Burbo Bank Extension Offshore Wind Farm

Similar documents
This project has been withdrawn by the developer. Atlantic Array Wind Farm

Atlantic Array Wind Farm

WESTERMOST ROUGH. OffshOre Wind farm.

Vattenfall Wind Power Ltd

OFFSHORE WIND: A CRASH COURSE

Safety Zone Application Construction Phase Sheringham Shoal Wind Farm Project

Virginia Offshore Wind Advanced Technology Demonstration Program and Test Pad Sites

Wind Energy 101 for Southeastern Policy Makers Overview of Wind Energy Development and Potential in the US

Offshore wind power in the Baltic sea

OFFSHORE SURVEY IN DEVELOPMENT PROJECTS. Ian Douglas Head, Offshore Surveys, Shell Projects & Technology Europe

OFFSHORE WIND ACCELERATOR (OWA) Access Competition. Competition Overview and Technical Specification

Wave Hub Update All Energy 21/22 May Stuart Herbert Commercial Director

NORCOWE Reference Wind Farm

OFFSHORE WIND Kosten heute und morgen welche Potentiale zur Kostensenkung gibt es

Offshore Service Vessels for Wind Farming. BALTEXPO 2011, September 2011

Notice of operations at London Array Offshore Wind Farm

AGGREGATE DREDGING AND THE MARINE ENVIRONMENT

Offshore Wind Vessels. Steven Kopits Douglas-Westwood LLC

V MW Offshore leadership

Offshore grid NL. Hollandse Kust (noord) & Hollandse Kust (west Alpha) General project introduction. 14 september 2018

That is why. April 24, 2008

Report of the Committee to Study Offshore Wind Energy and the Development of Other Ocean Power Technology

G+ Global offshore wind health and safety organisation

Norway s solution: Hywind- world s first full scale floating turbine Dr. Nenad Keseric Asset Manager/Specialist Statoil ASA MPR RE Operations

Cook Inlet pipeline crossing is about making the best choices

OFFICIAL 2016 A YEAR OF CHANGE IN THE REGULATION OF DECOMMISSIONING?

Examining the merits of jack up platforms as foundations for the offshore wind industry

East Anglia ONE North Offshore Windfarm

THE HORNS REV WIND FARM AND THE OPERATIONAL EXPERIENCE WITH THE WIND FARM MAIN CONTROLLER

Tidal Energy from the Severn Estuary: Opportunities and Challenges

Charlottetown Marine Terminal Pipeline Decommissioning Project Description

OCEAN BREEZE. Ocean Breeze is a Deeper Water Wind turbine Foundation System for The Largest Wind Turbine Towers Sited in Waters up to 200m

The shaded blocks below indicate the areas of activity published within this Bulletin.

The Array cable installation vessel Stemat 82 and Assist tugs Lydia D and Claudia B are expected to commence installing array cables during week 5.

Preliminary Survey Notification and Information for Fisheries Interests.

HARBOUR SEDIMENTATION - COMPARISON WITH MODEL

Morphodynamics of Borssele Wind Farm Zone

Protectingpipelinesfor

Experience with the design, manufacture, test and commercialisation of the REpower 6M turbine

Massachusetts Lobstermen s Association 3/14/2018. March

A2SEA corporate presentation. Søren Rønnow Poulsen Key Account Manager, Scandinacia & Baltic

Protection for Vessels Engaged in Servicing Submarine Cables

The Marking of Offshore Wind Farms. Provide guidance for a response to IALA. M-4 B445.8 &.9 (& B for on-shore wind farms).

LIGHTING CONTROL EQUIPMENT PART 1 TA 12/07 TRAFFIC SIGNALS ON HIGH SPEED ROADS SUMMARY

TRACK RECORD. First Mover. Burbo Bank Ext. - Tristan Stedman

2MW baseline wind turbine: model development and verification (WP1) The University of Tokyo & Hitachi, Ltd.

Galloper Wind Farm Project Response to Development Consent Order Part 3 Requirement 23 Temporary Fencing and other means of enclosure (Enabling

Wind Energy for Kids

Contributions from a multidisciplinary university Finn Gunnar Nielsen Professor Geophysical Institute

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-7 SUB-STATION SY NO-225, NEAR RAYACHERLU VILLAGE

GERMAN RENEWABLE SHIPBROKERS S GERMAN RENEWABLE VESSEL PORTFOLIO ANY VESSEL ANYTIME

US Offshore Wind An Industry in the Making

Low Wind High Yields Series

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-1 SUB-STATION SY NO-44, NEAR KYATAGANACHERLU VILLAGE

Vattenfall A/S Vind Exnersgade Esbjerg Tlf

Fukushima Floating Offshore Wind Farm Demonstration Project ( Fukushima FORWARD )

INDO-FRENCH TECHNOLOGY MEET. Round Table MARINE TECHNOLOGIES

Alstom Ocean Energy Path towards Industrailsation. Ken Street 18 th April 2013

DREDGING. with particular emphasis on Oil and Gas activities in Canada

Sheet 7 The Wind Turbine

Innovative and Robust Design. With Full Extension of Offshore Engineering and Design Experiences.

