Background Planning Committee STAFF REPORT March 7, 2018 Page 2 of 2 On June 21, 2017, the Authority approved the programming of second cycle One Bay

Similar documents
TOWN OF MORAGA MORAGA WAY AND CAMINO PABLO/CANYON ROAD IMPROVEMENTS Town Council Meeting March 13, 2019

MEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year AGENCY CONTACT INFORMATION

APPROVE A RESOLUTION ADOPTING A COMPLETE STREETS POLICY

PRESENTER: Christopher J. Blunk, Deputy Public Works Director / City Engineer

TOWN OF MORAGA. CAMINO PABLO & CANYON ROAD INTERSECTION IMPROVEMENTS Public Information Meeting February 20, 2019

CITY OF SIGNAL HILL Cherry Avenue Signal Hill, CA

RESOLUTION NO A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF MENLO PARK ADOPTING A COMPLETE STREETS POLICY

Transportation Development Act Grant Center Avenue Pedestrian Signal Project

Transportation Development Act Grant Radar Check Speed Signs

Planning Committee STAFF REPORT

CRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN

The total net revenue to the City for the previous four fiscal years was $255,856.

Honorable Mayor and Members of the City Council. Contract: AJW Construction for the 2013 Safe Routes to School Project

SAN MATEO COUNTY TRANSPORTATION AUTHORITY STAFF REPORT

Item 08M 1 of 9

AGENDA ITEM SUMMARY SPECIAL AGENDA ITEM NO. _1A_

El Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018

BD RESOLUTION NO RESOLUTION ADOPTING THE VISION ZERO RAMP INTERSECTION STUDY PHASE 1

City of Albert Lea Policy and Procedure Manual 4.10 ALBERT LEA CROSSWALK POLICY

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES

4APNOIPF Vh, YII PTC CITY COUNCIL AGENDA REPORT. Honorable Mayor and City Council Members. 8K TH 63 River Crossing Bridge Replacement Project

Michael Parmer, Management Aide, City Manager's Office

Traffic Calming Policy

Planning Committee STAFF REPORT March 7, 2018 Page 2 of 4 The following MTSOs are being used across the five subregions: Intersection Level of Service

TRAFFIC ACTION PLAN. Laurie Meadows Neighborhood CITY OF SAN MATEO

Watertown Complete Streets Prioritization Plan. Public Meeting #1 December 14, 2017

CITY OF PORTSMOUTH PLANNING DEPARTMENT

Omaha s Complete Streets Policy

MEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year AGENCY CONTACT INFORMATION

ITEM 3 ATTACHMENT A RESOLUTION NO

@ FRIENDLY ACRES COMMUNITY MEETING

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

NJDOT Complete Streets Checklist

P.O. Box 1749 Halifax, Nova Scotia B3J 3A5 Canada Item No. Halifax Regional Council January 16, 2017

Bicycle and Pedestrian Advisory Council May 15, 2015

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

Chapter 4: Funding and Implementation

City of Birmingham Draft Multi-modal Transportation Plan

CITY OF CASSELBERRY WINTER PARK DRIVE IMPROVEMENT STUDY

AUTHORIZE BID ADVERTISEMENT

San Ramon Elementary School. Travel Plan

Engineering - Bicycle and Pedestrian

FUNDING SOURCES CHAPTER 6

Oakland Pedestrian Master Plan Oakland Pedestrian Plan Draft Recommendations Chapter Outline

Applications for Funding

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

ST. PETERSBURG CITY COUNCIL. Consent Agenda. Meeting of February 5, The Honorable Charlie Gerdes, Chair and Members of City Council

MONTGOMERY COUNTY COUNCIL MEMORANDUM

San Francisco County Transportation Authority Proposition K Sales Tax Program Allocation Request Form

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018

Knox Street Complete Streets Project

San Jose Transportation Policy

Adopt Resolution to declare the intent of the City Council to vacate Worthington Street to allow for the widening of Laurel Street.

Venetia Valley Elementary School. Travel Plan

Click to edit Master title style

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

Pedestrian Crossing Guidelines 2016

BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY

AGENDA ITEM H-3 Public Works

Appendix T CCMP TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD

Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER

01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS

Pinellas County Safety Initiatives

Exhibit 1 PLANNING COMMISSION AGENDA ITEM

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK

TRANSPORTATION COMMISSION Agenda Staff Report

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

OneBayArea Grant Application

Measure A Pedestrian & Bicycle Program Update. April 4, 2019 Board of Directors Agenda Item #10 (b)

Crosswalk Policy Revisions & Pedestrian & Bicycle Connection Plans. Presentation to Sanibel City Council July 16, 2013

