On the protection of process equipment from fire exposure. A study on the effect of different means of protection.

Similar documents
Process Equipment Exposed to Fire. A Case Study on the Behaviour of a Fire Exposed LNG Segment.

Validation of VessFire

Analysis of the application and sizing of pressure safety valves for fire protection on offshore oil and gas installations Annex I

Chapter 4, Problem 30.

Use equation for the cylindrical section and equation or for the ends.

NEW IGC CODE AND IGF CODE

I. CHEM. E. SYMPOSIUM SERIES NO. 85

The model of thermal response of Liquefied Petroleum Gas Tanks subjected to accidental heat input

Liquid Gas Cylinder (LGC)

Liquefied gas cargo tanks and process pressure vessels

Fitness for Service Assessment of Ageing Pressure Vessel Experiencing External Corrosion: A Case Study

Corrosion problems in seawater pump caissons. Practical solutions.

2.1 Introduction to pressure vessels

Tube rupture in a natural gas heater

INF.41/Add.1/Rev.1. Economic Commission for Europe Inland Transport Committee

Pigging as a Flow Assurance Solution Avoiding Slug Catcher Overflow

EVOLUTION OF RUPTURE DISC MANUFACTURING TECHNOLOGY AND PERFORMANCE

Safety devices for overpressure protection. Rupture discs: applications, sizing, and types

Medium-sized vessels water connection. White paper

EDEXCEL NATIONALS UNIT 6 MECHANICAL PRINCIPLES and APPLICATIONS. ASSIGNMENT No. 4

Installation Operation Maintenance

Casing Spacer Technology Leaders

ASSIGNMENT 2 CHE 3473

2. Determine how the mass transfer rate is affected by gas flow rate and liquid flow rate.

ASSIGNMENT 2 CHE 3473

Orifice plate, model FLC-OP Orifice flange, model FLC-FL Annular chamber, model FLC-AC

Natural Gas Conditioning Skids & Equipments

CAST IRON SAFETY VALVE TYPE 6301

elastopipe the future of safe fire water systems

Coriolis Mass Flow Meter

Batch centrifuge basket design.

1 SE/P-02. Experimental and Analytical Studies on Thermal-Hydraulic Performance of a Vacuum Vessel Pressure Suppression System in ITER

BPZM-MRD Nitrogen Injection System

Dry Gas Seal Rack CH-3185 Schmitten Tel Mail:

FLAMMABLE GASES AND FLAMMABLE CRYOGENIC FLUIDS

MAHB. INSPECTION Process Hazard Analysis

IMO. Amendments to the IMDC Code, its annexes and supplements. Proposal for an MSC Circular on IMO Type Portable Tanks

CERTIFICATION OF COMPLIANCE OF THE USER S DESIGN SPECIFICATION

INHERENTLY SAFER DESIGN CASE STUDY OF RAPID BLOW DOWN ON OFFSHORE PLATFORM

Series VBA1110 to 4200

Process Safety Management Of Highly Hazardous Chemicals OSHA 29 CFR

Blast Damage Consideratons for Horizontal Pressure Vessel and Potential for Domino Effects

KAYDON RING & SEAL, INC.

Offshore platforms survivability to underwater explosions: part I

SAFETY DATA SHEET SECTION 1 PRODUCT AND COMPANY INFORMATION SECTION 2 COMPOSITION INFORMATION ON INGREDIENTS SECTION 3 HAZARDS IDENTIFICATION

Item ID: Rev.: 00 Status: Final Effective Date: 29-Feb-2015 EXECUTIVE SUMMARY

MSC Guidelines for Pressure Vessels

[PDF] DOWNLOAD PRESSURE VESSEL DESIGN FREE UNQUOTE BOOKS

LEAK FREQUENCY MODELLING FOR OFFSHORE QRA BASED ON THE HYDROCARBON RELEASE DATABASE

Gas Injection for Hydrodynamic Slug Control

Figure Vapor-liquid equilibrium for a binary mixture. The dashed lines show the equilibrium compositions.

Wastewater combination air valve in stainless steel AISI 316 Mod. SCS

Low GWP R-404A Alternatives for Commercial Refrigeration. Barbara H. Minor Dr. Frank Rinne DuPont Fluorochemicals

WP2 Fire test for toxicity of fire effluents

A SIMPLIFIED APPROACH TO THE ASSESSMENT OF DOMINO EVENTS CAUSED BY EXTERNAL FIRES

GUIDELINES FOR CONDUCTING HYDROGENATION REACTIONS

Design of Pressure vessel for the Hydrocarbon release from the Vent Header Lines

Rev. 1. Cryogenics Thermoflasks. 2122, 2123, 2124, 2129, and 2130

Challenges in Relief Design for Pilot Plants

Design and Finite Element Analysis of Fabricated Panama chock with 225T capacity

CONVECTION SECTION FAILURE ANALYSIS AND FITNESS-FOR-SERVICE ASSESSMENT

Pulsed Eddy Current (PEC) Inspection through Insulation

Rules for the Installation, Inspection and Testing of Air Reservoirs (Other than on Locomotives)