Japan s Floating Offshore Wind Projects

APPENDIX A. F107 & 380 Lines OYSTER RIVER DURHAM, NH

Nemo Link s puxo campaign

Willett Kempton Center for Carbon-free Power Integration College of Earth, Ocean, and Environment University of Delaware

Pile Gripper Systems

THE ROLE OF INSTALLATION AND SUPPORT VESSELS

V MW. Exceptional performance and reliability at high-wind-speed sites. vestas.com

Marine Character Areas MCA 04. Location and boundaries NORTH WALES OPEN WATERS

Location of Proposed Dredging Areas, spoil disposal area, beaches identified for nourishment and the Study Area Figure 1

Application for. Foreshore Lease. for the. Construction. and. Operation of an

Decommissioning Programme for Hywind Scotland Pilot Park

International Journal of Advance Engineering and Research Development

SEA BREEZE Sea Breeze

3. Types of foundation

G9 Offshore wind health and safety association

Sea-going vessel versus wind turbine

Richards Bay Coal Terminal

TECHNICAL MEMORANDUM 002 EMORANNO. 001

Proposed fisheries management measures for English offshore MPAs in the Channel, the Southwest Approaches and the Irish Sea

SPECIALISED SERVICES. Kris Vlaeminck, Jan De Nul Group, Luxembourg, explains the use of dredging vessels on the Macedon Project in Australia.

Wind Mills of the Mind Delivering large scale offshore wind. Andy Kinsella CEO, Offshore November 24th, 2011, Dundalk

Environmental Considerations

Technology and innovation challenges for UK Offshore Wind Energy Andrew Scott

MARINE ANTIQUITIES SCHEME

SPQ-1A Beach Volleyball System. Instruction

RELATIVE CONTRIBUTION FROM WIND AND WAVES TO LOADS ON OFFSHORE WIND TURBINES

Scour monitoring around offshore jackets and gravity based foundations

Sustainable Installation & Maintenance Methods Keith McDermott Commercial Director for Tidal Energy Mike Wilson - Managing Director Mike Wilson

Coastal and marine recreation in New England is ingrained in the region s economic and

Certified Professionals in Hydrographic Solutions

Ballast. Stability Lab Experiment. Have you ever been in a boat at sea in large waves? The boat moves up and down as the waves pass under the boat.

Wave Energy. ME922/927 Wave energy

To: William Woods, Jenni Austin Job No: CentrePort Harbour Deepening Project - Comments on community queries

Other vessel's involved in the Swale cable pull in and burial operations will be the multicat Wiltango, and the barges Wilcarry 300, & Wilcarry 342.

The Parliamentary Blades Project Newsletter

Wave Energy Converters (WECs)

High Energy Ship Collisions With Bottom Supported Offshore Wind Turbines

Dynamic analysis of offshore floating wind turbines

sarens

Transcription:

Burbo Bank Extension Offshore Wind Farm Developer: DONG energy Site Size: Covering an area of approximately 40 km² Site Location: The proposed project would be located west of the operational Burbo Bank offshore wind farm in Liverpool Bay; around 7 km north of the North Wirral coast, 8.5 km from Crosby beach, and 12.2 km from the Point of Ayr on the Welsh coast. The swell is predominantly westerly. There are no surf spots that will suffer a significant change due to this project. Image: Dong Energy Wind Power (UK) LTD Technology: The project is comprised of 69 wind turbine generators and associated infrastructure, with an installed capacity of up to 258MW. An individual turbine will have an output of approximately 3.6WM. This is enough energy to meet the average needs of up to 170,000 homes. Foundations for the turbines will be one of three types (yet to be confirmed):