Broad Street Bicycle Boulevard Design Guidelines

RESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

AGENDA REPORT SUMMARY. Ordinance : Amending the Los Altos Municipal Code Reassigning Commission Responsibility for Transportation Issues

Bicycle Facilities Planning

ACTIA Programs Annual Compliance Report Reporting Year Bicycle and Pedestrian Safety Table 1: Summary of Expenditures and Accomplishments

Appendix D: Planning Level Cost Calculator

Planning Committee STAFF REPORT May 6, 2015 Page 2 of 4 Background In November 2011, the City of Walnut Creek applied for Measure J Program 12 TLC fun

Building Great Neighbourhoods QUEEN ALEXANDRA

a contract for Zone A Roadside Landscape Maintenance Services and Resolution No awarding

AGENDA ITEM F-5 Public Works

SARGE LITTLEHALE COMMUNITY ROOM 22 ORINDA WAY

SC 41/Joe Rouse Intersection Improvements

Document 2 - City of Ottawa Pedestrian Crossover (PXO) Program

BETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY

BICYCLE AND TRAILS ADVISORY COMMISSION Meeting Minutes

Sixth Line Development - Transit Facilities Plan

Project Status Update

Water Street Promenade Engineering and Design Services

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

City Council Agenda Item #6-A CITY OF ALAMEDA Memorandum. To: Honorable Mayor and Members of the City Council. John A. Russo City Manager

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10

Staff Report. Within the $10 million funding limit, ten projects submitted by six different jurisdictions are recommended for funding:

Active Transportation Facility Glossary

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

Building Great Neighbourhoods BONNIE DOON

Bicycle + Pedestrian Connectivity Gap Analysis

CTDOT Pedestrian and Bicycle Safety Initiatives

Atwood Avenue Fair Oaks Avenue Cottage Grove Road

SBCAG STAFF REPORT Federal Transportation Improvement Program. MEETING DATE: January 19, 2017 AGENDA ITEM: 5E

Transcription:

Planning Committee STAFF REPORT Meeting Date: March 7, 2018 Subject Summary of Issues Recommendations Financial Implications Options Attachments Approval of Resolution 18-11-G Appropriating Measure J TLC Funding to the Moraga Way and Canyon Road at Camino Pablo Crossing Safety Project On June 21, 2017, the Authority approved allocations of funding through the second cycle of the One Bay Area Grant (OBAG 2), Measure J Transportation for Livable Communities (TLC) and Pedestrian, Bicycle and Trail Facilities (PBTF) programs. That action programmed $603,000 for the Moraga Way and Canyon Road at Camino Pablo Crossing Safety Project. The Town of Moraga, the project sponsor, has requested the appropriation of $253,000 of TLC funds for the initial phases of the project. Completion is scheduled by the end of 2020. Staff recommends Authority approval of Resolution 18-11-G appropriating $253,000 for the Moraga Way and Canyon Road at Camino Pablo Crossing Safety Project. Approve Resolution 18-11-G appropriating $253,000 to the City of Walnut Creek for the Moraga Way and Canyon Road at Camino Pablo Crossing Safety Project. The $253,000 in Measure J TLC funds requested is included in the budget for Program 12. Delay or otherwise modify the requested appropriation of funds A. Funding Appropriation Request from Shawn Knapp, Town of Moraga, dated February 22, 2017 B. Resolution 18-11-G Changes from Committee S:\05-PC Packets\2018\03\Packet Prep Docs\3.0 Brdltr Resolution 18-11-G TLC - Moraga - Moraga Way Canyon Road Crossing Safety.docx 3-1

Background Planning Committee STAFF REPORT March 7, 2018 Page 2 of 2 On June 21, 2017, the Authority approved the programming of second cycle One Bay Area Grant (OBAG 2), Measure J Transportation for Livable Communities (TLC) and Pedestrian, Bicycle and Trail Facilities (PBTF) funding. Included in this programming was $603,000 to the Town of Moraga for the Moraga Way and Canyon Road at Camino Pablo Crossing Safety Project. The project will improve two roadways: 1) Moraga Way from Moraga Road to Ivy Drive, and 2) the intersection of Canyon Road and Camino Pablo. The Moraga Way segment will: 1. Resurface Moraga Way and restripe with buffered Class II bike lanes; 2. Replace driveways and curb ramps to create an accessible path of travel; and 3. Install new sidewalk and pedestrian pathways along the south side of Moraga Way. At the intersection of Canyon Road and Camino Pablo, the project will: 1. Reduce through travel lanes in each direction along Canyon Road to calm traffic; 2. Construct bulb-outs to reduce the pedestrian crossing distance; 3. Add high visibility crosswalk stripes, install pedestrian level lighting, and install warning lighting like rectangular rapid flash beacons to increase pedestrian visibility; 4. Install speed feedback signs to advise drivers of their speed; and 5. Provide, as feasible, green street elements within the bulb-outs and landscaping to maintain proper roadway drainage and provide treatment. The Town is requesting $253,000 for the initial project management, environmental review and project approval, right-of-way, and project design. The remaining $350,000 programmed for the project, along with OBAG and Moraga Measure K funding, will be used to construct the project. The total project cost is $2.63 million. Staff recommends Authority approval of Resolution 18-11-G to appropriate $253,000 in Measure J TLC (Program 12) for the initial phases of the Moraga Way and Canyon Road at Camino Pablo Crossing Safety Project. S:\05-PC Packets\2018\03\Packet Prep Docs\3.0 Brdltr Resolution 18-11-G TLC - Moraga - Moraga Way Canyon Road Crossing Safety.docx 3-2

