Learn more at

Similar documents
DEEP WATER DRILLING RISER TECHNOLOGY, VIV & FATIGUE MANAGEMENT

Introduction. DEEPWATER DRILLING RISER INTEGRITY - FATIGUE, WEAR, INSPECTION AND MONITORING by Dr Hugh Howells and Dave Walters 2H Offshore Inc

RIGID RISERS FOR TANKER FPSOs

Subsea Wellhead and Conductor Fatigue

Learn more at

The Benefits Of Composite Materials In Deepwater Riser Applications. 26 th March 2015 Hassan Saleh Senior Engineer 2H Offshore Engineering Ltd

Steel Lazy Wave Risers A Step Change in Riser Technology for the NWS

RPSEA UDW Forum June 22 & 23, Secure Energy for America

Learn more at

Learn more at

Abstract. 1. Introduction. 2. Design Requirements. Naval Engineer - INTERMOOR DO BRASIL 2. Petroleum Engineer INTERMOOR DO BRASIL 3

The Impact of Composites on Future Deepwater Riser Configurations

Top Tensioned Riser Challenges and Solutions for Dry Tree Facilities in Asia Pacific

DEEP WATER DRILLING RISER TECHNOLOGY, VIV & FATIGUE MANAGEMENT

The topics I will briefly cover, are; Stack Configurations Wellhead Connector Considerations Control Systems Tensioning Systems will be discussed by

Development of a New Deep-Water Riser System. Daniel Karunakaran Subsea 7

Risers for Deepwater FPSO s

Development of Self-Installing Deepwater Spar. Ashit Jadav February 2017

Wellhead, Conductor and Casing Fatigue Causes and Mitigation Tze King Lim, Elizabeth Tellier, Hugh Howells 2H Offshore Engineering

Marine Technology Society

Proceedings of the ASME th International Conference on Ocean, Offshore and Arctic Engineering OMAE2011

Learn more at

Deepwater Floating Production Systems An Overview

Learn more at

Feasibility of Steel Lazy Wave Risers in the North Sea

Fully Submersible Heavy Lift Vessel

Catenary Offset Buoyant Riser Assembly for Malaysian Deepwater

OMAE S&R Paper 6129

(Dynamic Positioning System (DPS) Risk Analysis Using Probabilistic Risk Assessment (PRA))

STRIDE PROJECT Steel Risers in Deepwater Environments Achievements

Fully Submersible Heavy Lift Vessel

TLP Minimum tendon tension design and tendon down-stroke investigation

TARPON A Minimal Facilities Platform

Flexible Spools Solution at Hybrid Risers Base A. Karnikian, Total and S. Tarbadar, M. Bonnissel, S. Legeay, Technip France

LNG TANDEM OFFLOADING A KEY ENABLING TECHNOLOGY TO MAKE LNG PRODUCTION OFFSHORE HAPPEN

Grouped SLOR Deep Water Riser System and Installation Assessment

A NEW DEEPWATER TANKER LOADING SYSTEM FOR WEST AFRICA

A Novel Platform for Drilling in Harsh High-Latitude Environments.

Quicker and Safer Deployment of Deepwater MODU Moorings.

OTC MS. Free Span Rectification by Pipeline Lowering (PL) Method N. I. Thusyanthan, K. Sivanesan & G. Murphy

EFFECT OF VORTEX INDUCED VIBRATION ON FATIGUE DAMAGE OF TOP-TENSIONED RISER SUBJECTED TO CURRENT LOAD

Cathodic Protection Retrofit Options Comparison of Current Distribution

DRILLING HOSE SOLUTIONS

Coupling and Analysis of 981 Deep Water Semi-submersible. Drilling Platform and the Mooring System

HISTORIQUE ET EVOLUTION DES PLATES-FORMES AVEC TETES DE PUITS EN SURFACE (SPAR? ) LES TENDANCES POUR LE FUTUR

Design Challenges & Solutions for Large Diameter Export Risers

Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico Field Development

NOT TO COPY -- NO DISSEMINATE WITHOUT WRITTEN AGREEMENT. Presentation JB AG JCN JR 1

Faculty of Science and Technology MASTER S THESIS

Success Paths: A Risk Informed Approach to Oil & Gas Well Control

Dynamic Positioning: Method for Disaster Prevention and Risk Management

Module No. # 04 Lecture No. # 3.1 Case studies (continued) (Refer Slide Time: 00:10)

$ Millions. The PC Semi: A Low Motion Semisubmersible Capable of a Wet or Dry Tree Configuration. Semi Hull CAPEX Differentials. Topsides.