6-5 Maintenance Manual

Installation, Operation and Maintenance Instructions for Chemical Dosing Pots

Summary of Safety and Environmental Assessment of ARIES-AT. David Petti Fusion Safety Program, INEEL

INSTALLATION & MAINTENANCE INSTRUCTION

Thermodynamics ERT 206 Properties of Pure Substance HANNA ILYANI ZULHAIMI

PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES

Stress Analysis of The West -East gas pipeline with Defects Under Thermal Load

State of the Art in the Technical Assessment of DOMINO EFFECT

My Website:

Modular skylight warranty

Permitted MSS Emissions Tracking, Recordkeeping, and Reporting. Presented by ACES April 24, 2008

Release: 1. UEPOPL002A Licence to operate a reciprocating steam engine

Material Safety Data Sheet (MSDS): Sweet & Sticky

MSC Guidelines for Independent Fuel Tanks

Quiz #1 Thermodynamics Spring, 2018 Closed Book, Open Appendices, Closed Notes, CLOSED CALCULATORS

9.0 Equipment Cleaning and Repair

Self-operated Pressure Regulators for special applications

Ballot ID: Action item Reference Number: Addition of common causes and susceptibility diagram to API RP 581, 3rd Edition, Section 12

PURPOSE OF THE POLICY

Module # 8 DISTILLATION AND ABSORPTION COLUMN

Booster Regulator/Air Tank

OIL AND GAS INDUSTRY

ANL Bubble Chamber Superheated Active Target System

Manual for continuous distillation

Proceedings of the ASME th International Conference on Ocean, Offshore and Arctic Engineering OMAE2011

0800 WATER SAFETY DATA SHEET. Preparation/Chemical Nature: Polytetrafluoroethylene (PTFE) unsintered, purity >99,50% (residual oil content)

CHAPTER 31 IDEAL GAS LAWS

The Discussion of this exercise covers the following points:

HIGH RATE BASKET STRAINER

Automatic Non-freeze Valve NF6

COMMITTEE DRAFT. API 520 Part I 10 th Edition Ballot Item 2.1. This ballot covers the following item:

Pipeline Integrity Valve Spacing Engineering Assessment (CDN) Grande Prairie Mainline Loop 2 (Progress Section) NPS 36

Development of Accidental Collapse Limit State Criteria for Offshore Structures

AN APPROACH TO THE PROBLEMS OF PROCESS HAZARDS IN PLANT DESIGN

Vertical and Horizontal Bladder Tanks

17J Third Edition, January 2008 Specification for Unbonded Flexible Pipe

Fail-Safe Design by Outer Cover of High Pressure Vessel for Food Processing

Transcription:

On the protection of process equipment from fire exposure. A study on the effect of different means of protection. Geir Berge Petrell as www.petrell.no Kjøpmannsgt. 19 N-713 Trondheim, Norway Fire in process plants might occur for several reasons. During the industrial history fire has caused huge damage and loss of live as well as loss of economy and resources. Even in the best-operated process plant there might be small accidents. The difference between a minor event and a disaster is the ability to prevent escalation. It is crucial that process equipment containing flammables or poisoning material will maintain its integrity during a fire. For that reason the process components and pipes have to be designed to resist fire exposure in a time period sufficient to mitigate the event. This can be done by several means. In this article an overview is given, showing the different means for protection of process equipments and pipes. A demonstration case is presented showing the effect using the different means of protection. 1 Demonstration case. The demonstration case consists of a vessel exposed to fire according to the new procedure for design of process safety systems. The background for the procedure is outlined by H. Olstad and G. Berge (26). The procedure is fully described in Scandpower (24). The following definitions apply: Length of vessel: 3,2 m Inner diameter: 1,6 m Wall thickness: 5 mm Orifice inner diameter: 12 mm Material: Carbon steel, yield stress 455 MPa Background heat load: 1 KW/m2 Point load: 35 KW/m2 Composition in mol fractions: C1:.758679891 C2:.159499 C3:.57798812 IC4:.5236129 C4:.1556998 IC5:.231598 C5:.2416675 C6:.53474 C8:.3423623 C1:.352431 H2O:.5 Heat load is kept constant during calculation. The vessel is filled with oil and gas. The liquid level is.5 m. The vessel is horizontal. For this particular case yield stress is used as disintegration criteria. When applied stress is equal or above the yield stress the vessel is said to disintegrate. Utility Tensile Stress might alternatively be used.

