Notice to Mariners No 24 / 2017 Blyth Offshore Demonstrator Project 9 th September 2017

Similar documents
Notice of operations at London Array Offshore Wind Farm

The Array cable installation vessel Stemat 82 and Assist tugs Lydia D and Claudia B are expected to commence installing array cables during week 5.

Contents. 3) Construction Vessels ) Guard Vessels ) Crew Transfer Vessels ) Upcoming Operations (following 7 days)...

Contents. 3) Construction Vessels ) Guard Vessels ) Crew Transfer Vessels ) Upcoming Operations (following 7 days)...

NOTICE TO MARINERS DUDGEON OFFSHORE WIND FARM CONSTRUCTION WORKS

The vessel Nova K, will be undertaking survey and PLGR work on the array cable routes.

Notice of operations at London Array Offshore Wind Farm. Date of Notice: 20 th May 2012 Notice no: 75. London Array Offshore Wind Farm

Other vessel's involved in the Swale cable pull in and burial operations will be the multicat Wiltango, and the barges Wilcarry 300, & Wilcarry 342.

Contents. 3) WTG Installation Vessel ) Array cable installation Vessel ) Hotel vessel ) Survey Vessel ) Guard Vessels...

Contents. 3) Construction Vessels ) Guard Vessels ) Crew Transfer Vessels ) Upcoming Operations (following 7 days)...

Notice of operations at London Array Offshore Wind Farm. Date of Notice: 03 rd June 2012 Notice no: 77. London Array Offshore Wind Farm

Contents. 3) WTG Installation Vessel ) Hotel vessel ) Substation works ) Survey Vessel... 5

Contents. 3) WTG Installation Vessel ) Array cable installation Vessel ) Hotel vessel ) Rock bag removal Export cable ends...

Notice of operations at London Array Offshore Wind Farm. Date of Notice: 01 st July 2012 Notice no: 81. London Array Offshore Wind Farm

Preliminary Survey Notification and Information for Fisheries Interests.

THE ROLE OF INSTALLATION AND SUPPORT VESSELS

G+ Global offshore wind health and safety organisation

MARINERS BRIEFING NEW ENGLAND SURVEY ACTIVITY CONTACT. RODNEY AVILA FISHERIES LIAISON Phone:

Contents. 3) WTG Installation Vessel ) Array cable burial Vessel ) Hotel vessel ) Substation works... 5

Scottish Hydro Electric Power Distribution Operation, Inspection, Maintenance and Decommissioning Strategy Bute Cumbrae Cable Replacement

MARINERS BRIEFING NEW ENGLAND SURVEY ACTIVITY CONTACT. RODNEY AVILA FISHERIES LIAISON Phone:

Contents. 3) Construction Vessels (All dates are weather dependant) ) Survey Vessel ) Guard Vessels... 5

Anchor operations for Jack-up barge in offshore wind farms during service Customers perspective

Multi-Purpose Workboats and Vessels. Marine Engineering and Construction. Salvage and Wreck Removal. Marine Consultancy Services

NOTICE TO MARINERS DUDGEON OFFSHORE WIND FARM CONSTRUCTION WORKS

The shaded blocks below indicate the areas of activity published within this Bulletin.

All Array cables have been installed and the cables have now been buried.

INTERTANKO Guidance and Model Extension Request (MER) for US Coast Guard Ballast Water Management

Wind Farms and Fisheries: Some Commercial Solutions

Contents. 3) Construction Vessels (All dates are weather dependant) ) Survey Vessel ) Guard Vessels... 4

Protection for Vessels Engaged in Servicing Submarine Cables

NOTICE TO MARINERS DUDGEON OFFSHORE WIND FARM CONSTRUCTION WORKS

Maritime Rules Part 25: Nautical Charts and Publications

Fisheries Resource Access Mapping Project (FishRAMP):

Developing a. Guidance for operators who need to develop a. specified limits plan

July Ballast Water Management FAQ

Sustainable Installation & Maintenance Methods Keith McDermott Commercial Director for Tidal Energy Mike Wilson - Managing Director Mike Wilson

MARINE SAFETY REGULATION 2016 EXEMPTION ORDER. Clause 140(1)

Offshore Wind Vessels. Steven Kopits Douglas-Westwood LLC

For live Kingfisher updates of offshore activities, visit and on Twitter. 1 of 10

SAILING INSTRUCTIONS BILLY RUN. Saturday 28 April The organising authority (OA) is the South of Perth Yacht Club

OFFSHORE SURVEY IN DEVELOPMENT PROJECTS. Ian Douglas Head, Offshore Surveys, Shell Projects & Technology Europe

THE ROYAL INSTITUTION OF NAVAL ARCHITECTS

That is why. April 24, 2008

BASIC SAFETY GUIDANCE FOR YACHT RACES OR OCEANIC VOYAGES BY NON-REGULATED CRAFT

NOTICE TO MARINERS. Issue Date: 17 th March, Western HVDC Link Project - Shallow water cables installation in Liverpool bay

The shaded blocks below indicate the areas of activity published within this Bulletin.