Coiled Tubing string Fatigue Management in High Pressure Milling Operation- Case Study

IBP2739_10 FIELD TEST OF A FLEXIBLE PIPE INTEGRITY MONITORING SYSTEM Jean-Philippe Roques 1, Benoit Balagué 1, Dominique Dion 2, Gregoire Audouin 2

Development of a Subsurface Mudline Packer to Reduce Risk of Flow after Cementing and Sustained Casing Pressure, While Providing a Platform for P&A.

Ocean Engineering Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras

RAMSTM. 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs

Casing Design. Casing Design. By Dr. Khaled El-shreef

A New Thermoplastic Composite Riser for Deepwater Application

Completion Workover Riser System. Enabling efficient operations by reducing interface complexities and minimizes operational risk

Time-domain Nonlinear Coupled Analyses Covering Typical Mooring and Riser Configurations for FPSOs

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland

Moor, Tend Mooring And Unmoor Ship - Supervisor Level -

DP Station Keeping Event Bulletin


Re-usable Riser and Flowline System for Deep Water Application. C. DIEUMEGARD SUBSEA ASIA - 11 th June 2008

Safety and Risk Engineering. HSE Case Implementation Clive Rawson

Platelets & Plasma The Management of Unplanned Flow

Safety of DP Drilling Operations in the South China Sea

Numerical modelling of disconnectable turret mooring systems

Subsea Safety Systems

Offshore engineering science

Global Floating Rig (Floater) Market: Trends and Opportunities ( ) February 2014

Development of Accidental Collapse Limit State Criteria for Offshore Structures

Dynamic Positioning Control Augmentation for Jack-up Vessels

BUYER S GUIDE AQUAlogger 530WTD

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011

Permanent buoyancy systems. matrix composites & engineering

Offshore // Marine // Subsea Cable solutions that thrive under pressure

REVISITING GLOBAL RESPONSE OF FPSOS IN SHALLOW WATER AND THE RISER ANALYSIS REQUIREMENTS

The SPE Foundation through member donations and a contribution from Offshore Europe

APPENDIX D. Assessment of Ship Impact Frequencies

Marine Technology Society

FPSO Riser Solutions for Harsh environments

DIVERLESS SUBSEA HOT TAPPING OF PRODUCTION PIPELINES

Deepwater Challenges Pipeline Installation Case

OTC Copyright 2010, Offshore Technology Conference

Marine Technology Society

A NEW APPROACH TO BUCKLING DETECTION IN OFFSHORE PIPELINE LAYING

Best Practice RBI Technology Process by SVT-PP SIMTECH

PRESTIGE OIL RECOVERY FROM THE SUNKEN PART OF THE WRECK Massimo Fontolan, Sonsub Ltd., Robin Galletti, SATE srl. Introduction

A Generic Model To Assess Major Incident Frequencies For Offshore Assets

OMAE WET TREE SEMI-SUBMERSIBLE WITH SCRS FOR 4,000 FT WATER DEPTH IN THE GULF OF MEXICO

Site-Specific Assessment of Jack-Ups Part 1: Jack-Up Basics & Why We Do Site-Specific Assessments

Field Development & Construction

Minimal Structures for Marginal Nova Scotia Developments

INDEX OF REVISIONS DESCRIPTION AND/OR AFFECTED SHEETS

Full scale VIV response measurements of a drill pipe in Gulf of Mexico loop currents (OMAE )

Purpose. Scope. Process flow OPERATING PROCEDURE 07: HAZARD LOG MANAGEMENT

Transcription:

