 GP6 0 >200 >20 0 <30 <30 <30 Page 6 of 21

3.4 If GP4, GP5, and GP6 are above 30 psia, bleed the pressure out. Use procedure P0942, if appropriate. Bleed until GP4, GP5, and GP6 pressure is at about 20 psia and record final pressures here: Table 1A, GMA pressures, PSIA: GP1 GP2 GP3 GP4 GP5 GP6 Expected >20 Pressure 0 >200 >20 0 ~20 ~20 ~20 3.5 If GP1 reads below 200 psia, connect the GDS and the GMA fill manifold to the GMA, if necessary, and use the GDS to fill the tanks to about 250 psia using P0886 for both processes. 3.6 If GMA is installed on the space vehicle, verify that GSE is connected per diagram 2 (Note: the GDS may not be necessary). For this purpose, OMG1, OMG2, OMG3 etc. manual valves (see diagram 1) will be understood as S1, S2, S3 etc. (see diagram 2). 3.7 If the GMA is connected to the GAF, verify that plumbing is connected according to Diagram 4. 3.8 If the GMA is not connected to either, perform the following operations: 3.8.1 Verify that the spin up outlet manifold (including OMP1A and OMVent) is connected to the GMA. If it is not, connect it using procedure P0923. 3.8.2 Connect the pump cart to OMVent per diagram 4, using P0923, if necessary. 3.8.3 Plumb the P1A line together with the spin up manifold, and connect to the and leak detector per diagram 3 using a manual valve designated DP1. 3.9 Verify all outlet manifold manual valves are closed. 3.10 Open DP1 (and FF1 if connected to GAF, see drawing 4) or PC1, if appropriate, and use leak detector to evacuate this plumbing. 3.11 Open outlet manifold manual valves OMG1, OMG2, OMG3, OMG4, and OMP1A and evacuate this area with the leak detector. 3.12 Use the ECU to verify that V1 and V2 are closed. 3.13 Open GMA solenoid valves V3 through V30. 3.14 Use the leak detector to evacuate the downstream portion of the GMA. 3.15 Calibrate the leak detector and record here: date value 3.16 Use ECU to close GMA solenoid valves V3, V4, V5, and V6. Wait for the background leak rate to come down to a reasonable level. Record background leak rate here: Page 7 of 21

3.17 Close DP1. GMA now ready for leakage test. G.4 GMA Internal Leakage Test. Page 8 of 21 Quality Started on: Note: Mark off each step of procedure as it is completed. All GMA solenoid valves will be opened with the ECU Automatic vent on the leak detector should be disabled for this entire section PC2 is equivalent to OMvent when GMA is connected to the space vehicle. 4.1 Verify that GMA is in the same configuration as in the end of section G.3 (solenoid valves V1 through V6 closed, and V7 through V30 open, outlet manifold valves OMG1, OMG2, OMG3, OMG4, and OMP1A open and under vacuum). 4.2 Use the ECU to open GMA solenoid valves V3 and V5. 4.3 Open manual valve DP1. Start leak detector. 4.4 Wait ten minutes or until a stable leak rate is reached. 4.5 Record leak rate from V1 in Table 2. 4.6 Open solenoid valves V4 and V6. 4.7 Close solenoid valves V3 and V5. 4.8 Wait ten minutes or until a stable leak rate is reached. 4.9 Record leak rate from V2 in Table 2. 4.10 Close solenoid valves V4 and V6. 4.11 Open solenoid valve V1. 4.12 Wait ten minutes or until a stable leak rate is reached. 4.13 Record leak rate from V3 and V5 in Table 2. 4.14 Close GMA solenoid valve V1. 4.15 Verify automatic vent is disabled and stop leak detector. 4.16 Open solenoid valves V3 and V5 and start leak detector to evacuate. 4.17 After leak detector goes into test mode, wait one minute. 4.18 Close solenoid valves V3 and V5. 4.19 Wait for a sufficiently low background leak rate. Record background here. 4.20 Open solenoid valve V2. 4.21 Wait ten minutes or until a stable leak rate is reached. 4.22 Record leak rate from V4 and V6 in Table 2. 4.23 Close solenoid valves V7, V8, and V10-V30 (note: leave V9 open). 4.24 Close Outlet manifold manual valves OMG2, OMG3, OMG4, and OMP1A.

