Getting a. Bridge Built

Similar documents
SafetyBuletin. Se ingoutriggerstopreventaccidents

Item 404 Driving Piling

Fig. 3.1 (not to scale)

Dry Hydrants. The installation of a non-pressurized pipe system into local water sources provides a ready means of supplying water to fire engines.

Perched Box Caisson Overview. January 2014

UNDERWATER BRIDGE INSPECTION REPORT METRO DISTRICT - ANOKA COUNTY

TECHNICAL MEMORANDUM 002 EMORANNO. 001

SAFETY BULLETIN SETTING OUTRIGGERS TO PREVENT ACCIDENTS II SHORTRIGGING AMERICAN CONCRETE PUMPING ASSOCIATION

River. Dynamics Canoeing: This section focuses on rivers; how they flow and on some basic maneuvers which you can execute on the river.

Slide 1 / What is the density of an aluminum block with a mass of 4050 kg and volume of 1.5 m 3?

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 7 OVER THE SNAKE RIVER DISTRICT 1 - PINE COUNTY

TYPES OF FOUNDATION. Superstructure. Substructure. Foundation

Kentucky Lock Project Update Inland Waterways Users Board

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO OVER THE STRAIGHT RIVER DISTRICT 6 - RICE COUNTY

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 8 - LAC QUI PARLE COUNTY

SPECIAL LAUNCHING METHODS

Product Guide. Crawler Crane

ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL

Ocean Structures and Material Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 9 OVER THE BLUE EARTH RIVER DISTRICT 7 - BLUE EARTH COUNTY

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 1 PINE COUNTY

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 8 - LAC QUI PARLE COUNTY

GATES, CATTLE GUARDS AND PASSAGEWAYS. This factsheet looks at various options for allowing passage through fences for livestock, wildlife and people.

Blasting soft, plastic mineral inside a silo at a copper mine

PACIFIC SHORING, LLC ALUMINUM SHORING PRODUCTS PSH HEAVY DUTY HYDRAULIC WALER RAIL SYSTEM. TABULATED DATA Effective December 10, 2013

PACIFIC SHORING, LLC ALUMINUM SHORING PRODUCTS HEAVY DUTY HYDRAULIC WALER RAIL SYSTEM. TABULATED DATA Effective August 25, 2015

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 4 OVER THE BEAVER RIVER ST. LOUIS COUNTY

Canoe/Kayak Launch Sites and Accessibility

Swim Spa Pre-delivery Guide

(Revised February,2005) CULVERTS, BRIDGES, AND FORDS

STRUCTURAL STABILITY ASSESSMENT

Excavation and Trenching

Who Is OSHA? Who Is PERRP?

WONDERLAB: THE EQUINOR GALLERY. The science and maths behind the exhibits 30 MIN INFORMATION. Topic FORCES. Age

Team 50 Design Log Book. MEMS 0024 Design Project 2: Big Machine

GROVE MODEL RT58D - 20 TON CAPACITY

Q1. The diagram shows two buses. Bus A is empty. Bus B contains bags of sand upstairs to represent passengers.

Components of a Barrage

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO MSAS 123 (2 ND AVE. SW) OVER THE CANNON RIVER CITY OF FARIBAULT, RICE COUNTY

LoneStar Fiberglass Pools. Do-It-Yourself. Installation Manual

UNIT D: MECHANICAL SYSTEMS

CPCS renewal test factsheet

Design of Offshore Structures Prof. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras

Annex E Bridge Pier Protection Plan

ROHO QUADTRO SELECT CUSHION ADJUSTMENT INSTRUCTIONS

The Knowledge Bank at The Ohio State University. Ohio State Engineer. Testing the Bearing Power of Soils.