IBP1833_06 COST EFFICIENT ARTIFICIAL BUOYANT SEABED DRILLING SOLUTION Dan Moutrey 1, Frank Lim 2 Copyright 2006, Instituto Brasileiro de Petróleo e Gás - IBP This Technical Paper was prepared for presentation at the Rio Oi & Gas Expo and Conference 2006, held between September, 11-14 2006, in Rio de Janeiro. This Technical Paper was selected for presentation by the Technical Committee of the event according to the information contained in the abstract submitted by the author(s). The contents of the Technical Paper, as presented, were not reviewed by IBP. The organizers are not supposed to translate or correct the submitted papers. The material as it is presented, does not necessarily represent Brazilian Petroleum and Gas Institute opinion, nor that of its Members or Representatives. Authors consent to the publication of this Technical Paper in the Rio Oi & Gas Expo and Conference 2006 Annals. Abstract Atlantis Deepwater Technology Holding has developed an artificial buoyant seabed system to be used with smaller semi-submersible or ship drilling vessels, with lower specifications and running costs, for both exploration and development. This is highly significant in the present climate of high rig rates with demand far exceeding supply. The ABS system will allow operators not only to make the decision to suspend drilling operations and retrieve the short drilling riser much later, but when these decisions are made the fiscal and disruptive impact to the industry will be considerably less. The design is being advanced by 2H Offshore to take account of the demanding ocean conditions in different parts of the world. The efforts include riser analsyis to optimise system configuration and establish strutural integrity, and developing the design and specifications of the system components to a level suitable for construction and installation. This paper presents the outcome of some of the work carried out to make the system project ready. 1. Introduction The issues of the recent Gulf of Mexico hurricanes had a significant impact on the oil and gas industry due to extensive asset damage, production loss and market disruption. This has led to a change in the traditional definition of asset management for the industry. The management of storm risks is now incorporated into the activities of most operators. Drilling in deepwater has been the domain of advanced drilling vessels capable of supporting a 21 low pressure drilling riser, equipped with a subsea BOP, spanning the full water depth of the well location; however as water depth increases, the length and weight of this drilling riser becomes a heavy burden for any drilling vessel. A recent approach by the industry is to extrapolate the surface BOP drilling method, as used on shallow water jack-ups, into deeper waters; the drilling riser used is usually of a smaller diameter to drill for smaller casing sizes thus demanding a smaller tensioning requirement from the rig. Both surface BOP and subsea BOP methods have their pros and cons in terms of efficiency and operating limitations. In view of the above, Atlantis Deepwater Technology Holding (ADTH) has developed an artificial buoyant seabed (ABS) system to be used with smaller semi-submersible or ship drilling vessels. The technology allows a conventional shallow water drilling riser and its subsea BOP to be run to the ABS as they would be for a real seabed. On the approach of bad weather, the riser can be disconnected and retrieved, leaving the now new-surface BOP behind on the ABS for well control. The design is being advanced by 2H Offshore (2H) to a level suitable for construction and installation. This following sections summarises the typical results of the analysis carried out to confirm the system s structural integrity and operational characteristics. 2. The Solution The Atlantis Deepwater System represents a unique and very simple approach for meeting the deep and ultradeepwater challenges of offshore drilling. An artificial buoyant seabed (ABS) is installed at shallow depth, typically 200-300 meters, and replaces the functions of the real seabed and no equipment remains on the real seabed. A tieback 1 Marketing Director Atlantis Deepwater Technology Holding AS 2 Principal Director 2H Offshore Engineering Ltd.

of the well casing, e.g. the 20 casing, is used as a tether to anchor this new seabed. An artist impression of the ABS drilling system is shown in Figure 1. The wellhead and BOP are placed on the ABS, which provides enough buoyancy and tension in the tieback string to keep the well in a near vertical position. The offset of the ABS and well is controlled by the top tension resulting from the buoyancy. The cost efficiency from the use of the ABS system comes in a variety of areas, with the main ones being: Use of the Atlantis concept will increase the efficiency of the drilling operations considerably, as there is no need to run the BOP and the drilling riser through the water column to the seabed, merely down to 200-300 meters. In some cases this could save more than a week s rig time. A second/third generation rig, in combination with a taut-leg polyester mooring system, can be used instead of a higher rated drilling unit. The result of this is that the day rates can be reduced as much as 30% for most areas. For the well maintenance operations to be performed during the field lifetime, the availability of rigs will increase considerably, and the costs reduced similarly. All operations can be performed with cheaper rigs. Figure 1. Atlantis ABS Drilling System For the ABS technology to be used, the system design must demonstrate that it can manage the environmental conditions and substantiate in an industry accepted manner that any and all risks associated with the technology are as low as reasonably possible in the planned areas of application, such as India, China and the GOM. Therefore, the ABS system must be as safe as current methods, such as subsea BOP or surface BOP systems. In order to support the argument behind the ABS system, it has been considered that design documentation has to be established with respect to: Riser Analysis Quantitative Risk Assessment The studies have enabled ADTH and 2H to identify components to complete the full system that are designed to withstand the environmental conditions in the perceived areas of application. The next phase on completion of the documentation and procurement will be the planning and implementation of a full marine demonstration trial, for which several possible locations are being reviewed. 2