4.25 Open solenoid valves V1, V2, V3, V4, V5, and V6. 4.26 Wait ten minutes or until a stable leak rate is reached. 4.27 Record leak rate from V7 in Table 2. 4.28 Close solenoid valve V9 and open solenoid valve V10. 4.29 Wait ten minutes or until a stable leak rate is reached. 4.30 Record leak rate from V8 in Table 2. 4.31 Close solenoid valve V10 and open solenoid valve V7. 4.32 Wait ten minutes or until a stable leak rate is reached. 4.33 Record leak rate from V9 in Table 2. 4.34 Close solenoid valve V7 4.35 Verify automatic vent is disabled and stop leak detector. 4.36 Open V9. 4.37 Start leak detector to evacuate. 4.38 Wait one minute after leak detector goes into test mode and close V9. 4.39 Wait for a sufficiently low background leak rate. Record background here. 4.40 Open solenoid valve V8. 4.41 Wait ten minutes or until a stable leak rate is reached. 4.42 Record leak rate from V10 in Table 2. 4.43 Close solenoid valve V8. 4.44 Close Outlet Manifold Manual Valve OMG1. 4.45 Open Outlet Manifold Manual Valve OMG2. 4.46 Open V13. 4.47 Wait ten minutes or until a stable leak rate is reached. 4.48 Record leak rate from V11 in Table 2. 4.49 Close V13 and open V14. 4.50 Wait ten minutes or until a stable leak rate is reached. 4.51 Record leak rate from V12 in Table 2. 4.52 Close V14 open V11. 4.53 Wait ten minutes or until a stable leak rate is reached. 4.54 Record leak rate from V13 in Table 2. 4.55 Close solenoid valve V11 4.56 Verify automatic vent is disabled and stop leak detector. 4.57 Open V13. Page 9 of 21

4.58 Start leak detector to evacuate. 4.59 Wait one minute after leak detector goes into test mode and close V13. 4.60 Wait for a sufficiently low background leak rate. Record background here. 4.61 Open solenoid valve V12. 4.62 Wait ten minutes or until a stable leak rate is reached. 4.63 Record leak rate from V14 in Table 2. 4.64 Close V12. 4.65 Close OMG2 and open OMG3. 4.66 Open V17. 4.67 Wait ten minutes or until a stable leak rate is reached. 4.68 Record leak rate from V15 in Table 2. 4.69 Close V17 and open V18. 4.70 Wait ten minutes or until a stable leak rate is reached. 4.71 Record leak rate from V16 in Table 2. 4.72 Close V18 and open V15. 4.73 Wait ten minutes or until a stable leak rate is reached. 4.74 Record leak rate from V17 in Table 2. 4.75 Close solenoid valve V15. 4.76 Verify automatic vent is disabled and stop leak detector. 4.77 Open V17. 4.78 Start leak detector to evacuate. 4.79 Wait one minute after leak detector goes into test mode and close V17. 4.80 Wait for a sufficiently low background leak rate. Record background here. 4.81 Open solenoid valve V16. 4.82 Wait ten minutes or until a stable leak rate is reached. 4.83 Record leak rate from V18 in Table 2. 4.84 Close V16. 4.85 Close OMG3 and open OMG4. 4.86 Open V21 4.87 Wait ten minutes or until a stable leak rate is reached. 4.88 Record leak rate from V19 in Table 2. 4.89 Close V21 and open V22. 4.90 Wait ten minutes or until a stable leak rate is reached. Page 10 of 21