2 Protection means and effects. Protecting a process segment from exposure of fire is about maintaining integrity until disintegration of the segment no longer leads to escalation of the accident. Increased thickness of shell material or insulation is a way to postpone disintegration of components. If the breakdown does not lead to escalation, sooner or later the fire will cease. The major issue for all protection strategies is to buy time and prevent disintegration until certain criteria is achieved. Dependent on the character of the process plant and protection strategy, different criteria is set. The following means is used to maintain integrity of equipments: Increased wall thickness Increased gas release rate (to vent system) Change of material in equipment shell Use of insulation Drainage of liquid in equipment Active fire protection is not considered here. It has the effect of reducing heat load to the equipment. On the Norwegian continental shelf it is not allowed to take creditability of the effect of firewater due to the risk of failure to the firewater system. To study the effect on a vessel exposed to fire, VessFire is used to calculate the different means applied on the demonstration case described above. The computer code is described by G. Berge (1998) and verified against experiments reported in G. Berge, and Ø. Brandt (23a), G. Berge, and Ø. Brandt (23b) and G. Berge, H.T. Olstad (24). VessFire is designe to give the thermomechanical responce of process segment equipments and pipes when exposed to heat. 2.1 Base case. Pressure [kpa] 2 5 2 1 5 1 5 12 1 8 6 4 2 1 2 3 4 5 6 Pressure in vessel The figure above illustrates the pressure history for the demonstration case. That means no insulation and unit absorption coefficient. The stress analysis result is shown below. At its base conditions the vessel will disintegrate after about 2 minutes.

Stress [N/mm2] 5 45 4 35 3 25 2 15 1 5 1 2 3 4 5 6 The mass balance for oil, gas water and water mist is illustrated below. When the vesel is empty there is no potencial for escalation if it disintegrate. 1 4 4 1 2 35 1 3 Mass liquid [kg] 8 6 4 25 2 15 1 Mass gas [kg] 2 5 1 2 3 4 5 6 Mass oil Sum Mass Mass water Mass gas Mass steam The release rate for the base case is shown in the figure below. As can be seen the rate increases after 1 minutes due to boiling of the inventory and the temperature increase in the gas phase..7.6 Release rate [kg/s].5.4.3.2.1. 1 2 3 4 5 6 Release rate

2.2 Increased wall thickness If the wall thikness is increased from 5 mm to 1 mm the vessel will survive as shown in the figure below. All other parameters are maintained from the base case. Stress [N/mm2] 5 1 45 9 4 8 35 7 3 6 25 5 2 4 15 3 1 2 5 1 1 2 3 4 5 6 7 8 9 2.3 Increased gas release rate (to vent system) Increasing the orifice from 12 mm to 2 mm causes the vessel to survive, but the initial release rate increases from.34 to.94 kg/s. The release rate will nevertheless fall faster due to faster evacuation of mass from the vessel. The vessel will be emptied after 44 minutes compared to the base case that will need more than 6 minutes to empty. The figure below shows the pressure history for the case. 2 5 12 Pressure [kpa] 2 1 5 1 5 1 2 3 4 5 Pressure in vessel 1 8 6 4 2

2.4 Change of material in equipment shell Changing material form carbon steel to Duplex with yield stress of 515 MPa also cause the vessel to survive. The evaporation process is also prolonged with about 1 minutes. Stress [N/mm2] 5 45 4 35 3 25 2 15 1 5 1 2 3 4 5 6 7 12 1 8 6 4 2 2.5 Use of insulation Use of insulation postpones the heating process substantially. This is shown in the figure below. After 6 minutes of exposure the maximum temperature of the shell is only about 12 C. A drawback using insulation is that it makes inspection difficult. Corrosion hidden by the insulation material is a well-known phenomenon. This might in itself be safety problem. When using insulation it is also a need for maintenance. Stress [N/mm2] 5 14 45 4 12 35 1 3 8 25 2 6 15 4 1 5 2 1 2 3 4 5 6 7 2.6 Drainage of liquid in equipment In addition to evacuation of gas, the liquid content could be drained. The result is shown in the figure below. It is used a 1 mm opening in the lover part of the vessel as drainage. The vessel survive and the time to empty it is reduced to about 35 minutes.

Pressure [kpa] 2 5 2 1 5 1 5 5 1 15 2 25 3 35 4 Pressure in vessel 12 1 8 6 4 2 3 Conclusions Different means to maintain integrity of process equipment exposed to fire is presented above. Some means are more efficient than others. Insulation is quite efficient, but not preferred due to cost and inspection problems. Where possible, drainage of liquid is quite efficient as it remove mass faster than if the liquid should be build away. Exposure time is of cause an important parameter. Continually exposed, a segment is not safe before it is emptied, that means also the liquid content. Segmentation of the process is an efficient mean to reduce the exposure time. It can be concluded that, well planed and designed, it is possible to maintain integrity of a process plant during an accidental event. 4 References H.T. Olstad and G. Berge, 26, Risk of fire in process industry. Progress in legislation and standard development on the Norwegian continental shelf. CISAP-2, Naples, Italy. Scandpower AS, 24, Guide for Protection of Pressurised Systems Exposed to Fire, www.scandpower.no. G. Berge, 1998, A Calculation System for the Blowdown of Process Segments and Process Equipment Exposed and Unexposed to Fire. www.petrell.no. G. Berge, and Ø. Brandt, 23a. Analysis of fire load. Report no. NBL A418. SINTEF NBL AS. G. Berge, and Ø. Brandt, 23b, Fire load on process equipment, NBL report no., NBL A3111. SINTEF NBL AS. G. Berge, H.T. Olstad, 24, On Heat Load For Engineering Purpose Related To Process Industry. Proceedings of the 23rd International Conference on Offshore Mechanics and Arctic Engineering. OMAE 24.