ATTACHMENT A 3-3

3-4

Funding Allocation Request Form DATE OR REQUEST: February 12, 2018 On June 21, 2017, the Authority approved the second cycle of Measure J Transportation for Livable Communities (TLC) and Pedestrian, Bicycle and Trail Facilities (PBTF) program funding. As part of this programming, the Authority programmed $603,000 in Transportation for Livable Communities funds for the Strategic Bicycle, Pedestrian and Safe Routes to School Improvements project. The project schedule, expected use of programmed Measure J funds, requested and previous allocation of these funds, and expenditures is listed below. SCHEDULE PROGRAMMING ALLOCATION 2 USE OF FUNDS Phase 1 Begin (mm/yy) End (mm/yy) Expected Use of Measure J Funds Previous Allocation Requested Allocation Total Expended Remaining STU PRJM 3/18 6/20 $63,000 $0 $63,000 $63,000 $0 $63,000 PS&E 3/18 6/19 $144,000 $0 $144,000 $144,000 $0 $144,000 ENV PA&ED 3/18 12/18 $31,000 $0 $31,000 $31,000 $0 $31,000 ROW 3/18 12/18 $15,000 $0 $15,000 $15,000 $0 $15,000 CON $350,000 TOTAL 3 $603,000 $0 $253,000 $253,000 $0 $253,000 1 STU: studies and plans; PRJM: project management; PS&E: plans, specifications & estimates; ENV PA&ED: project approval & environmental clearance; ROW: right of way; CON: construction, including construction management 2 Incorporate any requested changes in the use of programmed funds into funding request 3 The remaining $350,000 in Measure J TLC funds will be requested at a later date for the construction phase of the project 3-5

This Page Intentionally Blank

ATTACHMENT B RESOLUTION 18-11-G RE: APPROPRIATION OF FUNDS TO TOWN OF MORAGA IN ACCORDANCE WITH MASTER COOPERATIVE AGREEMENT NO. 12SW.02 WHEREAS, the Contra Costa Transportation Sales Tax Expenditure Plan and Ordinance 04-02 (hereinafter Expenditure Plan ) sets aside five percent of the Measure J revenues received annually for Program 12, Transportation for Livable Communities (CC-TLC), and 0.4 percent of the Measure J revenues received annually for Program 25b, Additional Funding for Livable Communities as part of the West County component of Measure J Subregional Projects and Programs; and WHEREAS, on April 12, 2017, SWAT approved the use of $603,000 of its subregional share of CC-TLC funds by Town of Moraga (hereinafter Town ) for the Moraga Way and Canyon Road at Camino Pablo Crossing Safety Project (hereinafter Project ); and WHEREAS, the Contra Costa Transportation Authority (hereinafter Authority ) approved the Measure J Transportation for Livable Communities and Pedestrian, Bicycle and Trail Facilities Programs Programming Plan for Fiscal Years 2011 12 through 2014 15 on May 16, 2012 and updated it again on June 21, 2017 (hereinafter Programming Plan ), which programmed $603,000 for the Project; and WHEREAS, the Authority and the Town have entered into Master Cooperative Agreement No. 12SW.02 regarding the funding of projects eligible under the CC-TLC funding category; and WHEREAS, the Town has submitted a Request for Appropriation of Funds dated February 22, 2018 asking for $253,000 to fund the initial phases of the project and an overall financial plan for the project pursuant to 12SW.02; and WHEREAS, the funds are included in the Authority s budget in Item CCMP12. NOW, THEREFORE, BE IT RESOLVED THAT, 1. The Authority finds the Request for Appropriation of Funds consistent with the Expenditure Plan and with Master Cooperative Agreement No. 12SW.02; 2. The Authority appropriates $253,000 from Measure J CC-TLC Program to the Town pursuant to the scope-of-work and conditions set forth in Attachment A of this RESOLUTION, which is incorporated herein as though set forth at length; 3-7