4.91 Record leak rate from V20 in Table 2. 4.92 Close V22 and open V19. 4.93 Wait ten minutes or until a stable leak rate is reached. 4.94 Record leak rate from V21 in Table 2. 4.95 Close solenoid valve V19. 4.96 Verify automatic vent is disabled and stop leak detector. 4.97 Open V21. 4.98 Start leak detector to evacuate. 4.99 Wait one minute after leak detector goes into test mode and close V21. 4.100 Wait for a sufficiently low background leak rate. Record background here. 4.101 Open solenoid valve V20. 4.102 Wait ten minutes or until a stable leak rate is reached. 4.103 Record leak rate from V22 in Table 2. 4.104 Close V20. 4.105 Close OMG4 and open OMP1A. 4.106 Open V25 4.107 Wait ten minutes or until a stable leak rate is reached. 4.108 Record leak rate from V23 in Table 2. 4.109 Close V25 and open V26. 4.110 Wait ten minutes or until a stable leak rate is reached. 4.111 Record leak rate from V24 in Table 2. 4.112 Close V26 and open V23. 4.113 Wait ten minutes or until a stable leak rate is reached. 4.114 Record leak rate from V25 in Table 2. 4.115 Close solenoid valve V23. 4.116 Verify automatic vent is disabled and stop leak detector. 4.117 Open V25. 4.118 Start leak detector to evacuate. 4.119 Wait one minute after leak detector goes into test mode and close V25. 4.120 Wait for a sufficiently low background leak rate. Record background here. 4.121 Open solenoid valve V24. 4.122 Wait ten minutes or until a stable leak rate is reached. 4.123 Record leak rate from V26 in Table 2. Page 11 of 21

4.124 Close V24. 4.125 Close OMP1A and DP1 and disconnect leak detector. 4.126 Connect leak detector to BV1. 4.127 Open BV1 and start leak detector to evacuate plumbing. 4.128 After leak detector goes into test mode, verify automatic vent is disabled and stop leak detector. 4.129 Open OMvent and start leak detector. 4.130 Open V29. 4.131 Wait ten minutes or until a stable leak rate is reached. 4.132 Record leak rate from V27 in Table 2. 4.133 Close V29 and open V30. 4.134 Wait ten minutes or until a stable leak rate is reached. 4.135 Record leak rate from V28 in Table 2. 4.136 Close V30 and open V27. 4.137 Wait ten minutes or until a stable leak rate is reached. 4.138 Record leak rate from V29 in Table 2. 4.139 Close solenoid valve V27. 4.140 Verify automatic vent is disabled and stop leak detector. 4.141 Open V29. 4.142 Start leak detector to evacuate. 4.143 Wait one minute after leak detector goes into test mode and close V29. 4.144 Wait for a sufficiently low background leak rate. Record background here. 4.145 Open solenoid valve V28. 4.146 Wait ten minutes or until a stable leak rate is reached. 4.147 Record leak rate from V30 in Table 2. 4.148 Close OMvent and BV1. 4.149 Stop the leak detector without venting. G.5 GMA Final Configuration Started on: Note: Mark off each step of procedure as it is completed. 5.1 Verify Table 2 is completely filled out. 5.2 Read GP1 using the ECU and record final pressure here: 5.3 If desired, the tank pressure may be bled out using P0942. Page 12 of 21 Quality

5.4 Verify all outlet manifold manual valves are closed. 5.5 Use the ECU to close all solenoid valves. 5.6 The GMA is now safely filled to about 20 psia downstream. 5.7 Shut down the leak detector and remove any unneeded GSE. Quality Page 13 of 21

G.6 Tables Table 2, Solenoid valve leak rates Solenoid Valve Leak rate SCCS Test Engineer initial Quality Stamp Solenoid Valve Leak rate SCCS Test Engineer initial Quality Stamp V1* V17 V2* V18 V3 + V5 V4 +V6 V7 V8 V9 V10 V11 V12 V13 V14 V15 V16 V19 V20 V21 V22 V23 V24 V25 V26 V27 V28 V29 V30 *200+ psi differential Page 14 of 21

G.7 Diagrams Diagram 1, GMA Schematic Zone Zone Zone Zone Zone Zone OMG1 GAS SUPPLY BOTTLE 2000 PSI OMG2 GAS SUPPLY BOTTLE 2000 PSI OMG3 OMG4 Zone OMP1A Outlet Manifold Manual Valve Page 15 of 21