3. Riser Analysis The riser analysis consisted of a review of information and data provided for the expected application areas in order to compile the design basis. An important part of the design basis was the definition of environmental loading conditions, drilling riser configuration and drilling vessel configuration and responses applied in the analysis. 3.1. Modelling Based on the design information provided, an analysis model of the ABS drilling system was created. This model included all components from the seabed to the drilling vessel, including vessel interface, LP drilling riser system, ABS unit, and tieback string. In addition, the seabed soil support and interface with the subsea mudline wellhead and conductor were also included in the model to allow the loading in the conductor and subsea wellhead to be checked. Where appropriate, multi-string models were utilised to represent the inner casing string, tieback string in the ABS unit, and sub-mudline conductor / casing programs. Figure 2 shows a schematic model of the ABS system in drilling mode. Drill Floor UFJ Tension Ring Mean Water Level Slick Joint LFJ LMRP BOP Upper Wellhead 250m Below MWL ABS Unit Upper Special Joints Tieback Casing (21in) Lower Special Joints Lower Wellhead Conductor 20in & 13in Casing Figure 2. Analytical Model of the ABS Drilling System 3

3.3. Tension Optimisation Analysis Analysis was conducted to define the optimum tension distribution in the ABS system and drilling riser for the expected application areas. This tension was defined based on the water depth, expected maximum mud weight, and drilling riser buoyancy, and would also optimise the distribution of tension / buoyancy between the ABS unit and the tension pulled by the drilling rig. The tension level and distribution was selected based on maximising the operating window of the ABS drilling system, to ensure that the tie-back casing remained under tension in the event of a tensioner failure or flooding of a buoyancy tank compartment. 3.4. Operating Limitations Analysis Analysis was conducted to define the operating limits of the connected ABS drilling system considering a range of vessel offset and environmental loading conditions. Operating limits were defined based on typical conventional drilling riser limitations such as upper and lower flex-joint limits, riser and conductor stress limits and riser stroke at the vessel. Operating windows were defined based on drilling, connected non-drilling and survival criteria as defined in API 16Q. Figure 3 shows a graph of flex-joint angles in the marine drilling riser as a function of rig offsets in a typical water depth of 1,800 m. It indicates that a vessel offset range of approximately 5% of water depth is possible to maintain flex-joint angles of less than 2 degrees to minimise wear of marine riser components from drill string rotations. Flex Joint Rotation (degrees) 10 9 8 7 6 5 4 3 2 1 0-8 -6-4 -2 0 2 4 6 8 Vessel Offset (% Water Depth) LFJ - No Current UFJ - No Current LFJ - 50% Exceedence Current UFJ - 50% Exceedence Current LFJ - 10% Exceedence Current UFJ - 10% Exceedence Current LFJ - Maximum Current UFJ - Maximum Current Drilling Limit Figure 3. Variation of Upper and Lower Flex-Joint Angles with Vessel Offsets 3.5. Extreme Storm Analysis Extreme storm analysis was conducted to assess the response of the ABS system and wellhead and conductor under maximum environmental loading conditions. This was conducted with the following scenarios / ABS system configurations: Before LP drilling riser and BOP is installed (i.e. only tie-back string and ABS installed); LP drilling riser and BOP fully connected; LP drilling riser disconnected, BOP remains connected to ABS system. The design conditions also included a flooded buoyancy compartment, well control situation, etc. to ensure that all potential scenarios were considered. As discussed previously, the initial assessment focused on the use of existing hardware designs for the upper and lower taper joints etc. Figure 4 shows the stress distribution in the tieback string with one flooded compartment. 4