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 101 OVER THE MINNESOTA RIVER DISTRICT 8 - REDWOOD COUNTY

Siting and Installation Manual

MANUAL OF HANDLING, TRANSPORTATION AND STORAGE OF ELECTRICAL CABLE REELS

3. Types of foundation

Each enclosed presentation is copyrighted by the author of the presentation, and may not be used, re-used, or otherwise reproduced without the

. In an elevator accelerating upward (A) both the elevator accelerating upward (B) the first is equations are valid

TOCA MAINTENANCE & TROUBLESHOOTING MANUAL

Road Safety Facilities Implemented in Japan

N.Y. / REGION INFRASTRUCTURE Going Up! A Bridge Makes Way for Bigger Ships

Design of Offshore Structures Prof. Dr. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras

Break in the Bahamas. Cutters Head to the Caribbean to Wire Saw Sunken Pier. A 25-foot by 25-foot steel pier section had sunk into the water.

KCRC Ma On Shan Line. Railway Development in Hong Kong. Tai Wai Station and Maintenance Centre

ETL listed for installations within 5 ft. (1.5M) of outer edge of water

Stevens Creek Corridor

General Safety and Health Provisions for Construction Self Inspection Checklist

Aluminum Sheeting Guide (ASG)

General Information. NTA607HD Lift Assist Adjustments. Tools Required. Work Location. Notations and Conventions U B F D R B F L

Huntington District. For More Information Contact (304)

Students questions regarding the future of the Zoar Levee and the town of Zoar in Black

CKE4000 HYDRAULIC CRAWLER CRANE GENERAL DIMENSIONS PRELIMINARY. Max. Lifting Capacity

Talybont Deep Adit. A photographic Tour

Operator s Training Guide

h o l l o w poles for foundat i o n s

h o l l o w poles for foundat i o n s

CKE2500 HYDRAULIC CRAWLER CRANE GENERAL DIMENSIONS. Max. Lifting Capacity

River Dynamics - Rafting FOCUS. Read 10 point text from rear of the room. Bottom

TEKS Lesson 6.8E: Machines

NCDOT S EXPERIENCE USING HYDRAULIC SETTLEMENT GAUGES. David L. Teague,P.E. NCDOT GEOTECHNICAL ENGINEERING UNIT

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO B WABASHA STREET SOUTH BOUND (MASA 235 SB)

Related Rates. Instant (true at an instant)

LOAD CHARTS RT540E 85% STABILITY ON OUTRIGGERS 75% STABILITY ON RUBBER

JAP Additional Information Sheet

SAFE WALKS PROGRAM FREQUENTLY ASKED QUESTIONS

Swamp Road Residents Study

CAISSON SHAFT SYSTEM

Job Demands Analysis SPORTS FIELD INSPECTION (PARK BOARD)

Crane Rental Heavy Machinery Moving Project Management

The Railway from Pill Junction to Portishead in March 2015

In This Document. OBJECTIVES Upon completion of this module, you should be able to:

Grader Note: It is recommended that you read the Supporting Information page before you read this factsheet.

Appendix J: Q1-Highway 35 Route Construction Plan

CPCS renewal test factsheet

Dredging Keeping Our Underwater Highways Open

STUDY PROCESS & SCHEDULE

1. What is the top priority when working on Canadian Pacific (CP) property? 2. When working on CP property what must all Contractors comply with?

MOVEMENT FLOW SEQUENCING A REFORMER CADILLAC AND WUNDA CHAIR REFORMER

Division of Environmental Quality Wellhead Protection Section

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 133 OVER A DITCH ST. LOUIS COUNTY

Old-Exam.Questions-Ch-14 T072 T071

The Glockemann Pump Site & Installation Guide

CUSTOMS TARIFF - SCHEDULE 89 - i

Existing conditions of each bridge and repair plan are presented in Table

Protectingpipelinesfor

Parts of the Ship. Terms you should already know

Transcription:

Getting a Bridge Built The progress of the Black River bridge construction was recorded by two I men, the clerk and the bookkeeper of the project. Their photographs of the work have left a wonderful record of how a major engineering project was completed with only steam and manpower. We do not know the complete names of these men, but they presented albums of the photos to railroad executives, including Jack Myers, an inspector for the B & O, whose album has been preserved by his family and was given to the Lodi Historical Society. The batch plant mixed concrete to be poured into the cavity of the large stone piers that were built to support the bridge. Materials were brought by railroad car. There seems to be a steam pressure tank in the right background that might be sending steam in a line from a boiler in the building. The river bottom was found to be soft shale; therefore piles had to be driven to solid rock using this steam-powered pile driver. The men are standing on the superstructure over a cofferdam that kept the river from flooding the area. The excavation for the cofferdam was dug by hand. Each shovel of soil would be placed in the large bucket on the right and a steam-powered boom-jack would lift the load from the excavation. Piles and all timber used in the project were cut locally. FOURTH QUARTER 2013 The Sentinel 9