Nemo Link s puxo campaign

PASSENGER SHIP SAFETY. Review of Operational Safety Measures to Enhance the Safety of Passenger Ships. Submitted by ICS SUMMARY

Offshore Wind Terminal WELCOME VERSION APRIL EMMANUEL TIMMERMANS BUSINESS DEVELPMENT MANAGER

World Shipping Council. Bureau of Ocean Energy Management Department of the Interior

London Array Offshore Wind Farm. Vessel Data Matrix

MAW01 Cable Risk Assessment Hazard Workshop

Imray Correction Notice 28 March 2018

15B. Contents. Introduction...1. MGN 543 Checklist...1. Methodology Checklist INCH CAPE OFFSHORE LIMITED

NATIONAL MARINE RESEARCH VESSELS

Completing a Certificate of Survey

PILOTAGE DIRECTIONS REVIEWED DECEMBER 2016

ABU - Port of Barrow Island Cyclone Procedure

NOTIFICATION AND STANDARD EVENT PLANNING RISK ASSESSMENT GUIDANCE NOTE

AK-APC-NTV Operating Procedures for Cargo and Passenger Non Tank Vessels Transiting and Operating in Alaska Waters December 26, 2015

Notice of operations at London Array Offshore Wind Farm

Proposed UK Offshore Renewable Energy Installations (OREI) - Guidance on Navigational Safety Issues.

Interim Investigation Report pertaining to the investigation report 71/17. Very Serious Marine Casualty

Sailing Instructions

3 CONSTRUCTION. 3.1 Construction Methods and Sequence. 3.2 Construction Sequence

APPENDIX D Oil Loading Pipeline - Options

This project has been withdrawn by the developer. Atlantic Array Wind Farm

Field Development & Construction

Burbo Bank Extension Offshore Wind Farm

Atlantic Array Wind Farm

South African Maritime Safety Authority Ref: SM6/5/2/1 /1

GERMAN RENEWABLE SHIPBROKERS S GERMAN RENEWABLE VESSEL PORTFOLIO ANY VESSEL ANYTIME

Outcome of the discussion with other HSSC WG on contribution to the MSP MSP development work

World Shipping Council. Bureau of Ocean Energy Management U.S. Department of the Interior

IMO SAFETY PROVISIONS APPLICABLE TO TENDERS OPERATING FROM PASSENGER SHIPS. Passenger Vessel Tender Guidelines

NOTICE TO MARINERS. Western Link Project. Shallow and Deep water cable installation

Passage, co-use & nature inclusive building of offshore wind farms. Rob Gerits RWS-ZD

TRACK RECORD. First Mover. Burbo Bank Ext. - Tristan Stedman

ADANI PORTS & SEZ LTD. ++ MUNDRA PORT ++ GENERAL INFORMATION

MARINE SAFETY PLAN

Fishing in Wind Farms Brown & May Marine Ltd.

REBO terminal. REBO terminal Energy Port Oostende. the ideal hub for offshore wind & heavy lift activities in the North Sea

OVERVIEW MEASURES TO PREVENT GEAR LOSS FISHING GEAR CONFLICT PREVENTION AND CLAIM PROCEDURE

112 INDIAN OCEAN, Îles Crozet - Depth. Depth 126m, extend 200m contour NW to enclose depth,. *113 NAMIBIA, Walvis Bay - Buoyage.

DISCUSSION PAPER: NEW GENERALISATION POLICY FOR SMALL SCALE ADMIRALTY CHARTS.

DO NOT PRINT THIS PAGE

LOCAL NOTICE TO MARINERS

The shaded blocks below indicate the areas of activity published within this Bulletin.