Resolution 18-11-G Page 2 3. Funds will be disbursed to the Town after, in accordance with the provisions of Master Cooperative Agreement No. 12SW.02 but not to exceed, on an annual basis, the amounts programmed by fiscal year in the Measure J Transportation for Livable Communities and Pedestrian, Bicycle and Trail Facilities Programs Programming Plan, adopted May 16, 2012 and updated June 21, 2017; and 4. This appropriation shall expire three years from the date of this resolution; and 5. This RESOLUTION is incorporated into Exhibit B of Master Cooperative Agreement No. 12SW.02 which is enclosed as Attachment B to this RESOLUTION. This RESOLUTION was entered into at a meeting of the Contra Costa Transportation Authority Board held in Walnut Creek, California by the following vote: AYES: NOES: ABSENT: ABSTAIN: Federal D. Glover, Chair Attest: Tarienne Grover, Clerk of the Board Date: Resolution: 18-11-G Coop Agreement: 12SW.02 Proponent: Town of Moraga Amount: $253,000 3-8

Resolution 18-11-G Page 3 Attachment A Resolution 18-11-G Date: Amount of Funds: $253,000 Appropriated to: Town of Moraga Program Category: Transportation for Livable Communities (CC-TLC) Specific Project: Moraga Way and Canyon Road at Camino Pablo Crossing Safety Project Appropriated For: Project management, environmental and project approvals, right-of-way, and engineering design Scope-of-Work: See attached detailed Scope-of-Work Other Conditions: Staff Comments: Date: Resolution: 18-11-G Coop Agreement: 12SW.02 Proponent: Town of Moraga Amount: $253,000 3-9

Resolution 18-11-G Page 4 Total authorization to date under Master $588,000 Cooperative Agreement 12SW.02 Proponent Town of Moraga Resolution Revised Revised Amount $ Date: Resolution: 18-11-G Coop Agreement: 12SW.02 Proponent: Town of Moraga Amount: $253,000 3-10

Resolution 18-11-G Page 5 Attachment A (cont d.) Scope-of-Work The first portion of the project completes the pedestrian and bicycle network on Moraga Way from Moraga Road to Ivy Drive. Key components include: 1. Resurface Moraga Way and restripe with buffered Class II bike lanes; 2. Replace driveways and curb ramps to create an accessible path of travel; and 3. Install new sidewalk and pedestrian pathways along the south side of Moraga Way. The second portion of the project focuses on increasing pedestrian safety at the intersection of Canyon Road and Camino Pablo. Several key components include: 1. Reduce through travel lanes in each direction along Canyon Road to calm traffic; 2. Construct bulb-outs to reduce the pedestrian crossing distance; 3. Restriping with high visibility crosswalk stripes, installing pedestrian level lighting, and installing warning lighting like rectangular rapid flash beacons to increase pedestrian visibility; 4. Install speed feedback signs to advise drivers of their speed; and 5. Provide as feasible green street elements within the bulb-outs and landscaping to maintain proper roadway drainage and provide treatment. The Project Management phase includes oversight of project consultants and contract agreements; processing project environmental and approvals; provide public outreach; and management of grant funding and reimbursements. The Environmental and Project Approvals phase includes conducting field reviews and studies for biological and cultural resources; preparing environmental memos and reports, such as NEPA certification; and required permitting documents. The Right-of-Way (ROW) phase includes documenting ROW and utility locations; coordination with effected properties and utilities; and preparing ROW and Utility certifications. The PS&E phase includes review of field conditions, studies and mapping; coordinating with public utilities on improvement Date: Resolution: 18-11-G Coop Agreement: 12SW.02 Proponent: Town of Moraga Amount: $253,000 3-11

Resolution 18-11-G Page 6 impacts; develop preliminary and final layouts for new improvements; create preliminary and final biddable Plans, Specifications and Engineer s Estimate (PS&E). Date: Resolution: 18-11-G Coop Agreement: 12SW.02 Proponent: Town of Moraga Amount: $253,000 3-12

Resolution 18-11-G Page 7 Attachment B Revisions to Exhibit A of Cooperative Agreement No. 12SW.02 Chronological Listing of Fund Appropriation Resolutions to the City of Walnut Creek Project Number Resolution Number Date Funds Appropriated Cumulative Total 120022 12-43-G October 17, 2012 $335,000 $335,000 120039 18-11-G $253,000 $588,000 Total Funds Appropriated $588,000 Date: Resolution: 18-11-G Coop Agreement: 12SW.02 Proponent: Town of Moraga Amount: $253,000 3-13