Keeping the inside of the cofferdam clear of water was a constant job done by steam-powered pumps. This photo shows a pier being built adjacent to the bank of the river. This photo, probably taken from the bridge structure, shows all the major components of the job. The pile driver sits on a cofferdam; a boom-jack moves piles into place. In the background great stacks of stone are visible near the batch plant. On the right a narrow-gauge track is visible. These small tracks were placed and moved as needed to move stone and wood. All these tools were driven by stationary steam engines, some small and movable, and some in a central location with lines to the job. One pier has been completed behind the pile driver. Taken from the top and west end of the site, this photo offers another look at the basic components of the job. Hundreds of wood piles await the pile driver, which is centered over the cofferdam. The nearby countryside provided more than 3,00 piles for the bridge and trestle structure. The steam-powered boom-jack, predecessor of the modern crane, provided the great lifting power required. The machine consisted of two large wooden beams seated in a rotating base. The upright bea was connected by cable to the second beam, or boom, from which a lifting cable could be extended. By changing the angl of the boom to the upright beam with cable, the direction of the boom and lift cable could be moved. 10 The Sentinel FOURTH QUARTER

Berea sandstone, transported by rail from a quarry near Plymouth, Ohio, was the ultimate building material. It was both economical and convenient. Crude stone was cut and refined by English and Italian stone cutters. Each stone had to be individually cut to specific dimensions to form the arch. The top and bottom of the stone might vary by only one-quarter of an inch. Concrete was used only in the piers of the bridge. Every other stone was held in place by its own mass and gravity. By the summer of 1906 the principal piers were complete. The rounded ends of the piers are upstream and will divert the flow and occasional floodcarried debris around the bridge. The piles driven into the middle of the river will support the cribbing that is to be built to support the arch under construction. 5[_:s The central arch is complete with the river running freely underneath. The cofferdam protecting the piers and cribbing has been removed. FOURTH QUARTER 2013 The Sentinel 11

Each arch is a perfect half-circle The wood cribbing had to be stable and rugged enough to support the weight of the stone until the entire arch was finishe When the cribbing was removec each pier supported an estimate 22 tons of weight. The capstone is placed, but the work has only begun. Light showing through the cribbing shows that much more stone must be placed. Each stone in an arch had to be tapered onequarter of an inch even though the stone might be 5 feet long. Work continues on all three arches. At this time the walls between each arch are being constructed, to be filled in with aggregate material. Two platforms about 50 feet above the river support the boom-jacks needed to finish the structure. 12 The Sentinel FOURTH QUARTER

I The first row of stone is complete and the walls are gradually being added. The trestle for the final track is visible on the left. When the bridge is completed the trestle will be an embankment completely covered with soil and gravel. A great deal of fill material was required to bring the adjacent track up to the level of the completed bridge. An extensive wooden trestle was constructed and fill material excavated nearby was brought using a donkey engine and sidedumping cars. The fill area is about a mile long on either side of the bridge. i Even though the cars of fill material were usually pushed out onto the trestle and the engine was kept on the embankment, accidents did happen. The area near the east end of the project is muck soil and considered a swamp. Locals have a story that one engine and its cars fell from the track into the nearby swamp and disappeared. I On top of the arches, now almost complete, aggregate is added to fill the trough created by the walls. The fill material is lifted in barrels by boom-jack and then distributed by manpower. The unbonded stone and aggregate act as a cushion for the weight and vibration of trains. Weep holes allow water drainage and no freezing occurs. @.*«;* z=-3v3& mm. fee.*-..,*, *,«; FOURTH QUARTER 2013 The Sentinel 13