Diagram 2, GMA and Space Vehicle Page 16 of 21

Diagram 3, Vacuum system Plumbing Spinup outlets P1A outlets DP1 Leak Detector Vent outlet BV1 Leak Detector OMVent Page 17 of 21

Diagram 4, GMA and GAF Schematic Page 18 of 21

G.8 PRE-TEST CHECKLIST DATE PROCEDURE # CHECKLIST ITEM COMPLETED REMARKS 1. VERIFY THE TEST PROCEDURE BEING USED IS THE LATEST REVISION. 2. VERIFY ALL CRITICAL ITEMS IN THE TEST ARE IDENTIFIED AND DISCUSSED WITH THE TEST TEAM. 3. VERIFY ALL REQUIRED MATERIALS AND TOOLS ARE PRE- STAGED AND AVAILABLE IN THE TEST AREA. 4. VERIFY ALL HAZARDOUS MATERIALS INVOLVED IN THE TEST ARE IDENTIFIED TO THE TEST TEAM. 5. IF HELIUM IS TO BE USED VERIFY THAT A BLUE HELIUM TAG IS AROUND THE NECK OF THE HELIUM CYLINDER. 6. VERIFY ALL HAZARDOUS STEPS TO BE PERFORMED ARE IDENTIFIED TO THE TEST TEAM. 7. VERIFY EACH TEAM MEMBER KNOWS THEIR INDIVIDUAL RESPONSIBILITIES. 8. CONFIRM THAT EACH TEST TEAM MEMBER CLEARLY UNDERSTANDS THAT HE/SHE HAS THE AUTHORITY TO STOP THE TEST IF AN ITEM IN THE PROCEDURE IS NOT CLEAR. NOTE: DURING A HAZARDOUS OPERATION THE TEST WILL ONLY BE STOPPED WHEN IT IS SAFE TO DO SO. 9. CONFIRM THAT EACH TEST TEAM MEMBER CLEARLY UNDERSTANDS THAT HE/SHE HAS THE AUTHORITY TO STOP THE TEST IF THERE IS ANY ANOMALY OR SUSPECTED ANOMALY NOTE: DURING A HAZARDOUS OPERATION THE TEST WILL ONLY BE STOPPED WHEN IT IS SAFE TO DO SO 10. NOTIFY MANAGEMENT OF ALL DISCREPANCY REPORTS OR D-LOG ITEMS IDENTIFIED DURING THE PROCEDURE. IN THE EVENT AN INCIDENT OCCURS DURING PROCEDURE PERFORMANCE, MANAGEMENT WILL BE NOTIFIED IMMEDIATELY. 11. CONFIRM THAT EACH TEST TEAM MEMBER UNDERSTANDS THAT THERE WILL BE A POST-TEST TEAM MEETING. TEAM LEAD SIGNATURE: Page 19 of 21

G.9 POST-TEST CHECKLIST DATE PROCEDURE # CHECKLIST ITEM COMPLETED REMARKS 1- VERIFY ALL STEPS IN THE PROCEDURE WERE SUCCESSFULLY COMPLETED. 2- VERIFY ALL MINOR/MAJOR DISCREPANCIES DISCOVERED DURING TESTING ARE PROPERLY DOCUMENTED. 3- ENSURE MANAGEMENT HAS BEEN NOTIFIED OF ALL MINOR/MAJOR DISCREPANCIES. 4- ENSURE THAT ALL STEPS THAT WERE NOT REQUIRED TO BE PERFORMED ARE PROPERLY IDENTIFIED. 5- IF APPLICABLE SIGN-OFF TEST COMPLETION. TEAM LEAD SIGNATURE Page 20 of 21

H PROCEDURE SIGN OFF The results obtained in the performance of this procedure are acceptable: Test Director date: Discrepancies if any: Approved: date: C. Gray, GMA REE Approved: date: QA Representative Approved: date: D. Ross, QA Page 21 of 21