0.7 0.6 Von Mises Stress / Yield 0.5 0.4 0.3 0.2 0.1 0 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 Elevation Above Mudline (m) No Current, Zero Vessel Offset 10% Exceedence Current, 57.58m Vessel Offset (3.29% Water Depth) Figure 4. Stress Distribution Along Tieback String with Flooded ABS Compartment 3.6. First Order Fatigue Analysis A first order fatigue analysis was conducted to define the acceptable usage duration of the ABS system and drilling riser. Due to the ABS buoyancy tank being located well below the wave loading region, this analysis considered the drilling riser connected scenario only. The first order fatigue life of the system was established based on the expected fatigue details for the ABS and drilling riser system (including the conductor and wellhead). First order fatigue damage was found to be negligible. 3.7. VIV Fatigue Analysis A Vortex Induced Vibration (VIV) fatigue analysis was conducted to assess the response of the ABS system, drilling riser, subsea wellhead and conductor. The analysis was conducted using SHEAR7 based on exceedence current profiles, and considered the same three ABS system configurations as detailed in the extreme storm analysis. Long term VIV fatigue lives were defined based on the duration of the exceedence current events and the expected fatigue details of the tieback string components. Figure 5 shows the typical variation of VIV fatigue life along the tieback string. 1.0E+16 1.0E+14 Total Fatigue Life (Years) 1.0E+12 1.0E+10 1.0E+08 1.0E+06 1.0E+04 1.0E+02 1.0E+00 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 Elevation above Mudline (m) B - 1.2 / 3.0 E - 1.3 Figure 5. Variation of VIV Fatigue Life Along Tieback String 5

3.8. Installation/Retrieval Analysis An installation / retrieval analysis was conducted to consider the deployment of the ABS system. The analysis assessed the stress and deflections of the tie-back casing as it is deployed through the ABS unit under a range of environmental loading conditions. Analysis were conducted to consider the deployment of the tie-back string at quarter depth, mid depth and near landing. 3.9. Sensitivity Analysis Sensitivity analyses was conducted to consider the variation in tieback string dynamic response to selected parameters, such as applied tension and hydrodynamic coefficients, to demonstrate that the response of the ABS system was robust. 4. Quantitative Risk Assessment The Quantitative Risk Assessment (QRA) covered three areas: Evaluation of risk of blowout Evaluation of the frequency of interruptions to operations Reliability of the Atlantis Artificial Buoyant Seabed The hazards considered included internal events and external events. Internal events referred to failures within the system, failure of pumps, pipeline, errors made by personnel in following procedures, etc. External events referred to hazards that were outside of the systems, such as weather and sea conditions, collisions, etc. In order to get a good understanding of the operations and hazards, interviews were conducted with key personnel. Based on the information collected, analysts prepared questions relating to scenario development and frequencies of events. 4.1. Model Development and Quantification Analysts used the information derived from the earlier interviews to define blowout scenarios and operation interruption scenarios. Models were defined using fault trees to evaluate the undesirable consequences. The models included hardware failures as well as human errors. The scenarios generated were risk ranked. Major contributions to the scenarios were identified from this. RISKMAN software was used to define the fault tree models and to quantify them 4.2. Documentation of Findings The QRA work is the subject of another paper and will be published in due course. 5. Conclusions Drilling operations can be conducted safely utilising the Artificial Buoyant Seabed technology: It is designed and constructed with existing technology in accordance with accepted industry standards Analysis of the ABS system in a 1,800m deep drilling location with an environment similar to Brazil has shown that o Extreme Stresses are acceptable in the tieback string with the help of special taper joints at the upper and lower terminations, even in the flooded ABS compartment condition. o A good drilling window in terms of vessel offset can be achieved with the optimisation of tieback string tension applied by the ABS buoyancy and the marine drilling riser tension applied by the rig s tensioner system. o The ABS system is little affected by wave loading, even in the drilling riser connected case, so first order fatigue in the tieback string is negligible. o Fatigue life of the tieback string from VIV damage is acceptable given that the string is retrieved regularly and inspected at suitable intervals. QRA of the ABS drilling system with near-surface BOP has not identified any major risk that is more onerous than the subsea and surface BOP drilling systems. 6