SEA BREEZE Sea Breeze

UK Coastal Atlas of Recreational Boating 2.0: User Guide

REBO. wind terminal. Installation. Edition

Sailing instructions

NOTICE TO MARINERS. No 03 of Port of Southampton Precautionary Area (Thorn Channel)

GUIDELINES FOR NAVIGATION UNDER THE CONFEDERATION BRIDGE

Port of Barrow Island - Local Knowledge Certificate Examination

Maritime Rules. Part 31B Crewing and Watchkeeping Offshore, Coastal and Restricted (Non-Fishing Vessels)

World Shipping Council. U.S. Coast Guard. Port Access Route Study: The Atlantic Coast From Maine to Florida

Transport Infrastructure Act 1994 Gladstone Ports Corporation. Port Notice 04/17 LNG Vessel Operating Parameters

Pile Gripper Systems

Transcription:

Construction Update Gravity Base Foundations (GBFs), Cable Laying & Burial and Wind Turbine Generator Installation Please be advised of the following activities proposed to be undertaken at the Blyth Offshore Demonstrator (BOD) Project. Please note - All mariners are requested to maintain a minimum 500m safety zone around each turbine location indicated in Chart 1 and Table 1. Chart 1 - Array 2 Site and Turbine/GBF Locations Table 1 - Turbine Placement Locations Location Position GBF Location 6 N55 08.8702' W001 24.7913' GBF Location 7 N55 08.3793' W001 24.3781' GBF Location 8 N55 07.8805' W001 24.0344' GBF Location 9 N55 07.3406' W001 23.7706' GBF Location 10 N55 06.7974' W001 23.6067' Activity 1: Gravity Based Foundation Post-installation Works Please be advised that GBF post-installation works will be continuing on the BOD Project Array 2 site.all five GBFs are now installed and ballasted but regular vessel trips are still ongoing for the immediate period in order to undertake snagging works and to demobilise the installation infrastructure. The vessels request a 500m safety zone and can be contacted on VHF 16 when on location.

Transit Routes Chart 2 details the indicative transit routes for vessels operations from Port of Blyth. Vessels will use the shortest navigable route from the port to the site, making best efforts to avoid any conflicts with inshore fishing activity.

Vessel Details for Activity 1 Multrasalvor 3,multi-cat IMO No. 9635975 PCID W. Steyaert / R. de Muynck ICENI Courage, crew transfer vessel 2EIU7 P. Hanscombe MPI Rucio, crew transfer vessel 2CVW7 Gordon Connor Activity 2 Export and Array Cable Laying and Burial The export cable from the shore end near Cambois to GBF Location 6 has been laid and buried. The inter-array cable from GBF Location 6 through to GBF Location 10 has been laid however burial is not scheduled to take place to on or around 6 th October. The MCS Kaver (crew transfer vessel) will be making regular trips from the Port of Blyth to the Array 2 site to undertake works on the inter-array cable. A 500m safety zone around the vessel is requested at all times and the vessel can be contacted on VHF 16 when on location. As the inter-array cable has not been buried between GBF Locations 6 10 it is requested that a 500m safety zone is maintained at all times from the GBF Locations and from the areas directly between GBF Locations. Vessel Details for Activity 2 MCS Kaver, crew transfer vessel Owner/Operator Maritime Craft Services IMO No. 9694165 2GMB8 Ben Woods Activity 3 Wind Turbine Generator (WTG) Installation From on or around 13-14th September the Vole au vent jack-up vessel will be installing WTGs at the Array 2 site. The vessel will arrive at the site directly from the Port of Esbjerg loaded with all components to install WTGs at locations 6, 8 and 7. The vessel will return to the Port of Esbjerg after installing the first

three WTGs and return directly to the Array 2 site on or around 23rd September with all components to install WTGs at locations 9 and 10. The Vole au vent is expected to leave the Array 2 site on or around 25 th September. This period will be extended if weather conditions slow down the progress of the work. During operations the Vole au vent will be supported by the Wind Transfer and the Challenger crew transfer vessels, which will operate from the Port of Blyth and utilise similar transit routes illustrated in Chart 2. A 500m safety zone around the vessels is requested at all times and they can be contacted on VHF 16 when on location. Indicative installation dates are in Table 2: Table 2 Indicative WTG Installation Dates (without any weather standby) WTG Location Dates Location 6 14-09-14 15-09- 17 Location 8 16-09-17 Location 7 17-09-17 Location 9 23-09-17 Location 10 24-09-17 Vessel Details for Activity 3 Vole au vent, jack-up vessel Owner/Operator Jan De Nul Group IMO No. 9655315 LXVT Frederik Bruyninckx

Wind Transfer, crew transfer vessel Owner/Operator IMO No. North Sea Logistics N/A 2EAL9 Ian Hughes Owner/Operator IMO No. Challenger, crew transfer vessel North Sea Logistics N/A 21XX4 Rob Hughes Fisheries Liaison Contact Specialist Marine Consultants is the appointed Fisheries Liaison Coordinator and can be contacted as follows: Simon Prince Fisheries Liaison Co-ordinator Specialist Marine Consultants Ltd +44 (0) 7920 273866 Email: simonp@smchse.com John Armstrong- Fishing Industry Representative Specialist Marine Consultants Ltd +44 (0) 7498 318694 Email: smcflo@smchse.com