Single Steel Monopile This consists of a single steel tubular foundation that is inserted into the seabed. It also includes a transition piece with boat landing features and ancillary components. The diameter of each monopole is 8 m and reaches an embedment of 50m. Monopile foundations require little seabed preparation. Any that does occur will comprise of seabed levelling, debris removal (through dredging) or an application of a filter layer of stone where necessary. The seabed area take per foundation is 50.3m²(potential spoil per foundation is 2513 m³). Gravity Base The gravity base foundations would be flat- based and made of reinforced concrete. It would have a seabed diameter of 35m and a base slab thickness of 6m. The bases require a significant amount of seabed preparation. The area must be dredged of loose sand and clay, seabed levelled to 6 m below seabed level and gravel placed to provide a stable platform. The seabed area take per foundation is 962m²(potential spoil per foundation is 13000m³ in shallow water and 2500m³ in deeper water). Jacket Foundation (Pin Piles) Each would consist of 4 legs; each set 35 metres apart on the seabed. The leg diameter is 3m and would have a embedment depth of 60 m. Minimal seabed preparation is required, any that does occur will be debris removal or seabed levelling (most likely by dredging). The seabed area take per foundation is 200m²(potential spoil per foundation is 12000m³). The proposed design envelope for the turbines is; Parameter Unit Minimum Maximum Rotor Diameter m 112 200 Hub (Nacelle) Height above MHWS m 79 123 Blade tip height above MHWS m 141 223 Total Sweep Area m² 4902 31416 Turbine Separation m 700 1960 MHWS Mean High Water Spring Export Cables A maximum of 2 offshore cables will take electricity to the coast. One of those cables may be replaced by a smaller optical fibre optic running parallel to a single export cable. Offshore and intertidal cables will be buried 1-3m under the seabed. It is anticipated that simultaneous ploughing, pre- trenching (by plough), or a combination of the two will be the primary burial method Where burial is not possible or there is a high risk of exposure or damage, the cable may be protected with flexible concrete mattresses or buried beneath stones (rock dumped). The onshore cable will run south westerly from the landfall between Rhyl and Prestatyn to the onshore substation. At the landfall point, up to two buried concrete transition joint bays will be required to house the joint between the multi- core offshore export cable(s), and the single core onshore. All onshore cables from the landfall to the onshore substation will be installed underground. Development Stage Burbo Bank Extension is currently in the Examination stage. The deadline for close of examination is 26/03/2014.

Timeline Scoping Report submitted: 07/06/2010 Scoping Opinion published from IPC: 19/08/2010 Community consultation period: 05/2011 06/2012 Application Submitted: 22/03/2013 Application Accepted: 19/04/2013 Registration of Interested parties begins: 13/05/2013 Registration of interested parties closes: 24/06/2013 Preliminary Meeting: 26/09/2013 Examination begins: 26/09/2013 Examination Ends: 26/03/2014 Construction: Expected to begin in 2014 If you have a legal interest in land affected by the project and have not already registered to become an interested party, then you can make a request to the Examining Authority to become an interested party under s102a of the Planning Act 2008 (as amended). Contact Details DONG Energy Power (UK) Ltd. 33 Grosvenor Place Belgravia, SW1X 7HY Web: http://www.dongenergy.com/burbobankextension/ Tel: +44 (0)207 811 5200 Project Manager: Ferdinando Giammichele Tel: +44 (0)20 7881 5256 Stakeholder Manager: Emily Marshall Tel: + 44 (0)207 811 5235 Consents Project Manager: Stuart Livesey Commercial Management Assistant - Alexander Bakovljev

Regulator Details Planning Inspectorate Case Team: BurboBank@infrastructure.gsi.gov.uk Tel: 0303 444 5000 Consultees: Department of Energy and Climate Change (DECC) 3 Whitehall Place SW1A 2AW correspondence@decc.gsi.gov.uk Tel: 0300 060 4000 Marine Consents Unit of the Welsh Government Welsh Government Cathays Park Cardiff CF10 3NQ English: 0300 0603300 Welsh: 0300 0604400 English Heritage English Heritage 3rd floor Canada House 3 Chepstow Street Manchester M1 5FW Tel: +44 (0) 870 333 1181 northwest@english- heritage.org.uk Trinity House Tower Hill EC3N 4DH enquiries@thls.org The Maritime and Coastguard Agency Liverpool Marine Office Hall Road West Crosby Liverpool L23 8SY Tel: 0151 931 6600 The Marine Management Agency (MMO) Lancaster House Hampshire Court Newcastle upon Tyne NE4 7YH Tel: 0300 123 1032 info@marinemanagement.org.uk Cefas/Defra Nobel House 17 Smith Square SW1P 3JR Tel: 08459 33 55 77 defra.helpline@defra.gsi.gov.uk Denbighshire County Council Tel: 01824 706101 Natural England Natural England Northminster House Peterborough PE1 1UA Tel: 0845 600 3078 enquiries@naturalengland.org.uk

Countryside Council for Wales Natural Resources Wales Tŷ Cambria 29 Newport Road Cardiff CF24 0TP Tel: 0300 065 3000 enquiries@naturalresourceswales.gov.uk JNCC Joint Nature Conservation Committee Monkstone House City Road Peterborough PE1 1JY Tel: 01733 562626 comment@jncc.gov.uk SAS Traffic Light System Green Surfers Against Sewage have no objections to this development. Burbo Bank Extension is not located close to any surf beaches. The design of the turbines, foundations and export cable route will have no significant effect on the coast line.